CONSTRUCTION OF PROPOSED RETANING

WALL

BILL OF QUANTITIES

Prepared by: QS Checked Approved by:..........

Sign/Date: ............................. Sign/Date:............ Page1 of5


CONSTRUCTION OF PROPOSED RETANING WALL

BILL OF QUANTITIES

CONSTRUCTION OF PROPOSED RETANING WALL

Item Amount
Description
No. Rs. Cts.
A PRELIMINARIES 60,000.00

B EXCAVATION & BACK FILLING 1,408,105.97

C CONCRETE WORK & FILTER WORK 4,552,825.42

D MASONARY WORK 319,410.00

TOTAL AMOUNT 6,340,341.39

PREPARED BY : …………………………………………………

CERTIFIED BY : ………………………………………………..

Prepared by: QS Checked Approved by:..........

Sign/Date: ............................. Sign/Date:............ Page2 of5


CONSTRUCTION OF PROPOSED RETANING WALL

BILL OF QUANTITIES

CONST
Item Description Unit BOQ RATE Amount
no QTY Rs. Ct.

A PRELIMINARIES
Allow for all cost and expenses for complying Note
with the General conditions of contract and
Specification.
Note : Any service not specially provided for
will be demand to be included in the rates of
items in the Bill of Quantities
A PRELIMINARIES
A.1 Provision for temporary electricity supply Item client supply
during the construction period.
A.2 Provision for temporary water supply during the Item client supply
construction period.
A.3 Provision for temporary stores for contractor's Item 35,000.00
use.
-
A.4 Allow for site mobilization. Item 1.00 25,000.00 25,000.00
-
A.5 Cut and Removing of existing Tree Roots , in Item - 15,000.00 -
and around the Retainer wall area .
PRELIMINARIES CARRIED TO SUMMERY 60,000.00

Page3 of5
CONSTRUCTION OF PROPOSED RETANING WALL

BILL OF QUANTITIES

CONST
Item Description Unit BOQ RATE Amount
no QTY Rs. Ct.
LAND DEVELOPMENT WORK
CIVIL WORK

B EXCAVATION & BACK FILLING


visit the site and get the sound knowledge about Note
the site conditions.
B.1 Excavation for Retainer extention area wall m3 224.74 2,150.00 483,197.56
foundation

B.2 Filling Retainer wall back filling selected m3 107.57 3,950.00 424,908.41
imported soil filling with 300 mm layers
watered, compacted and well rammed.
b.3 Provision sum for Dewatering. P.sum 500,000.00

EXCAVATION & BACK FILLING 1,408,105.97


C CONCRETE WORK & FILTER WORK
Note : All Grade 25 to be ready mix concrete or Note
mixing by machine.
Unless other wise not specified separately Rate Note
for all concrete works shall include for
Necessary form works ,Reinforcement and
fixing adjustable props to avoid damages to
other structures.

Reinforcement
Note : - contractor must obtain approval form Note
the Engineer before commence of concrete work
with the reinforcement schedule. (SLS certify
Rebar in used )
CONCRETING
C.1 50mm thick Gr.15 Mass Concrete under R/W m2 43.57 1,350.00 58,819.16
foundation
CONCRETE WORK
C.2 Grade 25 concrete for Retaining wall base wall 3 38.15 32,500.00 1,239,953.20
m
as per detail . Reinforcement and Form work
paid separately.
C.3 Form work for Retaining Wall. & Base 2 242.89 3,250.00 789,395.75
m

C.4 Tor Steel Reinforcement for Retaining Wall Kg 2,358.52 690.00 1,627,378.80

C.5 Mild Steel Reinforcement for Retaining Wall Kg 71.89 690.00 49,606.63

Page4 of5
CONSTRUCTION OF PROPOSED RETANING WALL

BILL OF QUANTITIES

CONST
Item Description Unit BOQ RATE Amount
no QTY Rs. Ct.

C.6 4 1/2"" x 4" size wall stiffner columns for Lm 22.00 3,950.00 86,900.00
boundry wall in 10'-0" c/c ,Rate to be included
for necessary R/F with 2T10+R6 8" c/c and
Form work
C.7 4" x 4" size lintol Beam in boundry wall top Lm 22.00 3,650.00 80,300.00
Rate to be included for necessary R/F with
2T10+R6 8" c/c and Form work
C.8 supply & laying of 75mm Dia. Pvc weep holes Nos 3.78 2,900.00 10,962.00
pipe @ 1500mm c/c, filter rubble packing
climed separately.
C.9 Filter rubble packing 150*225mm 3 2.50 13,900.00 34,750.00
m
C.10 claimed for jcb macine hrs for Leveling & Hrs 5.00 6,500.00 32,500.00
removing - without transport cost
C.11 Supplying, spreading, compacting graded m3 37.87 7,850.00 297,259.88
37.5mm aggregates to form a dense graded
aggregates base .(compacted volume)
C.12 Supplying and placing pre cast rings Nos 12.00 17,500.00 210,000.00
1200mm*600mm as per the details Drawing.
C.13 Supplying and placing Construction joint 20mm Item 35,000.00
as per the details drwing.

CONCRETE WORK CARRIED TO SUMMERY 4,552,825.42

D MASONARY WORK
D.1 100mm thick Cement Block work in 1:5 cement m2 37.80 5,450.00 206,010.00
sand mortar

D.2 15mm thick external wall plaster in 1:5 cement 2 84.00 1,350.00 113,400.00
m
& sand finished semi rough.

MASONARY WORK CARRIED TO SUMMERY 319,410.00