Purpose :- To establish a system for carrying out advance product quality planning and development of control plans.
Scope :- It covers all New product and changes in New Product and existing product to be developed and manufactured by the company.
This procedure is applicable from development to till sop at customer end.
Less Than 1
1 Phase Wise Phase Wise
2. First time ok at customer line trial Months
Documents :
Sr. No. Document No. Document Name Indexing Special Protection Control Authority
Records :-
Special
Sr. No. Record No. Record Name Retention Period Indexing Disposal Authority
Protection
Receipt of Enquiry along with specification / Drawing/ RFQ , Customer approved RFQ , Customer approved NPD register
Customer Dwg., sample,
1 Reference sample etc. drawing Drawing, applicable std., Marketting drawing Drawing, applicable OPPL/F/MKT/17
ECN & RFQ
sample, ECN , std., sample, ECN ,
3 Quotation Sheet Quatation of Part NPD Check quotation Quotation on Letter Head/as per format
Send the Qutation to the Customer
4 Receving Of LOI P.O LOI / P.O NPD LOI / P.O from Customer
Reveview the LOI ( letter of Intent ) / P.O ( Purchase
Order ) by Mail / Hard Copy
CFT chart
Nomination of CFT Team With Role & Responsibility should
NPD OPPL/F/MKT/11
Preparation of CFT Leader Clear of CFT Members
5 Making of CFT
Team
Traninig Of APQP / Training about APQP / FMEA / Cp & Cpk / PPAP to the Cocerrn
6 FMEA / MSA / SPC & person who will handle the APQP or Project Development Training Attandence Sheet
&Training of Testing Equipment Trainings Record NPD/HR
Spl Measuring Tools OPPL/F/HR/05
Phase -II
( Poduct Design & Development )
Prepare detailed APQP Matrix ,APQP Time Plan in Product New Product Development Timing
Develoment Plan sheet from Prototype to approval of SOP. New Product Development Project Leader CFT APQP plan to be review at Plan OPPL/F/MKT/09
7 Review the Project on Weekly Basis By CFT Head & Top
Preparation of APQP Timing Plan specified freq. Project Review Sheet
Management
Timing Plan & approval OPPL/F/MKT/16
for TOP Mangaement.
Phase-III
(Process Design & Development)
Control Plan
16 PFD/PFMEA Prelaunch Control Plan NPD Check Control Plan
Preparation of Prelaunch control Plan OPPL/F/QA/03
Work Instruction,
PFD/PFMEA/CP/Drawi Preparation of WI,Operation Std. & inspection Work Instruction,Process OPPL/F/QA/18
17 NPD
ng/Std. Standard. Sheet,Process Drawing Check Work Process Sheet
Instruction,Process OPPL/F/QA/37
Sheet,Process Drawing Process Drawing
Preparation of Logistic Study & displayed of packing Check Customer approved Packing Standard
21 Customer Packing Std. Packing Std. NPD & QA
Standard. Packing Std. OPPL/F/QA/33
SPC Report
Control Plan/Critical OPPL/F/QA/31
22 Preparation of MSA & SPC Plan. SPC & MSA Plan & report NPD & QA Check SPC & MSA Report
Characteristics Sheet MSA Report
OPPL/F/QA/08
Process Sheet,Process
Training Attandance
23 Drawing,Work Training Given to Operator about Process Instruction / SOP / Process Training Attandence QA Check Attandence Record
Sheets & Process Drawing OPPL/F/HR/05
Instruction
SPC Report
Control Plan/Critical Preparation of Preliminary Process capability Study (Cp, OPPL/F/QA/31
26 Cpk Study) & Preliminary MSA / Gauge R&R Study SPC & MSA Report QA Check SPC & MSA Report
Characteristics Sheet MSA Report
OPPL/F/QA/08
28 PPAP Documents List PPAP Documents approval from customer Customer Approval NPD/ QA Check PPAP PPAP as per customer
Control Plan
29 PFD,PFMEA Control Plan NPD/ QA Check Production Control Plan
Preparation of Production Control Plan. OPPL/F/QA/03
Phase -V
(Feedback and Corretive Action)
Customer Compilation of quality problem during trial & pilot lot in PDCA CAPA Sheet
31 Feedback/Defect Study Analysis Summery sheet & CAPA Sheet CAPA Sheet QA Check CAPA Sheet
Report during
Development
Start Mass Production Plan ( Initial Production Control ) - 3month / IPC Procedure
33 IPC Procedure 3Lot / 5000 Nos. Whichever Later. IPC Procedure QA/PROD Check IPC Procedure
OPPL/TM/PM-25