CSR - L1-Che-Std-043
CSR - L1-Che-Std-043
CSR - L1-Che-Std-043
L1-CHE-STD-043
Version: 1
APPLICATION OF THIS ENGINEERING STANDARD
Contemporary Engineering Standards shall be used for all projects, with the exception of
work packages that have been exempted following approval by the Standards Governance
Group (SGG).
All contemporary versions (i.e. the latest published version) of MTM Engineering Standards
are available on MTM’s The Depot (internal access only) or the Metro Document Portal
https://documentportal.metrotrains.com.au/ (public access).
BACKGROUND
In accordance with PTV Standards Framework (CM Ref: DOC/19/110188), a project
adoption assessment for in-flight projects must be conducted by the PAAC (Project Adoption
Assessment Committee) for any new, revised or withdrawn Engineering Standard. Based
on this impact assessment, the PAAC has provided its recommendation to the SGG that
specified projects will be exempt from adopting the provisions of this Standard as set out
below.
The list of projects exempt from adopting this Engineering Standard may be progressively
updated without the requirement to update the version of the underlying Standard.
For designers, manufacturers, suppliers etc., Section 46 and 47 of RSNL details that
persons undertaking works on the railway are required to manage safety risk SFAIRP based
on what they know and what they ought reasonably to know. Sections 52 and 53 of the
RSNL go into further particulars around the duties of operators and designers.
Section 52 states that the operator has obligations to ensure SFAIRP that design is
undertaken in a manner that ensures the safety of the railway.
Section 53 states that a designer must ensure SFAIRP that the design is safe for its
purpose based on what they know or ought reasonably to know.
Page i of i
ENGINEERING STANDARD
STANDARD FOR CONSTRUCTION OF CABLE ROUTE
AND SIGNALLING CIVIL WORKS
L1-CHE-STD-043 Version: 1 Effective from: 1st July 2018
Approval
Document
Louisa Waymouth Manager Standards
Endorser
Approving
Phil Ellingworth Chief Engineer
Manager
Amendment Record
Approving Manager: Chief Engineer Approval Date: 20/06/2018 Next Review Date: 20/06/2021
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 2 of 87
ENGINEERING STANDARD
STANDARD FOR CONSTRUCTION OF CABLE ROUTE
AND SIGNALLING CIVIL WORKS
L1-CHE-STD-043 Version: 1 Effective from: 1st July 2018
PREFACE
This Standard replaces VRIOGS 012.2.1 Standard for Construction of Cable Route
and Signalling Civil Works.
The contents of this Standard were prepared by the Victorian Rail Industry Operators Group
(VRIOG). This VRIOG Standard has been rebadged as an MTM document due to the retirement
of VRIOG Standards as of 30th June 2018.
This Standard will be managed under the Engineering Standards Development Procedure
(L1-CHE-PRO-032).
As documents are uncontrolled once printed, it is imperative to check the currency of
the Document on The Depot or the MTM’s Document Portal which is available
externally at https://documentportal.metrotrains.com.au.
All MTM Standards and Specifications are periodically reviewed, and new editions are published
which incorporate learnings and Technical Notes (formerly known as Design Practice Notes).
Technical Notes are issued between editions which correct any errors or ambiguities contained in
an MTM Standard/Specification. Standards and Specifications may also be withdrawn and/or
replaced.
In the event of conflicts or discrepancies between different types of technical documents, refer to
the order of precedence as defined in ‘Chief Engineer’s Guideline Engineering Standards
Listing’ (L1-CHE-GDL-005).
Note: Any clarification described in a Technical Note or Design Practice Note shall take
precedence over the impacted clause or clauses in the associated MTM Standard/Specification.
In the event a clause within a Standard/Specification is not achievable a waiver will need to
be raised, please refer to the ‘Engineering Waiver Procedure’ - L1-CHE-PRO-001.
Note: MTM does not have the authority to grant waivers on any Standards/Specifications or
clauses within a Standard/Specification which relate to Government Regulations or Legislation,
e.g. Disability Discrimination Act.
Approving Manager: Chief Engineer Approval Date: 20/06/2018 Next Review Date: 20/06/2021
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 3 of 87
ENGINEERING STANDARD
STANDARD FOR CONSTRUCTION OF CABLE ROUTE
AND SIGNALLING CIVIL WORKS
L1-CHE-STD-043 Version: 1 Effective from: 1st July 2018
Approving Manager: Chief Engineer Approval Date: 20/06/2018 Next Review Date: 20/06/2021
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 4 of 87
Victorian Rail Industry Operators Group Standards
VRIOGS 012.2.1
Revision A
VRIOGS 012.2.1 Standard for Construction of Cable Route and Signalling Civil Works
Revision A
Issue Date: 07/09/2010
APPROVAL STATUS
Document Developer
Metropolitan Train
Intrastate Train
Interstate Train
Tram
VicTrack
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
PURPOSE OF THE STANDARD
The Standard has been created through the collaboration of members of the Victorian Rail
Industry Operators’ Group (VRIOG) for the purpose of establishing standards which, if
implemented throughout the Victorian Rail Network, will facilitate the interoperability of
infrastructure.
The use of the Standard is not prescribed by law but, if adopted, conformity with the
provisions of the Standard is mandatory in order that the purpose of the Standard be
achieved.
The Standard is published by the Director of Public Transport for information purposes
only and does not amount to any kind of advice.
Each person is responsible for making his or her own assessment of all such information
and for verifying such information. The content of this publication is not a substitute for
professional advice.
The Director of Public Transport and VRIOG accept no liability for any loss or damage to
any person, howsoever caused, for information contained in this publication, or any
purported reliance thereon.
COPYRIGHT STATEMENT
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 1
1. Words or phrases that appear capitalised out of context are defined within the
Definitions section of this VRIOG Standard.
b) The reader is not referenced to another Controlled Standard necessary for the
item to be adequately explained, ie. One document link only.
9. The numbering system for the VRIOG Standards is chronologically sequential from
the point of introduction, and is not based on any form of interpretive system.
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
2 VRIOGS 012.2.1 REVISION A
Terminology Definition
1100 The phone number for “dial before you dig” services
1800 619 1111 The phone number displayed on all VicTrack cable marker
posts for contact with VicTrack Access, for information on
underground VicTrack communications cables on Victorian rail
corridors
Backfill Backfill is compactable material free of rocks that will not pass
through a 30mm sieve and free of broken concrete, brick,
rubble, wood, glass, rubbish, steel or other metal objects that
could damage cables or affect the operation of electronic cable
locators and is used within 400mm of cables and conduits as
backfill.
Cables - Main Cables that are run from an equipment room, housing or
signalling cables equipment box to another equipment room, housing or
equipment box. Examples such as; signal cables, high voltage
signalling or power supply cabling, fibre optic cables, etc. Also
commonly referred to as “through type” cables.
Cables - Local All other cables that are not main cables; and are those run
signalling cables from equipment rooms, housings or boxes to trackside field
located equipment. Examples such as point mechanisms,
signals, track circuits, train detection equipment, trainstops, axle
counter disconnection points, TPWS disconnection points, post
telephones, local signalling power cabling, boom barrier
mechanisms, pedestrian gates mechanisms, train stabling
gates, etc.
Cable Ladder A cable ladder type cable route is generally required in areas
where clearance limitations demand it
Cable route Cable route means any material installed or excavation carried
out for the installation of cables between two or more points.
Clean fill Clean fill is sand (or soil) that is completely free of stones,
rocks, wood, metal and rubbish or similar.
Conduit A Conduit can also be generically known as a pipe and can be
manufactured from materials such as high density polyethylene
(HDPE) or galvanised steel. Within the railway environment
these materials require approval for use.
Communications Communications cable is all main and local communications
Cable cables including communication cables to station buildings,
relay rooms, Equipment Boxes, trackside telephones, etc.
Constructor Person or organisation undertaking supply, construction,
manufacturing, installation, testing or commissioning works
under this standard. Can often also be referred to as a
Contractor, within commercial arrangements, Standards and
Specifications.
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 3
Terminology Definition
External cable route External cable route is any cable route not in a building.
FOC Fibre Optical Cable
GLT Ground Level Troughing
GST Galvanised Steel Troughing
HDPE High Density Polyethylene as is used in manufacture of
conduits
Infrastructure Any structure or asset, be it new or existing, that exists in the
railway environment.
Installation-Major Where conduits are required for the use of main signalling and
Conduit or cable communications cable route installations such as; under rail line
enclosure Installations crossing, under all types of roads, under all vehicle access
tracks, or through station platform areas.
Installation-Minor Where conduits are required only for the use of local signalling,
Conduit or cable power and communications cabling and cable route
enclosure Installations installations, under or beside the rail line.
Internal cable route Internal cable route means any cable route inside a building or
similar structure.
Non invasive method For the purposes of this Standard this shall refer to the
potholing method for location of buried cables and services.
See potholing definition within this Standard.
Overloading Overloading is where there are too many cables for the troughing
lids to be correctly fitted.
Potholing Potholing is a procedure which uses water lance vacuum
excavation techniques to expose services such as; cables,
conduits or marker tape. Manual excavation using hand tolls
can also be used. This process is also known as “explorative
trenching”. At all times when carrying out such activities due
care is to be exercised so as not to damage any services.
Signalling cables Signalling cables means but is not limited to cables to signals,
points, trainstops, signal enforcement equipment, ground
frames, releasing switches, level crossings, buffer stop lights,
plus cables between equipment rooms and between equipment
rooms and Equipment Boxes.
Stabilised sand Stabilised sand is a mixture of sand and Portland cement in the
ratio 10:1.
Troughing Troughing is also commonly referred to as trunking, and forms
the type enclosure to install cabling within.
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
4 VRIOGS 012.2.1 REVISION A
The purpose of this Standard is to provide the requirements for the Construction of the
Signal and Communications cable route and Signalling civil type works.
This Standard describes the minimum requirements for the following works:
a) Construction of various types of cable routes
b) Construction of under line and under road crossings.
c) Construction of cable pits, jointing pits and cable turning chambers.
d) Construction of foundations for signals and signal gantries
e) Construction of foundations for Equipment Boxes
f) Construction of access paths and associated works
g) Construction of retaining walls, ladders and safety handrails
h) Construction of fencing and gates for signalling works
3.2 Application
This standard applies to all of the Victorian Rail Network encompassed by the State
borders and shall be applied for the construction of cable routes and signalling civil works,
as well as Telecommunications works in shared infrastructure such as trenches, ground
level troughing, trunking and similar.
This Standard shall be used in conjunction with VRIOGS 012.2 Signalling Supply,
Construction and Installation.
For Telecommunications Design and Construction works this specification shall be used in
conjunction with VicTrack Communications Installation Specification TS-SP013 (latest
version) and VRIOGS Telecommunications Standards and Specifications.
3.3 Background
The following standards have been superseded by this standard with relation to the
construction of cable routes and signalling civil works.
List of documents superseded or utilised for the signalling and communications cable
route and signalling civil type works areas;
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 5
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 7
4.3 Working Whilst Existing System is Operational
a) Under no circumstances shall the Constructor interfere with any equipment that is
operational without the prior approval of the Infrastructure Manager.
b) Buried metal conduits, (water, gas, sewerage, etc) and metal armour on some high
voltage cables are connected to the traction power supply return by means of
“Electrolysis Bonds” at a number of points along the line. The Constructor shall
ensure that electrolysis bonding connections or equipment are not damaged or
disturbed. .
c) Mechanical digging equipment shall not be utilised within 5 metres of an existing
buried telecommunications service without the approval of the VicTrack Network
Maintenance Manager (where applicable) When trenching alongside or across gas,
water mains or service utility lines the Contractor shall comply with any restrictions
that may apply to the easement and liaise with the owners of that easement to
establish mutually agreed methods of protection and support for the services.
d) The Constructor is responsible for rectifying any damage to services caused by the
Constructor’s works.
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
10 VRIOGS 012.2.1 REVISION A
c) Excavation work shall not commence in or near tracks, platforms or access roads
until sufficient shoring material is available on site to shore up the excavations as
the work progresses.
4.13 Blasting
NO blasting shall be undertaken without written permission from the relevant statutory
authorities and permission from the Infrastructure Manager.
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 11
ii. At pits on two (2) diagonal corners to identify the location of the pit and to
protect the pit from vehicular traffic
b) The rail protection posts (or other Infrastructure Manager approved structure) shall
be painted white and extending not less than 800 mm both above and below ground
level.
c) The protection posts can also be utilised as either cable route markers or cable joint
markers and shall be manufactured in accordance with drawing numbers STD
G0003 and STD G0004.
iv. At such spacing that, from any marker the adjacent marker on either side is
readily visible, with a maximum spacing of 200 metres in open country or
100 metres in closer settled or highly timbered areas.
b) The markers shall be mounted on rail posts (or other Infrastructure Manager
approved structure) painted white and extending not less than 800 mm both above
and below ground level. Cable route markers shall be manufactured in accordance
with drawing numbers STD G0003 and STD G0004.The marker plates are to be
fixed to the clean surface of the rail post by construction adhesive or similar
permanent fixing.
c) The cable route marker shall show by means of engraving on the plate the depth of
the installed signalling cable and the signalling cable route offset from the nearest
rail. Cable route markers installed for trenches that contain only telecommunications
cables will show the offset from the cable route marker.
d) Buried cable joints or joints in pits shall be indicated by rail posts (or other
Infrastructure Manager approved structure) painted yellow and extending not less
than 800 mm above and below ground level.
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
12 VRIOGS 012.2.1 REVISION A
e) Cable route markers shall be placed beside the trench and not directly over it. And
shall remain close to fences or fixed objects where possible and be positioned so
that they are unlikely to damaged by track maintenance or other vehicles. The cable
route markers shall not obstruct footpaths, walkways or vehicle access ways.
f) The Constructor shall prepare a plan in tabulation format to record the offset
distance of the centre line of the buried cable trench to the inside running edge of
the nearest rail. The plan shall be issued prior to the commencement of trenching
operations and offset distances shall be recorded as the work progresses. The data
shall be transferred to the final signalling drawings for incorporation into the final “as
in service and constructed” signal book of drawings. Measurements shall depict the
depth of the installed cabling. The location of all cable joints shall be recorded in the
exact same manner as for the cable route, and shall be shown in a tabulation format
and also on all cable running plans.
g) In station and yard areas the cable route markers shall be mounted on posts with
500 mm protrusion above ground (or on an adjacent fence line where available). In
all other areas markers shall be mounted on posts with 800mm protrusion above
ground.
h) In station or yard areas they shall not obstruct footpaths, walkways or vehicle
access ways.
i) Cable route markers shall be placed close to a fence or other fixed structure and in
such a position that they are not likely to be run over by track maintenance or other
vehicles.
j) Cable route marker signs may be installed on Overhead Wiring Structures where
approved. The bonding agent used to attach the marker to the structure shall not
cause deleterious effects to the structure or its protective coating and shall be a type
approved product.
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 13
b) The cover strip shall be placed on top of the cables and overlap the cables by not
less than 50 mm on each side as shown on Drawing No. 112000/5/4.
c) The protective cover shall be no closer than 75 mm above the cable/s and shall
comply to AS/NZS 3000 Wiring Rules
b) The depth of cables in rock and shale areas shall normally be at least 600 mm to
cover strip or conduit except that in areas of unbroken rock a reduction in depth to
300 mm may be permitted.
c) The final 150 mm of fill of trenches in rock areas shall be stabilised sand, or
concrete (minimum 25Mpa) if in vehicle access roads.
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
14 VRIOGS 012.2.1 REVISION A
6.6 Cable and Conduit Ploughing
a) Cable and Conduit Ploughing shall only be utilised for signalling and
communications installation works with approval from the Infrastructure Manager.
b) The wall thickness (or class) of conduit shall be sufficient to guarantee that there will
be no loss of cross sectional area and that there will be less than 10% loss of
diameter in any direction during or after backfilling, boring, ploughing or pulling.
c) The minimum diameter of conduits shall be at least three (3) times the outside
diameter of the cable to be pulled through the conduit with a minimum of 50 mm
diameter.
d) The number of conduits to be provided in ULX's, URX's and under access roads will
depend on the cable route requirements in that area but provision shall be made for
the following, as applicable.
e) Signalling and power cables shall be in separate conduits to communication cables.
f) High voltage cable shall be in a separate conduit to signalling or communications
cable.
g) Each 1 kv, 2 kv, 6.6 kv or other high voltage cable shall be in a separate conduit,
with separation distances in accordance with Australian Standard AS3000 and
VicTrack Cable Installation Specification TS-SP-013.
h) Unless otherwise approved, fibre optical cable shall be in a separate conduit.
i) Air lines shall be in a separate conduit.
j) Except for directionally bored ULX’s and URX’s; conduits shall be laid parallel and
level in a consistent format in the trench and secured in that position, then carefully
compacted with clean fill to hold them in their desired position.
k) The minimum cover to the upper most section of the conduits shall be as follows:
i. Station platforms, non vehicular areas: 300 mm.
ii. Pedestrian access ways: 450 mm (ACMA requirement)
iii. Heavy vehicular areas: 650 mm.
iv. Rail reserve and station areas: 650 mm
v. Access roads where conduits are less than 650 mm below surface level, the
final 150 mm of fill shall be concrete (25Mpa).
l) Rigid UPVC conduits used for protection of cables shall be white for communication
cable and white with a continuous black marking line for air mains. Orange conduits
shall be used for other cabling.
m) A draw wire of 6 mm polypropylene blue/yellow or similar rope shall be placed in
each conduit and suitably anchored at each end. Conduit ends shall be sealed using
conduit end caps or an approved equivalent to prevent the ingress of dirt or sludge
into the conduits.
n) All cables installed under rail lines shall be enclosed in conduits. The requirements
for installing conduits and pipes under tracks are further specified in AS4799
“Installation of underground utility services and pipe lines within railway areas”. The
preferred installation is by boring or jacking of conduits under tracks.
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 15
o) All conduits under rail lines shall be at a minimum depth of 1200 mm below head of
rail level. This depth shall be maintained for a distance of 3 metres from the nearest
rail. If site restrictions are such that this cannot be achieved, or the conduit extends
into a platform area, then the proposed solution for each instance is to be approved
by the Infrastructure Manager for signalling conduits works, and the VicTrack
Network Maintenance Manager for telecommunications conduit works.
p) The Constructor shall remove any excess spoil from the reserve.
q) All excavations for under rail lines, under roadways, through station platforms,
between rail lines, through waterways shall be backfilled and compacted with
progressive 150 mm thick layers of “A” grade 20 mm crushed rock or in accordance
to the Infrastructure Managers Standard.
s) All PVC Conduits that extend above the ground shall be painted silver to prevent
degradation by the sun and located to protect from mechanical damage, or use rigid
UPVC conduits. Where damage is likely; galvanised steel conduits or suitable
protection for the conduit shall be used in accordance with AS/NZ 3000.
t) Unless otherwise specified; in the Metropolitan area for open type excavations the
minimum number of 100 mm diameter PVC conduits that may be installed shall be:
u) Unless otherwise specified; in the Metropolitan Electrified area for sleeved or bored
type applications the minimum number of 100 mm diameter PVC conduits that may
be installed shall be:
v) Unless otherwise specified; in the Regional areas for excavated, sleeved or bored
type applications the minimum number of 100 mm diameter PVC conduits that may
be installed shall be:
x) Where conduits are to be provided for entry into signal equipment rooms, signal
equipment huts and as related to this specification; there shall be a cable pit
installed outside that building for entry to within that building. This cable pit shall
cater for all conduits required for the works, for future capacity and all other cabling
and conduits requirements within this specification.
y) Spigot type or bell mouth fittings shall be used on all conduits; during cable
installations to ensure that cabling is not damaged during installations.
z) All conduits, used or not, shall be appropriately sealed to prevent water and rodent
entry into the pit/s.
b) Where cables are to be pulled into relay rooms and other similar enclosures, all
spigot ends must face these enclosures.
b) The draw wire shall be continuous for the complete length of the conduit run
c) The draw wire shall have a minim of 2 metres of slack within each and every pit
along the conduit run, and shall be suitably anchored at each end of the conduit run
and then sealed with proprietary end caps to prevent the ingress of dirt, etc.
d) The draw wire shall be restrained in each pit to prevent it being inadvertently pulled
into the conduit/s.
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 17
6.12 Spare Buried Conduits
a) Spare conduits shall be supplied and installed with the following detailed minimum
requirements, and all spare conduits are the minimum spare conduits to be
provided after all cables have been installed:
i. Minor under rail line – One 100 mm orange conduit and one 100 mm white
conduit;
ii. Major under rail line, under roadway and through a station platform – Three
100 mm orange PVC conduits or 25% of the total number of conduits,
whichever is the greater, and also one 100 mm white conduit.
iii. Main Trenches- Three 100 mm orange PVC conduits or 25% of the number of
conduits, whichever is the greater, and also one 100 mm white conduit.
b) In addition to the requirements specified above, the below shall also be considered
for all conduit installations;
i. Type 2 One 100 mm orange conduit and one 100 mm white conduit
ii. Type 3 Two 100 mm orange conduits and one 100 mm white conduit or 25%
of the number of conduits whichever is the greater.
iii. Type 4 Three 100 mm orange conduits and one 100 mm white conduit or
25% of the number of conduits whichever is the greater.
iv. In determining the number of spare conduits to be provided based upon the
percentage of conduits, reference shall be made only to the resultant whole
number and fractions shall be ignored.
v. All spare conduits shall be tested for correct diameter by pulling a plug of a
diameter 90% of the internal conduit diameter through the conduit after
installation, backfilling and compaction.
vi. Where Type 2 or 3 routes is specified; the spare conduit(s) shall be laid over
the cover strip as shown on Drawing No. 112000/5/4.
vii. Where Type 4 route is specified the spare conduits shall be laid over the other
conduits as shown on Drawing No. 112000/5/5.
a) Conduits shall be arranged in fixed format for the full length of the platform or paved
area and shall be supported so that backfilling will not disturb the format.
b) Where only pedestrian traffic is involved the depth of the conduits from the top of the
trench to the top of the highest layer of conduits shall be not less than 300 mm.
c) Where motor vehicles can run over the surface the conduits shall be buried not less
than 300 mm and a reinforced concrete slab (25Mpa), minimum 150 mm thick and
overlapping the conduits by 300 mm each side shall be provided immediately under
the pavement surface material.
d) Cable pits for cable pulling purposes shall be provided in platforms in accordance
with this Standard.
e) Where new railway station platforms are constructed or existing railway station
platforms are required to be excavated; there shall be PVC conduits and cable pits
installed for the length of the excavation within the platform central area and at least
300mm deep. Conduits required are 100 mm PVC 4 orange and 2 white, and cable
pits located no further than 60 metres apart and quantities as defined within this
Standard.
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
18 VRIOGS 012.2.1 REVISION A
6.14 Conduits in High Voltage Areas
a) Where communications cables are required to be run into high voltage earthed
locations such as sub-stations, tie stations and transformer locations, these shall be
looped into and out of the locations and be protected by conduits.
b) An 'earth mat' is provided around high voltage locations as part of the earth
protection arrangements for the high voltage installations. All cables (signalling and
communications) to be installed within 20 metres of the earth mat shall be run in
conduits. Details of the extent of the earthing arrangements around each high
voltage installation will be provided by the Traction Substation Engineer.
c) Existing high voltage earthing arrangements shall not be disturbed under any
circumstances.
c) Conduits and cables shall be encased in clean fill to 50 mm above the uppermost
conduit or cable.
d) Whenever excavation of the track formation occurs the formation shall be restored
with compacted stabilised sand to the top of the capping layer. Any geotechnical
fabric encountered during excavation shall be replaced with like material, which
overlaps the original by at least 300 mm.
e) Ballast shall not be replaced until the trench or excavation has been filled and
compacted level with the top of the capping layer.
f) Where the buried conduit or cable is located in areas other than track formation,
platforms, access roads or pathways, the trench above the clean fill shall be filled
with material free of broken concrete, brick, rubble, wood, glass, rubbish, steel or
other metallic objects that could damage the cable or effect the operation of a
electronic cable locators and shall be free of stones that will not pass through a 30
mm sieve.
g) The top 150 mm at least of fill in access roads or pathways, which are not sealed,
shall consist of material, which as closely as possible matches that in the road or
pathway surface in both texture and density. The fill shall be compacted as
necessary to achieve matching density. Where the road or path is sealed, the trench
shall be capped with the same material to the same thickness as the original seal.
Any substrate or capping layer below the seal shall also be matched.
i) The backfilling of the excavations will normally take up the majority of the spoil.
However, any surplus spoil or unsuitable fill shall be removed for disposal at an
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 19
appropriate agreed location and not spread over the site.
j) Prior to any issue of the Certificates for Practical Completion or similar, all backfilled
trenches and excavations shall be examined and any depressions caused by
settlement or erosion of the backfilling shall be corrected and the cause of the
erosion rectified.
6.16 Compaction
a) Under no circumstances is the cable trench to be compacted by driving excavating
machinery or other vehicles along the trench.
b) In paved areas there shall be a certain amount of moisture evenly spread through
the surface material. Water shall be added by spraying it with a hose until moist.
d) Trenches and other excavations in the track formation, platforms, roads, pathways,
through shunting yards or at the base of embankments shall be:
i. Compacted by mechanical means to achieve 95% Standard Compaction in
accordance with AS1289, and
ii. Filled and compacted in layers of 150 mm maximum thickness to achieve the
specified density.
iii. Tests shall be performed to establish the backfill compaction levels achieved.
The tests shall be taken on a frequency of one (1) test per 200 linear metres
per layer or one (1) test per area per layer where any area of excavation is
less than 200 metres long. Audit testing of soil compaction at all levels may be
carried out by the Regional Representative and due allowance for any
interference caused by this testing shall be made.
e) Where backfill does not achieve the required density, it shall be re-excavated to
within 200 mm of the cover strips and/or conduits and re-filled and compacted
correctly.
f) Following compaction, the trench or excavation shall be finished with a slight
mound, height equal to approximately 25% of trench width, to provide for further
settlement.
a) For small creeks and occasional waterways the cables shall be enclosed in conduits
laid in trenches not less than 1 metre under the creek bed. The conduits shall be
covered to a minimum depth of 300mm with porous bags filled with stabilised sand
and the remainder of the trench then filled to the top with approved heavy grade
hardcore fill.
b) The conduits on creek banks shall be laid at a gentle slope in grooves in the bank so
that the conduits have a minimum cover of 800 mm. The conduits in the banks shall
be secured in position with suitable anchors and covered with porous bags filled with
stabilised sand and topped with other suitable fill to protect the conduits and prevent
erosion of the banks.
c) Every effort shall be made to avoid placing the conduits in any part of the bank
where obvious erosion has been taking place. If this cannot be avoided stabilisation
of the bank on each side of the trench shall be provided.
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
20 VRIOGS 012.2.1 REVISION A
d) The buried conduits shall be extended past the edge of the creek banks a minimum
of 4 metres on either side of the creek or waterway. The minimum depth of the
whole of this conduit run shall be 800 mm.
a) The proposed methods for installing cable routes up or down embankments shall be
submitted for approval to the Infrastructure Manager, and shall be compliant with
this Standard.
b) The methods proposed shall be such that there will be no destabilising of the
embankment and no erosion in the vicinity of the route.
a) The proposed methods for installing cable routes on bridges shall be submitted for
approval to the Infrastructure Manager.
b) The methods proposed shall be such that there will adequate capacity for future
cabling requirements, and all provisions of this Standard shall be complied with;
separation and segregation of the various services, access and egress for
maintenance purposes, installation methods.
c) Suggested appropriate cable route types being; Type 4 conduits and pits, Type 5
ground level troughing (GLT), Type 6 Galvanised steel Troughing (GST).
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 21
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 23
7.3 Drainage
a) In the installation of GLT special care is necessary to ensure that track and other
drainage on the Infrastructure Managers property is not affected. Ramps over
drains, ducts and conduits under the GLT route shall be provided as directed and
approved.
b) During installation of GLT, care shall be taken to ensure that track and other
drainage is not affected. In particular GLT shall not act as a drain. When GLT acts
as a barrier to water, then transverse drainage ducts of not less than 100 cm2 cross
section shall be installed under the troughing at not greater than ten (10) metre
intervals. These shall be located at vantage points to enable the quick dispersal of
storm water.
c) Drainage ducts may be constructed from inverted GLT, pre-cast concrete box drains
or PVC or High Density Poly Ethylene (HDPE) conduits.
a) The GLT lids shall be installed after all the cables are laid, otherwise the lids shall be
fitted as the GLT laying progresses.
b) The GLT shall be thoroughly cleaned prior to installing lids.
c) If the GLT is in the vicinity of pedestrian walkways, etc, the Constructor may be
required to fit the lids as the work progresses and reopen the GLT when required for
cable laying.
d) After the cables are laid all cable entry points to GLT shall be sealed with an
approved compound to prevent the entry of rodents and vermin. If the laying of
cables is not part of the construction of the cable route contract, the cable laying
Constructor shall be responsible for sealing the cable entries and refitting the lids
after cable laying.
e) Where PVC air lines are installed in GLT these shall be laid on top of the signalling
cables.
f) GLT covers or lids that cross over, or might be expected to be used as pathways,
are to be built to a suitable standard as agreed by the Infrastructure Manager, for
inclusion as part of a pathway.
g) Where GLT is being installed adjacent to or across pathways, the top surface should
be of suitable strength and of a non-slip finish to allow its use for pedestrian traffic.
The installation works must not render a pathway unsafe for use, and if so then
alternate access to at least the standard of the existing pathway must be provided.
h) GLT shall have reinforced lids interlocked with the trough. Individual lids should not
weigh any more than 25kgs. The final fitting of lids shall not take place until a cable
inspection by the Infrastructure Manager or their Representative has been
completed.
i) Polyethylene GLT shall have the lids secured to the trough by galvanised metal
screws. There shall be a minimum of six screws per lid (3 per side).
j) Lids are not to be left off the installed polyethylene GLT for any extended period due
to the risk of ground pressure pushing in the sides of the GLT making it difficult to fit
the lids properly.
k) Concrete troughing shall be fitted with lids and “RAILWAY SIGNAL AND
COMMUNICATIONS CABLES” embossed on the top of all lids in letters not less
than 50 mm high and 5 mm deep.
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
24 VRIOGS 012.2.1 REVISION A
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 25
n) GST shall be supported on galvanised steel, concrete posts or bracketed to walls or
structures as provided for in this specification.
o) GST support brackets & fittings shall be of sufficient strength to fully support a full
capacity load. They shall be fully protected from corrosion by hot galvanised dip.
Brackets and fittings shall not be in contact with or be attached to overhead
structures.
p) All GST shall be made continuous by the use of joining sleeves, and these sleeves
shall be installed midpoint between the trunking support posts.
q) Free standing supports:
i. Supporting posts shall be set at 3 metre intervals standing vertical.
ii. Every tenth post shall be constructed of steel (for earthing purposes)
iii. The minimum depth of post holes shall be the greater of 400 mm or one third
of the total length of the post.
iv. In unstable ground, posts shall be concreted into the ground for their entire
buried length.
v. GST support posts can be reinforced concrete, galvanised steel channel
sections or reclaimed rail with a minimum length of 800 mm.
r) The minimum height from ground level to bottom of the lowest trough on a post line
shall be 400 mm.
s) The maximum height from ground level shall be determined on the site survey, and
generally be not higher than 1800 mm (above water courses, etc).
t) Where existing GST is to be utilised by the Constructor, the Constructor shall
restore the GST to a suitable standard by replacing any damaged, corrugated or
missing sections and realigning the support posts.
u) All altered or new GST shall be designed and constructed to prevent the entry of
vermin.
v) Where track access is required; the GST shall be lowered to ground level and all
cabling either installed in conduits and pits as per this Standard, or in GLT with
protection from vehicular traffic (suitably sized and thickness one piece constructed
steel plates fastened securely to the GLT and as acceptable to the Infrastructure
Manager.
w) The Constructor should consider proposed troughing so that it does not interfere
with access pathways. Should GST cross any access pathway, then suitable
arrangements should be included to enable continuous access across the troughing
as it is installed and after completion.
x) The installation works must not render a pathway unsafe for use, and if so then
alternate access to at least the standard of the existing pathway must be provided.
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 27
8.5 Joining Sleeves
a) All troughing shall be made continuous by use of joining sleeves; these sleeves are
installed midway between troughing supports. The sleeve and troughing shall be
bolted together using cadmium plated or galvanised or similarly protected round
head bolts with bolt heads inside the GLT.
b) Jointing sleeves used shall be submitted for approval by the Infrastructure Manager.
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
28 VRIOGS 012.2.1 REVISION A
e) Where troughing is to enter a pit, the pit shall be installed flush with ground level.
Where the final ground level is not certain at the time of pit installation, the Constructor
shall ensure before the conclusion of the works, that no pits are left protruding above
the ground by either re installation or the use of “A” grade 20 mm crushed rock etc.
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 29
8.12 Bends
a) The minimum radius of all bends in the steel troughing route shall comply with the
requirements of this Standard.
b) All bends shall be smooth and rounded to prevent damage to or pressure on cables
due to sharp corners or edges.
c) Changes in direction in the vertical or horizontal plane of the troughing route shall be
at a maximum angle of 22.5 degrees in all cases. Where, for example, 90 degree
bends are required, they shall be made up of four 22.5 degree bends.
a) Troughing support brackets, fixings and other fittings shall be of sufficient strength to
support the troughing without permanent deflection when loaded to full capacity with
cable plus incidental loads up to 100kg applied at any point on the trough. A safety
factor of not less than three (3) shall be applied to the brackets.
b) All components shall be protected against corrosion or made of corrosion resistant
materials, which will provide a service life of at least 30 years.
c) Troughing brackets shall generally not extend past the side of the trough by more
than 25 mm.
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
30 VRIOGS 012.2.1 REVISION A
a) Cable ladder cable route is generally required in areas where clearance limitations
demand it. These areas include tunnels and along platform walls.
b) The environment in tunnels and platform walls suffers from:
i. Contaminated groundwater carrying highly corrosive products leaching
through the wall.
ii. Stray electrical currents.
iii. High levels of ground born vibration.
iv. High velocity winds with buffeting from train movements.
c) The design, construction of and the materials used in the cable route, shall be
suitable for this environment.
9.4 Bends
a) The minimum radius of all bends in the ladder route shall comply with the
requirements of this Standard.
b) All bends shall be smooth and rounded to prevent damage to or pressure on cables
due to sharp corners or edges.
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 31
c) Changes in direction in the horizontal and vertical planes of the ladder route shall be
constructed using the appropriate preformed bends and tees from the ladder
manufacturer’s range.
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
32 VRIOGS 012.2.1 REVISION A
a) The connection of the main cable ladder route to local cable route and equipment
shall be made using purpose built tee pieces from the ladder manufacturer’s product
range.
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 33
a) Where it is not practical to install an under line or under road crossing by the boring
process, the ULX or URX shall be installed by open excavation, trenching,
backfilling and compaction in accordance with this Standard.
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
34 VRIOGS 012.2.1 REVISION A
b) In continuous rock areas, permission may be given for the depth of ULX and URX to
be reduced. In such cases the conduits shall be placed in a trench chased into the
rock and encased in concrete with a minimum concrete cover of 150 mm.
c) The following inspections shall be carried out by the Constructor:-
i. Three days after the construction of the ULX to determine if there is any
subsidence and remedy where necessary.
ii. Three days after any remedial work to determine if the subsidence has been
halted and remedy where necessary.
iii. Two weeks after construction of the ULX if there is subsidence or other defect
and remedy as necessary.
d) In each case, the Infrastructure Manager shall be immediately advised if any
defect is found.
e) All URX works shall comply to VicRoads Standard Specification for Road works and
Bridge Works
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 35
ii. The minimum separation between communications cables and signalling and
power cables shall be as specified within this Standard.
iii. The communications cables shall be above the signalling and HV power
cables for the total length of the cable run
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
36 VRIOGS 012.2.1 REVISION A
a) Cable route for signalling, communications and high voltage sub station/traction
systems shall be installed in accordance to Drawings No. 112000/5/10,
112000/5/11, 112000/5/12, 112000/5/13
b) All installations shall comply with AS/NZS 3000 Wiring Rules and all Standards as
listed within this Standard.
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 37
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
38 VRIOGS 012.2.1 REVISION A
b) The alignment of square pits and chambers shall be parallel to the property line.
c) The size and depth of pits and chambers shall be calculated to accommodate the
particular cable route requirements, access requirements for cable installation and
cable jointing activities. The internal size of all pits and cable turning chambers shall
provide for the minimum bending radius of the largest cable to be installed in them
d) Pit and chamber entries and exits shall be kept to a minimal size. All sharp edges
and burrs shall be removed to prevent cable damage. All cable entries into pits and
cable turning chambers shall have large radius rounded edges to prevent damage to
cables during installation and to eliminate the danger of cables bearing on sharp
corners or edges after installation.
e) Pits and chambers shall not be installed any closer than 3 metres from the outside
edge of the closest running rail; unless otherwise approved by the Infrastructure
Manager.
f) The end of conduits shall not protrude more than 50 mm into the pit space.
g) Conduits are to enter the ends of pits unless site conditions restrict the space to the
extent where that is not possible. Entries through the sides of pits are problematic
with optical fibre cable due to the higher minimum bending radius required. Approval
should be sought from the Infrastructure Manager (and the VicTrack Network
Maintenance Manager where relevant) before conduits and pits are installed. Long
radius bends should be used at pit entries.
h) Pits and chambers installed in open areas shall be protected on two diagonal
corners by white painted rail post (or an agreed alternative structure) to prevent
damage by vehicles. If there is a joint in a pit then the associated protection posts
are to be painted yellow.
i) Buried cables shall access a pit or chamber via 100 mm or suitable size conduits
that extend a minimum 2 metres from the outside entry point. Entry holes shall be
100 mm minimum from the base of the pit or chamber. All conduits are to enter from
the ends of pits and not from under the pit.
j) The exterior entry points for conduits into pits shall be sealed by a mortar compound
(ratio 4:1 sand/cement) or both externally and internally using an approved,
expanding silicone or similar based type sealant.
k) Ground Level Troughing shall rest on a bed of “A” grade 20 mm crushed rock or
clean fill 150 mm in depth for approximately 4 metres before opening into the pit or
chamber.
l) All pits associated with GST to equipment box interface shall have minimum
dimensions of 600 mm x 600 mm as shown on Drawing No. 112000/14/3.
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 39
m) All pits and chambers shall have a prepared foundation of “A” grade 20 mm crushed
rock not less than 150 mm thick. The base of open ended conduit chambers shall
have a compacted base compound (ratio 8:1 crushed rock/cement) prior to
installation. Because of the time required for the cement mix to cure and for the
packing to solidify around an open ended pit or chamber, a temporary support using
a length of treated pine or red gum timber shall be placed either side of centre,
embedded in the crushed rock/cement base.
ii. Main cable routes and under line and under road crossings where depths are
1200 mm require chambers 1 metre minimum in diameter and shall allow a
person to stand within the chamber and work comfortably (or a suitable
alternative as approved by the Infrastructure Manager)
q) All pits and chambers shall be sealed against the entry of water and vermin proofed
by an approved method.
r) Concrete, concrete block and brick pits and cable turning chambers shall have a
concrete floor of not less than 75 mm thick.
s) Pits that have high voltage traction substation cables shall have dimensions no less
than;
a) Pits and cable turning chambers in excess of 1200 mm deep shall have rungs
(minimum width 300 mm constructed from 20 mm diameter galvanised steel rod or
other approved material) cast into the wall at 300 mm (maximum) centres, to permit
safe and easy entry and exit from the pit or chamber.
b) Alternatively, a galvanised steel ladder (of suitable length, with minimum width of
300 mm and 20 mm diameter rungs) fixed securely to the wall at the top and the
bottom of the ladder, may be provided.
a) Drainage arrangements shall be provided at the base of each pit and cable turning
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
40 VRIOGS 012.2.1 REVISION A
chamber. Pits and chambers in areas of clay, rocks and other areas where excess
water run-off and similar are encountered; shall each have a drainage system in
place to cater for the excess water condition, and where identified necessary shall
further have a sump and associated drainage system installed. These may include
installing drainage conduits to the nearest approved railway drain or to a public
stormwater drain or natural drainage course, where possible.
Construction of pits and chambers shall conform to one of the following types, and shall
be Infrastructure Manager approved;
a) Cast in situ concrete pits and cable turning chambers less than or equal to 1500 mm
deep shall be constructed with a minimum wall thickness of 100 mm with a layer of
F82 galvanised mesh reinforcement. The reinforcement shall be located to provide a
minimum cover of 50 mm from the outside of the wall.
b) Cast in situ concrete pits and cable turning chambers deeper than 1,500mm shall be
constructed with a minimum wall thickness of 150 mm with two layers of F62
galvanised mesh reinforcement. The reinforcement shall have a cover of 50 mm.
c) Pits and cable turning chambers constructed from concrete block shall include
appropriate steel reinforcement.
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 41
d) Heavy duty Gatic Highway loading pre-filled type covers shall be used for roadways
and heavy access paths and be rated for the vehicular or pedestrian load applicable
to the location. The precast collar to be constructed around Gatic covers shall have
a thickness of 200 mm. Backfill shall be compacted and level with the collar and
surrounds.
e) Collars for pits or chambers other than Gatic shall be reinforced concrete of A1
20MPa minimum strength rating. The collar shall have a minimal cross sectional
area of 200 mm x 200 mm encircling the top perimeter of the pit or chamber.
f) General purpose pits in open areas do not require concrete collars; however a
backfill of compacted rock in accordance to AS3798, and utilising 20 mm “A” grade
crushed rock shall be provided to a depth of 150 mm and extend 500 mm from the
outer perimeter of the pit.
g) All cable pit lids shall be in accordance to AS3996 Access Covers and Grates.
h) Covers on all other pits and cable turning chambers shall be capable of carrying
incidental live loads of 1.5 kpa and shall be sectioned as necessary to limit the
maximum weight of each section to 45 kg.
i) Gatic or similar covers shall be provided with recessed sockets or eyes for lifting
with appropriate tools. All other covers shall be provided with recessed or retractable
handles so that the cover can be removed without tools.
j) Except for covers in platforms, paved areas, sealed or unsealed roadways and
pathways, covers shall be secured to pits and cable turning chambers with
Infrastructure Manager type locks or similar approved lockable removable covers to
guard against theft, vandalism and unauthorised entry.
k) Communications pits installed outside the rail boundary shall be labelled with
“VicTrack Communications”
b) Where the main buried cable route has conduits installed along its length for
signalling, communications, airlines or similar purposes; then pits and chambers
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
42 VRIOGS 012.2.1 REVISION A
shall be installed at points where there is a major change of direction greater than
25 degrees, or where services leave the main cable route.
c) The maximum length between adjacent pits shall be 300 metres and nominally 150
metres.
d) Where pits and cable turning chambers are installed on embankments, protection
against erosion around and adjacent to the pit and special drainage arrangements
shall be provided to ensure that there will be no undermining or deterioration of the
embankment during periods of heavy rain.
e) Where it is identified that a defined length of spare or slack cable is required for
either;
i. Future use
ii. Additional Cable jointing purposes
iii. Temporary works
iv. Other identified purpose/s
b) Consideration shall be given to the need to have vehicular access for the jointing of
cables and splicing of optical fibre cables, and as such cable jointing pits shall where
possible be positioned where road access is available.
i. The minimum bend radius for the cable cannot be achieved within the GLT,
GST or cable ladder or,
ii. The cable is likely to bear heavily against sharp edges at the bend.
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 43
15.2 Signals
a) In general, local cables from equipment housing to signalling equipment shall be run
in PVC conduits.
b) Where the equipment is more than 50 metres from the equipment housing the
cables may be run in the main cable route for a proportion of the cable run.
c) Local cables in a main cable trench need not be in conduit if the main cables are
direct buried.
15.4 Points
a) The cable route and cabling to the points to provide for point controls and detection
circuits shall be provided in addition to cabling to a telephone post in the vicinity of
the points (where applicable and as identified by the Infrastructure Manager).
b) From buried cable routes the cables to the points equipment shall remain buried
then be brought up to the ground surface in 100 mm diameter conduit positioned
2500 mm from the rail face, adjacent to the points machine cable entry end.
c) From ground level troughing (GLT), which is within the track formation, the cable
from the GLT to the points machine shall be run in surface mounted flexible, heavy
duty, orange PVC conduits.
d) Where the GLT is not in the track formation or is on the other side of an access road
to the points machine, the cables shall be buried 800 mm deep between the GLT
and 2500 mm from the rail face and treated as for buried cable. 100 mm conduit
shall also be provided where the cable descends from the GLT into the ground.
e) Similar requirements shall apply to steel troughing routes.
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
44 VRIOGS 012.2.1 REVISION A
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 45
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
46 VRIOGS 012.2.1 REVISION A
16.5 Handrails
a) Handrails shall also be provided, where necessary, to protect train drivers and
others from drains or embankments, etc as defined within this Standard.
16.6 Walkways
a) Walkways (including handrails) from the rail track to signal post telephones shall be
provided where defined within this Standard.
b) These could include drainage ducts through the foundations or ducts or channels
around the foundations.
a) Where railway lines run alongside public roads; access to signals and signal
gantries shall be provided.
b) This shall include the provision of walkways / steps / handrails as necessary for safe
and convenient access in addition to the provision of a lockable single width gate in
the boundary fence in accordance with this Standard.
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 47
Except when otherwise approved by the Infrastructure Manager, ready mixed concrete
shall be used in the construction of all concrete structures (i.e. no use of dry premix
concrete).
a) Ready mixed concrete and stabilised sand shall be produced in accordance with the
requirements of AS 3600, AS1379.
b) The Constructor shall be responsible for ensuring that concrete and stabilised sand
is ordered with the correct properties for its intended application.
c) Concrete strength at 28 days shall be not less than 25 MPa.
c) Portland cement type A to AS3972 shall be used unless otherwise specified and
aggregate shall comply with AS2758.1.
d) Mixing water shall be clean and free from substances deleterious to concrete or
steel.
e) Chemical admixtures or fly ash shall not be used in the concrete mix.
f) Dry premix early strength concrete is not to be used in the rail environment.
i. Equipment boxes
ii. Equipment huts
iii. Equipment rooms
b) The area around equipment housings shall be cleared and levelled with the use of
compacted 10mm “A” grade crushed rock for a distance of at least 2 metres around
the perimeter of the combined area of all equipment housings, and to a depth of
150mm.
c) Equipment housings shall not be located in flood prone areas, or where inadequate
drainage could lead to flooding. In low lying areas, the local flood history shall be
determined and the top of the equipment box base shall be at a height not lower
than the recorded or projected 100 year flood level.
b) The foundations shall be installed on a level and compacted 100mm thick bedding
of 20 mm “A” grade crushed rock; that encompasses the foundation “footprint area”
plus 500mm in all directions past the perimeter of the foundation. Bathtub
foundation’s inspection cover plates shall be positioned at the rear of the relay box.
d) All equipment boxes shall have secure foundations and safe and convenient access
provided to the equipment box for maintenance and construction staff.
e) Concrete or brick retaining walls shall be provided where necessary to form a
secure level area for equipment box foundations.
f) For sloping or unstable sites the specific proposals shall be prepared for approval,
but the layout and method of cable entry shall, as far as possible, be similar to those
indicated on the drawings referred to above. In areas of sloping or unstable sites,
retaining walls forming part of the equipment box foundations shall be provided as
necessary.
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 49
g) Care shall be taken to ensure that equipment box foundations and equipment box
platform foundations do not impede drainage and do not lead to scouring or erosion.
a) Where it is not practical to install concrete foundations for Equipment Boxes such as
on steeply sloping sites and over culverts, etc. approved raised metal platforms shall
be provided.
b) The platforms shall comply with the relevant parts of AS1657. In addition each
platform shall be capable of carrying a minimum of six (6) persons in addition to the
equipment box(s) and shall not bend, distort or sway or vibrate under this load and
any combination of this load and wind loading (from passing trains).
d) The area under and extended up to 1 metre beyond the extremities of the raised
platforms shall be covered with 50mm of concrete. The area under the raised
platform shall be enclosed to prevent the build-up of rubbish and the growth of grass
or scrub underneath that could put equipment box contents and associated cables
at risk in the event of fires, etc.
a) Access shall be available to all Equipment Boxes from the track in the immediate
vicinity of the equipment box.
b) Where a public road runs alongside the railway line and Equipment Boxes are
positioned inside the boundary fences, personnel access shall be provided from the
public road for maintenance and fault finding purposes.
c) A personnel access gate in the boundary fence shall be provided in accordance with
this Standard.
d) Paths and safety handrails shall be provided between the access gates and
Equipment Boxes.
e) Where pre-existing gates are to be used for access to the Equipment Boxes, the
paths, steps and handrails shall be upgraded to comply with this Standard and / or
the relevant Australian Standards.
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
50 VRIOGS 012.2.1 REVISION A
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 51
c) The above shall equally relate to areas where access is required and the rail line is
located at a lower level, and access is required from the higher level to that of the
lower level.
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
52 VRIOGS 012.2.1 REVISION A
21.2 Gates
a) Gates shall be supplied and installed by the Constructor in accordance with
VRIOGS Standards and Specifications.
21.3 Fencing
a) Fencing shall be supplied and installed by the Constructor in accordance with
VRIOG Standards and Specifications.
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 53
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 55
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
56 VRIOGS 012.2.1 REVISION A
300
Marker Tape
800 minimum
650
White pipe for communications cable
(if required)
50
Separation as required by
ACMA and Victrack
Clean fill
Cover strip or
other suitable
separator
Cover strip
300
Marker Tape
650
White pipe/s for communications cable
(if required)
800 minimum
Separation as required by ACMA 50
and VicTrack
Spare Pipe(s)
Clean fill
Cover strip or
other suitable
separator
Cover strip
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 57
Marker Tape
Clean fill
Orange pipes for signalling, cables LV and HV cables power cables and air lines.
HV power to be in a separate conduit to signalling cables
Air line to be in a separate conduit
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
58 VRIOGS 012.2.1 REVISION A
300
650 minimum
50
100 min
300 minimum
50
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 59
NOTE; For Under Line crossing (ULX) installation works this shall be top of the head of the rail level
and for Under Road crossings (URX) installation works this shall be top of the road way level
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
60 VRIOGS 012.2.1 REVISION A
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 61
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
62 VRIOGS 012.2.1 REVISION A
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 63
Jan 2010
Date
112000 / 5 / 12
Drg No
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
64 VRIOGS 012.2.1 REVISION A
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 65
Concrete
Steel trough tar epoxy coated
to GLT lid
Metal end cover secured
to GLT lid
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
66 VRIOGS 012.2.1 REVISION A
ax
22.5 m
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
Figure 12
x a
(Except where GST continues on the to 150mm above ground
22.5 m
opposite side of the pit)
Metal end cover secured
to GLT lid
Concrete
Drg No
PIT
112000 / 8 / 3
Jan 2010
Date
67
68 VRIOGS 012.2.1 REVISION A
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 69
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
70 VRIOGS 012.2.1 REVISION A
GST
22.5 max
TYPICAL ARRANGEMENT
x 100 thick
required
600 x
PIT
min
600
GST
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 71
Figure 16 Preferred cable pits and covers for local signalling conduit type
works
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
72 VRIOGS 012.2.1 REVISION A
Figure 17 Preferred cable pits and covers for ULX, URX and Main Signalling
Conduit type works
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 73
Figure 18 Preferred cable pits and covers for fibre optic and communications
cabling for conduit works
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
74 VRIOGS 012.2.1 REVISION A
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 75
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
76 VRIOGS 012.2.1 REVISION A
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.
VRIOGS 012.2.1 REVISION A 77
NOTE: This document is controlled only when viewed on the DOT Engineering Standards website.
Any other copy of this document is uncontrolled, and the content may be inaccurate.