Marine Concrete UFGS 03-31-29

Download as pdf or txt
Download as pdf or txt
You are on page 1of 67
At a glance
Powered by AI
The document outlines specifications for marine concrete including mix design, testing, production, placement, curing and quality control. It specifies requirements and procedures to ensure the concrete will meet durability and strength requirements in marine environments.

Concrete mixtures must be designed to meet durability and strength requirements for the project environment through mixture proportioning and preconstruction testing. Fresh and hardened concrete properties, as well as corrosion resistance, must be tested as part of a concrete qualification program.

The key steps include batching, mixing and transporting concrete according to specifications, properly placing and consolidating it using vibration, and curing concrete to prevent cracking and maintain proper hydration. Quality control testing is done at various stages.

**************************************************************************

USACE / NAVFAC / AFCEC / NASA UFGS-03 31 29 (August 2012)


------------------------------
Preparing Activity: NAVFAC Superseding
UFGS-03 31 29 (February 2010)

UNIFIED FACILITIES GUIDE SPECIFICATIONS

References are in agreement with UMRL dated July 2014


**************************************************************************

SECTION TABLE OF CONTENTS

DIVISION 03 - CONCRETE

SECTION 03 31 29

MARINE CONCRETE

08/12

PART 1 GENERAL

1.1 REFERENCES
1.2 DEFINITIONS
1.3 SUBMITTALS
1.4 MODIFICATION OF REFERENCES
1.5 DELIVERY, PLACING, STORAGE, AND HANDLING OF CONCRETE
1.6 CONCRETE QUALITY CONTROL
1.6.1 Quality Control Personnel
1.6.1.1 Quality Manager Qualifications
1.6.1.2 Field Testing Technician and Testing Agency
1.6.2 Laboratory Qualifications for Concrete Qualification Testing
1.6.3 Laboratory Accreditation
1.7 CONCRETE DURABILITY
1.7.1 Concrete Mixture Proportions
1.7.2 Concrete Design Requirements
1.7.3 Concrete Mixture Qualifications
1.7.3.1 Previously Approved Concrete Mixtures
1.7.3.2 New Concrete Mixtures
1.7.4 Project Environment
1.7.4.1 Location Details
1.7.4.2 Exposure Conditions by Element
1.7.5 Concrete Qualification Program
1.7.5.1 Fresh Concrete Properties
1.7.5.2 Hardened Concrete Properties
1.7.5.3 Reinforcing Steel Corrosion Properties
1.7.5.4 Supplemental Corrosion Protection
1.7.6 Mass Concrete Temperature Control Plans
1.8 CONCRETE
1.8.1 Drawings
1.8.1.1 Formwork
1.8.1.2 Reinforcing Steel
1.8.1.3 Precast Elements
1.8.1.4 Joints
1.8.2 Pre-Construction Submittals
1.8.2.1 Curing Concrete Elements

SECTION 03 31 29 Page 1
1.8.2.2 Concrete Curing Plan
1.8.2.3 Form Removal Schedule
1.8.2.4 Concrete Placement and Compaction
1.8.2.5 Concrete Report
1.8.2.6 Coatings
1.8.2.7 Preconstruction Testing of Materials
1.8.2.8 Material Safety Data Sheets
1.8.2.9 Mixture Designs
1.8.3 Sampling
1.8.3.1 Ingredient Material Sampling
1.8.4 Reporting
1.8.4.1 Daily Inspection Reports
1.8.4.2 Sampling Logs
1.8.4.3 Quality Control Data
1.8.4.4 Quality Team Meetings
1.8.4.5 Non-conforming materials
1.8.5 Test Reports
1.8.5.1 Concrete Mixture Requirements
1.8.5.2 Complementary Cementing Materials
1.8.5.2.1 Ground Granulated Blast-Furnace Slag
1.8.5.2.2 Ultra Fine Fly Ash or Pozzolan
1.8.5.3 Silica Fume
1.8.5.4 Aggregates
1.8.5.5 Admixtures
1.8.5.6 Portland Cement
1.8.5.7 Testing During Construction
1.8.5.8 Test Section
1.8.5.9 Acceptability of Work

PART 2 PRODUCTS

2.1 CEMENTITIOUS MATERIALS


2.1.1 Portland Cement
2.1.2 Blended Cements
2.1.3 Pozzolan
2.1.3.1 Fly Ash
2.1.3.2 Raw or Calcined Natural Pozzolan
2.1.3.3 Ultra Fine Fly Ash and Ultra Fine Pozzolan
2.1.4 Ground Granulated Blast-Furnace (GGBF) Slag
2.1.5 Silica Fume
2.1.6 Complementary Cementing Materials (AKA Supplementary
Cementitious Materials (SCM) Content (SCM))
2.2 AGGREGATES
2.3 WATER
2.4 ADMIXTURES
2.4.1 Air Entraining
2.4.2 Accelerating
2.4.3 Retarding
2.4.4 Water Reducing
2.4.5 Corrosion Inhibitors
2.5 NON-SHRINK GROUT
2.6 MATERIALS FOR FORMS
2.6.1 Form Ties and Form-Facing Material
2.7 REINFORCEMENT
2.7.1 Prestressing Steel
2.7.2 Reinforcing Bars
2.7.2.1 Reinforcement and Protective Coating
2.7.3 Mechanical Reinforcing Bar Connectors
2.7.4 Welded Wire Fabric

SECTION 03 31 29 Page 2
**************************************************************************
USACE / NAVFAC / AFCEC / NASA UFGS-03 31 29 (August 2012)
------------------------------
Preparing Activity: NAVFAC Superseding
UFGS-03 31 29 (February 2010)

UNIFIED FACILITIES GUIDE SPECIFICATIONS

References are in agreement with UMRL dated July 2014


**************************************************************************

SECTION 03 31 29

MARINE CONCRETE
08/12

**************************************************************************
NOTE: This guide specification covers the
requirements for reinforced concrete exposed to
marine and chloride environments for projects with a
defined service life. This approach mandates that
the owner define the service life expectations of
the structure (in years) prior to design. This
document is a combination of prescriptive and
performance based specifications. It contains
specific requirements for quality control (actions
taken by the contractor) and quality assurance
(actions that may be taken by the owner). The
performance based portion of this document includes
requirements to predict the service life of the
candidate concrete mixtures prior to proceeding with
construction. During construction, concrete
cylinders are made from the production concrete at
intervals specified by the engineer of record to
measure transport properties and for microscopic
examination of the hardened concrete to verify that
the concrete quality remains consistent and
acceptable. Conventional requirements for
compressive strength and slump remain the same.
Service life modeling software is a tool that, when
used in combination with other tools and good
engineering judgment, enhances the Contractor's and
Owner's confidence that the completed structure will
perform for the defined service life. The only
acceptable service life modeling tool is STADIUM®.
STADIUM® is proprietary and a justification and
approval (J&A) is required. A class J&A for other
than full and open competition is on file at NAVFAC
Headquarters, which allows for the use of this
propriety software to predict the potential for the
concrete mixture to deliver the service life if the
Contractor properly executes placement and curing.
TR-NAVFAC ESC-CI-1215, the "Navy User's Guide to
Quality Assurance of New Concrete Construction"
provides a commentary for the user of this
methodology. Generally, this version of the marine
concrete UFGS is for major projects. For smaller
marine concrete projects and for projects without a

SECTION 03 31 29 Page 5
3.7.1.3 Pervious Sheeting
3.7.1.4 Impervious Sheeting
3.7.2 Liquid Membrane-Forming Curing Compound
3.7.2.1 Application
3.7.2.2 Protection of Treated Surfaces
3.7.3 Liquid Chemical Sealer-Hardener
3.7.4 Curing Periods
3.8 FIELD QUALITY CONTROL
3.8.1 Fresh Concrete Properties
3.8.1.1 Slump Tests
3.8.1.2 Temperature Tests
3.8.1.3 Air Content Tests
3.8.1.4 Unit Weight Test
3.8.2 Hardened Concrete Properties
3.8.2.1 Compressive Strength Tests
3.8.2.2 Transport Property Tests
3.8.2.3 Chloride Ion Concentration
3.8.2.4 Anti-Washout Admixture
3.8.2.5 Non-Destructive Tests
3.8.3 Core Samples and Compressive Strength Testing
3.8.4 Acceptance of Concrete Strength
3.8.4.1 Standard Molded and Cured Strength Specimens
3.8.4.2 Non-Destructive Tests
3.8.4.3 Extracted Core Tests
3.8.5 Inspection
3.9 REPAIR, REHABILITATION AND REMOVAL
3.9.1 Crack Repair
3.9.2 Repair of Weak Surfaces
3.9.3 Failure of Quality Assurance Test Results

-- End of Section Table of Contents --

SECTION 03 31 29 Page 4
**************************************************************************
USACE / NAVFAC / AFCEC / NASA UFGS-03 31 29 (August 2012)
------------------------------
Preparing Activity: NAVFAC Superseding
UFGS-03 31 29 (February 2010)

UNIFIED FACILITIES GUIDE SPECIFICATIONS

References are in agreement with UMRL dated July 2014


**************************************************************************

SECTION 03 31 29

MARINE CONCRETE
08/12

**************************************************************************
NOTE: This guide specification covers the
requirements for reinforced concrete exposed to
marine and chloride environments for projects with a
defined service life. This approach mandates that
the owner define the service life expectations of
the structure (in years) prior to design. This
document is a combination of prescriptive and
performance based specifications. It contains
specific requirements for quality control (actions
taken by the contractor) and quality assurance
(actions that may be taken by the owner). The
performance based portion of this document includes
requirements to predict the service life of the
candidate concrete mixtures prior to proceeding with
construction. During construction, concrete
cylinders are made from the production concrete at
intervals specified by the engineer of record to
measure transport properties and for microscopic
examination of the hardened concrete to verify that
the concrete quality remains consistent and
acceptable. Conventional requirements for
compressive strength and slump remain the same.
Service life modeling software is a tool that, when
used in combination with other tools and good
engineering judgment, enhances the Contractor's and
Owner's confidence that the completed structure will
perform for the defined service life. The only
acceptable service life modeling tool is STADIUM®.
STADIUM® is proprietary and a justification and
approval (J&A) is required. A class J&A for other
than full and open competition is on file at NAVFAC
Headquarters, which allows for the use of this
propriety software to predict the potential for the
concrete mixture to deliver the service life if the
Contractor properly executes placement and curing.
TR-NAVFAC ESC-CI-1215, the "Navy User's Guide to
Quality Assurance of New Concrete Construction"
provides a commentary for the user of this
methodology. Generally, this version of the marine
concrete UFGS is for major projects. For smaller
marine concrete projects and for projects without a

SECTION 03 31 29 Page 5
Water Used in Production of Hydraulic
Cement Concrete

ASTM C1610/C1610M (2010) Standard Test Method for Static


Segregation of Self-Consolidating Concrete
Using Column Technique

ASTM C1611/C1611M (2009b; E 2010) Standard Test Method for


Slump Flow of Self-Consolidating Concrete

ASTM C1621/C1621M (2009b) Standard Test Method for Passing


Ability of Self-Consolidating Concrete by
J-Ring

ASTM C171 (2007) Standard Specification for Sheet


Materials for Curing Concrete

ASTM C172/C172M (2014) Standard Practice for Sampling


Freshly Mixed Concrete

ASTM C173/C173M (2014) Standard Test Method for Air


Content of Freshly Mixed Concrete by the
Volumetric Method

ASTM C192/C192M (2013a) Standard Practice for Making and


Curing Concrete Test Specimens in the
Laboratory

ASTM C231/C231M (2010) Standard Test Method for Air


Content of Freshly Mixed Concrete by the
Pressure Method

ASTM C260/C260M (2010a) Standard Specification for


Air-Entraining Admixtures for Concrete

ASTM C294 (2012) Standard Descriptive Nomenclature


for Constituents of Concrete Aggregates

ASTM C295/C295M (2012) Petrographic Examination of


Aggregates for Concrete

ASTM C309 (2011) Standard Specification for Liquid


Membrane-Forming Compounds for Curing
Concrete

ASTM C31/C31M (2012) Standard Practice for Making and


Curing Concrete Test Specimens in the Field

ASTM C311/C311M (2013) Sampling and Testing Fly Ash or


Natural Pozzolans for Use as a Mineral
Admixture in Portland-Cement Concrete

ASTM C33/C33M (2013) Standard Specification for Concrete


Aggregates

ASTM C39/C39M (2014) Standard Test Method for


Compressive Strength of Cylindrical
Concrete Specimens

SECTION 03 31 29 Page 11
**************************************************************************

PART 1 GENERAL

1.1 REFERENCES

**************************************************************************
NOTE: This paragraph is used to list the
publications cited in the text of the guide
specification. The publications are referred to in
the text by basic designation only and listed in
this paragraph by organization, designation, date,
and title.

Use the Reference Wizard's Check Reference feature


when you add a RID outside of the Section's
Reference Article to automatically place the
reference in the Reference Article. Also use the
Reference Wizard's Check Reference feature to update
the issue dates.

References not used in the text will automatically


be deleted from this section of the project
specification when you choose to reconcile
references in the publish print process.
**************************************************************************

The publications listed below form a part of this specification to the


extent referenced. The publications are referred to within the text by the
basic designation only.

AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS


(AASHTO)

AASHTO M 182 (2005; R 2009) Standard Specification for


Burlap Cloth Made from Jute or Kenaf and
Cotton Mats

AMERICAN CONCRETE INSTITUTE INTERNATIONAL (ACI)

ACI 117 (2010; Errata 2011) Specifications for


Tolerances for Concrete Construction and
Materials and Commentary

ACI 121R (2008) Guide for Concrete Construction


Quality Systems in Conformance with ISO
9001

ACI 201.2R (2008) Guide to Durable Concrete

ACI 211.1 (1991; R 2009) Standard Practice for


Selecting Proportions for Normal,
Heavyweight and Mass Concrete

ACI 214R (2011) Evaluation of Strength Test Results


of Concrete

ACI 301 (2010; Errata 2011) Specifications for


Structural Concrete

SECTION 03 31 29 Page 7
d. "Cementitious material" as used herein shall include portland cement
and any pozzolanic material such as fly ash, natural pozzolans, ground
granulated blast-furnace slag and silica fume.

e. "Complementary cementing materials" (CCM) include coal fly ash,


granulated blast-furnace slag, natural or calcined pozzolans, and
ultra-fine coal ash when used in such proportions to replace the
portland cement that result in considerable improvement to
sustainability, durability and in some cases a reduction in initial
cost.

f. "Chloride threshold" (CTH) is the concentration of chloride ions in


concrete that is generally assumed to be the minimum necessary to
initiate corrosion of the reinforcing steel when all other necessary
conditions are satisfied. The threshold value is expressed in parts per
million (ppm) by mass of concrete.

g. "Concrete System" is the term describing a structural element comprised


of concrete, reinforcing steel and concrete cover.

h. "Corrosion initiation period" (Ti) is the number of years assumed before


the chloride ion reaches the chloride threshold for the reinforcing
steel at the depth of the steel. The corrosion initiation period will
be determined by STADIUM® software.

i. "Corrosion Propagation period" (Tp) is the number of years after the


corrosion initiation period before corrosion manifest as visible
cracking and spalling of the concrete cover to a degree that will
require extensive concrete repair. Based on evidence provided by the
Contractor and reviewed by the agency's Subject Matter Expert in
Concrete Materials, on a case-by-case basis the Contracting Officer may
approve extension to the typical corrosion propagation period of 15
years. Use of supplemental corrosion protection methods and benign
environmental conditions are two ways to extend the assumed propagation
period.

j. "Design strength" (f'c) is the specified compressive strength of


concrete at time(s) specified by Contracting Officer to meet structural
design criteria. Typical duration is 28 days; however, the Contracting
Officer and Engineer of Record are encouraged to consider specifying
strength at 56 or 90 days. For high-volume fly ash concrete mixtures,
the duration shall be a minimum of 56 days.

k. "Effective Diffusion Coefficient" (Deff) is a coefficient that combines


the ionic diffusion coefficient Doh and volume of permeable voids.

l. "Exposure Conditions" are the environmental parameters used in service


life modeling for each type of concrete element based on the structure
location and anticipated boundary conditions.

m. "Field test strength" (fcr) is the required compressive strength of


concrete to meet structural and durability criteria. Determine (fcr)
during mixture proportioning process.

n. "High-volume fly ash concrete" has a minimum of 50 percent Class F fly


ash as a partial replacement to portland cement.

o. "Ionic Diffusion Coefficient" (Doh ) is the ionic diffusion coefficient


as determined per the ionic diffusion coefficient migration testing for

SECTION 03 31 29 Page 14
ASTM A1055/A1055M (2010; E 2011) Standard Specification for
Zinc and Epoxy Dual Coated Steel
Reinforcing Bars

ASTM A1064/A1064M (2013) Standard Specification for


Carbon-Steel Wire and Welded Wire
Reinforcement, Plain and Deformed, for
Concrete

ASTM A276 (2013a) Standard Specification for


Stainless Steel Bars and Shapes

ASTM A416/A416M (2012) Standard Specification for Steel


Strand, Uncoated Seven-Wire for
Prestressed Concrete

ASTM A615/A615M (2014) Standard Specification for Deformed


and Plain Carbon-Steel Bars for Concrete
Reinforcement

ASTM A706/A706M (2014) Standard Specification for


Low-Alloy Steel Deformed and Plain Bars
for Concrete Reinforcement

ASTM A767/A767M (2009) Standard Specification for


Zinc-Coated (Galvanized) Steel Bars for
Concrete Reinforcement

ASTM A775/A775M (2007b; R2014) Standard Specification for


Epoxy-Coated Steel Reinforcing Bars

ASTM A882/A882M (2004a; R 2010) Standard Specification for


Filled Epoxy-Coated Seven-Wire
Prestressing Steel Strand

ASTM A886/A886M (2012) Standard Specification for Steel


Strand, Indented, Seven-Wire
Stress-Relieved for Prestressed Concrete

ASTM A934/A934M (2013) Standard Specification for


Epoxy-Coated Prefabricated Steel
Reinforcing Bars

ASTM A955/A955M (2014) Standard Specification for Deformed


and Plain Stainless-Steel Bars for
Concrete Reinforcement

ASTM C1017/C1017M (2013) Standard Specification for Chemical


Admixtures for Use in Producing Flowing
Concrete

ASTM C1064/C1064M (2011) Standard Test Method for


Temperature of Freshly Mixed
Hydraulic-Cement Concrete

ASTM C1074 (2011) Standard Practice for Estimating


Concrete Strength by the Maturity Method

SECTION 03 31 29 Page 9
ASTM C1077 (2014) Standard Practice for Laboratories
Testing Concrete and Concrete Aggregates
for Use in Construction and Criteria for
Laboratory Evaluation

ASTM C1107/C1107M (2013) Standard Specification for Packaged


Dry, Hydraulic-Cement Grout (Nonshrink)

ASTM C1152/C1152M (2004; E 2012; R 2012) Standard Test


Method for Acid-Soluble Chloride in Mortar
and Concrete

ASTM C1157/C1157M (2011) Standard Specification for


Hydraulic Cement

ASTM C1202 (2012) Standard Test Method for Electrical


Indication of Concrete's Ability to Resist
Chloride Ion Penetration

ASTM C1218/C1218M (1999; R 2008) Standard Specification for


Water-Soluble Chloride in Mortar and
Concrete

ASTM C1231/C1231M (2013) Standard Practice for Use of


Unbonded Caps in Determination of
Compressive Strength of Hardened Concrete
Cylinders

ASTM C1240 (2014) Standard Specification for Silica


Fume Used in Cementitious Mixtures

ASTM C1260 (2007) Standard Test Method for Potential


Alkali Reactivity of Aggregates
(Mortar-Bar Method)

ASTM C138/C138M (2013a) Standard Test Method for Density


("Unit Weight"), Yield, and Air Content
(Gravimetric) of Concrete

ASTM C143/C143M (2012) Standard Test Method for Slump of


Hydraulic-Cement Concrete

ASTM C150/C150M (2012) Standard Specification for Portland


Cement

ASTM C1567 (2013) Standard Test Method for Potential


Alkali-Silica Reactivity of Combinations
of Cementitious Materials and Aggregate
(Accelerated Mortar-Bar Method)

ASTM C157/C157M (2008) Standard Test Method for Length


Change of Hardened Hydraulic-Cement Mortar
and Concrete

ASTM C1585 (2013) Standard Test Method for


Measurement of Rate of Absorption of Water
by Hydraulic-Cement Concretes

ASTM C1602/C1602M (2012) Standard Specification for Mixing

SECTION 03 31 29 Page 10
Water Used in Production of Hydraulic
Cement Concrete

ASTM C1610/C1610M (2010) Standard Test Method for Static


Segregation of Self-Consolidating Concrete
Using Column Technique

ASTM C1611/C1611M (2009b; E 2010) Standard Test Method for


Slump Flow of Self-Consolidating Concrete

ASTM C1621/C1621M (2009b) Standard Test Method for Passing


Ability of Self-Consolidating Concrete by
J-Ring

ASTM C171 (2007) Standard Specification for Sheet


Materials for Curing Concrete

ASTM C172/C172M (2014) Standard Practice for Sampling


Freshly Mixed Concrete

ASTM C173/C173M (2014) Standard Test Method for Air


Content of Freshly Mixed Concrete by the
Volumetric Method

ASTM C192/C192M (2013a) Standard Practice for Making and


Curing Concrete Test Specimens in the
Laboratory

ASTM C231/C231M (2010) Standard Test Method for Air


Content of Freshly Mixed Concrete by the
Pressure Method

ASTM C260/C260M (2010a) Standard Specification for


Air-Entraining Admixtures for Concrete

ASTM C294 (2012) Standard Descriptive Nomenclature


for Constituents of Concrete Aggregates

ASTM C295/C295M (2012) Petrographic Examination of


Aggregates for Concrete

ASTM C309 (2011) Standard Specification for Liquid


Membrane-Forming Compounds for Curing
Concrete

ASTM C31/C31M (2012) Standard Practice for Making and


Curing Concrete Test Specimens in the Field

ASTM C311/C311M (2013) Sampling and Testing Fly Ash or


Natural Pozzolans for Use as a Mineral
Admixture in Portland-Cement Concrete

ASTM C33/C33M (2013) Standard Specification for Concrete


Aggregates

ASTM C39/C39M (2014) Standard Test Method for


Compressive Strength of Cylindrical
Concrete Specimens

SECTION 03 31 29 Page 11
specification. Resume shall detail the education, training and
experience related to the project-specific test methods and deleterious
materials and shall be submitted at least 20 days before petrographic
and deleterious materials examination is to commence.

g. Concrete Batch Plant Operator: National Ready Mix Concrete


Association (NRMCA) Plant Manager Certification at the Plant Manager
level.

1.6.1.1 Quality Manager Qualifications

The quality manager shall hold a current license as a professional engineer


in a U.S. state or territory with experience on at least five (5) similar
projects. Evidence of extraordinary proven experience may be considered by
the Contracting Officer as sufficient to act as the Quality Manager.

1.6.1.2 Field Testing Technician and Testing Agency

Submit data on qualifications of proposed testing agency and technicians


for approval by the Contracting Officer prior to performing testing on
concrete.

a. Work on concrete under this contract shall be performed by an ACI


Concrete Field Testing Technician Grade 1 qualified in accordance with
ACI SP-2 or equivalent. Equivalent certification programs shall
include requirements for written and performance examinations as
stipulated in ACI SP-2.

b. Testing agencies that perform testing services on reinforcing steel


shall meet the requirements of ASTM E329.

c. Testing agencies that perform testing services on concrete materials


shall meet the requirements of ASTM C1077.

d. Testing agencies or engineering companies that characterize the


transport properties of the concrete or conduct service life modeling
analysis shall be STADIUM® certified or pre-approved by the Contracting
Officer with concurrence of the agency's Subject Matter Expert in
Concrete Materials.

1.6.2 Laboratory Qualifications for Concrete Qualification Testing

The concrete testing laboratory shall have the necessary equipment and
experience to accomplish required testing. The laboratory shall meet the
requirements of ASTM C1077, be Cement and Concrete Reference Laboratory
(CCRL) inspected, and be a STADIUM® certified laboratory.

1.6.3 Laboratory Accreditation

Laboratory and testing facilities shall be provided by and at the expense


of the Contractor. The laboratories performing the tests shall be
accredited in accordance with ASTM C1077, including ASTM C78/C78M and
ASTM C1260. The accreditation shall be current and shall include the
required test methods, as specified.

a. Aggregate Testing and Mix Proportioning: Aggregate testing and mixture


proportioning studies shall be performed by an accredited laboratory
and under the direction of a licensed/registered civil engineer in a
U.S. state or territory, who shall sign all reports and designs.

SECTION 03 31 29 Page 23
ASTM D512 (2012) Chloride Ion in Water

ASTM D516 (2011) Sulfate Ion in Water

ASTM D6690 (2012) Standard Specification for Joint


and Crack Sealants, Hot Applied, for
Concrete and Asphalt Pavements

ASTM D75/D75M (2013) Standard Practice for Sampling


Aggregates

ASTM E329 (2014) Standard Specification for Agencies


Engaged in the Testing and/or Inspection
of Materials Used in Construction

CONCRETE REINFORCING STEEL INSTITUTE (CRSI)

CRSI 10MSP (2009; 28th Ed) Manual of Standard Practice

U.S. ARMY CORPS OF ENGINEERS (USACE)

COE CRD-C 39 (1981) Test Method for Coefficient of


Linear Thermal Expansion of Concrete

COE CRD-C 572 (1974) Corps of Engineers Specifications


for Polyvinylchloride Waterstops

COE CRD-C 61 (1989A) Test Method for Determining the


Resistance of Freshly Mixed Concrete to
Washing Out in Water

U.S. GENERAL SERVICES ADMINISTRATION (GSA)

FS SS-S-200 (Rev E; Am 1; Notice 1) Sealant, Joint,


Two-Component, Jet-Blast-Resistant,
Cold-Applied, for Portland Cement Concrete
Pavement

U.S. NAVAL FACILITIES ENGINEERING COMMAND (NAVFAC)

TR-NAVFAC ESC-CI-1215 (2012) Navy User's Guide for Quality


Assurance of New Concrete Construction

1.2 DEFINITIONS

a. "Aging factor" is used to estimate the change in the ionic diffusion


coefficient over time. The aging factor is defined as the ratio of the
ultimate ionic diffusion coefficient (Doh ) to the 28-day Doh .

b. "Atmospheric zone" is any portion of the waterfront structure above the


splash zone.

c. "Boundary Condition" is the environmental conditions in contact with the


concrete. The service life modeling tool must account for short term
and long-term changes in environmental conditions at the boundary
interface between the specific concrete element and the environment,
including wetting and drying due to daily tidal cycles and/or changes
over its lifecycle.

SECTION 03 31 29 Page 13
d. "Cementitious material" as used herein shall include portland cement
and any pozzolanic material such as fly ash, natural pozzolans, ground
granulated blast-furnace slag and silica fume.

e. "Complementary cementing materials" (CCM) include coal fly ash,


granulated blast-furnace slag, natural or calcined pozzolans, and
ultra-fine coal ash when used in such proportions to replace the
portland cement that result in considerable improvement to
sustainability, durability and in some cases a reduction in initial
cost.

f. "Chloride threshold" (CTH) is the concentration of chloride ions in


concrete that is generally assumed to be the minimum necessary to
initiate corrosion of the reinforcing steel when all other necessary
conditions are satisfied. The threshold value is expressed in parts per
million (ppm) by mass of concrete.

g. "Concrete System" is the term describing a structural element comprised


of concrete, reinforcing steel and concrete cover.

h. "Corrosion initiation period" (Ti) is the number of years assumed before


the chloride ion reaches the chloride threshold for the reinforcing
steel at the depth of the steel. The corrosion initiation period will
be determined by STADIUM® software.

i. "Corrosion Propagation period" (Tp) is the number of years after the


corrosion initiation period before corrosion manifest as visible
cracking and spalling of the concrete cover to a degree that will
require extensive concrete repair. Based on evidence provided by the
Contractor and reviewed by the agency's Subject Matter Expert in
Concrete Materials, on a case-by-case basis the Contracting Officer may
approve extension to the typical corrosion propagation period of 15
years. Use of supplemental corrosion protection methods and benign
environmental conditions are two ways to extend the assumed propagation
period.

j. "Design strength" (f'c) is the specified compressive strength of


concrete at time(s) specified by Contracting Officer to meet structural
design criteria. Typical duration is 28 days; however, the Contracting
Officer and Engineer of Record are encouraged to consider specifying
strength at 56 or 90 days. For high-volume fly ash concrete mixtures,
the duration shall be a minimum of 56 days.

k. "Effective Diffusion Coefficient" (Deff) is a coefficient that combines


the ionic diffusion coefficient Doh and volume of permeable voids.

l. "Exposure Conditions" are the environmental parameters used in service


life modeling for each type of concrete element based on the structure
location and anticipated boundary conditions.

m. "Field test strength" (fcr) is the required compressive strength of


concrete to meet structural and durability criteria. Determine (fcr)
during mixture proportioning process.

n. "High-volume fly ash concrete" has a minimum of 50 percent Class F fly


ash as a partial replacement to portland cement.

o. "Ionic Diffusion Coefficient" (Doh ) is the ionic diffusion coefficient


as determined per the ionic diffusion coefficient migration testing for

SECTION 03 31 29 Page 14
(1) ASTM C1611/C1611M slump flow shall not be greater than 609.6 mm
24 inches, with visual stability index not greater than 1.

(2) ASTM C1621/C1621M Passing ability using the J-ring. Spread within
25.4 mm 1 inch less than the slump flow.

(3) Passing ability using the L-Box between 4 and 8 seconds

(4) ASTM C1610/C1610M, static segregation shall be less than 4.0


percent.

For process control sampling, the slump flow limit as determined by


ASTM C1611/C1611M shall be no greater than 609.6 mm 24 inches and the
visual stability index limit shall be no greater than 1.0.

d. Underwater concrete: When the concrete is intended for placement under


water using the tremie technique, the concrete shall be proportioned to
be cohesive and flow with minimal out segregation. Viscosity modifying
admixtures are permitted for underwater concrete. Proportioning
guidance in ACI 304R shall be considered. Concrete mixtures shall be
qualified for tremie placement methods based on a trial placement
approved by the Contracting Officer.

1.7.5.2 Hardened Concrete Properties

**************************************************************************
NOTE: Navy waterfront structures typically take a
year or more to complete. With time all concrete
continues to gain strength. The Engineer of Record
is encouraged to design the structural elements
based on the compressive strength that will be
achieved at 56 or 90 days rather than at 28 days.
Doing so will better allow the Contractor to develop
and place concrete mixtures with less portland
cement. Excessive use of cement leads to more cracks
and shorter-lived structures. Embracing this
approach will result in structures that are less
expensive, greener and more sustainable.
**************************************************************************

a. Compressive Strength: The structural engineer shall specify the minimum


compressive strength results at [28] [56] days. Determine compressive
strength (f'cr) for qualification of concrete mixtures and for quality
acceptance testing. A compressive strength test result is defined as
the mean of three properly conducted tests on 100 by 200 mm 4 by 8 inch
cylinders in accordance with ASTM C39/C39M. Alternatively and for
concrete mixtures containing a maximum size aggregate greater than 25.4
mm 1 inch, a strength test result shall be defined as the mean of two
properly conducted 28-day tests on 150 by 300 mm 6 by 12 inch
cylindrical specimens in accordance with ASTM C39/C39M. In addition:

(1) Specified Compressive Strength: For structural concrete elements


exposed in a marine environment, the minimum specified [28] [56]
day design strength is denoted as (f'c). Strength of concrete
containing 50 percent or more fly ash shall be specified at a
minimum of 56 days.

(2) Required Average Strength: The concrete shall be proportioned such

SECTION 03 31 29 Page 29
z. "Required compressive strength" (f'cr) is the mean compressive strength
of concrete required to meet structural criteria. The required strength
is the mean concrete strength for tests of properly batched concrete at
the age specified herein.

aa. "Service life" is the Owner's stated expectation for the number of
years that the structure will function without needing major concrete
rehabilitation. A service life of 75 years for pile supported piers,
wharves and bridges is a reasonable objective. Service life is defined
as the number of years before major restoration is necessary given
minimal maintenance to the structure during its life. Major
restoration is defined as extensive areas that require extensive
repairs using a jack hammer or other destructive means to prepare the
concrete for rehabilitation. Service life is further defined as the
summation of the corrosion initiation period (Ti) and the corrosion
propagation period (Tp) for a given concrete system.

bb. "Service Life Modeling" in the context of this document refers to a


methodology using STADIUM® finite element software. It predicts the
time before the chloride ion contamination will reach a level of
reinforcing that is likely to result in the initiation of steel
corrosion. It also predicts delayed ettringite reaction, sulfate
attack and other chemical deterioration mechanisms.

cc. "Specified Effective Diffusion Coefficient" (Dspec) is the calculated


effective diffusion coefficient at which the chloride ion content is
within 10 percent (50 ppm) of the chloride threshold, at the steel
cover depth, for the given exposure.

dd. "Splash zone" is the portion of the structure just above the tidal
zone. This portion of the structure is predominantly dry, but is
likely to intermittently wet by wave action and wind driven spray. For
the purposes of this specification, the splash zone is defined as
follows:

(1) for locations protected by seawalls or otherwise sheltered from


open-ocean waves, the 2 meters 6 feet area just above the tidal
zone;

(2) for unprotected locations, the 6 meters 20 feet area just above
the tidal zone.

ee. "Submerged zone" is defined as the submerged portion of the structure.


For the purposes of this specification, any element or portion thereof
that is located below Mean Lower Low Water (MLLW). In areas with
minimal tides, it would be defined as that portion of the element below
Mean Sea Level (MSL).

ff. "Supplemental Corrosion Protection" includes (but not limited to)


fusion-bonded epoxy-coated steel reinforcing, galvanized steel
reinforcing, stainless reinforcing, corrosion inhibitors, barrier
coatings to the concrete surface, and cathodic protection.

gg. "Test Section" is a slab or wall separate from the main structure and
constructed prior to main construction as an all inclusive
demonstration of methods and materials. The adequacy of the Test
Section must be approved by the owner's representative prior to
construction of the project.

SECTION 03 31 29 Page 16
hh. "Tidal zone" is defined as the portion of the structure regularly
wetted by wave action. For the purposes of this specification, any
element or portion thereof that is located between Mean Lower Low Water
(MLLW) and Mean Higher High Water (MHHW) is in the tidal zone. In
areas with minimal tides, this would be defined as the area located
between Mean Sea Level (MSL) and Mean High Water (MHW).

ii. "Tolerance Limit" is defined for each transport parameter as the


characteristic value that will be surpassed in 1 of 10 batches, at a 90
percent confidence level. This definition is provided for reference
only, additional documentation and evaluation is needed prior to it
being suggested as prescriptive criteria.

jj. "Transport properties" refers to the properties that characterize the


rate of chloride penetration into a concrete element. These properties
include: volume of permeable voids (phi), ionic diffusion coefficient (D
oh ), aging factor, and moisture transport coefficient (MTC).

kk. "Transport property testing" refers to the testing procedures that


characterize the rate of chloride penetration into a concrete element.
These properties are used as input data for the service life modeling.

ll. "Volume of Permeable Voids" (phi) is the porosity of the concrete as


determined by ASTM C642.

mm. "50 percent Saturation water content" (S50 percent) is the degree of
saturation of the saturated concrete after being allowed to come to
equilibrium at 50 percent relative humidity. It is defined as the
volume of the water in the concrete at equilibrium divided by the
volume of permeable voids (phi) as determined by ASTM C642.

1.3 SUBMITTALS

**************************************************************************
NOTE: Review Submittal Description (SD) definitions
in Section 01 33 00 SUBMITTAL PROCEDURES and edit
the following list to reflect only the submittals
required for the project.

The Guide Specification technical editors have


designated those items that require Government
approval, due to their complexity or criticality,
with a "G". Generally, other submittal items can be
reviewed by the Contractor's Quality Control
System. Only add a “G” to an item, if the
submittal is sufficiently important or complex in
context of the project.

For submittals requiring Government approval on Army


projects, a code of up to three characters within
the submittal tags may be used following the "G"
designation to indicate the approving authority.
Codes for Army projects using the Resident
Management System (RMS) are: "AE" for
Architect-Engineer; "DO" for District Office
(Engineering Division or other organization in the
District Office); "AO" for Area Office; "RO" for
Resident Office; and "PO" for Project Office. Codes

SECTION 03 31 29 Page 17
Table 4 -Chloride Threshold Level and Corrosion Propagation Time

Description UNS EN No. Chloride Corrosion


Alloy Threshold Propagation
(CTH), Period
ppm (Tp) max,
years
ASTM A276 S31803 1.4462 5000 15
Duplex Stainless 2205 S32205

*See TR-NAVFAC ESC-CI-1215

** All other reinforcement not listed require approval of agency's


Subject Matter Expert in Concrete Materials

1.7.5.4 Supplemental Corrosion Protection

If the available materials in the region of the project cannot practically


be made to meet the service life based on testing and service life modeling
without the use of supplemental corrosion protection, then the Contractor
shall prepare a recommendation on how to accomplish the service life using
imported materials and/or supplemental corrosion protection. With input
from the agency's Subject Matter Expert in Concrete Materials, the
Contracting Officer shall consider approval of the Contractor's
recommendation on a case-by-case basis.

1.7.6 Mass Concrete Temperature Control Plans

a. Thirty days minimum prior to concrete placement, submit for approval a


mass concrete temperature control plan that includes:

(1) Location and identification of temperature monitoring sensors.

(2) Product data for automated temperature sensors and recording


equipment.

(3) Cooling pipe layout diagram with sizes and materials, if used.

(4) Proposed insulation materials and associated R-values.

(5) Anticipated form removal schedule and curing procedures.

(6) Maximum allowable concrete placement temperature for the range of


anticipated ambient temperatures based on thermal modeling.

(7) Monitoring procedures and contingency plans.

Concrete placement temperature shall be based on results of thermal


modeling for the element incorporating: the heat of hydration and specific
heat capacity for the concrete mixture, solar gain, and heat transfer to
the environment through formwork, insulation, and cooling techniques.

Mass concrete temperature control shall be monitored using automated


temperature recording devices that allow wireless transmission of data to
an on-site host computer for real-time monitoring of temperatures.

Temperature control sensor layout for each placement shall be provided with

SECTION 03 31 29 Page 34
Joint sealants

Materials for curing concrete

Material Safety Data Sheets

Mechanical Reinforcing Bar Connectors[; G][; G, [_____]]

Non-shrink grout

Preformed joint filler

Prestressing Steel[; G][; G, [_____]]

Reinforcing Bars[; G][; G, [_____]]

Reinforcement and Protective Coating[; G][; G, [_____]]

Reinforcement supports

Sealer-hardener

Waterstops

Welded Wire Fabric

SD-04 Samples

**************************************************************************
NOTE: Where flat surface finishing is important,
provide a sample installation to train the crew.
**************************************************************************

Mass Concrete Mock-up

Test Section

SD-05 Design Data

Concrete Mixture Requirements[; G][; G, [_____]]

Mixture designs

Mass Concrete Temperature Control Plans[; G][; G, [_____]]

SD-06 Test Reports

[ Mass Concrete Mock-up

] Air Entraining

Aggregates

Admixtures

As-Built Report

Cement

SECTION 03 31 29 Page 19
Concrete mixture proportions

Concrete Test Reports

Complementary Cementing Materials

Durability Modeling (Using STADIUM®)

Fresh Concrete Properties

Hardened Concrete Properties

Mechanical Reinforcing Bar Connectors

[ Silica fume
]
Reinforcing Bars

Reinforcement and Protective Coating

Water

SD-07 Certificates

Admixtures

Cementitious Materials

Cementitious material mill certificates

Field testing technician and testing agency

SD-08 Manufacturer's Instructions

Coatings

SD-11 Closeout Submittals

Aggregate Moisture Content

Aggregate Sampling

As-built report including observed defects and transport property


test results

Concrete Test Reports

Quality Control Charts

Daily inspection reports

Quality Team Meetings

Sampling logs

1.4 MODIFICATION OF REFERENCES

Accomplish work in accordance with ACI publications except as modified


herein. Consider the advisory or recommended provisions to be mandatory,

SECTION 03 31 29 Page 20
as though the word "shall" had been substituted for the words "should" or
"could" or "may," wherever they appear. Interpret reference to the
"Building Official," the "Structural Engineer," and the
"Architect/Engineer" to mean the Contracting Officer.

1.5 DELIVERY, PLACING, STORAGE, AND HANDLING OF CONCRETE

Follow ACI 301M ACI 301, ACI 304R, and ASTM A934/A934M requirements and
recommendations. Do not deliver concrete until vapor barrier, forms,
reinforcement, embedded items, and chamfer strips are in place and ready
for concrete placement. Store reinforcement of different sizes and shapes
in separate piles or racks raised above the ground. Protect materials from
contaminants such as grease, oil, and dirt. Ensure materials can be
accurately identified after bundles are broken and tags removed.

1.6 CONCRETE QUALITY CONTROL

**************************************************************************
NOTE: Service Life Modeling

Use of service life modeling predicts the


performance of the concrete mixture when placed and
cured properly. Concrete sampling during production
and (if necessary) from the completed structure
provides additional data to predict the service
life. This methodology enhances the Navy's
confidence that the structure will perform without
major repairs for the defined service life. It is
recommended that every significant structure employ
this section inclusive of service life modeling. The
Owner and the Engineer of Record shall determine if
this approach is applicable. Additional information
is provided in TR-NAVFAC ESC-CI-1215.

The goal is to provide quality concrete with the


specified concrete cover to protect the steel, which
provides the primary protection mechanism against
chemical deterioration and corrosion related
damage. All other corrosion protection strategies
are considered to be supplemental and include (but
are not limited to): barrier coatings to the
concrete surface, fusion-bonded epoxy-coated steel,
corrosion inhibitors, galvanized, stainless, MMFX,
Z-bar reinforcing and cathodic protection. All of
which may provide some life extension but by how
much is considered to be speculation for real
structures exposed to chloride environments. If the
available materials in the region of the project are
inadequate to meet the requirements for shrinkage,
compressive strength, constructability and service
life then the Contractor shall prepare a
recommendation for review by the agency's Subject
Matter Expert in Concrete Materials and approval by
the Contracting Officer and Engineer of Record on a
case-by-case basis to use supplemental corrosion
protection to meet project requirements.

The Navy recognizes only one numerical modeling


software program for predicting the service life of

SECTION 03 31 29 Page 21
concrete structures, STADIUM®. The most current
version of the software shall be used. Service life
modeling is a tool to be used with engineering
judgment to aid in the design, material selection
and construction methods to produce a durable
structure.

Where they are available, specify only ACI certified


personnel. Check the American Concrete Institute
(ACI) website for local availability:
www.concrete.org/Certification.

**************************************************************************

The objective of the concrete quality control program is for the Contractor
to outline the procedures that will be used to construct a structure that
will obtain the design service life. The Contractor shall develop and
submit for approval a concrete quality control program in accordance with
the guidelines of ACI 121R and as specified herein. The plan shall include
approved laboratories. The Contractor shall provide direct oversight for
the concrete qualification program inclusive of service life modeling,
associated sampling and testing. If concrete cylinders tested during
production indicate inadequate strength, excessive ion-transport
properties, or inadequate mixing, then the owner may require the Contractor
to extract concrete core samples from the hardened concrete for analysis at
Contractor's expense to assure that the quality of the concrete as placed
and cured will satisfy the defined service life.

Develop and submit for approval a concrete quality control program in


accordance with the guidelines of ACI 121R and able to meet the defined
service life using the methodology herein. Maintain a copy of ACI SP-15 and
CRSI 10MSP at the project site.

1.6.1 Quality Control Personnel

The contractor shall submit for approval an organizational chart defining


the quality control hierarchy, the responsibilities of the various
positions, including the names and qualifications of the individuals in
those positions.

Submit American Concrete Institute certification for the following:

a. CQC personnel responsible for inspection of concrete operations.

b. Lead Foreman or Journeyman of the Concrete Placing, Finishing, and


Curing Crews.

c. Field Testing Technicians: ACI Concrete Field Testing Technician,


Grade I.

d. Laboratory Testing Technicians: ACI Concrete Strength Testing


Technician and Laboratory Testing Technician, Grade I or II.

e. STADIUM® certified laboratory and users of STADIUM® software.

f. Petrographer: Bachelor of Science degree in geology or petrography,


trained in petrographic examination of concrete aggregate according to
ASTM C294 and ASTM C295/C295M and trained in identification of the
specific deleterious processes and tests identified in this

SECTION 03 31 29 Page 22
specification. Resume shall detail the education, training and
experience related to the project-specific test methods and deleterious
materials and shall be submitted at least 20 days before petrographic
and deleterious materials examination is to commence.

g. Concrete Batch Plant Operator: National Ready Mix Concrete


Association (NRMCA) Plant Manager Certification at the Plant Manager
level.

1.6.1.1 Quality Manager Qualifications

The quality manager shall hold a current license as a professional engineer


in a U.S. state or territory with experience on at least five (5) similar
projects. Evidence of extraordinary proven experience may be considered by
the Contracting Officer as sufficient to act as the Quality Manager.

1.6.1.2 Field Testing Technician and Testing Agency

Submit data on qualifications of proposed testing agency and technicians


for approval by the Contracting Officer prior to performing testing on
concrete.

a. Work on concrete under this contract shall be performed by an ACI


Concrete Field Testing Technician Grade 1 qualified in accordance with
ACI SP-2 or equivalent. Equivalent certification programs shall
include requirements for written and performance examinations as
stipulated in ACI SP-2.

b. Testing agencies that perform testing services on reinforcing steel


shall meet the requirements of ASTM E329.

c. Testing agencies that perform testing services on concrete materials


shall meet the requirements of ASTM C1077.

d. Testing agencies or engineering companies that characterize the


transport properties of the concrete or conduct service life modeling
analysis shall be STADIUM® certified or pre-approved by the Contracting
Officer with concurrence of the agency's Subject Matter Expert in
Concrete Materials.

1.6.2 Laboratory Qualifications for Concrete Qualification Testing

The concrete testing laboratory shall have the necessary equipment and
experience to accomplish required testing. The laboratory shall meet the
requirements of ASTM C1077, be Cement and Concrete Reference Laboratory
(CCRL) inspected, and be a STADIUM® certified laboratory.

1.6.3 Laboratory Accreditation

Laboratory and testing facilities shall be provided by and at the expense


of the Contractor. The laboratories performing the tests shall be
accredited in accordance with ASTM C1077, including ASTM C78/C78M and
ASTM C1260. The accreditation shall be current and shall include the
required test methods, as specified.

a. Aggregate Testing and Mix Proportioning: Aggregate testing and mixture


proportioning studies shall be performed by an accredited laboratory
and under the direction of a licensed/registered civil engineer in a
U.S. state or territory, who shall sign all reports and designs.

SECTION 03 31 29 Page 23
b. Acceptance Testing: Furnish all materials, labor, and facilities
required for molding, curing, testing, and protecting test specimens at
the site and in the laboratory. Furnish and maintain boxes or other
facilities suitable for storing and curing the specimens at the site
while in the mold within the temperature range stipulated by
ASTM C31/C31M.

c. Contractor Quality Control: All sampling and testing shall be performed


by an approved, onsite, independent, accredited laboratory.

1.7 CONCRETE DURABILITY

1.7.1 Concrete Mixture Proportions

At least 60 days prior to concrete placement, submit concrete mixture


proportions, ingredient material certificates and test data, and trial
batch test data for each class of concrete proposed for use on the
project. Submittal shall clearly indicate where each mixture will be used
when more than one mixture design is submitted. Obtain approval from
Contracting Officer prior to placement.

1.7.2 Concrete Design Requirements

Proportion concrete mixtures to meet the requirements listed in Table 1 in


accordance with the procedures outlined in ACI 201.2R and ACI 211.1.

The mixture proportions for concrete shall be developed by the Contractor


to produce the required compressive strength (f'cr), drying shrinkage, and
constructability for mixtures that have the potential to accomplish a
structure with the design service life.

Table 1 - Concrete Design Requirements

Prescriptive requirements Minimum Maximum

ASTM C666/C666M Method A Durability Factor at 300 cycles 90 --

Concrete ASTM C157/C157M Drying Shrinkage percent, as -- 0.05


modified per ACI 364.3R at 28 days except for high volume percent
fly ash (HVFA) at 56 days.

Initial acid-soluble chloride content in cast-in-place -- 0.10


concrete per ASTM C1152/C1152M, percent/cement

Initial acid-soluble chloride content in prestressed -- 0.06


concrete determined following ASTM C1152/C1152M,
percent/cement

1.7.3 Concrete Mixture Qualifications

1.7.3.1 Previously Approved Concrete Mixtures

For identical concrete mixtures previously approved for use within the past
12 months, the previous mixture qualification submittal may be re-submitted
without further trial batch testing if accompanied by:

SECTION 03 31 29 Page 24
lesser amounts of these materials are used to
produce concrete mixtures that do not show these
benefits then the term SCM remains applicable.

The Engineer of Record is encouraged to specify the


use of complementary cementing materials. For
example 50 percent replacement of the portland
cement using Class F fly ash has been successfully
demonstrated to offer the required compressive
strength (f'cr), drying shrinkage, lower
permeability, constructability, and the potential to
accomplish a structure with the design service life
while being less expensive with a smaller carbon
footprint.

**************************************************************************

Cementitious materials shall be portland cement or cement blended with


complementary cementing materials. New submittals are required when the
cementitious materials change sources or types.

The Contractor shall provide cementitious materials meeting the


requirements of the applicable specification, and as modified herein.
Provide mill certificates and test results conducted within six-months of
the submittal date as part of the concrete mixture qualification submittal.

Provide a single manufacturer of cementitious material for each type of


cement and complementary cementing materials supplied to the project.

2.1.1 Portland Cement

Provide portland cement conforming to ASTM C150/C150M, Type [I] [II]


[V],low alkali [including false set requirements] with tri-calcium
aluminates (C3A) content less than 10 percent and a maximum cement-alkali
content of 0.80 percent Na2Oe (sodium oxide) equivalent. Type III cement
shall be used only with concurrence of the agency's Subject Matter Expert
in Concrete Materials. When HVFA mixtures are specified they should be
blended with Type II portland cement. HVFA is encouraged instead of using
Type V cement in high-sulfate areas. Low alkali cement may be required if
the proposed aggregates are found to be expansive.

ASTM C150/C150M cements shall be combined with complementary cementing


materials in the concrete mixture.

2.1.2 Blended Cements

Blended cement shall conform to ASTM C595/C595M, Type IP or IS, including


the optional requirement for mortar expansion [and sulfate soundness] and
consist of a mixture of ASTM C150/C150M Type I, or Type II cement and a
complementary cementing material. The slag added to the Type IS blend shall
be ASTM C989/C989M ground granulated blast-furnace slag. The pozzolan
added to the Type IP blend shall be ASTM C618 Class F and shall be
interground with the cement clinker. The manufacturer shall state in
writing that the amount of pozzolan in the finished cement will not vary
more than plus or minus 5 mass percent of the finished cement from
lot-to-lot or within a lot. The percentage and type of mineral admixture
used in the blend shall not change from that submitted for the aggregate
evaluation and mixture proportioning.

SECTION 03 31 29 Page 44
2.1.3 Pozzolan

2.1.3.1 Fly Ash

**************************************************************************
NOTE: Class C fly ash is not permitted.

Use loss on ignition not exceeding 3 percent for


frost areas to reduce carbon interference with air
entraining admixture.
**************************************************************************

Fly ash shall conform to ASTM C618, Class F, including the optional
requirements for uniformity and effectiveness in controlling Alkali-Silica
reaction and shall have a loss on ignition not exceeding [3][6] percent.
Class F fly ash for use in mitigating Alkali-Silica Reactivity shall have a
Calcium Oxide (CaO) content of less than 8 percent and a total equivalent
alkali content less than 1.5 percent. Add with cement.

2.1.3.2 Raw or Calcined Natural Pozzolan

Natural pozzolan shall be raw or calcined and conform to ASTM C618, Class
N, including the optional requirements for uniformity and effectiveness in
controlling Alkali-Silica reaction and shall have an on ignition loss not
exceeding 3 percent. Class N pozzolan for use in mitigating Alkali-Silica
Reactivity shall have a Calcium Oxide (CaO) content of less than 13 percent
and total equivalent alkali content less than 3 percent.

2.1.3.3 Ultra Fine Fly Ash and Ultra Fine Pozzolan

Ultra Fine Fly Ash (UFFA) and Ultra Fine Pozzolan (UFP) shall conform to
ASTM C618, Class F or N, and the following additional requirements:

a. The strength activity index at 28 days of age shall be at least 95


percent of the control specimens.

b. The average particle size shall not exceed 6 microns.

c. The sum of SiO2 + Al2O3 + Fe2O3 shall be greater than 77 percent.

2.1.4 Ground Granulated Blast-Furnace (GGBF) Slag

Ground Granulated Blast-Furnace Slag shall conform to ASTM C989/C989M,


[Grade 100 or Grade 120]. Add with cement.

2.1.5 Silica Fume

**************************************************************************
NOTE: Silica Fume shall only be used for OCONUS
projects where Class F fly ash and GGBF slag are not
available, and when approved by the Contracting
Officer. Guidance for use of silica fume should be
sought from the agency's Subject Matter Expert in
Concrete Materials.
**************************************************************************

Silica fume shall conform to ASTM C1240, including the optional limits on
reactivity with cement alkalis. Silica fume may be furnished as a dry,
densified material or as slurry. Proper mixing is essential to accomplish

SECTION 03 31 29 Page 45
proper distribution of the silica fume and avoid agglomerated silica fume
which can react with the alkali in the cement resulting in premature and
extensive concrete damage. Supervision at the batch plant, finishing, and
curing is essential. Provide at the Contractor's expense the services of a
manufacturer's technical representative, experienced in mixing,
proportioning, placement procedures, and curing of concrete containing
silica fume. This representative must be present on the project prior to
and during at least the first 4 days of concrete production and placement
using silica fume. A High Range Water Reducer (HRWR) shall be used with
silica fume. Finishing may be more difficult. Proper curing is essential
because there is a tendency for plastic shrinkage cracking.

2.1.6 Complementary Cementing Materials (AKA Supplementary Cementitious


Materials (SCM) Content (SCM))

The concrete mix shall always contain complementary cementing materials


whether or not the aggregates are found to be reactive in accordance with
the subpart entitled "Aggregates". Concrete mixtures shall be designed and
proportioned to meet the requirements for strength, constructability,
shrinkage, and service life.

**************************************************************************
NOTE: This specification requires that the
structural requirements (f'c) be met and concrete
strength is between 1.0 f'c and 1.2 f'c. If the
prequalified mixture as approved by the Engineer of
Record should produce a higher design strength
(fcr), that strength shall be used instead of f'c.
Maintain required w/cm ratio regardless of strength
requirements.
**************************************************************************

2.2 AGGREGATES

Comply with ASTM C33/C33M Class 4S, except as modified herein.

The quantities to be retained on each sieve may be adjusted only where


available aggregates are elongated or slivered and cause interference with
mix mobility, or available aggregate gradations do not comply with the 18-8
requirement. When necessary to satisfy local conditions and when
permitted, the combined aggregate percentages may be changed to not more
than 22 percent nor less than 6 percent retained on any individual
sieve.The combined aggregates in the mixture (coarse, intermediate, and
fine) shall be well graded with no more than 18 percent nor less than 8
percent of the combined aggregate retained on any individual sieve, unless
satisfactory performance can be demonstrated. The 300 micrometers No. 50
sieve may have less than 8 percent retained; sieves finer than 300
micrometers No. 50 shall have less than 8 percent retained, and the
coarsest sieve may have less than 8 percent retained. Use intermediate
sizes for blending where necessary, to provide a well graded combined
aggregate.

a. Provide gradation of individual aggregate sizes using standard concrete


aggregate sieves including 37.5 mm 1-1/2 inches, 25 mm one inch, 19 mm
3/4 inch, 12.5 mm 1/2 inch, 9.5 mm 3/8 inch, 4.75 mm No. 4, 2.36 mm No.
8, 1.18 mm No. 16, 600 micrometers No. 30, 300 micrometers No. 50, and
150 micrometers No. 100.

b. Provide aggregates for exposed concrete from one source. Aggregate

SECTION 03 31 29 Page 46
based on the closest major city to the project.

Table 2 - Environmental Design Conditions

Latitude [_____] degrees Y' Z" [N][S]

Longitude [_____] degrees Y' Z" [E][W]

MLLW Elevation, meter feet [_____] meter feet

MHHW Elevation, meter feet [_____] meter feet

Salinity, ppt (Submerged zone) [_____] ppt

Salinity, ppt (Tidal zone) [_____] ppt

Salinity, ppt (Splash zone) [_____] ppt

Salinity, ppt (Atmospheric zone) [_____] ppt

Annual mean water temperature, C F [_____] Degrees C F

Annual maximum ambient temperature, C F [_____] Degrees C F

Annual mean ambient temperature, C F [_____] Degrees C F

Annual minimum ambient temperature, C F [_____] Degrees C F

Annual mean relative humidity, percent [_____] percent

1.7.4.2 Exposure Conditions by Element

The Contractor shall use the service life model and exposure conditions
listed above to provide concrete system(s) that meet or exceed the service
life requirement. Evaluate the service life of each element for its
severest service condition.

1.7.5 Concrete Qualification Program

1.7.5.1 Fresh Concrete Properties

a. Air Content: Concrete that is air entrained shall conform to the air
limits specified in ACI 301M ACI 301 for exposure and the aggregate
size used and tested in accordance with ASTM C231/C231M. Variations
outside the limits specified shall not be reason to reject the concrete
in locations not subject to freeze-thaw conditions.

b. Slump: The concrete mixture shall be proportioned to have, at the point


of deposit, a maximum slump of 100 mm 4 inches as determined by
ASTM C143/C143M when admixtures that affect slump are not used. Where
an ASTM C494/C494M, Type F or G admixture is used, the slump after the
addition of the admixture shall not exceed 200 mm 8 inches. Slump
tolerances shall comply with the requirements of ACI 117.

c. Self-Consolidating Concrete: When self-consolidating concrete is


proposed for use, the mixture shall be proportioned and tested for
qualification using:

SECTION 03 31 29 Page 28
(1) ASTM C1611/C1611M slump flow shall not be greater than 609.6 mm
24 inches, with visual stability index not greater than 1.

(2) ASTM C1621/C1621M Passing ability using the J-ring. Spread within
25.4 mm 1 inch less than the slump flow.

(3) Passing ability using the L-Box between 4 and 8 seconds

(4) ASTM C1610/C1610M, static segregation shall be less than 4.0


percent.

For process control sampling, the slump flow limit as determined by


ASTM C1611/C1611M shall be no greater than 609.6 mm 24 inches and the
visual stability index limit shall be no greater than 1.0.

d. Underwater concrete: When the concrete is intended for placement under


water using the tremie technique, the concrete shall be proportioned to
be cohesive and flow with minimal out segregation. Viscosity modifying
admixtures are permitted for underwater concrete. Proportioning
guidance in ACI 304R shall be considered. Concrete mixtures shall be
qualified for tremie placement methods based on a trial placement
approved by the Contracting Officer.

1.7.5.2 Hardened Concrete Properties

**************************************************************************
NOTE: Navy waterfront structures typically take a
year or more to complete. With time all concrete
continues to gain strength. The Engineer of Record
is encouraged to design the structural elements
based on the compressive strength that will be
achieved at 56 or 90 days rather than at 28 days.
Doing so will better allow the Contractor to develop
and place concrete mixtures with less portland
cement. Excessive use of cement leads to more cracks
and shorter-lived structures. Embracing this
approach will result in structures that are less
expensive, greener and more sustainable.
**************************************************************************

a. Compressive Strength: The structural engineer shall specify the minimum


compressive strength results at [28] [56] days. Determine compressive
strength (f'cr) for qualification of concrete mixtures and for quality
acceptance testing. A compressive strength test result is defined as
the mean of three properly conducted tests on 100 by 200 mm 4 by 8 inch
cylinders in accordance with ASTM C39/C39M. Alternatively and for
concrete mixtures containing a maximum size aggregate greater than 25.4
mm 1 inch, a strength test result shall be defined as the mean of two
properly conducted 28-day tests on 150 by 300 mm 6 by 12 inch
cylindrical specimens in accordance with ASTM C39/C39M. In addition:

(1) Specified Compressive Strength: For structural concrete elements


exposed in a marine environment, the minimum specified [28] [56]
day design strength is denoted as (f'c). Strength of concrete
containing 50 percent or more fly ash shall be specified at a
minimum of 56 days.

(2) Required Average Strength: The concrete shall be proportioned such

SECTION 03 31 29 Page 29
that the minimum required average compressive strength (f'cr)
exceeds the specified design strength (f'c) as per ACI 301M ACI 301.

(3) The average compressive strength may not exceed the specified
strength at the same age by more than 20 percent unless approved
by the Engineer of Record.

(4) Strength of any individual concrete placement shall be considered


satisfactory if both the following requirements are met:

(a) The arithmetic mean of any three consecutive lot strength


tests is between 1.0 and 1.2f'c, and;

(b) No individual strength test result is less than 0.90 f'c.

(5) In the event that a placement is represented by single sampling


lot, strength shall be considered satisfactory if either:

(a) The mean of the initial test is between 1.0 and 1.2 f'c, or;

(b) The mean of the initial test and retest is between 1.0 and 1.2
f'c, and neither strength test result is less than 0.90 f'c.

(6) For underwater concrete, cast compressive strength samples by


placing concrete in four 5-gallon buckets below water using
similar placement as the project. Permanently mark buckets as "3
days," "7 days," "[28] [56] days," and "Extra." Include date and
station. Provide specimen sets at every [76.5 cubic meters] [100
cubic yards] of concrete for the first [382.3 cubic meters] [500
cubic yards], then every [382.3 cubic meters] [500 cubic yards]
thereafter with a minimum of one set per day of underwater
concrete placement.

(a) Retrieve buckets at specified intervals and extract three


cores from each bucket. Conduct compressive strength test in
accordance with ASTM C42/C42M.

(b) Strength of underwater concrete shall be satisfactory if the


compressive strength result from extracted cores at the age of the
specified strength is between 0.85 and 1.2 f'c with no individual
strength test result less than 0.75 f'c.

b. Drying Shrinkage: Determine drying shrinkage for qualification of


concrete mixtures prior to the fabrication of the Test Section and from
samples made during the fabrication of the Test Section (see the
subpart entitled "Test Section"). All test results shall not exceed
0.05 percent. A drying shrinkage test result shall be the mean value
from three or more individual specimens constituting a test set. If an
individual specimen's measurements deviate from the mean value by more
than 0.009 percent length change the specimen's measurements shall be
discarded and a new average established. Casting more than three
specimens for each set is permitted. Test procedures and test
specimens shall conform to the following:

Drying shrinkage specimens, typically 75 by 75 by 285.8 mm 3 by 3 by 11.25


inch prisms for 25.4 mm 1 inch maximum size aggregate or smaller, shall be
fabricated, cured, dried, and measured at 28 days in the manner delineated
in ASTM C157/C157M except as modified by ACI 364.3R. Mixtures containing
50 percent or more complementary cementing materials shall meet the

SECTION 03 31 29 Page 30
2.8.5.2 Vertical Surfaces

**************************************************************************
NOTE: Specify ASTM C920 for vertical surfaces
greater than 3 percent slope and not subject to jet
fuel, gasoline, fuel oil, etc. For vertical
surfaces greater than 3 percent slope and subject to
jet fuel, specify FS SS-S-200, no sag.
**************************************************************************

Vertical surfaces are defined as all surfaces with a slope greater than 3
percent. ASTM C920, Type M, Grade NS, Class 25, Use T. FS SS-S-200, no sag.

PART 3 EXECUTION

3.1 FORMS

a. Provide formwork with clean-out openings to permit inspection and


removal of debris. Formwork shall be gasketed or otherwise rendered
sufficiently tight to prevent leakage of paste or grout under heavy,
high-frequency vibration. Use a release agent that does not cause
surface dusting. Limit reuse of plywood to no more than three times.
Reuse may be further limited by the Contracting Officer if it is found
that the pores of the plywood are clogged with paste so that the wood
does not absorb air and some of the high water-cementitious materials
ratio paste that may be trapped in pockets between the form and the
concrete.

b. Comply with ACI 301M ACI 301. Concrete for footings may be placed in
excavations without forms upon inspection and approval by the
Contracting Officer. Excavation width shall be a minimum of 100 mm 4
inches greater than indicated. Set forms rigidly, mortar-tight, and
true to line and grade. Chamfer above grade exposed joints, edges, and
external corners of concrete 20 mm 0.75 inch unless otherwise
indicated. Forms submerged in water shall be watertight.

c. Patch form tie holes with a no shrink patching material in accordance


with the manufacturer's recommendations and subject to approval.

3.1.1 Coating

Before concrete placement, coat the contact surfaces of forms with a no


staining mineral oil, no staining form coating compound, or two coats of
nitrocellulose lacquer. Do not use mineral oil on forms for surfaces to
which adhesive, paint, or other finish material is to be applied.

3.1.2 Removal of Forms and Supports

After placing concrete, forms shall remain in place for the time periods
specified in ACI 347, except for concrete placed underwater, forms shall
remain in place a minimum of 48 hours. Prevent concrete damage during form
removal.

3.1.2.1 Special Requirements for Reduced Time Period

Forms may be removed earlier than specified if ASTM C39/C39M test results
of field-cured samples from a representative portion of the structure or
other approved and calibrated non-destructive testing techniques show that
the concrete has reached a minimum of 85 percent of the design strength.

SECTION 03 31 29 Page 52
of concrete containing silica fume.

h. Ion Transport Properties: Determine ion transport properties of the


concrete in accordance with test procedures outlined by SIMCO, maker of
STADIUM® software. Ion Transport properties are required as inputs for
service life modeling and include: the volume of permeable voids
(porosity); the ion diffusion coefficient (Doh ); the moisture transport
coefficient (MTC), and an aging factor. A brief description of the
test procedures is provided below. See TR-NAVFAC ESC-CI-1215 for
further details.

(1) Porosity: The volume of permeable voids (porosity) of concrete is


determined in accordance with ASTM C642. Porosity is determined
for qualification of concrete mixtures and for quality acceptance
testing.

(2) Ion Diffusion Coefficient (Doh ): This test is a modified version of


ASTM C1202 and uses an electrical field to migrate chloride ions
through a vacuum saturated concrete specimen for approximately 14
days. The electrical charge flowing through the concrete is
related to the diffusion coefficient of ionic species in
cementitious materials. A test is defined as the average of two
specimens run together and whose results are analyzed together to
produce a single Doh value. The service life modeling software uses
the cementitious materials proportions and porosity measurements
to analyze the electrical measurements and determine the Doh . The D
oh is determined for qualification of concrete mixtures and for
quality acceptance testing.

(3) Moisture Transport Test: This modified version of the ASTM C1585
test determines the drying rate of pre-saturated cementitious
materials by measuring the evaporative mass loss of concrete
slices with different thickness exposed to constant temperature
and relative humidity environment. The moisture transport
coefficient (MTC) is then determined by analyzing the mass loss
data using the service life modeling software.

This test is only used for qualification of concrete mixtures, not


for production concrete.

(4) Aging factor: The aging factor is a necessary value to estimate


the change in diffusion coefficient over time. The aging factor
is defined as the ratio of the ultimate Doh to the 28-day Doh per
TR-NAVFAC ESC-CI-1215. Since we cannot wait for two or more years
to characterize project concrete, a surrogate aging factor is used
in this specification. This surrogate aging factor is calculated
as the ratio of 90-day, or longer, Doh to the 28-day Doh . The aging
factor is determined only for qualification of concrete mixtures
in compliance with TR-NAVFAC ESC-CI-1215.

1.7.5.3 Reinforcing Steel Corrosion Properties

The corrosion properties of the reinforcing steel used for service life
modeling shall be as follows unless otherwise approved by the Contracting
Officer after review by the agency's Subject Matter Expert in Concrete
Materials:

SECTION 03 31 29 Page 32
For slab construction use vibrating screeds designed to consolidate the
full depth of the concrete. Where beams and slabs intersect, use an
internal vibrator to consolidate the beam. Do not vibrate concrete placed
with anti-washout admixtures. Vibrators shall be equipped with rubber
vibrator heads.

3.4.2 Cold Weather

Comply with ACI 306R. Do not allow concrete temperature to decrease below
10 degrees C 50 degrees F. Obtain approval prior to placing concrete when
ambient temperature is below 4 degrees C 40 degrees F or when concrete is
likely to be subjected to freezing temperatures within 24 hours. Placement
of concrete shall be halted whenever the ambient temperature drops below 5
degrees C 40 degrees F. When the ambient temperature is less than 10
degrees C 50 degrees F the temperature of the concrete when placed shall be
not less than 10 degrees C 50 degrees F or more than 25 degrees C 75
degrees F. Heating of the mixing water or aggregates may be necessary to
regulate the concrete placing temperature. An accelerating admixture may be
used when the ambient temperature is below 10 degrees C 50 degrees F.
Covering and other means shall be provided for maintaining the concrete at
a temperature of at least 10 degrees C 50 degrees F for not less than 7
days after placing, and at a temperature above freezing for the remainder
of the curing period..

3.4.3 Hot Weather

Comply with ACI 305R. Maintain required concrete temperature using Figure
2.1.5, "Effect of Concrete Temperatures, Relative Humidity, and Wind
Velocity on the Rate of Evaporation of Surface Moisture From Concrete" in
ACI 305R to prevent the evaporation rate from exceeding one kg per square
meter 0.2 pound of water per square foot of exposed concrete per hour. If
necessary, cool ingredients before mixing or use other suitable means to
control concrete temperature and prevent rapid drying of newly placed
concrete. Shade the fresh concrete as soon as possible after placing.
Start curing when the surface of the fresh concrete is sufficiently hard to
permit curing without damage. If the evaporation rate exceeds 0.5 kg per
square meter 0.1 pound of water per square foot per hour, fog spray the
exposed concrete surfaces until active moist curing is applied.Provide
water hoses, pipes, spraying equipment, and water hauling equipment, where
job site is remote to water source, to maintain a moist concrete surface
throughout the curing period. Provide burlap cover or other suitable,
permeable material with fog spray or continuous wetting of the concrete
when weather conditions prevent the use of either liquid membrane curing
compound or impervious sheets. For vertical surfaces, protect forms from
direct sunlight and add water to top of structure once concrete is set.

3.4.4 Prevention of Plastic Shrinkage Cracking

During weather with low humidity, and particularly with high temperature
and appreciable wind, develop and institute measures to prevent plastic
shrinkage cracks from developing. If plastic shrinkage cracking occurs,
halt further placement of concrete until protective measures are in place
to prevent further cracking. Periods of high potential for plastic
shrinkage cracking can be anticipated by use of Figure 2.1.5 of ACI 305R.
In addition to the protective measures concrete placement shall be further
protected by erecting shades and windbreaks and by applying fog sprays of
water, the addition of monomolecular films, or wet covering. When such
water treatment is stopped, curing procedures shall be immediately
commenced. The methods and materials to remove or repair areas affected by

SECTION 03 31 29 Page 57
Table 4 -Chloride Threshold Level and Corrosion Propagation Time

Description UNS EN No. Chloride Corrosion


Alloy Threshold Propagation
(CTH), Period
ppm (Tp) max,
years
ASTM A276 S31803 1.4462 5000 15
Duplex Stainless 2205 S32205

*See TR-NAVFAC ESC-CI-1215

** All other reinforcement not listed require approval of agency's


Subject Matter Expert in Concrete Materials

1.7.5.4 Supplemental Corrosion Protection

If the available materials in the region of the project cannot practically


be made to meet the service life based on testing and service life modeling
without the use of supplemental corrosion protection, then the Contractor
shall prepare a recommendation on how to accomplish the service life using
imported materials and/or supplemental corrosion protection. With input
from the agency's Subject Matter Expert in Concrete Materials, the
Contracting Officer shall consider approval of the Contractor's
recommendation on a case-by-case basis.

1.7.6 Mass Concrete Temperature Control Plans

a. Thirty days minimum prior to concrete placement, submit for approval a


mass concrete temperature control plan that includes:

(1) Location and identification of temperature monitoring sensors.

(2) Product data for automated temperature sensors and recording


equipment.

(3) Cooling pipe layout diagram with sizes and materials, if used.

(4) Proposed insulation materials and associated R-values.

(5) Anticipated form removal schedule and curing procedures.

(6) Maximum allowable concrete placement temperature for the range of


anticipated ambient temperatures based on thermal modeling.

(7) Monitoring procedures and contingency plans.

Concrete placement temperature shall be based on results of thermal


modeling for the element incorporating: the heat of hydration and specific
heat capacity for the concrete mixture, solar gain, and heat transfer to
the environment through formwork, insulation, and cooling techniques.

Mass concrete temperature control shall be monitored using automated


temperature recording devices that allow wireless transmission of data to
an on-site host computer for real-time monitoring of temperatures.

Temperature control sensor layout for each placement shall be provided with

SECTION 03 31 29 Page 34
individual sensor ID identified.

Minimum sensor requirements include at least two sensors for each placement
located as follows:

(1) The geometric center of the element cross-section.

(2) Within 76.2 mm 3 inches of the side forms at mid-height.

(3) Within 76.2 mm 3 inches of the top surface located directly above
the center sensors.

(4) Within 76.2 mm 3 inches from the top corner at the intersection of
side forms.

(5) Ambient temperature sensors placed in a shaded location.

Procedures for installing, protecting sensors during placement, and testing


sensors a minimum of 24 hours prior to concrete placement shall be
provided. Initiate sensor recording at least 2 hours prior to placement.
Verify function of all sensors prior to and upon completion of concrete
placing operations. Provide additional sensors for placements greater than
305.8 cubic meters 400 cubic yards at each location.

Submit procedures for controlling concrete temperatures within the


following limits:

(1) Maximum temperature shall be less than 70 degrees C 158 degrees F.

(2) Maximum temperature differential between the mean of all


functioning center sensor temperatures to any individual surface
or corner sensor shall be less than 20 degrees C 68 degrees F.

(3) Temperature control procedures shall remain in effect until the


differential between the ambient low temperature and mean of all
functioning center sensor temperatures is less than 20 degrees C
68 degrees F.

(4) An additional submittal shall be provided for the Contracting


Officer's approval in the event the Contractor fails to control
temperatures within the limits listed above. The submittal shall
include documentation of any cracks that develop, identify
revisions to control procedures to prevent future cracking, and
procedures to seal or otherwise mitigate defects.

b. Mass Concrete Mock-up: For concrete mixtures intended for mass concrete,
cast thirty-one (31) 100 by 200 mm 4 by 8 inch cylinder specimens in
accordance with ASTM C192/C192M, three 75 by 75 by 285.8 mm 3 by 3 by
11.25 inch concrete prisms in accordance with ASTM C157/C157M, and at
least one semi-adiabatic cube from a trial batch.

The semi adiabatic cube shall have a minimum dimension of 3 feet per side,
and shall be insulated all sides with a minimum R-value of 30. Install
pairs of thermocouples at the center of mass, the middle of each side, the
top surface, and the top corner. Automatically record the temperature of
each sensor hourly for one week. Additional cubes may be cast to calibrate
active cooling system performance.

(1) Conduct compressive strength development testing at 3, 7, [28]

SECTION 03 31 29 Page 35
[56], and 90 days age using three specimens per age in accordance
with ASTM C39/C39M, and develop a compressive strength prediction
equation for the concrete mixture in accordance with ASTM C1074.

(2) Conduct tensile strength tests at 3, 7, [28] [56], and 90 days on


two specimens per age in accordance with ASTM C496/C496M, and
develop a tensile strength prediction equation for the concrete
mixture in accordance with ASTM C1074.

(3) Conduct elastic modulus tests at 3, 7, [28] [56], and 90 days on


two specimens per age in accordance with ASTM C469/C469M, and
develop an elastic modulus prediction equation for the concrete
mixture in accordance with ASTM C1074.

Conduct coefficient of thermal expansion testing in accordance with


COE CRD-C 39 after 28 days of moist curing. Test specimens in a saturated
condition.

Report all test results and predictive equations in the mock-up submittal.
The predictive equations may be used by the Contractor to establish the
duration of temperature control and form removal based on the allowable
temperature differential between the concrete core and ambient low
temperature.

1.8 CONCRETE

1.8.1 Drawings

Fabrication Drawings for concrete formwork, reinforcement materials,


precast elements, wall forms, and bulkhead forms must indicate concrete
pressure calculations with both live and dead loads, along with material
types. Provide design calculations by a registered Civil or Structural
Engineer for the formwork.

1.8.1.1 Formwork

Prior to commencing work submit drawings for approval showing details of


formwork including, but not limited to: joints, supports, studding and
shoring, and sequence of form and shoring removal. Reproductions of
contract drawings are unacceptable.

Design, fabricate, erect, support, brace, and maintain formwork so that it


is capable of supporting without failure all vertical and lateral loads
that may reasonably be anticipated to be applied to the formwork.

ACI 347. Include design calculations indicating arrangement of forms,


sizes, species, and grades of supports (lumber), panels, and related
components. Indicate placement schedule, construction, and location and
method of forming control joints. Include locations of inserts, pipe work,
conduit, sleeves, and other embedded items. Furnish drawings and
descriptions of shoring and reshoring methods proposed for slabs, beams,
and other horizontal concrete members.

1.8.1.2 Reinforcing Steel

ACI SP-66. Provide bending and cutting diagrams, assembly diagrams,


splicing placement and laps of bars, shapes, dimensions, and details of bar
reinforcing, accessories, and concrete cover. Do not scale dimensions from
structural drawings to determine lengths of reinforcing bars. Only

SECTION 03 31 29 Page 36
complete drawings will be accepted.

1.8.1.3 Precast Elements

**************************************************************************
NOTE: Modify requirements based on the scope of the
project.
**************************************************************************

Submit drawings and design calculations indicating complete information for


the fabrication, handling, and erection of the precast elements. Drawings
shall not be reproductions of contract drawings.

1.8.1.4 Joints

Submit a plan indicating the type and location of each expansion and
construction joint. Final joint locations are subject to Government
approval.

1.8.2 Pre-Construction Submittals

1.8.2.1 Curing Concrete Elements

Submit proposed materials and methods for curing concrete elements.

1.8.2.2 Concrete Curing Plan

Submit proposed materials, methods, and duration for curing and cooling
concrete elements in accordance with ACI 308.1.

Minimum moist curing duration shall be seven days.

Begin curing immediately after placement. Protect concrete from premature


drying, excessively hot temperatures, and mechanical injury; and maintain
minimal moisture loss at a relatively constant temperature for the period
necessary for hydration of the cement and hardening of the concrete. The
materials and methods of curing are subject to approval by the Contracting
Officer.

1.8.2.3 Form Removal Schedule

Submit schedule for form removal indicating element and minimum length of
time for form removal. Submit technical literature of forming material or
liner, form release agent, form ties, and gasketing to prevent leakage at
form and construction joints. Provide a full description of materials and
methods to be used to patch form-tie holes.

1.8.2.4 Concrete Placement and Compaction

a. Submit technical literature for equipment and methods proposed for use
in placing concrete. Include concrete pumping or conveying equipment
including type, size and material for pipe, valve characteristics, and
the maximum length and height concrete will be pumped. No adjustments
shall be made to the mixture design to facilitate pumping.

b. Submit technical literature for equipment and methods proposed for


vibrating and compacting concrete. Submittal shall include technical
literature describing the equipment including vibrator diameter,
length, frequency, amplitude, centrifugal force, and manufacturer's

SECTION 03 31 29 Page 37
The Contracting Officer will evaluate and validate core tests in accordance
with the specified procedures.

3.8.4 Acceptance of Concrete Strength

3.8.4.1 Standard Molded and Cured Strength Specimens

The acceptance of concrete strengths shall be based on averages of results


from three consecutive compressive strength tests. When the averages of
all sets of three consecutive compressive strength test results are between
1.0 and 1.2 times the field test strength (fcr), and no individual strength
test falls below fcr by more than 3.45 MPa 500 psi, the strength of the
concrete is satisfactory. These criteria also apply when accelerated
strength testing is specified unless another basis for acceptance is
specified.

3.8.4.2 Non-Destructive Tests

Non-destructive tests may be used when permitted to evaluate concrete where


standard molded and cured cylinders have yielded results not meeting the
criteria.

3.8.4.3 Extracted Core Tests

When the average compressive strengths of the representative cores are


between 0.85 fcr and 1.2 fcr and if no single core is less than 0.75 fcr,
the strength of concrete is satisfactory.

3.8.5 Inspection

ACI 311.4R. Inspect concrete placed under water with qualified divers.

3.9 REPAIR, REHABILITATION AND REMOVAL

Before the Owner accepts the structure and final payment is made the
Contractor shall inspect the structure for cracks, damage and substandard
concrete placements that may adversely affect the service life of the
structure. A report documenting these defects shall be prepared which
includes recommendations for repair, removal and/or remediation which, will
be reviewed by the agency's Subject Matter Expert in Concrete Materials and
submitted to the Contracting Officer for approval before any corrective
work is accomplished.

3.9.1 Crack Repair

Prior to final acceptance, all cracks in excess of 0.50 mm 0.02 inches wide
shall be documented and repaired. The proposed method and materials to
repair the cracks shall be submitted to the Contracting Officer for
approval. The proposal shall address the amount of movement expected in the
crack due to temperature changes and loading.

3.9.2 Repair of Weak Surfaces

Weak surfaces are defined as mortar-rich, rain-damaged, uncured, or


containing exposed voids or deleterious materials. Concrete surfaces with
weak surfaces less than 6 mm 1/4 inch thick shall be diamond ground to
remove the weak surface. Surfaces containing weak surfaces greater than 6 mm
1/4 inch thick shall be removed and replaced or mitigated in a manner

SECTION 03 31 29 Page 66
requirement.

c. Aggregate sampling for gradation and dry-rodded unit weight shall be


conducted for each 100 tons delivered for use on the project, or
portion thereof.

1.8.4 Reporting

1.8.4.1 Daily Inspection Reports

Contractor shall prepare daily inspection reports for all inspection


activities such as base preparation, formwork preparation, reinforcement
installation, concrete placement log, and temperature control activities.
Submit sample forms and describe the procedure used to organize, archive,
and retrieve inspection records in the Quality Program submittal.

1.8.4.2 Sampling Logs

Contractor shall maintain a concrete placement log as an electronic


spreadsheet or database identifying each placement date, placement
location, volume of concrete, batch ticket numbers, lot identification
code, fresh concrete properties, compressive strength results, transport
properties, inspection comments, and acceptance status. Contractor shall
provide/transmit the concrete testing log to the Contracting Officer
weekly. The Contractor shall provide copies of supporting documents for
any placement requested by the Contracting Officer immediately upon request.

1.8.4.3 Quality Control Data

The Contractor shall prepare, maintain, and report separate quality control
charts illustrating the slump, temperature, air content, compressive
strength test results, 28-day porosity, and Doh test results for each lot
of each concrete mixture used on the project.

1.8.4.4 Quality Team Meetings

The contractor shall conduct regular quality control team meetings to


review plans for future placements, review test results, and discuss
dispensation of non-conforming materials. The quality team shall include
the Contractor's quality manager, the project manager, the project
superintendent, the Contracting Officer, and representatives of the testing
agency and concrete producer, or approved substitutes. It is recommended
that the meetings be held on a weekly or bi-weekly basis during the service
life modeling submittal phases and then monthly, as the construction
progresses. The transition from the weekly or bi-weekly meetings to the
monthly meetings shall be with the Contracting Officer's approval.

The Contractor shall prepare quality control team meeting minutes for each
meeting. The minutes shall include the date of each meeting, attendees,
key discussion points, findings, recommendations, assigned tasks, assigned
personnel, task completion dates and status of each task.

1.8.4.5 Non-conforming materials

The exact location of non-conforming concrete as placed shall be identified


and the Contracting Officer and Engineer of Record shall be notified
immediately. There are numerous possible indicators that the as-placed
concrete is non-conforming including (but not limited to) excessive
compressive strength, inadequate compressive strength, excessive slump,

SECTION 03 31 29 Page 39
transport properties out of limits, excessive voids and honeycombing, and
concrete delivery records that indicate excessive time between mixing and
placement and/or excessive water was added to the mixture during delivery
and placement. Any of these indicators alone are sufficient reason for the
Contracting Officer to request additional sampling, testing and service
life modeling to quantify the concrete properties. If justified, cores may
be extracted for testing, and an investigation into the cause for
non-conformance shall be conducted. The investigation may include
statistical analysis of the test data collected to date; appropriateness of
the pre-defined QAL based on statistical analysis of production data; the
impact of the non-conforming material on the structure strength and/or
service life; and recommendations for concrete production process
improvements, mitigation, or remediation, as appropriate.

Investigations into non-conforming materials shall be conducted at the


Contractor's expense. The Contractor shall be responsible for the
investigation and shall make written recommendations to adequately mitigate
or remediate the non-conforming material. The Contracting Officer may
accept, accept with reduced payment, require mitigation, or require removal
and replacement of non-conforming material at no additional cost to the
Government.

1.8.5 Test Reports

Concrete Test Reports shall be identified by a sequential report


identification code. Each report shall identify the placement date,
placement location, weather, name of testing technician, time of sampling,
batch ticket number, fresh concrete test results, and hardened concrete
test results.

1.8.5.1 Concrete Mixture Requirements

a. Submit copies of test reports conforming to ASTM C1077 showing that the
mixture has been successfully tested to produce concrete with the
properties specified and that mixture will be suitable for the job
conditions. Test reports shall be submitted along with the concrete
mixture proportions. Obtain approval before concrete placement.
b. Fully describe the processes and methodology whereby mixture
proportions were developed and tested and how proportions will be
adjusted during progress of the work to achieve, as closely as
possible, the designated levels of relevant properties.

c. Submit copies of reports from STADIUM® analysis with laboratory


analysis and modeling results indicating contract-goal service life
will be met.

1.8.5.2 Complementary Cementing Materials

Submit test results in accordance with ASTM C618 and the physical and
chemical analysis in accordance with applicable ASTM standards such as
ASTM C311/C311M for fly ash. Submit test results performed within 6 months
of submittal date. Update this report during construction as necessary to
assure that the complementary cementing materials used on the projects
meets the ASTM criteria and the report on file is never older than 6 months.

1.8.5.2.1 Ground Granulated Blast-Furnace Slag

Submit test results in accordance with ASTM C989/C989M for ground


granulated blast-furnace slag. Submit test results performed within 6

SECTION 03 31 29 Page 40
months of submittal date. Update this report during construction as
necessary to assure that the report on file is never older than 6 months.

1.8.5.2.2 Ultra Fine Fly Ash or Pozzolan

Submit test results in accordance with ASTM C618 as a Class F fly ash or
Class N pozzolan with the following additional requirements:

a. The strength activity index at 28 days shall be at least 95 percent of


the control.

b. The average particle size shall not exceed 6 microns.

c. The sum SiO2 plus Al2O3 plus Fe2O3 shall be greater than 77 percent.

Submit test results performed within 6 months of submittal date. Update


this report during construction as necessary to assure that the report on
file is never older than 6 months.

1.8.5.3 Silica Fume

Submit test results in accordance with ASTM C1240 for silica fume. Data
shall be based upon tests performed within 6 months of submittal. Update
this report during construction as necessary to assure that the report on
file is never older than 6 months.

1.8.5.4 Aggregates

Aggregate samples shall be obtained in accordance with ASTM D75/D75M


and shall be representative of the materials to be used for the project.
Submit test results for aggregate quality in accordance with ASTM C33/C33M,
and the combined gradation curve proposed for use in the work and used in
the mixture qualification, and ASTM C295/C295M for results of petrographic
examination. Confirm that the potential for alkali-silica reaction are
within allowable limits by conducting tests in accordance with ASTM C1260.
Submit results of all tests during progress of the work in tabular and
graphical form as noted above, describing the cumulative combined aggregate
grading and the percent of the combined aggregate retained on each sieve.

1.8.5.5 Admixtures

Submit test results in accordance with ASTM C494/C494M and ASTM C1017/C1017M
for concrete admixtures, ASTM C260/C260M for air-entraining admixture, and
manufacturer's literature and test reports for corrosion inhibitors and
anti-washout admixture. Submitted data shall be based upon tests performed
within 6 months of submittal. Submit certified copies of test results for
the specific lots or batches to be used on the project. Test results shall
be not more than 6 months old prior to use in the work. Chemical admixtures
that have been in storage at the project site for longer than 6 months or
that has been subjected to freezing will be retested at the expense of the
Contractor.

1.8.5.6 Portland Cement

Portland cement[,ground granulated blast furnace (GGBF) slag,] [and


pozzolan] will be accepted on the basis of manufacturer's certification of
compliance, accompanied by mill test reports showing that the material in
each shipment meets the requirements of the specification under which it is
furnished. Mill test reports shall be no more than 1 month old, prior to

SECTION 03 31 29 Page 41
use in the work. No cementitious material shall be used until notice of
acceptance has been given by the Contracting Officer. Cementitious material
may be subjected to check testing by the Government from samples obtained
at the mill, at transfer points, or at the project site. If tests prove
that a cementitious material that has been delivered is unsatisfactory, it
shall be promptly removed at Contractor's expense from the site of the
work. Cementitious material that has not been used within 6 months after
testing shall be retested at the Contractor's expense and shall be rejected
if test results are not satisfactory. Submit test results in accordance
with ASTM C150/C150M portland cement and/or ASTM C595/C595M and
ASTM C1157/C1157M for blended cement.

1.8.5.7 Testing During Construction

During construction, the Contractor is responsible for sampling and testing


aggregates, cementitious materials, and concrete as specified herein. The
Government will sample and test concrete and ingredient materials as
considered appropriate. Provide facilities and labor as may be necessary for
procurement of representative test samples. Testing by the Government
will in no way relieve the Contractor of the specified testing requirements.

1.8.5.8 Test Section

a. Horizontal Placements. No more than 90 days prior to construction,


construct a Test Section 3048 mm by 3048 mm by 203.2 mm 10 by 10 feet
by 8 inches thick near the job site, but not as part of the structure.
The Test Section shall meet all specification requirements and be
acceptable to the Contracting Officer in all respects, including but
not limited to delivery time, placement, consolidation, curing and
surface texture. Use the Test Section to develop and demonstrate to the
satisfaction of the Contracting Officer the proposed techniques of
mixing, hauling, placing, consolidating, finishing, curing, initial saw
cutting, start-up procedures, testing methods, plant operations, and
the preparation of the construction joints. The mixing plant shall be
operated and equipment calibrated prior to start of placing the Test
Section. Use the same equipment, materials, and construction techniques
on the Test Section as will be used in all subsequent work. Concrete
production, placing, consolidating, curing, construction of joints, and
all testing shall be in accordance with applicable provisions of this
specification. At a minimum of three days after completion of the Test
Section, extract a sufficient number of concrete cores 100 by 200 mm 4
by 8 inch to conduct tests to evaluate; strength, homogeneity,
consolidation, segregation and transport properties. Test Results that
are unacceptable Test Section will necessitate construction of an
additional Test Section at no additional cost to the Government

b. Vertical Placements. No more than 90 days prior to construction,


construct a Test Section that represents the vertical placements, (if
applicable) near the job site, but not as part of the structure. Test
Section shall meet all specification requirements and being acceptable
to the Contracting Officer in all respects, including but not limited
to delivery time, placement, consolidation, curing and surface texture.
Use the Test Section to develop and demonstrate to the satisfaction of
the Contracting Officer the proposed techniques of mixing, hauling,
placing, consolidating, finishing, curing, initial saw cutting,
start-up procedures, testing methods, plant operations, and the
preparation of the construction joints. The mixing plant shall be
operated and equipment calibrated prior to start of placing the Test
Section. Use the same equipment, materials, and construction techniques

SECTION 03 31 29 Page 42
on the Test Section as will be used in all subsequent work. Concrete
production, placing, consolidating, curing, construction of joints, and
all testing shall be in accordance with applicable provisions of this
specification. At a minimum of three days after completion of the Test
Section, extract a sufficient number of concrete cores to evaluate
homogeneity, consolidation, segregation and transport properties. If
any of the test results are unacceptable, the Contracting Officer may
require that a new Test Section be accomplished at no additional cost
to the Government.

1.8.5.9 Acceptability of Work

The materials and the structure itself will be accepted on the basis of
tests made by the Contractor and shall be in compliance with the criteria
herein. The Government may make check tests at its expense to validate the
results of the Contractor's testing. Testing performed by the Government
will in no way relieve the Contractor from the specified testing
requirements.

PART 2 PRODUCTS

**************************************************************************
NOTE: Delete any reference to any products which
are not to be used on the project. Coordinate all
product requirements with the appropriate agency's
Contracting Officer.
**************************************************************************

2.1 CEMENTITIOUS MATERIALS

**************************************************************************
NOTE: Edit these paragraphs as appropriate for the
particular project. Guidance for use of cementitious
materials should be sought from the agency's Subject
Matter Expert in Concrete Materials. Consideration
should be given to the use of fly ash or GGBF slag
for partial replacement of portland cement up to 50
percent. Type III cement should not be specified.
Laboratory mixtures, proportioning studies, and
tests during the design stage of the project should
be inclusive of service life modeling.
**************************************************************************

**************************************************************************
NOTE: Complementary Cementing Materials (AKA
Supplementary Cementitious Materials (SCM))

When granulated slag, coal fly ash, and natural


pozzolans are used as cementing materials for
replacement of portland cement in a concrete
mixture, and if by doing so the sustainability,
durability and the initial cost of the concrete
mixture show considerable improvement then it is
improper to call these materials "supplementary
cementitious materials" (SCM). As the concrete
industry moves forward and takes better advantage of
this proven technology, it is appropriate to
introduce the term "complementary cementing
material" (CCM) to describe these mixtures. When

SECTION 03 31 29 Page 43
lesser amounts of these materials are used to
produce concrete mixtures that do not show these
benefits then the term SCM remains applicable.

The Engineer of Record is encouraged to specify the


use of complementary cementing materials. For
example 50 percent replacement of the portland
cement using Class F fly ash has been successfully
demonstrated to offer the required compressive
strength (f'cr), drying shrinkage, lower
permeability, constructability, and the potential to
accomplish a structure with the design service life
while being less expensive with a smaller carbon
footprint.

**************************************************************************

Cementitious materials shall be portland cement or cement blended with


complementary cementing materials. New submittals are required when the
cementitious materials change sources or types.

The Contractor shall provide cementitious materials meeting the


requirements of the applicable specification, and as modified herein.
Provide mill certificates and test results conducted within six-months of
the submittal date as part of the concrete mixture qualification submittal.

Provide a single manufacturer of cementitious material for each type of


cement and complementary cementing materials supplied to the project.

2.1.1 Portland Cement

Provide portland cement conforming to ASTM C150/C150M, Type [I] [II]


[V],low alkali [including false set requirements] with tri-calcium
aluminates (C3A) content less than 10 percent and a maximum cement-alkali
content of 0.80 percent Na2Oe (sodium oxide) equivalent. Type III cement
shall be used only with concurrence of the agency's Subject Matter Expert
in Concrete Materials. When HVFA mixtures are specified they should be
blended with Type II portland cement. HVFA is encouraged instead of using
Type V cement in high-sulfate areas. Low alkali cement may be required if
the proposed aggregates are found to be expansive.

ASTM C150/C150M cements shall be combined with complementary cementing


materials in the concrete mixture.

2.1.2 Blended Cements

Blended cement shall conform to ASTM C595/C595M, Type IP or IS, including


the optional requirement for mortar expansion [and sulfate soundness] and
consist of a mixture of ASTM C150/C150M Type I, or Type II cement and a
complementary cementing material. The slag added to the Type IS blend shall
be ASTM C989/C989M ground granulated blast-furnace slag. The pozzolan
added to the Type IP blend shall be ASTM C618 Class F and shall be
interground with the cement clinker. The manufacturer shall state in
writing that the amount of pozzolan in the finished cement will not vary
more than plus or minus 5 mass percent of the finished cement from
lot-to-lot or within a lot. The percentage and type of mineral admixture
used in the blend shall not change from that submitted for the aggregate
evaluation and mixture proportioning.

SECTION 03 31 29 Page 44
2.1.3 Pozzolan

2.1.3.1 Fly Ash

**************************************************************************
NOTE: Class C fly ash is not permitted.

Use loss on ignition not exceeding 3 percent for


frost areas to reduce carbon interference with air
entraining admixture.
**************************************************************************

Fly ash shall conform to ASTM C618, Class F, including the optional
requirements for uniformity and effectiveness in controlling Alkali-Silica
reaction and shall have a loss on ignition not exceeding [3][6] percent.
Class F fly ash for use in mitigating Alkali-Silica Reactivity shall have a
Calcium Oxide (CaO) content of less than 8 percent and a total equivalent
alkali content less than 1.5 percent. Add with cement.

2.1.3.2 Raw or Calcined Natural Pozzolan

Natural pozzolan shall be raw or calcined and conform to ASTM C618, Class
N, including the optional requirements for uniformity and effectiveness in
controlling Alkali-Silica reaction and shall have an on ignition loss not
exceeding 3 percent. Class N pozzolan for use in mitigating Alkali-Silica
Reactivity shall have a Calcium Oxide (CaO) content of less than 13 percent
and total equivalent alkali content less than 3 percent.

2.1.3.3 Ultra Fine Fly Ash and Ultra Fine Pozzolan

Ultra Fine Fly Ash (UFFA) and Ultra Fine Pozzolan (UFP) shall conform to
ASTM C618, Class F or N, and the following additional requirements:

a. The strength activity index at 28 days of age shall be at least 95


percent of the control specimens.

b. The average particle size shall not exceed 6 microns.

c. The sum of SiO2 + Al2O3 + Fe2O3 shall be greater than 77 percent.

2.1.4 Ground Granulated Blast-Furnace (GGBF) Slag

Ground Granulated Blast-Furnace Slag shall conform to ASTM C989/C989M,


[Grade 100 or Grade 120]. Add with cement.

2.1.5 Silica Fume

**************************************************************************
NOTE: Silica Fume shall only be used for OCONUS
projects where Class F fly ash and GGBF slag are not
available, and when approved by the Contracting
Officer. Guidance for use of silica fume should be
sought from the agency's Subject Matter Expert in
Concrete Materials.
**************************************************************************

Silica fume shall conform to ASTM C1240, including the optional limits on
reactivity with cement alkalis. Silica fume may be furnished as a dry,
densified material or as slurry. Proper mixing is essential to accomplish

SECTION 03 31 29 Page 45
proper distribution of the silica fume and avoid agglomerated silica fume
which can react with the alkali in the cement resulting in premature and
extensive concrete damage. Supervision at the batch plant, finishing, and
curing is essential. Provide at the Contractor's expense the services of a
manufacturer's technical representative, experienced in mixing,
proportioning, placement procedures, and curing of concrete containing
silica fume. This representative must be present on the project prior to
and during at least the first 4 days of concrete production and placement
using silica fume. A High Range Water Reducer (HRWR) shall be used with
silica fume. Finishing may be more difficult. Proper curing is essential
because there is a tendency for plastic shrinkage cracking.

2.1.6 Complementary Cementing Materials (AKA Supplementary Cementitious


Materials (SCM) Content (SCM))

The concrete mix shall always contain complementary cementing materials


whether or not the aggregates are found to be reactive in accordance with
the subpart entitled "Aggregates". Concrete mixtures shall be designed and
proportioned to meet the requirements for strength, constructability,
shrinkage, and service life.

**************************************************************************
NOTE: This specification requires that the
structural requirements (f'c) be met and concrete
strength is between 1.0 f'c and 1.2 f'c. If the
prequalified mixture as approved by the Engineer of
Record should produce a higher design strength
(fcr), that strength shall be used instead of f'c.
Maintain required w/cm ratio regardless of strength
requirements.
**************************************************************************

2.2 AGGREGATES

Comply with ASTM C33/C33M Class 4S, except as modified herein.

The quantities to be retained on each sieve may be adjusted only where


available aggregates are elongated or slivered and cause interference with
mix mobility, or available aggregate gradations do not comply with the 18-8
requirement. When necessary to satisfy local conditions and when
permitted, the combined aggregate percentages may be changed to not more
than 22 percent nor less than 6 percent retained on any individual
sieve.The combined aggregates in the mixture (coarse, intermediate, and
fine) shall be well graded with no more than 18 percent nor less than 8
percent of the combined aggregate retained on any individual sieve, unless
satisfactory performance can be demonstrated. The 300 micrometers No. 50
sieve may have less than 8 percent retained; sieves finer than 300
micrometers No. 50 shall have less than 8 percent retained, and the
coarsest sieve may have less than 8 percent retained. Use intermediate
sizes for blending where necessary, to provide a well graded combined
aggregate.

a. Provide gradation of individual aggregate sizes using standard concrete


aggregate sieves including 37.5 mm 1-1/2 inches, 25 mm one inch, 19 mm
3/4 inch, 12.5 mm 1/2 inch, 9.5 mm 3/8 inch, 4.75 mm No. 4, 2.36 mm No.
8, 1.18 mm No. 16, 600 micrometers No. 30, 300 micrometers No. 50, and
150 micrometers No. 100.

b. Provide aggregates for exposed concrete from one source. Aggregate

SECTION 03 31 29 Page 46
reactivity shall be limited per the subpart entitled "Aggregates".
Provide aggregate containing no deleterious material properties as
identified by ASTM C295/C295M.

c. Where a size designation is indicated, that designation indicates the


nominal maximum size of the coarse aggregate.

d. Aggregate tests shall be conducted within 6 months from the date of


concrete mixture submittal.

e. Provide ASTM C1260 or ASTM C1567 test results conducted with 6 months
of the submittal date showing the proposed coarse and fine aggregates
are either: innocuous to alkali silica reaction; or that reactivity has
been mitigated by the proposed cementitious materials as modified
herein. Conduct ASTM C1260 tests on each aggregate source separately.
Fine and coarse aggregates to be used in all concrete shall be
evaluated and tested for alkali-aggregate reactivity. Both coarse
aggregate size groups shall be tested. Test results of the individual
aggregates shall have a measured expansion equal to or less than 0.08
percent after 28 days of immersion in a 1N 1M NaOH solution at 176
degrees.

f. Should the test data indicate an expansion of greater than 0.08


percent, the aggregate(s) shall be rejected or additional testing shall
be performed as follows: utilize the Contractor's proposed low alkali
portland cement, blended cement, and/or complementary cementing
materials, in combination with each individual aggregate. If SCMs are
being evaluated, the testing shall be in accordance with ASTM C1567.
Determine the quantity that will meet all the requirements of these
specifications and that will lower the expansion equal to or less than
0.08 percent after 28 days of immersion in a 1N NaOH solution. Mixture
proportioning shall be based on the highest percentage of SCM required
to mitigate ASR-reactivity.

2.3 WATER

Water shall comply with the requirements of ASTM C94/C94M and


ASTM C1602/C1602M, except that the chloride and sulfate limits as tested in
accordance with ASTM D512 and ASTM D516 shall not exceed 500 parts per
million chloride ion and not more than 1000 parts per million of sulfate
ion as SO4. Water shall be free from injurious amounts of oils, acids,
alkalis, salts, and organic materials. Where non-potable water or water
from reprocessed concrete is proposed for use in the work, submit results
of tests in accordance with ASTM C1602/C1602M. Submit test results in
accordance with ASTM D512 and ASTM D516.

2.4 ADMIXTURES

a. Provide certifications that chemical admixtures comply with the


requirements shown in Table 5 and are compatible with each other. Use
admixtures in accordance with manufacturer's recommendations, as
appropriate for the climatic conditions and construction needs.

b. Do not use calcium chloride or admixtures containing chloride ion


content in more than trace amounts from impurities in admixture
ingredients or potable water. Provide maximum concentrations of
corrosion-inducing chemicals as shown in Table 5. For concrete that
may be in contact with prestressing steel tendons, the concentration
shall not exceed 60 percent of the limits given in Table 5. For the

SECTION 03 31 29 Page 47
concentration in grout for prestressing ducts, do not exceed 25 percent
of the limits in Table 5.

Table 5 - Limits on Corrosion-Inducing Chemicals

Chemical* Limits, Percent** Test Method

Chlorides 0.10 ASTM D512

Fluorides 0.10 ASTM D1179

Nitrates 0.17 ASTM D3867

* Limits refer to water-soluble chemicals

** Limits are expressed as a percentage of the mass of


the total cementitious materials.

c. Provide anti-washout or viscosity modifying admixtures for underwater


concrete placement. Provide certification that the admixture is
compatible with the cementitious materials and other chemical
admixtures in the proposed concrete mixture. The anti-washout or
viscosity modifying admixture shall require approval by the Contracting
Officer and have a proven record of performance with a minimum of five
similar projects. Test per COE CRD-C 61 to determine cumulative mass
loss shall be performed once for each 267.6 cubic meters 350 cubic yards
of underwater concrete and results submitted to Contracting Officer
for approval prior to continued use.

d. The total alkali contribution of chemical admixtures shall not increase


the total sodium-oxide equivalent content of the concrete mixture by
more than 0.3 kg/m3 0.5 lb/yd3.

2.4.1 Air Entraining

Provide air entraining admixtures conforming to ASTM C260/C260M

2.4.2 Accelerating

ASTM C494/C494M, Type C.

2.4.3 Retarding

ASTM C494/C494M, Type B, D, or G.

2.4.4 Water Reducing

ASTM C494/C494M, Type A, E, or F.

High Range Water Reducer (HRWR) shall be ASTM C494/C494M, Type F and
ASTM C1017/C1017M.

2.4.5 Corrosion Inhibitors

Corrosion inhibitors are considered "supplemental corrosion projection".


Adjust the quantity of concrete mixing water for the mass of water in the
admixture. Accelerating and set adjusted versions are acceptable Concrete

SECTION 03 31 29 Page 48
setting time and mixture workability shall be evaluated. The use of
supplemental corrosion protection shall not be used in lieu of the
fundamental requirement to meet the defined service life using quality
concrete with specified concrete cover over the steel reinforcing. Changes
to the corrosion propagation period that is calculated for quality concrete
due to the use of supplemental corrosion protection materials may be
approved by the Contracting Officer based on evidence provided by the
Contractor and reviewed by the agency's Subject Matter Expert in Concrete
Materials on a case-by-case basis.

2.5 NON-SHRINK GROUT

ASTM C1107/C1107M.

2.6 MATERIALS FOR FORMS

Provide wood, plywood, or steel. Use plywood or steel forms where a smooth
form finish is required. Lumber shall be square edged or tongue-and-groove
boards, free of raised grain, knotholes, or other surface defects.

Plywood: APA PS 1, B-B concrete form panels or better. Steel form


surfaces shall not contain irregularities, dents, or sags.

2.6.1 Form Ties and Form-Facing Material

a. Provide a form tie system that does not leave mild steel after
break-off or removal any closer than 50 mm 2 inches from the exposed
surface. Do not use wire alone. Form ties and accessories shall not
reduce the effective cover of the reinforcement.

b. Form-facing material shall be structural plywood or other material that


can absorb air and some of the high water-cementitious materials ratio
surface paste that may be trapped in pockets between the form and the
concrete. Maximum reuse is three times. Provide forms with a form
treatment to prevent bond of the concrete to the forms. Use a
controlled permeability form liner in strict accordance with the
manufacturer's recommendations.

2.7 REINFORCEMENT

2.7.1 Prestressing Steel

**************************************************************************
NOTE: Use prestressing in fender and bearing piles,
deck soffits, and wherever possible.
Post-tensioning of pile caps and decks is
recommended where feasible. Do not mix coated
prestressing strands and plain prestressing
strands. This will produce a large corrosion cell
between the plain strand and any defect in the
coated strand.
**************************************************************************

Use seven-wire stress-relieved or low-relaxation strand conforming to


ASTM A416/A416M, Grade 270. Use of indented seven-wire stress-relieved or
low-relaxation strand conforming to ASTM A882/A882M, Grade 270; or
epoxy-filled seven-wire stress-relieved or low-relaxation strand conforming
to ASTM A886/A886M, Grade 270 shall be permitted in lieu of prestressing
steel conforming to ASTM A416/A416M. Use prestressing steel free of grease,

SECTION 03 31 29 Page 49
oil, wax, paint, soil, dirt, and loose rust. Do not use prestressing
strands or wire having kinks, bends, or other defects.

2.7.2 Reinforcing Bars

**************************************************************************
NOTE: It is intended that plain steel rebar with
specified concrete cover of 75 mm 3.0 inches shall
normally be specified according to applicable
codes. Predictive modeling can confirm that the
candidate concrete mixture, type of steel and
concrete cover will yield the required service life
for the particular structural element under
consideration. For the purpose of predicting the
service life of the concrete, the design shall meet
the owner's design life without relying on a barrier
such as epoxy or zinc coating of the steel rebar or
passive cathodic protection for additional life
extension. The use of galvanized rebar and
epoxy-coated rebar are acceptable for use, but it is
difficult to justify a specific life extension from
either without conclusive research data.

ASTM A706/A706M bars are mainly used in seismic


design or for welding. Do not mix coated rebar and
plain reinforcing bars. This may produce a large
corrosion cell between the plain bar and any defect
in the coated bar.
**************************************************************************

ACI 301M ACI 301 unless otherwise specified and shall meet the design yield
strength and ductility requirements. Deformed reinforcing bars meeting the
requirements of ASTM A615/A615M with the bars marked A, Grade ASTM A276
stainless steel bars; ASTM A767/A767M Class 1 galvanized; prefabricated
epoxy coated, ASTM A934/A934M; ASTM A955/A955M stainless steel bars;
ASTM A1035/A1035M MMFX2 bars; ASTM A1055/A1055M Z bars; or other approved
reinforcing material shall be permitted for use in the cast-in-place
concrete system.

The reinforcing selected shall match the structural properties of the


reinforcing specified. Alternative reinforcing bars shall have similar
structural properties to the specified reinforcing and may be used with the
Contracting Officers approval.

2.7.2.1 Reinforcement and Protective Coating

Provide coating manufacturer's and coating applicator's test data sheets


certifying that applied coating meets the requirements of the concrete
system. Extensions to the corrosion propagation period may be approved by
the Contracting Officer based on evidence provided by the Contractor and
reviewed by the agency's Subject Matter Expert in Concrete Materials on a
case-by-case basis.

2.7.3 Mechanical Reinforcing Bar Connectors

ACI 301M ACI 301. Provide 125 percent minimum yield strength of the
reinforcement bar. Coat connectors in accordance with the requirements of
the reinforcing bars.

SECTION 03 31 29 Page 50
2.7.4 Welded Wire Fabric

Comply with ASTM A1064/A1064M carbon steel. Provide flat sheets of welded
wire fabric for slabs and toppings.

2.7.5 Wire

Comply with ASTM A1064/A1064M carbon steel.

2.8 ACCESSORY MATERIALS

2.8.1 Polyvinylchloride Waterstops

COE CRD-C 572.

2.8.2 Materials for Curing Concrete

2.8.2.1 Impervious Sheeting

ASTM C171; waterproof paper, clear or white polyethylene sheeting, or


polyethylene-coated burlap.

2.8.2.2 Pervious Sheeting

AASHTO M 182 or carpet covering the free surface and kept continuously wet
throughout the curing period..

2.8.2.3 Liquid Membrane-Forming Compound

Comply with ASTM C309, white-pigmented, Type 2, Class B.

2.8.3 Liquid Chemical Sealer-Hardener Compound

Provide magnesium fluosilicate compound which when mixed with water seals
and hardens the surface of the concrete. Do not use on exterior slabs
exposed to freezing conditions. Compound shall not reduce the adhesion of
resilient flooring, tile, paint, roofing, waterproofing, or other material
applied to concrete.

2.8.4 Expansion/Contraction Joint Filler

Comply with ASTM D1751 or ASTM D1752, 13 mm 1/2 inch thick unless otherwise
indicated.

2.8.5 Joint Sealants

2.8.5.1 Horizontal Surfaces

**************************************************************************
NOTE: For horizontal surfaces subject to jet fuel,
specify section 32 01 19 FIELD MOLDED SEALANTS FOR
SEALING JOINTS IN RIGID PAVEMENTS.
**************************************************************************

Horizontal surfaces are defined as all surfaces with a 3 percent maximum


slope. ASTM D6690 or ASTM C920, Type M, Class 25, Use T.

SECTION 03 31 29 Page 51
2.8.5.2 Vertical Surfaces

**************************************************************************
NOTE: Specify ASTM C920 for vertical surfaces
greater than 3 percent slope and not subject to jet
fuel, gasoline, fuel oil, etc. For vertical
surfaces greater than 3 percent slope and subject to
jet fuel, specify FS SS-S-200, no sag.
**************************************************************************

Vertical surfaces are defined as all surfaces with a slope greater than 3
percent. ASTM C920, Type M, Grade NS, Class 25, Use T. FS SS-S-200, no sag.

PART 3 EXECUTION

3.1 FORMS

a. Provide formwork with clean-out openings to permit inspection and


removal of debris. Formwork shall be gasketed or otherwise rendered
sufficiently tight to prevent leakage of paste or grout under heavy,
high-frequency vibration. Use a release agent that does not cause
surface dusting. Limit reuse of plywood to no more than three times.
Reuse may be further limited by the Contracting Officer if it is found
that the pores of the plywood are clogged with paste so that the wood
does not absorb air and some of the high water-cementitious materials
ratio paste that may be trapped in pockets between the form and the
concrete.

b. Comply with ACI 301M ACI 301. Concrete for footings may be placed in
excavations without forms upon inspection and approval by the
Contracting Officer. Excavation width shall be a minimum of 100 mm 4
inches greater than indicated. Set forms rigidly, mortar-tight, and
true to line and grade. Chamfer above grade exposed joints, edges, and
external corners of concrete 20 mm 0.75 inch unless otherwise
indicated. Forms submerged in water shall be watertight.

c. Patch form tie holes with a no shrink patching material in accordance


with the manufacturer's recommendations and subject to approval.

3.1.1 Coating

Before concrete placement, coat the contact surfaces of forms with a no


staining mineral oil, no staining form coating compound, or two coats of
nitrocellulose lacquer. Do not use mineral oil on forms for surfaces to
which adhesive, paint, or other finish material is to be applied.

3.1.2 Removal of Forms and Supports

After placing concrete, forms shall remain in place for the time periods
specified in ACI 347, except for concrete placed underwater, forms shall
remain in place a minimum of 48 hours. Prevent concrete damage during form
removal.

3.1.2.1 Special Requirements for Reduced Time Period

Forms may be removed earlier than specified if ASTM C39/C39M test results
of field-cured samples from a representative portion of the structure or
other approved and calibrated non-destructive testing techniques show that
the concrete has reached a minimum of 85 percent of the design strength.

SECTION 03 31 29 Page 52
3.1.3 Reshoring

Do not allow construction loads to exceed the superimposed load which the
structural member, with necessary supplemental support, is capable of
carrying safely and without damage. Reshore concrete elements where forms
are removed prior to the specified time period. Do not permit elements to
deflect or accept loads during form stripping or reshoring. Forms on
columns, walls, or other load-bearing members may be stripped after 2 days
if loads are not applied to the members. After forms are removed, slabs
and beams over 3 meters 10 feet in span and cantilevers over 1.2 meters 4
feet shall be reshored for the remainder of the specified time period in
accordance with subpart entitled "Removal of Forms and Supports." Perform
reshoring operations to prevent subjecting concrete members to overloads,
eccentric loading, or reverse bending. Reshoring elements shall have the
same load-carry capabilities as original shoring and shall be spaced
similar to original shoring. Firmly secure and brace reshoring elements to
provide solid bearing and support.

3.2 PLACING REINFORCEMENT AND MISCELLANEOUS MATERIALS

ACI 301M ACI 301. Remove rust, scale, oil, grease, clay, or foreign
substances from reinforcing that would reduce the epoxy coating bond from
reinforcing. Do not tack weld. Inspect and verify proper reinforcement
grade, quantity, spacing, and clearance requirements prior to concrete
placement. Inspect placed steel reinforcing for coating damage prior to
placing concrete. Repair all visible damage.

3.2.1 Coated Reinforcing

The use of supplemental corrosion protection shall not be used in lieu of


the fundamental requirement to meet the defined service life. Extensions to
corrosion propagation period may be approved by the Contracting Officer
based on evidence provided by the Contractor and reviewed by the agency's
Subject Matter Expert in Concrete Materials on a case-by-case basis.

Record coating lot on each shipping notice and carefully identify and retag
bar bundles from bending plant. Provide systems for handling coated bars
which have padded contact areas, nylon slings, etc., to keep bars free of
dirt and grit. Carefully handle and install bars to minimize job site
patching including lifting and supporting bundled coated bars with strong
back, multiple supports, or platform bridge to prevent sagging and
abrasion. When possible, assemble reinforcement as tied cages prior to
final placement into the forms. Bundling bands shall be padded where in
contact with bars. Do not drop or drag bars or bundles. Store coated bars
both in shop and in field, aboveground, on wooden or padded cribbing with
adequate protective blocking between layers. Schedule deliveries of coated
bars to the job site to avoid the need for long term storage. Protect from
direct sunlight and weather. Bars to be stored longer than 12 hours at the
job site shall be covered with opaque polyethylene sheeting or other
suitable equivalent protective material. Inspect for defects and provide
required repairs prior to assembly. After assembly, reinspect and provide
final repairs. Excessive nicks and scrapes which expose steel shall be
cause for rejection.

a. Immediately prior to application of the patching material, any rust and


debonded coating shall be manually removed from the reinforcement by
suitable techniques employing devices such as wire brushes and emery
paper. Care shall be exercised during this surface preparation so that

SECTION 03 31 29 Page 53
the damaged areas are not enlarged more than necessary to accomplish
the repair. Damaged areas shall be clean of dirt, debris, oil, and
similar materials prior to application of the patching material.

b. Repair and patching shall be done in accordance with the patching


material manufacturer's recommendations. These recommendations,
including cure times, shall be available at the job site at all times.

c. Allow adequate time for the patching materials to cure in accordance


with the manufacturer's recommendation prior to concrete placement.

d. Rinse placed reinforcing bars with ASTM C1602/C1602M compliant water to


remove chloride contamination prior to placing concrete.

3.2.2 Reinforcement Supports

Place reinforcement and secure with non-corrodible chairs, spacers, and


hangers. Metal hangers may be used, but shall be of similar material to
the reinforcing. Support reinforcement on the ground with concrete or other
non-corrodible material, having a compressive strength equal to or greater
than the concrete being placed and having permeability equal or less than
the concrete being placed.

Coated reinforcing bars supported from formwork shall rest on coated wire
bar supports, or on bar supports made of dielectric material or other
acceptable material. Wire bar supports shall be coated with dielectric
material, compatible with concrete, for a minimum distance of 50 mm 2 inches
from the point of contact with the coated reinforcing bars. Reinforcing
bars used as support bars shall be coated with the same material as the
reinforcing. Spreader bars, where used, shall be coated. Non-coated
combination bar clips and spreaders used in construction with coated
reinforcing bars shall be made corrosion resistant or coated with
dielectric material. Coated bars shall be tied with plastic-coated tie
wire; or other materials acceptable to the Contracting Officer.

3.2.3 Splicing

As indicated. For splices not indicated, comply with ACI 301M ACI 301. Do
not splice at points of maximum stress. Overlap welded wire fabric the
spacing of the cross wires, plus 50 mm 2 inches. Welded splices shall
comply with AWS D1.4/D1.4M and be approved prior to use.

3.2.4 Future Bonding

Plug exposed, threaded, mechanical reinforcement bar connectors with a


greased bolt. Bolt threads shall match the connector. Countersink the
connector in the concrete. Caulk the depression after the bolt is
installed.

3.2.5 Cover

**************************************************************************
NOTE: Uniform, high quality concrete cover over the
steel reinforcement is critically important for
long-term durability.
**************************************************************************

As a minimum, comply with ACI 318M ACI 318 for concrete cover over the
steel reinforcement. The cover may be greater than that required by ACI 318M

SECTION 03 31 29 Page 54
ACI 318 based on the results from service life modeling. Use ACI 117 to
determine allowable tolerances for the placement of the steel. When
predicting service life, use the effective value of concrete cover after
subtracting the allowable placement tolerances for the reinforcing. For
example a specified 76.2 mm 3 inch cover will result in about 63.5 mm 2.5
inches of effective concrete cover for predicting service life.

3.2.6 Setting Miscellaneous Material and Prestress Anchorages

Place and secure anchors, bolts, pipe sleeves, conduits, and other such
items in position before concrete placement. Plumb anchor bolts and check
location and elevation. Temporarily fill voids in sleeves with readily
removable material to prevent the entry of concrete. Electrically isolate
exposed steel work and its anchor systems from the primary steel
reinforcement with at least 50 mm 2 inches of concrete. Coat exposed steel
work to reduce corrosion. Take particular care to ensure against corrosion
on edges and horizontal surfaces. Use epoxy coatings for protection of
carbon steel plates and fittings.

3.2.7 Construction Joints

Locate joints to least impair strength. Continue reinforcement across


joints unless otherwise indicated. Final joint locations are subject to
Government approval or substantiating calculations from the Contractor.

3.2.8 Expansion Joints and Contraction Joints

Provide expansion joint at edges of interior floor slabs on grade abutting


vertical surfaces, and as indicated. Make expansion joints 13 mm 1/2 inch
wide unless indicated otherwise. Fill expansion joints not exposed to
weather with preformed joint filler material. Completely fill joints
exposed to weather with joint filler material and joint sealant. Do not
extend reinforcement or other embedded metal items bonded to the concrete
through any expansion joint unless an expansion sleeve is used. Place
contraction joints, either formed or saw cut or cut with a jointing tool,
to the indicated depth after the surface has been finished. Sawed joints
shall be completed within 4 to 12 hours after concrete placement. Protect
joints from intrusion of foreign matter.

3.2.9 Waterstop Splices

Fusion weld in the field.

3.2.10 Pits and Trenches

Place bottoms and walls monolithically or provide waterstops and keys.

3.3 BATCHING, MEASURING, MIXING, AND TRANSPORTING CONCRETE

ASTM C94/C94M,ACI 301M ACI 301, and ACI 304R, except as modified herein.
Batching equipment shall be such that the concrete ingredients are
consistently measured within the following tolerances: 1 percent for cement
and water, 2 percent for aggregate, and 3 percent for admixtures. Furnish
mandatory batch tickets imprinted with mix identification, batch size,
batch design and measured weights, moisture in the aggregates, and time
batched for each load of ready mix concrete. When a pozzolan is batched
cumulatively with the cement, it shall be batched after the cement has
entered the weight hopper.

SECTION 03 31 29 Page 55
3.3.1 Measuring

Make measurements at intervals as specified in subparts entitled "Sampling"


and "Testing."

Adjust batch proportions to replicate the mixture design using methods


provided in the approved quality assurance plan. Base the adjustments on
results of tests of materials at the batch plant for use in the work.
Maintain a full record of adjustments and the basis for each.

3.3.2 Mixing

Comply with ASTM C94/C94M and ACI 301M ACI 301.If time of discharge exceeds
time required by ASTM C94/C94M, submit a request along with description of
precautions to be taken.

3.3.3 Transporting

Comply with ACI 304R.

3.4 PLACING CONCRETE

Comply with ACI 304R and ACI 304.2R. Place concrete as soon as
practicable after the forms and the reinforcement have been inspected and
approved. Do not place concrete when weather conditions prevent proper
placement and consolidation; in uncovered areas during periods of
precipitation; or in standing water. Prior to placing concrete, remove
dirt, construction debris, water, snow, and ice from within the forms.
Deposit concrete as close as practicable to the final position in the
forms. Do not exceed a free vertical drop of one m 3 feet from the point
of discharge. Place concrete in one continuous operation from one end of
the structure towards the other or lifts for vertical construction.
Position grade stakes on 6 m 20 foot centers maximum for exterior slabs.

3.4.1 Vibration

**************************************************************************
NOTE: The requirement for vibrator spacing shall be
considered in the reinforcing steel design by the
engineer of record. ACI SP-66 requires that bar
bundling be done by the design engineer. It is very
important to provide space for placement and
consolidation of concrete.
**************************************************************************

Comply with the requirements of ACI 309R [and ASTM A934/A934M for
epoxy-coated bar] using vibrators with a minimum frequency of 9000
vibrations per minute (VPM). Use only high cycle or high frequency
vibrators. Motor-in-head 60 cycle vibrators may not be used. For walls
and deep beams, use a minimum of two vibrators with the first to melt down
the mixture and the second to thoroughly consolidate the mass. Provide a
spare vibrator at the casting site whenever concrete is placed. Place
concrete in 500 mm 18 inch maximum vertical lifts. Insert and withdraw
vibrators approximately 500 mm18 inches apart. Penetrate at least 200 mm 8
inches into the previously placed lift with the vibrator when more than one
lift is required. Extract the vibrator using a series of up and down
motions to drive the trapped air out of the concrete and from between the
concrete and the forms.

SECTION 03 31 29 Page 56
For slab construction use vibrating screeds designed to consolidate the
full depth of the concrete. Where beams and slabs intersect, use an
internal vibrator to consolidate the beam. Do not vibrate concrete placed
with anti-washout admixtures. Vibrators shall be equipped with rubber
vibrator heads.

3.4.2 Cold Weather

Comply with ACI 306R. Do not allow concrete temperature to decrease below
10 degrees C 50 degrees F. Obtain approval prior to placing concrete when
ambient temperature is below 4 degrees C 40 degrees F or when concrete is
likely to be subjected to freezing temperatures within 24 hours. Placement
of concrete shall be halted whenever the ambient temperature drops below 5
degrees C 40 degrees F. When the ambient temperature is less than 10
degrees C 50 degrees F the temperature of the concrete when placed shall be
not less than 10 degrees C 50 degrees F or more than 25 degrees C 75
degrees F. Heating of the mixing water or aggregates may be necessary to
regulate the concrete placing temperature. An accelerating admixture may be
used when the ambient temperature is below 10 degrees C 50 degrees F.
Covering and other means shall be provided for maintaining the concrete at
a temperature of at least 10 degrees C 50 degrees F for not less than 7
days after placing, and at a temperature above freezing for the remainder
of the curing period..

3.4.3 Hot Weather

Comply with ACI 305R. Maintain required concrete temperature using Figure
2.1.5, "Effect of Concrete Temperatures, Relative Humidity, and Wind
Velocity on the Rate of Evaporation of Surface Moisture From Concrete" in
ACI 305R to prevent the evaporation rate from exceeding one kg per square
meter 0.2 pound of water per square foot of exposed concrete per hour. If
necessary, cool ingredients before mixing or use other suitable means to
control concrete temperature and prevent rapid drying of newly placed
concrete. Shade the fresh concrete as soon as possible after placing.
Start curing when the surface of the fresh concrete is sufficiently hard to
permit curing without damage. If the evaporation rate exceeds 0.5 kg per
square meter 0.1 pound of water per square foot per hour, fog spray the
exposed concrete surfaces until active moist curing is applied.Provide
water hoses, pipes, spraying equipment, and water hauling equipment, where
job site is remote to water source, to maintain a moist concrete surface
throughout the curing period. Provide burlap cover or other suitable,
permeable material with fog spray or continuous wetting of the concrete
when weather conditions prevent the use of either liquid membrane curing
compound or impervious sheets. For vertical surfaces, protect forms from
direct sunlight and add water to top of structure once concrete is set.

3.4.4 Prevention of Plastic Shrinkage Cracking

During weather with low humidity, and particularly with high temperature
and appreciable wind, develop and institute measures to prevent plastic
shrinkage cracks from developing. If plastic shrinkage cracking occurs,
halt further placement of concrete until protective measures are in place
to prevent further cracking. Periods of high potential for plastic
shrinkage cracking can be anticipated by use of Figure 2.1.5 of ACI 305R.
In addition to the protective measures concrete placement shall be further
protected by erecting shades and windbreaks and by applying fog sprays of
water, the addition of monomolecular films, or wet covering. When such
water treatment is stopped, curing procedures shall be immediately
commenced. The methods and materials to remove or repair areas affected by

SECTION 03 31 29 Page 57
plastic shrinkage cracks shall be suggested by the Contractor, reviewed by
the agency's Subject Matter Expert in Concrete Materials, and approved by
the Contracting Officer. Cracks shall never be troweled over or filled with
cement slurry.

3.4.5 Mass Concrete

All mass concrete elements shall be placed per the requirements of the Mass
Concrete Temperature Control Plan.

3.4.6 Depositing Concrete Under Water

ACI 301M ACI 301 methods and equipment used shall prevent the washing of
the cement from the mixture, minimize the formation of laitance, prevent
the flow of water through the concrete before it has hardened, and minimize
disturbance to the previously placed concrete. Tremies, if used, shall be
watertight and sufficiently large to permit a free flow of concrete. Keep
the discharge end continuously submerged in fresh concrete. Keep the shaft
full of concrete to a level well above the water surface. Discharge and
spread the concrete by raising the tremie to maintain a uniform flow. Place
concrete without interruption until the top of the fresh concrete is at the
required height.

3.5 SURFACE FINISHES EXCEPT FLOOR, SLAB, AND PAVEMENT

3.5.1 Defects

Repair formed surfaces by removing minor honeycombs, pits greater than 600
square mm one square inch surface area or 6 mm 0.25 inch maximum depth, or
otherwise defective areas. Provide edges perpendicular to the surface and
patch with non-shrink grout. Patch tie holes and defects when the forms
are removed. Concrete with extensive honeycomb including exposed steel
reinforcement, cold joints, entrapped debris, separated aggregate, or other
defects which affect the serviceability or structural strength will be
rejected, unless correction of defects is approved. Obtain approval of
corrective action prior to repair. The surface of the concrete shall not
vary more than the allowable tolerances of ACI 347. Exposed surfaces shall
be uniform in appearance and finished to a smooth form finish unless
otherwise indicated.

3.5.2 Formed Surfaces

3.5.2.1 Tolerances

Comply with ACI 117 and as indicated.

3.5.2.2 As-Cast Rough Form

Provide for surfaces not exposed to public view. Patch holes and defects
and level abrupt irregularities. Remove or rub off fins and other
projections exceeding 6 mm 0.25 inch in height.

3.5.2.3 As-Cast Form

Provide form facing material producing a smooth, hard, uniform texture on


the concrete. Arrange facing material in an orderly and symmetrical manner
and keep seams to a practical minimum. Support forms as necessary to meet
required tolerances. Material with raised grain, torn surfaces, worn
edges, patches, dents, or other defects which will impair the texture of

SECTION 03 31 29 Page 58
the concrete surface shall not be used. Patch tie holes and defects and
completely remove fins.

3.6 FINISHES FOR HORIZONTAL CONCRETE SURFACES

3.6.1 Finish

Comply with ACI 301M ACI 301. Place, consolidate, and immediately strike
off concrete to obtain proper contour, grade, and elevation before
bleedwater appears. Permit concrete to attain a set sufficient for
floating and supporting the weight of the finisher and equipment. If
bleedwater is present prior to floating the surface, drag excess water off
or remove by absorption with porous materials. Do not use dry cement to
absorb bleedwater.

3.6.1.1 Scratched

Use for surfaces intended to receive bonded applied cementitious


applications. After the concrete has been placed, consolidated, struck
off, and leveled, the surface shall be roughened with stiff brushes of
rakes before final set.

3.6.1.2 Floated

Exterior slabs where not otherwise specified. After the concrete has been
placed, consolidated, struck off, and leveled, do not work the concrete
further, until ready for floating. Whether floating with a wood,
magnesium, or composite hand float, with a bladed power trowel equipped
with float shoes, or with a powered disc, float shall begin when the
surface has stiffened sufficiently to permit the operation.

3.6.1.3 Broomed

Perform a floated finish, then draw a broom or burlap belt across the
surface to produce a coarse scored texture. Permit surface to harden
sufficiently to retain the scoring or ridges. Broom transverse to traffic
or at right angles to the slope of the slab.

3.6.1.4 Pavement

Screed the concrete with a template advanced with a combined longitudinal


and crosswise motion. Maintain a slight surplus of concrete ahead of the
template. After screeding, float the concrete longitudinally. Use a
straightedge to check slope and flatness; correct and refloat as
necessary. Obtain final finish by a burlap drag. Drag a strip of clean,
wet burlap from 900 to 3000 mm wide and 600 mm longer 3 to 10 feet wide and
2 feet longer than the pavement width across the slab . Produce a fine,
granular, sandy textured surface without disfiguring marks. Round edges
and joints with an edger having a radius of 3 mm 1/8 inch.

3.6.1.5 Concrete Toppings Placement

Remove dirt, laitance, and loose aggregate by means of a stiff wire broom.
Keep the base wet for a period of 12 hours preceding the application of the
topping. Remove excess water prior to the topping placement. Do not allow
temperature differential between the completed base and the topping to
exceed 6 degrees C 10 degrees F at the time of placing. Place the topping
and finish as specified for pavement.

SECTION 03 31 29 Page 59
3.7 CURING AND PROTECTION

Comply with ACI 301M ACI 301 and ACI 308.1 unless otherwise specified.
Prevent concrete from drying by misting surface of concrete. Begin curing
immediately following final set. Avoid damage to concrete from vibration
created by blasting, pile driving, movement of equipment in the vicinity,
disturbance of formwork or protruding reinforcement, by rain or running
water, adverse weather conditions, and any other activity resulting in
ground vibrations. Protect concrete from injurious action by sun, rain,
flowing water, frost, mechanical injury, tire marks, and oil stains. Do
not allow concrete to dry out from time of placement until the expiration
of the specified curing period. Do not use membrane-forming compound on
surfaces where appearance would be objectionable, on any surface to be
painted, where coverings are to be bonded to the concrete, or on concrete
to which other concrete is to be bonded. If forms are removed prior to the
expiration of the curing period, provide another curing procedure specified
herein for the remaining portion of the curing period. Provide moist
curing for those areas receiving liquid chemical sealer-hardener or epoxy
coating.

**************************************************************************
NOTE: When the use of alkali-reactive aggregates is
permitted, add the following paragraph.
**************************************************************************

[Furnish ASTM C39/C39M test results to verify the anticipated rate of


strength development for the proposed concrete design mixture. Submit an
increased curing period and minimum time to strip formwork based upon the
reduced rate of strength development.

]3.7.1 Wet Curing

Wet cure marine concrete using ASTM C1602/C1602M compliant water for a
minimum of 7 days. Do not allow construction loads to exceed the
superimposed load which the structural member, with necessary supplemental
support, is capable of carrying in current condition safely and without
damage.

Leaving the forms in place for seven days is a suitable alternative to wet
curing.

3.7.1.1 Ponding or Immersion

Continually immerse the concrete throughout the seven-day curing period.


Water shall not be 11 degrees C 20 degrees F less than the temperature
ofthe concrete. For temperatures between 4 and 10 degrees C 40 and 50
degrees F, increase the curing period by 50 percent.

3.7.1.2 Fog Spraying or Sprinkling

Apply water uniformly and continuously throughout the curing period. For
temperatures between 4 and 10 degrees C 40 and 50 degrees F, increase the
curing period by 50 percent.

3.7.1.3 Pervious Sheeting

Completely cover surface and edges of the concrete with two thicknesses of
wet sheeting. Overlap sheeting 150 mm 6 inches over adjacent sheeting.
Sheeting shall be at least as long as the width of the surface to be

SECTION 03 31 29 Page 60
cured. During application, do not drag the sheeting over the finished
concrete or over sheeting already placed. Wet sheeting thoroughly and keep
continuously wet throughout the curing period.

3.7.1.4 Impervious Sheeting

Wet the entire exposed surface of the concrete thoroughly with a fine spray
of water and cover with impervious sheeting throughout the curing period.
Lay sheeting directly on the concrete surface and overlap edges 300 mm 12
inches minimum. Provide sheeting not less than 450 mm 18 inches wider than
the concrete surface to be cured. Secure edges and transverse laps to form
closed joints. Repair torn or damaged sheeting or provide new sheeting.
Cover or wrap columns, walls, and other vertical structural elements from
the top down with impervious sheeting; overlap and continuously tape
sheeting joints; and introduce sufficient water to soak the entire surface
prior to completely enclosing.

3.7.2 Liquid Membrane-Forming Curing Compound

**************************************************************************
NOTE: Stay in place forms and moist curing are the
preferred method for curing concrete. Use of a
liquid membrane-forming curing compound is only
permitted when approved by the Contracting Officer.
**************************************************************************

Seal or cover joint openings prior to application of curing compound.


Prevent curing compound from entering the joint. Apply in accordance with
the recommendations of the manufacturer immediately after any water sheen
which may develop after finishing has disappeared from the concrete
surface. Provide and maintain compound on the concrete surface throughout
the curing period. Do not use this method of curing where the use of
Figure 2 .1.5, "effect of Concrete Temperatures, Relative Humidity, and
Wind Velocity on the Rate of Evaporation of Surface Moisture From Concrete"
in ACI 305R indicates that hot weather conditions will cause an evaporation
rate exceeding one kg pf water per square meter per hour 0.2 pound of water
per square foot per hour.

3.7.2.1 Application

Mechanically agitate curing compound thoroughly during use. Use approved


power-spraying equipment to uniformly apply two coats of compound in a
continuous operation. The total coverage for the two coats shall be 5
square meters maximum per L 200 square feet maximum per gallon of undiluted
compound unless otherwise recommended by the manufacturer's written
instructions. The compound shall form a uniform, continuous, coherent film
that will not check, crack, or peel. Immediately apply an additional coat
of compound to areas where the film is defective. Respray concrete
surfaces subjected to rainfall within 3 hours after the curing compound
application.

3.7.2.2 Protection of Treated Surfaces

Prohibit pedestrian and vehicular traffic and other sources of abrasion at


least 72 hours after compound application. Maintain continuity of the
coating for the entire curing period and immediately repair any damage.

SECTION 03 31 29 Page 61
3.7.3 Liquid Chemical Sealer-Hardener

Apply the sealer-hardener in accordance with manufacturer's


recommendations. Seal or cover joints and openings in which joint sealant
is to be applied as required by the joint sealant manufacturer. The
sealer-hardener shall not be applied until the concrete has been moist
cured and has aged for a minimum of 30 days. Apply a minimum of two coats
of sealer-hardener.

3.7.4 Curing Periods

**************************************************************************
NOTE: Add the following if concrete will be
underwater: [Cure land-cast elements for a minimum
of 7 days prior to submerging].
**************************************************************************

Moist cure concrete using ASTM C1602/C1602M compliant water for a minimum
of 7 days. Continue additional curing for a total period of 21 days.
Begin curing immediately after placement. Protect concrete from premature
drying, excessively hot temperatures, and mechanical injury; and maintain
minimal moisture loss at a relatively constant temperature for the period
necessary for hydration of the cement and hardening of the concrete. The
materials and methods of curing shall be subject to approval by the
Contracting Officer.

3.8 FIELD QUALITY CONTROL

**************************************************************************
NOTE: Consider the size and complexity of job to
determine if all tests are required.
**************************************************************************

3.8.1 Fresh Concrete Properties

For each concrete mixture, the Contractor shall take samples in accordance
with ASTM C172/C172M, test and record the slump, and temperature. If the
slump deviates from the previous batch by more than 25.4 mm 1 inch, air
content shall also be determined. Adjustment of air content and/or slump
with chemical admixture is permitted provided the water to cementitious
material ratio is not exceeded.

3.8.1.1 Slump Tests

ASTM C143/C143M. Take concrete samples during concrete placement. The


maximum slump may be increased as specified with the addition of an
approved high range water reducing (HRWR) admixture provided that the
water-cementitious ratio is not exceeded. Perform tests at commencement of
concrete placement, when test cylinders are made, and for each batch
(minimum) or every 40 cubic meters 50 cubic yards (maximum) of concrete.
If concrete does not pass slump test, adjust using a HRWR and test every
concrete batch until two (2) consecutive batches meet slump without
adjustment.

3.8.1.2 Temperature Tests

a. Test the concrete delivered and the concrete in the forms. Perform
tests in hot or cold weather conditions below 10 degrees C and above 27
degrees C below 50 degrees F and above 80 degrees F for each batch

SECTION 03 31 29 Page 62
(minimum) or every 40 cubic meters 50 cubic yards (maximum) of
concrete, until the specified temperature is obtained, and whenever
test cylinders and slump tests are made.

b. Determine temperature of each concrete sample in accordance with


ASTM C1064/C1064M. Temperatures must comply with the Concrete
Temperature Control Plans.

3.8.1.3 Air Content Tests

ASTM C231/C231M or ASTM C173/C173M. Perform tests at commencement of


concrete placement each day, when test cylinders are made, and if slump
test varies by more than 25.4 mm 1 inch from previous results or concrete
does not pass slump test.

3.8.1.4 Unit Weight Test

ASTM C138/C138M. Take concrete samples during concrete placement. Perform


tests at commencement of concrete placement, when test cylinders are made,
and for each batch (minimum) or every 38.2 cubic meters 50 cubic yards
(maximum) of concrete.

3.8.2 Hardened Concrete Properties

**************************************************************************
NOTE: The Engineer of Record must specify the
frequency of testing during the construction phase.
Sufficient testing must be done to maintain
confidence that the concrete, as delivered and
placed, remains consistent. For example: sample and
test every 75 cubic meters 100 cubic yards for the
first 382 cubic meters 500 cubic yards, then every
382 cubic meters 500 cubic yards once confidence is
established in uniformity. However, this is only a
guideline, and the owner and Engineer of Record
should agree on the frequency of sampling as best
suits the particulars of each project and budget.

For example, a sampling interval for a new pier may


be as follows:

o During the first week of casting piles


o During the second week of casing piles
o Midway through the casting of all piles
o During the final week of casting piles
o At the first pile cap and every tenth bent
thereafter
o During the two first concrete deck pours
o During the final concrete deck pour
**************************************************************************

Sample and test each lot at [75] cubic meters [100] cubic yards for the
first [382] cubic meters [500] cubic yards, then every [382] cubic meters
[500] cubic yards thereafter.

Cast and cure specimens in accordance with ASTM C172/C172M, ASTM C31/C31M,
and applicable requirements of ACI 305R and ACI 306R.

For each lot, record the date and time sampled, the batch ticket code,

SECTION 03 31 29 Page 63
cylinder ID code the location of placement, total volume of concrete
represented by the sample, and fresh concrete properties; ASTM C143/C143M
for slump or ASTM C1611/C1611M for slump flow and visual stability index
(VSI), ASTM C231/C231M for air content, ASTM C1064/C1064M for temperature,
and ASTM C138/C138M unit weight.

For each lot sample, cast twelve 150 by 300 mm 6 by 12 inch cylinder
specimens for strength and seven 100 by 200 mm 4 by 8 inch cylinder
specimens for transport property testing. Special handling will be
necessary for shipments of transport property specimens. These cylinders
shall be wrapped completely with slightly damped paper towels with spring
water only. The wrapped cylinders shall be placed in either a vacuum
package or double layers of sealed plastic bags. Package cylinders to
prevent damage and ship priority mail to the approved testing laboratory.

In the event the results of cylinder tests fail to satisfy transport


properties, then an additional pair of specimens shall be tested. In the
event quality acceptance test results and retest results fail to meet the
quality acceptance criteria, the entire lot shall be considered
non-conforming material, refer to the subpart entitled "REPAIR,
REHABILITATION and REMOVAL".

For every [382.3 cubic meters] [500 cubic yards] perform a petrographic
examination in accordance with ASTM C856.

3.8.2.1 Compressive Strength Tests

**************************************************************************
NOTE: When the same mix design is used for multiple
elements such as slabs, beams, and walls, the design
element type may be specified in addition to the mix
design to better identify deficient concrete.
**************************************************************************

ACI 214R tests for strength - conduct strength tests of concrete during
construction in accordance with the following procedures:

a. Test cylinders in accordance with ASTM C39/C39M. Test three cylinders


at 3 days, three cylinders at 7 days, and three cylinders at the age
when the compressive strength requirement was specified. Hold the
remaining three cylinders in storage. If one specimen in a test shows
evidence of improper sampling, molding or testing, discard the specimen
and consider the strength of the remaining cylinder to be the test
result. If more than one specimen shows excess defects, the
Contracting Officer may allow the entire test to be discarded. Test
results shall not exceed the specified compressive strength by more
than 20 percent for the age specified.

b. If the average strength test results are less than the specified
strength (f'c) extract three core samples from the structure in
accordance with ASTM C42/C42M, from the area that correlates to the low
test results. These extracted cores shall not contain steel
reinforcing. Repair core holes with non-shrink grout. Match color and
finish of adjacent concrete. For concrete not meeting strength
criteria the Contractor shall prepare a remediation strategy for the
review by the Contracting Officer.

c. Strength test reports shall be provided within 7 days of test


completion.

SECTION 03 31 29 Page 64
3.8.2.2 Transport Property Tests

Test cylinder concrete for porosity and ion diffusion coefficient at 28


days. Calculate the Deff with the determined ionic diffusion coefficient (D
oh ) and volume of permeable voids (porosity). Concrete representative of
the tested concrete with Deff values greater than the quality acceptance
values determined in the Concrete Qualification Testing Requirements
program, will require retesting using spare samples. If the retest exceeds
the quality acceptance limit, this shall be grounds to stop concrete
placement and to review quality control issues.

The Contractor shall monitor the transport properties throughout the


duration of the project and prepare an as-built report documenting the
transport property test results. The report shall include a chart or table
of the effective diffusion coefficient (Deff) versus the specified
effective diffusion coefficient (Dspec) over the duration of the placement
for each concrete, indicate the concrete placed outside of the tolerance
limits, describe any mitigation measures taken to ensure the service life
specified, and estimate the service life of the various concretes, as placed.

[3.8.2.3 Chloride Ion Concentration

Comply with ACI 318M ACI 318. Determine water soluble chloride ion
concentration. Perform test once for each mix design. The limits for
average chloride ion content are provided in Table 3.

]3.8.2.4 Anti-Washout Admixture

Comply with COE CRD-C 61. Determine cumulative mass loss. Perform test
once for each 267.6 cubic meters 350 cubic yards of underwater concrete.

3.8.2.5 Non-Destructive Tests

Use of a rebound hammer to obtain data on the strength of the concrete


surface shall be in accordance with ASTM C805/C805M. Test results from the
rebound hammer and other non-destructive testing may be helpful in
selecting areas to extract concrete cores for destructive testing.

3.8.3 Core Samples and Compressive Strength Testing

Obtain and test cores in accordance with ASTM C42/C42M.

If concrete in the structure is dry under service conditions, air dry cores
(temperature 16 to 27 degrees C 60 to 80 degrees F, relative humidity less
than 60 percent) for 7 days before testing and test dry. Otherwise, test
the cores, after moisture conditioning, in accordance with ASTM C42/C42M.

Acceptance criteria for cylinder compressive strength are provided in


subpart entitled "Acceptance of Concrete Strength".

Take at least three representative cores from each member or area of


concrete in place that is considered potentially strength deficient. Impair
the strength of the structure as little as possible. If, before testing,
extracted cores show evidence of having been damaged subsequent to or
during removal from the structure, take replacement cores.

Fill core holes with low slump concrete or mortar of a strength equal to or
greater than the original concrete.

SECTION 03 31 29 Page 65
The Contracting Officer will evaluate and validate core tests in accordance
with the specified procedures.

3.8.4 Acceptance of Concrete Strength

3.8.4.1 Standard Molded and Cured Strength Specimens

The acceptance of concrete strengths shall be based on averages of results


from three consecutive compressive strength tests. When the averages of
all sets of three consecutive compressive strength test results are between
1.0 and 1.2 times the field test strength (fcr), and no individual strength
test falls below fcr by more than 3.45 MPa 500 psi, the strength of the
concrete is satisfactory. These criteria also apply when accelerated
strength testing is specified unless another basis for acceptance is
specified.

3.8.4.2 Non-Destructive Tests

Non-destructive tests may be used when permitted to evaluate concrete where


standard molded and cured cylinders have yielded results not meeting the
criteria.

3.8.4.3 Extracted Core Tests

When the average compressive strengths of the representative cores are


between 0.85 fcr and 1.2 fcr and if no single core is less than 0.75 fcr,
the strength of concrete is satisfactory.

3.8.5 Inspection

ACI 311.4R. Inspect concrete placed under water with qualified divers.

3.9 REPAIR, REHABILITATION AND REMOVAL

Before the Owner accepts the structure and final payment is made the
Contractor shall inspect the structure for cracks, damage and substandard
concrete placements that may adversely affect the service life of the
structure. A report documenting these defects shall be prepared which
includes recommendations for repair, removal and/or remediation which, will
be reviewed by the agency's Subject Matter Expert in Concrete Materials and
submitted to the Contracting Officer for approval before any corrective
work is accomplished.

3.9.1 Crack Repair

Prior to final acceptance, all cracks in excess of 0.50 mm 0.02 inches wide
shall be documented and repaired. The proposed method and materials to
repair the cracks shall be submitted to the Contracting Officer for
approval. The proposal shall address the amount of movement expected in the
crack due to temperature changes and loading.

3.9.2 Repair of Weak Surfaces

Weak surfaces are defined as mortar-rich, rain-damaged, uncured, or


containing exposed voids or deleterious materials. Concrete surfaces with
weak surfaces less than 6 mm 1/4 inch thick shall be diamond ground to
remove the weak surface. Surfaces containing weak surfaces greater than 6 mm
1/4 inch thick shall be removed and replaced or mitigated in a manner

SECTION 03 31 29 Page 66
acceptable to the Contracting Officer.

3.9.3 Failure of Quality Assurance Test Results

**************************************************************************
NOTE: Test results accomplished on concrete samples
during concrete production that fall short of the
acceptance criteria alert the Contractor to
something in the production and placement process
that has drifted out of calibration or that an error
has been made. The goal is to track down the
problem and correct it as quickly as possible.
Unless the concrete producer makes a large error in
batching or in placing, the chance that hardened
concrete needs to be removed is remote. Removal and
replacement is a last resort.

For those areas adversely affected by substandard


concrete new STADIUM® simulations can be helpful to
evaluate the effectiveness of the proposed
remediation strategies.
**************************************************************************

Proposed mitigation efforts by the Contractor to restore the service life


shall be reviewed by the agency's Subject Matter Expert in Concrete
Materials and approved by the Contracting Officer prior to proceeding.

-- End of Section --

SECTION 03 31 29 Page 67

You might also like