Razor Wire Fence Method - Statement Rev01
Razor Wire Fence Method - Statement Rev01
Razor Wire Fence Method - Statement Rev01
Documents Attached
1 Method Statement
2 QCP/ITP
3 Risk Assessment
Signature Date
Approved by:
Project
Manager
JAY AND BEE
Approved by: Project
Manager
Sibanye Stillwaters
1
INTRODUCTION
THE PURPOSE OF THIS DOCUMENT IS TO OUT LINE ALL THE WORK THAT JAY
AND BEE CONSTRUCTION W I L L BE DOING DURING THE TD6 AND TD8
TAILINGS DAM FENCING PROJECT. THIS WILL INCUDE ALL THE WORK
PROCEDURES AND INSTRUCTION THAT ARE MADE BY THE SHE AND SIBANYE
STILL WATER
SCOPE
1Site Establishment
Site Establishment will be executed as per approved method statement.
2Material Delivery
All material delivered to site will be delivered to Jay and Bee Construction site lay down area. All
material will be inspected and approved by client before installation as per quality control
procedures.
The contractor shall strip the topsoil which includes the top 150mm of soil (or
to the depth of the bedrock where the soil is shallower than 150mm) and root
material of cleared vegetation, for subsequent use during rehabilitation.
Topsoil shall be stripped from all areas of the working area where topsoil will
be impacted by construction activities including areas for temporary facilities,
as directed by the Engineer.
7.Earthworks
Clearing areas of all grass, weeds, shrubs, debris, including grubbing up all
roots and cart away all vegetation and debris to indicated spoil areas.
Once the clearing is completed the setting out will be carried out by the
qualified Surveyor, according to the coordinates on the drawings prior to any
excavation commences.
Tipper trucks will be used to transport the topsoil to the area of the stockpile.
Tipper truck
Roller
Grader
Excavator
TLB
Generator
Front End Loader
Water Tank
Shovels, Picks, jackhammer, Gwala, Grinder and Drill Machine
A 450mm and 750mm diameter razor wire will be inspected at the lay down
area then transported to site by a LDV with a trailer.
All employees will be doing the preparation by hand and full PPE will be
always worn
All quality control will be executed by Jay and Bee Construction in conjunction
with prescribed specifications of Sibanye.
A Quality control officer of Jay and Bee Construction will liaise with Sibanye
quality department to ensure that all requirements are met.
11.Poles installation:
12.Fence installation
A minimum of Five equally spaced strands of high tensile wire, with the
lowest strand being at ground level and the highest being at 2.4m
Razor wire fencing of 2.4m in height, secured to the wire strands and
posts, with binding wire.
Topped with overhangs secured to each post and intermediate with two
bolts.
Barbed wire to be attached to overhangs.
Trench will be backfilled and compacted after installation of welded
mesh fence, using the TLB or by hand and a walk behind roller.
13.Gate installation
The gates will be installed as per client’s specification. Gates shall be 2.4 m in
height and will comprise of the following:
14.Straining of wires
1
15.Cutting of Razor wire
Razor wire will be cut using a portable grinder or pliers used by somebody
with experience and have been inducted
All waste generated from cutting the razor w i r e shall be disposed of at
demarcated areas as indicated by client.
All cutting equipment compiled with OHS act in terms of safeguarding.
Safety goggles shall be always used to protect employees’ eyes from
sparks or hazardous material entering eyes.
This method statement will apply to the clearing, excavating, compacting and
loading of material, 2.4 welded mesh fence, waste management, casting
concrete, plant equipment and PPE to be worn on site when carrying out this
tasks/works by Jay and Bee Construction.
16.3Using of a ladder
We will ensure that persons at work receive prompt first aid treatment
in case of injuries or emergency
We will provide first aid box or boxes at or near the workplace which
shall be available and accessible
No persons are allowed to carry on with their task in case an
emergency siren or alarm sound
Report any incident/accident immediately to supervisor or safety
representative on site
Every minor injury shall be treated on site by the competent first aider
as OHS act
All person working on site will undergo induction, safety awareness
training and environmental training with regarding emergency
procedures, fire, or electrical shut down
All cleared vegetation will either be mulched and mixed into a topsoil or
disposed at an approved disposal site
All disposal of vegetation by burying or burning is prohibited
Topsoil will be stripped which will include the top 150mm of the soil, for
subsequent use during rehabilitation and re-vegetation.
17.2Noise
The contractor does envisage that the project will generate excessive noise
(more than 85 dB), but instances whereby the equipment such drilling machine
will be used, the workers will be advised to wear ear plugs.
17.3Dust
17.4Emergency preparedness
In the event of a spill, the source of the spillage shall be isolated, the
spillage will be contained. The area where the pillage incident has occurred
shall be cordoned off and secured. Jay and Bee Construction shall always
maintain spill kits on the site and shall ensure that there is always
adequate supply of absorbent material available in the spill kit.
17.7Ablution facilities
Jay and Bee Construction shall provide adequate ablution facilities for
workers in the construction camp. Acts of excretion and urination shall be
strictly prohibited other than at the facilities provided
I. Toilets shall be located within 100 m from any points of work
but not closer than 50 meters to any watercourse or water
body,
IV. No spillage shall occur when the toilets are cleaned or emptied,
and the contents shall be properly removed from site.
The management of solid waste at the working area shall be strictly controlled
and monitored; the quantities of waste generated shall be minimized as
wheelie bins will be made available. Littering will be avoided, there will be no
burying, dumping and burning of waste material shall occur. Bins shall never
be allowed to overflow and shall be emptied twice in a week. All solid waste
will be collected and be disposed off-site at an approved landfill site.
17.9Accommodation of traffic
Jay and Bee Construction shall always ensure vehicle traffic safety and shall
implement safety measures. Fence and Gate shall control the movement of
all the vehicles and equipment including of the suppliers so that they
remain on designated routes. On gravel road on the site and within 500 m
of the site, the vehicles of Fence and Gate and the suppliers shall not
exceed a speed of 40 km/h.
17.11Prevention of fire
Jay and Bee Construction shall take adequate precautions to ensure that the
fire hazard on and near the site is reduced to a minimum. Smoking shall
not be permitted on site; it will only be allowed in areas designated as smoking
area.
17.12Installation