(2021-12-11) Method Satement-Concrete Pouring Sequence Walls
(2021-12-11) Method Satement-Concrete Pouring Sequence Walls
(2021-12-11) Method Satement-Concrete Pouring Sequence Walls
Ministry of Health and Indigenous System S&P Enviromec International (Pvt) Ltd
Medical Services (MOH&IMS),
Democratic Socialist Republic
of Sri Lanka
Submittal Transmittal
Project: Design, Construction, Commissioning, Start-up and Initial Operation & Maintenance (3
Months) of Sewerage Treatment Plant (STP) for New Maternity Hospital, Karapitiya, Galle
Consultant: GITEC Consult GmbH Engineer: GITEC Consult GmbH
To Engineer/ Consultant
METHOD STATEMENT –
CONCRETING STAGES &
SEQUENCE
Project Manager:
Uditha Wijesena
REF: ENV/KMH/STP/MS-03
1. PURPOSE
The purpose of this Method Statement is to create awareness of common tasks involved in stages of
construction of the STP sludge tank and the concrete pouring of the construction stages and ensure the
execution is in full compliance with Project Specifications & Drawings complying with relevant EHS Standards
and norms. This Method Statement shall be communicated and be understood by all personnel associated
with the task before commencing the activity.
2. SCOPE OF WORKS
This document enumerates the planned activities and execution of concrete pouring in the STP sludge tanks. The
concrete pouring procedure shall be in accordance with this Method Statement. Supply, placing finishing and curing for
all applications in line with project requirements
3. REFERENCES
3.1. Contract documents
1) Specification for civil engineering works
2) RFI & Checklists for concrete works
3) Contract Drawings – ST-01. ST-01A, ST – 02, ST -03, ST-04, ST-05, ST-06.
4) Architectural Drawings – Execution Issue
Therefore, the number of Transit Mixer Trucks to have a continuous supply of concrete at the pouring area shall be
4.
Water curing shall be continued until the compressive strength has reached 70 % of the specified strength, but will
not be less than 7 days after placement. Casting dates will be noted down and 7 days curing period will be assured
by construction supervisors and continuously monitored by the Engineers.
1) The Engineer shall be informed for inspection through an RFI raised 24 hrs in advance before executing the
concreting.
2) Concrete Slump and the Casting of Test Cubes will be done by the concrete supplier and relevant labelling and
curing will be undertaken by the contractor.
REF: ENV/KMH/STP/MS-03
All workers will be inducted on the importance of wearing Personal Protective Equipment (PPE)
during work following the safety procedures. All staff and labour will be required to adhere to the
social distancing and wear face masks as stipulated in the Health Guideline issued to construction
sites.