Method Statement For Cement Board Dry Wall Partitions
Method Statement For Cement Board Dry Wall Partitions
Method Statement For Cement Board Dry Wall Partitions
, Ltd
No, (8) Room 6th Floor, Ayoekone st, Ayoekone Quarter, Tamwe Township,
Yangon Myanmar. Ph:95-9-5088487,95-9-785088487
E-mail: [email protected]
E-mail: [email protected]
..............................................................................................................................................................................
...
Contract Drawings.
Program of Work.
Approved project Quality & Safety plan and procedures.
12 mm Cement Board.
Metal Studs.
Wedge anchor
Joint Compound.
For example, TERRACO handy coat material.
PROCEDURES.
Preparation/Planning
Prior to works commencing, the Site Engineer shall ensure that the following activities
have been completed and signed-off by the Consultant:
Drawing must be approved for construction by the Consultant.
Materials Submittals (Cement board, Framing Stud, Track, screws, and joint filler material
are approved by Consultant.
The Site Engineer shall ensure that the necessary Statutory Authorities approvals have
been received WIR for completed concrete works should be approved.
Cement Partition and lining materials (Cement boards, insulation's (IF REQUIRED) and
Framing components), with delivery note to be delivered to the site accordingly and
Stored, protected against from any damage.
Execution.
The team will conduct a survey for specific layout marking as per Site Personnel.
The Team will carry out layout marking as per approved drawing in accord with the
schedule of work.
The layout would be mark with any marking line on the floor and subject for correct layout.
Once the setting out is completed, the end points will be marked with permanent markers.
The level and line for setting out would be taken from the approved Drawing from the
Contractor at site.
All layout and markings will be checked before proceeding with the installation.
Check for right angle and alignment of the framing / first fix
Fix the first and last vertical stud only for each expected wall partition and in the same time
fix the top track to check the alignment.
The stud will be installed between the top and bottom@600 mm Center to center tracks
taking into consideration the height of the partition and joints of studs to overlap 600 mm in
both directions.
The framework will inspect by Site In-charge for any discrepancy, to rectify, if any, before
proceeding the work.
Second will put the insulation inside the partition structure making sure of dimensions and
keeping the insulation tight inside the structure of the partition.
After the cutting and fixing of both side Cement board, it will start the Second layer of fire
rated gypsum board and then start the joint treatment with fiber tape and assuring that joint
level is not exceeding the board level.
Boards will be installed along the stud direction with plasterboard screw or using the
required accessories and metal angle as per approved materials and drawing.
The substrate shall be free from dust, oil, grease, and wax contaminants etc.
The substrate shall be repaired if the surface has imperfections. Appropriate repair
products shall be used.
Any MEP embedded items (Switches, power supplies etc.) shall be fully sealed and signed-
off.
First coat of joint filler should be applied with Tools of Sufficient width to extend a minimum
of 50 mm beyond both sides of the center of the Joint.
Joint tape to be embedded into the joint Filler to reinforce the joint between the Cement
Board.
Second Coat joint filler will be applied over the dried first Coat.
Once the Second Coat is dried, surface should be sanded and smoothed.
One coat of Primer will be applied over the board joints.
Another One coat of Primer applied over the entire Partition Area.