Casing Design Manual
Casing Design Manual
Casing Design Manual
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
INDEX
1. INTRODUCTION .............................................................................................................. 6
1.1 IMPLEMENTATION .............................................................................................. 6
1.2 UPDATING, AMENDMENT, CONTROL& DEROGATION.................................... 6
1.3 FIRST DEFINITIONS ............................................................................................ 7
1.4 PURPOSE OF CASING ........................................................................................ 7
1.5 GENERAL APPROACH TO CASING DESIGN .................................................... 8
8.5 BENDING.............................................................................................................. 66
8.5.1 GENERAL............................................................................................. 66
8.5.2 DETERMINATION OF BENDING EFFECT........................................... 66
8.5.3 COMPANY DESIGN PROCEDURE ...................................................... 68
8.5.4 EXAMPLE BENDING CALCULATION ................................................. 69
8.6 CASING WEAR .................................................................................................... 71
8.6.1 GENERAL............................................................................................. 71
8.6.2 VOLUMETRIC WEAR RATE ................................................................ 72
8.6.3 FACTORS AFFECTING CASING WEAR (EXAMPLE) ......................... 74
8.6.4 WEAR FACTORS ................................................................................. 78
8.6.5 DETECTION OF CASING WEAR ......................................................... 83
8.6.6 CASING WEAR REDUCTION............................................................... 84
8.6.7 WEAR ALLOWANCE IN CASING DESIGN.......................................... 84
8.6.8 COMPANY DESIGN PROCEDURE ...................................................... 85
8.7 SALT SECTIONS.................................................................................................. 86
8.7.1 GENERAL............................................................................................. 86
8.7.2 EXTERNAL LOADING DUE TO SALT FLOW ...................................... 86
8.7.2.1 UNIFORM EXTERNAL LOADS........................................... 87
8.7.2.2 ASYMMETRICAL FORMATION LOADS ............................. 88
8.7.3 COMPANY DESIGN PROCEDURE ...................................................... 91
9. CORROSION.................................................................................................................... 93
9.1 GENERAL............................................................................................................. 93
9.1.1 EXPLORATION AND APPRAISAL WELLS ......................................... 93
9.1.2 DEVELOPMENT WELLS...................................................................... 93
9.1.3 CONTRIBUTING FACTORS TO CORROSION .................................... 94
9.2 FORMS OF CORROSION..................................................................................... 95
9.2.1 SULPHIDE STRESS CRACKING (SSC)............................................... 95
9.2.2 CORROSION CAUSED BY CO2 AND CL- ............................................ 102
9.2.3 CORROSION CAUSED BY H2S, CO2 AND CL- .................................... 105
9.3 CORROSION CONTROL MEASURES................................................................. 105
9.4 CORROSION INHIBITORS................................................................................... 106
9.5 CORROSION RESISTANCE OF STAINLESS STEELS ....................................... 106
9.5.1 MARTENSITIC STAINLESS STEELS .................................................. 107
9.5.2 FERRITIC STAINLESS STEELS .......................................................... 107
9.5.3 AUSTENITIC STAINLESS STEELS ..................................................... 107
9.5.4 PRECIPITATION HARDENING STAINLESS STEELS ......................... 108
9.5.5 DUPLEX STAINLESS STEEL............................................................... 110
9.6 CASING FOR SOUR SERVICE ............................................................................ 111
9.7 ORDERING SPECIFICATIONS ............................................................................ 112
9.8 COMPANY DESIGN PROCEDURE ...................................................................... 112
9.8.1 CO2 CORROSION................................................................................. 112
9.8.2 H2S CORROSION ................................................................................. 113
1. INTRODUCTION
The present Casing Design Manual is aimed to define the Company’s rules, policies and
practices that shall be applicable in the process of casing design.
The purpose of this Manual is to provide Company’s technicians involved in the well
planning process worldwide, with the minimum set of information and guidelines needed to
define a casing profile (including the selection of proper shoe setting depth, tubular size
and material) that achieves the following objectives:
1) Guarantee the minimum required level of safety throughout the entire life cycle of the
well (from drilling to productive life and to the final abandonment).
2) Reduce well cost as much as possible, provided that safety is not compromised.
3) Take in proper consideration constrains arising from specific local conditions, logistic
and operational issues.
It shall be remarked that most of the rules and practices reported in this manual are based
on assumptions that are part of Company’s policy.
Indeed, the definition of the working conditions that a well can face during its life involves a
high level of uncertainties. For this reason and with regard to the purposes of casing
design, the worst possible conditions (i.e. blowouts, major equipment failures, drilling
problems etc.) and the related safety factors required are assumed. Different Companies
may consider different assumptions that could theoretically lead to different designs for the
same well, even though in most cases the final design will be basically the same.
Although casing design process could be carried out without any particular tool, today’s
general practice is to use the support of specific software. Several commercial software's
are available, all of them including many options in order to fit with different companies
design rules and procedures. Corporate software tools have been defined by Company,
and where needed, specific indications about which options to select in these tools are
reported in order to guarantee that Company’s rules and policies are respected.
1.1 IMPLEMENTATION
The guideline and policies specified herein will be applicable to all Company drilling
engineering activities.
All engineers engaged in Casing Design activities are expected to make themselves
familiar with the contents of this manual and be responsible for compliance to its policies
and procedures.
Derogations from the rules and policies reported in the manual are possible if required by
local particular conditions provided that they are duly justified and approved by the local
Company Well Operations Manager after the local Company Manager and the Corporate
Drilling & Production Optimisation Services Department in Eni E&P Division Head Office
have been advised in writing.
The Corporate Drilling & Production Optimisation Services Standards Department will
consider any feedback (also gained from the return of completed ‘Feedback and Reporting
Forms’ from well operations) and approved derogations for future amendments and
improvements of the Corporate manual, when the updating of the document will be
advisable.
11) Confining produced fluid to the wellbore and providing a flow path to surface.
12) Providing internal pressure containment when the tubing system leaks or fails.
13) Preventing wellbore fluids from contaminating production.
14) Providing protection for completion equipment.
15) Providing access to producing formations for remedial operations.
16) Providing cement integrity across producing formations.
As it will be detailed in the next sections of this manual, different types of casing are
characterised by their specific purpose, among the ones listed here above.
The latter verification is carried out by calculating the Design Factor, defined as the ratio
between the nominal resistance of the pipe, and the load: minimum acceptable values for
Design Factor are specified by Company for each type of casing and/or loading condition.
To carry out this process it is necessary to have as much information as possible on the
well that we are planning (pressure and temperature gradients, formation fluids
characteristics, formation strength and behaviour during drilling, problems that are likely to
be encountered, etc.).
The amount of information strictly depends on the experience gained in other wells of the
same or in similar area: it is clear that cases of exploration or development wells are
completely different, and then also approach of casing design will reflect this difference.
Basic verifications that are always performed include the verification of casing mechanical
resistance in different situations, which induce the following loads:
• Burst
• Collapse
• Tension.
The typical situations (load cases) are defined per each type of casing and well, and aim
to define the most demanding conditions that are likely to be encountered during the life of
the well.
Selected casing shall guarantee its resistance in these three different cases.
Besides the basic verifications (burst, collapse and axial loads or tension), other factors
that can induce loads and stresses or affect casing resistance may be considered, such as
changing of internal temperature or pressure due to production or stimulation, corrosion by
formation fluids or acid jobs, wear by mechanical friction, and others.
The evaluation of these loads may lead to a more sophisticated design process that shall
be defined according to the actual well situation.
S P E O IDENTIFICATION CODE PAG 9 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
Refer to the following sections for descriptions of the casings listed above.
S P E O IDENTIFICATION CODE PAG 10 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
The conductor casings are usually driven completely to depth or, alternatively, run into a
predrilled or jetted hole and cemented. If they are driven, they must be designed to
withstand hammering loads.
Conductor casings, in offshore drilling with subsea BOPs, are usually either jetted into
place or cemented in a predrilled hole. They support all future wellhead installations for
both the drilling and production phases. They directly carry both the axial and bending
loads imposed by the wellhead, but are rigidly connected to the next casing with
centralisers and cement in order to dissipate loading and minimise resulting stresses.
The surface casing string is cemented to surface or seabed and is the first casing on
which BOPs can be mounted. It is important to appreciate that the amount of protection
provided against internal pressure will only be as strong as the formation strength at the
casing shoe; hence it may be necessary to vent any influx taken through the surface
string, rather than attempt containment.
The surface string usually supports the wellhead and subsequent casing strings.
In offshore wells with surface wellhead, the annulus between the conductor and surface
string is often left uncemented above the mudline to minimise load transfer and bending
stresses in the surface string. In these cases, surface casing must be centralised to
prevent or limit the buckling.
S P E O IDENTIFICATION CODE PAG 11 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
The designer should plan to combine many of these objectives when selecting a single
casing point. A liner may be used instead of a full intermediate casing and difficult wells
may actually contain several intermediate casings and/or liners. Caution should be taken
when using liners as it is necessary to ensure the higher casing is designed for the
pressures at lower depths.
The cement should cover all hydrocarbon zones and any salt or other creeping evaporites.
Zones containing highly corrosive formation waters are also often cemented off, especially
where there may be aquifer movement which replenishes the corrosive elements around
the wellbore.
Longer cement columns are sometimes required to prevent buckling of the casing during
deeper drilling.
In most cases, the production casing will serve to isolate the productive intervals, to
facilitate proper reservoir maintenance and/or prevent the influx of undesired fluids.
In other cases, accumulation conditions are such that the well can be cased with an open
hole section below the casing for an open hole completion.
The size of the production casing should be selected to meet with the desired method of
completion and production.
On production wells the Casing Design must ensure the optimum completion design.
This usually impacts on the production casing design with regard to:
• Well flow potential, i.e. tubing size.
• The possibility of a multiple tubing string completion.
• The space required for downhole equipment e.g. safety valves, artificial lift
equipment etc.
• The geometry required for efficient through-tubing well intervention operations.
• Potential well servicing and recompletion requirements.
• Adequate annular clearances to permit circulation at reasonable rate and
pressures.
It is also possible that the casing itself could be used as a conduit for maximising well
deliverability (casing flow), for minimising the pressure losses during frac jobs, for
chemical injection or for lift gas.
Consideration must be given to production operations which will affect the temperature of
the production casing and impose additional thermal stresses. Annulus thermal expansion
can cause production casing collapse when it is cemented up into the intermediate casing.
The loads to which a production casing is subjected are, therefore, quite different from
those imposed during drilling.
It is very important that the selection of the steel grade and connections for the production
string are made correctly.
Special considerations are required where the production casing will be drilled through
and may therefore suffer some damage e.g.: open hole completions, open hole gravel
packs, liner completions, deep zone appraisal.
In a liner completion, both the liner and casing form the production string and must be
designed accordingly.
2.2.5 LINER
A liner is a string of pipe which is installed but does not extend all the way to surface. It is
hung a short distance above the previous casing shoe and is usually cemented over its
entire length to ensure it seals within the previous casing string.
Drilling liners may be installed to:
• Increase shoe strength
• Meet with rig tensional load limitations
• Minimize the length of reduced diameter and the possible adverse effects on
drilling hydraulics.
S P E O IDENTIFICATION CODE PAG 13 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
Either type of liner may subsequently be tied-back to surface with a string of pipe stabbed
into a liner hanger Polished Bore Receptacle (PBR).
The selection of casing setting depths is one of the most critical issues in the well design
process and is based on:
• Total depth of well
• Pore pressures
• Fracture gradients
• The probability of shallow gas pockets
• Problem zones
• Depth of potential prospects
• Time limits on open hole drilling
• Casing programme compatibility with existing wellhead systems
• Casing programme compatibility with planned completion programme
(production well)
• Casing availability (grade and dimensions)
• Economy, i.e. time consumption to drill the hole, run casing and cost of
equipment.
When planning, all available information should be carefully documented and considered
to obtain knowledge of the various uncertainties.
Information is obtained from:
• Evaluation of the seismic and geological background documentation used as
the decision for drilling the well.
• Drilling data from offset wells in the area. (Company wells or scouting
information).
The key factor to satisfactory picking of casing seats is the assessment of pore pressure
and fracture pressures throughout the well.
As the pore pressures in a formation being drilled approach the fracture pressure at the
last casing seat then installation of a further string of casing is necessary.
Figure 3-1 shows a typical example of casing seat selections.
S P E O IDENTIFICATION CODE PAG 15 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
This example does not include any safety or trip margins, which would, in practice, be
taken into account.
To ensure the integrity of the intermediate casing seat, leak-off tests are necessary and
must be specified in the Drilling Programme.
Sometimes it is necessary to alter the setting depth of the intermediate casing during
drilling under certain circumstances such as when:
• Hole problems prohibit further drilling.
• Pore pressure changes occur substantially shallower or deeper than originally
calculated or estimated. For this reason the Geological Drilling Programme
should state the pore pressure requirement at which casing should be set
when setting casing into a transition zone.
3.4 DRILLING LINER
The setting of a drilling liner is often an economically attractive decision in deep wells as
opposed to setting a full string. Such a decision must be carefully considered as the
intermediate string must be designed for burst as if it were set to the depth of the liner.
If drilling is to be continued below the drilling liner then burst requirements for the
intermediate string are further increased which increases the cost of the intermediate
string. Also, there is the possibility of continuing wear of the intermediate string that must
also be evaluated.
S P E O IDENTIFICATION CODE PAG 17 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
If a production liner is planned, then either the production liner or the drilling liner should
be tied back to the surface as a production casing.
If the drilling liner is to be tied-back, it is usually better to do so before drilling the hole for
the production liner. By doing this, the intermediate casing can be designed for a lower
burst requirement, resulting in considerable cost savings. Also, any wear to the
intermediate string is spanned prior to drilling the producing interval.
If increasing mud weight will be required, while drilling hole for the drilling liner, then leak-
off tests must be conducted and specified in the casing programme for the intermediate
casing shoe within the Geological Drilling Programme.
Insufficient fracture gradient at the shoe may limit the depth of the drilling liner.
For a normal exploration well, it is recommended that an 81/2ins hole be the smallest
diameter planned because of drilling and evaluation difficulties encountered with 6ins.
A 6ins hole size should only be planned as a contingency.
The choice of casing and bit sizes available to engineers is shown in Figure 3-2.
The chart in Figure 3-2 can be used to select the casing bit sizes required to fulfil many
drilling programme options.
To use the chart:
1) Determine the casing or liner size for the last size pipe to be installed.
2) Enter the chart at that point.
3) The flow of the chart then indicates hole sizes that may be required to set that size
pipe (i.e., 5” Liner inside 6” or 61/2” hole).
Solid lines indicate commonly used bits for that size pipe and can be considered
to have adequate clearance to run and cement the casing or liner (i.e., 51/2” casing
inside 77/8” hole).
The broken lines indicate less common optional hole sizes used (i.e., 5” inside
61/8” hole, etc.).
The selection of one of these broken paths requires special attention be given to
the connection, mud weight, cementing and doglegs.
Large connection ODs, thick mud cake build-up, problem cementing areas (high
water loss, lost returns, etc.) and doglegs all aggravate the attempt to run casing
and liners in low clearance situations.
Once the hole size has been selected, a casing large enough to allow passage of
a bit to make that hole can be selected. The solid lines are commonly required
casing sizes, encompassing most weights (i.e., 61/2” bit inside 75/8” casing).
The broken lines indicate casing sizes where only the lighter weights can be used
(i.e. 61/8” inside 7” casing).
This selection process is repeated until the anticipated number of casing sizes has
been reached.
Note that Figure 3-2 is reported in order to help the designer to select field proven
combination of casings and hole diameters, and shall not be intended as
exhaustive of all possible well profiles. Indeed, special requirements or the
availability of particular equipment may dictate or make possible the adoption of
profiles not included in Figure 3-2
Besides, some drilling programmes can require special tools and operations to
obtain the wellbore size for the casing to be installed. An underreamer is a drilling
tool, used to enlarge section of hole below a restriction (situations where
equipment, such as BOP or wellhead size restrictions, limits the tool entry size).
Figure 3-3 shows the standard casing programme and Figure 3-4 the possible
alternative. Further standard casing and hole sizes information is shown in Table
3-a.
S P E O IDENTIFICATION CODE PAG 20 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
Note: As general rule, the minimum clearance between the outer string ID
(drift diameter) and inner coupling OD should be 0.400”, while the
clearance between the hole wall and the coupling OD should be at least
2” on diameter.
There is a great range of casings available from suppliers from plain carbon steel for
everyday mild service through exotic duplex steels for extremely sour service conditions.
The casings available can be classified under two specifications, API and non-API.
Casing specifications, including API and its history, are described and discussed in
sections 4.1 and 4.2.
Manufacturers have also developed materials out of API specifications that meet the
demand for higher class of casings able to cope with extreme conditions beyond the range
of application of API casings. The areas of use for this casing are also discussed in
section 4.3 below.
The properties of steel used in the manufacture of casing are fundamentally important and
should be fully understood by design engineers, and to this end these properties are
described in section 5.
An example of API table showing the parameters listed above is given in Table 4-b.
Reference should always be made to current API specification 5C2 for casing lists and
performances.
In this case, the compound can be extruded exposing the threads to corrosive fluids,
which in turn reduces the strength of the connection.
For this reason, the connections must have metal-to-metal seals therefore, premium
connections (non API) are mandatory. On other side if it is necessary the use of D.V.
collar and liner slave/stem characterized by elastomeric seals, they are allowed only if
their working pressure is greater then casing/liner burst and collapse resistance.
Application
Domain Material SM’ Designation Notes
(Refer to Figure 4‑1)
API J 55 SM 95G
N 80 SM 125G
Mild Environment Domain “A”
P 110
(Q 125)
Cr or Cr-Mo Steel
Sulphide Stress Corrosion
Cracking (medium pressure and Domain “B” API L 80 SM 80S
temperature) C 90 SM 90S
T 95 SM 95S
1Cr 0.5Mo Steel SM 85SS Higher yield strength
Sulphide Stress Corrosion for sour service
Modified AISI 4130 SM 90SS
Cracking (high pressure and Domain “C”
temperature) SM C100
SM C110
9Cr 1Mo Steel SM 9CR 75 Quenched and
Wet CO2 Corrosion Domain “D” SM 9CR 80 tempered
SM 9CR 95
13Cr Steel SM 13CR 75 Quenched and
Modified AISI 420 SM 13CR 80 tempered
SM 13CR 95
22Cr 5Ni 3Mo Steel SM 22CR 65* Duplex phase Stainless
steels
SM 22CR 110**
Wet CO2 with a little H2S SM 22CR 125** * Solution Treated
Domain “E”
Corrosion 25Cr 6Ni 3Mo Steel SM 25CR 75*
SM 25CR 110** ** Cold drawn
SM 25CR 125**
SM 25CR 140**
25Cr 35Ni 3Mo Steel SM 2535 110 As cold drawn
SM 2535 125
22Cr 42Ni 3Mo Steel SM 2242 110
Wet CO2 with H2S Corrosion Domain “F”
SM 2242 125
20Cr 35Ni 5Mo Steel SM 2035 110
SM 2035 125
25Cr 50Ni 6Mo Steel SM 2550 110 As cold drawn
SM 2550 125
SM 2550 140
20Cr 58Ni 13Mo Steel SM 2060 110***
SM 2060 125***
Most Corrosive Environment Domain “G” SM 2060 140*** *** Environment with
free Sulphur
16Cr 54Ni 16Mo Steel SM 2060 155***
SM C276 110***
SM C276 125***
SM C276 140***
5.1 GENERAL
Failure of a material or of a structural part may occur by fracture (e.g. the shattering of
glass), yield, wear, corrosion, and other causes. These failures are failures of the material.
Buckling may cause failure of the part without any failure of the material.
As load is applied, deformation takes place before any final fracture occurs. With all solid
materials, some deformation may be sustained without permanent deformation, i.e. the
material behaves elastically.
Beyond the elastic limit, the elastic deformation is accompanied by varying amounts of
plastic, or permanent, deformation. If a material sustains large amounts of plastic
deformation before final fracture, it is classed as ductile material, and if fracture occurs
with little or no plastic deformation, the material is classed as brittle.
Similar arbitrary rules are followed with regard to the elastic limit in commercial practice.
Instead of determining the stress up to which there is no permanent set, as required by
definition, it is customary to designate the end of the straight portion of the curve (by
definition the proportional limit) as the elastic limit. Careful practice qualifies this by
designating it the ‘proportional elastic limit’.
As extension continues beyond yielding, the material becomes stronger causing a rise of
the curve, but at the same time the cross-sectional area of the specimen becomes less as
it is drawn out. This loss of area weakens the specimen so that the curve reaches a
maximum and then falls off until final fracture occurs. The stress at the maximum point is
called the tensile strength (TS) or the ultimate strength of the material and is its most often
quoted property.
The mechanical and chemical properties of casing, tubing and drill pipe are laid down in
API specifications 5CT , 5C2 and ISO 11960.
Depending on the type or grade, minimum requirements are laid down for the mechanical
properties, and in the case of the yield point even maximum requirements (except for H
40).
The denominations of the different grades are based on the minimum yield strength, e.g.:
In the design of casing and tubing strings the minimum yield strength of the steel is taken
as the basis of all strength calculations.
As far as chemical properties are concerned, in API 5CT / ISO 11960 only the maximum
phosphorus and sulphur contents are specified, the quality and the quantities of other
alloying elements are left to the manufacturer.
API specification 5CT (ISO 11960) ‘Restricted yield strength casing and tubing’ however,
specifies the complete chemical requirements for grades C 75, C 95 and L 80.
See the following tables for process of manufacturing, heat treatments, chemical
composition and mechanical properties of API tubulars.
S P E O IDENTIFICATION CODE PAG 31 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
Tempering
Temperature Min.
Group Grade Type Process of Heat o o
F C
Manufacture Treatment
H 40 - S or EW None - -
J 55 - S or EW None - -
Note 1
1 K 55 - S or EW None - -
Note 1
N 80 - S or EW None - -
(Casing) Note 1
N 80 (Tubing) - S or EW Note 1 - -
*** Special requirements unique to electric welded Q 125 casing are specified in SR11. When
welded Q 125 casing is furnished, the provisions of SR11 automatically in effect.
S = Seamless pipe
EW = Electric welded Pipe
Phos-
Group Grade T ype Carbon Manganese Molybdenum Chrom ium Nickel Copper Sulphur Silicon
phorous
m in m a x. m in m a x. m in m a x. m in m a x. m a x. m ax. m a x. m ax. m a x.
1 H - 40 ... ... ... ... ... ... ... ... ... ... ... 0.040 0.060 ...
J - 55 ... ... ... ... ... ... ... ... ... ... ... 0.040 0.060 ...
K - 55 ... ... ... ... ... ... ... ... ... ... ... 0.040 0.060 ...
N - 80 ... ... ... ... ... ... ... ... ... ... ... 0.040 0.060 ...
2 C - 75 1 ... 0.50 ... 1.90 0.15 0.40 *** *** *** *** 0.040 0.060 0.45
C - 75 2 ... 0.43 ... 1.50 ... ... ... ... ... ... 0.040 0.060 0.45
C - 75 3 0.38 0.48 0.75 1.00 0.15 0.25 0.80 1.10 ... ... 0.040 0.040 ...
C - 75 9Cr ... 0.15 0.30 0.60 0.90 1.10 8.0 10.0 ... ... 0.020 0.010 1.0
C - 75 13Cr 0.15 0.22 0.25 1.00 ... ... 12.0 14.0 0.5 0.25 0.020 0.010 1.0
L - 80 1 ... 0.43* ... 1.90 ... ... ... ... 0.25 0.35 0.040 0.060 0.45
L - 80 9Cr ... 0.15 0.30 0.60 0.90 1.10 8.0 10.0 0.5 0.25 0.020 0.010 1.0
L - 80 13Cr 0.15 0.22 0.25 1.00 ... ... 12.0 14.0 0.5 0.25 0.020 0.010 1.0
C90 1 ... 0.35 ... 1.00 ... 0.75 ... 1.20 0.99 ... 0.030 0.010 ...
C90 2 ... 0.50 ... 1.90 ... NL ... NL 0.99 ... 0.030 0.010 ...
C95 ... ... 0.45* ... 1.90 ... ... ... ... ... ... 0.040 0.060 0.45
3 P -105 ... ... ... ... ... ... ... ... ... ... ... 0.040 0.060 ...
P - 110 ... ... ... ... ... ... ... ... ... ... ... 0.040 0.060 ...
4 Q -125 1 ... 0.35 ... 1.00 ... .75 ... 1.20 0.99 ... 0.020 0.010 ...
Q -125 2 ... 0.35 ... 1.00 ... NL ... NL 0.99 ... 0.020 0.020 ...
Q -125 3 ... 0.50 ... 1.90 ... NL ... NL 0.99 ... 0.030 0.010 ...
Q -125 4 ... 0.50 ... 1.90 ... NL ... NL 0.99 ... 0.030 0.020 ...
Note:
*** For Grade C - 75, Type 1, Chromium, Nickel and Copper combined shall not exceed 0.50%.
* The Carbon contents for L - 80 may be increased to 0.50% max. if the product is oil quenched.
* The Carbon contents for C - 95 may be increased to 0.55% max. if the product is oil quenched.
NL No Limit. Elements shown must be reported in product analysis.
Table 5-b - Chemical Composition of API Tubulars
S P E O IDENTIFICATION CODE PAG 33 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
4 Q -125 125,000 860 150,000 1035 135,000 930 ... ... 0.500 or less 3.0
Q -125 125,000 860 150,000 1035 135,000 930 ... ... 0.501 to 0.749 4.0
Q -125 125,000 860 150,000 1035 135,000 930 ... ... 0.750 and above 5.0
* In case of dispute, laboratory Rockwell C hardness tests shall be used as the referee method.
Range 1 2 3
Casing And Liners
** Total range length include 16-25 25-24 24-48
* Range Length for 95% or more of carload
Permissible Variation, max. 6 5 6
Permissible length, min 18 28 36
Tubing
** Total range length include 20-24 28-32 -
* Range Length for 100% or more of carload
Permissible Variation, max. 2 2 -
Permissible length, min 20 28 -
Pup Joint
*** Lengths 2,3,4,6,8,10 and 12ft
Tolerance ±3ins
* Carload tolerance shall not apply to orders of less than a carload. For any carload
of pipe, shipped to the final destination without transfer or removal from the car, the
tolerance shall apply to each car. For any order consisting of more than a carload
and shipped from the manufacturer’s facility by rail, but not to the final destination,
the carload tolerance shall apply to the total order, but not to the individual carloads.
** By agreement between purchaser and manufacturer or processor the total range
length for range 1 tubing may be 20-28ft.
*** 2ft pup joints may be furnished up to 3ft long by agreement between purchaser and
manufacturer, and lengths other than those listed may be furnished by agreement
between purchaser and manufacturer.
Range 1 2 3
Casing And Liners
Total range length include 4.88-7.62 7.62-10.36 10.36-14.63
* Range Length for 95% or more of carload
Permissible Variation, max. 1.83 1.52 1.83
Permissible length, min 5.49 8.53 10.97
Tubing
** Total range length include 6.10-7.32 8.53-9.75 -
* Range Length for 100% or more of carload
Permissible Variation, max. 0.61 0.61 -
Permissible length, min 6.10 8.53 -
Pup Joint
*** Lengths 0.61, 0.19, 1.22, 1.83, 2.44, 3.05 and 3.66m
Tolerance ±76.2mm
* Carload tolerance shall not apply to orders of less than a carload shipped from the
manufacturer’s or processor’s facility. For any carload of pipe shipped from the
manufacturer’s or processor’s facility to the final destination without transfers or
removal from the car, the tolerance shall apply to each car. For any order
consisting of more than a carload and shipped by rail, but not to the final
destination in the rail cars loaded, the carload tolerance shall apply to the total
order, but not to the individual carloads.
** By agreement between the purchaser and manufacturer or processor the total
range length for range 1 tubing may be 6.10-8.53m.
*** 0.61m pup joints may be furnished up to 0.91m long by agreement between
purchaser and manufacturer, and lengths other than those may be furnished be
agreement between purchaser and manufacturer.
For pup joints shorter than 6ft (1.83m) in length, the entire surface except the threads shall
be painted.
The colour and number of bands shall be as follows:
Grade H 40 No colour marking, or black at the manufacturer’s option
Group 2
1) A paint band or bands encircling the pipe at a distance not greater than 2ft (0,61m)
from the coupling or box.
Grade C75 One blue band
Grace C75, 9Cr One blue band and two yellow bands
Grade L80, 9Cr One red and one brown and two yellow bands
Grade L80, 13Cr. One red and one brown and one yellow band
4) For pup joints shorter than 6ft (1.83m) in length, the entire surface except the
threads shall be painted.
S P E O IDENTIFICATION CODE PAG 40 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
Casing design is actually a stress analysis procedure. The objective of the procedure is to
produce a pressure vessel which can withstand a variety of external, internal, thermal, and
self weight loading, while at the same time being subjected to wear and corrosion.
During the drilling phase, this pressure vessel is a composite of steel and in conjunction
with a variety of biaxially stressed rock materials.
As there is little point in designing for loads that are not encountered in the field, or in
having a casing that is disproportionally strong in relation to the underlying formations,
there are four major elements to the casing design process:
• Definition of the loading conditions likely to be encountered throughout the life
of the well.
• Specification of the mechanical strength of the pipe.
• Estimation of the formation strength using rock and soil mechanics.
• Estimation of the extent to which the pipe will deteriorate through time and
quantification of the impact that this will have on its strength.
It is obvious that loads that can affect casing during the life of the well can not be exactly
predicted; for this reason they will be defined taking into account the most demanding
situations that can realistically occur. These “Load Cases” are not arbitrarily selected, as
they are defined by Company on the base of previous experience and statistical data,
when available (see section 8).
It is also necessary to have as much information as possible on the formations that we are
going to drill: pressure and temperature gradients, formation fluids characteristics,
formation strength and potential problems that are likely to be encountered due to
formation behaviour during drilling. The amount of information strictly depends on the
experience gained in other wells of the same field or similar areas: it is clear that the
amount of information available is different for exploration or development wells, and then
also approach of casing design will reflect this difference.
Besides it will be necessary to know the tubular material resistance, which depends on
geometrical characteristics (diameter, thickness, type of connection) and class of material.
International organisations and manufacturers provide information on the resistance to the
three typical loads that can affect a pipe: internal pressure (burst), external pressure
(collapse) and axial tension.
The DF is closely linked to the uncertainties, (the higher the uncertainties, the higher the
DF needed) and has the purpose of limiting the risk to an acceptable value.
Different DF are specified for the three typical load cases and for the different steel grades
(high grades require higher DF because they have a smaller margin between Yield
Strength and Tensile Strength, and because they have a lower capability to resist to
damage inflicted from handling and running equipment).
The company values selected for DFs are a compromise between safety margin and
economics. The use of high DFs provides more guarantees against failure but requires
higher class of material and, therefore, increased cost.
On the other side, the use of low DFs requires accurate knowledge about the loads to be
imposed on the casing, in order to keep the risk at an acceptable level, as there is less
margin available.
This can be the case when a D.F. lower than those specified by company could be
accepted; in this case, however, the acceptance must be duly justified from the
engineering point of view and authorised by the responsible position.
It should be noted that the Design Factor used in the context of casing string design is
essentially different from the ‘Safety Factor’ used in many other engineering applications
(e.g. tubing design). Indeed the term ‘Safety Factor’, implies that the actual physical
properties and loading conditions are exactly known and that a specific margin is being
allowed for safety.
In Casing Design the loading conditions are not always precisely known, therefore the
term ‘Safety Factor’ is not appropriate in this context.
S P E O IDENTIFICATION CODE PAG 42 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
Design Factor
Casing Grade
Burst Collapse Tension
Note: The DF for tension is considerably higher than the ones for burst and
collapse, to avoid exceeding the elastic limit and, therefore invalidating
the criteria on which burst and collapse resistances are calculated.
Casing verification process, with correct use of Design Factor is reported in following
section 7.2.
This approach has the advantage of directly comparing the loads with the relevant casing
resistance. The casing resistance (also addressed as “minimum performance properties”)
shall be worked out from API bulletin or from Manufacturer’s technical documentation in
case of non API material (e.g. proprietary grades or premium connections).
The load cases will be specified in section 8 of this manual.
S P E O IDENTIFICATION CODE PAG 43 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
After having defined a casing string with the basic verifications, the designer may evaluate
one or more of the additional loads described above (if applicable in the specific well
condition); this will lead to a more sophisticated design process and possibly to a further
upgrading of casing.
The list of loads affecting casing verification is by no means comprehensive of all possible
of all possible stresses and can be modified as research and technology progress.
S P E O IDENTIFICATION CODE PAG 44 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
Axial stress is mostly due to the weight of the casing string, but also buoyancy provides a
major contribution.
Furthermore any changes in the internal and external pressures acting on casing will
induce changes in the axial stress as well as the radial (σr) and tangential (σt) stresses.
In addition, since the pipe is held or fixed at both ends, changes in all three stresses will
occur due to temperature changes and from the occurrence, and degree, of any buckling
effect.
The inter-relationship between these loads can be analysed manually by applying a
combination of Hooke's Law, ‘Lame's Equations’ and some form of yield criteria. This is
referred to as ‘Triaxial Stress Analysis’, but is not normally performed in our Company.
S P E O IDENTIFICATION CODE PAG 45 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
8. DESIGN CRITERIA
Actually, the Company soft-ware adopted to perform the casing load conditions analysis
is: Landmark “Stress Check “.This software is not fully in compliance with the Company
criteria, but it is however accepted only if used as stated in STAP-P-1-N-13568, where
some of the criteria that stress check foresees have been selected and tested in order to
obtain values having the better compliance with the values obtained using Company
criteria.
8.1 BURST
Burst loading on the casing is induced when internal pressure exceeds external pressure.
Based on the vast amount of well data which is currently available, a set of key design
considerations are made:
a) Blowouts, especially those which are capable of exerting ultra high surface
pressure (i.e. dry gas blowouts), are very rare.
b) Ultra high surface pressures can only be experienced if an actual dry gas
blow-out does occur.
c) High strength casing, regardless of how overdesigned it may be, has no
impact on the reduction of the blow-out risk.
d) Once a blow-out has occurred, damage to the rig, environment, etc. will have
already commenced, regardless of how strong the casing may be.
e) If there is a blow-out, even a dry gas blow-out, it does not always concur that
the casing will be exposed to high burst pressures.
S P E O IDENTIFICATION CODE PAG 46 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
The key to this problem is to recognise the rare and exceptional well circumstances that
may require or result in a hard dry gas shut-in. The decision process should be based on
the initial adoption of a ‘middle ground’ design.
The Drilling & Completion Engineering Department evaluated these key design
considerations and have decided to use the most conservative method and to reduce the
obtained results by 40%.
c) The bottom-hole internal pressure limit is set equal to the predicted fracture
gradient of the formation below the casing shoe.
d) Connect both the wellhead and bottom-hole internal pressure values with a
straight line to obtain the maximum internal pressure load versus depth.
2) External Pressure
a) In wells with surface wellheads, the external pressure is assumed to be equal
to the hydrostatic pressure of a column of drilling fluid which the casing has
been ran through.
In wells with subsea wellheads:
At the wellhead - Water Depth x Seawater Density x 0.1 (atm)
At the shoe - (Shoe Depth - Air Gap) x Seawater Density x 0.1 (atm).
b) Using Stress Check, to bring the external pressure calculation in line with the
Company standard, shall be considered:
• Select the criterion “Fluid Gradients w/Pore Pressure” without setting
the flag that uses open hole pore pressure, makes it possible adopt in
both the annulus, with open hole and annulus with the previous casing,
the pressure applied by the mud in which casing is run, and thus
reproduce the current Eni-E&P rule exactly.
3) Net Pressure
The resultant burst load, or net pressure, will be obtained by subtracting, at each
depth, the external from internal pressure.
2) External Pressure
a) The external collapse pressure is taken to be equal to that of the formation
pressure.
• With a subsea wellhead, at the wellhead, hydrostatic seawater pressure
should be considered.
b) Using Stress Check, to bring the external pressure calculation in line with the
Company standard, shall be considered:
• Select the criterion “Fluid Gradients w/Pore Pressure” for calculating
external pressure; this assumes the pressure deriving from the pore
gradient, in the annulus with the open hole, while in the annulus with the
previous casing the pressure deriving from the gradient of the cementing
slurry mixing water up to TOC and above TOC is considered as the
pressure deriving from the mud gradient in which casing is run.
1) Internal Pressure
a) The wellhead internal pressure value is obtained as the difference between
the pore pressure of the reservoir fluid and the hydrostatic pressure of the
produced fluid which is inside the tubing. In case of uncertainty on the nature
of produced fluid (hence of its density), a column of gas having density = 0.3
kg/dm3 will be considered. Actual gas/oil gradients can be used if information
on these is known and available.
b) Using Stress Check, to bring the internal pressure calculation in line with the
Company standard, shall be considered:
• Select the criterion “Tubing Leak” to exactly reproduce the Company
criterion.
c) The bottom-hole internal pressure value is obtained by adding the wellhead
internal pressure to the annulus hydrostatic pressure exerted by the
completion/packer fluid. Generally the completion fluid density is equal to, or
close to, the mud weight in which casing is installed.
d) Connect both the wellhead and the bottomhole internal pressure with a straight
line to obtain the maximum internal pressure.
Note: It is usually assumed that the completion fluid and mud on the outside
of the casing remains homogeneous and retains the original density
values’ however this is not actually the case, particularly with heavy
fluids, but it is also assumed that the two fluids will degrade similarly
under the same conditions of pressure and temperature.
S P E O IDENTIFICATION CODE PAG 49 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
2) External Pressure
a) The external pressure is taken to be equal to that of the formation pressure.
With a subsea wellhead, at the wellhead, hydrostatic seawater pressure
should be considered.
b) Using Stress Check, to bring the external pressure calculation in line with the
Company standard, shall be considered:
• Select the criterion “Fluid Gradients w/Pore Pressure” for calculating
external pressure. This assumes a pressure deriving from the pore
gradient in the annulus with the open hole, while in the annulus with the
previous casing, the pressure deriving from the gradient of the
cementing slurry mixing water up to TOC and above TOC is considered
as the pressure deriving from the mud gradient in which casing is run.
c) Resulting pressure - at the casing head and in the open hole section will be the
same as that calculated using the Company criterion.
Tie-Back String
In a high pressure well, the intermediate casing string above a liner may be unable to
withstand a tubing leak at surface pressures according to the production burst criteria. The
solution to this problem is to run and tie-back a string of casing from the liner top to
surface, isolating the intermediate casing.
S P E O IDENTIFICATION CODE PAG 50 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
8.2 COLLAPSE
Collapse loading of the casing is induced if the external pressure exceeds the internal
pressure.
It occurs as a result of either, or a combination of:
• Reduction in internal fluid pressure.
• Increase in external fluid pressure.
• Additional mechanical loading imposed by plastic formation movement.
Note : The calculation criteria used by the Stress Check can exactly
reproduce the Company criteria.
2) External Pressure
a) In wells with a surface wellhead, the external pressure is assumed to be equal
to that of the hydrostatic pressure of a column mud in which casing was run. In
offshore wells with a subsea wellhead, it is calculated:
• At the wellhead - Water Depth x Seawater Density x 0.1 (atm).
• At the shoe - (Shoe Depth - Air Gap) x Seawater Density x 0.1 (atm).
S P E O IDENTIFICATION CODE PAG 51 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
b) Using Stress Check, to bring the external pressure calculation in line with the
Company standard, shall be considered:
• Select the criterion “Fluid Gradients w/Pore Pressure”, and without
setting the flag which uses open hole pore pressure, it is possible to
adopt the pressure deriving from the mud gradient in which casing is
run, for both the annulus with the open hole and the annulus with the
previous casing.
When thief zones cannot be confirmed and in case of wells with surface wellheads
or in case of exploration wells, the casing is assumed to be half empty and the
remaining part full of the heaviest mud planned to drill the next section below the
shoe.
Using Stress Check, to bring the internal pressure calculation in line with the
Company standard, shall be considered:
• Select the criterion “Full/Partial evacuation”.
2) External Pressure
The pressure exerted on the outside of the casing is the pressure of mud which
the casing is installed in.
In case of salt sections, consider uniform external loading equal to the overburden
pressure at the true vertical depth of the relevant point (See section 8.7).
Using Stress Check, to bring the external pressure calculation in line with the
Company standard, shall be considered:
• Select the criterion “Fluid Gradients w/Pore Pressure”, and without setting
the flag which uses open hole pore pressure, it is possible to adopt the
pressure deriving from the mud gradient in which the casing is run, for both the
annulus with the open hole and the annulus with the previous casing.
Using Stress Check, to bring the internal pressure calculation in line with the
Company standard, shall be considered:
• Select the criterion “Full/Partial evacuation”.
2) External Pressure
Assume the hydrostatic pressure exerted by the mud in which casing is installed.
In case of salt sections, consider uniform external loading equal to the overburden
pressure at the true vertical depth of the relevant point (See section 8.7).
S P E O IDENTIFICATION CODE PAG 53 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
Using Stress Check, to bring the external pressure calculation in line with the
Company standard, shall be considered:
• Select the criterion “Fluid Gradients w/Pore Pressure”, and without setting
the flag which uses open hole pore pressure, it is possible to adopt the
pressure deriving from the mud gradient in which the casing is run, for both the
annulus with the open hole and the annulus with the previous casing.
Tie-Back String
If the intermediate string above the liner is unable to withstand the collapse pressure
calculated according to the production collapse criteria, it will be necessary to run and tie-
back a string of casing from the liner top to surface.
8.3 TENSION
8.3.1 GENERAL
Tensile failure occurs if the longitudinal force exerted on a pipe exceeds either the tensile
strength of the pipe or its connection. Generally, the connection used in a string of casing
is stronger than the pipe body although this must always be confirmed.
For situations where a connection coupling has to be special clearance, (i.e. of a smaller
diameter than the normal) the connection will be weaker or if flush joint pipe must be used
in special circumstances.
Tensile loads are imposed on the casing by:
1) The weight of pipe itself. The highest tensile stresses will occur at the uppermost
portion of the pipe. The tension is the weight of the pipe in air less buoyancy.
2) Shock loading:
• While lowering casing through unstable formations such as cavings where the
casing string may get temporarily stuck before suddenly slipping through
thereby inducing tensile shock loads.
• When landing casing in a subsea wellhead from a floater.
3) Upward and downward reciprocating movements carried out where there is a
tendency to become differential stuck, etc. in order to become free. To free the pipe
considerable pull may be necessary.
S P E O IDENTIFICATION CODE PAG 54 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
Note: The varying parameters which can affect tensile loading leads to the
estimates used for the tensile forces are more uncertain than the
estimates for either burst or collapse. The DF imposed is therefore
correspondingly much larger.
The forces acting on the areas of collar shoulders (F3) are for practical purposes
negligible in casing design as the upward and downward facing shoulders countered each
other over short distances.
Note: When calculating the tension with regard to buoyancy trends, the
different weights per unit length of the casing must be taken into
account, as they have different cross-sectional areas. In the following
example an average weight value is assumed since this does not
substantially affect the calculations.
Example:
Weight of casing in air = 250,000kg
Mud weight = 1.70kg/dm3
Buoyancy factor = 0.782
Weight of casing in mud = 250,000 x 0.782
= 195,500kg
Buoyancy force = 54,500kg
3) Add the additional load due to bumping the cement plug to the casing string weight
in mud.
Take into account eventual pressurisation about both opening /closing DV
operations and setting ECP.
Note: More than one section of the casing string may be loaded in
compression.
S P E O IDENTIFICATION CODE PAG 59 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
Using Stress Check, it is possible to reproduce the Company standards, and to perform
more accurate calculations.
The following criteria shall be considered:
• Select the criterion “Precementing static load” to simulate bottom hole casing
with the stress factors generated by applying the buoyancy.1
• Select the criterion “Running in hole” (with a rate =0) to simulate the tensile
stress sustained by the casing during its run in (tension and bending)
producing a “Load line” which will have the same value at the casing head as
the casing string weight in mud, taking into account the borehole inclination
and the fact that shoe tensile stress = 0
• Select the criterion “Green cement pressure test” to consider any additional
stress due to Bumping plug pressure.
Example Data
Estimated top of cement 2,800m
Cemented length of casing 1,250m
Casing size 7ins
Steel grade P 110
Weight (imperial) 38lbs/ft
Weight (metric) 56.55kg/m
Internal diameter 5.898ins
Casing shoe depth 4050m
Mud weight during cementing operation 1.93kg/l
Average cement slurry density 2.00kg/l
Expected mud weight at end of next phase 2.16kg/l
Estimated bump plug pressure 140kg/cm2
Next phase total depth 4400m
1 Buoyancy –Stress-Check considers the relative depths of the different exposed surfaces (casing shoe, top liner or section variation
due to mixed casings), and the force generated by the hydrostatic pressure of the fluid which the casing is immersed in applied to
these surfaces.
S P E O IDENTIFICATION CODE PAG 60 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
API recommendation is to land the casing with the same tension at the end of the
displacement in all wells where the mud density does not exceed 12.5ppg (1.50kg/l) in the
next section.
S P E O IDENTIFICATION CODE PAG 61 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
The second option is used when excessive mud weights are anticipated, to prevent any
tendency of the casing to buckle above the freeze point.
Note: The effects of axial stress on burst resistance are negligible for the
majority of wells.
X= Tensile load
Pipe body yield strength
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1 1.1
0
0.1
Collapse resistence without tensile load
0.2
Collapsresistence with tensile load
0.3
0.4
0.5
0.6
0.7
0.8
Y=
0.9
1.1
From the curve or stress curve factors in Figure 8-4, if X = 0.695 then Y = 0.445 and the
collapse resistance against tensile load can be determined:
Collapse resistance under load = Nominal Collapse Rating x 0.445
Refer to Figure 8-5 for a graphical representation of this calculation.
S P E O IDENTIFICATION CODE PAG 65 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
8.5 BENDING
8.5.1 GENERAL
When calculating tensile loading, the effect of bending must also be considered, if
applicable.
The bending of the pipe causes additional stress in the walls of the pipe. This bending
causes tension on the outside of the pipe and in compression on the inside of the bend,
assuming the pipe is not already under tension (Refer to Figure 8-6).
Bending is caused by any deviation in the wellbore resulting from side tracks, build-ups
and drop-offs.
Since bending load increases the total tensile load, it must be deducted from the usable
rated tensile strength of the pipe.
where:
α = Rate of build-up or drop off (degrees per 30m)
where:
MB = Bending moment (MB = E x J/R) (kg x cm)
MB × L
θ= Eq. 8.C
E×J
where:
MB = Bending moment (kg x cm)
θ×E×J
Obtaining MB = from equation 2), equation 1) becomes:
L
θ×E×D
σ= Eq. 8.D
2×L
Then, by using the more current units giving the build-up or drop-off angles in
degrees/30m, we obtain the final form of the equation for ‘TB’ as follows:
TB
σ=
Af
θ × E × D × Af Eq. 8.E
TB =
2×L
S P E O IDENTIFICATION CODE PAG 68 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
180 × 30 × 100
R=
π ×α
1
L= Eq. 8.F
θ
π × α × E × D × Af
TB =
180 × 2 × 30 × 100
α = Degrees/100ft
TB = 218 x α x D x Af (lbs)
or
TB = 63 x α x D x W (lbs)
Note: Since most casing has a relatively narrow range of wall thickness (from
0.25 to 0.60ins), the weight of casing is approximately proportional to
its diameter. This means the value of the bending load increases with
the square of the pipe diameter for any given value of build-up/drop-off
rate. At the same time, joint tension strength rises a little less than the
direct ratio. The result is that bending is a much more severe problem
with large diameter casing than with smaller sizes.
Calculation:
1) Casing weight in air (Wa)
Wa = 107.14 x 2,000 = 214t
2) Casing weight in mud (Wm)
Wm = 214 x 0.859 = 184t
3) Additional tension due to the bending effect (TB)
TB = 15.52 x 3 x 13.375 x 133.99 = 83,441kg = 83t
This stress will be added to the tensile stress already existing on the curved
section of hole.
4) Tension in the casing at 300m(TVD)=156 t. 5)
5) Total tension in the casing at 300m = 156 + 83 = 239t
6) Tension in the casing at 600m (MD) =129t.
7) Total tension in the casing at 600m (MD) = 129 + 83 = 212t.
The location and magnitude of volumetric wear in the casing string can be estimated by
calculating the energy imparted from the rotating tool joints to the casing at different
casing points and dividing this by the amount of energy required to wear away a unit
volume of the casing. The percentage casing wear at each point along the casing is then
calculated from the volumetric wear.
S P E O IDENTIFICATION CODE PAG 72 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
Note: The chemical action of gases such as H2S, CO2 and 02 tends to reduce
the surface hardness of steel and, thus, contributes significantly to the
rate of wear.
where:
V = Wear volume per foot
The frictional energy imparted to the casing by the rotating tool joint equals:
Energy Input Per Foot = Friction Force Per Foot x Sliding Distance Eq. 8.I
where:
Friction Force Per Foot = Friction Factor x Tool Joint Lateral Load Per Foot
and
S x TJL
Tool Joint Contact Time = Eq. 8.J
DPJL
where:
S = Drilling distance (ft)
where:
L = Drill pipe lateral load per foot
where:
V = Wear volume per foot (in3/ft)
The tool joint and drill pipe lengths do not appear in Eq. 8.M because they do not affect
the amount of casing wear in the linear model.
Drilling Fluid Tool Joint Wear Factor (F) (10-1 psi -l)
Water+Betonite+Barite Smooth 0.5 to 1
Water+Betonite+Lubricant (2%) Smooth 0.5 to 5
Water+Betonite+Drill Solids Smooth 5 to 10
Water Smooth 10 to 30
Water+Betonite Smooth 10 to 30
Water+Betonite+Barite Slightly Rough 20 to 50
Water+Betonite+Barite Rough 50 to 150
Water+Betonite+Barite Very Rough 200 to 400
Table 8-c - Typical Casing Wear Factors
When tool joints are smooth, casing wear is minimised when the mud consists of water,
bentonite and barite, (F = 0.5 to 1.0).
The small particles of barite appear to act as ball bearings and prevent the tool joint and
casing materials from coming into intimate contact.
Casing wear is increased tenfold when the mud is weighted with drill solids instead of
barite, (F = 5 to 10). This shows the importance of having good solids control when
running heavily weighted muds.
Water (without solids) causes high wear, (F = 10 to 30) because there are no solids to
prevent the sliding metals surfaces from coming into contact and causing galling wear. In
extreme cases, the surface can weld together resulting in chunks of metal being torn from
the surfaces.
S P E O IDENTIFICATION CODE PAG 79 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
When tool joints have rough hardbanding, the wear is controlled primarily by the
roughness of the tool joint and is almost independent of the mud properties. In this case,
the rough tool joints tend to machine away the casing in even larger pieces (similar to the
cutting action of a mill) resulting in rapid failure of the casing. Table 8-d gives comparisons
of casing wear with twelve different hardmetal materials tested in the DEA-42 project.
Figure 8-18 shows casing wear versus tool joint passes.
The data given in Table 8-c and Table 8-e show that drill pipe rubber protectors (F= 1 to
10) will reduce casing wear under all conditions except when using smooth tool joints with
water base mud weighted with barite, (F = 0.5 to 1.0).
In applications where very rough hard metal tool joints (F= 200 to 400) are being used, the
rubber protectors (F = 1 to 10) can reduce casing wear by 95 to 99 percent.
Limited casing wear data for oil based muds is also available. These limited tests indicate
that casing wear rates are nearly identical for oil based and water based muds.
Shell (Bol. 1985) found that the addition of barite to the mud significantly reduces casing
wear (Refer to Figure 8-19).
The barite apparently acts as ball bearings and keeps the sliding metal surfaces from
coming into contact with each other and causing galling wear as already described in the
previous section.
S P E O IDENTIFICATION CODE PAG 81 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
The barite reduced the wear factor from 25 using no barite to 1 to 2 with barite.
Shell (Bol, 1985) conducted tests which showed that a 10ppg mud weighted with drill
solids produced significantly more casing wear then a 10ppg mud weighted with barite
(Refer to Figure 8-20 below).
With lateral loads of 900 to 1,800lbs (4 to 8kN), the wear factor ranged from 5 to 10 with
drill solids compared to 0.5 to 1.0 with barite. Apparently the small diameter of the barite
contributed to this reduced wear.
Shell (Bol, 1985) conducted tests with muds weighted with different weighting materials
and found that weighting materials significantly reduce casing wear.
Weighting materials were found to reduce casing wear in all cases. Wear was greatest (F=
22 to 27), when no weighting material was present to act as a buffer between the tool joint
and the casing. The addition of silica sand to the bentonite and water reduced the casing
wear in half, (F = 11 to 13).
Drill solids (F = 5 to 11) produced less wear than silica sand.
Iron oxide (F = 3 to 4), which is often considered very abrasive, produced less wear than
all of the other weighting materials except barite. This is apparently due to the small size
of the iron oxide weighting particles.
These tests indicate that the size of the weighting particles may be more important than
the composition of the particles.
S P E O IDENTIFICATION CODE PAG 83 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
Oil based and water based muds weighted with barite produced minimal wear (F = 0.8 to
1.6). This shows the importance of having good solids control when using heavily
weighted muds.
Shell (Bol, 1985) found that the addition of 2% lubricant to an unweighted mud consisting
of water and bentonite significantly reduced casing wear refer to Figure 8-22.
The addition of 2% lubricant reduced the wear factor when using bentonite mud from
about 30 to 5 with 1,800lbs lateral load (8kN) on the tool joint and from about 30 to 0.5
with 900lbs load (4kN) on the tool joint.
These tests show that lubricants may be useful in wells where casing wear may be a
problem.
If the allowable operating time is less than the anticipated operating time, use heavier
casing (or increases the grade) 100m above and to 60m below the wear point until the
allowable operating time exceeds the anticipated operating time.
S P E O IDENTIFICATION CODE PAG 85 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
If the allowable operating time is greater than the anticipated operating time (say
estimated 50 days allowable versus estimated 20 days operating) do not include a wear
allowance. If the allowable operating time and the anticipated operating time are about the
same, either:
a) Include a wear allowance
or
b) Monitor casing wear during drilling, and commission an intermediate string if
the worn casing strength approaches the design loads.
In any given situation whether option a) or b) is exercised will be dependent upon a
number of factors, many of which are beyond the scope of routine casing design.
Option a)
Is the conservative approach, but it may be too high, given the gross uncertainties
inherent in wear estimations. However, in rank wildcats, particularly in remote locations, it
may be justified.
Option b)
Requires a base caliper survey to be run immediately after installing the casing string,
followed by runs at discrete intervals during the drilling phase.
If wear is proven to have occurred, and an intermediate string has to be commissioned
early, the deeper objectives of the well may not be reached. However, conditions as
drilling proceeds may indicate that the design loads assumed are not going to be
encountered and the reduction in casing strength is acceptable.
In any event, valuable data on casing wear in the area will be obtained and field practices
may be improved as result of the attention paid to wear, eventually leading to a reduction
in overall wear rates.
In most cases, option b) is preferred.
With regards to trouble free drilling, sticking due to salt flow, mud problems from salt
contamination, hole enlargement and the well's overall casing programme, are the prime
factors to be considered.
There are other factors that have to not be under evaluated such as:
• Control of gas flows from porous zones interbedded in the salt, differential
sticking in porous zones.
• Abnormal pressure due to entrapment of pressure by salt.
• Shale sloughing from interbedded or boundary shales.
To prevent casing collapse, the designer should plan for non-uniform salt loading,
obtaining the best possible cement job, using casing with higher than normal collapse
ratings and possibly two strings of casing through the salt section.
Running casing in salt sections is rather a cementing problem than a casing design
problem.
In some cases, two strings may be more advantageous as experience has demonstrated
that it is not practical to design a casing string to resist collapse. This technique is
probably the most reliable and safest approach for preventing casing collapse but is
probably not necessary for the majority of salt sections.
If there is a possibility of salt loading, several remedial actions may be taken. The first
group of precautions may be classified under the general heading of filling the casing
internally, either, with gravel, other solids or a fluid. For production casing, such actions
are usually not possible.
The alternative is to run a scab liner inside the casing opposite the suspect formation and
cement the annulus between the two casing strings refer to Figure 8-24.
The benefits gained from running such a liner are substantial.
In the lower portion of the figure, the flowing formation has come in contact with the casing
thus restricting its movement. Above this point of contact, additional flow of the formation
is depicted as being in progress. Subsequent formation movement above the frozen point
will cause severe bending loads and, thus, reduce the casing cross-sectional integrity.
Problems may be observed before final catastrophic failure of the cross section e.g. the
ovality of the cross section may be sufficient enough to result in restrictions in the casing
that will prohibit the passage of bits or production equipment.
However, even in the presence of non-uniform external loads, the structural benefits of
using concentric casing strings are substantial.
S P E O IDENTIFICATION CODE PAG 91 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
Conclusions:
• Running casing in salt sections is rather a cementing problem than a casing
problem.
• If the pipe is well cemented, it is sufficient to design for collapse load in the
traditional mode (overburden pressure/design factor).
• If the casing is poorly cemented the collapse effect may be very high. In this
case, contingency actions may be evaluated.
• Designer may consider high collapse casing grades, (exceeding API
standards) that are currently offered by most pipe manufacturers (Refer to
Figure 8-28).
S P E O IDENTIFICATION CODE PAG 92 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
9. CORROSION
9.1 GENERAL
A production well design should attempt to contain produced corrosive fluids within tubing.
They should not be produced through the casing/tubing annulus.
However, it is accepted that tubing leaks and pressured annuli are a fact of life and as
such, production casing strings are considered to be subject to corrosive environments
when designing casing for a well where hydrogen sulphide (H2S) or carbon dioxide (CO2)
laden reservoir fluids can be expected.
During the drilling phase, if there is any likelihood of a sour corrosive influx occurring,
consideration should be given to setting a sour service casing string before drilling into the
reservoir.
The BOP stack and wellhead components must also be suitable for sour service.
These measures will provide a degree of short term protection necessary to control
corrosion of the casing in the hole during the drilling phase.
2) External corrosion
Where the likelihood of external corrosion due to electrochemical activity is high
and the consequences of such corrosion are serious, the production casing
should be cathodically protected (either cathodically or by selecting a casing
grade suitable for the expected corrosion environment).
S P E O IDENTIFICATION CODE PAG 94 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
1) Oxygen (O2)
Oxygen dissolved in water drastically increases its corrosion potential. It can
cause severe corrosion at very low concentrations of less than 1.0ppm.
The solubility of oxygen in water is a function of pressure, temperature and
chloride content. Oxygen is less soluble in salt water than in fresh water.
Oxygen usually causes pitting in steels.
4) Temperature
Like most chemical reactions, corrosion rates generally increase with increasing
temperature.
S P E O IDENTIFICATION CODE PAG 95 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
5) Pressure
Pressure affects the rates of chemical reactions and corrosion reactions are no
exception.
In oilfield systems, the primary importance of pressure is its effect on dissolved
gases. More gas goes into solution as the pressure is increased; this may in turn
increase the corrosion action of the solution.
The following formulae are used to calculate the value of pH2S (partial pressure of H2S) in
both the cases of gas (or condensate gas) wells or oil wells.
Firstly, the potential for SSC occurring is evaluated by studying the water cut values
combined with the type of well and deviation profile. If the conditions specified above are
verified then the pH2S can be calculated.
where:
SBHP = Static bottom-hole pressure [atm]
Undersaturated Oil
Oil in which the gas remains dissolved, because the wellhead and bottom-hole pressures
are higher than the bubble point pressure (Pb) at reservoir temperature, is termed
undersaturated.
In this case the pH2S is calculated in two ways:
• Basic method.
• Material balance method.
If the quantity of H2S in gas at the bubble point pressure [mole fraction = Y(H2S)], is not
known or the values obtained are not reliable, the pH2S is calculated using both methods
and the higher of the two results is taken as a reliable value. Otherwise the basic method
is used.
S P E O IDENTIFICATION CODE PAG 97 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
Basic Method
This method is used, without comparison with the other method, when the H2S value in the
separated gas at bubble point conditions is known and is reliable or if Y(H2S), molar
fraction in the separated gas at bubble point pressure (Pb) is higher than 2%.
The pH2S is calculated by: pH2S = Pb x Y(H2S)/100
where:
Pb = Bubble point pressure at reservoir temperature [atm]
Y(H2S) = Mole fraction in the separated gas at bubble point (from PVT data if
extrapolated)
γ 1000
PM =
GOR
γ 1000 + ( d 29) GOR Eq. 9.B
23. 6 −
PM res 23. 6
where:
⎡⎛ n ⎞ ⎤
PM res = mean molecular weight of the reservoir oil = ⎢⎜ ∑ CiMi⎟ / 100⎥
⎣⎝ i = 1 ⎠ ⎦
Ci = Mole% of the ith component of the reservoir oil
Mi = Molecular weight of the ith component of the reservoir oil
d = Density of the gas at separator conditions referred to air =1.
S P E O IDENTIFICATION CODE PAG 98 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
where:
H1 = Henry constant of the produced oil at separator temperature
(atm/Mole fraction). (See Procedure for calculating Henry constant)
The quantity of H2S in the gas in equilibrium is calculated (per litre of oil):
[H2S]gas = (GOR/23.6 x H2Ssep/106) Eq. 9.D
where:
GOR = Gas oil ratio Nm3/m3 (from production tests)
H2 = Henry constant for the reservoir temperature and reservoir oil. (See
procedure for calculating Henry constant).
In general, H2S corrosion can occur at either the wellhead or bottom-hole without
distinction.
There is SSC potential if pH2S >0.0035 atm and STHP >18.63 atm.
PM
• Hept Heptane = 100
PM
• N-propyl benzene = 120
PM
• Methylnaphthalene = 142
S P E O IDENTIFICATION CODE PAG 99 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
Having calculated the molecular weight of the produced oil PM using the formula in Eq.
9.B, the reference curve is chosen (given by points) to calculate the Henry constant on the
basis of the following value thresholds:
PM ≥
• I If 142, the H(t) curve of methylnaphthalene is used.
PM
• If = 120, the H(t) curve of propyl benzene is used.
PM ≤
• If 100, the H(t) curve of heptane is used.
PM
• If 100 < < 120, the mean value is calculated using the H(t) curve of propyl
benzene and the H(t) curve of methylnaphthalene.
PM
• If 120 < < 142 the mean value is calculated using the H(t) curve of heptane
and the H(t) curve of propyl benzene.
• Given FTHT, wellhead flowing temperature, the H1 value is interpolated
linearly on the chosen curve(s). For this purpose the temperature values
immediately before and after the temperature studied are taken into
consideration.
Having calculated the molecular weight of the reservoir oil PM res, using temperature
measured at the separator, H2 is measured in a similar way as H1.
S P E O IDENTIFICATION CODE PAG 100 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
130 Henry
atm/Y[H2S]
120
110
100
90
methylnaphthalene PM = 142
80
N-propylbenzene PM = 120
70 heptane PM = 100
60
50
40
30
20
20 30 40 50 60 70 80 90 10 11 12 13 14 15 16 17 18 19 20
0 0 0 0 0 0 0 0 0 0 0
T C°
Oversaturated Oil
Oil is considered oversaturated when the gas in the fluid separates because the pressure
of the system is lower than the bubble point pressure. Two situations can arise:
Case A
FTHP < Pb
FBHP > Pb
Case B
FTHP < Pb
FBHP < Pb
Basic Method
pH2S = STHP x Y(H2S) / 100
where:
STHP = static tubing head pressure [atm]
The SSC phenomenon is triggered off at the wellhead if pH2S >0.0035 atm and
STHP>18.63 atm.
S P E O IDENTIFICATION CODE PAG 102 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
2) the PVTs are not reliable, the material balance method can be used as in the case of
undersaturated oil; these are the worst conditions. The error made can be high when
Pb >FBHP.
Calculation Of Partial Pressure At Wellhead
The calculation method is that used for case A (FTHP <Pb)(3)
-
9.2.2 CORROSION CAUSED BY CO2 AND CL
In the presence of water, CO2 gives rise to a corrosion form which is different to those
caused by the presence of H2S. It also occurs only if the partial pressure of CO2 exceeds a
particular threshold. As in the case of SSC, the possibility that corrosions exist in water cut
values combined with the type of well and deviation profile, is evaluated. If the conditions
described in section 9.2.1 exist, then the pCO2 is then calculated.
where:
SBHP = Static bottom-hole pressure [atm]
2 If the percentage (ppm) of H2S in the gas under static conditions is not known, the corresponding value in reservoir
conditions is assumed as being partial pressure at the wellhead.
3 If the percentage (ppm) of H2S in the separated gas under static conditions is not known, the corresponding value in
reservoir conditions is assumed as being partial pressure at the wellhead.
S P E O IDENTIFICATION CODE PAG 103 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
where:
Pb = Bubble point pressure at reservoir temperature
Y(CO2) = Mole fraction of CO2 in separated gas at bubble point pressure (from
the PVTs)
Oversaturated Oil
The oil is considered oversaturated when the gas separates in the fluid because the
pressure of the system is lower than bubble point pressure. Two situations may arise:
Case A
FTHP <Pb
FBHP >Pb
Case B
FTHP <Pb
FBHP <Pb
where:
Pb = bubble point pressure at reservoir temperature
Y(CO2) = mole fraction in separated gas at bubble point pressure (from the
PVTs)
where:
pCO2 = partial pressure of CO2 [atm]
where:
FBHP = flowing bottom-hole pressure [atm]
Y(CO2) = mole fraction in separated gas at pressure FBHP (from the PVTs)
4 If the percentage (ppm) of CO2 in the gas under static conditions is not known, the corresponding value in reservoir
conditions is assumed as being partial pressure at the wellhead.
S P E O IDENTIFICATION CODE PAG 105 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
where:
pCO2 = partial pressure of CO2 [atm]
-
9.2.3 CORROSION CAUSED BY H2S, CO2 AND CL
It is possible to encounter H2S and CO2 besides Cl-. In this case the problem is much more
complex and the choice of suitable material is more delicate. The phenomenon is
diagnosed by calculating the partial pressures of H2S and CO2 and comparing them with
the respective thresholds.
5 If the percentage (ppm) of CO2 in the gas under flowing/static conditions is not known, the corresponding value in
reservoir conditions is assumed as being partial pressure at the wellhead.
S P E O IDENTIFICATION CODE PAG 106 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
Measure Means
Control of the environment • pH
• Temperature
• Pressure
• Chloride concentration
• CO2 concentration
• H2S concentration
• H2O concentration
• Flow rate
• Inhibitors
Surface treatment • Plastic coating
• Plating
Improvement of the corrosion resistivity of the Addition of the alloying elements micro
steel structure
Either of the above will cause a stress wave to be created which will travel through the
casing at the speed of sound.
This effect is quantified as follows:
SL = 150 x V x Af
where:
SL = Shock load (lbs x ins/sec2)
where:
CCL = Cementing contribution load (lbs)
When establishing an internal casing pressure test, the differential pressure due to a
difference in fluid level and/or fluid density, inside and outside the casing, shall be taken
into account.
Consideration should be taken on the maximum allowable tensile strength of the casing
thread considering the relevant tensile design factor.
Each casing shall be pressure tested at the following times:
• When cement plug bumps on bottom with a pressure stated in the drilling
programme.
• When testing blind/shear rams of the BOP stack against the casing.
• After having drilled out a DV collar.
A cemented liner overlap will be positively tested applying a pressure greater than the lea-
off pressure of the previous casing. If there is any doubt, an inflow test could be carried
out, with a sufficient drawdown to test the liner top to the most severe negative differential
pressure that will exist during the life of the well.
The test pressure shall be held and remain stable for at least 10-15 mins.
The test pressure and method for each well are determined on an individual basis and
shall be included in the Geological and Drilling Programme.
11.5.1 BUCKLING
Buckling is a failure of stability which can occur at stress levels well below the yield stress
of the material. Buckling cannot occur where the casing is supported by cement.
Factors responsible for buckling and the degree of buckling are:
• Length of casing, supported by cement
• Hole size and degree of washout
• Tensile loads on the casing string
• Changed pressure conditions across the pipe
• Temperature increases downhole.
All these factors are interrelated but the first three are generally considered major
contributors to buckling, while temperature and pressure changes are primarily the
mechanisms that cause the initial buckling.
A buckling potential may exist in the uncemented portion of a string of casing, if the:
• Internal mud density is increased
• Internal surface pressure is increased
• Annular fluid removed or its density reduced
• Casing is landed with less than full hanging weight
• Temperature of the casing increases.
S P E O IDENTIFICATION CODE PAG 119 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
Buckling of long, uncemented portions of the casing string, in vertical wells, can be
prevented by:
• Cementing the casing up above the neutral point.
• Pre-tensioning the casing after landing.
• Limiting the increase in mud density used after drilling out the casing.
• Rigidly centralising the casing below the neutral point.
Provided that all casing strings can be landed with full hanging weight, the buckling
calculation is only required on the small percentage of deep vertical wells in which the
mud density is to be raised during the drilling of the next open hole section. Thus, for the
majority of wells, buckling is not a major design problem.
In most well designs, the total compressive load is the buoyant load of the intermediate
casings, the tubing to production packer overpull and the weight of the wellhead. This
compressive load is carried by the outer casing string. This outer casing is usually the
conductor or surface casing.
When discussing compressive loads it is convenient to consider three types of well where:
a) The wellhead is at ground level or at the seabed.
b) The wellhead is above seabed (i.e.: platform wells).
c) The mudline suspension takes the weight of the casing at the seabed, but the
wellhead is above seabed.
Mudline Suspension
In this case, the weight of the casing strings is taken at the seabed. The surface casing
must be designed and cemented as outlined in a) above.
The tieback strings above the mudline suspension hanger may be subject to some degree
of buckling.
Most wellhead hook-ups can be safely supported on a 20ins x 133lbs/ft casing string in
water depths up to 300ft (92m). However, if buckling may be suspected to occur in the tied
back surface string a full structural analysis should be commissioned. The structural
analysis may be carried out by companies involved in the supply of conductors.
The analysis is in effect a Riser Tensioner Analysis as is evaluated for semi-submersibles
and it takes into account the effect of waves, current and the weight of the pipe in the free
standing mode.
Decrease in Temperature
1) Drilling Phase:
It is highly unlikely that any routine operation (other than extensive reverse
circulation) will cause a long term temperature decrease in the uncemented
portion of a casing string, thus, no loading applies.
2) Production Phase:
Temperature induced stresses are of no consequence in the outer strings of
casing and attention need only be paid to the production string.
Producers are normally subjected to temperature increases under operating
conditions and the compressive load induced should be treated in the context of
buckling.
S P E O IDENTIFICATION CODE PAG 121 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
Appendix A - ABBREVIATIONS
API American Petroleum Institute GLR Gas Liquid Ratio
BG Background gas GMS Gyro Multi Shot
BHA Bottom Hole Assembly GOC Gas Oil Contact
BHP Bottom Hole Pressure GOR Gas Oil Ratio
BHT Bottom hole temperature GPM Gallon (US) per Minute
BOP Blow Out Preventer GPS Global Positioning System
BPD Barrel Per Day GR Gamma Ray
BPM Barrels Per Minute GSS Gyro Single Shot
BSW Base Sediment and Water HAZOP Hazard and Operability
BUR Build Up Rate HHP Hydraulic Horsepower
BWOC By Weight Of Cement HP/HT High Pressure - High Temperature
BWOW By Weight Of Water HW/HWDP Heavy Weight Drill Pipe
CBL Cement Bond Log IADC International Drilling Contractor
CCD Centre to Centre Distance ID Inside Diameter
CCL Casing Collar Locator IPR Inflow Performance Relationship
CET Cement Evaluation Tool JAM Joint Make-up Torque Analyser
CGR Condensate Gas Ratio KMW Kill mud weight
CP Conductor Pipe KOP Kick Off Point
CRA Corrosion Resistant Alloy LAT Lowest Astronomical Tide
CW Current Well LCM Lost Circulation Materials
DC Drill Collar LCP Lower Circulation Position (GP)
DHM Down Hole Motor LEL Lower Explosive Limit
DLP Dog Leg Potential LOT Leak Off Test
DLS Dog Leg Severity LQC Log Quality Control
DOB Diesel Oil Bentonite LWD Log While Drilling
DOBC Diesel Oil Bentonite Cement MAASP Max Allowable Annular Surface
DOR Drop Off Rate Pressure
DP Drill Pipe MD Measured Depth
DST Drill Stem Test MLS Mudline Suspension
DV DV Collar MMS Magnetic Multi Shot
ECD Equivalent Circulation Density MODU Mobile Offshore Drilling Unit
ECP External Casing Packer MOP Margin of Overpull
EMS Electronic Multi Shot MPI Magnetic Particle Inspection
EMW Equivalent Mud Weight MSL Mean Sea Level
EOC End Of Curvature MSS Magnetic Single Shot
ESD Electric Shut-Down System MW Mud Weight
ESP Electrical Submersible Pump MWD Measurement While Drilling
FBHP Flowing Bottom Hole Pressure NACE National Association of Corrosion
FBHT Flowing Bottom Hole Temperature Engineers
FPI/BO Free Point Indicator / Back Off NDT Non Destructive Test
FTHP Flowing Tubing Head Pressure NMDC Non Magnetic Drill Collar
FTHT Flowing Tubing Head Temperature NSG North Seeking Gyro
NTU Nephelometric Turbidity Unit
S P E O IDENTIFICATION CODE PAG 123 OF 124
ENI S.p.A.
E&P Division REVISION
STAP-P-1-M-6110 0 1
Appendix B - BIBLIOGRAPHY
Company Document Document code
Drilling Design Manual STAP-P-1-M-6100
Well Control Policy Manual STAP-P-1-M-6150
Completion Design Manual STAP-P-1-M-7100
Overpressure Evaluation Manual STAP-P-1-M-6130
Drilling Fluids Operations Manual STAP-P-1-M-6160