Ati Manila South Harbour Expansion Project: Eib Reclamation Monthly Report No. 4 - APRIL 2019, MPR - 004

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

ATI MANILA SOUTH HARBOUR EXPANSION PROJECT : EIB RECLAMATION

Monthly Report No. 4 - APRIL 2019, MPR -004


Project Month No. 5
Projects Details 1.0 Progress/Schedule Status & Trend 2.0 Financial Status Php

Owner : ATI, DP WORLD Planned 87.00% Plan 100.0


PMC : AECOM Actual 25.68%

Contractor : FF CRUZ & CO., INC. Variance -61.32% A.P. 25.68 Original Contract Value for Construction 612,023,852
Approved Variation Orders -
Contractual Milestones Var 74.32
Revised Contract Value for Construction 612,023,852
0 50 100
Effective Date : 26 Nov 2018 3.0 Resources Status 4.0 Health, Safety & Environment
Proj Completion : 25 April 2019
Proj Duration : 150 DAYS Indirect Manpower 27 Nos. Man-hours Worked (April 1 -30, 2019) 40,404 Hrs
Project Elapsed : 155 days Direct Manpower 50 Nos. Man-hours Worked (since Proj Start) 188,736 Hrs
Proj Days to Go : -5 days Lost Time Incidents (Since Proj Start) - Nos
Near Misses/Incidents Reported ( for this Month) - Nos
Total Resources Involved 77 Nos.

Description of Works 5.0 Monthly Progress Highlights 7.0 Monthly Progress Photos
Mobilization
The activities on this project covers the
● moblization 100% done
following activities:
Section 2 : Reclamation
It includes sandfilling works, installation
Construction
of primary and secondary rock armour,
PVDs And Geotextile ● As of April 30, 2019, 120,101 cumulative cu.m of sand were unload to the
offshore (Required cu.m 371,205.84, actual progress is 32.35%)
Section3: Monitoring And Instrumentation
● Continue dragflow operation
Section 4: Paving and Fencing ● Completion of rubbles and concrete disposal took from ATI Side and
It includes Temporary Terminal Fencing, were dumpled to Malabon and Navatos Dumping Area
pavement works and truckpave

6.0 Areas of Concern

Page 1of 1

Unloading of Sandfill materials


As of April 30, 2019, 120,101 cumulative cu.m of sand were unload to the offshore
(Required cu.m 371,205.84, actual progress is 32.35%)
Identification of Long Lead Items=
CONTRACTOR to submit deliverables lists including all materials whose delivery
period is 5 weeks or more.
COMPANY RAISE CONCERN ABOUT SLOW PROGRESS FOR SUBMITTALS
AS PER EOT & ACTION PLAN the new dates for SHOP DRAWINGS on 21 APRIL
2015 And MATERIAL 28 MAR 2015
COMPANY inform CONTRACTOR that existing villa dismantling items list (with
GSD signature) should be submitted to GSD

COMPANY RAISED concern about delays in subcontractor approvals drawings &


materials approvals for swimming pool ,PQ submitted by DTF no 0272 on 23-2-
2015 also for ANTITERMITE its approved and LANDSCAPING to be done by EDICO

BOUNDARY WALL drawings submitted via DTF no 332 on 11-3-2015 approved B


on 18-3-2015,Design calculation submitted on 18-3-2015 via DTF 348. It was
resubmitted via DTF 433, DATED 07-04-2015 with received status C dated 12-
04-2015
Approved Senior Structural Engineer should attend the Progress Meeting
EDICO pointed outh that SPECIFICATION being used by the COMPANY
ENGINEERING TEAM is different for those issued to EDICO as part of CONTRACT
DOCUMENT DOSSIER and shall be provided to COMPANY ENGINEERING TEAM to
avoid further conflict to this effect