Dredging Management Plan
Dredging Management Plan
Dredging Management Plan
Revision status
Revision Number: Rev. 2.0
Revision Date: 20-Jun-2018
Approval Status: Issued for Approval
Prepared By: Irena Doets Role: Environmental Engineer
Reviewed By: Paul Bartley Role: Project Manager
Interdisciplinary Check: Chris Tombolato Role: Tender Manager
Approved By: Pieter Jan Stuiver Role: Project Manager
Change log
Revision Section Change
Rev. 0.1 All Issued for internal review
Rev. 0.2 All Revision after internal (BKA) review
Rev. 1.0 All Revision after external (LPC) review, issued for Approval of Consent
Authority
Rev 2.0 Cover Page Added “Environment Canterbury Certified’’
DOCUMENT PREPARATION
This document has been jointly prepared by Boskalis and Lyttelton Port Company. This Dredge
Management Plan is required by Condition 4 of the resource consent (CRC 172455/CRC172522 and
describes Boskalis’ dredging plant, work method, and management systems used for the delivery of the
Lyttelton Port of Christchurch Channel Deepening Project Stage 1.
This document forms part of the Boskalis Way of Working, the integrated quality management system
applicable to all operations in Boskalis. The Boskalis Way of Working is structured around four Phases
as pictured below. This Dredging Management Plan is typically prepared in the PLAN Phase, where the
main implementation is taking place in the EXECUTION Phase.
More detailed information about the Boskalis Way of Working can be found in the Group Manual and the
User Guide. A dedicated website with all supporting materials is available at wow.boskalis.com
TABLE OF CONTENTS
1. INTRODUCTION 6
1.1. General 6
1.2. Purpose 7
1.3. Scope of Document 7
2. SCOPE OF WORK 8
2.1. Project Overview 8
2.2. The Works 9
2.2.1. Dredging Limits and Depths 9
2.2.2. Batters 9
2.3. Tolerances 9
2.4. Dredging Quantities 10
3. WORK METHOD 11
3.1. Mobilisation and Preparation 11
3.2. Pre-Dredge Survey 11
3.3. Selection of Work Method 11
3.4. Equipment 11
3.4.1. Primary Dredging Equipment 11
3.4.2. TSHD overflow with ‘Green valve’ 13
3.4.3. Supporting Dredging Equipment 13
3.5. Dredging Method 13
3.5.1. TSHD dredging works 13
3.5.2. Channel Widening 15
3.5.3. Sweeping method 15
3.6. Dredge Spoil Method 16
3.7. Regulations for Dredging Equipment 17
3.8. Plant Operating Hours 17
3.9. Demobilisation 17
4. EQUIPMENT MAINTENANCE 17
6. ENVIRONMENTAL MANAGEMENT 19
6.1. Contractor’s corporate statement with respect to environment 19
6.2. Adaptive Management 20
6.3. Outdoor lighting 21
6.4. Environmental training 21
6.5. Waste Management & Hazardous Substances 21
6.5.1. Hazardous waste 22
6.5.2. Waste Management Measures 22
9. ATTACHMENTS 29
9.1. Specifications TSHD Oranje 29
9.2. Specifications TSHD Fairway 31
9.3. Specifications Sweeping Vessel 33
9.4. Specifications Backhoe Dredge 35
9.5. Specifications Crew/Survey Vessel 38
1. INTRODUCTION
1.1. General
Lyttelton Port of Christchurch (the Port) is located on Banks Peninsula on the east coast of the South
Island (Figure 1.1). It is the largest port in the South Island and the third largest in New Zealand.
Lyttelton Port Company is the operator of the Port and is currently 100% owned by the Christchurch City
Council through its investment arm, Christchurch City Holding Limited.
The Port is currently New Zealand’s third largest deep-water port, and the largest port in the South
Island, and provides a vital link to international trade routes and a key role in the global transport
network. The Port Lyttelton Plan (PLP) has been developed and is the first step in developing a 30-year
vision for the Port.
As a result of the Canterbury earthquakes in 2010 and 2011, the Port sustained significant and
widespread damage to infrastructure. While these events have had a significant impact on the LPC’s
ability to meet existing service demands in relation to throughput, productivity and customer service it is
now the driving force behind the redevelopment program.
The current access channel does not have the draught to cope with the international trend for increasing
vessel sizes. Deepening and widening the channel will allow the Port to keep up with international trade
demand which is a key facilitator of the regional and national economy.
The existing channel is 180m wide, 11.9m deep and approximately 6.5km in length. Stage 1 of the
Channel Deepening Project (CDP) will see the channel widened to 200m, increased in length to
approximately 9km and increased in depth by approximately 2m (Figure 1.2). The swing basin is also
being deepened and enlarged increasing the width from approximately 450m to 615m. The dredged
material will be discharged at a designated dredge spoil ground, located approximately 5 nautical miles
offshore of the Harbour Heads.
1.2. Purpose
The purpose of this document is to describe Boskalis’ dredging plant, work method, and management
systems used for the delivery of the Lyttelton Port of Christchurch Channel Deepening Project Stage 1.
This Dredging Management Plan (DMP), together with the Environmental Monitoring and Management
Plan (EMMP) [14], the Marine Mammal Management Plan (MMMP) [15] and the Biosecurity
Management Plan (BMP) [16], specify how Dredging practices and procedures will ensure that any
actual or potential adverse effects on the marine receiving environment are avoided or otherwise
mitigated to the greatest extent practicable.
The content and scope of the DMP has been guided by Boskalis’s normal best practise dredge
management and the scope and requirements for the DMP as set out in condition 4.4 of Resource
Consent CRC 172455 and CRC 172522.
This DMP has been prepared by Boskalis, with input from LPC. The Boskalis personnel who prepared
and reviewed this DMP have significant experience in both the operation of the proposed dredge
equipment and the management of environmental effects of dredging.
2. SCOPE OF WORK
The existing channel is 180m wide, 12.2m deep and approximately 6.5km in length. Stage 1 of the
Channel Deepening Project will see the channel widened to 200m, increased in length to approximately
9km and an increase in depth by approximately 2m. The swing basin is also being deepened and
enlarged which will increase the width from approximately 450m to 615m. All dredged material is to be
transported to and disposed of within the designated dredge spoil ground.
Areas to be dredged and the applicable design depths required are shown in Table 2.1, Figure 2.1 and
Figure 2.2.
Dredge areas
Description Area Design Depth (m below CD)
Swing Basin A -13.3 (note Cruise Berth Pocket is -11.5)
Te Awaparahi Bay B -13.3
Inner Channel Areas C to G -13.6 to -15.0
Outer Channel Areas H to J -14.5 to -14.0
2.2.2. Batters
Batters shall be constructed to the slopes as detailed on the Drawings. If during the execution of the
Works, material is encountered which requires batter slopes flatter or steeper than specified, the
Employer may issue a written direction to carry out the dredging to other slopes. Batters shall be formed
as follows:
Batter Slope
Area Batter Slope
A 1:4 to 1:5
B to D 1:3
E to J 1:2
2.3. Tolerances
The Contractor shall achieve the required design depth and profile at all locations. The Contractor shall
dredge all areas so as to leave the seabed surface as level as possible.
Maximum permitted tolerances to achieve design depth for the different dredge areas are given in Table
2.3 and Figure 2.3.
Table 2.3 Dredge Tolerances
Dredge Tolerances
Dimensions Location Tolerance To Dredge Design
Deeper: 0.5 m
Vertical All areas
Shallower: 0.0 m
Plus: 5.0 m (i.e. outside design line)
Horizontal All areas
Minus: 0m
Design Slope
0.5m Vertical OD
Dredge Volumes
Dredge Area Net Volume (m3) Gross Volume (m3)
A 1,812,500 2,277,160
B 237,900 354,456
C 294,400 393,240
D 446,000 583,332
E 501,600 629,486
F 253,100 316,672
G 312,600 377,486
H 634,600 798,537
I 245,800 377,346
J 33,100 104,145
TOTAL 4,771,600 6,211,860
3. WORK METHOD
With this in mind the optimal work method for the works consists of a large Trailing Suction Hopper
Dredge (TSHD) installed with draghead side jetting nozzles supported by a Sweeping Vessel.
Additionally, areas consisting of hard soil may be dredged with the use of a Backhoe Dredge (BHD).
3.4. Equipment
These TSHDs are selected based on their hopper capacity, twin pipe configuration and proven
draghead design leading to the following advantages/benefits:
1. The large hopper capacity and the relatively short sailing distance to the spoil ground virtually
negates the need to overflow during hopper loading as overflow will result in no or little production
advantage in the anticipated material. This also proves beneficial from an environmental
perspective. Regardless, any overflow water from the hopper will be via the “green valve”, explained
in detail in section 3.4.2;
2. The twin pipe configuration will allow greater accessibility to areas regardless of sailing direction;
3. The dragheads on the TSHD can be installed with side jetting nozzles, shown in Figure 3.2, to
assist with dredging alongside quay walls and also for dredging channel batters.
Side jet
Figure 3.2 Draghead with side jetting nozzle
The TSHD will be used to dredge all materials encountered within the dredging envelope. These are
generally expected to be predominantly fine grained sediments, comprising clayey silt with lesser silty
clay which are of low to medium plasticity that can be dredged relatively easily. The TSHD will be used
to gradually deepen and widen the channel and basin as per the specifications and drawings.
The TSHD will be supported by a Sweeping Vessel and, if required a Backhoe Dredge as described in
sections 3.4.2 & 3.4.3 respectively.
3.4.2. TSHD overflow with ‘Green valve’
The TSHD hopper overflows are fitted with ‘green valves’. ’Green valves’ are devices installed on the
overflow that reduce turbidity by preventing entrainment of air into the overflow. When dredging in
normal mode, the overflows are fully open and the water mixture including fine sediments, which have
not settled in the hopper, makes more or less a free fall down the overflow until it reaches seawater
level. During this free fall, air gets entrained. The main part of the fine sediments will settle directly to the
seabed due to differences in density. However, a part of the mixture will be pulled towards the water
surface by the rising air bubbles creating a visible plume.
When using a green valve, the overflow is partly closed (right picture in Figure 3.3), preventing the free
fall of the water sediment mixture. This results in hardly any air being entrained, bringing less fine
sediments in suspension in the upper part of the water column. Because a larger part of the fine
sediments in the mixture settles to the seabed more rapidly with the use of a green valve, the turbid
plumes are smaller, of shorter duration, and mostly confined to the lower parts of the water column
where currents have less power for sediment dispersion.
At some locations within the Dredge Area the soil may be too hard to dredge with the use of a TSHD. In
these areas a Backhoe Dredge (BHD) may be required.
In addition, various auxiliary craft will be used to support the dredging operations including a crew
transfer vessel (CTV) and a hydrographic survey vessel. Typical crew/survey vessels are available
locally and will be chartered for the duration of the works.
Specifications of a Sweeping Vessel, BHD and crew/survey vessel which will be used, or similar, are
given in section 9.3, 9.4 and 9.5.
Speed
The dredged material settles out in the hopper and the excess transport water is evacuated through the
overflow system. This overflow system can be adjusted, in order to optimise production and minimise
losses. In the cases where use of the overflow is not advantageous (e.g. no increase in production) or
not permitted, the hopper is only filled up to the overflow level.
When the draught of the vessel reaches the dredging load mark or when circumstances do not allow
further loading, dredging will be suspended and the suction pipe(s) will be hoisted on deck. The vessel
then sails loaded with dredged material to the approved disposal ground.
The general sequence of actions when dredging in the work areas are described below and will depend
on actual current directions, wind speed and direction and at the Dredge Master’s discretion:
TSHD will approach its pre-planned dredge target location;
THSD will reduce speed within 2000 meters from the dredging area;
TSHD will reduce speed to 6 knots within 1000 meters from the dredging area;
TSHD will further reduce her speed to 3 knots within 500 meters from the dredging area;
TSHD will have reduced her speed to 0 -3 knots upon arrival at the dredging area;
Upon arrival at the dredging area, the dredge pipes, fitted with a ‘normal’ multi-purpose draghead,
will be put overboard and lowered to the seabed by the winches;
When the draghead has reached a depth of 5 meters above the seabed, the pumps will be started;
The TSHD will start "trailing" in Dynamic Positioning and Dynamic Tracking (DP/DT) mode with an
operating speed of 0.5 – 3knots;
Simultaneously the draghead will be lowered onto the seabed and dredging commences;
The TSHD will continue “trailing” until the draghead has reached the end of a particular stretch, after
which the draghead will be hoisted clear above the seabed and the “trailing” will be stopped;
The TSHD will then go astern to the starting position, or turn around, or proceed to different area.
If loading has not been completed yet the TSHD will relocate to an appropriate stretch for
completing the loading;
Draghead will be lowered on the seabed again;
Sequence will be repeated as described above.
The Sweeping Vessel consists of a tug on which an A-frame and bed leveller are installed. By lowering
the bed level bar to a certain level (Figure 3.6), the tug will start to sail and the material above the cutting
edge of the bar will be gathered and will be swept and deposited in lower areas.
Onboard the Sweeping Vessel, Boskalis inhouse DV2 survey system will be installed to enable accurate
positioning and operation of the bed levelling vessel.
Figure 3.6 Typical Tug and Bed leveller Setup
Dredge spoil plans will be based upon a grid of boxes (see Figure 7.2) representing the size of a hopper
load.
LPC Inductions
Port Operations Harbour Masters Directions
Notices to Mariners
Admiralty Charts
Local knowledge and pilot exemptions
Communication with LPC Port Control
Priority of commercial shipping
Restrictions for cruise shipping
Caution with recreational craft
AIS requirements.
3.9. Demobilisation
Specific equipment will be demobilised from site after it has completed its tasks for the Works.
Demobilisation will be in accordance with the procedures and regulations of the relevant authorities and
contract conditions.
4. EQUIPMENT MAINTENANCE
During the works, regular maintenance will take place of all equipment. The purpose of the maintenance
is to ensure proper and efficient operation of the dredger and to minimise potential effects on the
environment (i.e. underwater noise and possible leakage of hazardous substances).
Boskalis vessels and equipment follow the Boskalis Fleet Management System (FMS), which is based
on the International Safety Management Code for the Safe Operation of Ships and for Pollution
Prevention (ISM-code). All main vessels and equipment of Boskalis are managed centrally by
Fleet Management Dredging (FM). To keep track of repair, maintenance and stock of each vessel
in the fleet Boskalis uses IBM Maximo Asset Management software. Required intervals of routine
inspections, repairs and refits are shown in the system. This also helps plan necessary quantity of
assets to stock on the vessels before they leave the port.
Specific attention is made to ‘Critical Equipment’, which is defined as equipment that is vital for the
safety of the Fleet and its crew. FM-430 ‘Critical Equipment’ describes the control, preventive
maintenance, purchasing and logistics of these Critical Equipment. For each vessel a general criticality
assessment matrix is made for each equipment based on seven parameters:
1. Class
2. Environmental
3. Risk failure start-up
4. Risk failure in operation
5. Effect on production
6. Complexity
7. Cost re-install/change-out
cal
Environmental the equipment on the N Moderate Considerable Extremely
environment?
ISM Criti
Risk failure installation/personnel when the Extremely
start up equipment fails to start N Low High high
Moderate Considerable
al Critical
Effect on What is the influence of the reduction of reduction of Stop of
production equipment on the production ? N production production production
eration
Moderate Considerable Extremely
Complexity How complex is the installation? Simple complex complex complex
How high are the costs of repair/
Cost re-install / replacement in case the installation Extremely
Op
change-out fails? Minor Moderate Considerable high
1. Based on the 4 first parameters, all equipment with a critical value above 80% is considered as
ISM critical.
2. Based on the 4 last parameters, all equipment with a critical value above 50% is considered as
Operational critical.
3. Based on all 7 parameters, all equipment with a critical value below 50% is considered as non-
critical.
For all ISM Critical Equipment, a Preventive Maintenance Schedule has to be implemented to increase
the reliability of the equipment. This schedule includes planned maintenance, corrective maintenance
and a planned testing and inspection regime. For Operational Critical Equipment, the Preventive
Maintenance scheme is based on regular inspections, experience and wear & tear.
Defining the criticality of each equipment on board of the vessel allows to assess the critical equipment
of each vessel and the required maintenance. The critical value of the equipment is displayed in Maximo
and all maintenance activities on Critical Equipment is registered in Maximo. In case of failures of
Critical Equipment, the Captain shall directly inform the Fleet Management Team. The Fleet
Management Team and the Captain shall jointly and as soon as possible initiate the necessary
mitigating actions to limit the risks involved.
As an example, equipment for the TSHD Fairway assessed as ISM critical (critical value above 80%) are
i.a.: CO2 system, Foam Fire Fighting System, Water Mist Installation, Engine, Rudder, Propulsion,
Thruster, Oil Pollution Prevention, Pilot ladder, Radar and Magnetic Compass.
Routine maintenance activities conducted on the dredge vessels to prevent biofouling will be elaborated
further in the BMP [16].
5. SAFE IMPLEMENTATION OF SIMULTANEOUS OPERATIONS
The Channel Deepening and Widening works require interaction with multiple port users. Maintaining a
safe environment for the current port users and operators is paramount. This includes but not limited to
onshore operations, shipping, associated ancillary vessels and labour.
A SIMOPS plan will be used to illustrate the measures that will be taken to ensure safe implementation
of Simultaneous Operations (SIMOPS) and Interface Management during the works.
The TSHD will sail under its own power and will therefore be able to relocate relatively easily to an
alternate dredging area or sail to the deposition site prior to the arrival or departure of traffic.
However, prior to the start of the Project the Employer and Contractor will meet with the Naval Point
Club Lyttelton and Charters Bay Yacht Club to ensure that the Project activities will not intervene with
any yachting events in the Project Area. Notices will also be placed on the local boat ramps to provide
project information and navigations recommendations for the general boating public. The local fishing
fleet and general Port users will also be provided information on the project and navigation hazards via
LPC’s normal customer communications and formal central government Notices to Mariners.
6. ENVIRONMENTAL MANAGEMENT
It is the Employer and Contractor’s aim to minimise any negative impacts of the dredging and associated
discharge of dredged materials on the marine receiving environment. This includes measures related to
minimising turbidity as described in detail in the EMMP [14], monitoring of marine mammals as
described in the MMMP [15], biofouling as described in the BMP [16] and management of waste,
hazardous substances and refuelling as described in the HSE plan [29]. This section describes
environmental measures related to dredging in line with the Consent conditions for the DMP which are
not covered in the aforementioned plans.
Complying with the applicable statutory environmental provisions and regulations and, wherever
possible, going further than required;
Focusing policy on the permanent prevention or limitation, as far as possible, of pollution of soil,
water and air, sound creation, creation of waste products and use of dangerous materials;
Collecting and having waste processed separately, and using water and energy efficiently;
Translating policy into clear practical guidelines and, furthermore, ensuring that the policy and the
guidelines are implemented in practice;
Permanently ensuring that the environmental awareness and motivation of the employees and
others who work on the premises of Boskalis is such that environmental protection - although
primarily the management's responsibility - is everybody's concern;
Optimising our environmental management system according to ISO 14001 standard, to achieve
continuous improvement of our environmental performance SHE-Q structure.
By monitoring throughout the construction activities in combination with reviewing the process (for
example dredging cycle, production rates, bathymetric surveys etc.) opportunities can be identified d to
amend the activities to reduce impacts and increase efficiency.
The adaptive management approach and mitigation measures for this Project consist of:
Continuous real-time turbidity monitoring and associated trigger/compliance levels as described in
detail in the EMMP [14].
Use of a ‘green valve’ to reduce turbulence in the overflow system, described in section 3.4.2.
Assurance monitoring, undertaken by LPC, to monitor potential longer term effects, by a
comprehensive set of ecological monitoring prior, during and post-Dredging as described in detail in
the EMMP [14].
Marine mammal monitoring to prevent collision with marine mammals and impact from underwater
noise, as described in detail in the MMMP [15].
Management of biofouling as described in [16].
Minimisation of outdoor lighting to reduce the potential for bird strike as described in section 6.3.
Waste management and handling and storage of hazardous wastes, as described in section 6.5 and
in further detail in the HSE Plan [29].
Training to relevant personnel consisting of general environmental induction, marine mammal
monitoring and identification of potential archaeological material as described in section 6.4.
Measures to prevent any conflicts between the Dredging program and organized sporting events in
the Lyttelton Harbour/ Whakaraupō as described in section 5.2.
The effect of the Project on marine avifauna is assessed to be low to very low for most species, due to
the mobile nature of these species, the large foraging area available, the restricted spatial extent and
short-term nature of any effects.
However, to minimise any effects of bird strike associated with vessel lights, lighting on the vessels will
be kept to the minimum required to ensure safe operations and navigation. As a standard all lighting will
be faced downwards, whenever practicable. Lighting on the vessel will comprise of:
Deck lighting;
Navigational lights;
Lighting on the trailing arm and draghead such that the Dredge Master can visually locate the
dredging equipment during deployment and retrieval.
The various types of solid and liquid wastes that may be generated during the dredging activities
are:
Liquid waste;
Hazardous waste;
General solid waste (putrescible);
General solid waste (non-putrescible);
Recyclables.
6.5.1. Hazardous waste
No bulk hazardous materials are planned to be used during the course of the Project. The Contractor
Project Manager will ensure that any hazardous materials used during the project are controlled and
appropriately managed. An inventory of any hazardous materials will be maintained on the respective
vessels.
The Contractor will ensure that the Employer is provided with details of chemicals and hazardous
substances proposed to be used in execution of the project. Information on all chemical and hazardous
substances will be provided by reference to the appropriate Safety Data Sheets (SDSs).
Physical storage, handling/transport and usage shall comply strictly with the procedures as defined in
the product MSDS guidelines and New Zealand legislative requirements. Personal Protective Equipment
(PPE) will be provided to the workers and extra precautionary measures shall be taken where
necessary. Welding, cutting or grinding operations will not be permitted in the vicinity of flammable
substances storage.
All project personnel are responsible for making themselves aware of and applying the controls and
precautions as per manufacturer’s instructions/recommendations when working with hazardous
materials, this includes Environmental controls.
For more detail on waste management and storage and handling of Hazardous substances reference is
made to the HSE plan [29].
7. DREDGING CONTROL & SURVEY
The positioning system determines the actual vessel and draghead position(s) and presents the results,
relative to the area to be dredged, on navigational displays. The vessel and draghead position results
are derived by calculation from the X, Y, Z inputs from the RTK-DGPS positioning and tide gauge
systems together with the data from the angle transducers, the pressure sensors and the vessel’s gyro
compass.
The position of the vessel and draghead(s) are visualised on screen against a background of
bathymetric data, obstacles, buoys and special features such as the presence of existing cable(s) or
pipeline(s). For example a plan view is displayed with a coloured differential chart showing the areas to
be dredged, together with a longitudinal and cross sectional profile indicating the seabed level and
design. The graphical display can also visualise the tracks the TSHD has sailed previously.
DV2-HMS allows the operator maximum control over the dredge area, both in the horizontal and vertical
planes. Impressions of the DV2-HMS’s operator’s displays are given below.
Figure 7.1 DV2-HMS TSHD control displays. Suction tube display, suction production display and main navigation
display
Dredging tolerances are an accumulation of positioning and tracking accuracy, soil characteristics, swell,
tide, data errors and operator’s skills.
For discharging via the bottom doors, it is possible to pre-define so called ‘discharge-boxes’ in the DV2-
HMS module. These boxes enable the helmsman to accurately position the TSHD above a specific
target, in order to discharge the dredged material in that particular box. This is illustrated in the figure
below. The location of the boxes can be defined during preparation of the works by the surveyor,
superintendent and TSHD’s Captain.
7.2. Survey
Dredged spoil material will be discharged in the designated disposal ground by means of TSHD bottom
dumping as described in section 3.6. The disposal ground is located approximately 5 NM offshore of the
Harbour Heads, located as shown in Figure 1.2.
The disposal area will be subdivided by the Contractor into various disposal boxes as described in the
previous section. To ensure the dredged material is always discharged within the boundaries of the
Dredge Spoil Disposal Area each box will be subdivided into smaller disposal boxes. The size of each
individual disposal box will be adjusted to the discharge footprint of the vessel, therefore ensuring that
the TSHD has disposal boxes suitable for its specific dimensions. The additional subdivision of the main
boxes will allow for control of distribution and gradual build-up of the material within the disposal area. A
100m buffer zone where disposal will not occur will be maintained along the edge of the Dredge Spoil
Disposal Area as a safeguard.
The disposal location of each load will be logged and recorded. Regular progress surveys will be
undertaken to ensure all vessels are provided with accurate bathymetrical data. The vessel will
discharge its load evenly across the dedicated discharge boxes. In practice this means that the vessel
will be discharging at slow speed to ensure the load is spread and no unwanted high spots are created.
Based on the sediment behaves during disposal (informed by the progress surveys) the disposal
process may be further optimised to ensure even deposition by altering the vessel speed whilst
depositing the load.
8. REFERENCES, ABBREVIATIONS, DEFINITIONS
8.1. References
Controlled Legislation
No. Document No. Document Title
[1] CRC172455 Coastal Permit under section 12 of the Resource
Management Act 1991
[2] CRC172522 Discharge Permit under section 15, 15A and 15B of
the Resource Management Act 1991.
Client Documents
No. Document No. Document Title
[11] LYT263462 5982618.6 Request for Tender – Channel Deepening Project
Stage 1 - September 01, 2017
Boskalis Documents
No. Document No. Document Title
[29] 554-10023-02-01 Health, Safety, Environment Management (HSE)
Plan
[30] 554-10023-02-02 Quality Management Plan
[31] 554-10023-02-03 Emergency Response Plan
[32] 554-10023-14-01 Survey Method Statement
8.2. Abbreviations
Keys” Table 9.1 Specifications Typical Crew Transfer/Survey Vessel “Star Keys”
Classification Survey/Patrol/Crew/Research
Year built 1998
Length O.A. 19.10 m
Beam 5.4 m
Draft 1.9 m
Builder Image Marine Group WA
Construction Aluminium
Maximum Speed 24 knots
Transit Speed 10 knots
Fuel 6,000 litres
Fresh Water 600 litres + Water Maker
Deck Area 45m2
Tender IBC RIB, 25HP
Radar, Autopilot, Depth Sounder, Radios, Magnetic Compass, GPS, SSB,
Navigation
Plotters, AIS.
Other Towing Post, Survey Pole
Main Engines Caterpillar C32 Total 1,099 HP
Generators 1 x Onan 27 kVA
Deck Power
3 Phase, 400V/20A/5 Pin
Outlet
Classification Survey/Patrol/Crew/Research
Propulsion Single Screw 4 Blade, Bowthruster
Deck Machinery Palfinger PK 11001 crane (aft), Pot Hauler
Bollard Pull 5T
Helm Stations Bridge/Fly Bridge/Deck
Enclosed &
42 POB, Passenger
Inshore (12 miles)
Coastal (50 miles) 10 POB, Non-Passenger
Offshore (200
10 POB, Non-Passenger
miles)