PROJECT MANAGEMENT:

CPM/PERT
PROJECT MANAGEMENT: CPM/ PERT
E

F G M
B

A D H L

C N
I

J K
E 19 89
70 19 89
S 0 0

B 2 16 F 19 33 G 33 34 M 89 90
14 2 16 14 74 88 1 88 89 1 89 90
S 0 0 S 55 55 S 55 55 S 0 0

A 0 2 D 16 19 H 19 20 L 40 41
START

2 0 2 3 16 19 1 89 90 1 88 89
S 0 0 S 0 0 S 70 70 S 48 48
N 90 91
C 2 16 I 19 26
1 90 91
14 2 16 7 84 91
S 0 0
S 0 0 S 65 65
O 91 92

FINISH
J 19 26 K 26 40
1 91 92
7 67 74 14 74 88
S 0 0
S 48 48 S 48 48

Forward pass
Backward pass
Table Activity Schedule for Candlelight Choir Service Project
Earliest Start Latest Start Earliest Finish Latest Finish
Activity Float (LS –ES) Critical Path
(ES) (LS) (EF) (LF)
A 0 0 2 2 0 Yes
B 2 2 16 16 0 Yes
C 2 2 16 16 0 Yes
D 16 16 19 19 0 Yes
E 19 19 89 89 0 Yes
F 19 74 33 88 55
G 33 88 34 89 55
H 19 89 20 90 70
I 19 84 26 91 65
J 19 67 26 74 48
K 26 74 40 88 48
L 40 88 41 89 48
M 89 89 90 90 0 Yes
N 90 90 91 91 0 Yes
O 91 91 92 92 0 Yes
Project completion time = 92 days

Critical activities are A, B, C, D, E, M, N and O

Critical path:
A – B – D – E –M – N – O
A–C–D–E–M–N–O