INSPECTION RELEASE NOTE( GENERAL)

DATE : 15-Sep-2021 IRN NO. : 20-2101-HAM-IRN-1724

CLIENT : Seaway 7 JOB NO. : CN/20/2101

PROJECT : Seagreen Offshore Wind Farm PAGE : 1 OF 1

RFI REFERENCE : CN-20-2101-EXT010419-Rev.No.00 LOCATION : Hamriyah

ITEM INSPECTED : J-4 UPPER JACKET LEG-A (BAY-3) ALONG WITH NODES & NODE TKY STUBS.

DESCRIPTION : FINAL VISUAL INSPECTION PRIOR TO RELEASE FOR PAINTING.

DESCRIPTION WELD MAP DRAWING FABRICATION DRAWING


Leg Tubular to Tubular/Node Joint No.4, 3 20-2101-EN-S-SD-CL1-1105 SH 01 OF 01
20-2101-EN-S-WD-CL1-6002 SH 01 OF 03 REV 1
(C1U-1-LG-1, C1U-2A-LG-5, C1U-2A-LG-1), REV1

20-2101-EN-S-SD-CL1-1108 SH 01 OF 01
Leg Node TKY Joint Nos: 21,50 20-2101-EN-S-WD-CL1-6002 SH 03 OF 03 REV 1 REV 2, 20-2101-EN-S-SD-CL1-1109 SH 01
(C1U-4-BR-2-2, C1U-4-BR-1-1) OF 02, 2 OF 2 REV1

Verification of Completion Yes No N/A Comments

n All materials traceability verified and Material Tracebility Record completed. ✘

n All fit ups completed and accepted. ✘

n All applicable NDT completed and accepted. ✘

n Post Weld Heat Treatment (PWHT) completed and accepted. ✘

n Additional NDT such as Hardness, PMI, Ferrite testing completed and accepted. ✘

n Dimensional Control verification completed and accepted. ✘

n Pressure testing / Hydrostatic testing / Leak testing completed and accepted. ✘

n Final coating completed and accepted. ✘

n Final Preservation Completed (Lay up, Nitrogen Purging, Covering Protection etc.) ✘

n All NCR's and CAR'S close out verification completed. ✘

n All Inspection Test Record (ITR) Certifcates signed off. ✘

n Punch list if any generated. ✘

n Final visual inspection completed and accepted. ✘

Released for :


Painting Testing Released for Erection Transfer to Other facility

Post Weld Heat Treatment Others Specify

REMARKS :

Punch Comments:-

CONTRACTOR EMPLOYER
LEL PRODUCTION LEL QC
(Seaway 7) (Seagreen)
NAME : JESWIN JOHN

DESIGNATION : QC Inspector

SIGNATURE :

DATE : 15-Sep-2021 15-Sep-2021

Form : 20/2101/HAM/QC/F/015 Page 1 of 2


Rev. : 0
Date : Oct.2020
PUNCH LIST
CLIENT: SEAWAY 7 / SEAGREEN JOB: CN/20/2101 DATE: 31.5.21
PROJECT: SEAGREEN OFFSHORE WIND FARM DISCIPLINE: STRUCTURAL

Ref : RFI COMPLETED CHECKED BY


SL. NO. DESCRIPTION RESPONSIBILITY CATEGORY COMMENTS
No DATE
LEL QC DATE CLIENT DATE TPI DATE

Joint No: 2, Item No: C2U-3-LG-1-Node can, along with Leg Stubs & Ring Plate to
CN/20/2101- 20-201-HAM-IRN-
1 be installed at erection Weld Map No: 20-2101-EN-S-WD-CL2-6008 Sheet 01 0f QC B
EXT005602 0902
03

Form : 20/2101/LGQCF021
Rev. : 0
Date : June. 2020