Ati Manila South Harbour Expansion Project: Eib Reclamation Monthly Report No. 4 - APRIL 2019, MPR - 004
Ati Manila South Harbour Expansion Project: Eib Reclamation Monthly Report No. 4 - APRIL 2019, MPR - 004
Ati Manila South Harbour Expansion Project: Eib Reclamation Monthly Report No. 4 - APRIL 2019, MPR - 004
Contractor : FF CRUZ & CO., INC. Variance -61.32% A.P. 25.68 Original Contract Value for Construction 612,023,852
Approved Variation Orders -
Contractual Milestones Var 74.32
Revised Contract Value for Construction 612,023,852
0 50 100
Effective Date : 26 Nov 2018 3.0 Resources Status 4.0 Health, Safety & Environment
Proj Completion : 25 April 2019
Proj Duration : 150 DAYS Indirect Manpower 27 Nos. Man-hours Worked (April 1 -30, 2019) 40,404 Hrs
Project Elapsed : 155 days Direct Manpower 50 Nos. Man-hours Worked (since Proj Start) 188,736 Hrs
Proj Days to Go : -5 days Lost Time Incidents (Since Proj Start) - Nos
Near Misses/Incidents Reported ( for this Month) - Nos
Total Resources Involved 77 Nos.
Description of Works 5.0 Monthly Progress Highlights 7.0 Monthly Progress Photos
Mobilization
The activities on this project covers the
● moblization 100% done
following activities:
Section 2 : Reclamation
It includes sandfilling works, installation
Construction
of primary and secondary rock armour,
PVDs And Geotextile ● As of April 30, 2019, 120,101 cumulative cu.m of sand were unload to the
offshore (Required cu.m 371,205.84, actual progress is 32.35%)
Section3: Monitoring And Instrumentation
● Continue dragflow operation
Section 4: Paving and Fencing ● Completion of rubbles and concrete disposal took from ATI Side and
It includes Temporary Terminal Fencing, were dumpled to Malabon and Navatos Dumping Area
pavement works and truckpave
Page 1of 1