Commissioning Schedule Rev00
Commissioning Schedule Rev00
Commissioning Schedule Rev00
Page 1
Commissioning Schedule for Adani ENOC
ID Task Task Name Duration Start Finish Predecessors
Resource
Mode Names
02 May '22 09 May '22 16 May '22 23 May '22 30 May '22
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
39 Communication establishment 1 day 04-05-2022 04-05-2022 37
40 IEC 104 Addressing/ Checking 1 day 04-05-2022 04-05-2022 37
41 Signal simulation to ENOC 1 day 05-05-2022 05-05-2022 38
42 132kV GSS Baytu, Barmer Dist. 3 days 05-05-2022 07-05-2022 Contractor- 1B
43 Panel Shifting to erection location 1 day 05-05-2022 05-05-2022 38
44 Panel Erection 1 day 05-05-2022 05-05-2022 38
45 Cable Laying and termination - Power, Networking
1 day 05-05-2022
cables and Earthing
05-05-2022
of panel
38
46 Panel Power ON 1 day 06-05-2022 06-05-2022 45
47 Communication establishment 1 day 06-05-2022 06-05-2022 45
48 IEC 104 Addressing/ Checking 1 day 06-05-2022 06-05-2022 45
49 Signal simulation to ENOC 1 day 07-05-2022 07-05-2022 46
50 132kV GSS Ram ji ki gol, Barmer Dist. 3 days 07-05-2022 10-05-2022 Contractor- 1B
51 Panel Shifting to erection location 1 day 07-05-2022 07-05-2022 46
52 Panel Erection 1 day 07-05-2022 07-05-2022 46
53 Cable Laying and termination - Power, Networking
1 day 07-05-2022
cables and Earthing
07-05-2022
of panel
46
54 Panel Power ON 1 day 09-05-2022 09-05-2022 53
55 Communication establishment 1 day 09-05-2022 09-05-2022 53
56 IEC 104 Addressing/ Checking 1 day 09-05-2022 09-05-2022 53
57 Signal simulation to ENOC 1 day 10-05-2022 10-05-2022 54
58 132kV GSS Bar, Pali Dist. 3 days 10-05-2022 12-05-2022 Contractor- 1B
59 Panel Shifting to erection location 1 day 10-05-2022 10-05-2022 54
60 Panel Erection 1 day 10-05-2022 10-05-2022 54
61 Cable Laying and termination - Power, Networking
1 day 10-05-2022
cables and Earthing
10-05-2022
of panel
54
62 Panel Power ON 1 day 11-05-2022 11-05-2022 61
63 Communication establishment 1 day 11-05-2022 11-05-2022 61
64 IEC 104 Addressing/ Checking 1 day 11-05-2022 11-05-2022 61
65 Signal simulation to ENOC 1 day 12-05-2022 12-05-2022 62
66 132kV GSS Ghumati, Pali Dist. 3 days 11-05-2022 13-05-2022 Contractor- 1B
67 Panel Shifting to erection location 1 day 11-05-2022 11-05-2022 61
68 Panel Erection 1 day 11-05-2022 11-05-2022 61
69 Cable Laying and termination - Power, Networking
1 day 11-05-2022
cables and Earthing
11-05-2022
of panel
61
70 Panel Power ON 1 day 12-05-2022 12-05-2022 69
71 Communication establishment 1 day 12-05-2022 12-05-2022 69
72 IEC 104 Addressing/ Checking 1 day 12-05-2022 12-05-2022 69
73 Signal simulation to ENOC 1 day 13-05-2022 13-05-2022 70
74 132kV GSS Ahore, Jalore Dist. 3 days 13-05-2022 17-05-2022 Contractor- 1B
75 Panel Shifting to erection location 1 day 13-05-2022 13-05-2022 70
76 Panel Erection 1 day 13-05-2022 13-05-2022 70
77 Cable Laying and termination - Power, Networking
1 day 13-05-2022
cables and Earthing
13-05-2022
of panel
70
78 Panel Power ON 1 day 16-05-2022 16-05-2022 77
Page 2
Commissioning Schedule for Adani ENOC
ID Task Task Name Duration Start Finish Predecessors
Resource
Mode Names
02 May '22 09 May '22 16 May '22 23 May '22 30 May '22
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
79 Communication establishment 1 day 16-05-2022 16-05-2022 77
80 IEC 104 Addressing/ Checking 1 day 16-05-2022 16-05-2022 77
81 Signal simulation to ENOC 1 day 17-05-2022 17-05-2022 78
82 132kV GSS Rajmatai, Jaisalmer Dist. 3 days 03-05-2022 05-05-2022 Contractor- 1C
83 Panel Shifting to erection location 1 day 03-05-2022 03-05-2022
84 Panel Erection 1 day 03-05-2022 03-05-2022
85 Cable Laying and termination - Power, Networking
1 day 03-05-2022
cables and Earthing
03-05-2022
of panel
86 Panel Power ON 1 day 04-05-2022 04-05-2022 85
87 Communication establishment 1 day 04-05-2022 04-05-2022 85
88 IEC 104 Addressing/ Checking 1 day 04-05-2022 04-05-2022 85
89 Signal simulation to ENOC 1 day 05-05-2022 05-05-2022 86
90 132kV GSS Bengantikalan, Jodhpur Dist. 3 days 05-05-2022 07-05-2022 Contractor- 1C
91 Panel Shifting to erection location 1 day 05-05-2022 05-05-2022 86
92 Panel Erection 1 day 05-05-2022 05-05-2022 86
93 Cable Laying and termination - Power, Networking
1 day 05-05-2022
cables and Earthing
05-05-2022
of panel
86
94 Panel Power ON 1 day 06-05-2022 06-05-2022 93
95 Communication establishment 1 day 06-05-2022 06-05-2022 93
96 IEC 104 Addressing/ Checking 1 day 06-05-2022 06-05-2022 93
97 Signal simulation to ENOC 1 day 07-05-2022 07-05-2022 94
98 132kV GSS Shekhsar, Bikaner Dist. 3 days 07-05-2022 10-05-2022 Contractor- 1C
99 Panel Shifting to erection location 1 day 07-05-2022 07-05-2022 94
100 Panel Erection 1 day 07-05-2022 07-05-2022 94
101 Cable Laying and termination - Power, Networking
1 day 07-05-2022
cables and Earthing
07-05-2022
of panel
94
102 Panel Power ON 1 day 09-05-2022 09-05-2022 101
103 Communication establishment 1 day 09-05-2022 09-05-2022 101
104 IEC 104 Addressing/ Checking 1 day 09-05-2022 09-05-2022 101
105 Signal simulation to ENOC 1 day 10-05-2022 10-05-2022 102
106 132kV GSS Ghamurwali, Ganganagar Dist. 3 days 10-05-2022 12-05-2022 Contractor- 1C
107 Panel Shifting to erection location 1 day 10-05-2022 10-05-2022 102
108 Panel Erection 1 day 10-05-2022 10-05-2022 102
109 Cable Laying and termination - Power, Networking
1 day 10-05-2022
cables and Earthing
10-05-2022
of panel
102
110 Panel Power ON 1 day 11-05-2022 11-05-2022 109
111 Communication establishment 1 day 11-05-2022 11-05-2022 109
112 IEC 104 Addressing/ Checking 1 day 11-05-2022 11-05-2022 109
113 Signal simulation to ENOC 1 day 12-05-2022 12-05-2022 110
114 132kV GSS Sorda, Sirohi Dist. 3 days 12-05-2022 16-05-2022 Contractor- 1C
115 Panel Shifting to erection location 1 day 12-05-2022 12-05-2022 110
116 Panel Erection 1 day 12-05-2022 12-05-2022 110
117 Cable Laying and termination - Power, Networking
1 day 12-05-2022
cables and Earthing
12-05-2022
of panel
110
118 Panel Power ON 1 day 13-05-2022 13-05-2022 117
Page 3
Commissioning Schedule for Adani ENOC
ID Task Task Name Duration Start Finish Predecessors
Resource
Mode Names
02 May '22 09 May '22 16 May '22 23 May '22 30 May '22
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
119 Communication establishment 1 day 13-05-2022 13-05-2022 117
120 IEC 104 Addressing/ Checking 1 day 13-05-2022 13-05-2022 117
121 Signal simulation to ENOC 1 day 16-05-2022 16-05-2022 118
122 ±500kV, MOHINDERGARH HVDC Terminal3 days 03-05-2022 05-05-2022 Contractor- 2B
123 Panel Shifting to erection location 1 day 03-05-2022 03-05-2022
124 Panel Erection 1 day 03-05-2022 03-05-2022
125 Cable Laying and termination - Power, Networking
1 day 03-05-2022
cables and Earthing
03-05-2022
of panel
126 Panel Power ON 1 day 04-05-2022 04-05-2022 125
127 Communication establishment 1 day 04-05-2022 04-05-2022 125
128 IEC 104 Addressing/ Checking 1 day 04-05-2022 04-05-2022 125
129 Signal simulation to ENOC 1 day 05-05-2022 05-05-2022 126
130 765/400KV Akola SS 3 days 03-05-2022 05-05-2022 Contractor- 3A
131 Panel Shifting to erection location 1 day 03-05-2022 03-05-2022
132 Panel Erection 1 day 03-05-2022 03-05-2022
133 Cable Laying and termination - Power, Networking
1 day 03-05-2022
cables and Earthing
03-05-2022
of panel
134 Panel Power ON 1 day 04-05-2022 04-05-2022 133
135 Communication establishment 1 day 04-05-2022 04-05-2022 133
136 IEC 104 Addressing/ Checking 1 day 04-05-2022 04-05-2022 133
137 Signal simulation to ENOC 1 day 05-05-2022 05-05-2022 134
138 765/400kV Koradi SS 3 days 05-05-2022 07-05-2022 Contractor- 3A
139 Panel Shifting to erection location 1 day 05-05-2022 05-05-2022 134
140 Panel Erection 1 day 05-05-2022 05-05-2022 134
141 Cable Laying and termination - Power, Networking
1 day 05-05-2022
cables and Earthing
05-05-2022
of panel
134
142 Panel Power ON 1 day 06-05-2022 06-05-2022 141
143 Communication establishment 1 day 06-05-2022 06-05-2022 141
144 IEC 104 Addressing/ Checking 1 day 06-05-2022 06-05-2022 141
145 Signal simulation to ENOC 1 day 07-05-2022 07-05-2022 142
146 400kV SAMI Switching Substation 3 days 09-05-2022 11-05-2022 Contractor- 2A
147 Panel Shifting to erection location 1 day 09-05-2022 09-05-2022 235
148 Panel Erection 1 day 09-05-2022 09-05-2022 235
149 Cable Laying and termination - Power, 1 day 09-05-2022 09-05-2022 235
Networking cables and Earthing of
150 Panel Power ON 1 day 10-05-2022 10-05-2022 149
151 Communication establishment 1 day 10-05-2022 10-05-2022 149
152 IEC 104 Addressing/ Checking 1 day 10-05-2022 10-05-2022 149
153 Signal simulation to ENOC 1 day 11-05-2022 11-05-2022 150
154 400/220kV Alwar SS 3 days 12-05-2022 16-05-2022 Contractor- 1A
155 Panel Shifting to erection location 1 day 12-05-2022 12-05-2022 30
156 Panel Erection 1 day 12-05-2022 12-05-2022 30
157 Cable Laying and termination - Power, Networking
1 day 12-05-2022
cables and Earthing
12-05-2022
of panel
30
Page 4
Commissioning Schedule for Adani ENOC
ID Task Task Name Duration Start Finish Predecessors
Resource
Mode Names
02 May '22 09 May '22 16 May '22 23 May '22 30 May '22
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
158 Panel Power ON 1 day 13-05-2022 13-05-2022 157
159 Communication establishment 1 day 13-05-2022 13-05-2022 157
160 IEC 104 Addressing/ Checking 1 day 13-05-2022 13-05-2022 157
161 Signal simulation to ENOC 1 day 16-05-2022 16-05-2022 158
162 400/220/132kV Deedwana SS 3 days 16-05-2022 18-05-2022 Contractor- 1B
163 Panel Shifting to erection location 1 day 16-05-2022 16-05-2022 77
164 Panel Erection 1 day 16-05-2022 16-05-2022 77
165 Cable Laying and termination - Power, Networking
1 day 16-05-2022
cables and Earthing
16-05-2022
of panel
77
166 Panel Power ON 1 day 17-05-2022 17-05-2022 165
167 Communication establishment 1 day 17-05-2022 17-05-2022 165
168 IEC 104 Addressing/ Checking 1 day 17-05-2022 17-05-2022 165
169 Signal simulation to ENOC 1 day 18-05-2022 18-05-2022 166
170 400/220kV Morena SS 3 days 05-05-2022 07-05-2022 Contractor- 2B
171 Panel Shifting to erection location 1 day 05-05-2022 05-05-2022 126
172 Panel Erection 1 day 05-05-2022 05-05-2022 126
173 Cable Laying and termination - Power, Networking
1 day 05-05-2022
cables and Earthing
05-05-2022
of panel
126
174 Panel Power ON 1 day 06-05-2022 06-05-2022 173
175 Communication establishment 1 day 06-05-2022 06-05-2022 173
176 IEC 104 Addressing/ Checking 1 day 06-05-2022 06-05-2022 173
177 Signal simulation to ENOC 1 day 07-05-2022 07-05-2022 174
178 765kV Rajnandgoan Switching Station 3 days 03-05-2022 05-05-2022 Contractor- 3B
179 Panel Shifting to erection location 1 day 03-05-2022 03-05-2022
180 Panel Erection 1 day 03-05-2022 03-05-2022
181 Cable Laying and termination - Power, Networking
1 day 03-05-2022
cables and Earthing
03-05-2022
of panel
182 Panel Power ON 1 day 04-05-2022 04-05-2022 181
183 Communication establishment 1 day 04-05-2022 04-05-2022 181
184 IEC 104 Addressing/ Checking 1 day 04-05-2022 04-05-2022 181
185 Signal simulation to ENOC 1 day 05-05-2022 05-05-2022 182
186 Dhanbad 3 days 05-05-2022 07-05-2022 Contractor- 3B
187 Panel Shifting to erection location 1 day 05-05-2022 05-05-2022 182
188 Panel Erection 1 day 05-05-2022 05-05-2022 182
189 Cable Laying and termination - Power, Networking
1 day 05-05-2022
cables and Earthing
05-05-2022
of panel
182
190 Panel Power ON 1 day 06-05-2022 06-05-2022 189
191 Communication establishment 1 day 06-05-2022 06-05-2022 189
192 IEC 104 Addressing/ Checking 1 day 06-05-2022 06-05-2022 189
193 Signal simulation to ENOC 1 day 07-05-2022 07-05-2022 190
194 Fatehgarh 3 days 18-05-2022 20-05-2022 Contractor- 1B
195 Panel Shifting to erection location 1 day 18-05-2022 18-05-2022 166
196 Panel Erection 1 day 18-05-2022 18-05-2022 166
197 Cable Laying and termination - Power, Networking
1 day 18-05-2022
cables and Earthing
18-05-2022
of panel
166
Page 5
Commissioning Schedule for Adani ENOC
ID Task Task Name Duration Start Finish Predecessors
Resource
Mode Names
02 May '22 09 May '22 16 May '22 23 May '22 30 May '22
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
198 Panel Power ON 1 day 19-05-2022 19-05-2022 197
199 Communication establishment 1 day 19-05-2022 19-05-2022 197
200 IEC 104 Addressing/ Checking 1 day 19-05-2022 19-05-2022 197
201 Signal simulation to ENOC 1 day 20-05-2022 20-05-2022 198
202 Badaun 3 days 07-05-2022 10-05-2022 Contractor- 2B
203 Panel Shifting to erection location 1 day 07-05-2022 07-05-2022 174
204 Panel Erection 1 day 07-05-2022 07-05-2022 174
205 Cable Laying and termination - Power, Networking
1 day 07-05-2022
cables and Earthing
07-05-2022
of panel
174
206 Panel Power ON 1 day 09-05-2022 09-05-2022 205
207 Communication establishment 1 day 09-05-2022 09-05-2022 205
208 IEC 104 Addressing/ Checking 1 day 09-05-2022 09-05-2022 205
209 Signal simulation to ENOC 1 day 10-05-2022 10-05-2022 206
210 Lakhadia 3 days 11-05-2022 13-05-2022 Contractor- 2A
211 Panel Shifting to erection location 1 day 11-05-2022 11-05-2022 150
212 Panel Erection 1 day 11-05-2022 11-05-2022 150
213 Cable Laying and termination - Power, 1 day 11-05-2022 11-05-2022 150
Networking cables and Earthing of
214 Panel Power ON 1 day 12-05-2022 12-05-2022 213
215 Communication establishment 1 day 12-05-2022 12-05-2022 213
216 IEC 104 Addressing/ Checking 1 day 12-05-2022 12-05-2022 213
217 Signal simulation to ENOC 1 day 13-05-2022 13-05-2022 214
218 Ahmedabad-ENOC 26 days 03-05-2022 04-06-2022 Contractor- 4
219 Panel Shifting to erection location 1 day 03-05-2022 03-05-2022
220 Panel Erection 1 day 03-05-2022 03-05-2022
221 Cable Laying and termination - Power, 2 days 03-05-2022 04-05-2022
Networking cables and Earthing of
222 Panel Power ON 1 day 05-05-2022 05-05-2022 221
223 Communication establishment 2 days 05-05-2022 06-05-2022 221
224 IEC 104 Addressing/ Checking 15 days 05-05-2022 24-05-2022 221
225 Signal simulation to ENOC 15 days 06-05-2022 25-05-2022 222
226 Cloud Historian Testing 3 days 26-05-2022 30-05-2022 225
227 Video Integration Testing 20 days 06-05-2022 01-06-2022 222
228 Cyber Security Testing 5 days 26-05-2022 01-06-2022 225
229 System Handing Over 2 days 02-06-2022 03-06-2022 228
230 Go Live 1 day 04-06-2022 04-06-2022 229
231 Mundra-ENOC 24 days 05-05-2022 04-06-2022 Contractor- 2A
232 Panel Shifting to erection location 1 day 05-05-2022 05-05-2022
233 Panel Erection 1 day 05-05-2022 05-05-2022
234 Cable Laying and termination - Power, 2 days 05-05-2022 06-05-2022
Networking cables and Earthing of
Page 6
Commissioning Schedule for Adani ENOC
ID Task Task Name Duration Start Finish Predecessors
Resource
Mode Names
02 May '22 09 May '22 16 May '22 23 May '22 30 May '22
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
235 Panel Power ON 1 day 07-05-2022 07-05-2022 234
236 Communication establishment 2 days 07-05-2022 09-05-2022 234
237 IEC 104 Addressing/ Checking 15 days 07-05-2022 26-05-2022 234
238 Signal simulation to ENOC 15 days 09-05-2022 27-05-2022 235
239 Cloud Historian Testing 3 days 30-05-2022 01-06-2022 238
240 Video Integration Testing 15 days 09-05-2022 27-05-2022 235
241 Cyber Security Testing 4 days 30-05-2022 02-06-2022 238
242 System Handing Over 1 day 03-06-2022 03-06-2022 241
243 Go Live 1 day 04-06-2022 04-06-2022 242
Page 7