November, 2018
Acute Engineering P.L.C
Tel: (+251) 118 60 2050
Fax: (+251) 116 39 21 20
P. O. Box: 23219 code1000, Addis Ababa, Ethiopia
E-mail address: [email protected]
Table of Content
1. General Information ……………………………………………………….…..
1.1. Employer …............................................................................................................1
2. Summary of Report……………………………………………………………
2.1 Project Name …………………………………………………....................1
2.2 Contract Amount ……………………………………………………...……1
2.3 Project Particular : Site hand over Date,Time Elapsed & Contractors
Cumulative progress status ………………………......2
3. Project Status
3.1. A short description of the works accomplished during the reporting month
3.2. Financial Status With respect to Contractors & their site progress verses
Schedule (Table 3.2.1) & (Table 3.2.2)………………………5
2. Summary of Report
2.2 Contract Amount for the Buildings part (Expansion & New
Expansion projects)
Date of Time
Site Hand Revised elapsed in Progress of
Project Name of Contract
over(Com Completion days & tage Contract
Phase Contractor Period
NO mencemen Date % (Cumulative)
t date)
1 FE Costruction PLc 545 days 2 Jan ,2016 24- Nov- 2017 849 (122.68%) 99.07%
Mat General
88.01%
2 construction PLC 545 days 2 Jan ,2016 8-Jan-2017 849 (112.89%)
3 Fufa Legissa B.C 545 days 2 Jan ,2016 18-Sept-2017 849(135.84%) 92.85%
Expansi
4 on Abera Mamo G.C 365 days 2 Jan ,2016 2- Aug-2017 849(146.85%) 96.68%
Project
5 Desalegn Ayalew B.c 365 days 2 Jan ,2016 3-Aug-2017 849 (178.04%) 100%
6 Kassu G/Tsadik B.c 545 days 2 Jan ,2016 7-April-2017 849(90.03) 93.07%
2 Fufa Legissa B.C 450 days 24-Mar- 2017 7-Octo-2018 491 (109.11%) 56.00%
3 New Kassu G/Tsadik B.C 365 days 24-Mar-2017 24-Mar- 2018 461 (134.52%) 50.25%
Expansi Tesfaye Demissie
4 on B.C 365 days 2-Feb-2017 26-Apr-2018 510 (112.83%) 78.38%
Project 9-July-2018
5 Bahiru Eyasu B.C 365 days 2-Feb-2017 510 (92.72%) 97.83%
6 Shafi Madi B.C 365 days 2-Feb- 2017 2-Feb-2018 510 (139.72% 88.01%
3. PROJECT STATUS
3.1 A short description of the works accomplished during the reporting month
Fufa Lejisa Site:-on Students dormitory Block
Sanitary works on progress
Toilet & shower wall ceramic works Completed.
External painting works on progress.
Handrail guard rail works on progress.
:-On Teachers Resident , Combined class Room & entertainment
Form work ,Rebar placing and concrete casting works on progress for Teachers Resident.
Rebar placing works also on progress for roof slab
HCB, Plastering works also on progress
No registered activity on Combined Class room
On Entertainment water proofing membrane works completed
Gypsum plastering on progress
But the overall activity of the contractor is unsatisfactory on this month
Mat General Contractor PLC:-Students Dormitory , Combined Class room with Lecture halls & seminars
No registered activity in this reporting month on this Blocks
Only Slope protection works on progress .But no other activity is registered at mini stadium .
At Teachers Resident Road works on progress.
Desalegn Ayalew :- Combined class room with Lecture hall & Seminar room
Completed & provisional acceptance held.
Table 3.1 & 3.2 shows that Financial Status of the project respectively for Expansion & New Expansion
projects (Refer Table 3.1 & 3.2)
3.3 Table Shows that Physical Statues of the project (Refer Table 3.3)
5,452,882.42 3,917,074.10 -
Kassu G/Tsadik B.C
7,918,487.22 7,918,487.22 2,903,377.57 6,008,207.38 6,778,963.14 1,799,187.88 3,735,483.76
Abera Mamo B.C
- -
Desalegn Ayalew BC
Shafi Madi B.C 7,994,797.80 4,243,340.91 6,402,208.18 4,957,564.42
3.4 (A ).BONDS
The validity of Advance Guarantee Bond and performance bond is summarized in the table as follows:
Expansion projects
Project Phase Contractor Name Deducted Advance Expiry Date Written Letters to Performance Expiry
Advance/Repaid Notify the expiry Date
advance/ payments date
New Expansion FE Construction March 25,2018 June 26,2018
Project (TR)
Fufa Legisa B.C 5,152,908.26 March 19,2019 September 17,2019
(TR)
Admin,Maingate, FE Construction PLC 15,389,166.26 May 20,2018 March 26,2018
Guard Houses &
Front Fence
3.5 CLAIMS
Table: list of claim and their status
S.No. Description of claim Comments Status
2
In this month it seems good after the University
No responsible body Temporally solved
Robbery discussed with the zone police
Lack of Construction
3 Contractors Not solved.
Materials
4. Problems encountered & actions taken during the reporting month of November , 2018
Quantity Variations - -
Suspension - -
Material Change - -
Rectification -
Others - -
RE-BAR φ 20 kg
- 0.00 - - - - - - -
RE-BAR φ 24
Sr.No Type of Unit FE Mat Fufa Bahiru Kassu Abera Shafi Madi Tesfaye Total
Material Const G.C Legisa Eyasu G/Tasdik Mamo Demisie
3 LTZ profile Pcs 489 378 78 - 0.000 - 250 420 1615
4 River sand M3 150 30 300 45 20.56 48 128 45 766.56
5 Aggregate M3 80 20 500 30 28 - 32 30 720
4 CHS/RHS pcs - 139 40 112 0.00 - - - 291
Marble ml 250 1504 - - 250 650 165 - 2819
100x10
Marble ml 200 328 - - 30 65 65 - 688
6
100x20
Marble ml - 12 - - 108 - 320 - 440
120x30
7 Water proof roll - - - - - - - - -
membrane
8 Ceramic M2 1100 1850 3215 -- 1500 - 50 - 5876
9 Carpentry M2 60 0.00 - - 32 60 - - 152
10 Painting gallon 50 70 450 160 720 85 250 - 1790
11 Sanitary pcs 200 789 350 50 0.00 - 120 - 1459
upvc+ppr
12 Hand wash 30 0 25 - 0.00 - - - 55
basin
Soup& soft 80 0 30 - 0.00 - - - 110
holder
13 Electrical wire roll - 2 120 12 0.00 - 57 - 201
14 Cable ml - 520 - 125 0.00 - - - 645
15 Fittings no - 0 - - 0.00 - - - -
4 Surveyor - 2 - - - - 2
5 General Foeman 3 4 2 1 - 1 - 1 16
6 Forman 2 3 - 1 1 1 1 1 6
7 Surveyor's - 3 - - - - 3
Assistance
8 Operator 4 1 1 1 2 - - - 9
8 Skilled Laborer 13 20 23 4 - 2 2 9 73
9 Unskilled Laborer 32 65 58 5 15 21 - 36 232
Administration & 1 1 1 1 1 1 1 1 8
10 Finance head
11 Personnel 1 1 1 1 1 1 1 1 8
12 Accountant 1 1 1 1 - - - - 4
13 Casher 1 1 1 1 1 1 1 1 8
14 Store 3 3 2 2 2 1 1 1 15
Equipment FE Fufa Mat G.C Kassu Bahiru Tesfaye Abera Shafi Madi Total
Planned Constr Legisa PLC G/Tsad Eyasu Demissi Mamo
Item Type uction B.C ik e
No
1 Mixer (200 - 2 2 3 1 1 1 1 14
Lt)
2 Vibrator 2 2 2 2 2 2 2 2 21
3 Small 1 1 2 1 1 - - - 6
Vehicle
4 Damp 3 2 5 1 1 - 1 1 14
Tracks
5 Back Hoe - 1 1 - - - - - 2
Excavator
6 HCB 1 1 1 1 - - 4 - 8
Production
machine
7 Water Track 1 1 2 1 1 1 1 1 9
8 Loader 1 1 3 1 - - - - 6
9 Roller - 2 - - - - 2
10 Crasher 1 1 1 - - 1 1 5
11 Compactor - 1 1 1 1 - 1 1 7
12 Concrete - 1 1 - - - - 2
Pump
Yes/No
Item Description Previous This Reporting
Reporting Period
period
1) Is there shortage of
a) Construction Materials Yes Yes
b) Equipment and plant Yes Yes
c) Professionals Yes Yes
d) Skilled Manpower Yes Yes
B. Phase II 108,327,566.38
MAT GC 365
2 Phase II 04-Jul-2014 19-Jul-2015 91.00%
PLC Days
Complete
but
Sport MAT GC 365
3 22-Jan-2015 07-Feb-2016 provisionall 99.00%
Field PLC Days
y not
accepted!
New TR
4 MAT GC 408
Infrastruc 15-Feb-2017 30-Mar-2018 144.12% 42.15%
PLC Days
ture
2. PROJECT STATUS
2.1 A short description of the works accomplished during the reporting month
A. On Phase One( Lot-A & Lot-B)
Road works (Main walk ways & access roads) has been completed.
Site Electrical works has been completed.
Site Sanitary works (Potable & Non-potable Supply system, Sewerage line)
completely done.
B. On Phase Two
Road works (Main walk ways & access roads) has been completed with a
little correction remark.
Site Electrical works has been completed.
Site Sanitary works (Potable & Non-potable Supply system, Sewerage line)
almost done.
Ramp and access to the buildings completed.
C. On Sport Field
Here, the contract is doing Excavation & earth work (cut & fill, load & cart
away surplus materials). Hence, it’s completely done.
D. On New TR Contract
Road work (Triple surface treatment) on progress.
Ramp & access to the TR & PV bldgs on progress.
Site sanitary & electrical works completely done.
Septic tank & sub-surface sand filter completely done.
Presidential villas site work & retaining walls completed.
Mini stadium spectators’ seat isn’t active.
1300m3 pioneer water reservoir completely done.
12.1 Photographs