Operating and Maintenance Manual: Customer Plant Site Project Service Item Pump Type Purch. Order Date Works Order
Operating and Maintenance Manual: Customer Plant Site Project Service Item Pump Type Purch. Order Date Works Order
Operating and Maintenance Manual: Customer Plant Site Project Service Item Pump Type Purch. Order Date Works Order
MANUAL
CLIENTE
CUSTOMER /
IMPIANTO
PLANT /
LOCALITA'
SITE /
PROGETTO
PROJECT /
SERVIZIO
SERVICE /
SIGLA
ITEM /
TIPO POMPA
PUMP TYPE TITANO 3140
ORDINE
PURCH. ORDER /
DATA
DATE /
COMMESSA
WORKS ORDER /
1 GENERAL PRESCRIPTION
2 MACHINE DESCRIPTION
3 DATA SHEET
4 DRAWINGS
5 INSTALLATION
5.1 Positioning of baseplate
5.2 Positioning of the main component of the unit
5.3 Assembly of the auxiliary circuits
5.4 Hydraulic system connection
5.5 Electric system connection
8 TROUBLE SHOOTING
9 MANUAL OF COMPONENTS
At this point disconnect (if already connected) the suction and discharge flanges of
the main pump to be sure that the pump itself is not under pressure, start the crank
lube oil system; start the main motor at the minimum RPM and for the time strictly
necessary for to check the following:
h) make sure the motor runs in the correct direction and that the absorbed
current is adequate;
j) disconnect the Injection pumps tubing from the stuffing boxes and make sure
the liquid flows during the main pump suction stroke; if not, a new adjustment
of the coupling between Main and Injection pump is necessary;
k) make sure that the Flushing liquid flows is correctly; close the Sample Point
valves and open the Regulation valves downstream the sight flow indicators;
l) check that all the aux. circuits are working at the right pressures and there are
no leakages.
Stop the main motor and reconnect the suction and discharge flanges.
Arrange for water feeding to the Main pump (under atmospheric or very low
pressure), start the motor again, check that no leakages in the hydraulic end occur.
Stop the main and aux. motors - Now the unit is ready for the Start up.
Check the oil levels of main pump, of gear reducer and make sure the correct type of
lubricants is being used;
Start the main pump crankshaft mechanism lubrication pump (if it’s included), control
the direction is that shown on the gear pump;
For water testing plug with a blind flange the connecting piping between suction and
oil tank;
Check that the valves on suction and delivery pipes are open;
Start the main motor;
Check that the values on the local instruments and control panels are those of
normal running;
Check that there are no losses in the auxiliary circuits, in the process connections
and in the hydraulic part of main pump;
Adjust the pressure gauges cut-off devices to reduce oscillations.
Before starting the pump it is necessary to heat the lube oil through the heater
mounted inside the frame of the pump. The heater shall be started through the
power control center if the oil temperature inside the frame is below than 15 °C (59
°F) and shall be stopped when the temperature reaches 30 °C (86 °F).
If the sequences above described have been properly carried out the main electric
motor can be started. If there are no anomalies during operation the electric motor
will run until it is manually stopped. The operating sequence must allow the lube oil
electric motors (if it’s included), be stopped a few seconds after stopping of the main
motor.
For personnel safety purpose and wholeness of the machine it is necessary that:
Before intervening on the machine and in particular on the pump it is necessary that:
Peroni Pompe S.p.A. refuses all responsibility for damages resulting from alterations
of the machine in respect to its configuration of supply, and by the utilisation of spare
parts non supplied by Peroni Pompe.
For service on Pump unit ("hydraulic end" and "crankshaft mechanism") hereinafter
described, make reference to dwg. 314H S5 000 000 SEZ and to the mentioned pos.
numbers.
Unscrew the front (130-136) and rear screws of the valve body (139).
Remove the valve body (139) and place it with its front side on the worktable.
Unscrew the screws (127) on discharge valve flange (137).
Remove the discharge valve flange and the discharge spacer (111).
Extract the discharge valve column.
Do the same to disassemble the suction valve column.
Unscrew the splash guard disk (2), the plunger ring nut (3), the main packing ring
nut (102) and the secondary packing ring nut (101);
Extract the extensions (106);
Extract the hydraulic cylinder (131), with which will be removed the plunger (135),
the lantern (132), and rear ring;
Remove the plunger (135);
Remove the lantern (132) and the main stuffing box packing;
IMPORTANT NOTE
OR
Valve plug
(113)
Valve guide
(114)
Valve spring
(115)
Valve
(118)
Valve
seat (116)
OR
Remove the screws (15-45) that fix upper and lateral covers (16-34-43);
Remove upper and lateral covers (16-34-43) paying attention not to damage the
gasket in between;
Remove the lubrication shoot (9);
Unscrew the connecting rod fixing screws (12) and remove the caps of
connecting rods (11) with relevant half-bushings (33);
Push the crosshead (22) onwards;
Keep the three connecting rods (11) on the frame (1);
Remove the screws (38) that fix the exit shaft cover (25) and screw in the relevant
holes two screws which allow extraction; this cover will also carry together the cap
with relevant MIM gasket (28);
Unscrew the bearing lock ring nut and push-back together the safety washer;
Extract the blind cover (39) acting as described for exit shaft cover (25);
Extract the shaft (26), will also carry the roller bearing;
Remove splash guard disk (2) and unscrew the plunger ring nut (3);
Extract from the frame the connecting rods (11) which will carry together the pin
(24), the connecting rod small end bushing (23) and the crosshead (22);
Using the proper clamps remove the two seeger rings (if any);
Extract the pin (24), hence disengaging the connecting rod (11) from the
crosshead (22);
To extract the connecting rod small end bushing (23) uses the press.
Clean and degrease all disassembled parts and carefully wash the frame inside.
Inspect the frame inside to verify there are no scorings or scratches in the
crosshead working area.
The same inspection has to be carried out on all disassembled parts.
Check with a thickness gauge the clearance between bushing-crosshead and the
pin; if clearance is higher than 0.05 mm, disassemble the pin from the crosshead
and the connecting rod using a press.
Possible scorings shall be removed by slightly scraping with an emery cloth.
CLEARANCES DEFINITION
D1 - E1
Take dimensions D1 and E1
from spacer.
D2 - E2
G - G1
F - F1
N.B.: Dimensions outside brackets refer to discharge column, while those into brackets are
to be taken on suction column.
VALVES ELEVATION
In order to assemble the pin (24) on the crosshead (22) and on the connecting rod
(11), it is necessary to heat the connecting rod eye up to 90/100° C; make sure
that after assembly the pin (24) doesn’t project out of the crosshead (22);
During crank bushing (33) assembly on connecting rod (11), check that between
contact surfaces THERE IS NO OIL;
Fixing screws of connecting rod (10) to the connecting rod cap (11) will have to be
tightened to nominal torque stated in the previous table in two times;
Keying of shaft (26) bearings (31) frame (1) is done using a jack and having care
to centre-position the particulars;
Screws that fix power inlet side cover must be properly tightened but not to the
extent to cause seeger deformation;
Fixing screws of covers shall be clamped with threads braking loctite; once
assembly is over, oil everything and turn the pump manually, and check any
possible hardening.
Hydraulic side reassembly is carried out with reverse sequence to the disassembling
one, paying attention to the following:
Assembly of valves columns must be done as shown on the drawing and without
reversing the operations.
Assembly of packing must be done as shown on the drawing, having care to
position the bladder cut 180° from previous ring and 90° from previous unit.
Grease the OR before assembling them;
Restore oil levels consulting the enclosed table of suggested oils.
Adjustment of seal packings tightening is very important not only during machine
running-in but also when packing are replaced.
During starting phase with new packing, adjust the stuffing box ring nuts , letting the
main packing drip.
It is important not to leave any space between a bladder ring and the other.
Any possible axial clearances of the packing would cause damages to the hydraulic
cylinder and to the plunger.
7.6.1) Introduction
In the following chapters it is described the procedure that must be followed in order
to prepare the stuffing box packings, with description and indication of what must be
done for the braid rings and the supporting rings, their assembly on the plunger and
its installation on the pump. Moreover it is described how to commission a new
stuffing box packing and indication are given for a proper maintenance and care.
The average life of the stuffing box packings is strictly depending upon the care and
experience used for its preparation, the care taken during its assembly, the
commissioning and its further tightening and regulation.
It is important to note that the best maintenance can be done and can be planned
only on the basis of the daily experience of the technical personnel assigned to
reciprocating pumps on the plant. Only after some time the technicians can develop
the best feeling and experience that will lead to a long life of such wearing parts.
Picture #1
Front seal packing sequence
The soft braid rings, for their characteristics, have a grade of elasticity and, so each
ring must be pre-stressed before being mounted. Procedure for preparation of the
soft braid rings is described below:
do not define braid length by winding it on the plunger, as in this way the length
results too long and during compression phase the inside diameter may be altered.
b) Roll up 2 or 3 times with adesive tape the braid where it will have to be cut.
c) Make a 45° cut using a very sharp blade.
where:
S sb .[ cm 2 ]
stuffing .box .chamber .diameter 2
plunger .diameter 2
3,14
4
Once the force has reached the required value, wait 45 seconds before discharging
the pressure.
Introduce the extractor (pos. 6 as shown on dwg. NOR 166-B shown at page 8) and
remove the pressed braid ring, having care not to deform it.
Insert the ring on the plunger and check that a correct overlap of braid ring ends
occurs as shown below. A incorrect overlap could lead to the damage of supporting
rings.
In case a incorrect overlap is checked:
Throw away the soft braid ring in case of negative overlap (Picture #5) and proceed
again from point 1.
Reduce length of soft braid ring correcting the edge, in case of positive overlap
(Picture #6).
Repeat procedure from point 1. up to preparation of all the required soft braid rings.
Usually Peroni provides pre-stressed braid rings but, due to elasticity of material,
such stress could reduce along time (for example when material is kept in stock for a
1) Support. 1) Support.
2) Bushing. 2) Bushing.
3) Spacer ring. 3) Spacer ring.
4) Braid ring. 4) Braid ring.
5) Braid mold 5) Braid mold.
6) Extractor.
This procedure must be followed once the stuffing box packings have been prepared
and checked.
Assembly of Rear Sealing System
Place lantern ring in vertical position, after having mounted on the outside diameter
the relevant O-Rings as per main sectional drawing.
Insert one by one the terminal and spacer rings and the soft braid rings, following the
sequence shown in Picture #2.
The soft braid rings must be inserted so that each cut is at 90° clockwise with respect
to the cut of the previous ring.
Once the hydraulic cylinder has been prepared as above described, it is possible to
proceed with the installation of the plunger:
Lubricate well with oil the internal bottom part of the hydraulic cylinder, paying
attention not to come in touch with any of the two sealings, main or secondary.
Insert the plunger into the hydraulic cylinder, taking maximum care not to damage
the stuffing box packings. The plunger should slide in freely, for almost its entire
length. Only near the end, a pressure should be applied in order to complete the
plunger insertion. The value of such pressure can be indicated as a nominal figure of
100 kg.
The force applied by the technician that is performing the operation should normally
be enough. In case a strong resistance would be requested, few small hits (avoiding
hammer blows) could be applied but it is preferable to remove the plunger, to remove
the lantern ring with the sealing system and re-check the installation of main sealing
system.
Once the pump have been completely reassembled and before starting the
pump, proceed to tighten the stuffing box packings as follows:
Tighten main stuffing box packing through main threaded ring by hands, as much
as possible.
tighten main stuffing box packing through main threaded ring using the front
packing ring nut wrench until resistance is offered.
now the rings have been packed properly.
un-tighten main stuffing box packing through main threaded ring using the front
packing ring nut wrench.
tighten main stuffing box packing through main threaded ring by hands. main
threaded ring must be only in touch with the stuffing box packing.
now the rings can extend again due to the thermal expansion and the elasticity of
the material.
repeat the same operation for the rear stuffing box packing.
pump can now be put in operation, after having followed normal operating
procedure regarding all the auxiliary circuit.
once the pump has been put in operation, the first thing to be verified is the
checking of eventual leakages from the rear sealing system. the admissible
leakage from this packing is an indicative quantity of few drops per minute. in
case a major leakage is occurring, the rear sealing system must be slightly
tightened of 1/4 of turn. after a period of approximately 30 minutes such checking
must be repeated. In case a major dripping is still occurring, repeat the operation
again (1/4 turn tightening and re-checking after 30 minutes) until the leakage
reaches the rated figures of few drops per minutes.
POS. P PM P PR P PM P PGR
HRS 2000 4000 6000 8000 10000 12000 14000 16000
G General revision:
- clearances and surfaces 8 1 Assembler
checking of crankshaft
mechanism; 8 1 Assistant
- clearances and surfaces of
hydraulic side.
Clean the suction filters very often during first running phases.
Adjust the main and secondary packing every time they leak allowing anyway a slight
leakage.
Add oil every time is needed. Replace the oil completely after first 1000 hours of
running and change it every 8000 hours, but not later than 12 calendar months.
The bearings.
The bushings of connecting rod big end.
The crosshead.
The bushings of connecting rod small end.
The pin.
The oil quantity to be supplied is shown on relevant level gauge placed on the frame.
First filling quantities are the following:
Strong blows can be One of the valves closes Total revision of valves
heard which sporadically late and causes a defect and of valves body
overlap the usual valves in the running. seats.
noise.
Component Manufacturer
Electric motors
Gear reducer
Couplings
Pulsation dampeners
Injection pump
Pressure gauges
Level switch
Vibration switch
Globe valve
When proceeding with setting out of service and demolition of pumping unit (Ref.
General arrangement n° 3140 ZZ 088 000 NGR it is suggested to carry out materials
separated disposal.
It is important that inside the pump and all the other components there are no
residual lubricants and/or solvents, which in case will have to be eliminated
according to specific rules in force.