FTU - Module - Foundations of Business Law - Final - 2022 - -đã chuyển đổi
FTU - Module - Foundations of Business Law - Final - 2022 - -đã chuyển đổi
FTU - Module - Foundations of Business Law - Final - 2022 - -đã chuyển đổi
Note:
This is an open book exam and the student have a maximum of 120 minutes.
Submit your solution by mail to me by 3.45 p.m. at the latest
([email protected]).
Solutions which are not submitted within time won’t be accepted.
Overall the students can reach 53 points.
Sophie Freiburghaus
1
Part I: True/False Questions
The following true/false-questions yield 1 point for each correct answer. (32 points)
1.1. BASICS:
True False
Laws are rules enforced by public opinion. ⃝ ⃝
In terms of number of countries, Common Law is the dominant legal ⃝ ⃝
system globally.
Judicial opinion is a source of law in Common Law only, not in Civil law. ⃝ ⃝
Contract Law is Private Law. ⃝ ⃝
Tort Law is Public Law. ⃝ ⃝
Civil Law is the dominant system in continental Europe. ⃝ ⃝
Conduct is a source of law in both Civil Law and Common Law Systems. ⃝ ⃝
2
1.3. Tort:
True False
Contributory negligence is a form of strict liability. ⃝ ⃝
There are torts committed intentionally by the tort teaser. ⃝ ⃝
The vicarious liability of the employer is a form of strict liability. ⃝ ⃝
A company cannot commit a tort. ⃝ ⃝
Under strict liability, the damaged person has to show that the defendant ⃝ ⃝
did not act with reasonable care.
3
Part II: Further Questions
2.1 List five measures which a company could take to minimize product liability claims. (5 points)
2.2. List the preconditions that need to be fulfilled for a successful product liability claim.
(5 points)
Case A
In 2021, Mueller Bridge Ltd. (“Mueller”; domiciled in Olten) enters into a “Joint Venture Agreement”
with Schmid Construction Ltd. (“Schmid”; domiciled in Brugg; Mueller and Schmid together are called
“JVC” (joint venture companies)), to jointly offer their services in a construction project to the Swiss
Federal Railways (“SBB”).
The contract concluded between Mueller and Schmid as contractors and SBB includes the
construction of a bridge. Mueller is responsible for the provision of the steel structure of the bridge
4
and Schmid for the subsequent assembly of the bridge. The agreement between the JVC and SBB
includes as delivery date the first week of June 2022.
1. What kind of contract has SBB and JVC agreed to? (1 point )
[Case continues] Mueller delivers the steel construction according to the time schedule agreed in the
Joint Venture Agreement. Subsequently, Schmid has difficulties to assemble it. Therefore, the JVC are
not able to deliver the assembled bridge on time; at the end of August 2022 the bridge is still not
ready to be delivered. SBB asks you if it can terminate the agreement with the JVC and what
preconditions it must observe to do so.