Hse Ext. Audit Report Godrej - Nature + MCC 13.08.2021
Hse Ext. Audit Report Godrej - Nature + MCC 13.08.2021
Hse Ext. Audit Report Godrej - Nature + MCC 13.08.2021
AUDIT REPORT
OF
Modern Construction Co. ( Delhi )
Site : Godrej – Nature +
Sector – 33 , Sohna,
Gurugram , Haryana - 122022.
Conducted on 13.08.2021.
BY
By Y R CHAWLA, BE (MECHANICAL),PDIS
HSE Consultant
LEAD AUDITOR – ISO – 45001 – 2018 & ISO – 14001 – 2015.
Member of the Institution of Engineers
Ex L & T Employee with 20 years of working
Ex Competent Person approved by CIF Orissa , Haryana and
Rajasthan U/S 28,29 & 31.
Ex Bam International , Holland employee for two years.
Empanelled with TPL for their vendors assessment since
Sept’2018.
Y.R.Chawla
Page 1 of 12 HSE Report
Audit Date 13.08.2021
Introduction
HSE Audit was carried out at M/S Modern Construction Co. ( Delhi ) at their construction site at
Godrej- Nature +, Sector 33 , Sohna , Gurugram - 122022 , Haryana on 13.08.2021. The company
is carrying out Civil structure work in Towers G,H,J, E , T 3 , T 4 , STP and Non Tower Area on
behalf of M/S Godrej Properties Limited.
At the time of HSE Audit, it was observed that the structure work is complete of Towers E,G,H,J,
Tower 3 and 2 floors remaining of Tower 4. About 6 % Structure work of Non Tower area ( 1200
sqm out of 20,000 sqm) is complete. 10 % STP work is complete.
The contractor has been working since 06.04.2018.
Opening & Closing Meetings were held with the following staff :
1. Mr. Naval Singh Yadav - Project In charge - MCC
2. “ Pawan Kumar Singh – HSE Officer – GPL
3. “ Anjani Kumar Singh - HSE Manager - MCC
4. “ Sanjeev Kumar – HSE Officer - MCC
1. Assess the gaps between provision of HSE Plan and actual implementation at field level for all
construction activities.
2. Assess the awareness of staff and the work force regarding the provisions of the same.
3. Give recommendation and suggestions for effective implementation.
Y R Chawla
Page 2 of 12 HSE Report
Audit Date 13.08.2021
Overall Conclusion:
1. All documents like Induction , TBT , Training , Work Permits , Check lists , Emergency
Preparedness including Mock drills etc are up to date.
2. MCC should initiate the process for ISO 45001 – 2018 certification for the site and its
implementation afterwards. HSE Staff needs to be trained accordingly.
3. No major Accident took place ever since the project started.
4. I Cards were possessed by the work force.
5. From the records it is apparent that Induction ,tool box talks and training are being organised
on regular basis .
6. Poor protocol was shown by the work force by not wearing Nose mask in the prevailing
Corona pandemic.
7. Nearest hospital with whom the company is tied up is Ram Rati Hospital, Sohna at about 3
Km from the site.
8. Scaffolds are perfectly erected along the periphery of the Towers.
9. Majority of the Work Force and Staff were observed with mandatory PPE.
10. Safety rules in Non Tower Area are not being followed for working at height.
11. Last Mock Drill was carried out on 29.06.2021 in Labour camp on Covid 19 suspects.
12. House – Keeping needs improvement. A lot of debris accumulated at the site needs
immediate disposal.
13. Majority of the Peripheral Safety Nets fixed at about 5m height of all towers need refixing.
14. Last SCM was conducted on 29.07.2021
15. Last Motivation Program was conducted on 22.07.2021 in presence of the client where in
total 12 persons were awarded.
16. National Safety Day , Environment day , Road Safety etc are being celebrated.
17. LOTO is followed as and when required.
18. HSE Statistics Board is not displayed.
Y R Chawla
Page 3 of 12 HSE Report
Audit Date 13.08.2021
3. House – Keeping is not up to the mark. Team is to be formed for House Keeping.
4. Debris accumulation is on the increase and it needs immediate disposal.
5. Use of Hand gloves is to be improved.
6. Workmen working at low heights as in Non Tower Area are to use Safety Belts. Surrounding area
should be cleaned before starting the height work.
7. Peripheral Primary Safety nets are to maintained as far as possible.
8. Grass , weeds etc grown everywhere need regular cutting.
Site Specific Observations to show the prevailing practices at the site and
Recommendations:
A. GOOD PRACTICES :
Y R Chawla
Page 4 of 12 HSE Report
Audit Date 13.08.2021
Patient Bed is available.
2
Audio video system is
available for imparting
Induction and other
trainings.
Y R Chawla
Page 5 of 12 HSE Report
Audit Date 13.08.2021
3. PPE Selection Matrix is
displayed.
4 No reportable accidents took place since the start of the project Congratulations !!!!!
i.e. 06.04.’2018. Minor/First Aid injuries
should also be
investigated and
analysed.
Y R Chawla
Page 6 of 12 HSE Report
Audit Date 13.08.2021
5
.
NO GO zone provided at
the periphery of the
tower.
Such NO GO Zones
should be provided and
maintained around all
the towers to protect
the persons from falling
objects.
Y R Chawla
Page 7 of 12 HSE Report
Audit Date 13.08.2021
6 Properly erected and
anchored scaffold.
Y R Chawla
Page 8 of 12 HSE Report
Audit Date 13.08.2021
Y R Chawla
Page 9 of 12 HSE Report
Audit Date 13.08.2021
7 Debris chutes have
been provided to ease
debris disposal from the
towers.
Y R Chawla
Page 10 of 12 HSE Report
Audit Date 13.08.2021
Y R Chawla
Page 11 of 12 HSE Report
Audit Date 13.08.2021
8.
Few areas observed
with good House -
keeping. To be
continued in other areas
also.
Y R Chawla
Page 12 of 12 HSE Report
Audit Date 13.08.2021
9.
Floor openings found
covered.
To ensure all floor
openings are protected
like this.
Y R Chawla
Page 13 of 12 HSE Report
Audit Date 13.08.2021
Proper hand rails
provided to the
staircase.
Y R Chawla
Page 14 of 12 HSE Report
Audit Date 13.08.2021
10.
Three portable toilets
have been provided for
the workmen at
different locations of
the site.
Sprinkling of bleaching
powder in and around
of the toilets is not
visible.
Y R Chawla
Page 15 of 12 HSE Report
Audit Date 13.08.2021
11. Primary safety nets
have been provided at
5m height. It should be
provided and
maintained in other
areas also.
Y R Chawla
Page 16 of 12 HSE Report
Audit Date 13.08.2021
B. AREAS OF CONCERN :
It needs thorough
investigation.
Y R Chawla
Page 17 of 12 HSE Report
Audit Date 13.08.2021
2. Poor House –
Keeping was
observed at a
number of places.
House Keeping is to
be maintained on
regular basis.
Y R Chawla
Page 18 of 12 HSE Report
Audit Date 13.08.2021
Nearby areas of the
builders hoist should
always be clean.
Y R Chawla
Page 19 of 12 HSE Report
Audit Date 13.08.2021
Needs cleaning.
Needs cleaning.
Y R Chawla
Page 20 of 12 HSE Report
Audit Date 13.08.2021
Weeds need cutting.
Needs proper
stacking and
cleaning.
Y R Chawla
Page 21 of 12 HSE Report
Audit Date 13.08.2021
Needs proper
stacking.
Needs proper
stacking and
cleaning.
Y R Chawla
Page 22 of 12 HSE Report
Audit Date 13.08.2021
Packaging materials
left by other agency
may cause fire.
Needs immediate
removal
4. Mannequin is to be
maintained.
R. Jacket meant for
workmen should be
used. Full sleeve shirt
in place of T shirt
should be
encouraged at the
site as full sleeve
shirt gives maximum
protection at the site
especially from
Sun,Mosquitoes and
other chemical
effects of cement etc.
Y R Chawla
Page 23 of 12 HSE Report
Audit Date 13.08.2021
5. Hand Gloves are not
being used.
Social distancing
should always be
maintained.
Y R Chawla
Page 24 of 12 HSE Report
Audit Date 13.08.2021
7. Loosely kept grill for
lift shaft may lead to
accident
8. Water accumulation
near entry to Tower
4.
No clear access.
Y R Chawla
Page 25 of 12 HSE Report
Audit Date 13.08.2021
9. Poorly maintained
access to tower.
Weed cutting
required. Shade nets
are to be fixed on the
sides.
Number of the Tower
should be mentioned.
FEs , HSE Posters ,
Emergency nos. etc
may be displayed.
Y R Chawla
Page 26 of 12 HSE Report
Audit Date 13.08.2021
10. No edge protection of
the roof of non-tower
area.
Y R Chawla
Page 27 of 12 HSE Report
Audit Date 13.08.2021
Instructions are not
properly displayed.
Y R Chawla
Page 28 of 12 HSE Report
Audit Date 13.08.2021
13. Such unsafe
conditions should not
be allowed at the
site.
Y R Chawla
Page 29 of 12 HSE Report
Audit Date 13.08.2021
15 Safety Belts , Nose
masks and Hand
gloves are not being
used.
Y R Chawla
Page 30 of 12 HSE Report
Audit Date 13.08.2021
16.
Such protruding
rebars may cause trip
hazards.
17.
After plaster and tile
work , left the place
in unsafe condition.
Y R Chawla
Page 31 of 12 HSE Report
Audit Date 13.08.2021
18. Too much fire load
and no FE kept.
19.
Weed grown in front
of DG surrounding
needs cutting.
Y R Chawla
Page 32 of 12 HSE Report
Audit Date 13.08.2021
Needs House
Keeping.
Needs House
Keeping and proper
cable management.
Y R Chawla
Page 33 of 12 HSE Report
Audit Date 13.08.2021
20.
Refixing of peripheral
nets is required.
Y R Chawla
Page 34 of 12 HSE Report
Audit Date 13.08.2021
Y R Chawla
Page 35 of 12 HSE Report
Audit Date 13.08.2021
21. Since the labour
camp is being shifted
from its earlier place
, it is expected that
proper cleanliness
and hygiene
conditions will be
maintained once
shifted to new place.
Following HSE Documents verified and found being implemented and recorded.
Y R Chawla
Page 36 of 12 HSE Report
Audit Date 13.08.2021
PTW – Hot Work PTW – Height Work
Y R Chawla
Page 37 of 12 HSE Report
Audit Date 13.08.2021
Attendance sheet for training on Electrical Safety Medical Certificate
during monsoon.
Y R Chawla
Page 38 of 12 HSE Report
Audit Date 13.08.2021
Medical Certificate Details of medical certificate
Y R Chawla
Page 39 of 12 HSE Report
Audit Date 13.08.2021
MoM of SCM Attendance sheet for SCM
Y R Chawla
Page 40 of 12 HSE Report
Audit Date 13.08.2021
TBT Calendar Display of precautions against Covid 19.
Y R Chawla
Page 41 of 12 HSE Report
Audit Date 13.08.2021
DATE : 13.08.2021 Y R CHAWLA
HSE CONSULTANT
Y R Chawla
Page 42 of 12 HSE Report
Audit Date 13.08.2021