This document outlines the master plan for developing a client website. It includes multiple phases such as requirements gathering, UX/UI development over two sprints, front-end and back-end development over two sprints, system integration testing over two rounds, user acceptance testing over two rounds, security scanning, go-live preparation and support, and sign-offs by the client and for go-live. The project will take approximately 6 months and involve collecting requirements, designing wireframes and layouts, coding, testing, fixing bugs, and preparing for launch.
This document outlines the master plan for developing a client website. It includes multiple phases such as requirements gathering, UX/UI development over two sprints, front-end and back-end development over two sprints, system integration testing over two rounds, user acceptance testing over two rounds, security scanning, go-live preparation and support, and sign-offs by the client and for go-live. The project will take approximately 6 months and involve collecting requirements, designing wireframes and layouts, coding, testing, fixing bugs, and preparing for launch.
This document outlines the master plan for developing a client website. It includes multiple phases such as requirements gathering, UX/UI development over two sprints, front-end and back-end development over two sprints, system integration testing over two rounds, user acceptance testing over two rounds, security scanning, go-live preparation and support, and sign-offs by the client and for go-live. The project will take approximately 6 months and involve collecting requirements, designing wireframes and layouts, coding, testing, fixing bugs, and preparing for launch.
This document outlines the master plan for developing a client website. It includes multiple phases such as requirements gathering, UX/UI development over two sprints, front-end and back-end development over two sprints, system integration testing over two rounds, user acceptance testing over two rounds, security scanning, go-live preparation and support, and sign-offs by the client and for go-live. The project will take approximately 6 months and involve collecting requirements, designing wireframes and layouts, coding, testing, fixing bugs, and preparing for launch.
Download as XLSX, PDF, TXT or read online from Scribd
Download as xlsx, pdf, or txt
You are on page 1of 2
Client Website Development Master Plan Estimate
Project Kick-off 0 days
Discovery Phase Requirements gathering Collect requirements 5 days Develop BRD 15 days Deliver BRD to Client for review 0 days Client reviews BRD 5 days Update BRD base on Client's feedbacks 3 days Client approves BRD 0 days UX/UI Development Sprint 1 Build Wireframe 5 days Feedback wireframe 2 days Revise wireframe 2 days Approve wireframe 0 days Build layout Desktop 5 days Feedback layout Desktop 2 days Revise layout Desktop 3 days Design Desktop sprint 1 approved 0 days Build Layout Mobile 4 days Feedback layout Mobile 2 days Revise layout Mobile 3 days Design Mobile sprint 1 approved 0 days Sprint 2 Build Wireframe 5 days Feedback wireframe 2 days Revise wireframe 3 days Approve wireframe 0 days Build Layout Desktop 5 days Feedback layout Desktop 2 days Revise layout Desktop 3 days Design Desktop sprint 2 approved 0 days Build Layout Mobile 4 days Feedback layout Mobile 2 days Revise layout Mobile 3 days Design Mobile sprint 2 approved 0 days Front-end & Back-end Development Sprint 1 Coding & Unit Testing 15 days Sprint 2 Coding & Unit Testing 15 days Execute SIT Execute testing round 1 5 days SIT Bugs Fix round 1 5 days Execute testing round 2 5 days SIT Bugs Fix round 2 5 days Deliver to UAT 0 days UAT Execution Execute UAT round 1 10 days UAT Bugs Fix round 1 10 days Execute UAT round 2 10 days UAT Bugs Fix round 2 10 days UAT Sign-off 0 days Go-live Security Scan & Prepare Works for Go-live 5 days Support Go-Live 5 days Go-live Sign-off 0 days