Guide To Good Commercial Refrigerant Practice

Download as pdf or txt
Download as pdf or txt
You are on page 1of 40
At a glance
Powered by AI
The document outlines best practices for installing commercial refrigeration systems including safety procedures, operative responsibilities, pipework installation and electrical work.

Safety precautions that should be taken include following risk assessments and method statements, taking general site safety measures, safety when brazing or welding, pressure testing, handling refrigerants, working in hazardous areas and positioning equipment.

Operatives are responsible for obeying site rules, ensuring work area safety and tidiness, using PPE safely, and prioritizing safety. They must also maintain a clean appearance and vehicle.

 

Guide to Good Commercial 
Refrigeration Practice   
 
 
 
    
Part 4 
System Installation 
 
 
 
 
 
 
 
 
 
 
British Refrigeration Association 
 
 
Institute of Refrigeration 
 
Issue 1 October 2008 
Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
 
CONTENTS 
4.0.0  GENERAL 
   
4.1.0  OPERATIVES RESPONSIBILITIES.   
               4.1.1  SITE RULES.   
               4.1.2  SITE CONDITIONS.   
               4.1.3  PROGRAMME OF WORK.   
               4.1.4  WORKMANSHIP.   
               4.1.5  LIAISON WITH CLIENT/ CO‐CONTRACTORS.   
               4.1.6      SITE REQUIREMENTS.   
 
4.2.0     HEALTH & SAFETY REQUIREMENTS. 
4.2.1      RISK ASSESSMENTS AND METHOD STATEMENTS   
             4.2.2    GENERAL SITE SAFETY.   
             4.2.3        SAFETY IN WORKING WITH OXY‐ACETYLENE BRAZING OR WELDING  
      EQUIPMENT        
             4.2.4    SAFETY IN PRESSURE TESTING.   
             4.2.5    SAFETY IN HANDLING REFRIGERANTS.   
             4.2.6    WORKING IN HAZARDOUS AREAS.   
             4.2.7        SAFETY REQUIREMENTS FOR UNLOADING AND POSITIONING OF PLANT     
        AND EQUIPMENT.   
             4.2.8    SAFETY IN POSITIONING OF ELECTRICAL EQUIPMENT.   
             4.2.9      SAFETY REQUIREMENTS FOR DRAINAGE.   
 
4.3.0  LOCATIONS AND POSITIONING OF PLANT AND EQUIPMENT.   
             4.3.1    GENERAL DETAILS.   
             4.3.2      SETTING DOWN PLANT AND EQUIPMENT. 
 
4.4.0  PIPEWORK ROUTING ARRANGEMENTS.   
             4.4.1         ROUTING OF PIPEWORK 
             4.4.2      PRESSURE EQUIPMENT DIRECTIVE (PED) 
   
4.5.0              PIPEWORK INSTALLATION. 
             4.5.1      LEAK PREVENTION   
             4.5.2    COPPER TUBING.   
             4.5.3    COPPER TO COPPER PIPEWORK FITTINGS.   
             4.5.4    COPPER ‐ FLARE AND THREAD FITTINGS.   
             4.5.5    COPPER ‐TYPES OF JOINT.   

British Refrigeration Association            Institute of Refrigeration   

Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
           
            4.5.6    COPPER ‐INSTALLATION OF LINE COMPONENTS.   
            4.5.7    COPPER ‐ PIPEWORK SUPPORT METHODS FOR COPPER PIPEWORK.   
            4.5.8    COPPER ‐ METHODS OF CUTTING TUBES.   
            4.5.9    COPPER ‐ PIPE OR TUBE BENDING.   
            4.5.10   COPPER ‐ BRAZING OF PIPEWORK.   
            4.5.11   PIPEWORK INSULATION.   
            4.5.12   STEEL & STAINLESS STEEL PIPEWORK.   
       
4.6.0  ELECTRICAL INSTALLATION WORK.   
             4.6.1    CABLES AND WIRING SYSTEMS.   
             4.6.2    MAIN SUPPLIES.   
             4.6.3    INTERCONNECTING WIRING AND CABLE ROUTE.   
             4.6.4    CABLE SIZING AND VOLTAGE DROP.   
             4.6.5      EARTHING AND TESTING. 
   
4.7.0  CONDENSATE DRAINAGE.   
             4.7.1    CONDENSATE SYSTEM AND MATERIALS.   
             4.7.2    GRAVITY DRAINAGE.   
             4.7.3      PUMPED CONDENSATE DRAINAGE. 
   
4.8.0              PRE‐COMMISSIONING SYSTEM TESTING AND   PREPARATION. 
 
4.9.0              DRAWINGS 

4.10.0             APPENDICES  
 
   

British Refrigeration Association            Institute of Refrigeration   

Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
 
4.0.0     GENERAL 
 
The  appearance  of  the  refrigeration  installation  engineer/operative  and  their  attitude  to 
clients, colleagues and co‐contractors,  is of  great  importance in presenting the image of a 
company.  He/she  should  present  themselves  in  a  pleasant  manner  ensuring  they  are 
wearing  clean  and  tidy  work‐wear  at  all  times.    Users  of  company  vehicles  should  ensure 
these are kept in a clean and tidy condition. 
 
4.1.0  OPERATIVES RESPONSIBILITIES ON SITE 
 
4.1.1  SITE RULES 
 
Installation Operatives are responsible for: 
 
• obeying any site rules and safety regulations that may be in force 
 
• ensuring the safety and tidiness of their work area 
 
• for using in a safe manner any personal protective equipment or safety equipment 
that has been made available for their use. 
 
• working with safety as a prime consideration at all times 
 
4.1.2  SITE CONDITIONS 
 
All working areas are to be kept clean tidy, only sufficient materials for the work in progress 
at the time are to be allowed in the working area.  Other materials are to be stored in a safe 
area agreed with client/principal contractor. 
 
Prior  to  hand  over,  operatives  should  ensure  that  their  working  areas  have  been  cleaned 
and tidied to a reasonable standard. 
 
All  debris  etc.  should  be  removed  from  site  or  deposited  in  designated  areas  on  site.  
Particular  attention  should  be  paid  to  plant  room  plenum  chambers,  the  tops  of 
coldrooms/coldstores, and the undersides of display cases.  Care should be exercised with 
the disposal of waste materials and substances, see the Environmental Protection Act 1990, 
Duty of Care, section 34, and the company’s waste disposal procedures both which should 
be complied with. 
 
4.1.3  PROGRAMME OF WORK 
 
Installation operatives should ensure they are familiar with the programme of works agreed 
with  client/principal  contractor,  for  which  they  are  responsible.    They  should  make  every 
effort to ensure the programme is maintained.  Operatives will be required to give progress 
reports as and when required by their manager or the project engineer. 
 

British Refrigeration Association            Institute of Refrigeration   

Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
 
In  the  event  of  major  unforeseen  problems  on  site,  the  engineer  should  contact  their 
management immediately to ensure difficulties are dealt with quickly and efficiently. 
 
Operatives should record and report to their manager any verbal on site instructions given 
by the client/principal contractor. 
 
4.1.4  WORKMANSHIP 
 
Operatives should be qualified and competent, able to demonstrate that all work is carried 
out  to  the  best  of  their  ability  and  in  accordance  with  the  guidelines  laid  down  in  these 
procedures. 
 
4.1.5  LIAISON WITH CLIENT / CO‐CONTRACTORS 
 
Contact  with  the  client,  principal  contractor,  or  the  other  co‐contractors  should  be 
maintained at the highest levels by the company’s personnel.  
 
4.1.6  SITE REQUIREMENTS 
 
Site operatives must ensure that the following requirements are maintained at all times: 
 
• Contact client or principal contractor when first arriving at site. 
 
• Sign in and out of site on a daily basis. 
 
• Keep  client/principal  contractor  informed  of  your  work  programme  and  safety 
requirements which may affect other people. 
 
• Do not work in a manner which may affect the health and safety of you and/or that 
of other workers, or members of the general public. 
 
• Report  any  accident  or  incident  to  your  supervision  and  to  the  client/principal 
contractor,  and  see  that  details  are  entered  in  Site  Accident  Book  and  Company 
Accident Book. 
 
• Do not use, or interfere with, any malfunctioning work equipment; report it to your 
supervisor so that it can be replaced. 
 
• Compliance  with  Permits  to  Work  e.g.  hot  works,  fire  alarm  isolation,  electrical 
isolation, restricted access, etc 
 
• Maintain a site diary including a H&S file covering attendance record, site induction 
record,  induction  of  risk  assessments  record,  H&S  training  and  any  Tool  box  talk 
records 
 
 
British Refrigeration Association            Institute of Refrigeration   

Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
 
4.2.0   HEATH AND SAFETY REQUIREMENTS 
 
4.2.1  RISK ASSESSMENTS & METHOD STATEMENTS 
 
For all site work to  be  completed by  operatives, risk assessments  and method statements 
covering activities required and substances to be used are to be completed and submitted 
within  the  site  safety  plan  prior  to  commencement  of  any  work.  All  operatives  should  be 
inducted so fully understand the requirements and able to comply with the site safety plan. 
For  guidance  refer  to  British  Refrigeration  Association’s  publication  “Task  Procedures  and 
Risk Assessments 
 
4.2.2  GENERAL SITE SAFETY 
 
Certain safety rules apply to all sites, some of the more important ones, but not all of them, 
are: 
 
• Operatives  should  wear  or  use  appropriate  Personal  Protective  Equipment  at  all 
times while they are on site. 
 
• Work  areas  should  be  kept  in  a  tidy  condition  and  all  hazards  removed  as  far  as 
practicable.    Where  any  hazards  remain,  a  risk  assessment  should  be  made  and 
control methods employed to reduce the risk e.g., safe systems of work, safety signs 
etc.    If  certain  work  processes  are  going  to  affect  others  working  in  the  area,  they 
should  be  advised  and,  if  necessary,  the  area  cleared  before  work  is  allowed  to 
commence. 
 
• Permits  to  Work.    In  certain  areas  where  hazardous  situations  can  arise,  a  system 
known as a “Permit to Work” may be required.  Operatives should be aware of this 
requirement and check with the site management before commencing work in any 
of the following situations: 
 
(i)  Working at height,  
(ii)  Work involving hot work, (brazing). 
(iii)  Working with abrasive wheels. 
(iv)  Working with hazardous substances, (where this may affect others in 
work). 
(v)  Working in confined spaces. 
(vi)  Working on live electrical equipment. 
 
Further details on Permits to Work can be located in the British Refrigeration Association’s 
publication Task Procedures and Risk Assessments. 
 
Permits to work are usually administered by the client or principal contractor. It is prudent 
to  train  operatives  to  be  able  to  administer  a  self‐raising  permit  allowing  them,  and  the 
client or principle contractor to sign, particularly when small work is involved and/or site  
 

British Refrigeration Association            Institute of Refrigeration   

Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
 
management does not have a permit system in place. Some Contractor’s company warranty 
insurance may become invalid if permit is not in place prior to commencement of work.  
 
• Safe  storage  of  materials  and  equipment.  Before  work  has  commenced  on  site, 
arrangements  should  be  made  with  the  client/principal  contractor  for  the  storage  of 
materials to be used for the installation, together with any work equipment which may 
be used. Hazardous chemicals, gases, etc. need to be stored in a secure, well ventilated 
area  away  from  the  normal  working  areas  of  the  site.  Only  sufficient  materials  for  the 
work  in  progress  should  be  maintained  within  the  work  area.  Likewise  any  hazardous 
materials or equipment should be removed from the area at the end of the working day.  
 
4.2.3  SAFETY IN WORKING WITH OXY‐ACETYLENE, BRAZING OR WELDING EQUIPMENT 
 
Oxy‐Acetylene  equipment  presents  many  safety  problems  if  not  used  or  maintained 
properly.  Following are the requirements for satisfactory use and operation: 
 
• Cylinders  to  be  secured  to  a  purpose  built  trolley  mounted  in  a  vertical  position, 
when in use. 
 
• Equipment  should  be  visually  checked  at  the  beginning  of  each  working  day  for 
damage, malfunction and leaks etc. 
 
• Anti‐flash back arrestors must be fitted to equipment at all times and changed every 
5 years. 
 
• Do not use lines longer than are necessary to reach inaccessible work areas, (assess 
if the cylinder trolley can be moved to a nearer location). 
 
• Use  appropriate  Personal  Protective  Equipment  including  heat  resistant  gloves, 
goggles and arm protection, as necessary. 
• Ensure  adequate  ventilation  to  the  work  area.    If  necessary  additional  ventilation 
must be made available. 
 
• Check  that  suitable  fire    precautions  are  taken  and  that  fire  extinguishers  are 
available ready for use. 
 
• Purge both oxygen and acetylene lines before lighting up. 
 
• Always uncoil lines fully, do not coil excess hose around cylinders or regulators. 
 
• Move  cylinders  only  using  an  appropriate  trolley.    Never  transport  cylinders  with 
regulators and hoses attached unless on a purpose‐designed trolley or carrier. 
 
 
 

British Refrigeration Association            Institute of Refrigeration   

Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
 
• During carriage of cylinders by road.  Ensure all concerned are aware of which gases 
are  being  carried  and  which  are  flammable,  toxic  or  corrosive  by  displaying 
appropriate safety signs. 
 
• Ensure that relevant safety data, TREM Cards and COSHH sheets are carried for each 
type of gas or substance.  This information must be available in an emergency and 
visible in the driving compartment. 
 
• Make  sure  cylinders  are  properly  loaded  and  secured  so  that  they  cannot  move 
about.  Ensure all gauges and lines etc, are removed. 
 
• Do not smoke or ignite flammable materials.  Oxy‐acetylene equipment is subject to 
examination annually by a competent person. 
 
4.2.4  SAFETY IN PRESSURE TESTING 
 
The  main  safety  requirements  for  the  pressure  testing  of  refrigeration  systems  are:    That 
access  to  the  area  where  the  testing  is  being  carried  out  should  be  restricted  to  the 
personnel concerned with the testing. Oxygen Free Nitrogen (OFN) used for the testing must 
be  introduced  into  the  system  via  a  steel  braided  hose.  (Demanded  on  the  majority  of 
construction  sites  giving  resistance  to  kinking  and  damage  by  possible  third  parties)      Any 
pressure  gauges  used  for  reading  the  system  pressure  must  be  fitted  remote  from  the 
charging line, (no refrigeration lines to be used for charging the OFN).  
 
In  addition  to  system  integrity  pressure  testing  there  is  a  requirement  for  leak  tightness 
testing.  This  is  usually  carried  out  with  lower  pressures.  The  distinction  between  the  two 
tests is covered in section 4.8.0. A good practice guide is the IOR Service Engineers Guide 24 
– Leak Tightness Testing. 
 
For further guidance and compliance refer: BS EN 378‐2:2008 'Pressure Requirements and 
Pressure Vessels’ ‐‐ BRA Task Procedure Risk Assessment R10 covering Pressure Testing of 
Refrigeration Pipe‐work Systems ‐‐ HSE GN4 Safety in Pressure Testing ISBN0717616290. 
 
4.2.5  SAFETY IN HANDLING REFRIGERANTS 
 
The  deliberate  venting  of  refrigerants  to  the  atmosphere  has  been  prohibited  since  1990, 
under  the  terms  of  the  Environmental  Protection  Act.    This  is  because  of  the  affect  that 
HFC’s and other refrigerants have on Global Warming and Ozone Depletion. This has led to 
the  introduction  of  the  Safe  Handling  of  Refrigerant  Assessments  for  operatives  installing, 
servicing and maintaining refrigeration equipment and systems. 
 
It is a legal requirement that all operatives handling HCFC and HFC refrigerants are trained 
and their competence demonstrated by obtaining C&G 2078, (At appropriate time through 
UK  legislation  C&G  2078  will  be  superseded  by  C&G  2079)  or  CITB  qualification.  All 
operatives with one of these qualifications should then register with ACRIB (Air  
 

British Refrigeration Association            Institute of Refrigeration   

Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
 
Conditioning, Refrigeration  Industry Board) to allow Clients and End‐Users access to check 
credentials 
 
It  is  highly  recommended  that  operatives  do  not  handle  any  refrigerant  including 
hydrocarbon,  carbon  dioxide,  or  ammonia  without  proper  training  and  the  ability  the 
demonstrate competence 
 
 4.2.6  WORKING IN HAZARDOUS AREAS 
 
As  previously  mentioned  in  4.2.1,  working  in  hazardous  areas  usually  requires  a Permit  to 
Work system.  Operatives should check before commencing work to see if such a system is 
required.    Further  information  on  working  in  hazardous  areas  can  be  found  in  the  British 
Refrigeration Association's Task Procedures and Risk Assessments. 
 
4.2.7  SAFETY REQUIREMENTS FOR UNLOADING AND POSITIONING OF PLANT AND EQUIPMENT. 
 
Before delivery of the main items of refrigeration equipment for a project, a thorough site 
survey needs to be carried out to ensure both a safe and level area is available for unloading 
to take place, and clear unobstructed routes can be found to the final positions where the 
equipment is to be installed. 
 
Where  lifting  operations  to  high  levels  are  required,  these  are  normally  carried  out  by  a 
mobile  crane  (usually  hired  for  the  occasion).    The  responsibility  for  the  operation  and 
movement  of  the  crane  rests  with  the  operator,  but  the  user/hirer  needs  to  assure 
themselves  that  all  the  appropriate  regulations  and  codes  of  practice  are  being  complied 
with.  Crane operator should make available prior to commencement of work a completed 
Risk Assessment with method statements 
 
The  final  positioning  of equipment  (e.g,  refrigeration  packs,  condensing  units,  condensers, 
cabinets, etc.) often comes down to manual handling by a team of workers.  Care should be 
exercised  at  all  times  if  injury  is  to  be  prevented.    It  is  important  that  all  members  of  the 
team understand  how  and when to lift. Risk Assessments with  method statements should 
be completed prior to commencement of work, for further information of lifting operations 
refer to the BRA Task Procedures and Risk Assessments. 
 
4.2.8  SAFETY IN POSITIONING OF ELECTRICAL EQUIPMENT 
 
During the design stage of the project, in order to allow sufficient access for servicing and 
maintenance  purposes,  thought  must  be  given  to  the  positioning  of  items  of  equipment 
such  as  packs,  electrical  control  panels.    The  Electricity  at  Work  Regulations  requires  a 
minimum  of  1  metre  clear  space  to  the  front  and  the  sides  for  persons  working  on  live 
electrical equipment. 
 
 
 
 

British Refrigeration Association            Institute of Refrigeration   

Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
 
4.2.9  SAFETY REQUIREMENTS FOR DRAINAGE 
 
Again at the design stage it must be ensured that a suitable drainage system is available in 
which  to  discharge  the  condensate  from  evaporators.    This  applies  particularly  to 
refrigerated cabinets using secondary refrigerants.  These require a special drainage system, 
where filters and scrubbers prevent discharge of pollutants into the sewage system. 
 
 4.3.0  LOCATIONS AND POSITIONING OF PLANT AND EQUIPMENT 
 
4.3.1  GENERAL DETAILS 
 
In  many  cases  the  location  of  the  refrigeration  plant  for  a  project  will  have  already  been 
decided  before  commencement  of  work  on  site.    It  is  the  designer’s  responsibility  under 
CDM Regulations to assess the situation and to stress to the client his responsibilities under 
Health & Safety Law (e.g., PUWER: 1998, CDM: 2007, and the Health & Safety at Work Act: 
1974,  etc.).    Account  should  be  taken  of  any  access  problems  which  may  arise  for 
maintenance, service and decommissioning, noise problems when plant is running, also the 
plant or equipment must have adequate ventilation and weather proofing.  
 
In  the  case of  “small  works”,  where  a  designer  has  not  been  employed,  or  the  work  does  
not fall within the requirements of CDM: 2007, the “Installation Engineer” may be required 
to select the locations/positions for such items as condensing units, air cooled condensers, 
pumps,  control  panels  etc.,  and  agree  these  with  the client.    The  following  good practices 
are recommended: 
 
• Care must be taken to ensure condensing equipment is sited in a well ventilated 
area with adequate weather protection. 
 
• Do not site condensing equipment in roof wells.  In hot weather these will form a 
heat trap and effect the operation of the equipment (e.g. high head pressure and 
nuisance tripping of HP switch). 
 
• When  choosing  the  location  and  position  of  refrigeration  and  air  conditioning 
equipment,  thought  needs  to  be  given  to  access  for  service  and  maintenance 
purposes.    E.g.,  how  can  heavy  items,  such  as  compressors,  be  brought  in  and 
out?  Is there enough space around the equipment for a person to work safely?  
Too  often  end  users  want  equipment  to  be  installed  where  service  technicians 
are  placing  themselves  in  hazardous  situations  in  order  to  carry  out  service  of 
maintenance operations.  Reference to CDM Regulations and the Health & Safety 
at Work Act is recommended. 
 
• Adequate weather protection must be provided, either in the form of individual 
housings  or  purpose  built  plant  rooms,  for  packs  or  racked  condensing  unit 
systems.  Further information on this can be found in Section Two ‐ Design. 
 
 

British Refrigeration Association            Institute of Refrigeration   
10 
Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
 
4.3.2  SETTING DOWN PLANT AND EQUIPMENT 
 
Refrigeration  equipment  needs  to  be  set  down  on  adequate  surfaces  or  fixing  points,  to 
prevent problems of noise, vibration, and leakages of refrigerant at a later stage in the life of 
the plant.  The following points need to be observed to achieve this: 
 
• Bases  should  be  constructed  from  concrete  wherever  possible,  and  have  a 
smooth and level surface on which the equipment is to sit. 
 
• If equipment is to be situated on a wooden floor, insulation material such as cork 
or fire retardant composite board should be placed between the equipment and 
the floor. 
 
• Wherever  possible,  it  will  be  an  advantage  to  supply  and  fit  proprietary  anti‐
vibration mounts. 
 
• Where  equipment  is  situated  on  cantilever  wall  brackets,  ensure  that  the 
construction of the wall is such that it will support the weight of the brackets and 
the equipment. 
 
• In  outside  locations,  the  surface  of  the  base  needs  to  be  raised  above  ground 
level by at least 100 mm to prevent flooding in storm conditions. 
 
• Wherever possible, equipment should be fixed firmly to the surface on which it is 
located.    Equipment  situated  at  height  (i.e.  on  wall  brackets), should  always  be 
fixed in order to prevent movement. 
 
4.4.0  PIPEWORK ROUTING ARRANGEMENTS 
 
4.4.1  ROUTING OF PIPEWORK 
 
The route of the pipework between the evaporator and the condensing unit or compressor, 
and remote condenser, should be as direct and as short a distance as possible. All pipework 
should  be  designed  and  installed  to  give  liquid  and  oil  a  “drain”  flow  with  no  traps.  Traps 
should only be used to obtain oil entrainment in vertical risers. Traps and bends which can 
create pressure drops in the system should be kept to a minimum. 
   
  Consideration  should  be  given  to  allow  for  expansion  in  long  lengths  of  discharge  line. 
Distortion due to expansion can cause working of joints at the connection points leading to 
refrigerant leaks 
 
Wherever  possible,  pipework  should  utilise  “pulled”  bends  and  sets  using  patented 
mechanical  tube  bending  equipment.    The  use  of  manufactured  elbows  produces  greater 
pressure drops when the system is operating. 
 
 
British Refrigeration Association            Institute of Refrigeration   
11 
Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
 
4.4.2  PRESSURE EQUIPMENT DIRECTIVE (PED) 
 
Pressure  Equipment  Directive  (PED  97/23/EC)  covers  a  number  of  areas  with  regard  to 
refrigeration  and  air  conditioning  piping  and  vessels.  Engineers  may  require  assessment 
qualifications  to  be  able  to  complete  brazing  e.g.  BRA  –  Jointing  of  Copper  Pipework  for 
Refrigeration Systems, or equivalent/better alternative. Refer paragraph 4.5.9 
  PED  requires  systems  operating  with  0.5  bar  and  greater,  that  design  processes  and  site 
work methods demonstrate compliance with the regulations and hence the safety pressures 
declared  for  that  system.  Dependent  upon  the  system  declared  safety  pressures  and  into 
which category of certification this fall, there may be a requirement for elements of design 
and  site  work  methods  to  be  assessed  and  approved  by  a  “Notifiable  Body”.  These  are 
organisations  that  are  responsible  for  setting  standards  or  auditing  to  standards  such  as 
insurance companies’ e.g. Lloyds or in standards, BSI. Design documentation and site work 
instructions should state if the system is subject to Notifiable Body attendance to audit and 
approve compliance  
 
4.5.0  PIPEWORK INSTALLATION 
 
4.5.1   LEAK PREVENTION 
 
  F‐Gas Regulations 842/2008 details requirements for refrigerant containment. Pipework and 
component  installation  is  a  major  process  where  following  recommended  industry  good 
practice  in  conjunction  with  current  codes  and  regulations  should  give  a  system  that  is  at 
least risk to leak. Specifications and processes along with reference to codes and regulations 
are covered in the following paragraphs with the aim of achieving a leak tight system 
 
4.5.2  COPPER TUBING 
   
  With  the  introduction  of  refrigerants  that  operate  at  higher  pressures  care  is  necessary 
when considering the strength of the copper tube to be used. Design documentation should 
show  tube  sizes  with  wall  thickness  and  these  should  be  checked  prior  to  commencing 
installation. 
 
  To  conform  to  EN378:2008  the  majority  of  copper  tube  suppliers  now  label  tubing  by 
marking to the external surface or the tubing is supplied certificated. 
   
  For  practical  help  to  ensure  the  correct  pipe  wall  thickness  is  used  for  the  appropriate 
refrigerant two guides are available with selection tables: 1) BRA Fact finder no7 A Guide to 
Selecting Copper Tube and Fittings for New Refrigeration and Air Conditioning Systems. 2) 
IOR Service Engineers’ Section Datasheet no 4 Copper Pipe Wall Sizing and New Refrigerants 
 
  Copper tube used for refrigeration systems must conform to the following specifications:  BS 
EN12735‐1  These  specifications  cover  seamless  (Refrigeration  &  Air  Conditioning  Grade) 
copper tubing in soft, half hard, and hard tempers, it is normally available sizes listed below 
(all based on Outside Diameters ‐ OD):‐ 
 

British Refrigeration Association            Institute of Refrigeration   
12 
Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
 
Soft Drawn 
U

 
1/8”, 3/16”. 1/4”, 3/8”, 1/2”, 5/8”, 3/4”, 7/8” ‐ in 6 metre and 15 metre coils. 
 
Half Hard Temper 
U

 
3/8”, 1/2”, 5/8”, 3/4”, 7/8”, 1 1/8”, 1 3/8”, 1 5/8”, 2 1/8” ‐ in 3 metre and 6 metre lengths. 
 
Hard Temper 
U

 
2 5/8”, 3 1/8”, 3 5/8”, 4 1/8” ‐ in 3 metre and 6 metre lengths. 
 
All  refrigeration  grades  copper  tubing  is  marketed  as  clean,  dehydrated  and  sealed  at  the 
ends. 
 
4.5.3  COPPER TO COPPER PIPEWORK FITTINGS 
 
There are several ranges available.  Again these fittings are manufactured specifically for the 
refrigeration  industry  and  are  based  on  OD  sizes.    These  fittings  are  used  to  join  various 
lengths and sizes of copper tube together, thus forming the pipework system.  The method 
of joining is by manual flame brazing.  These fittings conform to ASME D16.22.‐1995. 
 
Types of fittings are:‐ 
 
• Long Radius Elbows 
• Short Radius Elbows 
• Tee Pieces (Equal and reducing) 
• Couplings (Equal and reducing) 
• Reducing Elbows 
• 45° Elbows 
• Caps 
• Return Bends 
• “P” Traps 
 
4.5.4  COPPER ‐ FLARE AND THREAD FITTINGS 
 
For the smaller sizes of soft drawn pipework a range of brass flare fittings are available. The 
use  of  these  should  be  kept  to  a  minimum  due  to  their  susceptibility  to  leakage  of 
refrigerant and the effects this has on the environment.  These fittings conform to SAEJ513. 
 
4.5.5  COPPER ‐ TYPES OF JOINT 
 
There  are  many  ways  of  joining  copper  pipework  for  refrigeration  systems.    Some  of  the 
more common ones are listed and explained here: 
 

British Refrigeration Association            Institute of Refrigeration   
13 
Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
 
• Flared Joint:  These joints should only be used where other means of jointing are 
impractical  due  to  the  weakness  of  this  type  of  joint  and  the  environmental 
impact of refrigerants. This is achieved by the use of a flare nut for the respective 
size of pipe (1/4” OD, 1/2” OD, etc.) being slipped over a prepared end of copper 
tube.    The  end  of  the  copper  tube  is  then  flared  outward  to  an  angle  of 
approximately  45°.    The  flare  nut  is  then  connected  to  a  flared  fitting  or 
component, forming a vapour proof joint. 
 
• Swaged Joints:  Swaging of joints in copper pipework permits two pieces of tube 
of the same diameter to be joined together without the use of fittings, it being 
more  convenient  to  braze  one  joint  than  two  with  the  use  of  connectors  and 
improves  risk  against  leakage.  Less  joints,  less  leaks,  containment  being  the 
major requirement of the F‐Gas regulations. 
 
To  achieve  a  swaged  joint,  one  piece  of  tubing  is  swaged  out  to  the  outside 
diameter of the other piece.  As a general rule the length of overlap should equal 
the outside diameter of the tube. 
 
Generally the use of swaged joints in copper pipework is acceptable, however on 
the  larger  sizes  there  is  a  possibility  of  thinning  the  wall  of  the  tube,  thereby 
leading  to  problems  of  leakages  later.    Therefore  the  maximum  size  of  pipe 
where swaging is acceptable is 1 5/8".  All pipework above this diameter shall be 
joined  using  standard  copper‐to‐copper  couplings.    Two  types  of  swaging  tools 
are  commonly  used;  the  punch  type  for  smaller  diameter  tubes  and  the 
mechanical expander type.  With both types, different tool sizes are available for 
use with the many sizes of copper tubing.  The swage is then brazed to achieve a 
leak proof joint.  See also Section 10 sub‐section 29 relating to pulled tees. 
 
• Flanged  Joints:    Where  pipework  has  to  bolt  onto  items  of  equipment,  such  as 
compressors,  a  flange  joint  is  used.    The  actual  joint  being  formed  by  a  gasket 
which sits between the two flanges, thus forming a leak proof joint.  The jointing 
of the copper pipework to the flange is achieved by brazing. 
 
• Lok‐Ring:  Brass  Lokring  fittings  are  now  available  to  suit  refrigeration  and  air 
conditioning pipework up to 7/8”. Designed for working pressures up to 50 bar 
and  therefore  a  preferred  acceptable  alternative  to  brazing  particularly  in 
locations  where hot works is prohibited  
 
 4.5.6  COPPER ‐ INSTALLATION OF LINE COMPONENTS 
 
Before  any  components  are  fitted  into  a  refrigeration  system  it  is  important  that  the 
installer understands where within the system they have to be fitted, the correct methods 
to  be  used  to  fit  them  and  the  correct  orientation  for  satisfactory  operation.    Further 
information on various components of the refrigeration system can be found in Section 2. 
 
 
British Refrigeration Association            Institute of Refrigeration   
14 
Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
 
4.5.7  COPPER ‐ PIPEWORK SUPPORT METHODS FOR COPPER PIPEWORK 
 
Numerous  methods  of  fixing  have  been  developed  over  the  years  because  of  the  many 
situations  in  which  refrigeration  pipework  is  installed..    It  is  important  to  survey  the  site 
thoroughly  before  work  on  site  commences.    This  enables  the  route  for  the  pipework  be 
established  with  others  (e.g.,  Client/Co‐contractor  etc.)  and  the  methods  of  fixing 
confirmed. 
 
All piping should be adequately supported, the supports or hangers being sized to carry the 
weight  of  the  pipe  including  the  contents,  and  where  required  the  insulation.  The 
recommended distance between supports is as follows: 
 
COPPER PIPE SIZES  MAX, SPACING OF SUPPORTS 
(mm)  (inch)                         (m) 
                                     
15‐22  1/2 ‐ 7/8 soft drawn                           1 
22‐54  1/2 ‐ 2 1/8 half hard    2 
54‐67  2 1/8 ‐ 2 5/8 half hard    3 
 
Pipework  for  installation  may  involve  routing  through  floor  ducts  or  fastened  to  walls  or 
ceiling, or at high level on supports suspended from roof purlins or rafters.  Following are 
recommended methods of fixing for the various situations. 
 
• Floor Ducts:  Where ducts have been formed to take the refrigeration, electrical or 
plumbing services to a refrigerated fixture, or group of fixtures, there is normally no 
need for clipping or fixing of pipework.  It is laid in the bottom of the duct resting on 
load  bearing  insulation  materials.    Care  needs  to  be  taken  to  ensure  that  the 
pipework  does  not  foul  the  corners  of  the  ducts,  or  the  other  services  where 
crossovers  of  these  occur.    Cradles  need  to  be  made  in  order  to  prevent  chaffing.  
Where ducts hold a number of pipes and double stacking is necessary, load bearing 
insulation needs to be placed between the layers of pipework. 
 
• Fixing to Walls and Ceilings:  If pipework has to run up or down a wall, or traverse a 
ceiling, several methods of fixings are available as follows:‐ 
 
a)  Pipe  clips:  Where  pipework  for  a  single  system  is  involved,  the  suction  and 
liquid lines are fixed directly to the wall by  means  of pipe saddles clamping 
over each of the pipes.  As most suction lines are insulated, a saddle that is 
slightly  smaller  than  the  outside  diameter  of  the  insulation  needs  to  be 
selected.    This  enables  the  pipework  to  be  held  satisfactorily,  with  only  a 
slight indentation of the insulation material. 
 
b)  Cable  Trays:    The  use  of  cable  trays  allows  for  a  tidy  fixing  of  pipework, 
particularly where a large number of pipes have to be run.  The tray, which 
can be obtained in standard sizes from 50 mm up to 60 mm, is fixed to the  
 

British Refrigeration Association            Institute of Refrigeration   
15 
Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
 
wall or ceiling with a spacer between the tray and the surface.  The pipework, 
and/or electrical services, are then clipped to the tray by means of special  
 
nylon  ties.    Again,  care  must  be  exercised  in  fixing  suction  lines  to  ensure 
insulation around the pipe is not distorted, and the vapour seal is not broken.  
The  advantages  of  using  cable  tray  are  that  it  gives  the  installation  a  tidy, 
professional  look,  and  enables  the  vapour  seal  on  suction  lines  to  be 
maintained  by  gluing  the  lengths  of  insulation  end  on  end.    It  is  important 
that  where  exposed  copper  pipework  is  run  on  galvanised  cable  tray  some 
means  of  insulating  the  pipework  from  the  tray  is  used.    This  prevents 
electrolytic action and corrosion. 
 
c)  Proprietary Fixing Systems:   There are a number of fixing systems available.  
These systems are very adaptable and can be used to fix or support single or 
multiple  pipework  systems,  whether  fixed  to  a  surface  or  suspended  from 
rafters  or  purlins.    The  pipework  is  fixed  by  means  of  insulated  clamps  to 
support  brackets  cut  and  assembled  on  site  to  suit  the  particular 
requirements. 
 
Reference should be made to suppliers’ literature for fixing materials and insulation 
for further information. 
 
4.5.8  COPPER ‐ METHODS FOR CUTTING TUBE 
 
To cut copper tube either a hacksaw or tube cutters may be used.  Wherever possible tube 
cutters should be used, the tubing should be cut squarely (90°).  After the tubing has been 
cut the ends of the pipe must be reamed and scraped, in order to remove any sharp burrs 
on the inside and ends of the tube.  If tube cutters are unavailable or inappropriate and a 
hacksaw  has  to  be  used,  a  wave  set  blade  of  32  teeth  per  inch  is  recommended.    It  is 
important that filings or chips of any kind do not enter the pipework.  
Whenever pipework is left with an exposed or unconnected end it needs to be sealed with a 
suitable cap to prevent the ingress of moisture, dust etc. 
 
4.5.9  COPPER ‐ PIPE OR TUBE BENDING 
 
As explained in 4.4.1, wherever possible, refrigeration pipework should have any bends or 
sets  formed  by  means  of  mechanical  tube  bending  equipment,  this  makes  for  a  neater, 
more  professional  installation  and  reduces  the  possibility  of  pressure  drops  when  the 
system is working. 
 
There are several brands of mechanical tube bending equipment ranging from the smaller 
hand held lever type (sizes 1/4” ‐ 5/8” OD), to the larger hydraulically operated (sizes 7/8” 
OD ‐  2 1/8” OD). 
 
In order to achieve a consistent high standard of bends and sets in pipework, requires skill, 
accuracy in measurement and lots of practice.  If a bend is not formed satisfactorily the  

British Refrigeration Association            Institute of Refrigeration   
16 
Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
 
work  may  have  to  be  done  again  (i.e.  stretching  of  the  wall  of  the  tube,  under  or  over 
estimating the distances in which the pipework has to fit).  This leads to increased cost in 
both material and labour, therefore the following rules apply: 
 
• Measure very accurately the distance between the centre of the joint into which the 
pipework is going to fit, and the position where the outside of the bend is going to 
finish; add an extra half diameter of  the  pipe size to this measurement (1 1/8” OD 
pipe extra to measurement 9/16”.  Line up this measurement with the outside edge 
of  the  former.    Carry  out  the  forming  of  the  bend,  the  pipework  with  the  bend(s) 
formed should accurately fit into the space measured. 
 
• To  aid  the  forming  of  bends  and  sets,  lightly  oil  the  slipper  of  the  bending 
equipment.  This will help prevent ripples and scoring of the tube. 
 
4.5.10  COPPER ‐ BRAZING OF PIPEWORK 
 
Brazing  is  one  of  the  best  methods of  joining  together refrigeration pipework, it  produces 
strong, leak free joints, which stand up to the most extreme temperature conditions. 
 
Only  suitably  qualified  personnel  should  undertake  brazing,  e.g.  holders  of  BRA  Brazing 
Assessment  or  CITB  Assessment  or  an  appropriate  NVQ  including  this  activity  with 
assessment. 
 
Oxyacetylene  brazing  equipment  provides  the  best  means  of  achieving  this  with  the 
combined mixture  of  pure  oxygen and acetylene producing  a very  hot flame (no less  than 
600°C).  Brazing can be done relatively easily if the correct procedures are followed: 
 
• Thoroughly degrease and clean parts and joints to be brazed. 
 
• Support all parts and ensure the joints fit closely. 
 
• Apply  flux  recommended  for  the  brazing  alloy,  (if  a  flux  is  required).    Follow  the 
manufacturer’s instructions. 
 
• Heat  the  joint  evenly  to  the  recommended  temperature.    Keeps  the  torch  moving 
constantly in a circular motion. 
 
• Apply the brazing alloy to the heated joint, do not melt the alloy with the torch. 
• Allow the joint to cool. 
 
• Clean  the  joint  thoroughly,  using  warm  water  and  a  brush.    Ensure  all  flux  is 
removed. 
 
 
 

British Refrigeration Association            Institute of Refrigeration   
17 
Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
 
• Pass  oxygen  free  nitrogen  (OFN)  through  the  pipework  being  joined  while  the 
brazing operation is taking place, this will reduce the scale build up on the inside of 
the pipework. 
 
• Use only brazing filler alloys which comply with EN 1044. 
 
A  more  detailed  guide  to  the  brazing  of  refrigeration  pipework  may  be  found  in  the  BRA 
“guide  to  the  joining  of  copper  pipework  for  refrigeration  systems”.      The  person  carrying 
out  the  brazing  procedure  must  have  an  appropriate  brazing  assessment  qualification,  a 
legal requirement within the European F‐Gas regulations, and either be or be supervised by 
a person holding an F Gas qualification i.e. C&G 2079 or CITB equivalent 
 
4.5.11  PIPEWORK INSULATION 
 
All suction and hot saturated vapour defrost pipework must be fully insulated with the 
correct sized insulation material in order to prevent ice and condensation forming on the 
pipework.   
 
When the pipework has been successfully pressure tested, the joints in the insulation may 
then be glued together using an adhesive recommended by the manufacturer. 
 
4.5.12  STEEL & STAINLESS STEEL PIPEWORK 
 
General 
Carbon, Carbon Manganese, low alloy and Austenitic stainless steel pipe and fittings are 
regularly used within the refrigeration industry in particular for industrial ammonia systems. 
These materials correctly applied offer a robust pipe work system with high pressure 
integrity and are compatible with most refrigeration applications. 
Unless purchased in large quantities these materials are not available with the same level of 
cleanliness as found in refrigeration quality copper tube. 
Further processing such as acid pickling or abrasive blasting should be employed to remove 
the residue from manufacturing processes such a mill scale, protective lacquers and oxides. 
Where this is not practical the introduction of additional serviceable filters with valves as 
appropriate should be considered. 
 
Materials 
B

The material specification and grade shall be chosen with regard to the lowest temperatures 
either in operation or at standstill. The specification and wall thickness should be 
determined in accordance with an appropriate National or International standard such as BS 
EN 14276‐ Part 2 Pressure equipment for refrigerating systems and heat pumps. Piping. 
General requirements. 
Traceability of steel pipe and fittings can be achieved by the recording of their markings. 
These cast or heat numbers should then be cross referenced to the material test 
certification to verify that the materials are in compliance with the specification and grade. 
Test certificates should be to level 3.1B of BS EN 10204 Metallic materials.‐Types of  
 

British Refrigeration Association            Institute of Refrigeration   
18 
Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
 
inspection documents. Welding consumables that form part of the pressure containment 
envelope should also be controlled by batch number and supplied with certificates of 
conformity from the manufacturer. 
 
Stainless Steel 
B

Whilst stainless steel offers good low temperature ductility and corrosion resistance, it does 
distort, more than carbon steels, due to welding stresses and if these residual fabrication  
 
stresses are high they will cause stress fractures, particularly in thin wall materials. Also the 
process operating conditions and environment should be checked for certain corrosive 
elements such Acids, chlorides, bromine, cupric ions, ferric ions, sulphide ions etc that may 
cause corrosion. 
 
Dissimilar materials. 
Special consideration needs to be given to the possible combinations of dissimilar materials, 
their joining techniques and their operating environments. To prevent electrolytic action 
between reactive materials such as some grades of stainless steel and copper/brass a 
eutectic break should be considered. If joined by brazing the alloys of the brazing material 
will also have to be considered to avoid the elements leaching out of the joint by electrolytic 
action. Brazing and/or welding procedure specifications and qualifications were appropriate 
should identify the material combinations applicable. 
 
Pipe Connections 
B

The number of joints should be kept to a minimum and fusion welded joints used in 
preference to flanged or screwed connections. 
 
Welded Joints 
B

Welding should be carried out so far as practical in a controlled environment such as a 
workshop and if practical strength tested prior to final assembly on site. 
In situ ‘positional welds’ should be kept to a minimum and their location considered at the 
design stage to ensure adequate access for welding, cleaning, and inspection including non‐
destructive testing (NDE). 
As with all hot work extra care should be taken to remove flammable materials from the 
work area, task risk assessment carried out and cooling down (fire watch) periods observed. 
 
Joint design. 
Preference should be shown for multi‐pass full penetration butt‐welded joints due to their 
superior fatigue and brittle fracture resistance. Fillet welds should be avoided for low 
temperature and or cyclic service. 
 
Due to the difficulty of fabricating and achieving good joint geometry and distortion free 
welds, size on size, off‐set and tangential branch welds should be avoided unless special 
process conditions require their use. Proprietary weld fittings should be used where 
possible; these should be to an applicable standard such as BS 1640‐1:1962 Specification for 
steel butt‐welding pipe fittings for the petroleum industry. Wrought carbon and ferritic alloy 
steel fittings or equivalent. 

British Refrigeration Association            Institute of Refrigeration   
19 
Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
 
Welded end caps to BS EN 10253‐2:2007 should also be used for the termination of pipe and 
in particular headers. Where this is not possible the end closure should be formed from a 
material to an appropriate specification and it’s thickness calculated in accordance with 
PD5500: 2006 Specification for unfired fusion welded pressure vessels. The use an 
appropriate NDE technique should be considered to check the weld quality. 
Socket weld fittings to BS 3799:1974 Specification for steel pipe fittings, screwed and 
socket‐welding for the petroleum industry up to DN40 can assist in achieving correct pipe 
alignment and prevent contamination where access or site conditions are adverse. 
 
Weld Procedure Specifications 
B

An appropriate documented procedure should be produced to detail the material group (s) 
being joined, size range, joint geometry and tolerances, welding parameters and 
consumables specifications. Were either by contract or regulation these should be qualified 
by a United Kingdom Accreditation Service (UKAS) approved third party to an appropriate 
standard such as BS EN 15614‐1:2004 Specification and qualification of welding procedures 
for metallic materials. Welding procedure test 
 
Welding Operator Qualifications 
B

The welding operators competence should also qualified where required either by contract 
or regulation these should be qualified by a UCAS approved third party to an appropriate 
standard such BS EN 287‐1:2004 Qualification test of welders. Fusion welding. Steels. The 
extent of the qualification (s) should cover the range of materials, welding positions 
diameter range, welding process and wall thickness and checked that the validity has not 
time expired. 
 
Welding Processes 
B

Gas Tungsten Arc Welding (GTAW), sometimes referred to as TIG, Shielded Metal Arc 
Welding (SMAW) Oxyfuel Gas Welding (OGW) and Gas Metal Arc Welding (GMAW) 
sometimes called MIG are all commonly used. 
Care should be taken to efficiently remove flux and spatter expelled during the welding 
process. For single sided full penetration welds the GTAW (TIG) process should be 
considered to minimise the build up of oxides on the second side (inside) of the pipes. 
Stainless Steel, and elsewhere if required by the welding specification, will require an 
appropriate shielding gas to be purged thought the inside of the pipe to prevent 
unacceptable internal oxidisation and root weld defects. 
 
Detachable Joints, 
Flanges 
B

Flange materials and bolting should be appropriate for the temperature either in service or 
at standstill. Steel flanges should comply with BS EN 14276‐2 
Bolting should be to BS EN 1515‐1:2000 Flanges and their joints. Bolting. Selection of bolting 
or PD 5500:2006 
 
Gaskets, 
Flange gaskets should meet the requirements of BS EN 378:2008 and checked for 
compatibility with the refrigerant and lubrication oils used. 

British Refrigeration Association            Institute of Refrigeration   
20 
Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
 
Pipe Threads 
B

Taper threads should be restricted to DN40 and used to connect control, safety and 
indicating devices. The fittings should of the correct pressure rating to an applicable 
standard such as BS3799 Any sealing medium used should must be check with the 
manufacture for compatibility with the refrigerant and lubricating oils used. 
Threaded coupling welded to pipe should be checked for distortion and their threads chased 
out as appropriate. Small diameter < DN10 threaded fittings are vulnerable to damage from 
weld spatter and over tightening and care should be taken not to strip their threads. 
 
Steel Pipe Supports and Hangers 
B

All piping shall be adequately supported, the supports or hangers being designed to carry 
the weight of pipe including its contents and, where required, insulation.  Particular 
attention should be paid to pipe work that could operate full of liquid. 
 
The distance between supports depends on the size and service weight of the pipeline: a 
recommended maximum spacing for steel pipes is as follows: 
 
Steel pipe sizes  Max. Spacing 
  of supports 
DN  Horizontal  Vertical run 
run (m)  (m) 
15‐25  2  2.4 
32‐50  3  3.0 
65‐80  4.5  4.6 
100‐175  5  4.6 
200‐350  6  8.5 
400‐450  7  20.0 
 
 
4.6.0  ELECTRICAL INSTALLATION WORK  
 
GENERAL 
Refer  BS  EN378‐3:2008  Section  6  “Electrical  Installation”,  and  British  Refrigeration 
Association  Fact  Finder  No  11  titled  “Identification  of  Electrical  Conductors  in  Fixed 
Installations” 
 
Electrical work for the larger refrigeration installations (e.g. supermarkets, large coldstores, 
industrial  installations),  is  usually  carried  out  by  an  electrical  contractor  using  qualified 
electricians to install the wiring systems.  However, in some “small works” the installation 
engineer  may  be  called  upon  to  carry  out  the  interconnecting  wiring  installation  from  the 
fused  isolator  (provided  by  the  client)  to  the  various  components  of  the  refrigeration 
system.    It  is  important  that  the  person  carrying  out  this  work  understands  the  rules  and 
regulations of BS 7671: 2008 IEE Wiring Regulations, commonly known as 17th edition; and 
the Electricity at Work Regulations 1989, and that the electrical installation is inspected and 
tested by a qualified and competent electrician before the power is switched on.  
 

British Refrigeration Association            Institute of Refrigeration   
21 
Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
 
An  inspection  completion  certificate  must  be  issued  to  the  client  on  completion  of  the 
works.    Accreditation  of  the  contractor  to  the  NICEIC  (National  Inspection  Council  for 
Electrical Installation Contracting) is recommended but not essential. 
 
4.6.1  CABLES AND WIRING SYSTEMS 
 
This  section  identifies  the  types  of  cable  and  wiring  systems  suitable  for  use  with 
refrigeration  equipment.    It  must  be  remembered  that  some  of  them  are  not  suitable  for 
locations  where  the  temperatures  are  constantly  below  0°C,  for  example  conduit,  and 
trunking systems. 
 
• Steel Wire Armoured Cable (SWA):  Suitable for most applications except in 
locations constantly below 0°C.  This cable manufactured to BS 6346 is in common 
use within the refrigeration industry and is preferred wherever possible both from 
the cost and suitability points of view.  The method of fixing is by means of 
clipping direct to the surface or clipping to the cable tray,  the cable is terminated 
using the appropriate glands for connection into the various components.  SWA 
can be purchased in a variety of cable sizes and cores (1.5 mm2 to 95 mm2 and 1 
core to 19 cores are the most popular sizes). 
 
• FP200 Fire Resistant Cable:  This cable was developed primarily to offer improved 
protection against fire and heat damage, allowing it to be installed in high 
temperature locations and where there is a requirement for essential services.  
However these properties lend themselves to refrigeration applications, 
particularly in situations where the temperatures are constantly below 0°C (i.e., 
connection to evaporators and other components within a coldroom/coldstore).  
This is mainly because of the butyl rubber insulation covering the cores; the outer 
protection being made of plastic coated aluminium.  
 
This  type  of  cable  is  generally  available  in  sizes  1.0  mm2  ‐  2.5  mm2  and  with  a 
number  of  cores  from  2+ECC  (Earth  Conducting  Core)  to  4+ECC.    Fixing  is  by 
means of clips, either direct to a surface, or fastened with nylon cable ties to the 
cable  tray.    On  no  account  is  the  cable  to  be  strapped  to  any  refrigerant  lines.  
Termination ferrules are available for connecting to equipment. 
 
• Conduit Systems:  There are four types of electrical conduit system: 
 
a) PVC ‐ High impact 
b) Steel ‐ Galvanised 
c) Steel ‐ Stainless 
d) Steel ‐ Black enamelled 
 
The steel versions are not recommended for locations which give rise to humidity 
or  where  the  temperatures  are  constantly  below  0°C,  for  reasons  previously 
mentioned in this guide. 
 
British Refrigeration Association            Institute of Refrigeration   
22 
Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
 
Available in standard  tubing sizes of 20 mm, 25  mm and 32 mm (OD), comes a 
variety  of  fittings  such  as  pipe  saddles,  bends,  adaptors,  reducers,  tees  and 
circular  boxes.    All  these  enable  the  conduit  wiring  systems  to  be  adapted  and 
fitted into the installation.   
On  completion  of  the  conduit  work,  suitably  interconnecting  wiring  is  drawn 
through the pipework and connected to the various electrical components.  This 
cable  usually  comprises  of  “single  core”  PVC  or  Butyl  rubber  insulated 
conductors. 
 
• Trunking  Systems:    Like  conduit,  trunking  is  available  in  PVC,  galvanised  steel, 
stainless steel and enamelled steel.  Galvanised steel being the one in most  
 
common  use.    However,  plastic  trunking  may  be  preferred  for  humid  and 
corrosive atmospheres.  Sizes are normally available in 1” to 6” plastic, and 2” to 
6” steel. 
 
Trunking is appropriate where several electrical items are installed (e.g adjacent 
control  panels)  with  numerous  cables  converging  (either  from  above  or  below) 
from  the  various  parts  of  the  refrigeration  system.    The  final  connections  with 
the individual components being made with conduit or SWA etc. 
 
• Other Forms of Electrical Wiring:  These are less frequently used in refrigeration 
electrical works. 
 
a)  Flexible concentric insulate copper braided cable CY type.  This cable has 
been used mainly in Europe but is becoming more available in the UK.  It 
is particularly useful in situations where movement is necessary, as with 
connection  to  moving  machinery.    However,  check  the  manufacturer’s 
specification  before  installing  it  in  situations  where  temperatures  are 
constantly  below  0°C.    It  is  available  in  sizes  0.75  mm2  to  2.5  mm2  and 
with 3 to 18 cores. 
 
b)  Concentric  PVC  insulated  steel  braided  cable  SY  type.    As  with  the 
copper braided type mentioned above, this cable has been used mostly in 
Europe.    With  its  steel  braiding  it  is  particularly  suitable  for  locations 
where there is a possibility of impact damage.  As with the fabric braided 
type  or  fixed  with  the  special  clips  supplied  by  the  manufacturer,  it  can 
also  run  in  trunking.    The  cable  is  terminated  into  the  components  by 
means  of  cable  glands,  giving  a  water  proof‐dust  proof  connections.  
Available in sizes 0.75 mm to 6.0 mm and with 2 to 16 cores. 
c) PVC insulated cable is not recommended for refrigeration purposes, it is 
mostly used for domestic installations. 
 
 
 
 

British Refrigeration Association            Institute of Refrigeration   
23 
Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
 
4.6.2  MAINS SUPPLIES 
 
It  is  important  at  the  design  stage  for  the  correct  electrical  power  supply  details  and 
required  loading  to  be  established.    An  area  that  is  often  overlooked  at  the  outset  of  a 
project  is  the  checking  that  there  are  sufficient  available  incoming  supplies  to  meet  those 
required for the new equipment to be installed.  Plus to ensure there is a provision for the 
new  supply  to  be  brought  to  the  position  where  the  refrigeration  equipment  is  to  be 
installed. 
 
There are three main types of electrical power supply available in the United Kingdom. 
 
a)  400 V + 10% ‐ 6%  3 Phase 50 Cycles 
b)  400 V + 10% ‐ 6%  3 Phase and Neutral 50 Cycles 
c)  230 V + 10% ‐ 6%  Single Phase 50 Cycles 
 
It  should  be  noted  that  the  voltage  references  will  be  ±  10%  from  January  2003.    All 
electrical supplies contain an earth. 
 
Ensure that the equipment being installed will operate on one of these supplies. 
 
4.6.3  INTERCONNECTING WIRING AND CABLE ROUTES 
 
The mains power supply is usually run to the condensing unit or pack position, terminating 
in  either  a  control  panel  mounted  on  the  plantroom  wall,  or  directly  into  the  electrical 
section  of  the  refrigeration  or  air  conditioning  equipment.    From  these  panels 
interconnecting  wiring  is  fed  out  to  the  various  items  of  equipment  making  up  the 
refrigeration system. 
 
In  some  instances,  two  separate  power  supplies  are  provided.    One  to  operate  the 
condensing equipment, and the second to operate the cooling/evaporator section; this may 
be situated a considerable distance away.  With this arrangement interconnecting wiring is 
not required, (system designed with facility to pump down). 
 
In both cases it is important to ensure that the final sub circuits are protected by fuses of 
the  appropriate  rating  and  where  necessary  with  local  “lock  off”  isolation  to  protect  the 
engineer safely when completing service or maintenance work.  
 
4.6.4  CABLE SIZING AND VOLTAGE DROP 
 
The dual purposes of sizing cables properly, is to: 
 
(a)  ensure  that  the  temperature  of  the  conductor’s  insulation  does  not  exceed  the 
temperature  for  which  it  was  designed  when  carrying  its  rated  current  carrying 
capacity. 
 
 

British Refrigeration Association            Institute of Refrigeration   
24 
Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
 
(b)  to prevent an excessive drop in the voltage applied to the equipment to which it is 
connected. 
 
The current carrying capacity of the conductor is based on there being no obstruction to the 
flow  of  heat  from  the  conductor,  thus  an  equilibrium  is  reached,  and  the  conductor 
maintains a steady temperature. 
 
Full  information  on  the  current  carrying  capacity  and  voltage  drop  can  be  obtained  from 
Appendix 4 of BS 7671: 2008 (IEE Wiring Regulations) 17th Edition. 
 
4.6.5  EARTHING AND TESTING 
 
Regulation  8  of  the  Electricity  at  Work  Regulations  requires  precautions  to  be  taken  to 
ensure that any conductors of electricity which may become charged as a result of either, 
use of a system, or a fault in a system, do not present a danger to persons or property.  The 
most commonly used method of achieving this is by means of earthing. 
 
It is the practice in the UK for the Public Electricity Supply System to be referenced to earth 
by a deliberate electrical connection made at sub stations or power transformer.  It is this 
means of “system earthing” that enables earth faults on electrical equipment to be detected 
and the electrical supply to be cut off automatically.  In order to ensure safe system earthing 
the following factors must be observed: 
 
• Electrical bonding of exposed conductive parts of refrigeration equipment and their 
connection to earth services to limit the shock risk from transient voltages appearing 
between  various  components  in  the  system.    Equipment  earthing  therefore 
encompasses  the  bonding  of  metallic  enclosures,  cable  armouring,  conduits, 
trunking  etc.,  so  that  these  conductors  are  electrically,  continuously  and  securely 
connected to the general mass of earth at one or more points. 
 
• Equipotential Bonding:  It is essential that all exposed extraneous conductors which 
may  become  electrically  charged  from  a  fault  on  refrigeration  equipment  are  also 
connected to the main supply earthing system. 
 
• Inspection  and  Testing:    Before  new  installations  or  extensions  to  existing 
installations  are  put  into  operation  they  must  be  inspected  and  tested  upon 
completion to verify that the requirements of the Electricity at Work Regulations and 
BS 7671: 2008 (IEE Wiring Regulations) 17th Edition have been satisfied. 
 
Guidance  on  Inspection  and  Testing  may  be  found  in  Part  7  of  BS  7671:  2008.    On 
completion  of  the  inspection  and  testing  process,  forms  as  required  by  the 
regulations  must  be  completed  by  a  qualified  and  competent  person  in  respect  to 
the design, construction, and inspection and testing of the installation. 
 
 
 

British Refrigeration Association            Institute of Refrigeration   
25 
Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
 
4.7.0  CONDENSATE DRAINAGE  
 
GENERAL 
To  ensure  satisfactory  disposal  of  condensate  from  refrigeration  equipment,  a  properly 
designed and fitted plumbing system must be installed. This is an area that often does not 
get sufficient design consideration and inadequate condensate systems have been installed.  
Care  has  to  be  taken  to  avoid  fixing  condensate  pipework  close  to  refrigeration  pipework 
with the possibility of the pipes becoming frozen and blocked at some stage.  If there is no 
alternative route away from the refrigeration pipes, then the condensate pipework must be 
insulated.  Since  there is  a possibility of sludge building up  in the pipework (dust particles 
and  other  objects),  the  largest  size  of  pipe  should  be  chosen.    If  blockages  and  drain 
problems are to be avoided where pipework is run within the refrigerated space, it must be 
insulated  with  a  refrigeration  grade  insulation.    On  installations  where  the  temperature  is 
0°C  and  below,  a  proprietary  type  of  heater  tape  needs  to  be  wrapped  around  the 
condensate pipework prior to fitting the insulation.  The type of heater tape used should be 
one which is permanently “on”, therefore supplying a constant heat to the pipework. 
 
At the design stage, notice should be taken of any local bye laws or regulations, particular 
site conditions, and requirements for final connections into the mains drainage. 
 
4.7.1  CONDENSATE SYSTEMS AND MATERIALS 
 
Copper  and  plastic  are  the  two  main  types  of  material  from  which  condensate  drainage 
systems are constructed.  Details are as follows:‐ 
 
• Copper:  Copper tube and fittings manufactured to British Standard BS 2871 are 
available  in  3  metre  and  6  metre  lengths  in  nominal  bore  sizes  from  15  mm 
through  to  159  mm.    Fittings  are  available  for  sizes  15  mm  ‐  108  mm  in  both 
solder joint and compression joint. 
 
Pipework  in  installed  using  normal  plumbing  methods  including  bending  of 
pipework by mechanical tube bending equipment. 
 
• Plastic:  Plastic plumbing systems currently provide the most common method of 
installing  pipework  for  condensate  drainage.    It  has  several  advantages  over 
other forms, e.g., costs, non corrosiveness, and ease of assembly. 
 
There are several proprietary types on the market, all manufactured to a British 
standard.  Each type has three main methods of jointing as follows:‐ 
 
a)  Solvent Weld:  This is perhaps the best method utilised, provided care is 
taken  with  the  preparation  of  the  joint  before  applying  the  solvent.  
Pipework  is  joined  by  applying  solvent  to  the  ends  of  the  pipe  and 
inserting this into the appropriate fitting i.e., socket, bend etc. 
 
 

British Refrigeration Association            Institute of Refrigeration   
26 
Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
 
The solvent bonds the two surfaces together forming a strong water tight 
joint.    A  standard  range  of  fittings  and  adaptors  is  available  in  nominal 
bore sizes from 19 mm ‐ 50 mm, all manufactured to BS 5254. 
 
b)  Compression:    This  type  of  joint  utilises  a  knurled  nut  and  rubber  collar 
which fits over the pipe.  The pipe is first inserted into the socket of the 
appropriate  fitting,  with  the  knurled  nut  then  tightened  onto  the 
threaded portion of the fitting.  The rubber collar is compressed between 
the nut and the fitting forming the water tight joint.  A standard range of 
fittings and adaptors is available in nominal bore sizes 32, 40, 50 mm. 
 
c)  Push  Fit  Ring  Seal  Type:    This  form  of  joint  relies  on  the  neoprene  ring 
seal  forming  a  water  tight  joint  when  the  pipe  end  is  inserted  into  the 
socket of the fitting.  Standard. fittings are available in nominal bore sizes 
32,  40,  50  mm.    Use  of  this  plumbing  system  is  not  recommended  for 
refrigeration applications because of the susceptibility to movement, and 
the weakness of this type of joint,. 
 
4.7.2  GRAVITY DRAINAGE 
 
This method of condensate drainage depends upon the fall or slope of the pipework away 
from the equipment and is the most commonly used.  This is particularly important where 
there is restricted space (i.e., under refrigerated cases). 
 
When  installing  a  gravity  drainage  system  some  thought  needs  to  be  given  during  the 
design, to dismantling for cleaning and maintenance purposes.  Pipework also needs to be 
fixed  at  appropriate  points  so  that  low  points  are  not  allowed  to  form.    Finally  the 
connection into the mains drainage system must be “trapped” just before the connection. 
 
4.7.3  PUMPED CONDENSATE DRAINAGE 
 
There  are  numerous  arrangements,  from  collection  pans  fitted  with  float  switches  which 
control  the  operation  of  a  pump  to  small  self  contained  pumps  (with  electronic  sensors) 
which can be fitted directly into the air handling unit: 
 
• The  pipe  or  tubing  used  on  this  type  of  installation  is  of  a  small  diameter,  usually 
between 6 mm and 12 mm nominal bore depending on the application and the size 
of  the  pump.    It  is  normally  made  from  clear  polythene,  is  very  flexible,  and  is 
supplied  in  standard  50  metre  bundles.    A  more  expensive  type  is  available  where 
nylon braiding is laminated into the polythene tube to give more strength and less 
susceptibility to kinking. Preferable condensate drainage tubing is Black plastic that 
excludes  daylight  and  hence  discourages  growth  of  slime  inside,  however  is  not 
always available in the size/s required. 
 
 
 

British Refrigeration Association            Institute of Refrigeration   
27 
Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
 
• Where  condensate  pipework  is  to  be  connected  into  mains  drainage system,  a  tun 
dish  which  is  connected  into  the  mains  drainage  via  a  trapped  gravity  pipework 
arrangement should be provided. 
 
• A  separate  electrical  supply  (independent  from  the  supply  to  refrigeration 
equipment) should be installed for the condensate pump to allow the condensate to 
be pumped away should the refrigeration electrical supply be interrupted. 
 
• Any  condensate  drainage  installed  in  coldrooms  operating  below  0C  will  require 
trace heating  
 
4.8.0  PRE‐COMMISSIONING SYSTEM TESTING AND PREPARATION 
 
  System testing and preparation must be included in the installation program and at an early 
stage there must be determination whether or not to complete these tasks in phases, may 
be  due  to  access  or  requirement  for  part  system  start  up,  or  at  the  end  of  all  installation 
work.  These  tasks  shall  be  prior  to  the  commencement  of  the  commissioning  stage  and 
putting systems into service. 
 
System testing shall cover pressure testing for mechanical strength and leak tightness test to 
permit detection of leaks. 
 
  Components, e.g. compressors, condensers, evaporators, pressure valves, safety valves and 
control  gear,  which  have  been  previously  strength  tested  by  a  manufacturer  need  not  be 
subject  to  a  further  strength  test.  Manufacturer’s  certificates  should  be  obtained  and 
included to system and operation manuals. 
 
  Strength  tests  will  normally  be  carried  out  before  a  leak  tightness  test,  using  oxygen  free 
nitrogen (OFN) or other inert gas. Oxygen, air, ammonia, fluorocarbons, combustible gas or 
any combustible mixture shall not be used as a strength test medium  
 
  Refer to design documentation for details of pressures to be achieved with time periods for 
the mechanical strength and leak tightness test. These shall comply with BSEN378:2008.  
If there is a need to complete a leak tightness test prior to strength test to confirm system 
or part system integrity this test shall be completed at very low pressure, say 5% of design. 
 
  The leak tightness test shall be carried out with oxygen free nitrogen (OFN) or a mixture of 
OFN and a tracer. The tracer should be zero ODP and low GWP. Mixtures of HCFCs or HFCs 
with air should not be used 
 
  All  joints  shall  be  checked  for  leaks  using  either  a  leak  detecting  bubble  spray  or  an 
electronic leak detector suitable for use with the tracer. 
 
Following  satisfactory  testing,  test  certificates  shall  be  completed  and  included  to  system 
operation end user manual. 
   

British Refrigeration Association            Institute of Refrigeration   
28 
Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
 
The  BRA  Task  Procedures  &  Risk  Assessments  cover  the  following  tasks  to  be  completed 
prior to commencement of commissioning and system start up:‐ 
 
• A strength and leak pressure test must be carried out on the entire system.  See task 
procedure and risk assessment R10 and R14. 
 
• A vacuum drawn on the whole system including condensing unit, pack etc to at least 
2 mm HG.  See task procedure and risk assessment R9. 
 
• The correct grade of refrigeration oil should be added as required according to the 
manufacturer’s instructions for the compressor, oil separator, and oil control system, 
where fitted.  See task procedure and risk assessment R15. 
 
• The vacuum should be broken by charging the system with the correct refrigerant for 
that particular application.  See task procedure and risk assessment R6. 
 
For  further  guidance  on  strength  pressure  and  leak  tightness  testing  refer  to  BSEN  378 
1:2008 and BSEN 378 2:2008. In addition refer to the IOR Safety Code for Refrigerating  
 
Systems using A1 Refrigerants which is a comprehensive guide bringing together a number 
of regulations and directives that should be complied with. 
 
Leak  tightness  pressure  test  to  permit  detection  of  leaks  and  then  demonstrate  system 
integrity  to  contain  refrigerant,  along  with  refrigerant  charging,  reclaiming,  leak  detection 
methods  including  labelling  and  records  shall  comply  with  the  F‐Gas  regulations  No 
842/2006.  Refer to BRA Code of Practice for Refrigerant Leak Tightness published 2007 for a 
comprehensive interpretation of regulation into practice. 
 
4.9.0         DRAWINGS 
 
Please refer to 'Section 4 Drawings' which is at the back of this document. 
HU UH

Drawing titles are:‐ 
 
‐  Liquid Distribution ‐ Header Method 
‐  Liquid Distribution ‐ Ring Main Method 
‐  Liquid Distribution ‐ Reducing Method 
‐  Liquid Trap 
‐  Swaged Joints 
‐  Standard Brazing Equipment 
 
4.10.0  APPENDICES 
     
    Acknowledgement of References, Standards and Legislation 
 
    ACRIB    Air Conditioning, Refrigeration Industry Board 
    BRA    British Refrigeration Association 

British Refrigeration Association            Institute of Refrigeration   
29 
Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
     
    CITB    Construction Industry Training Board 
    C&G     City & Guilds qualifications. 
    IOR    Institute of Refrigeration 
    NICEIC   National Inspection Council for Electrical Installation Contracting 
    TREM     Transport Emergency Card 
    UKAS    United Kingdom Accreditation Service 
 
    BRA Documents 
Code of Practice for Refrigerant Leak Tightness in compliance with F‐Gas 
regulations – issue 1. 
 
Model Statements of Task Procedures and Risk Assessments for Commercial 
Refrigeration – issue 3. 
 
Jointing of Copper for Refrigeration Systems – issue 2. 
 
Fact Finders, Good Practice Guides. 
 
IOR Documents 
  Safety Code for Refrigerating Systems using A1 Refrigerants. 
 
  Service Engineer Guides 
 
Regulations 
  CDM – Construction (Design & Management) 2007 
  COSHH ‐Control of Substances Hazardous to Health 2002 
  Electricity at Work 1989 
  Environmental Protection Act 1990 
  Environmental Protection (Control of substances that deplete the ozone 
layer) 
  F‐Gas 842/2008 
  Health & Safety at Work Act 1974 
  PSS ‐Pressure Systems Safety Regulations: 2000 
  PED – Pressure Equipment Directive 97/23/EC 
  PUWER – Provision and Use of Work Equipment  
  GN4 – Safety in Pressure Testing guidance note 
 
Standards 
  BS EN378:2008 parts 1/2/3/4, Refrigerating Systems and Heat Pumps – Safety 
and Environmental requirements. 
  BS EN 12735‐1:2001 Copper Tube for Air Conditioning & Refrigeration. 
  BS 3799 – 1974 Specification for Steel Pipe Fittings, Screwed & Sockets. 
  BS EN 10204:2004 Metallic Materials. 
  BS EN 14276‐2:2007 Pressure Equipment for Refrigerating Systems and Heat 
Pumps – Piping. 
  BS EN 287‐1:2004 – Approval Testing of Welders for Fusion Welding. 

British Refrigeration Association            Institute of Refrigeration   
30 
Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
   
  BS EN 10253‐2:2007 Butt Welding Pipe Fittings. Non Alloy & Ferritic Alloy 
Steels with Inspection Requirements. 
  BS EN 15614‐1:2004 Specification and Qualification of Welding procedures 
for Metallic Materials. 
  BS EN 1515‐1:2000 Flanges and their Joints. Bolting. 
  BS 7671:2008 IEE Wiring Regulation – 17th Edition 
  BS 6346:1997  Electric cables 
  BS 5254:1976 Polypropylene Waste Pipe & Fittings 
  EN 1044:1999 Brazing, Filler Metals. 
  PD 5500:2006 Specification for unfired fusion welded pressure vessels 
   
   
 
   
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

British Refrigeration Association            Institute of Refrigeration   
31 
Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
 
Section 4 Drawings

British Refrigeration Association            Institute of Refrigeration   
32 
Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 

British Refrigeration Association            Institute of Refrigeration   
33 
Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 

British Refrigeration Association            Institute of Refrigeration   
34 
Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 

British Refrigeration Association            Institute of Refrigeration   
35 
Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 

British Refrigeration Association            Institute of Refrigeration   
36 
Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 

 
 

British Refrigeration Association            Institute of Refrigeration   
37 
Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
 
 

British Refrigeration Association            Institute of Refrigeration   
38 
Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
 
 
 
This Guide is published in the following Parts: 
 
Part 1                                    Introduction 
Part 2                                    System Design and Component Selection 
Part 3                                    Safety Regulations, Standards and Directives 
Part 4                                    System Installation                                                                           
Part 5                                    System Commissioning                                                                  
Part 6                                    System Maintenance and Service 
Part 7                                    System and Component Decommissioning and Waste Disposal 
Part 8                                    Refrigerants and Retrofitting 
Part 9                                    Assessment of Skills Related Competence and Training     
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
The BRA and IOR disclaim all liability to any person for anything or for the consequences of 
anything done or omitted to be done wholly or partly in reliance upon the whole or any part 
of the contents of this Guidance document. 

British Refrigeration Association            Institute of Refrigeration   
39 
Guide to Good Commercial Refrigeration Practice Part 4     
System Installation 
 
 
 
 
 
 
 
 
 
 
 
Published By: 
 
 
British Refrigeration Association 
2 Waltham Court, Milley Lane, Hare Hatch, Reading, Berkshire, RG10 9TH United Kingdom 
Tel No: + 44 (0)118 940 3416 ‐ Fax No: + 44 (0)118 940 6258 
e‐mail: [email protected] 
HU U

Institute of Refrigeration 
Kelvin House, 76 Mill Lane, Carshalton, Surrey SM5 2JR, Tel No:  +44(0)2086477033 ‐  Fax 
No: +44 (0)20 8773 0165                                    
e‐mail: [email protected]  
HU UH

British Refrigeration Association            Institute of Refrigeration   
40 

You might also like