HSF-PR-0063 Work at Height
HSF-PR-0063 Work at Height
HSF-PR-0063 Work at Height
Procedure: HSF-PR-0063
SCOPE
This procedure applies to all Company projects, offices, facilities, asset and concession companies and
Joint Venture (JV) projects where the Company Management System has been adopted by the JV Board.
Where the Company is required to operate another party’s Management System then the requirements of
the Joint Venture/Alliance Business Management System (BMS) Assessment (MSC-PR-0002) must be
followed in relation to assessing the validity of third party management systems.
PURPOSE
The purpose of this procedure is to identify and control the risks associated with work at height. This
procedure applies to any type of work at height, e.g. working platforms, roof work, scaffolds, ladders or
steps, climbing etc., where a person could be injured falling from height, even if it is at or below ground
level.
The requirements in this procedure are considered to be our current standards and must be adopted as
part of a safe system of work. However, Projects and Contracts are also encouraged to identify new
methods of working as long as these are: developed through rigorous risk assessment, demonstrably
improve on current standards, deliver legal compliance and are approved in accordance with the Control
of HSES Derogation procedure (HSES-PR-0004).
PROCEDURAL REQUIREMENTS
1. COMPETENCE
1.1 Anyone involved with designing, planning, supervising, organising or the carrying out of work at
height must be competent to do so.
1.2 MEWP Coordinator. A MEWP Coordinator must have IPAF MEWPs for Managers Training.
1.3 MEWP Operators MEWP Operators must have IPAF, CPCS or NPORS (CSCS) training
applicable to the item of plant to be used. In addition, the operator must be given
familiarisation training on the particular equipment prior to use. This familiarisation must include
machine specific emergency lowering information. Operators must also be able to demonstrate
their fitness for their role in accordance with the Occupational Health Surveillance – Assessment
procedure (HSF-PR-0035).
1.4 PAV Operators. PAV Operators must have IPAF or CPCS training applicable to the item of
plant to be used and must be given familiarisation training on the specific equipment prior to
use. This familiarisation must include machine specific emergency lowering information.
1.5 MCWP Coordinator. A MCWP Operator must have attended the relevant IPAF Operator
(either OP or OP(M)) training course and have a minimum of an SMSTS qualification (or
company accepted equivalent).
1.6 MCWP Operator. An MCWP Operator must have attended the IPAF Operator – OP training
course and must also receive MCWP specific familiarisation training from the supplying
company’s demonstrator.
1.7 MCWP Mobile Operator. Must have attended IPAF Mobile Operator – OP(M) training course.
In addition, the MCWP Operator must also receive MCWP specific familiarisation training from
the supplying company’s demonstrator.
1.8 Cradle Coordinator. A Cradle Coordinator must have attended the cradle specific
familiarisation training from the supplying company’s demonstrator and have a minimum of an
SMSTS qualification (or company accepted equivalent).
1.9 Cradle Operators. Cradle Operators Must have attended the cradle specific familiarisation
training from the supplying company’s demonstrator.
1.10 Scaffold Design. All tube and fitting scaffolds must be designed, assembled and dismantled by
trained and competent people unless it is a basic scaffold as described in NASC document TG
20. System scaffolds must be designed, assembled and dismantled by trained and competent
people in accordance with the manufacturer’s guidelines. See SBU Temporary Works
procedures (definitions section) for further details.
1.11 Scaffolder. A Scaffolder must hold a current and valid CISRS qualification, relevant to the type
of scaffold being erected or dismantled. Erection of a designed scaffold must be carried out
under the direct supervision of a CISRS Advanced Scaffolder with relevant competence for the
type of scaffold being erected. See here for Scaffolders CISRS CPD requirements from July
2017
1.12 Scaffolding Inspectors. A person who has passed a CISRS Basic Scaffold Inspection Course
is deemed competent to inspect basic scaffold structures, as defined in NASC document TG20.
All other scaffold structures must be inspected by one of the following:
An Advanced Scaffolder who was not involved in the erection of the structure
A person who has passed a CISRS Advanced Scaffold Inspection course
A scaffold/temporary works designer
1.13 Persons who are required to carry out inspections of system scaffolds must, in addition to the
above, attend a product training course for the specific system and hold certification for that
scaffolding system.
1.14 Hoist Erector. NVQ levels two or three in Hoist Installation.
1.15 Hoist Operator. Familiarisation training by the hoist supplier and holds a valid CPCS A20
Category Card.
1.16 Appointed Person for hoist activities. Must have attended a 2 hour awareness session as a
minimum on Managing Hoists to gain an understanding of statutory legislation, in particular
BS7212.
1.17 Competent Person for hoist activities. Must have received familiarisation training from the
suppler of the hoist.
1.18 Prefabricated mobile tower scaffolds. These scaffolds must only be erected, altered, and
dismantled in accordance with the manufacturer’s instructions by those holding a valid PASMA
or CISRS qualification competency.
Users of mobile tower scaffolds who do not hold a PASMA qualification must receive the Safe
Working from Mobile Towers briefing (HSF-RM-0063c).
1.19 Safety Nets. Safety net installers/providers must be members of FASET.
Safety netting installation must be carried out by a holder of the CSCS / FASET Safety Net
Rigger Card. Note that this is not applicable to the nets used to protect assets during overhead
line work.
1.20 Podium Steps. Users of podium steps must familiarise themselves with the equipment by
reviewing the manufacturer’s guidance and instructions. If the equipment is hired, this
familiarisation must be provided by the hire company.
1.21 Harnesses issued to individuals for sole use (Personal issue equipment): Users should
be trained in the safe use and inspection of harnesses to IRATA, IPAF (for use in MEWPs only)
or the manufacturer’s standards.
1.22 Non Personal Issue. The Plant Specification Checklist for Lanyard and Harness (HSF-CL-
0046cy) for initial pre-use and Inspection of Safety Harness/Lanyard/Inertia Reels (Weekly and
Thorough) (HSF-SF-0048c) must be undertaken by a competent person who is trained in
harness use and holds a recognised harness qualification from IRATA, IPAF (for use in MEWPs
only) or the manufacturer.
1.23 All harnesses must undergo a quarterly Thorough Examination, undertaken by competent
person who holds a recognised Thorough Examination harness qualification from IRATA, IPAF
(for use in MEWPs only) or the harness manufacturer.
1.24 Hired harnesses must be supplied with a current examination certificate. Pre-use inspections
should still be completed.
1.25 All users of harnesses must be suitably trained in harness use for the activity they are
undertaking.
1.26 Anyone supervising, using or inspecting rope access techniques or equipment must be trained,
competent and able to provide documentary proof of an accredited qualification e.g. IRATA,
LANTRA approved (original format only), relevant to the type and complexity of the technique
being used. Copies of documentary proof will be retained on site.
2. ZERO TOLERANCE
2.1 Zero Tolerance rules apply to Working at Height. See Health and Safety Communications for
more details and examples of breaches.
3. WORKING AT HEIGHT
3.1 Site Leads must ensure that any work being carried out at height is:
Necessary or unavoidable
Properly planned, including the selection of work equipment
Appropriately supervised
Carried out in a safe manner
3.2 All temporary works must be managed in line with the SBU Temporary Works procedures (see
later definitions section). The Temporary Works Co-ordinator, where required is to be involved
with, or consulted on, the procurement or hire of temporary structures, such as scaffolds,
working platforms and MEWPs etc.
3.3 Risk Assessments and Method Statements/Work Package Plan must incorporate the hierarchy
of controls illustrated below to identify the most appropriate methods for control of risk from work
at height:
Level Description Risk Control Measures
ELIMINATE Avoid the risk by not working at height At design stage, review the need to
work at height and consider then
apply the hierarchy of control. (i.e.
prefabricate at ground level, pipe-
jacking/moling etc.)
MINIMISE Where work at height is unavoidable, This will include choosing the right
assess the risks to workers and provide work equipment to prevent falls, e.g.
suitable and sufficient measures to guardrails, MEWPs, tool tethering
allow the work to be done whilst etc.
preventing people or objects falling.
MITIGATE Where the risk of people or objects This involves the selection and use
falling still remains, steps must be taken of work equipment e.g. harnesses,
to reduce the distance and netting, airbags, etc.
consequences of such falls.
3.4 At all stages collective protective measures which protect the whole workforce (e.g. guardrails,
nets, airbags, etc.) must be given precedence over personal protective measures (e.g. safety
harnesses) which are focused on protection of an individual.
3.5 When carrying out a risk assessment the following controls must be considered, and were
applicable, detailed in the assessment:
Trained and competent individuals
Selection of suitable work equipment
Safe systems for protecting people from falls from height which where practicable must
include a physical rigid barrier to prevent falls from height. Where this is not practicable,
the risk of a fall must be controlled by netting, airbags, or fall arrest / restraint harnesses
and lanyards
The working conditions, the natural environment and the effects of the weather
The location of the work to be undertaken (including access and egress, ground
conditions, overhead obstructions)
Access and egress
The height or distance and consequences of any potential fall
Emergency, evacuation and rescue requirements e.g. health conditions, entrapment,
equipment failure, etc.
Elimination of unauthorised plant or equipment modifications
Prevention of the modification or overriding of any controls or safety devices
Inspection and maintenance of work equipment.
Ensuring non-compliant or unserviceable plant or equipment is immediately removed
from use, tagged and quarantined until made safe or removed from site
The prevention of tools or materials from falling from height, including the use of
exclusion zones with physical barriers or demarcation zones e.g. cones or sigma posts
with a rope around the tops complete with appropriate signage
Managing the risks from working on or around fragile surfaces
3.6 Rope access activities require health checks to be conducted for operators. Operators must be
able to demonstrate their fitness for role in accordance with the Occupational Health
Surveillance – Assessment procedure (HSF-PR-0035).
3.7 Following the production of a risk assessment, method statement/work package plan and task
briefing the contents must be communicated to those who will undertake the work in accordance
with the Setting People to Work Safely procedure (HSES-PR-0011).
3.8 The Site Lead must ensure emergency and rescue procedures are included within the safe
system of work in accordance with the requirements of Section 25 Emergency procedures of
this procedure.
3.9 The throwing (‘bombing’) of materials or objects from height is strictly prohibited.
5.8 Any defective guardrails, toe boards and brick guards must be taken out of service immediately,
with the supporting structure being ‘tagged’ as unfit for use. Safety signs identifying the areas
where access is not permitted must be displayed at the access points to these areas. In
addition, access to the defective areas must be prevented by suitable physical means (e.g.
secure full-height barriers fitted to stairways, ladders removed to prevent access on to the
platform, etc.).
6. OPENINGS
6.1 Works must be planned and the risks assessed to ensure that protection is in place at openings
during all phases of the works.
6.2 All openings in concrete slabs, floors, decking, risers and manholes must be effectively
highlighted and protected with securely fixed covers (Approved by Temporary Works
Coordinator) to prevent persons or materials falling through them.
6.3 Lift shafts must be protected by:
A proprietary system to prevent persons, tools, equipment or materials falling into them,
or if this is not available, a physical secured barrier
Warning signage, or have an authorised person access control system established
7. REQUIREMENTS FOR WORKING PLATFORMS
7.1 Any surface upon which a supporting structure rests must be stable and of sufficient strength to
support the structure and any additional loading placed on it.
7.2 If a working platform is mobile it must be prevented from inadvertently moving during work at
height.
7.3 The supporting structure must be stable whilst being erected, used, altered, or dismantled.
7.4 When working at height the working platform must:
Be a minimum of 600 mm wide. Where this is not possible a specific risk assessment
must be produced which ensures the platform is of sufficient dimensions to allow for safe
passage and safe use of equipment and materials
Be built to prevent person or materials falling through a gap
Be free of hazards that could cause trips and be kept clean and tidy, ensuring that debris
and other material does not build up on platforms
Clearly display the Safe Working Load of the platform
Not be overloaded which may result in a risk of collapse or any deformation
7.5 Exclusion zones, complete with appropriate signage, must be established to prevent access to
areas where there is a risk of falling objects.
7.6 The use of the following items is prohibited at all Company properties and projects for work at
height:
Low Level Access Systems (Metal Trestles / Bandstands / Ironmen)
Stilts
9.5 Where appropriate safety netting will be overlaid with debris netting, consideration must be
given to the type of materials likely to fall, e.g. fixings or tools, when choosing the overlay debris
netting.
9.6 A Safe System of Work (including Risk Assessment and Method Statement/Work Package
Plan) developed in conjunction with the manufacturer and installer must be produced for the
retrieval of debris from safety netting.
9.7 A handover certificate must be issued by the netting installer before being put into service.
9.8 Safety netting must be formally inspected (in accordance with manufacturer’s instructions or
recommendations) by a trained and competent person (CSCS or FASET Safety Net Rigger card
holder):
After installation or assembly in any position.
After any event likely to have affected its stability, e.g. following strong winds or
substantial alteration.
At intervals not exceeding seven days.
9.9 Site Leads must ensure a daily visual check of the safety netting is undertaken and recorded by
a nominated competent person who has an SMSTS (or Company accepted equivalent course)
qualification and has attended a briefing by the FASET approved netting installer.
9.10 Safety netting must be thoroughly tested annually off-site and immediately following the fall of a
person or object that has the potential to affect the integrity of the net.
9.11 The Site Lead must ensure emergency and rescue procedures are included within the safe
system of work in accordance with the requirements of Emergency section below in this
procedure.
10. SOFT LANDING APPARATUS (AIR OR BEAN BAGS)
10.1 Airbags, landing mats or similar safeguards must be suitable for the deployment circumstances.
They should be installed in accordance with the manufacturer’s instructions and installers must
be briefed on the installation procedure.
10.2 Soft Landing Apparatus:
Must only be used if no safer alternative exists.
Must only be used where fall distances are kept to a minimum, but never greater than 2
m and where practicable their use should be in conjunction with fall restraint equipment.
Must be installed in accordance with the manufacturer’s instructions which must be
readily available on site.
Must be inspected by a competent person, who has also attended the suppliers or
manufacturers briefing, before first use, daily or following reinstallation, to ensure that it
has been correctly installed and maintained.
Any component parts found to be damaged or degraded in any way must be
quarantined, reported to the Supervisor and replaced immediately.
11. MOBILE ELEVATED WORKING PLATFORMS (MEWPs) INCLUDING PUSH AROUND
VERTICALS (PAVS)
11.1 A MEWP Coordinator must be appointed to coordinate the selection of the correct MEWP,
planning of the works and to coordinate their use. If the number of MEWPs operating cannot be
effectively controlled by one individual additional MEWP Coordinators must be appointed and
specific areas of responsibility defined.
11.2 All MEWPs used on Company projects, either directly or through subcontractors, must be
designed to prevent entrapment through sustained involuntary operation of the MEWP, through
interference with either electronic or mechanical systems. Examples include SkySiren or SiOPS
pressure sensitive systems, shrouded protection to the platform controls or Sanctuary Zones.
11.3 The Site Lead, in conjunction with the MEWP Coordinator, must ensure that site specific risk
assessments and safe system of works are completed and that they consider the following:
Delivery and collection
Ground conditions including evidence of ground disturbance
Controlling the People and Plant Interface, including members of the public
Plant and Vehicle Marshal(s) requirements
MEWP routes to be free of obstructions, significant holes or depressions
Underground utilities, man hole covers, cable ducts etc.
Overhead or adjacent hazards including utilities, overhead structures etc.
Induced or Impressed Voltage Hazard, from working in close proximity to live electricity
Operating speed and capability of the MEWP, ensuring it is suitable for the terrain,
gradients and site ground conditions
Physical exclusion zones
Lone working requirements
Maintenance requirements
Emergency response and rescue arrangements (e.g. rescue provided by in-house
personnel, specialist contractors or the emergency services by prior arrangement).
Fragile Surfaces
11.4 The duties of a MEWP Coordinator include ensuring the following:
All risk assessments and safe systems of work are suitably reviewed and communicated
to all relevant parties
Records of familiarisation training, operator qualifications and driving licences or CPCS
training, where applicable, are maintained
MEWP movements from one work area or exclusion zone to another are coordinated
with the Plant and Vehicle Marshal and other planned activities.
The Plant Specification checklist – MEWP (relevant to the type of MEWP in use) (HSF-
CL-0046al, am, an, ao or ap) is completed prior to first use and daily checks of MEWPs
are carried out thereafter (HSF-SF-0046AL)
When working in proximity to live electricity, that the Additional Option on the Plant &
Equipment Specification ‘Dedicated Earthing Point for MEWP’s working in proximity to
overhead power lines and Sub-Stations’ is specified at the time of ordering. On delivery
of the MEWP visually check to ensure that the dedicated earth is connected and is
electrically continuous from the chassis to the basket
There are appropriate numbers of nominated persons on site within close proximity, on
the ground, to MEWPs in operation who have demonstrated they can implement the
emergency lowering procedure
Any reported defects are rectified before a MEWP is put back into operation
A safe loading and unloading area has been provided for the delivery and collection of
the MEWP(s). See Minimum Controls for Loading and Unloading Areas (HSF-RM-
0063e)
Safety harnesses, with a suitable restraint lanyard, are provided as identified in Risk
Assessment/Method Statement (Work Package Plan) and relevant personnel are
specifically trained in their use and inspection
A safety harness and lanyard inspection register is maintained
Safety harnesses and lanyards have been examined and certificated
11.5 Operation and use of MEWPs or PAVs must be carried out in compliance with a Safe System of
Work and the manufacturer’s operating instructions.
11.6 For short duration MEWP use, the Site Lead or MEWP Co-ordinator will determine the
emergency rescue drill requirements. All projects which use MEWPs continuously for more
than 12 weeks must undertake an Emergency rescue drill on a quarterly basis. All rescue drills
must be recorded on the Emergency Evacuation and Drill Response Record (HSF-SF-0009b).
11.7 Emergency lowering procedures must be demonstrated by the supplier or hirer to employees as
identified by the MEWP Coordinator(s). The MEWP Coordinator must ensure a record of this
demonstration is recorded on the MEWP Recovery Checklist (HSF-SF-0063d).
11.8 During a rescue drill all individuals in a MEWP must remain on the basket floor.
11.9 Exiting or entering a MEWP is only permitted when it is not elevated or not operating at height,
unless the access or egress is covered by a safe system of work and specific risk assessment
approved by the HSES Advisor and the Site Lead’s Line Manager in accordance with industry
and HSE Guidance, such as BS8460:2005 Annex B Guidance on safe systems of work for
exiting the work platform at height or IPAF’s Exiting the Platform at Height guidance.
11.10 Driving and operating MEWPs from outside the platform is not permitted unless in an
emergency.
11.11 The loading and unloading of MEWPs onto road-going transport must be undertaken in
accordance with the Plant Procedure (HSF-PR-0046). Also see Minimum Controls for Loading
and Unloading Areas (HSF-RM-0063e)
11.12 The Safe Working Load (SWL) of the MEWP must not be exceeded.
11.13 The issue and wearing of a full body harness (BS EN 361) and restraint lanyard (BS EN 354),
which restricts the limit of travel to the confines of the basket, is only mandatory in Boom Type
MEWPs and must be worn at all times. The only exception to this mandate is when working
over or adjacent to water that presents a risk of drowning should the MEWP inadvertently
overturn. In such circumstances an automatically inflating life jacket must be worn. Refer to
Working Near Water procedure (HSF-PR-0065).
11.14 Lanyards must only be attached to the designed anchorage point within the confines of the
basket.
11.15 Scissor lift MEWPs must only be traversed when in lowered position. If traversing is required at
any other height, a safe system of work must be in place and a harness and restraint lanyard
must be worn.
11.16 Any defective MEWP or PAV must be taken out of service immediately and ‘tagged’ as unfit for
use with relevant safety signs being displayed at the access points. In addition, the equipment
must be quarantined in such a way that it cannot be used in error until it has been approved for
re-use e.g. the ignition keys removed and held in a secure location within the site office.
11.17 Specific control measures must be recorded on a Task Briefing Sheet (HSES-TF-0011b) and
the contents communicated to the relevant employees in accordance with the Setting People to
Work Safely Procedure (HSES-PR-0011).
11.18 When an attachment is fitted to a MEWP or PAV and is used to lift equipment or materials (such
as a SkyRak) a lift plan must be produced in accordance with the Lifting Procedure (HSF-PR-
0039).
11.19 The Site Lead, in conjunction with the MEWP Coordinator, must ensure that MEWP operations
are suspended during adverse weather conditions, in accordance with the manufacturer’s
instructions. This may include periods of high wind speed, lightning, snow, fog and heavy rain.
12. MEWPs Working on the Rail Infrastructure – Additional Requirements
12.1 When planning to use MEWPs on the rail infrastructure the following documents must be
consulted or used:
Network Rail
Infrastructure Plant Manual – NR/0200/PLANT
NR/0200/Plant – Module P300 Plant approval and design, section 4.2
NR/0200/Plant – Module P508 Mobile elevating work platforms MEWPs
London Underground
S1171 - All Plant - Acceptance, Use and Maintenance
S1173 - On Track Plant – Design and Acceptance
M&EE Codes of Practice
COP0023 - Inspection of Demountable MEWP and Lifting Equipment
COP0024 - Use and Loading of MEWPs
12.2 Some examples of equipment covered by the above standards are:
Baskets fitted to excavators or cranes
MEWPs on modular systems
Knuckle boom cranes on modular systems
12.3 Site Lead must ensure that:
The combinations of base vehicle and module or attachment type permitted shall be
specified on the Rail Infrastructure Manager’s Plant Approval Certificate e.g. Network
Rail - EAC (Engineering Acceptance Certificate), ECC (Engineering Conformance
Certificate) or London Underground - Certificate of Acceptance as appropriate.
The Thorough Examination certificate, issued in accordance with The Lifting Operations
and Lifting Equipment Regulations 1998 (LOLER), shall include reference to the base
vehicle and module or attachment by unique identifier or serial number.
Where the base vehicle is capable of using more than one module or attachment a
Thorough Examination certificate is required for each individual module or attachment.
12.4 The fitting of a module or attachment to the base vehicle must be undertaken in accordance
with the manufacturer’s instructions.
12.5 A function check of the base vehicle and module or attachment must be carried out to confirm
correct functionality.
12.6 The module or attachment must only be fitted to the base vehicle by a person trained and
competent to do so.
13. MAST CLIMBING WORK PLATFORMS (MCWP)
13.1 All MCWP supplied must comply fully with BSEN1495:1997+A2:2009.
13.2 The Site Lead must ensure that a Lead MCWP Co-ordinator is appointed and deputies where
required who has overall control of each specific MCWP operation.
13.3 The duties of a MCWP Coordinator include the following:
All risk assessments and safe systems of work are suitably reviewed and communicated
to all relevant parties
Records of familiarisation training and operator qualifications are maintained
MCWP movements from one work area or exclusion zone to another are coordinated
with the Plant and Vehicle Marshal and other planned activities.
Plant Specification Checklist – Mast Climber (HSF-CL-0046cq), pre-use, daily and
weekly checklists are completed
There are appropriate numbers of nominated persons on site within close proximity to
MCWP in operation who have demonstrated they can implement the emergency
lowering procedure
Any reported defects are rectified before a MCWP is put back into operation
Ensuring that a safe loading and unloading area has been provided for the delivery or
later collection of the MCWP(s). See Minimum Controls for Loading and Unloading
Areas (HSF-RM-0063e)
13.4 The MCWP supplier must undertake a site survey for each MCWP location which will include:
Establishing the primary purpose that MCWPs will be used for, together with any other
additional requirements there might be for the unit, e.g. prevention of falling debris
Length of the work platform required and the work platform configuration, including any
edge extensions, for the full duration of the installation
Mast positions
Maximum height of travel
The work platform loading capacity and method of loading
Access and egress for personnel and materials
Ground and supporting base conditions (levels and load bearing capacity)
Area conditions around base with particular relevance if an MCWP is movable and is to
be moved while on site
Tie fixing point strengths and fixing point details on the structure, including suitable
means of access to such points for installation and dismantling
The results of the assessment of the strength of the structure to support MCWPs carried
out by Temporary Works Designer
Identification of uninsulated electrical conductors in the vicinity of MCWPs. These
exposed conductors must be adequately shielded or moved as appropriate
Windows or doors that open into path of the work platform.
Debris netting around the cradle is installed to prevent materials or tools falling
14.7 Once the initial installation has been completed in accordance with the supplier method
statement, no modification to the installation will be allowed without a reassessment by the
supplier. This will include a full study of the proposed modification, implications for safety during
the remainder of the cradles planned use, and its subsequent dismantling. Any modification
must only be undertaken by the cradle supplier’s qualified workforce.
14.8 Repositioning of a cradle must only be carried out by the cradle supplier’s qualified workforce.
14.9 Inspection and testing by the cradle supplier must be carried out after erection and before being
taken back into their service, after the occurrence of a dangerous incident (prior to being put
back into service) and at least quarterly thereafter. A Thorough Examination must be carried out
every 6 months.
14.10 At the beginning of each shift or working day, the Cradle Operator must ensure cradles are
checked to ensure that they are in a fit condition to start work. The cradle supplier will supply a
check list specific to the cradles on site.
14.11 Once a week the cradle must be inspected to ensure that no damage or wear has occurred and
that all safety systems are functioning correctly. This inspection must be carried out by the
Cradle Coordinator using the daily inspection checklist and operators manual supplied by the
cradle supplier.
14.12 The cradle will be maintained by the Supplier in accordance with the manufacturer’s
recommendation and the supplier organisations thorough examination regime.
14.13 The Cradle Coordinator must ensure that a designated access and egress route to and from the
cradle is ascertained and communicated to all cradle users including installers and those
persons carrying out examinations, inspections and maintenance.
14.14 An exclusion zone must be implemented with physical barriers around the base location of the
cradle to ensure that the risk of injury from being trapped and/or crushed by the descending
cradle or being struck by falling debris is eliminated. Suitable, clear and durable notices
warning of the danger and instructing persons to keep clear must be conspicuously displayed.
14.15 The use of harnesses within Cradles is obligatory for all personnel. Harnesses must be fixed to
a structural member. Secondary lines can also be used direct to each operative. Fall protection
equipment must not be attached to the work platform unless the supplier has agreed the
location and suitability of anchor points.
14.16 Where cradles are to operate near to other construction equipment, such as cranes and
especially where any part of the construction equipment or load can occupy the same space
that is traversed by the work platform for a cradle, a specific safe system of work must be
implemented. In particular each operator must have an adequate field of vision and be able to
communicate reliably with other operators.
14.17 Specific emergency arrangements must be put in place prior to works commencing on a cradle.
Emergency arrangements must be tested on a quarterly basis and the recorded on the
Emergency Evacuation and Drill Response Record (HSF-SF-0009b).
15. INDEPENDENT SCAFFOLDS
15.1 See competence section regarding scaffold design and erection for relevant competencies.
15.2 Prior to any scaffold being erected on the Public Highway a relevant permit or licence must be in
place from the Local Authority. The licence must be in place for the full duration of the
construction works and must be renewed when necessary.
15.3 All scaffolding companies responsible for designing scaffolding must hold Professional
Indemnity (PI) insurance or have employed a design engineer who holds PI insurance. In both
cases the validity of the insurance must be checked before the contract is awarded.
15.4 Emergency Access Routes and Emergency rescue arrangements must be discussed and
agreed with the HSES Function and/or Emergency Services prior to erection of the scaffold.
15.5 Completed scaffold must be in accordance with BS EN 12811-1, BS EN 12810-1, TG 20 or to a
specific engineered design
15.6 All scaffolding contractors must work in accordance with NASC guidelines.
15.7 Scaffold structures including scaffold edge protection, must be erected and inspected by an
appropriately qualified CISRS operative with the appropriate grade of training and competence
(this includes tube and fitting scaffolding around lift shafts, openings, prefabricated staircases,
etc.) and undertaken in accordance with the Safe System of Work.
15.8 Handrails must be erected and inspected by an appropriate qualified CISRS operative with the
appropriate grade of training/competence (Class A handrails (Steel work erection – BS EN
13374 etc.) must be designed as such to be inspected by a competent person (CISRS).
Handrails used for demarcation / excavation (tubes pushed into the ground / ‘A’ frames) need to
be inspected by competent trained scaffold inspector with TW coordinator input).
15.9 Any scaffold erected for more than 7 days must have a proprietary staircase installed for all
primary access routes where this is reasonably practicable. The safe system of access must be
agreed with the Site Lead and the HSES Function using the hierarchy below, where practicable:
Passenger hoist
Proprietary staircase
External ladder with landings and gates
Internal ladder with gates and toe boards
External ladder with hatches
Internal ladder with hatches
15.10 During the erection or dismantling of scaffolds all works must be carried out in accordance with
SG4 (latest issue). Advanced guardrails must be given the priority as the preferred erection
method.
15.11 Scaffold must be close boarded to prevent people, material or tools falling, and must be kept
clear at all times. A clear access of at least 600 mm must be maintained where practicable.
15.12 When the area beneath is an exclusion zone the size and type of material/components being
used on the platform and the potential for deflection if something falls through must be assessed
e.g. a piece of 20mm x 2m reinforcement steel has the potential to roll and fall through a 25mm
gap and dependent on height of scaffold has the potential to deflect a considerable distance.
15.13 Where access to the area below the working platform cannot be excluded all gaps must be
physically covered using plywood or proprietary products. The covering plywood or proprietary
product must overlap at least 100 mm either side of the gap in accordance with NASC standard
requirements.
15.14 Boards potentially exposed to inclement weather must be secured to prevent movement.
15.15 Timber scaffold boards and battens must be clearly marked showing that they are graded to
BS2482, normally located on the end bands. The letter ‘M’ or ‘V’ denoting ‘Machine’ or ‘Visual’
grading should also be clearly marked. Boards and battens must not exceed the maximum
support centres marked. Laminated Veneer Lumber and Composite Plastic scaffold boards and
battens as defined in TG20 are also acceptable for use.
Document Authoriser: Craig McCallum Uncontrolled when printed or downloaded
Date of Issue: 11/07/2018 Page 18 of Version: 2.2 A Balfour Beatty UK Document
32
Work at Height
Procedure: HSF-PR-0063
15.16 Edge protection must be installed without gaps over 470 mm. The top rail height will be
preferably 1000 mm high, but at least 950 mm high. Where scaffolds are loaded above toe
board height, or where risk assessment shows the potential for materials or tools to fall, brick
guards must be in place.
15.17 Where there is a requirement for sheeting or encapsulation, the scaffold must be designed to
withstand the potential loads imposed, refer to SBU Temporary Works procedures (see
definitions section). The sheeting must conform to LPS 1215 (Flame Retardant Certification).
15.18 Hemping or topping up of scaffold standards must be kept to distances as small as reasonably
practicable. Twenty one foot tubes must not be hemped or topped up.
15.19 Where there is a requirement to tie scaffolding to a building or structure, the Temporary Works
Function must ensure the building or structure will withstand the imposed load. The Site Lead /
Temporary Works Coordinator must ensure the Scaffold Designer and Building Designer /
Structural Engineer / Temporary Works Designer confirms the correct tie type, tie points and
testing regime.
15.20 Prior to a hand over certificate being issued, a joint inspection between the Company and the
scaffold provider must be carried out. The Handover Certificate (HSF-SF-0063e) or an
equivalent form provided by the scaffold provider (stating scaffold type, loading(s), intended use
and pull out test results including tie counts, design drawings) is required for all scaffold and
subsequent major adaptions. All hand over certificates must be retained and used for reference
where required.
15.21 All hand over certificates must be accompanied by a completed Scaffold Inspection Checklist
(HSF-SF-0063f) or an equivalent form provided by the company handing over the scaffold.
15.22 All scaffolding must be inspected prior to first use, following any event or inclement weather
which may have affected the integrity of the scaffold, after any major adaption, and at least
every seven days. All inspections, except daily or pre-use visual must be recorded using the
Scaffold, Working Platform and Mobile Tower Inspections (HSF-SF-0063h) or an equivalent
form provided by the company engaged to carry out the inspections.
15.23 Design drawings and / or a TG20 NASC Compliance Sheet must be on site and in the
possession of the Scaffold Supervisor prior to commencing erection and must be available at
the time of handover and during any inspections.
15.24 Exclusion zones may require to be erected whilst carrying out scaffold works at height. The
exclusion zone must be a solid barrier with appropriate safety signs in place. Whilst planning
exclusion zones, dropped objects and deflection must be taken into account.
15.25 When a scaffold is not available for use it must be marked with warning signs (e.g. Scafftag)
and secure barriers fitted to stairways or ladders to prevent access.
15.26 Precautions must be taken prior to inclement weather conditions that may adversely affect the
safety of the scaffold.
15.27 Any defective scaffold equipment must be taken out of service immediately and quarantined
until removed from site.
15.28 Where there is a risk of dropping tools or equipment from height, tool tethering must be
implemented.
15.29 The Safe System of Work for erecting or dismantling scaffold must contain suitable and
sufficient detail including the planned sequence, significant risks, exclusion zones, resource and
methodology for safely passing component parts from their ground level to installed location and
vice versa and briefed to all involved in accordance with the Setting People to Work Safely
procedure (HSES-PR-0011).
15.30 Where a scaffold is supplied and controlled by a Client or Third Party the above requirements
must all be checked and records in place to demonstrate that the scaffold has been erected in
accordance with the design and inspected as required by a competent person. Where a Client
or a Third Party hands over a scaffold to the Company for its sole use, the above requirements
must also be checked and appropriate records in place. The Insurance Function must also be
consulted to ensure all requirements are in place.
16. PREFABRICATED MOBILE TOWERS
16.1 All prefabricated mobile towers must be erected in accordance with the safe system of work and
manufacturer’s instructions by trained erectors. Preference to be given to collective measures
(i.e. advanced guardrail) where practicable.
16.2 All working platforms must have two handrails and toe boards in place to the correct spacing in
accordance with the manufacturer’s instructions and as defined within Schedule 2 of the Work
at Height Regulations. Where this cannot be achieved e.g. in arches, tunnels etc. a safe system
of work must be implemented.
16.3 An inspection must be carried out by a trained competent person and an appropriate tag (e.g.
Mobile Tower Scafftag) must be completed and fixed to the tower:
Before first use
When the tower is erected for more than 7 days
After an alteration is made to the platform e.g. removal of handrails and alteration of
platforms
16.4 The inspection must be recorded on the Scaffold, Working Platform and Mobile Tower
Inspections Register (HSF-SF-0063h) and the Scafftag updated.
16.5 As the stability of any mobile tower scaffold can be easily affected by inappropriate use the Site
Lead must ensure, unless the tower has been specifically designed for such use, the following
activities are never carried out from a mobile tower:
Fixing of sheeting, or other similar materials
Grit blasting or water jetting
Using the tower to hoist materials or support rubbish chutes
Attaching, supporting plant or materials to the exterior of the tower
16.6 Specific control measures for working from prefabricated mobile towers must be recorded on a
Task Briefing Sheet (HSES-TF-0011b) and the contents communicated to the relevant
employees in accordance with the Setting People to Work Safely Procedure (HSES-PR-0011).
16.7 The Site Lead must ensure the following checks are carried out prior to mobile scaffold towers
being moved:
The height of tower must be reduced, where appropriate, to 4 m or less
Location of power lines or other overhead obstructions are noted
The ground is firm, level and free from potholes
There are no people or materials on the tower. Tower surfing is strictly prohibited!
16.8 Any defective towers, that cannot be rectified immediately, must be dismantled by a trained
person under a specific safe system of work.
Ropes are kept in safe positions, e.g. away from obstructions, vehicles, equipment and
the public
Precautions that have been taken to exclude the public and traffic from the work area
are maintained while work is in progress
19.6 Rope access personnel must have an appropriate emergency first aid qualification, and as a
minimum carry a personal first aid kit, incorporating a large wound dressing, barrier gloves,
plasters and means to call the emergency services.
19.7 On all reasonably foreseeable approaches to the work area, appropriate warning and prohibition
signs must be erected informing that unauthorised access is prohibited. In areas where
pedestrians may access, additional controls, e.g. physical barriers and /or extra personnel must
be used.
19.8 Rope access personnel not specifically trained in working adjacent to overhead power lines
must observe the appropriate minimum distances:
Description Exclusion Zone
Low-Voltage Line 1 metre
11 kV and 33 kV Lines 3 metres
25 kV (Network Rail only) 2.75 metres
132 kV Line 6 metres
275 kV and 400 kV Lines 7 metres
19.9 Work may only proceed under the authority and guidance of the appropriate utility authority.
The exclusion may have to be extended dependent upon the Owner’s requirements or to allow
for the possibility of other machinery/equipment encroaching into the exclusion zone.
19.10 Everyone engaged in rope access operations must be fit to undertake the task. Physical or
mental issues that could affect performance must be reported to their Line Manager.
19.11 A certificate of conformity with the relevant BS EN standard must be provided with all new items
of rope access equipment. Equipment must carry a relevant CE mark.
19.12 All items of rope access equipment must be used according to the manufacturer’s instructions.
The equipment must only be used for its intended purpose.
19.13 Weekly inspections of equipment must be recorded in the Inspection of Safety Harness-
Lanyard-Inertia Reels (Weekly and Thorough) (HSF-SF-0048c) or the specialist contractors
equivalent and equipment ‘thoroughly examined’ by a ‘competent person’ every 3 months.
Defective equipment must be immediately withdrawn from use and destroyed.
19.14 All rope access equipment must be maintained and stored in accordance with manufacturer’s
instructions. Wet equipment must be dried thoroughly before storage, e.g. in a well-ventilated
environment away from any direct heat source.
20. STEPLADDERS AND LOOSE LADDERS
20.1 All projects and locations must commence with a prohibition on the use of stepladders and
loose ladders. Stepladders and loose ladders must only be used as a last resort.
20.2 Site Leads must ensure that a stepladder or loose ladder is NOT used unless a site specific
Risk Assessment has demonstrated that the use of other types of work equipment is not
practicable, justified and the safest option. The risk assessment must also detail the site
specific controls for the safe use of ladders.
20.3 Stepladders and Loose Ladders can only be used to work from if the following applies (as
defined by the Health and Safety Executive):
Document Authoriser: Craig McCallum Uncontrolled when printed or downloaded
Date of Issue: 11/07/2018 Page 23 of Version: 2.2 A Balfour Beatty UK Document
32
Work at Height
Procedure: HSF-PR-0063
Any site specific off-loading/on-loading restrictions are taken into account e.g. overhead
lines
Public interfaces are reviewed and additional control measures taken e.g. traffic
management controls and/or the use of plant and vehicle marshals, See People, Vehicle
and Plant Interface procedure (HSF-PR-0047)
21.2 Work at height on vehicles must be avoided whenever possible.
21.3 Where access to the delivery vehicle is unavoidable, the following hierarchy of controls must be
considered:
Vehicle-based edge protection systems, or alternatively, location-based edge protection
systems
Fall restraint systems (e.g. Safety harness and restraint lanyard)
Fall protection systems (airbags and/or mats)
21.4 Personnel must not be permitted to gain access to areas of a vehicle at height unless a risk
assessment has been carried out and a safe system of work is in place relative to the type and
size of edge protection afforded by the vehicle.
21.5 If a safe means of unloading or loading is not achievable, then the activity must not proceed and
the vehicle must be turned away until a safe method of unloading/loading is provided.
21.6 Three points of contact must be used at all times when accessing or climbing on/off a vehicle
using the designated access point(s).
21.7 See Minimum Controls for Loading and Unloading Areas (HSF-RM-0063e)
22. EXCAVATIONS AND VOIDS
22.1 When working in or near to any excavation, void (including chambers, man holes, basements
etc.), suitable barriers must be in place to prevent any person or materials from falling into the
opening. Barrier systems may include, but not be limited to:
Fabricated guard rail assemblies that connect to the sides of the trench box or clamped
onto piling sheet
Trench box extensions or trench sheets extending above ground level
Guard rails and toe boards adjacent to a Temporary Works approved excavation at one
metre distance from the excavation where site constraints allow
Physical barriers (such as double clipped Heras fencing, water filled barriers, pedestrian
barriers etc.) at one metre distance from the excavation, where site constraints allow
22.2 Refer to the Excavations Procedure (HSF-PR-0016) for further details.
23. MAN-RIDING BASKETS
23.1 Man-riding baskets must be used and operated in accordance with the requirements of the
Lifting Operations Procedure (HSF-PR-0039). All man-riding baskets and lifting equipment
used for providing safe access to a task must be subject to a thorough examination by an
authorised competent person every six months. If there is no valid certificate of thorough
examination it must be quarantined and taken out of use.
23.2 The man-riding basket must display the Safe Working Load (SWL) and the number of persons
that it can carry. The SWL must not be exceeded.
23.3 The Lift Supervisor or Slinger/Signaller must conduct a recorded pre-use inspection before each
shift (HSF-SF-0046IQ).
23.4 All users of man-riding baskets must use a fall restraint harness and fixed length lanyard
attached to a designated anchor point. The only exception to this being where working over or
adjacent to water that presents a risk of drowning. Automatic inflation life jackets must be worn
in such cases. Refer to Working Near Water procedure (HSF-PR-0065).
23.5 When using Rescue Man Riding Baskets, refer to Emergency Arrangements section of this
procedure below.
24. OVERHEAD LINE TOWER PLATFORMS
24.1 Prior to use a Platform Inspection Check sheet must be carried out, and recorded (OPS-SF-
5647a), for each work platform by a competent person, paying particular attention to the
condition of the welds, structural stability and condition.
24.2 Where work is carried out using 12 m, 16 m, 19 m and 21 m temporary working platforms a
safety line must be installed on the inside of the platform to allow safe attachment and
anchorage. The worker must be secured to the safety line at all times whilst inside the working
platform.
24.3 In the case of the 6 m platform an inertia reel must be used anchored to a safe point on the
tower’s cross-arm steelwork.
24.4 When working within permanent platforms attachment is not required.
24.5 The safe working load of the platform must never be exceeded.
24.6 The installation, use and removal of platforms must be in accordance with the current work
instruction unless authorised by the review team.
24.7 Platforms must be subject to a recorded thorough examination by a competent person every six
months. Any platform without a valid certificate of thorough examination must be removed from
use.
25. POWERED SPACER TROLLEYS
25.1 All Powered Spacer Trolleys must be subject to a thorough examination by a competent person
every six months. The Powered Spacer Trolley must display the safe working load and the
number of persons that it can carry.
25.2 Prior to use a documented pre-use inspection (OPS-SF-5646a) must be carried out, on each
spacer chair by a competent person, paying particular attention to the condition of the welds,
condition of the frame, operation of wheels and the brake system.
25.3 Safety nets must be utilised at all times as a secondary safety control to prevent objects from
falling.
25.4 All tools and equipment must be securely attached to the trolley at all times.
25.5 Whilst working in the powered spacer trolley a suitable lanyard secured to the chair handrail
must be used.
26. WOOD POLE PLATFORMS
26.1 Wood pole platforms used for providing safe access to a task must be subject to a visual pre-
use inspection and to a recorded thorough examination by a competent person every six
months. Any platform without a valid certificate of thorough examination must be removed from
use.
27. PERMANENT ATTACHMENT SYSTEMS
27.1 Tower Access Ropes / Rapid Rail / Latchway / Steel Temporary Rope Access System (STARS)
must be inspected for damage or signs of excessive wear. Inspections must be undertaken and
recorded after installation and before use.
27.2 Pre-installed systems (e.g. Rapid Rail and Latchway) will be thoroughly inspected before use.
Thereafter a competent person will carry-out a daily visual inspection before use.
27.3 Grab locks on to the rope must be checked by moving it slowly up the rope for approximately
500 mm then pulling the grab sharply downwards.
27.4 When on site the ropes for STARS and universal rope grabs must be thoroughly examined by a
competent person every three months and a record of that inspection kept throughout the life of
the equipment.
28. HOISTS
28.1 The Supervisor of Hoist Erection must be on location at all times during erection and must not
undertake the Thorough Examination for the equipment.
28.1.1 The Appointed Person for Hoist activities must have overall control of the selection, siting,
erection, use, inspection, maintenance and ultimate dismantling of the hoist and the expertise of
the Supplier must be utilised.
28.2 Ground Base and Tie Stability
28.2.1 All necessary load bearing data, including the tying arrangements must be received, appraised
and approved prior to commencing the erection of a hoist by a competent person in consultation
with the Temporary Works Function.
28.3 Rescue Procedure
28.3.1 The Site Lead must ensure the suppliers rescue procedure for erection and dismantling of the
structure is approved by a competent person.
28.4 Inspection and Maintenance
28.4.1 The Site Lead must ensure a competent person conducts daily and weekly inspections and
record details on the Lifting Equipment Accessories Register (HSF-TF-0039j)
28.4.2 The Supplier must undertake routine maintenance activities as specified in the Manufacturers
Instruction Manual and details must be recorded in the Lifting Equipment Accessories Register
(HSF-TF-0039j)
28.5 Statutory Examinations
28.5.1 A competent engineer must be appointed to conduct the statutory examination and test which
must be witnesses by an independent and impartial engineer. Timescales for examinations are:
28.5.2 Rope Hoist Six Month
Rack and Pinion Hoist Three Month
Electrical Installation Three Month
28.5.3 Examination certificates must be available for inspection.
28.5.4 A documented procedure must be in place for passenger hoists to rescue personnel whilst it is
in operation at its maximum passenger load and its maximum height or worse-case scenario.
This must be in place prior to commissioning the hoist for use and include emergency
communication or signalling arrangements.
28.5.5 Practice drills must be conducted at a frequency agreed by the Site Lead with any resulting
outcomes recorded and actioned.
28.6 Electrical Arrangements
28.6.1 Electrical installation, termination, testing and energising arrangements must comply with HSF-
PR-0068 Electrical Safe System of Work.
28.7 Hoist way, Gates, Interlocks and Notices
Document Authoriser: Craig McCallum Uncontrolled when printed or downloaded
Date of Issue: 11/07/2018 Page 27 of Version: 2.2 A Balfour Beatty UK Document
32
Work at Height
Procedure: HSF-PR-0063
28.7.1 The hoist platform must be fully enclosed to a height of at least 2m and where possible fully
enclose the hoist way.
28.7.2 2m high close-meshed gates must be provided at every landing point and these must be
equipped with electrical and mechanical interlocks.
28.7.3 An additional exclusion zone must be provided around the base to restrict plant interface and
exclude unauthorised personnel.
28.7.4 Highly visible notices must be displayed advising:
Safe working load
Gates to be closed
No passengers (unless a passenger hoist is provided)
Hoist to be operated by a competent Hoist Operator only
28.7.5 All hoists must be fitted with mechanical and electrical overrun devices to prevent travel beyond
safe limits.
28.7.6 To prevent unauthorised use the hoist controls must be fitted with an isolator.
28.8 Commissioning and Testing Arrangements
28.8.1 A testing regime must be in place and will be dependent upon the hoist location and
configuration. It must include a 25% overload test. A record of the test must be recorded on
HSF-TF-0039j Lifting Equipment Accessories Register.
28.9 Manufacturers Operating Instructions
28.9.1 The Manufacturers Operating Instructions for the hoist must be available on site and be held by
the Appointed Person or other delegate. The safe system of work and Lift Plan must incorporate
any relevant information contained in the Manufacturers Operating Instructions.
29. EMERGENCY PROCEDURE
29.1 The planning of work at height activities must identify suitable means of rescue for all stages of
the work, including the provision of suitable facilities and resources to rescue personnel from
their working area should they become ill, incapacitated or they are involved in any type of
incident.
29.2 A Rescue Plan must be documented by a competent person in liaison with the HSES Function.
The Rescue Plan must clearly identify the following:
Risk Assessments and Method Statements (Work Package Plan) including use of any
specialist rescue equipment
Casualty recovery procedure including aerial rescue procedures, if applicable
Risk of, and actions in the event of, suspension trauma
Staffing levels, allocation of roles and competencies
Means of raising the alarm and coordinating emergency services (if required)
Arrangements for securing and controlling the incident location and access routes
The inspection regime for rescue equipment and method for reporting defects
The frequency of practice drills and testing of the emergency procedure, along with
methods of implementing lessons learnt
Selection of appropriate PPE (i.e. relief step safety devices to alleviate the effect of
suspension syncope (trauma))
Document Authoriser: Craig McCallum Uncontrolled when printed or downloaded
Date of Issue: 11/07/2018 Page 28 of Version: 2.2 A Balfour Beatty UK Document
32
Work at Height
Procedure: HSF-PR-0063
The contact and specific location information for the emergency services, e.g. a grid
reference, a designated meeting point, the distance from the main road, ground
conditions for emergency vehicles including the type of access (suitable for car, four-
wheel drive, emergency service vehicles etc.), etc. In urban areas, the use of identifying
features, street names and postal codes are essential.
29.3 Where fall arrest harnesses are used, the Rescue Plan must address the avoidance and relief
of suspension trauma and in particular first aiders must be made aware of the proper treatment.
Paramedics arriving at the site must be made aware that the casualty may have suffered from
suspension trauma. Conscious casualties should be kept in a sitting position where possible.
29.4 Rescue Plans must be briefed to all relevant parties included in the working at height operation.
29.5 Where appropriate the emergency services must be consulted at the planning stages for work at
height, they should not be relied upon as the primary option for rescue and should only be used
as a last resort.
29.6 Appropriate training must be provided to sufficient personnel to ensure the planned rescue
techniques can be successfully implemented without delay. Refresher training will be provided
at appropriate intervals.
29.7 Rescue equipment must be used, maintained and inspected in accordance with the
manufacturers’ instructions and thoroughly examined after being used for a rescue or
evacuation (where applicable). Non-compliant equipment must not be used. It must be
immediately quarantined, replaced and returned to the supplier or destroyed with appropriate
records/reports maintained.
INPUTS
Reference Type Title
I Link British Standards
Document Authoriser: Craig McCallum Uncontrolled when printed or downloaded
Date of Issue: 11/07/2018 Page 30 of Version: 2.2 A Balfour Beatty UK Document
32
Work at Height
Procedure: HSF-PR-0063
S.I. 2005 No. 735 Legislation The Work at Height Regulations 2005
GHO/HSEN/SF/013- Group Standard Working at Height – 001
A01
INDG401 HSE Guidance Working at height – A brief guide
HSG33 HSE Guidance Health and safety in roof work
HSG150 HSE Guidance Health and safety in construction
TG20 NASC Technical
Guidance
HSE Guidance Work at Height toolkit
Website http://www.faset.org.uk
HSF-PR-0016 Procedure Excavations
HSF-PR-0047 Procedure People, Vehicles and Plant Interface
SBU specific Temporary Works Procedures:
ENG-PR-0008 UKCS
DES-PR-1102-GW Gas & Water
DES-PR-5965-PTD Power,
Transmission &
Distribution
OPS-PR-6623 Rail
OPS-PR-6624 Rail
HSES-PR-0004 Procedure Control of Derogation
HSF-PR-0035 Procedure Occupational Health Surveillance – Assessment
HSES-PR-0011 Procedure Setting People to Work Safely
HSF-PR-0039 Procedure Lifting Operations
HSF-PR-0046 Procedure Plant
HSF-PR-0065 Procedure Working Near Water
HSF-RM-0063a Reference Material Safe Use of Podium Steps
HSF-RM-0063b Reference Material Stepladders-Loose Ladders
HSF-RM-0063c Reference Material Safe Working from Mobile Towers Briefing
HSF-RM-0063d Reference Material High Rise Construction HSE Guide
HSF-RM-0063e Reference Material Minimum Controls for Loading and Unloading Areas
OUTPUTS
Reference No. Document Title Retention Responsibility
Period
HSES-TF-0011b Task Briefing Sheet 3 years Site Lead
HSF-SF-0009b Emergency Evacuation and Drill Response 3 Years Site Lead
Record
Document Authoriser: Craig McCallum Uncontrolled when printed or downloaded
Date of Issue: 11/07/2018 Page 31 of Version: 2.2 A Balfour Beatty UK Document
32
Work at Height
Procedure: HSF-PR-0063
OUTPUTS
Reference No. Document Title Retention Responsibility
Period
HSF-CL-0046al Plant Specification Checklist – MEWP – 3 Years Site Lead
Trailer Mount
HSF-CL-0046am Plant Specification Checklist – MEWP – 3 Years Site Lead
Scissor Lift
HSF-CL-0046an Plant Specification Checklist – MEWP – 3 Years Site Lead
Boom Lift
HSF-CL-0046ao Plant Specification Checklist – MEWP – Push 3 Years Site Lead
Around Vertical (PAV)
HSF-CL-0046ap Plant Specification Checklist – MEWP – 3 Years Site Lead
Vehicle Mounted
HSF-CL-0046cq Plant Specification Checklist – Mast Climber 3 Years Site Lead
HSF-CL-0046cy Plant Specification Checklist – Lanyard and 3 Years Site Lead
Harness
HSF-SF-0048c Inspection of Safety Harness/Lanyard/Inertia 3 Years Site Lead
Reels (Weekly and Thorough)
HSF-SF-0063a Fragile Roof-High Risk Roof Working Permit 3 Years Site Lead
HSF-SF-0063b MCWP Pre Use-Daily Weekly Checklist 3 Years Site Lead
HSF-SF-0046AL MEWP (All) Pre-Use-Daily-Weekly Check 3 Years Site Lead
HSF-SF-0063d MEWP Recovery Checklist 3 Years Site Lead
HSF-SF-0063e Scaffold Handover Certificate 3 Years Site Lead
HSF-SF-0063f Scaffold Inspection Checklist 3 Years Site Lead
HSF-TF-0039j Lifting Equipment Accessories Register 3 Years Site Lead
HSF-SF-0046IQ Man Basket Pre-Use-Daily-Weekly Check 3 Years Site Lead
HSF-SF-0063h Scaffold, Working Platform and Mobile Tower 3 Years Site Lead
Inspections
HSF-SF-0063i Weekly Podium Inspection Report 3 Years Site Lead
HSF-SF-0063j Permit to Work on Steps or Loose Ladders 3 Years Site Lead
HSF-SF-0063k Weekly Inspection of Steps/Loose Ladders 3 Years Site Lead
OPS-SF-5647a Platform Inspection Check Sheet 3 Years Site Lead
OPS-SF-5646a Powered Spacer Trolley Visual Inspection 3 Years Site Lead
HSF-SF-0046BI Ladder Pre-Use-Daily-Weekly Check 3 Years Site Lead