2007 02 12 GTZ - Sector Project Mechanical Biological Waste Treatment
2007 02 12 GTZ - Sector Project Mechanical Biological Waste Treatment
2007 02 12 GTZ - Sector Project Mechanical Biological Waste Treatment
Sector Project
Mechanical-biological Waste Treatment
Final Report
Desk Officer
Elke Hüttner (GTZ, Division 44 - Environment & Infrastructure)
Editing
Gernod Dilewski (INFRASTRUKTUR & UMWELT, Darmstadt),
Joachim Stretz (Berlin)
in cooperation with
Gabriele Janikowski (IKW Beratungsinstitut für
Kommunalwirtschaft GmbH, Cologne),
Dr. Dirk Maak (Wilhelm Faber GmbH, Alzey),
Dr. Aber Mohamad (University of Kassel),
Dr. Dieter Mutz (Basel University of Applied Sciences - FHBB),
Bernhard Schenk (Berlin)
Design
Christopher Heck•eyes-luna Multimedia-Design •,
D- 64291 Darmstadt
Printed by
Digitaldruck Darmstadt GmbH & Co. KG
Eschborn 2003
CONTENT
This report presents the main activities and results of the sector project "Promotion of Mechanical-
biological Waste Treatment", which was conducted by Deutsche Gesellschaft für Technische
Zusammenarbeit (GTZ) GmbH on behalf of the Federal German Ministry for Economic Cooperation
and Development (BMZ) between 1998 and 2003. The focal areas of the sector project were a trio of
pilot projects in São Sebastião (Brazil), Phitsanulok (Thailand), and Al-Salamieh (Syria), in which
mechanical-biological waste treatment (MBWT) options were field-tested under the relevant local
boundary conditions. All three pilot projects yielded satisfactory results following appropriate adapta-
tion of the decomposition process. The specific costs of MBWT ranged between 11 and 15 Euro/Mg
in all three cases. However, these expenditures are at least partially compensated by the resultant
savings in landfilling.
1
Sector Project MBWT - Final Report
Table of contents
2 Introduction to MBWT 10
2.1 Characterization of MBWT 10
2.2 Waste Treatment Processes 11
2.3 Integration of MBWT into Municipal Waste Management Schemes 12
2.4 Climatic Factors 13
2
4.2.6 Emissions from MBWT 43
4.2.6.1 Basic principles 43
4.2.6.2 Odors 44
4.2.6.3 Hygiene 44
4.2.6.4 Process water 44
4.2.6.5 Methane emissions 48
4.2.7 Disposal of pretreated waste to the landfill 48
4.2.7.1 Fundamental considerations 48
4.2.7.2 Mass reduction determined in the pilot projects 51
4.2.7.3 Emplacement trials in the pilot projects 52
4.2.7.4 Landfill leachate in São Sebastião 54
4.2.8 Costs 54
4.2.8.1 Costing principles 54
4.2.8.2 Examples of costs incurred in the pilot projects 55
4.2.8.3 Effects of MBWT on the cost of waste dis-posal 60
4.2.9 Informal sector 61
6 Summary 69
3
Sector Project MBWT - Final Report
APPENDICES
Appendix 3 Bibliography
LIST OF TABLES
Table 2: Anthropogenic emissions of CO 2, CH4, and N2O within the EU in 1994 [1] 14
Table 3: Proposed monitoring program for the pilot-scale field trial in Phitsanulok 24
Table 5: Backstopping work scope for Faber during the one-year imple-
mentation phase in São Sebastião 32
4
LIST OF FIGURES
Figure 1: The "Alvarenga" garbage dump in Sao Paulo, and the "Billings"
drinking water impounding reservoir Source: GTZ Photo Archive 8
Figure 17: Piling the waste for biological treatment in Atlacomulco, Mexico 29
5
Sector Project MBWT - Final Report
Figure 20: Time history of in-heap temperatures in the Al-Salamieh scale-model trial 35
Figure 23: Relationship between oxygen content and carbon dioxide concentration 37
Figure 28: Cumulative curves showing the precipitation onto and the pro-
cess water volume emerging from the test heap in São Sebastião 46
Figure 29: Quality of process water from test heaps in Rio de Janeiro
and São Sebastião 47
Figure 30: Process water seeping out from the base of a heap in São Sebastião 47
6
Figure 38: Comparison of pilot-project cost calculations (specific costs in EUR/Mg) 59
Figure 42: Avenues of waste disposal in the member countries of the EU in 1999 [7] 66
7
Sector Project MBWT - Final Report
8
Past attempts to transfer waste technologies Numerous German and foreign partners were
from industrialized countries of the West to attracted to the project to help implement its
developing countries have led to numerous activities:
disappointments. Hence it was not the sole
objective of the GTZ sector project "Promotion Federal German Ministry of Education and
of Mechanical-biological Waste Treatment" to Research (BMBF)
simply disseminate the technology, but also and Knoten Weimar
in particular to carry out a critical analysis of the the Faber Group
risks and potentials of MBWT. The pilot-scale the University of Kassel
MBWT field tests conducted in various countries Prefeitura São Sebastião
provide the main basis for this analysis. Prefeitura Municipal Ilhabela
Municipality of Phitsanulok
The sector project focused on both the technical
components and some key areas of develop-
ment policy, including in particular the living The individual project partners' names, addres-
conditions of waste pickers and how they would ses and contact persons are listed in the
be affected by the introduction of mechanical- Appendix.
biological waste treatment.
9
Sector Project MBWT - Final Report
2 Introduction to MBWT
Sewage sludge
posal by way of extensive stabilization. MBWT
Mechanical conditioning
can also help to recover valuable materials (cf.
Nonbiodegradables Coarse sorting Screening
Chapter 2.3). The terms composting and MBWT Recyclables Sorting Combinution
High-Energy Magnetic Separation Homogenization
are often used together, because both approa- Fraction
Inert fractions
Biological treatment
the two processes do pursue different objectives Aerobic Anaerobic/Aerobic
Decomposition Ferm. + post-decomp.
(cf. Table 1).
Cover
Screening
Optional
Disposal to landfill
Process Main objective Input Figure 2: The operational sequence of mechanical-biological waste treatment
10
To keep the leachate and the landfill gas from 2.2 Waste Treatment Processes
escaping to the environment, the landfill needs
to be sealed so that they can be collected and There is a broad spectrum of equipment and
treated systematically. biological treatment methods that can be com-
Through the controlled decomposition of organic bined for the purposes of mechanical-biological
substances, mechanical-biological waste treat- waste treatment, depending on the local situa-
ment substantially reduces both the gas and tion and the waste-management targets. For
water emissions which would otherwise be sub- example, some facilities are modestly equipped
sequently generated at the landfill and the volu- and are operated using extensive-type proces-
me of the residual waste requiring emplacement. ses, i.e. processes involving little automation
Waste containing a large share of biodegradable and low outlays for construction and process
organic material is most suitable for such treat- control.
ment. This is generally the case for household
and commercial waste. However, contaminated
waste, e.g. hazardous industrial waste; infec-
tious waste, e.g. waste from hospitals and
slaughterhouses; and constructionsite waste are
inherently unsuitable. The suitability of industrial
waste needs to be determined in advance, e.g.
by analyzing, on a case-by-case basis, its pollu-
tant concentrations and biomass fractions.
Fresh air
Exhaust air
Atmospheric
Biofilter pressure
~20 cm
~2,5 m
Homogenized waste
Slope approx.
Base ~25 m
ca. 3%
11
Sector Project MBWT - Final Report
Closed Hall
Exhaust-air
Mechanical
conditioned Post-treatment,
waste landfill
Vacuum ventilation
Exhaust-air
scrubbing
Intensive approaches help reduce the decompo- 2.3 Integration of MBWT into Municipal
sing time and the specific space requirements. Waste Management Schemes
Closed systems (hall, container) allow emissions
(gas, odor, dust, ...) to be controlled. Also, the The first step toward determining the extent to
decomposition process can be controlled and which MBWT may or may not constitute a good
optimized by way of active ventilation, moisturi- approach to waste management for a given city
zing and blending. This significantly accelerates or region is to survey and analyze the existing
the main decomposition process and increases waste-management situation.
the share of organic matter that actually decom-
poses. However, the structure and the requisite Prior to deciding in favor of mechanical-biologi-
equipment make this approach too expensive cal waste treatment, other waste-treatment
for anything but large amounts of waste, and the alternatives should also be considered. In indu-
high degree of automation makes the system strialized countries, for example, waste incinera-
more susceptible to disturbances and therefore tion is a fairly popular form of residual-waste
necessitates higher expenditures for maintenan- treatment. The flue-gas emissions are of primary
ce and repair. interest when evaluating environmental pollution
from waste incineration plants (WIPs).
12
In recent years many countries have adopted In many different countries, recent years have
emission standards for the control of flue-gas seen the installation of organic waste compo-
emissions from waste incinerating plants. Com- sting facilities (primarily for prunings and kitchen
plying with such standards necessitates very slops). As a rule of thumb, the composting of
high process-technological and financial invest- separately collected kitchen slops and garden
ments. Such plants are designed for high waste can always be regarded as useful, whet-
throughputs with a view to minimizing the speci- her or not mechanical-biological waste treat-
fic costs. ment is introduced.
Mechanical-biological
MBWT MBWT
treatment
high - energy
fraction
Conventional Slag-
Disposal to landfill MBWT-landfill
landfill dump
13
Sector Project MBWT - Final Report
Units [Gg] (over 100 years) [Gg] in CO2- equiv. em. [Gg] in CO2- equiv. em.
(with waste-disposal fraction, in (with waste-disposal distribution
wt.%, parenthesized) parenthesized))
Most of the greenhouse effect attributable to Another way to reduce methane emissions from
waste management can be ascribed to metha- landfills is to cover the older parts of the dump
ne, which is produced by the anaerobic diges- with a biofilter cap consisting of pretreated,
tion of biodegradable waste in landfills. Approxi- screened waste. The filter layer helps diminish
mately one-third of all anthropogenic CH4 emis- the amount of methane that can escape from
sions within the EU derive from that source. By the landfill.
contrast, only 1 % of the N 2O emissions and
less than 0.5 % of the CO 2 emissions can be
traced to landfilled waste. Hence, reducing CH4
emissions from landfills holds the greatest
potential for reducing greenhouse gas emissions
in the waste-management context.
14
3 MBWT Reference Material and Events
1 A PDF version of the guide is available in German, English and Spanish at www.gtz.de/MBA.
15
Sector Project MBWT - Final Report
To help estimate the initial investment costs and Numerous events dedicated to MBWT were held
the cost of operating an MBWT facility, a costing in Germany and in the partner countries in the
module based on a question-and-answer appro- course of the sector project. They included:
ach has been developed. It allows the user to
arrive at a cost estimate by entering the relevant 1. a workshop entitled Mechanisch-biologische
data appropriate to the local situation. The user Abfallbehandlung in Entwicklungsländern
should, of course, have some idea of how (mechanical-biological waste treatment in deve-
MBWT works, because the program includes loping countries) serving to help establish co-
multiple-choice questions about such matters as operative relationships with German facility ope-
procedural alternatives.2 rators, engineering companies, technology-
transfer organizations and academic institutions.
The costs to be taken into account are based on March 18, 1999, in Eschborn, Germany
empirical data gleaned from the German / Euro-
pean market. To find out what those costs 2. a sectoral forum entitled Mechanisch-biologi-
would amount to in one's own country, the user sche Abfallbehandlung in Entwicklungsländern
has to estimate and enter a correction factor to (mechanical-biological waste treatment in deve-
account for, say, the cost of importing the requi- loping countries) held in cooperation with Kno-
site mechanical equipment (customs, cost of ten Weimar, dealing with methods of mechani-
transportation, ...). Naturally, the cost of con- cal-biological waste treatment, as employed
struction must be based on local wage levels. under circumstances specific to developing
The program was designed for application to countries. July 22/23, 1999, in Eschborn, Ger-
facilities with throughputs of 20,000 Mg/a and many
higher. Sizing of the biological treatment stage
assumes as its treatment target that the biologi- 3. a training course in mechanical-biological
cal activity of the treated material will amount to waste treatment for Thai specialists representing
approximately one quarter of that of fresh mate- municipal authorities, held in cooperation with
rial. While this does not correspond to Ger- the Technical Cooperation Project "Solid Waste
many's stringent requirements for the disposal Management Programme for Phitsanulok". Sep-
of biologically pretreated waste, it does hold the tember 1/8, 1999, in Germany
promise of substantial improvements with regard
to emissions and landfilling space require- 4. a workshop on mechanical-biological waste
ments. treatment for Brazilian communities and univer-
sities, held in cooperation with "Wilhelm Faber
The program provides an initial overview of the GmbH" and Prefeitura Municipal de São Se-
costs to be expected for various alternative vari- bastião. December 6/7, 1999, in São Sebastião,
ants. However, detailed planning with due allow- Brazil
ance for the local framework conditions is
necessary for reliable costing.
2 This information can be found, inter alia, in the aforementioned decision-maker's guide.
16
5. a workshop for recycling and waste-sorting The partners participating in the pilot projects
cooperatives, held in cooperation with Prefeitura held additional training / information events and
Municipal de São Sebastião. September 23/26, seminars for their local specialists. Documenta-
2000, in São Sebastião, Brazil. tion of the aforementioned events is available via
the sector project's own documentation and the
6. a workshop and training event entitled "Pilot website www.gtz.de/MBA.
Project on Waste Management in Atlacomulco",
sponsored by Wilhelm Faber GmbH for the City
of Atlacomulco and other Mexican communities.
September 2002, in Atlacomulco, Mexico.
17
Sector Project MBWT - Final Report
Firstly, a trial decomposing heap based on the Figure 7: Mechanical-biological waste treatment using the
FABER-AMBRA® process in São Sebastião
FABER-AMBRA® process was established and
studied in Rio de Janeiro. Then, in May 2000, a
six-month trial commenced in São Sebastião.
The trial was attended and evaluated both by
Wilhelm Faber GmbH and by independent
experts from GTZ. Some minor adjustments
were made in the process to accommodate
local factors, with a bearing on, for example,
homogenization and moisturizing of the waste
18
4.1.2 Pilot project in Phitsanulok, Thailand
In November 2001 a pilot project at the Phit- ted optimizing measures during the rainy season
sanulok municipal landfill was commenced on too. Completion of the trial-operation phase will
the basis of a GTZ-commissioned feasibility stu- be followed by negotiations regarding continua-
dy produced in 1999 on the suitability of mecha- tion of the process and its implementation into
nical-biological waste treatment for the city. The the local waste management system.
purpose of this experiment was to demonstrate
that the FABER-AMBRA® process can also be
successfully applied in cases involving very
moist, weakly structured waste materials contai-
ning large amounts of plastics. Another goal was
to clarify the extent to which high rates of preci-
pitation during the rainy season would cause
problems with the open-air decomposing heaps.
The project was conducted in cooperation with
the City of Phitsanulok and with the support of
the Technical Cooperation project "Thai-German
Solid Waste Management Programme for Phit-
sanulok."
19
Sector Project MBWT - Final Report
Considering the composition of the waste, the The properties of compost are heavily depen-
pedological situation and the economic context, dent on both the nature of the inputs and the
together with the country's dependence on composting process. Pretreatment (separate
imported fertilizers, the generation of compost collection and/or removal of disturbants, un-
from waste makes economic sense in Syria, and wanted materials and - optionally - recyclables,
is not unknown there. However, since the con- comminution, etc.) and the composting condi-
ventional method of composting the aggregate tions therefore had to be selected to produce
waste input had proved unable to yield compost composts of defined quality for defined purpo-
of the required quality and environmental safety, ses, and to enable sustained achievement of the
a mechanical-biological waste treatment con- requisite quality parameters. For example, diffe-
cept was applied in an attempt to stabilize the rent windrows were built up of summer waste
residual waste while obtaining a high-quality and winter waste, the compositions of which dif-
compost fraction, and hence reducing the ulti- fer considerably. All in all, approximately 220 Mg
mate amounts of waste destined for the landfill. of waste from garbage collection in Al-Salamieh
Unlike other pilot-scale field trials, in which pre - was employed in the experiment. In addition to
treatment is intended to improve the disposal the common-landfill variant as the reference
situation, the Al-Salamieh experiment focused embodiment, three windrows composed of
on obtaining a good soil conditioner. The main mixed, coarsely presorted household waste and
objectives of the experiment were: separately collected biowaste were investigated.
1. to demonstrate and explain different process- The waste was piled up in pressure-ventilated
technological variants for MBWT and compost windrows of trapezoidal cross section. To keep
production by comparison with currently the windrows from drying out, and in order to
employed concepts, minimize the odor nuisance, the heaps were
covered with a semi-permeable tarpaulin.
2. to portray the general legal situation regarding
the operation of an MBWT facility and the use of
the subfractions obtained,
20
The experiments demonstrated the suitability of 4.1.4 Other projects
the procedural approach employed for MBWT
and hence for the production of high-quality In addition to the aforementioned projects,
compost. With regard to the quality of the matu- which focus on the field-testing of MBWT, the
re compost, the study also illuminated the sector project also provided support to various
importance of either collecting biowaste separa- other projects of similar thrust.
tely or subjecting it to a similarly oriented form
of pretreatment.
Pilot project in Atlacomulco, Mexico
A large-scale pilot project based on the results
of this model experiment is presently in prepara- The purpose of this project is to introduce an
tion for validating and adjusting the process. integrated, sustainably safe and reliable form of
The goal is to build and operate an MBWT facili- waste management with integration of the infor-
ty in Al-Salamieh with a capacity of 15,000 - mal sector. To this end a waste-sector training
20,000 Mg/a. Appropriate technical and politi- and upgrading program is being implemented in
cal-institutional embodiment measures are being the City of Atlacomulco and its surrounding
provided to ensure the long-term efficiency of communities. The training and upgrading pro-
the MBWT facility. GTZ will help finance and gram consists of three components:
implement the training and upgrading measures
for the various target groups, the production of composting,
training and reference materials, the promotion sorting of recyclables and management of a
of public awareness, and the provision of con- microenterprise (Microempresa),
tacts in Syria. The firm W. L. Gore will be treatment of waste inputs according to the
responsible for building and operating the waste MBWT process.
treatment plant, for coordinating the various
parts of the system, and for adapting them opti- The overall concept envisages the coupling of
mally to the local situation. The entire measure composting, recovery of recyclables, and MBWT
will enjoy the scientific backstopping of the Uni- (using the FABER-AMBRA® process). The inten-
versity of Kassel, Waste Technology Faculty. tion is to implement an ecologically optimized
scheme that will simultaneously make an impor-
tant contribution to poverty reduction. Until now,
most salvaging has been done by the informal
sector (waste pickers = Pepenadores). The com-
posting, recycling and sale of compost and
secondary raw materials will substantially impro-
ve the latter's income situation.
21
Sector Project MBWT - Final Report
Promotion of ecologically sound waste manage- 4.2 Results and Experience Gathered
ment in Colombia from Pilot Projects
The waste management engineering consultants The essential results of the pilot projects are
Ingenieurbüro für innovative Abfallwirtschaft (ia) discussed below, with special attention given to
GmbH, in cooperation with B.A.U.M. TRACOM the projects in São Sebastião, Brazil; Al-Sala-
Ltda, in Bogotá, and with GTZ, have implemen- mieh, Syria; and Phitsanulok, Thailand. These
ted a pilot project in Armenia (capital of Quindío pilot projects have either already been comple-
Department, Colombia) for introducing an inte- ted, or soon will be, and they have yielded volu-
grated approach to sustainable development via minous data. The pilot projects in Phitsanulok
theory and practical training in the areas of and São Sebastião come close to normal opera-
"integrated waste management" and "sustain- tion in terms of their quantitative throughput3
able waste management". The project objectives and equipment endowment, so the results are
were to establish a technical college and to reliable with regard to costs and the use of
plan, build and operate a model MBWT facility machinery. The model experiment in Al-Sala-
with a practical training mandate. mieh involved relatively small amounts of waste,
so its results do not necessarily apply uncondi-
After sorting and screening, the material is tionally to normal operation as far as costs and
homogenized in a mixing drum and then com - the use of machinery are concerned. On the
posted in bamboo composting bins. The project other hand, the model project in Al-Salamieh
also qualified trainers for turning out future spe- enjoyed very intensive scientific backstopping,
cialists. A further focal point of the project was and the data yield is accordingly voluminous.
to compile the experience gained and make it
available to interested parties across South
America via the internet portal "Foro-Z", the
waste-management knowledge portal for Latin
America" (www.foro-z.com). The project has
been completed, and further cooperation and
the development of additional projects within the
region are planned.
3 In Sao Sebastiao, all waste arriving at the landfill is now pretreated. In Phitsanulok, approximately 30 % of the waste arriving at the landfill undergoes
pretreatment in connection with the pilot project.
22
4.2.1 Project preparation
70
to assess the chances and risks of the pro-
cess employed in the project area. 60
40
The experience gained in the pilot projects
Post-decomposition phase
Pre-decomposition-phase
23
Sector Project MBWT - Final Report
Gas evolution
Aerobic decomposition is a process in which Frequency Meas. point
Input Dayly Weekly Monthly Quar- Output On Site Lab
oxygen-dependent microorganisms break down terly
Visual inspection
organic substance. The process liberates carbon -
Ambient temperature
the resultant fermentation becomes recognizable -
Precipitation -
by the generation of methane. Consequently, by
-
methane levels in the heap, the operator can tell Carbon dioxide -
Oxygen
whether or not it is getting enough oxygen, how -
Nitrogen -
well the gases resulting from the biological pro- Methane -
TOC (eluate)
Solids analysis Respiration activity (AT 4)
Process water
(AT 4). -
Quantity
Conductivity -
pH -
BOD5 -
COD -
4.2.2.2 Implementation via pilot projects * German directive governing the ecologically viable disposal of municipal solid waste
24
In addition, numerous other data of importance The results of the pilot projects show that the
for evaluating the process and for further plan- locally available resources do not suffice for
ning purposes were collected, e.g.: conducting the tests that are necessary for
assessing the progress and results of the
mass/bulk and volume analyses decomposition process. The specific standards
process water quantification and facilities required for the performance of
equipment operation and downtime waste analyses are largely lacking in the coun-
personnel working hours tries in question. The analysis of solid waste, for
operational resource requirements example, is very complicated and can only be
performed by specialized laboratories. Conse-
quently, most of the pretreated waste from the
The most important data were published in the pilot projects was analyzed in Germany.
experts' reports and can be accessed, inter
alia, via the GTZ MBWT website
www.gtz.de/MBA/English/index.html.
25
Sector Project MBWT - Final Report
4.2.3.1 Technology selection criteria Hence as far as possible, MBWT projects should
be implemented in a manner to promote better
Experience shows that caution is of the essence working conditions for these people, and not to
for transferring waste treatment technologies rob them of their basis of subsistence. Another
from Germany to developing and threshold essential criterion is that the technology employ-
countries. In the past, imported technologies ed must be affordable. This requirement sub-
have often worked well only as long as they had stantially diminishes the range of potential pro-
the benefit of external technical support. There cesses. In Phitsanulok, for example, the charac-
are various reasons for this, and they apply not teristics of the waste (high water content, little
only to financial aspects, but to legal, organiza- structural material, large share of waste in pla-
tional and cultural factors as well. First of all, the stic bags) made it appear expedient to employ a
basic tenets of development cooperation in the rather complex process technology (e.g. inclu-
area of waste management - such as those des- ding fermentation of residual waste). On the
cribed in the BMZ sector concept for waste other hand, the boundary conditions still prevai-
management [4] - must be adhered to. For ling in Phitsanulok made it unlikely that such a
example, technologies must be selected in con- costly approach would be successful with
sideration of the fact that, for many people in regard to the financial and technological sustai-
many countries, waste-picking is the sole avai- nability of waste management. Consequently,
lable means of making a livelihood. the only technologies with a potential for suc-
cess were those that would allow the targeted
waste treatment objectives to be achieved with
26
4.2.3.2 The Al-Salamieh scale-model trial
The following approach to mechanical-biological and to drain off the resultant press water and
treatment and composting of inputs amounting leachate) are needed to set up the heaps. The
to 15,000 Mg/a was developed on the basis of finished heaps are then covered with a semi-
the scale-model trial: permeable tarpaulin and pressure-ventilated.
Input
At first, the waste is collected in the normal
manner (mixed collection) and delivered to the
waste treatment site. Eventually the biowaste is
to be collected separately.
Waste comminution
For successful biological treatment, the collec-
ted waste first has to be removed from the pla-
stic bags. To this end a special comminutor
(homogenizing drum), which is to be built in
Syria, is needed to rip open the bags in such a
manner that the recyclables are not rendered
useless or irretrievable by excessively destructi-
ve handling.
Sorting Figure 14: Compost heaps during the model experiment in Al-Salamieh
After the bags are ripped open, the recyclables Compost recovery
and the disruptive materials (disturbants and At the end of a 14-week composting process
unwanted materials) have to be sorted out by the material is comminuted once again and
hand. Judging by the waste composition already screened to a size of 20 mm. Here, too, a wheel
ascertained, it should be possible to recover loader (or a grab excavator) is needed for fee-
approximately 150 Mg of scrap metal and 100 ding the compost into the appropriate comminu-
Mg of used glass per year as secondary raw tors.
materials. That corresponds to roughly 1 % of
the total input. Theoretically, this would yield Landfilling
revenues amounting to some PS 1 million The oversized material is dumped at the landfill.
(approx. EUR 20,000) per annum. Removal of the recyclables, in combination with
the decomposition of organic substance, redu-
Piling and operation of the compost heaps ces the volume and weight of the original waste.
Following mechanical conditioning, the material This saves space at the landfill and is therefore
to be composted is piled into heaps with the aid highly desirable.
of a wheel loader. Suitably reinforced (concreted)
composting areas with integrated ventilating
ducts (possibly in the form of channels in the
concrete to accommodate flexible vent pipes
27
Sector Project MBWT - Final Report
Homogenizing
Further mechanical conditioning of the waste
takes place in a mobile homogenizing drum that
Faber built especially for this purpose.
28
The vent pipes are laid out approximately 4 m uniform heat-soaking of the heaps thanks to
apart. The heaps are piled between 1.80 and the insulating effect of the cover,
2.50 m high 5, depending on the nature and reduction of odors escaping from the heaps
structure of the waste. Regarding the space with the vented air,
requirement for the heaps, roughly 1 m² per ton achievement of a more uniform distribution
of waste input can be taken as a rule of thumb of moisture,
for calculation purposes. If the heaps are torn partial decomposition of organic carbon
down before the scheduled end of biological tre- compounds in the biofilter,
atment, the organic fraction will not have time to better optical appearance of the compost
undergo full biological decomposition. heaps,
provision of a vermin barrier.
5 Both in Phitsanulok and in Sao Sebastiao, the heap heights were reduced to improve the supply of oxygen.
29
Sector Project MBWT - Final Report
30
Al-Salamieh extent to which the finished items of equipment
The process concept also worked well in Al- actually meet the set requirements, remains to
Salamieh. The decomposition process and its be seen. In Brazil, options for local manufacture
results are in line with expectations. Covering of a homogenizing drum are being explored.
the heaps with an air-permeable membrane
made it possible to dispense with supplemen-
tary moisturizing of the heaps. While this does 4.2.4 Operation of an MBWT facility
make the process somewhat more complex
than the FABER-AMBRA® process, it also offers Extensive MBWT processes are characterized
advantages for applications in arid climates as by the use of "simple" technology. However, that
well as in areas with abundant precipitation. In does not mean that such processes are "simple"
Al-Salamieh it is planned to integrate the field- to control. On the contrary. It is probably more
tested process into normal operation. However, difficult to create optimal conditions for the bio-
the requisite equipment will have to be locally logical degradation of organic material in an
redesigned. uncomplicated, extensive process than it would
be in a more intricate, intensive one. For exam-
ple, in any country where composting and other
Provision of special-purpose equipment for comparable techniques are not widely dissemi-
waste treatment nated, it takes time to build up the requisite
No special waste-treatment equipment - waste know-how. Hence one major constituent of all
comminutors, homogenizing drums, screeners, pilot projects was to provide training for the
etc. - is to be found in any of the project coun- local personnel.
tries. That, of course, means that such equip-
ment either has to be imported or fabricated
locally as one-off items. For imported equip-
ment, proper maintenance and spare-parts pro-
curement must be assured for the long term,
and any locally fabricated equipment has to
meet certain quality standards with regard to
corrosion resistance, mechanical strength, etc.
Within the scope of the pilot projects it was not
possible to determine the extent to which local
fabrication of low-cost equipment meeting these
quality standards could actually be realized.
31
Sector Project MBWT - Final Report
For an MBWT process to achieve good results, Both in São Sebastião and in Phitsanulok, Faber
it must be managed with due competence and not only provided technical support for the
commitment. In addition to normal managerial MBWT facility, but also trained the local workfor-
and leadership skills, the operator must also ce. During the first months of the project, Faber
have the experience needed to optimally control personnel were in constant attendance. That
a biological decomposition process. The per- was also the time frame of the intensive training
sonnel needed for the other work must have phase for the workers. In both pilot projects, the
qualifications comparable to those of civil- per-sonnel were hired by the municipal authori-
engineering workers (e.g. shovel men, truck dri- ties. Their theory-based training encompassed
vers, mechanics). explanations of the mechanical and biological
steps of the process and of the various machi-
nes, but their actual practical training took place
directly at the landfill with the MBWT in opera-
Job scope Personnel requirement
tion. The engineers and political decisionmakers
Main season Off season involved were invited to attend information
(4 months) (8 months)
Laborers 6 4
Total 18 10
Table 4: Personnel requirements for MBWT opera -
tions in São Sebastião (throughput: 30,000 Mg/a)
3rd backstopping phase 6 months twice monthly, Nov. 6 - Apr. 30, 2001
32
4.2.4.3 Integration into the organizational
structures
In developing and threshold countries, it is rat- The findings show that the existing structures
her an exception to the rule to encounter well- and the available personnel suffice only for low-
qualified, well-motivated personnel working at quality operation of MBWT facilities. Numerous
landfills. Consequently, it is not only necessary problems were encountered, including frequent
to teach the local staff how to operate the cases of people not showing up for work, orga-
MBWT facility, it is also necessary to establish nizational deficits (lack of pallets or other resour-
better-paying job slots for better-qualified per- ces), defective vehicles, and the pulling of per-
sonnel. sonnel for other assignments. Both in São Seba-
On the administrative side, the prerequisites for stião and in Phitsanulok, the early phase of ope-
effective, controlled operation of the landfills and ration therefore achieved only 30 - 40 % of the
MBWT facilities must be established. This inclu- theoretically possible throughput.
des on the one hand proper organization of the
operation (responsibilities, assignments, material
procurement, budgeting), and on the other hand
performance control.
60
40
30
20
10
0
September October
Date 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Day of week W T F S S M T W T F S S M T W T F S S M T W T F
Wheel loader*
Excavator*
Rotary drum*
Veh. operator**
Laborer**
*defective Machine ** absent personnel half day full day
Figure 19: Theoretically achievable and actu-
al throughput at the MBWT facility of the
Phitsanulok pilot project
33
Sector Project MBWT - Final Report
Considering the given structures and the organi- 4.2.5 Chronology and results of aerobic
zational problems encountered in São Sebastião decomposition
and Phitsanulok, further operation of the MBWT
facility by the local staff with no outside help fol- Biological decomposition of the organic con-
lowing completion of the pilot phase would have tents of the waste input is the central step of the
been inconceivable. MBWT process. Since there is no way to control
the processes of decomposition directly in the
In the meantime, operation of the MBWT facility course of aerobic waste treatment, various para-
and landfill in São Sebastião has been priva- meters are used to describe its progress (cf.
tized. Faber has contracted to provide all the Chapter 4.2.2). The results of aerobic decompo-
requisite special-purpose operating equipment sition in the pilot projects are discussed below
and to remain available for providing follow-up on the basis of these parameters.
assistance and controlling functions. Privatiza-
tion has had positive effects on the MBWT facili-
ty's operation, because the economic incentive 4.2.5.1 Time history of in-heap
gives the operator more reason to be interested temperatures
in efficiency than the previous municipal
employees were. The workers are at home in In all pilot projects, the temperature inside the
their jobs now and appear to be very well moti- heap was continuously monitored at various
vated. Indeed, the clear-cut allocation of respon- points. During the most intensive phase of orga-
sibilities and the designation of supervisory per- nic decomposition, the in-heap temperature
sonnel have significantly improved the operatio- should be situated between 55°C and 70°C. If
nal organization. Impediments such as a lack of the temperature drops below 50°C for any con-
operational resources or having the city's landfill siderable length of time during the first phase of
personnel fail to show up for work due to orga- decomposition, something is probably slowing
nizational or motivational problems no longer down or disrupting the processes of decay. Low
occur. Moreover, the manager of the operating temperatures during the initial phase may also
company has professed an interest in introdu- indicate excessive moisture (and the possible
cing MBWT for other waste projects as well. resultant occurrence of anaerobic processes).
This concept appears to be ensuring the suc- As time passes, the in-heap temperature gradu-
cess of MBWT's sustainable implementation in ally declines, as shown in the following diagram,
São Sebastião. which exemplifies the time history of temperatu-
re in all decomposing heaps of the Al-Salamieh
field test in Syria.
34
Time history of temperatures in all heaps as a function of decomposing time, in Al-Salamieh, Syria
80
70
60
50
40
30
20
10
0
0 10 20 30 40 50 60 70 80 90 100
Time (days)
Figure 20: Time history of in-heap temperatures in the Al-Salamieh scale-model trial
90
T1 T2 T3 Umgebung
80
70
60
50
40
30
20
10
0
Jan Feb Mar April May Juni Juli Aug Sep Oct Nov
2001
35
Sector Project MBWT - Final Report
80
Precipitation (mm/week)
300
Precipitation Temp. 2s, 0,8m
Temp. 2l, 1,2m Temp. Air
70 250
60 200
50 150
30 50
20 0
1 2 3 4 5 6 7 8 9 10 11 12 13 1 4 15 16 17 18 1 9 20 21 22 23 2 4 25 26 27 28 2 9 30 31 32 33
Process duration [weeks]
Figure 22: Time history of temperatures in a FABER-AMBRA® heap exposed to heavy precipitation
The in-heap temperature is seen to drop precipi- put less water in the homogenizing drum
tously with the onset of heavy rains in early Sep- ensure good off-flow of process water from
tember, while the light rains before that time had the heaps by paving the biotreatment area
no detectable effect on the temperature. Begin- and providing adequate slope (at least 3 %)
ning around mid-September, the temperature choose the pallets for the ventilating course
rises slowly but surely until more heavy rains in with care as regards quality and durability
late October again quench the heap. After that, reduce the height of the heaps
the temperature recovers again, rising to bet- apply a thicker layer of biofilter material
ween 55°C and 60°C, which corresponds well to
the age of the heap. During the month of Oct-
ober, samples were taken from the heaps for The use of different geotextiles for covering the
use as specimens in determining the heaps' bio- heaps during the rainy season is presently being
logical efficiency. The samples display high moi- investigated.
sture contents ranging between 55 % by weight
and 62 % by weight. Various ways and means
of keeping the heaps from becoming waterlog-
ged were considered and developed:
36
4.2.5.3 Gas composition
The composition of the biogas that is being If the oxygen concentration drops below the
generated within the heap can provide informa- aforementioned 10 % by volume, and if the CO2
tion on the quality of the composting process concentration rises significantly above 10 % by
and on any disturbances which may be affecting volume at the same time, either the heap is not
it. First of all, aerobic decomposition is highly getting enough fresh air, or the off-gas is not
dependent on an adequate supply of atmos- escaping as well as it should. If the methane
pheric oxygen. In an ideal case, the oxygen con- concentration is also higher than normal for any
centration within the heap should amount to at considerable length of time, the aerobic decom-
least 10 % by volume. As the microorganisms position processes are apparently disturbed.
digest the organic matter, they respire oxygen The following illustration visualizes the relation-
into carbon dioxide. Accordingly, the CO2 con- ship between oxygen content and CO 2 concen-
centration within the heap increases markedly tration in the light of selected readings from
and may even reach levels of the order of 10 % Phitsanulok.
by volume. Methane is an indicator of anaerobic
decomposition processes and has been identi-
fied as a climaterelevant gas. In a well-functio-
ning windrow, the methane concentration should
remain at roughly 1 % by volume most of the
time, though short-lived higher concentrations
may occasionally occur.
25
O2, MP 1 CO 2 , MP 1
O2, MP 2 CO 2 , MP 2
20
15
10
0
0 5 10 15 20 25
Biological treatment time [weeks]
Figure 23: Relationship between oxygen content and carbon dioxide concentration
37
Sector Project MBWT - Final Report
The diagram clearly shows how any increase in Visual inspection of the heaps revealed that the
the CO2 concentration is accompanied by a points in question were very wet and fairly
corresponding decrease in the oxygen concen- blackened. These were points at which the pal-
tration. Whenever the O2 concentration drops lets had broken, and the bottoms of the heaps
below 5 % by volume, the CO2 level increases were standing in water.
markedly. Conversely, the CO 2 level drops
below 5 % by volume as soon as the oxygen
content rises above 15 % by volume.
38
Composition of gas in heaps C and D in Phitsanulok, Thailand
Samples drawn Feb. 13, 2003
Gas concentration [vol.%]
20
O2 CO 2 CH 4
18
16
14
12
10
0
C2 C3 C4 C5 D1 D2 D3 D4 D5
Heap on old landfill Reinforced composting area with adequate
slope and pallet checks
The relevant evolution of methane may be attri- In Brazil, too, elevated methane concentrations
butable to any of the following factors: were noted at the beginning of the decomposi-
tion process. However, this was attributed to
During the rainy season, the high initial methane emissions from the old landfill, on top
moisture level coupled with heavy precipi- of which the heaps were standing. In the further
tation causes partial waterlogging of the course of process implementation, there were
heap and, hence, formation of anaerobic no more indications of elevated methane con-
zones. centrations (odor, visual inspection, ...).
Sloppily installed, perhaps already broken, In Syria, oxygen concentration readings indica-
pallets of poor quality allow waste to block ted that the inferior structural properties of the
off the ventilating course and interrupt the waste might cause a shortage of oxygen. To
supply of air. verify this, the plastic bags were removed from
some of the waste, and the heaps' oxygen-sup-
If the ground is not adequately reinforced ply situation was seen to improve substantially.
and becomes muddied by process water It was also recommended that extra structural
and rainwater, the pallets will sink in and cut material be mixed into the waste in order to
off the supply of air. promote better aeration.
39
Sector Project MBWT - Final Report
The water balance of the heaps is also an Evaluating the biological efficiency of the
important criterion for optimal decomposition. decomposition process necessitates an analysis
On the one hand, the microorganisms need of the residual solids and eluate in the digested
water for their metabolic processes, but on the material. This includes determining its total orga-
other hand high water contents promote the for- nic content (TOC) and its biological activity
mation of anaerobic cells as soon as the excess (dynamic respiration activity level, AT 4, and gas
water cannot be drained out of the heap. Hence formation rate, GB21) in order to characterize
for the duration of the decomposition process, the remaining active organic substance. Analysis
the water content must be maintained within a of the pollutants, e.g. of heavy metals and or-
range that is amenable to aerobic decomposi- ganochlorine compounds in the eluate from the
tion. Consequently outdoor heaps have to be solids, can provide information on the remaining
watered during dry periods, but process water pollutant inventory, and hence on how much
can dribble out of the heaps during periods of pollution could result from emplacement of the
heavy rainfall. (The reader is referred to Chapter decomposed material.
4.2.6.4 with regard to the incidence and compo-
sition of process water.) The pilot project included various analyses of
solids and eluates. The following table compares
In Germany, initial water contents of 40 - 55 the results of the FABER-AMBRA® process in
wt.% are regarded as favorable for extensive Brazil after six months and after nine months of
decomposition processes. The water-retaining biotreatment with the correlative values stated in
capacity of the waste material is a relevant para- Germany's waste disposal directive on mechani-
meter. Since the starting material normally con- cal-biological waste treatment facilities (AbfAblV,
tains relatively little water, an appropriate App. 2), which must be adhered to in Germany
amount is added at the beginning of biological for proper landfilling of such material.
treatment. In the pilot project, however, the star-
ting material contained more water, because it
consisted largely of organic substances.
40
Solids analysis Sample of Sample of Correlation value
6-month-old comp. 9-month-old comp. (AbfAblV*, App. 2)
Ignition loss [wt. % TS] 23,8 27,7 -
BOD5 [mg/l] 5 6 -
The results show that six months suffice for 4.2.5.6 Results of composting trials in
most of the organic substance to decompose, Al-Salamieh, Syria
and that after nine months, the requirements of
Germany's waste disposal directive are reliably The Al-Salamieh field trials included broad-scale
satisfied. While some initial data on the results tests and investigations on the treatment of
of decomposition have been gathered in Phit- various input materials. In addition to the
sanulok, the findings indicate that the biological mechanical-biological treatment of waste inputs,
activity can be expected to decline significantly the trials were also intended to investigate the
in the course of the process. Biotreatment-out- suitability of the process for producing market-
put analyses are under way. able compost. Both pure household waste and
separately collected and sorted biowaste were
test-composted.
6 The laboratory analyses were conducted by the Leichtweiss Institute for Hydraulic Engineering at the Technical University of Braunschweig.
41
Sector Project MBWT - Final Report
The compost substrates obtained via the In addition to documenting the suitability of the
various forms of treatment all display good qua- process approach applied for mechanical-biolo-
lity in terms of such value-defining physical and gical waste treatment and obtaining high-quality
chemical parameters as their nutrient contents, compost, the results also illuminate the benefits,
salinity, pH and total organic content. However, with respect to the quality of the finished com -
the benefits of collecting biowaste separately post, of either collecting biowaste separately or
are reflected by the significantly lower heavy pretreating the waste in a manner to achieve
metal contents of the output. similar results. Accordingly, the separate collec-
tion of biowaste would provide much-improved
conditions for an effective, more inexpensive
form of waste aftercare. However, the separate
collection of good-quality biowaste would most
likely have to be implemented on a step-by-step
basis and be correspondingly expensive.
Nickel mg/kg 56 53 32 34 49 26 50 50 70
Mercury mg/kg 2,3 2,1 1,90 1,90 2,10 0,89 1,00 1,50 3,00
Zinc mg/kg 456 446 201 214 324 159 400 350 500
42
4.2.6 Emissions from MBWT
43
Sector Project MBWT - Final Report
4.2.6.2 Odors
None of the pilot projects included any olfacto- Assuming that the decomposition process is
metric investigations as a basis for assessing functioning properly, no annoying odor emis-
the odor situation. Nevertheless, both for the sions need be feared in connection with turning
waste treatment process itself and for subse- or tearing down the heaps, or from emplacing
quent landfilling of the residual waste, there can the pretreated waste at the landfill. The hoped-
be no doubt that the odor emissions are much for improvement in the odor situation at the
lower than if the untreated waste had simply landfill thanks to waste pretreatment can gene-
been dumped. rally be considered to have been fully achieved.
44
For the first few days after the heaps are put up,
they may release what is referred to as water of
consolidation. In Al-Salamieh, the water regi-
mens of the various heaps were monitored and
analyzed in the course of the composting pro-
cess. Thanks to the cover, the only process
water to appear was this water of consolidation,
i.e. some 4 - 6 l of process water per Mg waste
emerged from the covered heaps during the first
few days of the process. Table 9, below, shows
the composition of the process water.
pH - 7,4 6,8
COD mg/l 36.780 24.750
BOD 5 mg/l 12.230 6.580
This process water is so polluted, that the base In São Sebastião, the process water emerging
of the biotreatment area will need a liner. Co- from a commercial-scale test heap (230 m²) was
vered and indoor heaps produce so little pro- monitored with regard to quality and quantity.
cess water during the decomposition process The heap was put up on a specially sealed field.
that there is no problem in collecting and retur-
ning.
45
Sector Project MBWT - Final Report
Sediment washout had very detrimental effects Process water began to emerge from the heap
on the operability of the analytical setup, so the about 2 days after the first rain. In the case
results of quantitative monitoring are only relia- under review, some 30 % of the overall precipi-
ble for the very brief period between May 15 tation eventually reappeared in the form of pro-
and June 3, 2001. Some 98 l/m² of rain fell cess water.
during that period. Projected over the full area,
that results in 22,540 l of rainfall, while 7,245 l of The quality of the process water from the test
process water emerged from the test heap. heaps in Rio de Janeiro and São Sebastião was
Figure 28 illustrates the course of the cumulative monitored over a prolonged period of time. Figu-
curves over the period in question. re 29 reflects the results of analysis.
25.000
Volume (l)
20.000
15.000
10.000
5.000
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
Time (d)
Figure 28: Cumulative curves showing the precipitation onto and the process
water volume emerging from the test heap in São Sebastião
46
Rio de Janeiro and Sao Sebastiao pilot projects
Process water burden
65.000
mg/l
COD Rio
60.000
BOD 5 Rio
55.000
COD Sao Sebastiao
50.000
BOD 5 Sao Sebastiao
45.000
40.000
35.000
30.000
25.000
20.000
15.000
10.000
5.000
0
0 50 100 150 200 250 300 350 400 450
Treatment time (d)
Figure 29: Quality of process water from test heaps in Rio de Janeiro and São Sebastião
These results show that, during the first four Both in São Sebastião and in Phitsanulok, the
months of biological treatment, the process accumulated process water is used for watering
water burden remains at levels that do not per- the heaps during dry spells. It is assumed in São
mit its infiltration into the ground or its discharge Sebastião that approximately one-half of the
into an effluent stream. After that, the process incidental process water can be reused. The
water burden gradually decreases, but never to remainder requires wastewater treatment.
the point of negligibility any time before the end
of biological treatment. Consequently, the
decomposition process should always take pla-
ce on sealed surfaces.
Figure 30: Process water seeping out from the base of a heap in São Sebastião
47
Sector Project MBWT - Final Report
48
Consequently, the situation in and around the Firstly, the readily degradable components
landfill can be expected to improve in the follo- decompose within a relatively short time,
wing ways: while the substances that are more difficult
to break down become more concentrated
Less waste for ultimate disposal as the process progresses and the degrada-
The combination of biological degradation of tion rate slows down. Once biodegradation
organic substance and possible extraction of of the easily degradable substances is com -
certain material varieties at the mechanical plete, the total organic content will remain
conditioning stage markedly reduces the essentially unchanged up to the end of the
residual quantity of waste to be disposed of. process. Within certain limits, the loss of
The extent of the mass (or bulk) reduction mass can be manipulated by the process
taking place in the course of biological treat- engineering invested. The extent of mass
ment results from the decrease in water con- reduction is, as a rule, largely dependent on
tent and total solids. The weight reduction the length of the decomposition process and
resulting from the loss of water is the diffe- on the amount of work and material that was
rence between the water content of the invested in the waste treatment.
input material and that of the end product.
The decrease in total solids, in turn, Compaction
depends on how much organic substance Thanks to pretreatment, residual waste
(total organic solids) is degraded, and on its emplaced in thin layers can be compacted
percentage share in the total solids content. to a much higher in situ density than can
Biodegradation proceeds at different intensi- waste in conventional landfills, and the land-
ty levels, depending on which natural sub- fill body sustaining much less settling after-
stances predominate. ward. Figure 31 compares various densities
of compaction, as ascertained for different
forms of waste pretreatment in Germany.
Compact. density ρdry [t MS/m3] ρdry ρdry* [t TS/m3]
1,8
Absolute density of compaction (dry)
1,6 Relative density of compaction (dry) based on
1,56
1,4 waste bulk prior to treatment
Density of compaction (moist)
1,2 1,25
1,11 1,14
1,0 1,02
0,97
0,8 0,87
0,82
0,76 0,76
0,6 0,68 0,67 0,67
0,56 0,56
0,4
0,2
0
BS I BS II BS III BS IV WH V*
(Standard landfill) (Comminuted + (Comminuted, (Comminuted, (Comminuted,
thin layer) homogenized homogenized, homogenized,
* other landfill site + thin layer) decomposed decomposed
MS = moist substance + thin layer) + thin layer)
TS = total solids
Figure 31: Densities of compaction with and without pretreatment [6]
49
Sector Project MBWT - Final Report
50
In Phitsanulok, the loss of mass was determined
by weighing the waste input prior to mechanical
conditioning and after biological treatment. The
findings show that mechanical-biological waste
treatment reduced the moist mass by 53 %,
mainly in the form of lost water. At 19.2 %, the
organic decomposition rate is comparable to
data found in pertinent literature. The results
could probably be improved somewhat by opti-
mizing the MBWT processes beyond what was
achievable during the early phase of the Phit-
sanulok project. Figure 33 summarizes the
Figure 32: Emplacement of pretreated waste in São Sebastião
results.
The loss of mass (or bulk) due to Hand-sorted bio- Mixed, commin-
waste uted waste
aerobic decomposition and the
Duration of biotreatm. d 100 110
remaining mass of organic material
in the product of biotreatment were Input treatment % 100 100
water content of input % 58,5 57,1
investigated as part of the Al-Sala- TOC of input % 41,5 42,9
mieh field trials. The moist mass Output treatment % 38,9 34,5
was weighed at the beginning and water content of output % 10,5 10,0
TOC of output % 28,4 24,5
end of the composting process,
Loss of mass % 61,1 65,5
and the water content of lots weig-
Table 10: Mass reduction through biotreatment in the Al-Salamieh, Syria, scale-model trials
hing roughly 20 kg each was deter-
mined. The total organic content
was ascertained via the ignition loss.
Phitsanulok project
Mass reduction
1.600
Mass (Mg)
H 2O TS
1.400
53 % reduction MS
1.200
938
1.000
800
19 % reduction TS
600 211
400
577 465
200
0
Input to heaps A + B Output to heaps A + B
MS = moist substance Figure 33: Mass reduction in the pilot phase of MBWT in Phitsanulok
TS = total solids
51
Sector Project MBWT - Final Report
The main objective of landfilling is to make opti- waste treatment facility by means of the pre-exi-
mal use of the - expensive - available emplace- sting landfill compactor were run at the Phit-
ment volume. Consequently, commercial-scale sanulok landfill. The compactor in question
compaction tests designed to ascertain the weighs 20 tons and is 3 m wide. A test field
maximum achievable density of compaction for measuring 15 x 15 m was staked out on undis-
residual waste from a mechanical-biological turbed soil at the Phitsanulok landfill site.
15 m
Top of emplaced waste
Waste
Test- Formation level
15 m
field Formation
Turning area
Figure 34: Test-field dimensions for the commercial-scale compaction trial (Deutsche Gesell -
schaft für Geotechnik e.V., Recommendation E 24, as modified)
52
The waste to be emplaced was weighed, spread
out across the test field by an excavator in lay-
ers approximately 30 cm thick, with each layer
being compacted in five passes. A tachymeter
was used to determine the volume of the empla-
ced waste.
Phitsanulok project
1,2
(Mg/m3)
Dry density
Moist density
1,0
0,8
0,6
1,1
0,4 0,76
0,53
0,2
0,17
0
Heaps A + B Density of compaction
Figure 36: Comparison of in-heap densities and achieved landfill compaction densities
The Phitsanulok landfill's 20-ton compactor However, past experience in Germany and São
compressed the unscreened waste to an abso- Sebastião shows that the incorporation of pre-
lute density of 1.10 Mg MS/m³ or 0.76 Mg treated waste becomes increasingly difficult with
TS/m³. In Brazil, where a 30-ton compactor was increasing precipitation. As it absorbs water, the
used, compaction densities of 1.1 - 1.4 Mg/m³ waste becomes pasty and eventually impossible
were measured in application of the volume- to drive over or compact. If possible, then, no
replacement method. waste should be emplaced during rainy periods.
Of course, that would be very difficult to put into
The densities determined during the emplace- practice in regions with high precipitation rates.
ment trials were arrived at under dry weather There are various technical options for improving
conditions. The emplacement of pretreated the emplacement situation during rainy seasons,
waste is also unproblematic with regard to the but the scope of the pilot project did not allow
ground's load-carrying capacity and traver- their testing.
sability, as long as the weather stays dry.
53
Sector Project MBWT - Final Report
A landfill reserved for pretreated waste has been These investigations confirm expectations to the
in operation in São Sebastião since the fall of effect that pretreatment definitely improves the
2002. The leachate is collected and routinely quality of landfill leachate. However, long-term
sampled to keep tabs on the typical parameters studies would be necessary to arrive at any reli-
shown in Figure 37. able information on leachate incidence and
emburdenment.
2.200
mg/l
1.800
1st emplacement in July 2002 2nd emplacement in December 2002
1.600
1.400
1.200
1.000
800
600
400
200
0
07/23/02 08/22/02 09/21/02 10/21/02 11/20/02 12/20/02 01/19/03 02/18/03
Time
4.2.8 Costs
54
throughput-dependent operating costs re disposal system must be accounted for in any
(e.g. electricity, fuel, residual-waste dis- proper cost assessment. Only then can the
posal, etc.) additional costs of mechanical-biological waste
returns (e.g. proceeds from the sale of treatment be properly compared with and
recyclables) weighed against corresponding cost reductions,
particularly with regard to final disposal
Since there are so many variants to choose (cf. Chapter 4.2.8.3).
from, the cost of mechanical-biological waste
treatment can vary widely. Other specific-cost 4.2.8.2 Examples of costs incurred in
factors include the plant throughput rate (mean- the pilot projects
ing that the specific costs decline with increa-
sing throughput rate) and the capacity utilization The cost calculations for the pilot projects in
rate (meaning that the specific costs rise with Brazil and Thailand, as well as for the scale-
decreasing capacity utilization rate). However, model trial in Syria, are presented and discussed
these costs do not transfer readily from one below. The cost of waste treatment in Brazil can
country to the next, because: be determined fairly accurately, because the
project was of long duration, and normal opera-
the expenditures for personnel, construction tion has already commenced. The project in
and energy, in addition to the customs and Thailand is still in its pilot phase, so no complete
tax laws, vary widely from country to country sets of data are available, especially not for the
and from region to region, variable costs of operation. However, the same
country-specific standards for emission con- process with the same procedures and the
trol, wastewater purification, monitoring, same equipment can be employed for normal
etc., exert a major influence on costs, operations here, too. Moreover, the availability of
fluctuating exchange rates can alter the cost extensive pertinent analyses and calculating
of capital goods and operating supplies. models makes it possible to at least determine
the general orientation.
Hence the cost of personnel accounts for a lar-
ge percentage of the overall cost at extensive By reason of the differences in process techno-
facilities in countries with high wages. Conver- logy, the project in Syria is interesting for com-
sely, in countries with low labor costs, the per- parison purposes. However, the cost estimates
sonnel costs account for a much lower percen- for Syria are not unconditionally comparable
tage of the overall cost. At intensive facilities, with those of the other two projects because
the cost of labor accounts for a lower percenta- they are based on the experience drawn from
ge of the overall cost, while customs regulations and the assumptions made in the (220-ton) field
and conditions of supply and warranty are much trial. These same assumptions have not yet
more important. been verified in any large-scale field trial.
If the results of cost determination are to be reli- The basic prerequisites for calculating project
able, the boundary conditions of each concrete costs differ from case to case, sometimes sub-
case must also be taken into consideration. One stantially. For example, no interest rates were
should also keep in mind that considering the included in the calculations for Phitsanulok,
cost of waste treatment only could lead to erro- because that would have run counter to the nor-
neous conclusions. After all, mechanical-biologi- mal investment financing practices of Thai com -
cal waste treatment influences all the other munities.
aspects of waste management, too, so the enti-
55
Sector Project MBWT - Final Report
56
Thailand Syria
By reason of Thailand's public-sector invest- The postulated costs are in line with the
ment policy, no interest rates have to be data gathered in the course of the field trial.
accounted for, because all investments are They are not based on empirical data or on
directly financed. However, in the interest of figures deriving from actual operation of a
comparability, a 6 % capital interest rate plant. Consequently, these costs must be
was figured into the calculations. regarded as the minimal process costs wit-
hin the local context. Hence this project
The biotreatment area was prepared accor- does not lend itself well to comparison with
ding to a relatively elaborate technique cor- others. Especially with regard to operating
responding to the base of the landfill body. costs, no reliable information is available.
The cost of consumables, maintenance and Since the design of the plant is not yet com-
repairs can only be estimated, because the plete, the technical equipment has not yet
plant has not yet entered its regular opera- been outlined or sized. For purposes of
tion phase at nominal throughput. The esti- comparison, an equipment fleet consisting
mates were made on the basis of facts alre - of a homogenizing drum, a screener, a wheel
ady established. loader and a truck was postulated.
The treatment of process water has been Prices cited by local manufacturers were
integrated into the treatment of leachate, so assumed here as the cost of procurement
the cost of leachate treatment is accounted for a homogenizing drum and screener nee-
for here as a proportion of the overall invest- ded for conditioning the waste input. Consi-
ment costs. No operating cost data are avai- dering the empirical data collected in other
lable. projects, the suitability of the equipment,
and hence of its durability and depreciation
Watering is effected via a pump and sprink- expenses, are somewhat questionable.
ler system. Again, no operating cost data are
available. Thanks to the fact that the composting time
is shorter than for passively aerated heaps,
Under the present circumstances, the mate- the treatment area is correspondingly smal-
rial used for the biofilter is obtained free of ler.
cost, i.e. producers deliver it to the landfill
free of charge. The heaps require no watering.
57
Sector Project MBWT - Final Report
Pos. Project Sao Sebastiao, Brazil Phitsanulok, Thailand Al- Salamieh, Syria
Notes No plans for screening Operating costs indetermi- Costs roughly calculated
drum or comminution of nate for watering and lea- and only conditionally com-
green waste; no landfilling chate disposal parable; suitability of local
equipment requires further
study
Specific costs Specific costs Specific costs
Designation [€/Mg Input] [€/Mg Input] [€/Mg Input]
1. Investment costs 3,8 € 5,0 € 6,8 €
1.1 Buildings + infrastructure 0,4 € 2,4 € 0,1 €
1.2. Technical equipment 3,4 € 2,6 € 6,7 €
1.2.1. Comminution homogenization 1,9 € 1,4 € 0,2 €
1.2.2. Excav., wheel loader transport 1,5 € 0,9 € 2,1 €
1.2.3. Ventilation / cover / watering -- € 0,3 € 4,2 €
1.2.4. Leachate collection and treatment -- € ** 0,1 € 0,2 €
2. Wages and salaries 1,7 € 0,8 € 1,1 €
3. Maintenance and repair 2,2 € 1,6 € 2,8 €
4. Var. operating costs 7,1 € 3,3 € 1,1 €
4.1 Fuel/lubricants 2,4 € 0,7 € 1,0 €
4.2 Ventilation 1,0 € 2,6 € < 0,1 €
4.3 Watering 0,3 € -- € -- €
4.4 Biofilter/cover/seal 2,5 € -- € -- €
4.5 Leachate disposal 0,9 € -- € < 0,1 €
Total 15 € 11 € 12 €
58
The following assumptions were made in esti-
mating the existing uncertainties (margin of safe-
ty):
Phitsanulok
Since the MBWT facility is still in its pilot-scale
field trial phase (30 Mg/d), and since some of
the costs can only be estimated, a 20 % safety
allowance was added to the overall costs to
account for unforeseen items.
Al-Salamieh
Cost basis: comminution / homogenization
at German rates (EUR 175,000 instead of
EUR 25,000 for the homogenizing drum and
rotary screener)
Additional personnel required (+25%)
Higher fuel / energy consumption (+25%)
14 4€
12 2€
7€ 1€
10
3€ 3€
8
1€
2€ 2€
6
1€
2€
4 7€
5€
2 4€
0
São Sebastião , Brazil Phitsanulok, Thailand Al-Salamieh, Syria
59
Sector Project MBWT - Final Report
When interpreting the above figures it is impor- 4.2.8.3 Effects of MBWT on the cost of
tant to keep in mind that the Al-Salamieh project waste disposal
is not directly comparable with the other pro-
jects, because the plant is still at the planning The MBWT costs described above in Chapter
phase and no practical experience has been 4.2.8.2 at least partially offset the net cost of
gained to date. waste disposal. The cost-related effects of
MBWT were explained in Chapter 4.2.7. The
The various calculations yield overall costs of costs of the various residual-waste treatment
mutually similar proportions. The specific invest- alternatives were estimated within the scope of
ment costs of the process employed in Syria are a comprehensive cost investigation for the pro-
approximately 30 % higher than those of the ject in Phitsanulok, Thailand. The effects of
FABER-AMBRA® process, because the techni- MBWT on the cost of waste disposal were des-
cal equipment fleet is more expensive. Conspi- cribed for the following set of boundary condi-
cuously, the operating costs are roughly twice tions:
as high in Brazil as they are in Thailand and
Syria. This is partially attributable to differences Pure landfilling: continuation of landfill ope-
in the local situation (e.g. higher waste incidence rations (approx. 90 Mg/d) in the present
during the tourist season, high personnel costs form; optimization of placement practice.
and expensive biofilter material), but probably
also to the greater reliability of the Brazilian MBWT / landfill: combination of MBWT (with
data. all incoming waste, i.e. approx. 90 Mg/d,
being given the full treatment) and subse-
The variable operating costs of the FABER- quent landfilling (thin-layer emplacement),
AMBRA® process were essentially defined by which prolongs the useful life of the landfill,
the cost of the aerating course and the biofilter. causes less leachate to be produced, and
The costs of fuel and lubricants for the projects means that the landfill requires less
in Thailand and Syria were extrapolated from the aftercare.
current consumption rates and, respectively,
estimated on the basis of the mechanical equip -
ment used. Likewise, presently available infor-
mation does not allow quantification of the
watering and leachate-treatment costs in Thai-
land. The energy consumption rates assumed
for ventilation in the Syrian project are very low.
60
Comparison of specific landfilling costs with and without MBWT
Spezific costs [€/Mg]
16
Cost of landfill aftercare
14 Cost of landfill operation
landfill investment costs
12
10
8
Approx. 50% lower
6 landfilling costs
0
Landfill MBWT/landfill
Figure 39: Comparison of specific landfilling costs in Phitsanulok with and without MBWT (specific costs in EUR/Mg)
Waste collection
Reloading Hauling Industry
incidence (mixed)
Putting out
for collection
Separation collection
Sorting Agriculture
by producer (seperate)
Disposal
Composting
Recycling material
Incineration
Organic material
Resid waste
Total waste
Intervention MBWT
by informal sector
61
Sector Project MBWT - Final Report
62
The success of these measures greatly increa- Two to three years of support will probably
sed the members' motivation and improved their be necessary.
standing with the municipal authorities.
Granting small-scale loans to such groups
The following recommendations and conclu- can have a supportive effect but needs to be
sions can be drawn from the results of support considered on a case-by-case basis and
given in São Sebastião and Ilhabela: should not be allowed to become too much
of a burden on the group. Experience in
other areas shows that small, short-term
Some of the people populating the various loans are often more appropriate than large,
parts of the informal waste-management sec- long-term loans, because it is easier to learn
tor cannot be successfully integrated into more how to deal with them. Credit organizations
formal structures, because, among other fac- should be advised of this.
tors, some are alcoholics and/or drug addicts,
and some are unable to subordinate themsel-
ves to regular work regimens.
63
Sector Project MBWT - Final Report
Threshold Countries
5.1 Conclusions Drawn from the Pilot
Projects
64
The close cooperation between GTZ, the partner
communities and private enterprises practiced in
the sector project has proved fruitful and contri-
buted decisively to the success of the pilot pro-
jects. Hence cooperation between communities
and private enterprises - public-private partners-
hips (PPP) - would appear to be sensible and
advisable for future implementation of MBWT in
developing and threshold countries. German
companies can assume an important role here.
65
Sector Project MBWT - Final Report
100
90
80
70
60
50
40
30
20
10
0
AU BE DK FI FR GE GR IR IT LU NL PO SP SW UK EU
66
Except in a few urban agglomerations, the inci- 5.3 Need for Further Study
neration of municipal solid waste in developing
and threshold countries is not a viable avenue of This sector project provided a crucial point of
disposal, if only for economic reasons. However, departure for assessing the perspectives of
the objective of reducing the emission potentials MBWT in developing and threshold countries,
of MSW could also be achieved by means of but the duration of the project did not suffice to
separate collection and recycling of the organic find conclusive answers to all questions, and
components. Another conceivable solution is to there was little empirical background to draw on
combine composting with MBWT. regarding the construction and operation of
lined and sealed landfills in tropical and subtro-
In any case, the benefits of the various alternati- pical areas. Indeed, the since acquired know-
ves can only be secured if certain assumptions how shows that waste-disposal standards deve-
are fulfilled. For example, the anticipated results loped in Central Europe cannot be applied to
of MBWT decomposition processes can only be such areas without further ado. Hence there is a
achieved if the facility is actually being operated continuing need for further investigation into
with due competence. Likewise, the hoped-for various aspects of MBWT, including and in parti-
income from composting can only be realized if cular the following:
the compost is of good quality and can be suc-
cessfully marketed. Landfilling concept as a function of climate and
waste composition
The comparison of alternatives as a basis for Observations made at landfills in tropical and
deciding on a waste disposal concept will subtropical areas show that organic decomposi-
always include some unavoidable uncertainties. tion proceeds much more rapidly there than it
The degree of uncertainty will depend on how does in more temperate climates. A systematic
much experience has been gained through analysis of relevant empirical data could have a
application of the various alternatives. In order fundamental impact on the operation of such
to minimize the risks resulting from uncertain landfills. For example, the prevailing routine
assumptions, new processes should always first practice of immediately compacting the empla-
be field-tested and then implemented in stages. ced waste and covering it with a layer of topsoil
Extensive MBWT processes, for example, can at the end of each day requires systematic
be tested by way of scale-model trials followed management of the incidental leachate and
by large-scale pilot schemes to establish the landfill gas. That, however, is still unrealizable in
process suitability while adapting it to fit the many countries. Consequently, different ways of
local boundary conditions. The treatment pro- modifying landfill concepts to achieve extensive
cesses dealt with in this report allow such a aerobic decomposition of the organic fraction
step-by-step form of introductory implementa- directly at the landfill need to be investigated
tion. (including "shredded refuse landfills" as the
Also, MBWT enables the separation of high- most elementary form of MBWT).
energy fractions at the mechanical conditioning
stage. That, in turn, makes it possible to integra-
te additional paths of recovery and disposal into
the waste management system, extending
beyond mere improvements in the waste dispo-
sal situation.
67
Sector Project MBWT - Final Report
68
6 Summary
69
Sector Project MBWT - Final Report
70
APPENDICES
71
Sector Project MBWT - Final Report
72
Project characterization - Phitsanulok, Thailand
Project designation Partners in cooperation
Pilot project Phitsanulok Thailand
GTZ sector project "Promotion of Mechanical-biological Waste Treatment"
Country, community Official contact Elke Hüttner; Division OE44; Phone: ++49 6196 79 0
Thailand, Phitsanulok e-mail: [email protected]; Internet: www.gtz.de/mba/
Employed technology
Delivery by collecting vehicle or container truck
Registration of weight and origin via truck weigher
Conditioning/preparation
Manual presorting by waste pickers and possibly employees
Homogenizing drum, i.e. modified rotary drum vehicle from Ger -
many, capacity: 7 Mg
Homogenization and comminution of waste input Landfill entry point
Each batch takes 70 minutes, incl. 45 min for homogenization
Decomposition
Preparation of heap base with pallets and drain pipes
Building of heaps with excavator
Covering with biofilter, installation of watering system and sam-
pling gauges
Decomposing time: 9 months; temperature-controlled process
Teardown of heaps with excavator
Disposal of output
Thin-layer emplacement by compactor (initial trials)
Local peculiarities
Well-developed private recycling sector, large water and plastics
fractions, little structural material in residual waste
73
Sector Project MBWT - Final Report
Description
Short description of the project
Research project for investigating the suitability of, and for appropriately adapting, the Gore laminate process (force-ventilated,
controlled-heap decomposition with inert semi-permeable laminate cover) as a technically uncomplicated, relatively inexpensive,
easy to operate, quickly implementable waste treatment facility for the production and quality control of soil conditioners (com-
post).
Local integration
Integration into the waste sector and landfill environment, composting of biowaste,
cooperation with local specialists and training of sector employees
Technical description Photos
Basic waste-management data
Population served: approx. 125,000
Rainy season: Oct. - April, precipitation approx. 300 mm
Annual waste input: 20,000 Mg (in 2001)
Waste composition: 70 wt.% organics
10 wt.% plastics
Water content: > 60 wt.%
Planned plant capacity: 40-50 Mg/d, 15,000 Mg/a
(treatment of approx. 220 Mg in scale-model trial)
Employed technology
Delivery: by collecting vehicle
Registration of weight and origin via truck weigher
Conditioning/preparation: Manual presorting by waste pickers
and possibly employees Cover and forced ventilation of heaps
Homogenization and comminution of the waste in a mobile com-
minutor; planned: 10 Mg/h homogenizing drum made in Syria
Decomposition: Construction of channels for ventilation and
drainage / collection of leachate; manual setting up and tearing
down of heaps; inert, semi-permeable laminate cover; three-
month composting process, controlled via temperature and oxy-
gen level; use of excavator and wheel loader planned
Disposal of output: Mechanical conditioning (screening) and
separation of fine material as compost in the handling of bio-
waste; otherwise disposal to landfill.
Local peculiarities
Well-developed private recycling sector (waste pickers), large
water and plastics fractions; plastic bags, little structural materi-
al in household waste; dryness; high organic fraction Heap with ventilating elements (aerators)
Project status
Present state and activities to date Planned activities
The research project "Appropriate waste disposal for TC and Construction and commissioning of waste-treatment facility, trai-
DC" has been completed. Preparations for a PPP program for ning program, public awareness-raising, use of compost output
implementation of residual-waste treatment incl. separation of in agriculture, scientific backstopping program
useful compost fraction, is under way. Plant scheduled for com-
missioning May 2003.
Technoscientific investigations and findings
Extensive test program to determine waste composition, temperature profiles, water content, ignition loss, nutrients and heavy
metals, sampling of inputs and other material
Particularities, remarks
Thanks to forced ventilation and covering of the heaps, no watering was necessary for the duration of mechanical-biological treat-
ment, because the evaporated water condensed on the inside of the laminate cover and dripped back onto the decaying material.
74
Project characterization - Atlacomulco, Mexico
Project designation Partners in cooperation
Pilot project, Atlacomulco Mexico
GTZ sector project "Promotion of Mechanical-biological Waste Treatment"
Country, community Official contact Elke Hüttner; Division OE44; Phone: ++49 6196 79 0
Mexico, Atlacomulco e-mail: [email protected];
Internet: www.gtz.de/mba/
Description
Short description of the project
Pilot project for introducing integrated waste management (recycling, composting, residual-waste treatment, landfill-ing) in applica-
tion of the FABER-AMBRA® process of Wilhelm Faber GmbH (non-mobile, passively ventilated heaps, with mechanical conditio -
ning) for waste treatment and compost production, transfer of know-how by training and local project backstopping, integration of
the informal sector ("Pepenadores")
Local integration
Integration of "Pepenadores" upon introduction of integrated waste management
Cooperation with the local GTZ project "Decentralization of Waste Management in the State of Mexico"
Employed technology
Delivery by collecting vehicle and container truck;
No registration of weight or origin of waste
Conditioning/preparation
Manual sorting by "Pepenadores" and possibly employees
Homogenizing drum as an individually modified rotary drum
machine from Germany; capacity: 7 Mg
Homogenization and comminution of waste material First group of trainees
Each batch takes 70 minutes, incl. 45 min for homogenization
Decomposition
Preparation of biological treatment with pallets and drain pipes
Building of heaps with excavator
Cover with geofilter, manual irrigation, monitoring of gas, tem-
perature and process water
Planned decomposing time: 9 months, process control via tem-
perature measurements
Teardown of heaps with excavator
Disposal of output
First, mechanical conditioning (e.g. screening): planned, but no
experience gained to date
Local peculiarities
No organic biofilter material available; use of slightly geogenous
material as cover for the heaps
Building of the first heap
Project status
Present state and activities to date Planned activities
Waste treatment commenced in 11/ 02, Introduction of separate waste collection in certain parts of town
three test heaps on an old leachate pond; new heaps put up in to obtain mono-batches of biowaste for compost production
new grounds since 01/03.
Particularities, remarks
75
Sector Project MBWT - Final Report
Description
Short description of the project
Pilot project for implementing an integrated approach to sustainable development via theoretical and practical training in "integra-
ted waste management" and "sustainable waste management". Establishment of a technical school. Planning/construction/opera-
tion of a model MBWT facility, incl. practical training. Training of specialists to serve as trainers. Integration of the Recicladores
cooperatives. Summarization and publication of experience gained via the Internet portal "ForumZ for Latin America" (www.foro-
z.com).
Local integration
Elaboration and provision of training; planning and implementation of a social project; goals include strengthening and stabilization
of democratic structures and of municipal self-administration.
Permanent local project partners: Cámara de Comercio de Armenia, Servicio Nacional de Aprendizaje SENA Quindío, Universidad
Empresarial Armenia
Technical description Photos
TMB demonstration facility
Basic waste-management data
No separate collection of waste
No waste treatment and landfilling to technical standards
High organic fraction ( ~ 70 wt.%)
Temporary TMB demonstration facility with separation and com-
post-ing of a) household waste, b) central market waste, and c)
waste from gardens and parks
Employed technology
Delivery
by container truck, with registration of waste origin (hauling and
collecting routes) and weight (truck weigher)
Receiving point Waste receiving, input check, registration
Mechanical conditioning Coarse and fine sorting, screening
(manual)Separation of interfering objects,
pollutants and recyclables (manual)
Comminution, homogenization (mixing drum) Indoor part of model facility
Weighing of all material fractions
Biological (aerobic) treatment
Indoor composting in bamboo composting bins;
No active ventilation
Collection of leachate and process water
Mechanical post-treatmentScreening and, as necessary, post-
composting
Local peculiarities
Disposal of residual waste: ~15-20 % of material input
Integration of Recicladores cooperatives, incl. training
Lack of overall waste-management strategy
Municipal dump (Armenia) soon to close (Dec. 2002), but no
concrete alternative plans to date.
76
Appendix 2 List of Important Contacts
Team of experts
1. Gernod Dilewski 6. Dr. Dieter Mutz
Infrastruktur & Umwelt, Professor Böhm und Partner Basel University of Applied Sciences (FHBB)
77
Sector Project MBWT - Final Report
78
9. Knoten Weimar - International Transfer Center 13. Ingenieurbüro für innovative Abfallwirtschaft
for Environmental Biotechnology GmbH; iA GmbH
Braunschweig Technical University Werner P. Bauer
Leichtweiss Institute, Waste-management Gotzinger Str. 48/50
Department D- 81371 Munich
Prof. Dr.- Ing. Klaus Fricke Phone: +49 (0)89 / 189 35 0
Dipl.-Ing. Heike Santen Fax: +49 (0)89 / 189 35 199
Beethovenstraße 51 a URL: www.ia-gmbh.de
D- 38106 Braunschweig E-Mail: [email protected]
Phone: +49 (0)531 / 391 3969
Fax.: +49 (0)531 / 391 4584 14. Sustainable Technologies, Building-Business
URL: www.bionet.net Consultants (TBW) GmbH
E-Mail: [email protected] Hr. Hartlieb Euler
Baumweg 10
10. Wilhelm Faber GmbH D- 60316 Frankfurt am Main
Wolfgang Tönges Phone: +49 (0)69 / 9435 070
Dr. Dirk Maak Fax: +49 (0)69 / 9435 0711
Galgenwiesenweg 23-29 URL: www.tbw-frankfurt.com
D- 55 232 Alzey E-Mail: [email protected]
Phone: +49 (0)6731 / 492 232
Fax: +49 (0)6731 / 492 283 15. Ingenieurgemeinschaft Witzenhausen
URL: www.faber-ambra.de IGW Fricke & Turk GmbH
E-Mail: [email protected] Bischhäuser Aue 12
D- 37 213 Witzenhausen
11. University of Kassel Phone: +49 (0)5542 / 93 080
Waste Technology Faculty Fax: +49 (0)5542 / 93 08 20
Prof. Dr.-Ing. Arnd Urban E-Mail: [email protected]
Dr.-Ing. Aber Mohamad
Mönchebergstraße 7 16. INTECUS Dresden GmbH
D- 34125 Kassel Pohlandstraße 17
Phone: +49 (0)561 / 95 29 095 D- 01309 Dresden
Fax: +49 (0) 561 / 95 29 098 Phone: +49 (0)351 / 318 23 14
URL: www.uni-kassel.de/fb14/abfalltechnik/ Fax: +49 (0)351 / 318 23 33
E- Mail: [email protected] URL: www.intecus.de
E-Mail: [email protected]
12. Solid Waste Treatment W.L.
Gore & Associates GmbH 17. Faber Serviço Ltda.
Lothar Deyerling Christiane Dias Pereira
Hermann-Oberth-Str. 24 Rua Duque de Caxias, 188
D-85640 Putzbrunn 2° Piso - SALA 13
Phone: +49 (0)89 / 4612 2726 Centro - São Sebastião
Fax: +49 (0)89 / 4612 4 2726 São Paulo, 11600-000
E-Mail: [email protected] BRASIL
Phone/Fax: +55 (0)12 38 93 10 12
E-Mail: [email protected]
79
Sector Project MBWT - Final Report
18. Wilhelm Faber GmbH 24. Infrastruktur & Umwelt, Professor Böhm und
Maria Elena Mendoza Partner
Galgenwiesenweg 23 - 29 Gernod Dilewski
D- 55232 Alzey Julius-Reiber-Straße 17
Phone/Fax: +52 (0)712 1228 127 D- 64293 Darmstadt
E-Mail: [email protected] Phone: +49 (0)6151 / 81 30 0
Fax: +49 (0)6151 / 81 30 20
19. Wilhelm Faber GmbH URL: www.iu-info.de
Chaiwat Teankum Schlicht E-Mail: [email protected]
Galgenwiesenweg 23 - 29
D- 55232 Alzey 25. Dr. Uwe Cusnick
Phone: +66 (0)1 820 52 76 Organization Consultant
Fax: +66 (0)55 21 79 35 Wehrhofstraße 1
E-Mail: [email protected] D- 60489 Frankfurt
Phone: +49 (0)69 / 789 39 15
20. Dr. Kornelia-Theodora Drees Mobil: +49 (0)179 / 699 29 15
Viktoriaallee 46 E-Mail: [email protected]
D- 52066 Aachen
Phone: +49 (0)241 / 997 997 87
80
Appendix 3 Bibliography
[1] AEA Technology (1998): Options to reduce [8]* Alziro da Silva Gregorio (n.b.): Programa de
methane emissions. Report to DG XI of the formacao de Cooperativas, Objetivo: Gestao
European Comission. participativa e Economia domestica sustentavel.
São Sebastião
[2] Zeschmar-Lahl B., Jager J., Ketelsen K., Lahl
U., Scheidl K., Steiner M., Heckmann A.: [9]* Dilewski, Gernod (2002): Bericht über den
Mechanisch-biologische Abfallbehandlung in Einsatz von Dipl.Ing. Gernod Dilewski vom
Europa. Hrsg.: VKS e.V., A.S.A. e.V., Blackwell 26.01.2002 bis 10.02.2002 in Mexiko.
Wissenschafts-Verlag, Berlin, 2000, ISBN 3- Infrastruktur & Umwelt, Professor Böhm und
8263-3261-X Partner, Darmstadt
[3] Heering M., Zeschmar-Lahl B.: Der Bran- [10]* dos Santos, Anna Lúcia Florisbela (2000):
chenführer MBA-Technik. Systemanbieter und Der Informelle Sektor in der Abfallwirtschaft Bra-
Verfahren der mechanisch-biologischen Abfall- siliens am Beispiel São Sebastião sowie Auswir-
behandlung, 2001. Hrsg.: VDMA, Rombos Ver- kungen der Einführung der Mechanisch-Biologi-
lag, Berlin 2001, ISBN 3-930894-40-8 schen- Abfallbehandlung auf diesen Sektor.
Deutsche Gesellschaft für technische
[4] Bundesministerium für wirtschaftliche Zusammenarbeit GmbH (GTZ) (available in Ger-
Zusammenarbeit und Entwicklung (1996): Sek- man, Portuguese)
torkonzept Abfallwirtschaft. BMZ aktuell, 067,
Mai 1996, 15 Seiten [11]* dos Santos, Anna Lúcia Florisbela (2001):
Der Informelle Sektor in der Abfallwirtschaft -
[5] Kayser, R., Chang, L. (1993): Physikalische das Beispiel Ilhabela, Brasilien -. Deutsche
und biologische Vorbehandlung von Hausmüll zu Gesellschaft für technische Zusammenarbeit
Minimierung des Raumbedarfes und der Emis- GmbH (GTZ), Ilhabela, Brasilien / Atizapan de Z.,
sionen. Institut für Siedlungswasserwirtschaft, Mexiko (available in German, Portuguese)
TU Braunschweig, 1993
[12]* dos Santos, Anna Lúcia Florisbela (2002):
[6] Collins, H.-J., Brammer, F., Maak, D. (1998): Unterstützung bei der Gründung eines Vereins
Ergebnisse der mechanisch-biologischen Abfall- der Abfallsortierer und der Formalisierung ihrer
behandlung bei mehrjährigem Praxisbetrieb; Aktivitäten (informeller Sektor) - Ilhabela, Brasi-
Entsorgungspraxis Heft 4/98, S. 26 - 29 und lien, Schlussbericht. Deutsche Gesellschaft für
Heft 5/98, S. 36 - 41, Bertelsmann Verlag technische Zusammenarbeit GmbH (GTZ), Esch-
born
[7] Commission of the European Communities
(2001): Third Communication from the European [13]* dos Santos, Anna Lúcia Florisbela; Alves,
Community under the UN Framework Conven- Fábio Cidrin Gama (2001): OS CATADORES E
tion on Climate Change, 30. November 2001 TRIADORES DE RESÍDUOS SÓLIDOS DOCU-
MENTAÇÃO DO PRIMEIRO ENCONTRO INTER-
NACIONAL. Deutsche Gesellschaft für techni-
sche Zusammenarbeit GmbH (GTZ), Eschborn
81
Sector Project MBWT - Final Report
[14]* Drees, Kornelia-Theodora; Diebels, Dagmar [20]* Janikowski, Gabriele (2002): Continuation
(2000): Mechanical-Biological Waste Treatment of Investigations on the Feasibility of a Mechani-
in Germany, Video. Deutsche Gesellschaft für cal-Biological Waste Treatment Plant in Phitsan-
technische Zusammenarbeit GmbH (GTZ), Esch- ulok, Thailand, Part I. Deutsche Gesellschaft für
born technische Zusammenarbeit GmbH (GTZ), Esch-
born
[15]* GFA Umwelt, Bonn (1999): Decision
Maker's Guide to Compost Production, Software [21]* Janikowski, Gabriele (2002): Continuation
Tool - Economic Model, Version 0.9 E. Deutsche of Investigations on the Feasibility of a Mechani-
Gesellschaft für technische Zusammenarbeit cal-Biological Waste Treatment Plant in Phitsan-
GmbH (GTZ), Eschborn ulok, Thailand, Part II. Deutsche Gesellschaft für
technische Zusammenarbeit GmbH (GTZ), Esch-
[16]* Hüttner, Elke; Kebekus, Frauke (1999): born
Counterpart Training Sept. 1- 8, 1999, Sector
operation "Mechanical-biological waste treat- [22] Janikowski, Gabriele (2003): Comparative
ment options in developing countries". Deutsche Cost/Benefit Analysis for Conventional Disposal,
Gesellschaft für technische Zusammenarbeit Large Scale Composting and Mechanical Biolo-
GmbH (GTZ), Eschborn gical Waste Treatment for Phitsanulok, Final Pre -
sentation of the Current Results. Thai-German
[17]* Hüttner, Elke; Kebekus, Frauke (2000): Ein- Solid Waste Management Programme for Phits-
satzpotentiale der mechanisch-biologischen anulok, Phitsanulok
Abfallbehandlung in Entwicklungsländern, Vor-
trag auf den Potsdamer Abfalltagen 22.- [23]* Kebekus, Frauke (1999): Hospitationsbe-
23.05.2000. Deutsche Gesellschaft für techni- richt zum Einsatz innerhalb des Sektorvorha-
sche Zusammenarbeit GmbH (GTZ), Eschborn bens "Möglichkeiten der mechanisch-biologi-
schen Abfallbehandlung in Entwicklungslän-
[18]* Intecus GmbH; Universität Gesamthoch- dern". Deutsche Gesellschaft für technische
schule Kassel, Fachgebiet Abfalltechnik (2000): Zusammenarbeit GmbH (GTZ), Eschborn
Untersuchungen zu den Auswirkungen einer
mechanisch-biologischen Abfallbehandlung [24]* Kebekus, Frauke; Drees, Kornelia-Theodo-
(MBA) auf die Errichtung und den Betrieb einer ra; Dilewski, Gernod (2000): Mechanisch-biologi-
Deponie in Al-Salamieh/Syrien hinsichtlich öko- sche Abfallbehandlung?- Einführung und Ent-
nomischer und ökologischer Kriterien. Deutsche scheidungshilfen für den Einsatz in Entwik-
Gesellschaft für technische Zusammenarbeit klungsländern -. Deutsche Gesellschaft für tech-
GmbH (GTZ), Eschborn nische Zusammenarbeit GmbH (GTZ), Entwurf,
Eschborn (available in German, English,
[19] IP Institut für Projektplanung GmbH, Stutt- Spanish )
gart (1997): Study on Municipial Solid Waste
Management in Phitsanulok, Thailand. Deutsche [25]* Kebekus, Frauke; Janikowski Gabriele;
Gesellschaft für technische Zusammenarbeit Dilewski, Gernod (2000): Study on the Feasibility
GmbH (GTZ), Eschborn of a Mechanical-biological Residual Waste Treat-
ment Plant in Phitsanulok, Thailand. Deutsche
Gesellschaft für technische Zusammenarbeit
GmbH (GTZ), Eschborn
82
[26]* Maak, Dirk; Pereira, C.; Tönges Wolfgang [32]* N.N. (2000): New Approaches in Waste Tre-
(2000): Zweiter Zwischenbericht zum Vorhaben atment, Mechanical- Biological Waste Treatment
"Einführung der FABER-AMBRA® in Rio de Options. Deutsche Gesellschaft für technische
Janeiro, Brasilien. FABER-Recycling GmbH, Zusammenarbeit GmbH (GTZ), Eschborn (availa-
Schlierstett ble in English, Spanish)
[27]* Mohamad Aber; Urban, Arnd I. (2003): GTZ [33]* N.N. (n.b.): Innovative solutions for an envi-
Sektorvorhaben MBA, Förderung der mecha- ronmentally beneficial waste disposal at reaso-
nisch-biologischen Abfallbehandlung, Endbe- nable costs, Video. Wilhelm Faber GmbH, Alzey
richt des Modellversuchs in Al-Salamieh, Syrien.
Universität Kassel, Fachbereich Bauingenieur- [34]* Santen, Heike (2000): Fortschrittliche
wesen, Fachgebiet Abfalltechnik Abfallwirtschaftssysteme mit verstärkter Wert-
stoffrückgewinnung in Brasilien, Randbedingun-
[28]* N. N. (2001): Public Private Partnerships im gen und derzeitige Praxis. Technische Univer-
internationalen Abfallsektor, Unternehmerforum, sität Hamburg-Harburg, Arbeitsbereich Abfall-
Dokumentation. Deutsche Gesellschaft für tech- wirtschaft und Stadttechnik, Prof. Dr.-Ing. Rainer
nische Zusammenarbeit GmbH (GTZ), Eschborn. Stegmann
[29]* N.N. (1999): Dokumentation des Fachfo- [35]* Schenk, Bernhard (2000): Machbarkeitsstu-
rums "Mechanisch- Biologische Afallbehandlung die für eine mechanisch biologische Abfallbe-
in Entwicklungsländern". Knoten Weimar, Deut- handlungsanlage in Ilhabela, Brasilien. Deutsche
sche Gesellschaft für technische Zusammenar- Gesellschaft für technische Zusammenarbeit
beit GmbH (GTZ), Eschborn GmbH (GTZ), Eschborn (available in German,
Portuguese)
[30]* N.N. (1999): Dokumentation des Works-
hops: "Mechanisch-Biologische Abfallbehand- [36]* Schenk, Bernhard (2001): Bewertung des
lung in Entwicklungsländern", Arbeitsfeld "Was- Betriebs der mechanisch biologischen Abfallbe-
ser und Abfallwirtschaft", Eschborn, 18.03.1999. handlungsanlage in São Sebastião, Brasilien.
Deutsche Gesellschaft für technische Deutsche Gesellschaft für technische
Zusammenarbeit GmbH (GTZ), Eschborn Zusammenarbeit GmbH (GTZ), Eschborn (availa-
ble in German, Portuguese)
[31]* N.N. (2000): Konzept für ein Jahr Probebe-
trieb, Phitsanulok, Thailand. Faber- Ambra®, [37]* Schenk, Bernhard (2002): Bewertung der
Alzey 2000 Mechanisch-Biologischen Abfallbehandlung in
São Sebastião, Brasilien, Technische Bewertung
des Betriebes nach ca. 22 Monaten Betrieb.
Deutsche Gesellschaft für technische
Zusammenarbeit GmbH (GTZ), Eschborn (availa-
ble in German, Portuguese)
83
Sector Project MBWT - Final Report
84
Deutsche Gesellschaft für
Technische Zusammenarbeit (GTZ) GmbH
- German Technical Cooperation -
Dag-Hammarskjöld-Weg 1-5
Postfach 5180
65726 Eschborn, Germany
Telephone: +49 (6196) 79-0
Fax: +49 (6196) 79-1115
Internet: http://www.gtz.de
On behalf of: