Method Statement and Risk Assessment - Concrete Repair Works Rev 02
Method Statement and Risk Assessment - Concrete Repair Works Rev 02
Method Statement and Risk Assessment - Concrete Repair Works Rev 02
Date 08/08/2022
PROJECT
Method statement and Risk assessment for MA-PTM-0202-MET-GEN-C01-
Doc. n°
WGM-00001-01
-ZS1- Rev 01
EMPLOYER ENGINEER
CONTRACTOR
WILLEMEN GROEP
BOERENKRIJGSTRAAT 133
2800 - MECHELEN
BELGIUM
WG Maroc Succursale
PROJECT:
DOCUMENT TITLE:
SUBCONTRACTOR /SUPPLIER:
1
APMT TERMINALS MEDPORT TANGIER EXPANSION
Date 08/08/2022
PROJECT
Method statement and Risk assessment for MA-PTM-0202-MET-GEN-C01-
Doc. n°
WGM-00001-01
-ZS1- Rev 01
1 TABLE OF CONTENTS:
1 TABLE OF CONTENTS:..................................................................................................................2
1 DOCUMENT DISTRIBUTION AND ACCESS..............................................................................3
2 SUBJECT..........................................................................................................................................3
3 REFERENCES.................................................................................................................................3
4 LOCATION........................................................................................................................................4
5 SCHEDULE.......................................................................................................................................4
6 PROCESS OF EXECUTION...........................................................................................................4
6.1 Equipment........................................................................................................................................5
6.2 Process of Concrete repair..........................................................................................................5
6.3 Defects without exposed reinforcement...................................................................................5
6.4 Defects with exposed reinforcement.........................................................................................6
7 HSSE..................................................................................................................................................7
2
APMT TERMINALS MEDPORT TANGIER EXPANSION PROJECT Date 09/06/2022
Method statement and Risk assessment for MA-PTM-0202-MET-PAV-
Doc. n°
-Concrete Block Paving- C01-WGM-00002-01
Rev 01
The latest revision of this project specific Method Statement will be accessible to all
members of the Project Management Team through the corporate network server. All
project staff are notified of this latest revision by means of internal memo or by internal e-
mail.
A hard copy of this document must always be available with the team lead on site during
execution of the considered activity.
2 SUBJECT
The aim of this document is to list the construction phases of the Concrete repair works in
order to make the construction process clear and to ensure that the works are performed in
line with the project specifications and drawings
3 REFERENCES
The most important documents that are used as a reference, are listed in the table below.
Title
ISO 9001 :2008 Standard
ISO 14001:2004 Standard
FIDIC RED BOOK
Contract agreement
Global HSSE Plan Willemen
Global baseline planning Willemen
Quality Plan
Material approval request ( MAP) for concrete mortar repair
APMT TERMINALS MEDPORT TANGIER EXPANSION
Date 08/08/2022
PROJECT
Method statement and Risk assessment for MA-PTM-0202-MET-GEN-C01-
Doc. n°
WGM-00001-01
-ZS1- Rev 01
4 LOCATION
The works related to this project will be carried out in section 4 of the APMT container
terminal in the Port of “Tanger Mediterranée 2 – TM2”, Tangier, Morocco.
5 SCHEDULE
The detailed Schedule of execution of the works will be integrated in the general execution
schedule and will be updated on a regular basis following the progress on site.
6 PROCESS OF EXECUTION
Before the works start, the following activities will be studied and taken into account:
- The material to be used for the concrete repairs should be approved by the
Engineer.
- After de-shuttering, a visual inspection of the concrete surface is carried out by the
quality inspector to identify any defects requiring repair; these defects will be
identified and marked out on the wall of the concrete.
- a demonstration of the application of the repair product will be organized on site
before the start of the repair work,
- Designation of a dedicated repair team
4
APMT TERMINALS MEDPORT TANGIER EXPANSION
Date 08/08/2022
PROJECT
Method statement and Risk assessment for MA-PTM-0202-MET-GEN-C01-
Doc. n°
WGM-00001-01
-ZS1- Rev 01
6.1 Equipment
The equipment to used is limited to
The types of repairs that will be covered by this document are the following:
These defects concern segregation in the concrete surface with > 10mm depth and with
exposed reinforcement
These defects concern segregation and in the concrete surface with exposed
reinforcement.
- When the area to be repaired exceeds the surface by 15 cmx15 cm the surface will
be sawcut to a depth of at least 10 mm. for the surface less than 15cm x 15 cm the
sawcut/grinder cannot be used.
- Removal of damaged concrete and cleaning of the concrete surface with a brush;
The substrate shall be free from dust, loose material, surface contamination and
material which reduce the bond or prevent suction or wetting by repair material.
- The removal of concrete should be kept to a minimum.
- Moistening of the areas to be repaired
- Applying the bonding agent with material SIKALATEX or NITOBOND LATEX.
- Repairing concrete segregations with mortar type R4 repair mortar in accordance
with standard EN 1504-3 and in accordance with the procedure in the repair product
data sheet.
- Repair mortar will be worked into the prepared substrate and will be compacted
without inclusion of entrapped air pockets and in such a way that the required
strength is achieved.
- The repair mortar will be applied layer by layer not exceeding 50 mm for the vertical
surface and it can be increased to 100 mm for horizontal application; the layer
thickness and the time between application will be respected.
- After application the finishing and curing will be carried out.
6
APMT TERMINALS MEDPORT TANGIER EXPANSION
Date 08/08/2022
PROJECT
Method statement and Risk assessment for MA-PTM-0202-MET-GEN-C01-
Doc. n°
WGM-00001-01
-ZS1- Rev 01
- For reinforcement where half the cross-section has been exposed after concrete
removal, the whole circumference of the exposed reinforcement shall be uniformly
cleaned, except when structural consideration prevents it.
- Moistening of the areas to be repaired
- Applying the bonding agent SIKALATEX or NITOBOND LATEX.
- Repairing concrete segregations with mortar type R4 repair mortar in accordance
with standard EN 1504-3 and in accordance with the procedure in the repair product
data sheet.
- Repair mortar will be worked into the prepared substrate and will be compacted
without inclusion of entrapped air pockets and in such a way that the required
strength is achieved and the reinforcement is protected against corrosion.
- The repair mortar will be applied layer by layer not exceeding 40 mm for the vertical
surface and it can be increased to 100 mm for horizontal application; the layer
thickness and the time between application will be respected.
- After application the finishing and curing will be carried out.
7
APMT TERMINALS MEDPORT TANGIER EXPANSION PROJECT Date 09/06/2022
Method statement and Risk assessment for MA-PTM-0202-MET-PAV-
Doc. n°
-Concrete Block Paving- C01-WGM-00002-01
Rev 01
7 HSSE
Unboxing the Personal Injury, material damage, 1 2 2 Low TBT to the unboxing 1 1 1 Low
electrical panel Material damage environment of work team
from the wooden environment Inspection of all
9
APMT TERMINALS MEDPORT TANGIER EXPANSION
Date 08/08/2022
PROJECT
Method statement and Risk assessment for MA-PTM-0202-MET-GEN-C01-
Doc. n°
WGM-00001-01
-ZS1- Rev 01
Assembly of the Personal minor injury- 1 2 2 LOW Wearing adequate PPE 1 1 1 Low
three panels
separately from the
existing switchgear
10
APMT TERMINALS MEDPORT TANGIER EXPANSION
Date 08/08/2022
PROJECT
Method statement and Risk assessment for MA-PTM-0202-MET-GEN-C01-
Doc. n°
WGM-00001-01
-ZS1- Rev 01
12
APMT TERMINALS MEDPORT TANGIER EXPANSION
Date 08/08/2022
PROJECT
Method statement and Risk assessment for MA-PTM-0202-MET-GEN-C01-
Doc. n°
WGM-00001-01
-ZS1- Rev 01
cables to be protected
• Use clamps, a vice or
other devices to hold and
support the piece being
worked on
• Ensure good
housekeeping in the area
• Never surprise or touch
anyone who is operating
a tool
• Only use accessories
recommended by the
manufactures
• Never Hold the tool
close to the body
13
APMT TERMINALS MEDPORT TANGIER EXPANSION PROJECT Date 09/06/2022
Method statement and Risk assessment for MA-PTM-0202-MET-PAV-
Doc. n°
-Concrete Block Paving- C01-WGM-00002-01
Rev 01