IJPR2016 Lacerda Xambre Alvelos 2
IJPR2016 Lacerda Xambre Alvelos 2
IJPR2016 Lacerda Xambre Alvelos 2
António Pedro Lacerda, Ana Raquel Xambre & Helena Maria Alvelos
To cite this article: António Pedro Lacerda, Ana Raquel Xambre & Helena Maria Alvelos (2016)
Applying Value Stream Mapping to eliminate waste: a case study of an original equipment
manufacturer for the automotive industry, International Journal of Production Research, 54:6,
1708-1720, DOI: 10.1080/00207543.2015.1055349
Download by: [b-on: Biblioteca do conhecimento online UA] Date: 03 January 2017, At: 07:23
International Journal of Production Research, 2016
Vol. 54, No. 6, 1708–1720, http://dx.doi.org/10.1080/00207543.2015.1055349
Applying Value Stream Mapping to eliminate waste: a case study of an original equipment
manufacturer for the automotive industry
António Pedro Lacerdaa, Ana Raquel Xambrea,b* and Helena Maria Alvelosa,b
a
Department of Economics, Management and Industrial Engineering, University of Aveiro, Aveiro, Portugal; bCIDMA – Center for
Research and Development in Mathematics and Applications, University of Aveiro, Aveiro, Portugal
(Received 15 September 2014; accepted 19 April 2015)
Since its beginning, lean manufacturing has built a worldwide reputation based on results related to production
improvement and cost reduction in several companies. This management philosophy focuses on customer value creation
through the elimination of production wastes. Lean methods and techniques have spread their scope from the automotive
industry to a wide range of industries and services. This article presents a case study that describes the use of the lean
tool value stream mapping in the production process of automotive parts for a major automotive company. At the
beginning of the project, relevant data from the process were collected and analysed. Subsequently, the initial process
was mapped, the related wastes were identified, and then future processes were mapped and financial results were
estimated. The proposals were presented on kaizen meetings, the action plan was discussed and the decision regarding
which option to choose was taken. Consequently, the Cycle Time and the level of the workforce were reduced, the
process was improved and savings were obtained.
Keywords: lean manufacturing; continuous improvement; value-stream mapping; automotive industry; plastic injection
1. Introduction
The economic crisis that Europe currently faces has had a huge impact on companies’ revenue. In order to strive
through this period, many were forced to implement cost-saving management philosophies; one among them is lean
manufacturing. Lean manufacturing is based on the principles of the Toyota Production System (TPS). In essence,
lean manufacturing philosophy focuses on customer value maximisation through the elimination of production wastes
(Womack and Jones 2003; Belekoukias, Garza-Reyes, and Kumar 2014). Contrary to product standardisation and
assembly lines, lean thinking promotes small production lots and quick changeovers thus reducing production time
and focusing on product quality and diversity at a competitive price (Womack, Jones, and Roos 1990; Rahani and
al-Ashraf 2012). This article describes the work that was carried out in a Portuguese original equipment manufactur-
ing company, operating in the injection moulding industry, that supplies major automotive companies. A mid- to
long-term strategic decision led the company to invest on a production project of plastic parts for a luxury car of a
current customer. The work was carried out during a period of 8 months, and its main objective was to improve
the performance of the production process, through the reduction of wastes and thus increasing its quality and effi-
ciency.
In order to achieve the proposed objectives, firstly lean manufacturing and continuous improvement methods, mainly
value stream mapping (VSM), were analysed and considered. Afterwards, production data related to the project, both
from documentation and on-site, were collected and analysed. Subsequently, the following steps were followed: (i) the
mapping of the current production process and the identification of critical points, (ii) the mapping of the desired pro-
duction process together with the development of the action plan required to implement the proposed changes and (iii)
the analysis of the financial impact of those changes.
This article is organised as follows: the current section makes an introduction to the project, its objectives and the
methodology followed; the second section consists of a brief description of lean manufacturing and continuous
improvement tools and metrics used in the project; the third section reports the analysis and implementation made
during the project to achieve the proposed objectives; and finally, the fourth section describes the main conclusions
of the work.
The implementation of lean manufacturing calls for constant development and refinement of its practices (Marodin
and Saurin 2013). This led to the development of continuous improvement, a culture that simultaneously emerged in
Japan, concerning the elimination of wastes and cost reduction (Imai 1997). Kaizen, as it is known, is a systematic
approach that focuses on client needs. It is process orientated and encourages the participation and proactivity of every
individual (Glover et al. 2011).
Implementing lean manufacturing is a complex process that encompasses all the hierarchy levels of an organisation
and several aspects of the way the company works. Some authors have suggested ways to delineate the required steps
for implementing lean (Black 2007; Serrano Lasa, Castro, and Laburu 2009; Vienazindiene and Ciarniene 2013) but
there is still, according to Marodin and Saurin (2013), the need for further research so as to define coherent methods for
implementing lean systems.
After a general description of the lean philosophy, the specific tools used in the case study are presented in the
following subsections.
Value Added Time refers to the time of the operations that, according to the client, add value to the product and for
which he is willing to pay (Rother and Shook 2003).
Cycle Time is defined by the period of time between repetitions of the same task. It is, therefore, the time taken by
all operations of the slowest station/operator of the process (Rother and Shook 2003).
Takt Time is the frequency in which a product must be produced, to meet the clients demand. This metric is used to
synchronise the production and the sales cadence (Rother and Shook 2003). Takt Time can be determined using the
following formula:
Figure 1. Production process: (a) general flowchart; (b) operations and components.
1712 A.P. Lacerda et al.
This project was one of the first the company has had involving a luxury car. A production volume of parts for
16,688 cars per year have been defined between the company and the client. The client is responsible for providing data
to the information system for orders’ management, taking into account the semi-annual demand forecast and the weekly
demand for products. The system manages the needs of raw materials and provides the necessary information to the
plant sections. Inside the injection and the assembly area, the production orders are delivered to the stations, which are
responsible for pulling the raw materials and components from the warehouse.
Q P 6 0.74 6.7 15 4 5
I P 3 0.56 11.8 15 3 3
U P 9 1.26 7.9 15 7 8
U P (2) 7 1.47 17.7 18 5 6
I P (2) 1 15 1 1
Total 25 20 22
International Journal of Production Research 1713
T P X 2 0.35 13.7 15 1 2
U P X 4 0.97 23.8 24 3 3
Q P X 8 2.09 24.6 25 7 7
A 4 X 31 5.94 13.8 15 25 27
A 5 X 15 2.64 12.6 15 12 12
A 6 X 16 2.16 7.3 15 13 13
R 7 X 9 1.85 15.5 17 7 8
A 7 X 2 0.46 15.7 16 2 2
A 3 X 81 7.83 3.6 15 65 69
A 3 (2) X 23 4.38 14.5 16 18 19
R P X 2 0.49 16.8 17 2 2
T 1 X 2 0.41 13.6 15 2 2
U 1 X 6 1.38 23.9 24 4 5
Q 1 X 23 5.15 19.6 20 18 20
A 2 X 122 7.99 1.7 15 97 104
A 2 (2) X 22 6.04 27.9 28 18 19
R 1 X 16 2.17 7.1 15 13 14
R 1 (2) X 22 5.58 24.0 26 18 19
A 1 XX 44 8.92 15.6 16 35 38
R 1 (3) X 49 9.38 14.2 15 39 42
B 1 X 110 14.75 6.9 15 88 95
R 1 (4) X 43 6.32 8.3 15 34 37
R 1 (5) X 100 12.74 6.2 15 80 86
R 8 X 15 1.11 2.2 15 12 13
A 8 X 24 3.07 6.2 15 19 21
I F X 12 2.03 10.3 15 10 11
R F X 17 3.59 17.7 18 13 14
U F X 8 1.72 18.7 19 6 7
U F (2) X 6 0.65 4.6 15 5 5
I F X 1 15 1 1
Total 165 220 368 836 669 716
As for the objects, the designations P and F refer to the plastic part that is injected and to the final product,
respectively. The rest of the objects are the components used to assemble the final product. Component 1 is particularly
important as it is a very sensitive aluminium part.
Concerning the activities identified by I.P(2) and by I.F, the methodology used to determine the standard time was
different. Their duration was assumed to be 1 s due to the fact that, in both cases, the packages take 12 parts and it
required less than 12 s to pack them all.
Number of Operators 1 3
Cycle Time 65 s 370 s
Operation Time 23 s 717 s
Value Added Time 15 s 480 s
Monthly Occupation 1.24 days/month 23.66 shifts/month
Monthly Workforce Necessity 0.17 workers/month 3.23 workers/month
The Monthly Occupation sets the need of production days per month, working at a specific Cycle Time, to meet the
demand, and can be computed using the following formula:
The critical points represent either wastes of the production process or operations with improvement potential and
are presented in Figure 2. Twelve operations, represented in bold black font, were identified as waste. Additionally, there
are other five sources of waste, also highlighted in bold black font, that represent metrics that are considered critical,
namely an inventory time of 13 days, and the differences between Value Added Time, operation time and available time
for all of the four operators (machine operator, assembly operator 1, 2 and 3).
As for the reworks integrated in the production process in response to quality demands of the client are represented
by the use of a bold grey font and account for nine critical points. These rework tasks are temporary until the necessary
corrections (either to the part or to the production process) are made and consequently eliminate the need for those
tasks.
A total of 26 critical points were identified, concerning two major groups.
The first group refers to the problems related to the process flow. For instance, the time consumed by the manual
bending of aluminium engaging clips (operation B.1) represented one of the process major bottlenecks. Other critical
points with potential for improvement are as follows: (i) the operator’s traffic intersection (between operators 1 and 2),
visible in Figure 3; (ii) the difference between the operation time, the available time and the Value Added Time for each
operator and (iii) the inventory level.
The second group of critical points is related to quality issues. Spots in injected parts or stains and cracks in alu-
minium parts (component 1) were often identified when performing quality control operations and were considered,
therefore, a major concern. Another problem was detected by the client, when some products were shipped without
component 8.
OperationTime
Monthly Workforce Necessity ¼
Planned Cycle Time
The results of the metrics used for the future state of the production process were the following:
25; 800
Takt Time ¼ ¼ 344 s
75
Number of Operators 1 2
Cycle Time 69 s 132 s
Operation Time 68 s 231 s
Value Added Time 68 s 231 s
Monthly Occupation 1.32 days/month 8.44 shifts/month
Monthly Workforce Necessity 0.18 workers/month 0.77 workers/month
International Journal of Production Research 1717
Figure 5. Stations’ layout for the future state of the production process.
261
Monthly Workforce Necessity ¼ ¼ 0:84 workers=month
310
Despite the obtained value, the involvement of two operators is essential to perform the assembly of component 1 in
the plastic part without putting at risk the quality of the product, as refereed in Section 3.3. Therefore, a mapping of a
future state with two operators in the assembly station was developed, which enabled a decrease in the Monthly
Occupation of that station.
In Figure 4, it is possible to observe the future process state balanced and without the critical points identified
previously.
The estimated values for the lean metrics used in the study are presented in Table 4.
In Figure 5, the proposed layout for both stations, in the future state of the process, is presented.
To achieve the proposed future state of the process, an action plan was defined, containing 14 actions that gathered
consensus among the main interveners in the project during kaizen events.
The critical points of the process were, therefore, solved through multiple approaches, depending on the type of
problem.
Concerning the previously identified process flow problems, the bending of engaging clips (operation B.1) was
improved through the acquisition of a bending machine, a solution financially supported by the client. This solution
eliminated one of the major bottlenecks, turning a 95 s operation into a 1 s operation (operation T.F (3) – transport of
the final part to the bending machine).
The traffic intersection between operators 1 and 2 was solved with the reformulation of the layout (Figure 5) and
with the use of the 5S methodology in the assembly station.
Mapping a balanced process (Figure 4) was the solution for the differences between the available time, the operation
time and the Value Added Time.
In order to decrease the inventory level and achieve a more flexible process, the methodology Single Minute
Exchange of Die (SMED) was applied to the exchange of the injection mould. As for the previously identified quality
problems, changes in the injection parameters, in the structure of the plastic part and in the packages configuration, as
well as the purchase of support structures, helped to eliminate spots, stains and cracks that occasionally occurred in the
product.
To address the problem of shipping incomplete products, a Poka Yoke system was created with the use of optic
sensors, alerting the operators whenever task A.8 had been skipped.
At that time, 11 of the 14 proposed actions were implemented and the Cycle Time of the assembly station was
reduced by 62% (from 370 to 140 s). The Cycle Time of 132 s, estimated for the future state (see Table 4), corresponds
to the expected value after the implantation of the final actions.
1718 A.P. Lacerda et al.
Savings
Monthly Workforce Necessity 3.4 workers/month 0.95 workers/month
Monthly Occupation – Assembly Stations 23.66 shifts/month
2
8.44 shifts/month
2
Unfinished Stock Warehouse Area 24.33 m 17.84 m
Workforce savings = Δworkforce × 211.5 (€/h) × 8 (h) × 22 (days) × 10 (months) 49,588 €/year
Area savings = Δarea × 0.15 (€/m ) × 24 (h) × 22 (days) × 10 (months) 5,140.1 €/year
Costs
Monthly Occupation – Injection Station 1.24 days/month 1.32 days/month
Injection Machine Occupation Cost = Δoccupation × 48 (€) × 0 (months) 921.6 €/year
Necessary Investment – Action Plan 3,500 €
Other important results were the reduction of the required number of operators, from four to three, and the reduction
in 25% of the inventory level of the unfinished product, consequence of the referred SMED action. Decreasing the chan-
geover time made it possible to have a smaller economic lot size, while maintaining the injection machine operational
performance’ level at 90%.
The implementation of the solutions of the action plan was thus essential to reach the desired state of the process.
4. Conclusions
Lean manufacturing methodologies have been implemented by the companies who intend to achieve competitive advan-
tage and business sustainability (Pavnaskar, Gershenson, and Jambekar 2003).
The implementation of the lean tool VSM in the company studied aimed at reducing waste and thus increasing both
the quality and efficiency of a production process. The production process of the part considered in this case study was
firstly studied through data collection and analysis. The resulting information led to the definition of the initial state as
well as to the identification of the critical points. Afterwards, a future state was mapped representing a balanced produc-
tion process with a considerable waste reduction. A financial analysis was also performed, pointing out the expected
profit of the proposed changes.
Lean wastes have been identified and fourteen solutions were proposed to eliminate them, of which eleven were
implemented. As a result, the Cycle Time on the assembly sub-process was reduced from 370 to 140 s, the number of
operators was reduced from four to three, and the inventory level of the unfinished product has also decreased by 25%,
and one of the major bottlenecks was eliminated by changing a 95 s operation into a 1 s one. The financial analysis was
essential for the decision-making process and provided better results than expected by the decision-makers. Ultimately,
by implementing the action plan, the resulting production system became more functional and effective.
Apart from the improvements mentioned above, a change of mindset was also noticed within the operators involved
in the production of the analysed part. By being frequently heard on-site and participating in kaizen events, they felt as
an active part of the solution and so they became more committed in their work. The involvement of the workers and
the change in terms of mentality were essential to implement new ways of working but also to keep the continuous
improvement process on track (Hines, Holwe, and Rich 2004; Mann 2010; Vienazindiene and Ciarniene 2013).
International Journal of Production Research 1719
The results achieved in the case study suggest that the remaining solutions from the action plan could lead the
production process to the proposed state and should therefore be implemented. The referred lean metrics should also
continue to be closely monitored and the VSM tool should be applied to the complete value chain as well as to other
processes in the company.
The implementation of the VSM described in this article was crucial for the reduction of waste and the increase of
productivity of the process studied, thus providing evidence of the potential of this lean tool.
This article can be valuable both for researchers on the impact of lean thinking in manufacturing, as for companies’
decision-makers or staff that want to implement lean tools, particularly VSM.
Disclosure statement
The authors state that they have no interests, financial or otherwise, which might be perceived as posing a conflict or bias.
Funding
This work was supported by Portuguese funds through the CIDMA – Center for Research and Development in Mathematics and
Applications, and the Portuguese Foundation for Science and Technology (‘FCT–Fundação para a Ciência e a Tecnologia’), within
project UID/MAT/04106/2013.
References
Abdulmalek, Fawaz Z., and Jayant Rajgopal. 2007. “Analyzing the Benefits of Lean Manufacturing and Value Stream Mapping via
Simulation: A Process Sector Case Study.” International Journal of Production Economics 107 (1): 223–236. doi:10.1016/
j.ijpe.2006.09.009.
Bateman, Nicola, Peter Hines, and Peter Davidson. 2014. “Wider Applications for Lean.” International Journal of Productivity and
Performance Management 63 (5): 550–568. doi:10.1108/IJPPM-04-2013-0067.
Belekoukias, Ioannis, Jose Garza-Reyes, and Vikas Kumar. 2014. “The Impact of Lean Methods and Tools on the Operational Perfor-
mance of Manufacturing Organisations.” International Journal of Production Research 52 (18): 5346–5366. doi:10.1080/
00207543.2014.903348.
Bhasin, S., and P. Burcher. 2006. “Lean Viewed as a Philosophy.” Journal of Manufacturing Technology Management 17 (1): 56–72.
doi:10.1108/17410380610639506.
Black, J. T. 2007. “Design Rules for Implementing the Toyota Production System.” International Journal of Production Research 45
(16): 3639–3664. doi:10.1080/00207540701223469.
Chen, Joseph C., Ye Li, and Brett D. Shady. 2010. “From Value Stream Mapping toward a Lean/Sigma Continuous Improvement
Process: An Industrial Case Study.” International Journal of Production Research 48 (4): 1069–1086. doi: 10.1080/
00207540802484911.
Duggan, Kevin J. 2013. Creating Mixed Model Value Streams: Practical Lean Techniques for Building to Demand. Boca Raton, FL:
CRC Press (Taylor & Francis Group).
Glover, Wiljeana, Jennifer Farris, Elieen Van Aken, and Toni Doolen. 2011. “Critical Success Factors for the Sustainability of Kaizen
Event Human Resource Outcomes: An Empirical Study.” International Journal of Production Economics 132 (2): 197–213.
doi:10.1016/j.ijpe.2011.04.005.
Halwachs-Baumann, Gabriele. 2010. “Concepts for Lean Laboratory Organization.” Journal of Medical Biochemistry 29 (4): 330–338.
doi:10.2478/v10011-010-0036-5.
Hines, Peter, Matthias Holwe, and Nick Rich. 2004. “Learning to Evolve: A Review of Contemporary Lean Thinking.” International
Journal of Operations & Production Management 24 (10): 994–1011. doi:10.1108/01443570410558049.
Imai, Masaaki. 1997. Gemba Kaizen: A Commonsense, Low-cost Approach to Management. New York: McGraw-Hill.
Jones, Daniel T., and James P. Womack. 2002. Seeing the Whole. Mapping the Extended Value Stream. 1st ed. Brookline, MA: The
Lean Enterprise Institute.
Krafcik, John. 1988. “Triumph of the Lean Production System.” Sloan Management Review 30 (1): 41–52.
Liker, Jeffrey K., and David Meier. 2006. The Toyota Way Fieldbook. New York: McGraw-Hill.
Lyon, S. W., H. J. Quesada-Pineda, and S. D. Crawford. 2014. “Reducing Electrical Consumption in the Forest Products Industry
Using Lean Thinking.” BioResources 9 (1): 1373–1386.
Mann, David. 2010. Creating a Lean Culture. New York: Productivity Press (Taylor & Francis Group).
Marodin, Giuliano A., and Tarcisio A. Saurin. 2013. “Implementing Lean Production Systems: Research Areas and Opportunities for
Future Studies.” International Journal of Production Research 51 (22): 6663–6680. doi:10.1080/00207543.2013.826831.
Meyers, Fred E., and James R. Stewart. 2002. Motion and Time Study for Lean Manufacturing. 3rd ed. Upper Saddle River, NJ:
Prentice-Hall.
1720 A.P. Lacerda et al.
Ohno, Taiichi. 1988. The Toyota Production System: Beyond Large-scale Production. Portland, OR: Productivity Press.
Pavnaskar, S. J., J. K. Gershenson, and A. B. Jambekar. 2003. “Classification Scheme for Lean Manufacturing Tools.” International
Journal of Production Research 41 (13): 3075 3090. doi: 10.1080/0020754021000049817.
Rahani, A. R., and Muhammad al-Ashraf. 2012. “Production Flow Analysis through Value Stream Mapping: A Lean Manufacturing
Process Case Study.” International Symposium on Robotics and Intelligence Sensors 41: 1727–1734. doi:10.1016/j.pro-
eng.2012.07.375.
Rother, Mike, and John Shook. 2003. Learning to See: Value-stream Mapping to Create Value and Eliminate Muda. Brookline, MA:
The Lean Enterprise Institute.
Schiele, Joseph J., and Clifford P. McCue. 2011. “Lean Thinking and Its Implications for Public Procurement: Moving Forward with
Assessment and Implementation.” Journal of Public Procurement 11 (2): 206–239.
Serrano Lasa, I., R. D. Castro, and C. O. Laburu. 2009. “Extent of the Use of Lean Concepts Proposed for a Value Stream Mapping
Application.” Production Planning and Control 20 (1): 82–98. doi:10.1080/09537280802685322.
Seth, Dinesh, and Vaibhav Gupta. 2005. “Application of Value Stream Mapping for Lean Operations and Cycle Time Reduction: An
Indian Case Study.” Production Planning & Control 16 (1): 44–59. doi:10.1080/09537280512331325281.
Simon, Ross W., and Elena G. Canacari. 2012. “A Practical Guide to Applying Lean Tools and Management Principles to Health
Care Improvement Projects.” AORN Journal 95 (1): 85–103.
Staats, Bradley R., David James Brunner, and David M. Upton. 2011. “Lean Principles, Learning, and Knowledge Work: Evidence
from a Software Services Provider.” Journal of Operations Management 29 (5): 376–390. doi:10.1016/j.jom.2010.11.005.
Surekha, S., R. V. Praveena Gowda, and Manoj Kulkarni. 2013. “Standardized Work: An Important Principle Implemented in the
Manufacturing Industry.” International Journal of Management Research and Business Strategy 2 (2): 62–66.
Teichgräber, Ulf K., and Maximilian de Bucourt. 2012. “Applying Value Stream Mapping Techniques to Eliminate Non-value-added
Waste for the Procurement of Endovascular Stents.” European Journal of Radiology 81 (1): e47–e52. doi:10.1016/
j.ejrad.2010.12.054.
Vienazindiene, Milita, and Ramune Ciarniene. 2013. “Lean Manufacturing Implementation and Progress Measurement.” Economics &
Management 18 (2): 366–373. doi:10.5755/j01.em.18.2.4732.
Vlachos, Ilias, and Aleksandra Bogdanovic. 2013. “Lean Thinking in the European Hotel Industry.” Tourism Management 36: 354–363.
doi:10.1016/j.tourman.2012.10.007.
Womack, James, and Daniel T. Jones. 2003. Lean Thinking: Banish Waste and Create Wealth in Your Corporation. New York: Free
Press.
Womack, James, and Daniel T. Jones. 2005. “Lean Consumption.” Harvard Business Review 83 (3): 58–69.
Womack, James P., Daniel T. Jones, and Daniel Roos. 1990. The Machine That Changed the World. New York: Rawson.