Hydraulic Structures Mod 4
Hydraulic Structures Mod 4
Hydraulic Structures Mod 4
A gravity dam is a dam constructed from concrete or stone masonry and designed to hold back
water by primarily utilizing the weight of the material alone to resist the horizontal pressure of
water pushing against it. Gravity dams are designed so that each section of the dam is stable,
independent of any other dam section
1
The total pressure is in horizontal direction and acts on the upstream face at a height from
the
bottom. The pressure diagram is triangular and the total pressure is given by
Where w is the specific weight of water. Usually it is taken as unity.
H is the height upto which water is stored in m.
(ii) Upstream face with batter and there is no water on the downstream side (figure 2).
Figure 2
Here in addition to the horizontal water pressure as in the previous case, there is vertical
pressure of the water. It is due to the water column resting on the upstream sloping side.
The vertical pressure acts on the length ‘b’ portion of the base. This vertical pressure is given
by
Pressure acts through the centre of gravity of the water column resting on the sloping
upstream face.
If there is water standing on the downstream side of the dam, pressure may be calculated
similarly. The water pressure on the downstream face actually stabilizes the dam. Hence as an
additional factor of safety, it may be neglected.
2
II) Water pressure below the base of the dam or Uplift pressure
When the water is stored on the upstream side of a dam there exists a head of water equal to the
height upto which the water is stored. This water enters the pores and fissures of the foundation
material under pressure. It also enters the joint between the dam and the foundation at the base
and the pores of the dam itself. This water then seeps through and tries to emerge out on the
downstream end. The seeping water creates hydraulic gradient between the upstream and
downstream side of the dam. This hydraulic gradient causes vertical upward pressure. The
upward pressure is known as uplift. Uplift reduces the effective weight of the structure and
consequently the restoring force is reduced. It is essential to study the nature of uplift and also
some methods will have to be devised to reduce the uplift pressure value.
Figure 3
Where is the uplift pressure, B is the base width of the dam and H is the height upto which
water is stored.
This total uplift acts at from the heel or upstream end of the dam.
Uplift is generally reduced by providing drainage pipes or holes in the dam section.
Self weight of the dam is the only largest force which stabilizes the structure. The total weight of
the dam is supposed to act through the centre of gravity of the dam section in vertically
downward direction. Naturally when specific weight of the material of construction is high,
restoring force will be more. Construction material is so chosen that the density of the material is
about 2.045 gram per cubic meter.
3
2. Earthquake Forces
The effect of earthquake is equivalent to acceleration to the foundation of the dam in the
direction in which the wave is travelling at the moment. Earthquake wave may move in any
direction and for design purposes, it is resolved into the vertical and horizontal directions. On an
average, a value of 0.1 to 0.15g (where g = acceleration due to gravity) is generally sufficient for
high dams in seismic zones. In extremely seismic regions and in conservative designs, even a
value of 0.3g may sometimes by adopted.
Vertical acceleration reduces the unit weight of the dam material and that of water is to
times the original unit weight, where the value of g accounted against earthquake
forces, i.e. 0.1 is when 0.1g is accounted for earthquake forces. The horizontal acceleration
acting towards the reservoir causes a momentary increase in water pressure and the foundation
and dam accelerate towards the reservoir and the water resists the movement owing to its inertia.
The extra pressure exerted by this process is known as hydrodynamic pressure.
3. Silt Pressure
If h is the height of silt deposited, then the forces exerted by this silt in addition to the external
water pressure, can be represented by Rankine formula
4. Wave Pressure
Waves are generated on the surface of the reservoir by the blowing winds, which exert a pressure
on the downstream side. Wave pressure depends upon wave height which is given by the
equation
for F > 32 km
Where is the height of water from the top of crest to bottom of trough in meters.
V – wind velocity in km/hour
4
F – fetch or straight length of water expanse in km.
The maximum pressure intensity due to wave action may be given by
Figure 4
5. Ice Pressure
The ice which may be formed on the water surface of the reservoir in cold countries may
sometimes melt and expand. The dam face is subjected to the thrust and exerted by the
expanding ice. This force acts linearly along the length of the dam and at the reservoir level. The
magnitude of this force varies from 250 to 1500 kN/sq.m depending upon the temperature
variations. On an average, a value of 500 kN/sq.m may be taken under ordinary circumstances.
6. Weight of dam
The weight of dam and its foundation is a major resisting force. In two dimensional analysis
of dam
5
FAILURES OF GRAVITY DAM
Failure of gravity dam occurs due to overturning, sliding, tension and compression. A gravity
dam is designed in such a way that it resists all external forces acting on the dam like water
pressure, wind pressure, wave pressure, ice pressure, uplift pressure by its own self-weight.
Gravity dams are constructed from masonry or concrete. However, concrete gravity dams are
preferred these days and mostly constructed. The advantage of gravity dam is that its structure is
most durable and solid and requires very less maintenance.
Fig: sum of external horizontal forces greater than vertical self-weight of dam (overacting,
sliding occurs)
6
Sliding Failure of Gravity Dam: When the net horizontal forces acting on gravity dam at the
base exceeds the frictional resistance (produced between body of the dam and foundation), The
failure occurs is known as sliding failure of gravity dam.
In low dams, the safety against sliding should be checked only for friction, but in high dams, for
economical precise design, the shear strength of the joint is also considered
Factor of safety against sliding can be given based on Frictional resistance and shear strength of
the dam
Factor of safety based on frictional resistance:
Gravity Dam Failure due to Tension Cracks: Masonry and concrete are weak in tension. Thus
masonry and concrete gravity dams are usually designed in such a way that no tension is
developed anywhere. If these dams are subjected to tensile stresses, materials may develop
tension cracks. Thus the dam loses contact with the bottom foundation due to this crack and
becomes ineffective and fails. Hence, the effective width B of the dam base will be reduced. This
will increase pmax at the toe. Hence, a tension crack by itself does not fail the structure, but it
leads to the failure of the structure by producing excessive compressive stresses.
For high gravity dams, certain amount of tension is permitted under severest loading conditions
in order to achieve economy in design. This is permitted because the worst condition of loads
may occur only momentarily and may not occur frequently.
7
Gravity Dam Failure due to Compression: A gravity dam may fail by the failure of its
material, i.e. the compressive stresses produced may exceed the allowable stresses, and the dam
material may get crushed.
Design principles
8
friction alone especially if the rock is markedly stratified and horizontally bedded. The factor of safety
against sliding (F) along a plane may be computed from
Where,
The calculation of the stresses in the body of a gravity dam follows from the basics of elastic theory,
which is applied in a two-dimensional vertical plane, and assuming the block of the dam to be a cantilever
in the vertical plane attached to the foundation. Although in such an analysis, it is assumed that the
vertical stresses on horizontal planes vary uniformly and horizontal shear stresses vary parabolically, they
are not strictly correct. Stress concentrations develop near heel and toe, and modest tensile stresses may
develop at heel. The basic stresses that are required to be determined in a gravity dam analysis are
discussed below:
On any horizontal plane, the vertical normal stress (σz) may be determined as:
Where,
T is the thickness of the dam block i.e., the length measured from heel to toe
Y is the distance from the neutral axis of the plane to the point where σ z is being determined
At the heel, y= -T/2 and at the toe, y=+T/2. Thus, at these points, the normal stresses are found out as:
9
The eccentricity e may be found out as:
Naturally, there would be tension on the upstream face if the overturning moments under the
reservoir full condition increase such that e becomes greater than T/6. The total vertical stresses at the
upstream and downstream faces are obtained by addition of external hydrostatic pressure.
Shear stresses on horizontal planes
Horizontal stresses (τzy) and the shear stresses (τyz) are developed at any point as a result of the
variation in vertical normal stress over a horizontal plane. The following relation can be derived relating
the stresses with the distance y measured from the centroid
τ τ τ τ τ τ τ
Where,
The shear stress is seen to vary parabolically from τ yzU at the upstream face up to τyzD at the
downstream face.
It is not the maximum direct stress produced anywhere in the dam. The maximum normal stress
will, indeed, be the major principal stress that will be generated on the major principal plane. The
principal (σ) and shear (τ) stresses at the toe and heel of gravity dam can be expressed by
σ toe = pv sec2 α - (pˊ- peˊ) tan2 δ
σ heel = pv sec2 φ - (p + pe) tan2 θ
τ toe = [pv – (pˊ- peˊ)] tan δ
τ heel = [pv - (p + pe)] tan θ
10
Where,
δ is the angle which the downstream face of the dam makes with the vertical,
θ is the angle which the upstream face makes with the vertical,
pv is the intensity of uplift pressure,
p is the minor principal stress at the heel
pe is the hydrodynamic pressure exerted by the head water
peˊ is the hydrodynamic pressure exerted by the tail water during an earthquake
In a gravity dam, stability is secured by making it of such a size and shape that it will resist
overturning, sliding and crushing at the toe. The dam will not overturn provided that the moment around
the turning point, caused by the water pressure is smaller than the moment caused by the weight of the
dam. This is the case if the resultant force of water pressure and weight falls within the base of the dam.
However, in order to prevent tensile stress at the upstream face and excessive compressive stress at the
downstream face, the dam cross section is usually designed so that the resultant falls within the middle at
all elevations of the cross section (the core). For this type of dam, impervious foundations with high
bearing strength are essential.
For reservoir empty condition it will For reservoir empty condition tension is developed at
provide maximum possible stability. toe and hence some masonry is provided on u/s side.
11
Function and types of galleries in Dams
12
MODULE -2- EARTH DAMS
Introduction
An embankment dam is a large artificial dam. It is typically created by the placement and
compaction of a complex semi-plastic mound of various compositions of soil, sand, clay, or rock.
It has a semi-pervious waterproof natural covering for its surface and a dense, impervious core.
This makes such a dam impervious to surface or seepage erosion. Such a dam is composed of
fragmented independent material particles. The friction and interaction of particles binds the
particles together into a stable mass rather than by the use of a cementing substance.
Embankment dams come in two types: the earth-filled dam (also called an earthen dam or
terrain dam) made of compacted earth, and the rock-filled dam. A cross-section of an
embankment dam shows a shape like a bank, or hill. Most have a central section or core
composed of an impermeable material to stop water from seeping through the dam. The core can
be of clay, concrete, or asphalt concrete. This dam type is a good choice for sites with wide
valleys. They can be built on hard rock or softer soils. For a rock-fill dam, rock-fill is blasted
using explosives to break the rock. Additionally, the rock pieces may need to be crushed into
smaller grades to get the right range of size for use in an embankment dam.
The building of a dam and the filling of the reservoir behind it places a new weight on the floor
and sides of a valley. The stress of the water increases linearly with its depth. Water also pushes
against the upstream face of the dam, a nonrigid structure that under stress behaves
semiplastically, and causes greater need for adjustment (flexibility) near the base of the dam than
at shallower water levels. Thus the stress level of the dam must be calculated in advance of
building to ensure that its break level threshold is not exceeded.
1. Hydraulic Failure:
1. Overtopping of dams
2. Erosion of the Upstream Surface
3. Erosion of the Downstream Surface
4. Erosion of the Downstream toe
13
i. Overtopping of dams:
This type of dam is made up of only one type of material. Usually porous materials is used.
These dams are easy and cheap to construct but cannot be used to make multipurpose large
dams. For large multipurpose dams zoned type method is used. Over topping failures result from
the erosive action of water on the embankment. Erosion is due to un-controlled flow of water
over, around, and adjacent to the dam. Earth embankments are not designed to be over-topped
and therefore are particularly susceptible to erosion. Once erosion has begun during over-
topping, it is almost impossible to stop. A well vegetated earth embankment may withstand
limited over topping if its crest is level and water flows over the crest and down the face as an
evenly distributed sheet without becoming concentrated. The owner should closely monitor the
reservoir pool level during severe storms.
Due to rainfall, snow and winds the downstream surface of the dam also erodes. By providing a
section of coarse materials here, this erosion can be reduced or prevented.
2. Seepage Failure:
All earth dams have seepage resulting from water permeating slowly through the dam and its
foundation. Seepage must be controlled in both velocity and quantity. If uncontrolled, it can
progressively erode soil from the embankment or its foundation, resulting in rapid failure of the
dam. Erosion of the soil begins at the downstream side of the embankment, either in the dam
proper or the foundation, progressively works toward the reservoir, and eventually develops a
direct connection to the reservoir. This phenomenon is known as "piping." Piping action can be
recognized by an increased seepage flow rate, the discharge of muddy or discolored water,
sinkholes on or near the embankment, or a whirlpool in the reservoir. Once a whirlpool (eddy) is
observed on the reservoir surface, complete failure of the dam will probably follow in a matter of
minutes. As with over topping, fully developed piping is virtually impossible to control and will
likely cause failure. Seepage can cause slope failure by creating high pressures in the soil pores
or by saturating the slope. The pressure of seepage within an embankment is difficult to
14
determine without proper instrumentation. A slope which becomes saturated and develops slides
may be showing signs of excessive seepage pressure.
1. Piping thorugh the dam: There are two kinds of forces acting on the downstream face
of the dam:
If the seepage force exceeds the weight of the material the water washes away the soil from the
plate and creates a hole in the ground. This hole deepens as more and more mateial is taken away
from it and extends longitudinally, making a pipe hole called "Piping in the dam".
3. Structural Failure:
Structural failures can occur in either the embankment or the appurtenances. Structural failure of
a spillway, lake drain, or other appurtenance may lead to failure of the embankment. Cracking,
settlement, and slides are the more common signs of structural failure of embankments. Large
cracks in either an appurtenance or the embankment, major settlement, and major slides will
require emergency measures to ensure safety, especially if these problems occur suddenly. If this
type of situation occurs, the lake level should be lowered, the appropriate state and local
authorities notified, and professional advice sought. If the observer is uncertain as to the
seriousness of the problem, the Division of Water should be contacted immediately. The three
types of failure previously described are often interrelated in a complex manner. For example,
uncontrolled seepage may weaken the soil and lead to a structural failure. A structural failure
may shorten the seepage path and lead to a piping failure. Surface erosion may result in
structural failure.
15
1. Usually upper part of the dam is dry and the lower is saturated with water which gives
rise to pore water pressure within the voids. Dam body is saturated - All pores / voids are filled
with water, pore water pressure is induced. Effective pressure reduces and shear strength of soil
decreases
2. When water is suddenly withdrawn or in other words if the level of water in the reservoir
reduces suddenly, the soil on the upstream face of the dam body may be highly saturated and has
pore water pressure that tries to destabilise the dam and if this force is high enough, it can fail the
dam.
3. If the shear strength of the soil on which the foundation is built is weak though the
foundation itself may be strong but due to weakness of the soil foundation may slide on the sides
and in some cases the foundation itself may be not able to resist the shear force that may have
increased from normal due to any reason.
4. Burrowing animals - Small animals living in the holes and pits may have dug theri holes
anywhere in te dam body which may widen with the passage of time and can be dangerous.
5. Earthquake
Minor defects such as cracks in the embankment may be the first visual sign of a major problem
which could lead to failure of the structure. The seriousness of all deficiencies should be
evaluated by someone experienced in dam design and construction. A qualified professional
engineer can recommend appropriate permanent remedial measures.
16
7. Toe Drain: It is a drain constructed at the downstream slope of an earthen dam to collect and
drain away the seepage water collected by the drain filters.
8. Transition Filter: It is a component of an earthen dam section which is provided with core and
consists of an intermediate grade of material placed between the core and the shells to serve as a
filter and prevent lateral movement of fine material from the core.
Fig.. Cross-section of an Earthen Dam with Various Components. (Source: Michael and Ojha, 2012)
Advantages
1. Design procedures are straightforward and easy.
2. Local natural materials are used.
3. Comparatively small establishment and equipment are required.
4. Earth fill dams resist settlement and movement better than more rigid structures and can be more
suitable for areas where earth movements are common.
Disadvantages
1. An earthen embankment is easily damaged or destroyed by water flowing on, over or against it.
Thus, a spillway and adequate upstream protection are essential for any earthen dam.
2. Designing and constructing adequate spillways is usually the most technically difficult part of any
dam building work. Any site with a poor quality spillway should not be used.
3. If it is not adequately compacted during construction, the dam will have weak structure prone to
seepage.
4. Earthen dams require continual maintenance to prevent erosion, tree growth, subsidence, animal
and insect damage and seepage.
17
Types of Earthen Dam
2. Based on the mechanical characteristics of earth materials used in making the section of dam:
(a) Homogeneous Earthen Dams: It is composed of one kind of material (excluding slope protection).
The material used must be sufficiently impervious to provide an adequate water barrier, and the slopes
must be moderately flat for stability and ease of maintenance (Fig.).
18
Fig.. Diaphragm Earthen Dam. (Source: Michael and Ojha, 2012)
Design Criteria
Following main design criteria may be laid down for the safety of an earth dam:
1. To prevent hydraulic failures the dam must be so designed that erosion of the embankment is
prevented. For this purpose, the following steps should be followed:
(a) Spillway capacity is sufficient to pass the peak flow.
(b) Overtopping by wave action at maximum water level is prevented.
(c) The original height of structure is sufficient to maintain the minimum safe freeboard after
settlement has occurred.
(d) Erosion of the embankment due to wave action and surface runoff does not occur.
(e) The crest should be wide enough to withstand wave action and earthquake shock.
2. To prevent the failures due to seepage:
(a) Quantity of seepage water through the dam section and foundation should be limited.
(b) The seepage line should be well within the downstream face of the dam to prevent sloughing.
(c) Seepage water through the dam or foundation should not remove any particle or in other words
cause piping.
(d) There should not be any leakage of water from the upstream to the downstream face. Such leakage
may occur through conduits, at joints between earth and concrete sections or through holes made by
aquatic animals.
3. To prevent structural failures:
(a) The upstream and downstream slopes of the embankment should be stable under all loading
conditions to which they may be subjected including earthquake.
(b) The foundation shear stresses should be within the permissible limits of shear strength of the material.
Design of Earthen Dam
The preliminary design of earthen dam is done on the basis of past experiences. For designing purpose
several parameters, given below should be considered.
1. Top Width
2. Free Board
3. Settlement Allowance
4. Casing or Outer Shell
5. Cut-off Trench
6. Downstream Drainage System
1. Top Width: Minimum top width (W) should be such that it can enhance the practicability and protect
it against the wave action and earth wave shocks. Sometimes it is also used for transportation purposes. It
depends upon the height of the earthen dam and can be calculated as follows:
19
where H = the height of the dam (m), for Indian conditions it should not be less than 6 m.
Free board: It is the vertical distance between the top of the dam and the full supply level of the reservoir
or the added height. It acts as a safety measure for the dam against high flow condition that is waves and
runoff from storms greater than the design frequency from overtopping the embankment. The
Recommended values of free board for different heights of earthen dams, given by U.S.B.R., are given in
Table.
Table . Recommended Values of Free Board given by U.S.B.R.
Nature of spillway Height of dam Free board
Free Any Minimum 2 m and maximum 3 m over the maximum flood level
If fetch length or exposure is given then the free board can also be calculated by Hawksley's formula:
20
Cutoff Trench: It is provided to reduce the seepage through the foundation and also to reduce the piping
in the dam. It should be aligned in a way that its central line should be within the upstream face of the
impervious core. Its depth should be more than 1 m. Bottom width of cutoff trench (B) is calculated as:
where h = reservoir head above the ground surface (m); and d = depth of cutoff trench below the ground
surface (m).
4. Downstream Drainage System: It is performed by providing the filter material in the earthen dam
which is more pervious than the rest of the fill material. It reduces the pore water pressure thus adding
stability to the dam.
Three types of drains used for this purpose are:
a) Toe Drains
b) Horizontal Blanket
c) Chimney Drains.
Phreatic line is also known as seepage line or saturation line. It is defined as an imaginary line within a
dam section, below which there is a positive hydrostatic pressure and above it there is a negative
hydrostatic pressure. The hydrostatic pressure represents atmospheric pressure which is equal to zero on
the face of phreatic line. Above the phreatic line, there is capillary zone, also called as capillary fringe, in
which the hydrostatic pressure is negative. The flow of seepage water, below the phreatic line, reduces the
effective weight of the soil; as a result shear strength of a soil is reduced due to increased intergranular
pressure in earth fill material.
In this case, before going directly for derivation, the important features of phreatic line must be known.
From the experimental evidence, it has been found that, the seepage line is pushed down by the toe filter
21
and is very close to parabolic shape except at the junction point of the upstream face. The upstream face
of the dam represents 100% equipotential line when it is covered by the water; under this condition the
seepage line should be drawn perpendicular to this face at the junction point.
Casagrande method is used for deriving the phreatic line (Fig); the procedure is described as follows:
22
Where, s = focal distance (FH)
From equation,
1
This is the desired equation of base parabola.
For deriving the expression of discharge (q) for the earth dam equipped with horizontal filter, the Darcy's
law is used. According to which, the discharge (q) through vertical section PD, is equal to:
2
Partial differentiation of Eqn.2, resulted
3
Substituting the value of in Eqn. 3, the rate of seepage flow through the dam is given by:
This is the expression for computing the rate of seepage discharge through the body of earthen dam, in
terms of focal distance s. The distance s can be determined either graphically or analytically.
Considering C as co-ordinate, the value of s can be obtained as:
From Eqn: 1
At point C, x = D and y = H
23
By using this equation, if the value of coefficient of permeability (k) and focal distance (s) are known, the
discharge (q) can be calculated. This gives an accurate value of seepage rate and is applicable to such
dams, which are provided with horizontal drainage (filter) system but can also be used for other types of
dam section.
24
Let, if a is the slope angle of the discharge face with the horizontal is known, and then various values
Here, JF indicates the distance of the focus from the point, where base of parabola cuts downstream face.
The values of and can be obtained by Eqn and Table.
Estimation of seepage
Example:
An earth dam made of a homogeneous material has a horizontal filter and other parameters
as shown in the figure. Determine the phreatic line and the seepage quantity through the
body of the dam.
25
For the origin of the Cartesian co-ordinate system at the face of the filter (point F), the
equation of the parabola of the seepage line can be expressed as:
2
y
2
x xS
At point A, x = 65m, and y = 20m. Inserting into the parabola equation, S = 3.07m. Working
out a few more points from the equation, the parabola can be easily drawn and corrected for
the curve at the upstream face of the dam, so as to get the seepage line.
x -1.51 0 10 15 25 30 40 45 55 65
2
y 0 9.06 69.26 99.36 159.56 189.66 249.86 279.96 340.16 400.36
y 0 3.01 8.32 9.97 12.63 13.77 15.81 16.73 18.44 20.01
26
The seepage line will, however, emerge out at K, meeting the downstream face tangentially there.
The portion KF is known as discharge face and always saturated. The correction JK (say ∆a) by
which the parabola is to be shifted downward can be determined as follows:
‡ a
α in degrees
a a
o
30 0.36
o
60 0.32
o
90 0.26
o
120 0.18
o
135 0.14
o
150 0.10
o
180 0.0
α is the angle which the discharge face makes with the horizontal. a and ∆a can be connected by
the general equation;
27
Module 3
Spillways
Spillway is the most important component of the dam which serves to release excess flood from a
reservoir efficiently and safely. It is the most expensive of all the appurtenances structure. Its capacity is
determined from the hydrological studies over the drainage area.
Spillway components include;
a. Entrance channel: to minimize head loss and to obtain uniform distribution of flow over the spillway
crest
b. Control structure: to regulate and control the outflow. It may consist of a sill, weir, orifice, tube, or
pipe.
c. Discharge channel: to convey the discharge from the control structure to the terminal
structure/stream bed. The conveyance structure may be the downstream face of a concrete dam, an
open channel excavated along the ground surface, a closed cut-and-cover conduit placed through or
under a dam, or a tunnel excavated through an abutment.
d. Terminal structure: to dissipate excess energy of the flow in order to avoid scouring of the stream
bed
e. Outlet channel: to safely convey the flow from the terminal structure to the river channel.
b. Uncontrolled (Ungated) spillway: is a spillway, the crest of which permits water to escape
automatically, as the water level in the reservoir rises above the crest.
Types of Spillway
1. Free overfall (straight drop) spillway
28
1) Free Overfall / Straight drop Spillway:
In this type of spillway, the water freely drops down from the crest, as for an arch dam (Figure 1)
also for a decked over flow dam with a vertical or adverse inclined downstream face (Figure 2). Flows
may be free discharging, as will be the case with a sharp-crested weir or they may be supported along a
narrow section of the crest. Water freely falls from crest under the action of gravity. Since vacuum is
created in the under-side portion of the falling jet, sufficient ventilation of nappe is required in order to
avoid pulsating and fluctuating effects of the jet.
This type of spillway is the most common type adopted in the field. It divides naturally into three
zones i.e. Crest, spillway face and the toe. The concept evolves from replacing the lower nappy of the
flow over thin plate weir by solid boundary. The overflow type spillway has a crest shaped in the form of
an ogee or S-shape. The upper curve of the ogee is made to conform closely to the profile of the lower
nappy of a ventilated sheet of water falling from a sharp crested weir (figure 3). Flow over the crest of an
overflow spillway is made to adhere to the face of the profile by preventing access of air to the underside
of the sheet of flowing water.
Naturally, the shape of the overflow spillway is designed according to the shape of the lower nappe
of a free flowing weir conveying the discharge flood any discharge higher than the design flood passing
through the overflow spillway would try to shoot forward and get detached from the spillway surface,
which reduces the efficiency of the spillway due to the presence of negative pressure between the sheet of
29
water and spillway surface. For discharges at designed head, the spillway attains near-maximum
efficiency.
Fig- Outflow from a freely falling weir properly Fig Section of an Ogee spillway with vertical u/s
ventilated from below, face
A chute spillway, variously called as open channel or trough spillway, is one whose discharge is
conveyed from the reservoir to the downstream river level through an open channel, placed either along a
dam abutment or through a saddle. The control structure for the chute spillway need not necessarily be an
overflow crest, and may be of the side-channel type, as has been shown in Figure 5. Generally, the chute
spillway has been mostly used in conjunction with embankment dams, like the Tehri dam. Chute
spillways are simple to design and construct and have been constructed successfully on all types of
foundation materials, ranging from solid rock to soft clay. Chute spillways ordinarily consist of an
entrance channel, a control structure, a discharge channel, a terminal structure, and an outlet channel.
30
Fig- side channel entry to a Chute spillway
4. Side Channel Spillway:
A side channel spillway is one in which the control weir is placed approximately parallel to the upper
portion of the discharge channel, as may be seen in fig 6. The flow over the crest falls into a narrow
trough opposite to the weir, turns an approximate right angle, and then continues into the main discharge
channel. The side channel design is concerned only with the hydraulic action in the upstream reach of the
discharge channel and is more or less independent of the details selected for the other spillway
components.
Discharge characteristics of a side channel spillway are similar to those of an ordinary overflow
spillway and are dependent on the selected profile of the weir crest. Although the side channel is not
hydraulically efficient, nor inexpensive, it has advantages which make it adoptable to spillways where a
long overflow crest is required in order to limit the afflux (surcharge held to cause flow) and the
abutments are steep and precipitous.
31
Fig- sketch of a side-channel spillway
A Shaft Spillway is one where water enters over a horizontally positioned lip, drops through a vertical
or sloping shaft, and then flows to the downstream river channel through a horizontal or nearly horizontal
conduit or tunnel. A drop inlet spillway can be used advantageously at dam sites that are located in
narrow gorges where the abutments rise steeply.
Discharge characteristics of the drop inlet spillway may vary with the range of head. The head
increases, the flow pattern would change from the initial weir flow over crest to tube flow and then finally
to pipe flow in the tunnel. This type of spillway attains maximum discharging capacity at relatively low
heads. However, there is little increase in capacity beyond the designed head, should a flood larger than
the selected inflow design flood occur.
32
Fig- Section through a shaft spillway
Where a closed channel is used to convey the discharge around a dam through the adjoining hill sides, the
spillway is often called a tunnel or conduit spillway. The closed channel may take the form of a vertical or
inclined shaft, a horizontal tunnel through earth or rock, or a conduit constructed in open cut and
backfilled with earth materials. Most forms of control structures, including overflow crests, vertical or
inclined orifice entrances, drop inlet entrances, and side channel crests, can be used with tunnel spillways.
Tunnel spillways are advantageous for dam sites in narrow gorges with steep abutments or at sites where
there is danger to open channels from rock slides from the hills adjoining the reservoir. Conduit spillways
are generally most suited to dams in wide valleys as in such cases the use of this types of spillway would
enable the spillway to be located under the dam very close to the stream bed.
33
Fig-8 Tunnel spillway with a morning glory entrance
7. Siphon spillway:
A siphon spillway is a closed conduit system formed in the shape of an inverted U, positioned so that
the inside of the bend of the upper passageway is at normal reservoir storage level. This type of siphon is
also called a Saddle siphon spillway. The initial discharges of the spillway, as the reservoir level rises
above normal, are similar to flow over a weir. Siphonic action takes place after the air in the bend over the
crest has been exhausted. Continuous flow is maintained by the suction effect due to the gravity pull of
the water in the lower leg of the siphon.
Siphon spillways comprise usually of five components, which include an inlet, an upper leg, a throat
or control section, a lower leg and an outlet. Another type is hooded type of siphone spillway in which
reinforced concrete hood is constructed over an ordinary overflow section of a gravity dam. The inlet of
this hood is kept submerged so as to prevent entry of debris and ice. A small depriving hood is kept above
the main hood and both these hoods are connected by air vent and head of the depriver hood is kept at
normal pool level.
34
Fig- Saddle Siphon
For the free overflow ogee a sound rock foundation is assumed to exist for the construction of the gravity
dam and a ski jump is found to be satisfactory at the toe of the ogee for the dissipation of energy. From
the topography it is observed that there is no need for the construction of an approach channel.
Design data
Design discharge (Q) = 1410 m3/s
35
River bed elevation = 1390 m
The design head is 6m, but a negative pressure head of 1.0 m is assumed to develop in the crest of the
spillway for economic reasons and the workmanship is assumed to be good enough not to create rough
surface for this negative head to result in cavitation problem. The vapor pressure of water for the spillway
site is 3.595m
Therefore, from the negative pressure head (hu) specified the corresponding design head (hdes) is
hu = h(1-h/hdes) -1. = 6(1- 6/hdes) hdes = 5.14 m
P/h = 6
This value (P/h = 6) hence the effect of approach velocity is too small and can be neglected. But a case
where the dam is filled by sediment is considered and P is decreased. Therefore P is assumed to be 2m.
P/h = 2/6
= 0.333
The respective value of Co (coefficient of discharge) from chart is
Co = 2.175
qo = CoH1.5 = 2.175 * 6 1.5 = 32 m3/s/m vo = q/(P + h) = 32/(2+6) = 4 m/sec
Velocity head (ha)
ha = vo2/2*g = 16/19.62 = 0.81 m adding 10% of ha for entrance and other losses h a = 0.9 m
Therefore, He = 6.9 m
Correction for the coefficient of discharge
P/He = 0.29
Co = 2.18 hence, no appreciable change from the previous value.
For an upstream slope of 2:3
Ci/Co = 1.026
Submergence effect is not considered here because the downstream apron is much below the crest level
for any submergence to occur for the design discharge. For similar reason the correction for downstream
apron is not carried out.
Therefore, the final corrected value of the coefficient of discharge for the ogee is
C = 2.18 *1.026 = 2.23
From the discharge equation by Polini
Q = CL‟He1.5 1410 = 2.23 *L‟* 6.9*1.5 L‟ = 35.00m
For the provision of round nosed piers (kp = 0.01) at every 8m interval along the ogee
Number of piers required = 4
Pier thickness is 2m
Rounded abutments with headwalls at 900 to the direction of flow are used (ka = 0.1)
36
The effective length of the crest will then be
Adding the pier width the total width of the crest will be B = 37.0 + 8 = 45.0 m
The profile of the nape is determined based on the charts available on USBR design of small dams.
Ha/He = 0.9/6.9 = 0.13
For an upstream slope of 1:1 crest position
Xc/He = 0.195 Xc = 1.35m Yc/He = 0.07 Yc = 0.49m
Profile upstream of the crest
R1/He = 0.465
R1 = 3.21m R2/He = 0.367
R2 = 2.53m
Down stream of the crest
Y/He = -k(X./He)n values of the constants are found(from charts on USBR) to be
K = 0.52
n = 1.763
y = -0.119 x1.763
Tabulating values for the above equation,
The point of tangency in the downstream for a slope of m= 0.6
The value of a is obtained from table (a = 1.80)
YT = -HeK(mkn)n/(1-a)
= -9.4m
The coordinate values obtained so far for the ogee nape profile are tabulated and plotted as follows.
X Elevation
-30 1390
-20.5 1390
-20 1390
-1.35 1419.5
-1 1419.7
0 1420
1.3 1419.8
2 1419.6
2.5 1419.4
3 1419.2
3.5 1418.9
4 1418.6
4.5 1418.3
5 1418
5.5 1417.6
6 1417.2
37
6.5 1416.8
7 1416.3
7.5 1415.8
8 1415.3
8.5 1414.8
9 1414.3
9.5 1413.7
10 1413.1
10.5 1412.5
11 1411.8
11.5 1411.2
12 1410.5
13 1409.1
24.28 1390
25 1390
30 1390
38
39
40
41
Energy dissipation devices
The flood water discharging through the spillway has to flow down from a higher elevation at the
reservoir surface level to a lower elevation at the natural river level on the downstream through a passage,
which is also considered a part of the spillway. At the bottom of the channel, where the water rushes out
to meet the natural river, is usually provided with an energy dissipation device that kills most of the
energy of the flowing water. These devices, commonly called as Energy Dissipators, are required to
prevent the river surface from getting dangerously scoured by the impact of the out falling water.
42
(C) Roller Bucket Types
Diversion Headwork’s
The works, which are constructed at the head of the canal, in order to divert the river water towards the
canal, so as to ensure a regulated and continuous supply of silt-free water with a certain minimum -head
into the canal, are known as Diversion Head Works
43
Gravity and Non-Gravity Weirs
When the weight of the weir (I.e. its body and floor) balances the uplift pressure caused by .the head of the
water seeping below the weir, it is called a Gravity weir. On the other hand, if the weir floor is designed
continuous with the divide piers as reinforced structure, such that the weight of concrete slab together with
the weight of divide piers, keep the structure safe against the uplift ; then the structure may be called as a
Non gravity Weir.
44
Fig. Typical Layout of Diversion Head-Works.
45
Fig. Rock-fill weir
(2) Under-sluices
A comparatively less turbulent pocket of water is created near the canal head regulator by constructing
under-sluice portion of the weir. A divide wall separates the main weir portion from the under-sluice
portion of the weir. The crest of the under-sluice portion "of the weir is kept at a lower level than, the crest
of the normal portion of the weir. Normally, the crest level of the under-sluices is kept equal to the deepest
bed level of the river during non-monsoon season; whereas, the crest level of the 'weir' is kept higher by
about 1 to 1.5 m.
46
(3) Divide wall
The 'divide wall' is a masonry or a concrete wall constructed at right angle to the axis of the weir, and
separates the 'weir proper' from the 'under-sluices'. The divide wall extends on the upstream side beyond
the beginning of the canal head regulator; and on the downstream side, it extends up to the end of loose
protection of the under sluices. The top width of divide wall is about 1.5 to 2.5 metres. These walls are
founded on wells closely spaced beyond, the pucca floor upto the end. The wells are taken well below the
deepest possible scour. Typical cross-section of the divide wall on pucca floor and beyond the pucca floor
are shown in Fig. (a) and (b).
a) Cross-section of Divide Wall on Pucca floor b) Cross-section of Divide Wall beyond Pucca floor.
River training works are required near the weir site in order to ensure a smooth and an axial flow of water,
and thus, to prevent the river from outflanking the works due to a change in its course. The river training
work required on a canal headworks, are
(i) Guide banks
(ii) Marginal bunds and
(iii) Spurs or groynes.
(i) Guide Bank
When a barrage is constructed across a river which flows through the alluvial soil, the guide banks must
be constructed on both the approaches to protect the structure from erosion.
Guide bank serves the following purposes:
It protects the barrage from the effect of scouring and erosion.
It provides a straight approach towards the barrage.
It controls the tendency of changing the course of the river.
It controls the velocity of flow near the structure.
47
(ii)Marginal Bunds
The marginal bunds are earthen embankments which are constructed parallel to the river bank on one or
both the banks according to the condition. The top width is generally 3 m to 4 m. The side slope on the
river side is generally 1.5: 1 and that on the country side is 2:1.
It prevents the flood water or storage water from entering the surrounding area which may be
submerged or may be water logged.
It retains the flood water or storage water within a specified section.
It protects the towns and villages from devastation during the heavy flood.
It protects valuable agricultural lands.
(iii)Spurs or groynes
These are temporary structures permeable in nature provided on the curve of a river to protect the river
o o
bank from erosion. These are projected from the river bank towards the bed making angles 60 to 75
with the bank of the river. The length of the spurs depends on the width of the river and the sharpness
of the curve. The function of the spurs is to break the velocity of flow and to form a water pocket on the
upstream side where the sediments get deposited. Thus the reclamation of land on the river bank can be
achieved. The spurs may be of the following types:
Bamboo Spur
Timber Spur
Boulder Spur
48
(6) Canal Head Regulator
A canal head regulator (C.H.R.) is provided at the head of the off-taking canal, and serves the following
functions:
(i) It regulates the supply of water entering the canal.
(ii) It controls the entry of silt in the canal.
(iii) It prevents the river floods from entering the canal.
49
Bligh’s Creep Theory for Seepage Flow
According to Bligh’s Theory, the percolating water follows the outline of the base of the foundation of
the hydraulic structure. In other words, water creeps along the bottom contour of the structure. The length
of the path thus traversed by water is called the length of the creep. Further, it is assumed in this theory,
that the loss of head is proportional to the length of the creep. If HL is the total head loss between the
upstream and the downstream, and L is the length of creep, then the loss of head per unit of creep length
(i.e. HL/L) is called the hydraulic gradient. Further, Bligh makes no distinction between horizontal and
vertical creep.
Consider a section a shown in Fig above. Let HL be the difference of water levels between upstream
and downstream ends. Water will seep along the bottom contour as shown by arrows. It starts percolating
at A and emerges at B. The total length of creep is given by
L = d1 + d1 + L1 + d2 + d2 + L2 + d3 + d3
= b + 2(d1 + d2 + d3)
50
Head loss per unit length or hydraulic gradient =
HL =H L
b 2 d1 d2 d3 L
H H
HL L L
Head losses equal to 2d1 , 2d 2 , 2d3 ; will occur respectively, in the planes of three
L L L
vertical cut offs. The hydraulic gradient line (H.G. Line) can then be drawn as shown in figure above.
The ordinates of the H.G line above the bottom of the floor represent the residual uplift water head at
each point. Say for example, if at any point, the ordinate of H.G line above the bottom of the floor is 1 m,
then 1 m head of water will act as uplift at that point. If h′ meters is this ordinate, then water pressure
equal to h′ meters will act at this point, and has to be counterbalanced by the weight of the floor of
thickness say t.
Uplift pressure = γw ×h′ [where γw is the unit weight of water]
Downward pressure = (γ w ×G).t [Where G is the specific gravity of the floor material]
For equilibrium,
γw ×h′ = γw ×G. t
h′ = G × t
Subtracting t on both sides, we get
(h′ – t) = (G×t – t) = t (G – 1)
'
t= h t = h
G 1 G 1
Where, h′ – t = h = Ordinate of the H.G line above the top of the floor
G – 1 = Submerged specific gravity of the floor material
51
Khosla’s Theory and Concept of Flow Nets
Many of the important hydraulic structures, such as weirs and barrage, were designed on the basis of
Bligh’s theory between the periods 1910 to 1925. In 1926 – 27, the upper Chenab canal siphons, designed
on Bligh’s theory, started posing undermining troubles. Investigations started, which ultimately lead to
Khosla’s theory. The main principles of this theory are summarized below:
(a) The seepage water does not creep along the bottom contour of pucca flood as started by Bligh, but
on the other hand, this water moves along a set of stream-lines. This steady seepage in a vertical
plane for a homogeneous soil can be expressed by Laplacian equation:
d2 +d 2
2
2
dx dz
Where, φ = Flow potential = Kh; K = the co-efficient of permeability of soil as defined
by Darcy’s law, and h is the residual head at any point within the soil.
The above equation represents two sets of curves intersecting each other orthogonally. The resultant
flow diagram showing both of the curves is called a Flow Net.
Stream Lines: The streamlines represent the paths along which the water flows through the sub-soil.
Every particle entering the soil at a given point upstream of the work, will trace out its own path and will
represent a streamline. The first streamline follows the bottom contour of the works and is the same as
Bligh’s path of creep. The remaining streamlines follows smooth curves transiting slowly from the outline
of the foundation to a semi-ellipse, as shown below.
Equipotential Lines: (1) Treating the downstream bed as datum and assuming no water on the
downstream side, it can be easily started that every streamline possesses a head equal to h 1 while entering
the soil; and when it emerges at the down-stream end into the atmosphere, its head is zero. Thus, the head
h1 is entirely lost during the passage of water along the streamlines.
Further, at every intermediate point in its path, there is certain residual head (h) still to be dissipated
in the remaining length to be traversed to the downstream end. This fact is applicable to every streamline,
and hence, there will be points on different streamlines having the same value of residual head h. If such
points are joined together, the curve obtained is called an equipotential line.
52
Every water particle on line AB is having a residual head h = h1, and on CD is having a residual head
h = 0, and hence, AB and CD are equipotential lines.
Since an equipotential line represent the joining of points of equal residual head, hence if piezometers
were installed on an equipotential line, the water will rise in all of them up to the same level as shown in
figure below.
(b) The seepage water exerts a force at each point in the direction of flow and tangential to the
streamlines as shown in figure above. This force (F) has an upward component from the point
where the streamlines turns upward. For soil grains to remain stable, the upward component of this
force should be counterbalanced by the submerged weight of the soil grain. This force has the
maximum disturbing tendency at the exit end, because the direction of this force at the exit point is
vertically upward, and hence full force acts as its upward component. For the soil grain to remain
stable, the submerged weight of soil grain should be more than this upward disturbing force. The
disturbing force at any point is proportional to the gradient of pressure of water at that point (i.e.
dp/dt). This gradient of pressure of water at the exit end is called the exit gradient. In order that the
soil particles at exit remain stable, the upward pressure at exit should be safe. In other words, the
exit gradient should be safe.
53
Khosla’s Method of independent variables for determination of pressures and exit gradient
for seepage below a weir or a barrage
In order to know as to how the seepage below the foundation of a hydraulic structure is taking place,
it is necessary to plot the flow net. In other words, we must solve the Laplacian equations. This can be
accomplished either by mathematical solution of the Laplacian equations, or by Electrical analogy method,
or by graphical sketching by adjusting the streamlines and equipotential lines with respect to the boundary
conditions. These are complicated methods and are time consuming. Therefore, for designing hydraulic
structures such as weirs or barrage or pervious foundations, Khosla has evolved a simple, quick and an
accurate approach, called Method of Independent Variables.
In this method, a complex profile like that of a weir is broken into a number of simple profiles; each
of which can be solved mathematically. Mathematical solutions of flownets for these simple standard
profiles have been presented in the form of equations given in Figure (11.5) and curves given in Plate
(11.1), which can be used for determining the percentage pressures at the various key points. The simple
profiles which hare most useful are:
(i) A straight horizontal floor of negligible thickness with a sheet pile line on the u/s end and d/s end.
(ii) A straight horizontal floor depressed below the bed but without any vertical cut-offs.
(iii) A straight horizontal floor of negligible thickness with a sheet pile line at some intermediate point.
The key points are the junctions of the floor and the pole lines on either side, and the bottom point of
the pile line, and the bottom corners in the case of a depressed floor. The percentage pressures at these key
points for the simple forms into which the complex profile has been broken is valid for the complex profile
itself, if corrected for
(a) Correction for the Mutual interference of Piles
(b) Correction for the thickness of floor
(c) Correction for the slope of the floor
C = 19
D d D
'
b b
Where,
b′ = The distance between two pile lines.
D = The depth of the pile line, the influence of which has to be determined on the neighboring pile
of depth
d. D is to be measured below the level at which interference is desired.
d = The depth of the pile on which the effect is considered
b = Total floor length
The correction is positive for the points in the rear of back water, and subtractive for the points
forward in the direction of flow. This equation does not apply to the effect of an outer pile on an
intermediate pile, if the intermediate pile is equal to or smaller than the outer pile and is at a distance less
than twice the length of the outer pile.
54
Suppose in the above figure, we are considering the influence of the pile no (2) on pile no (1) for
correcting the pressure at C1. Since the point C1 is in the rear, this correction shall be positive. While the
correction to be applied to E2 due to pile no (1) shall be negative, since the point E2 is in the forward
direction of flow. Similarly, the correction at C2 due to pile no (3) is positive and the correction at E2 due
to pile no (2) is negative.
(b) Correction for the thickness of floor:
In the standard form profiles, the floor is assumed to have
negligible thickness. Hence, the percentage pressures
calculated by Khosla’s equations or graphs shall pertain to the
top levels of the floor. While the actual junction points E and
C are at the bottom of the floor. Hence, the pressures at the
actual points are calculated by assuming a straight line
pressure variation.
′
Since the corrected pressure at E1 should be less than the calculated pressure at E1 , the correction to be
′
applied for the joint E1 shall be negative. Similarly, the pressure calculated C 1 is less than the corrected
pressure at C1, and hence, the correction to be applied at point C 1 is positive.
The correction factor given above is to be multiplied by the horizontal length of the slope and divided
by the distance between the two pile lines between which the sloping floor is located. This correction is
applicable only to the key points of the pile line fixed at the start or the end of the slope.
Exit gradient (GE)
It has been determined that for a standard form consisting of a floor length (b) with a vertical cutoff of
depth (d), the exit gradient at its downstream end is given by
GE = H 1
d
2
Where, λ = 11
2
α = b/d
H = Maximum Seepage Head
55
Problem-2
Determine the percentage pressures at various key points in figure below. Also determine the exit gradient
and plot the hydraulic gradient line for pond level on upstream and no flow on downstream
Solution:
(1) For upstream Pile Line No. 1
Total length of the floor, b = 57.0 m
Depth of u/s pile line, d = 154 – 148 = 6 m
α = b/d = 57/6 = 9.5
1/α = 1/9.5 = 0.105
From curve plate 11.1 (a)
φC1 = 100 – 29 = 71 %
φD1 = 100 – 20 = 80 %
These values of φC1 must be corrected for three corrections as below:
Since the point C1 is in the rear in the direction of flow, the correction is (+) ve.
Correction due to pile interference on C 1 = 1.88 % (+ ve)
56
57
(b) Correction at C1 due to thickness of floor: 154
′ ′
Pressure calculated from curve is at C1 , (Fig. 7.1) but we C1 1.0 m
want the pressure at C1. Pressure at C1 shall be more than C1 153
′ ′
at C1 as the direction of flow is from C1 to C1 as shown;
and hence, the correction will be + ve and
80% 71% FLOW
= × (154 – 153)
154 148
= (9/6)×1
D1, 148
= 1.5% (+ ve)
Fig: 5.1
(c) Correction due to slope at C1 is nil, as this point is neither situated at the start nor at the end of a
slope Corrected (φC1) = 71 % + 1.88 % + 1.5 %
= 74.38 % (ans)
And (φD1) = 80 %
58
(c) Correction at E2 due to slope is nil, as the point E2 is neither situated at the start of a slope nor at the
end of a shape
Hence, corrected percentage pressure at E2 = Corrected φE2 = (70 – 1.88 – 1.17) % = 66.95 %
Corrections for φC2
(a) Correction at C2 due to pile interference. Pressure at C2 is affected by pile No.(3) and since the
point C2 is in the back water in the direction of flow, this correction is (+) ve. The amount of this
correction is given as:
Correction = 19 D d D
Where, D = Depth of pile No.3, the effect of
b
'
b which is considered below the level at which
interference is desired = 153 – 141.7 = 11.3 m
11 11 5 d = Depth of pile No. 2, the effect on
= 19× which is considered = 153 – 148= 5 m
40 57
b′ = Distance between two piles (2 &3) = 40 m
= 2.89 % (+ ve) b = Total floor length = 57 m
o Correction at C2 due to floor thickness. From Fig. 11.10, it can be easily stated that the pressure at
′ ′
C2 shall be more than at C2 , and since the observed pressure is at C2 , this correction shall be + ve and
its amount is the same as was calculated for the point E2 = 1.17 %
Hence, correction at C2 due to floor thickness = 1.17 % (+ ve)
p Correction at C2 due to slope. Since the point C2 is situated at the start of a slope of 3:1, i.e. an up
slope in the direction of flow; the correction is negative
Correction factor for 3:1 slope from table 11.4 = 4.5
Horizontal length of the slope = 3 m
Distance between two pile lines between which the sloping floor is located = 40 m
Actual correction = 4.5 × (3/40) = 0.34 % (- ve)
Hence, corrected φC2 = (56 + 2.89 + 1.17 – 0.34) % = 59.72 %
Correction = 19
D d D Where, D = Depth of pile No.2, the effect of
b
'
b which is considered = 150.7 – 148 = 2.7
m d = Depth of pile No. 3, the effect on
2.7 9 2.7 which is considered = 150 – 141.7 = 9 m
= 19×
40 57 b′ = Distance between two piles = 40 m
= 1.02 % (– ve) b = Total floor length = 57 m
(b) Correction due to floor thickness
From Fig. 7.3, it can be stated easily that the pressure at E 3 E3
′
′
shall be less than at E3 , and hence the pressure observed form E3
′
curves is at E3 ; this correction shall be – ve and its amount
38% 32%
(1) × 1.3 = (16/10.3)×1.3
152 141.7
(2) 0.76 % (– ve)
Fig:5.3
59
Correction due to slope at E3 is nil, as the point E3 is neither situated at the start nor at the end of
any slope
Hence, corrected φE3 = (38 – 1.02 – 0.76) % = 36.22 %
The corrected pressures at various key points are tabulated below in Table below
Exit gradient
Let the water be headed up to pond level, i.e. on RL 158 m on the upstream side with no flow
downstream
The maximum seepage head, H = 158 – 152 = 6 m
The depth of d/s cur-off, d = 152 – 141.7 = 10.3 m
Total floor length, b = 57 m
o = b/d = 57/10.3 = 5.53
Hence, the exit gradient shall be equal to 0.105, i.e. 1 in 9.53, which is very much safe.
o
= 0.18
60
Module 4
Cross Drainage Works
Introduction
In an irrigation project, when the network of main canals, branch canals, distributaries, etc. are
provided, then these canals may have to cross the natural drainages like rivers, streams, nallahs, etc at
different points within the command area of the project. The crossing of the canals with such obstacle
cannot be avoided. So, suitable structures must be constructed at the crossing point for the easy flow of
water of the canal and drainage in the respective directions. These structures are known as cross-drainage
works.
61
Aqueduct
The aqueduct is just like a bridge where a canal is taken over the deck supported by piers instead of a
road or railway. Generally, the canal is in the shape of a rectangular trough which is constructed with
reinforced cement concrete. Sometimes, the trough may be of trapezoidal section.
An inspection road is provided along the side of the trough.
The bed and banks of the drainage below the trough is protected by boulder pitching with cement
grouting.
The section of the trough is designed according to the full supply discharge of the
canal.
A free board of about 0.50 m should be provided.
The height and section of piers are designed according to the highest flood level and velocity of
flow of the drainage.
The piers may be of brick masonry, stone masonry or reinforced cement concrete.
Deep foundation (like well foundation) is not necessary for the piers. The concrete foundation
may be done by providing the depth of foundation according to the availability of hard soil.
Siphon Aqueduct
The siphon aqueduct, the bed of the drainage is depressed below the bottom level of the canal trough by
providing sloping apron on both sides of the crossing.
o The sloping apron may be constructed by stone pitching or cement concrete.
o The section of the drainage below the canal trough is constructed with cement concrete in the form
of tunnel. This tunnel acts as a siphon.
o Cut off walls are provided on both sides of the apron to prevent scouring.
o Boulder pitching should be provided on the upstream and downstream of the cut-off walls.
o The other components like canal trough, piers, inspection road, etc. should be designed according
to the methods adopted in case of aqueduct.
62
Super Passage
The super passage is just opposite of the aqueduct. In this case, the bed level of the drainage is above
the fully supply level of the canal. The drainage is taken through a rectangular or trapezoidal trough of
channel which is constructed on the deck supported by piers.
The section of the drainage trough depends on the high flood discharge.
A free board of about 1.5 m should be provided for safety.
The trough should be constructed of reinforced cement concrete.
The bed and banks of the canal below the drainage trough should be protected by boulder pitching
or lining with concrete slabs.
The foundation of the piers will be same as in the case of aqueduct.
63
Siphon Super Passage
It is just opposite siphon aqueduct. In this case, the canal passes below the drainage trough. The section
of the trough is designed according to high flood discharge. The bed of the canal is depressed below the
bottom level of the drainage trough by providing sloping apron on both sides of the crossing.
The sloping apron may be constructed with stone pitching or concrete slabs.
The section of the canal below the trough is constructed with cement concrete in the form of tunnel
which acts as siphon.
Cut-off walls are provided on upstream and downstream side of sloping pron.
Other components are same as in the case of siphon aqueduct.
Level Crossing
The level crossing is an arrangement provided to regulate the flow of water through the drainage and
the canal when they cross each other approximately at the same bed level. The level crossing consists of
the following components:
Crest Wall: It is provided across the drainage just at the upstream side of the crossing point. The top level
of the crest wall is kept at the full supply level of the canal.
Drainage Regulator: It is provided across the drainage just at the downstream side of the crossing point.
The regulator consists of adjustable shutters at different tiers.
Canal Regulator: It is provided across the canal just at the downstream side of the crossing point. This
regulator also consists of adjustable shutters at different tiers.
Crest wall
Canal
Canal
River
River Regulator Regulator
64
Inlet and outlet
In the crossing of small drainage with small channel no hydraulic structure is constructed. Simple
openings are provided for the flow of water in their respective directions. This arrangement is known as
inlet and outlet.
o In this system, an inlet is provided in the channel bank simply by open cut and the drainage water
is allowed to join the channel
o At the points of inlet and outlet, the bed and banks of the drainage are protected by stone pitching.
65
It was stated earlier that the velocity through syphon barrels is limited to a scouring value of about
2 to 3 m/sec. A higher velocity may cause quick abrasion of the barrel surfaces by rolling grit, etc.
and shall definitely result in higher amount of afflux on the upstream side of the siphon or
syphon-aqueduct, and thus, requiring higher anJ longer marginal banks. The head loss (h) through
syphon barrels and the velocity (V) through them are
generally related by Unwin's formula*, given as :
66
5. Design of Pucca Canal Trough.
For an Aqueduct, In case of an aqueduct, the bottom of the canal i.e. the roof of the culvert is
subjected to the dead weight and the vertical load of water from the top, as shown in Fig.
67
(ii) Drainage wings or Water wings or River wings. These wing walls retain and protect the
earthen slopes of the canal, guide the drainage water entering and leaving · the work, and join it to
guide banks and also provide a vertical cut-off for the water seeping from the canal into the
drainage bed.
The following methods may be used for designing the channel transitions:
(i) Mitra's method of design of transitions·(~hen water depth remains constant).
(ii) chaturvedi's method of design of transitions (when water depth remains constant).
(iii) Rind's method of design of transitions (when water depth may or may not vary).
(i) Mitra's Hyperbolic Transition when water depth remains constant. Shri A.C. Mitra, Chief
Engineer, U.P. Irrigation Deptt. (Retd.), has proposed a hyperbolic transition for the design of
channel transitions. According to him, the channel width at any section X-X, at a distance x from
the flumed section (Fig.) is given by
68
(ii} Chaturvedi's Semi Cubical pararabolic transition when water depth remains constant. Pz:of.
R.S. Chaturvedi, Head of Civil engineering Deptt. in Roorkee Univer. sity (Retd.), on the basis of
his own experiments, had in 1963, proposed the. Following equation for the design of channel
transitions when water depth remains constant
(iii) Hind's Method for the design of Transitions when water depth may also vary. This is a
general method and is applicable either when the depth in the flumed and unflumed portions is the
same, or when these depths are different. · In Fig., the contraction transition (i.e. the approach
transition) starts at section 1-1 and finishes at section 2-2. The flumed section continues from
section 2-2 to section 3-3. The expansion transition starts at section: 3-3 and finishes at section 4-
4. From section 4-4 onwards, the channel flows in its normal cross-section and the conditions at
this section are completely known. Let V and y with appropriate subscripts refer to velocities and
depths at different sections. ·
Design a suitable cross drainage work, given the following data at the crossing of a canal and a
drainage.
Canal
Full supply discharge= 32 cumecs
Full supply level=R.L 213.5
Canal bed level=R.L. 212.0m.
Canal bed width=20.
Trapezoidal canal section with 1 f H: 1 V slopes.
Canal water depth = 1.5 m.
Drainage.
High flood discharge =300 cumecs.
High flood level =210.0m.
High flood depth = 2.5 m.
General ground level = 212.5 m.
69
Solution Since the drainage is of a large size, work of type. III will be adopted. Further, because
the canal bed level (212.0 m) is much above the H.F.L. of drainage (te. 210.0 m) an aqueduct will
be constructed. The earthen banks of the canal will be discontinued and the canal water taken in a:
concrete trough. For effecting economy the canal shall be flumed.
Step 1. Design of Drainage Waterway
Lacey's regime perimeter= P = 4:75 √Q
where Q = High flood discharge of drain= 300 cumecs (given)
P = 4.75 √1300 = 82.3 m.
Let the clear span between piers be 9 m and the pier thickness be 1.5 m.
Using 8 bays of 9 m each, clear waterway = 8 x 9 = 72 m.
Using 7 piers of 1.5 each, length occupied by piers= 7 x 1.5 = 10.5 m.
Total length of waterway= 72 + 10.5 = 82.5 m
Step 2. Design of Canal Waterway
Bed width of canal = 20.0 m.
Let the width be flumed to 10.0 m.
Providing a splay of 2: 1 in contraction, the length of contraction transition
=10.0m
Length of the flumed rectangular portion of the canal between abutments = 82.5 m (provided).
In transitions, the side slopes of the canal section' will be warped in plan from the original slope
of 1.5: 1 to vertical
70
71
72
73
74
Module 5
Canal Regulation Works
Introduction
The works which are constructed in order to control and regulate discharges, depths, velocities
etc. in canals, are known as canal regulation works. These structures ensure the efficient
functioning of a canal irrigation system, by giving full control upon the canals. The important of
these structures are:
(i) Canal Falls.
(ii) Canal Regulators (Head Regulator and Cross Regulator).
(iii) Canal Escapes.
(iv) Metering Flumes, etc.
(v) Canal Outlets and Modules.
CANAL REGULATORS
A head regulator provided at the head of the off-taking channel, controls the flow of water entering the
new channel.
While a cross regulator may be required in the main channel downstream of the off-taking channel, and is
operated when necessary so as to head up water on its upstream side, thus to ensure the required supply in
the off-taking channel even during the periods of low flow in the main channel.
Main functions of a head regulator:
To regulate or control the supplies entering the off-taking canal
To control the entry of silt into the off-taking canal
To serve as a meter for measuring discharge.
Main functions of a cross regulator:
To control the entire Canal Irrigation System.
To help in heading up water on the upstream side and to fed the off-taking canals to their full
demand.
To help in absorbing fluctuations in various sections of the canal system, and in preventing the
possibilities of breaches in the tail reaches.
Cross regulator is often combined with bridges and falls, if required.
75
Canal falls
Irrigation canals are constructed with some permissible bed slopes so that there is no silting or scouring
in the canal bed. But it is not always possible to run the canal at the desired bed slope throughout the
alignment due to the fluctuating nature of the country slope. Generally, the slope of the natural ground
surface is not uniform throughout the alignment. Sometimes, the ground surface may be steep and
sometimes it ma be very irregular with abrupt change of grade. In such cases, a vertical drop is provided to
step down the canal bed and then it is continued with permissible slope until another step down is
necessary. This is done to avoid unnecessary huge earth work in filling. Such vertical drops are known as
canal falls or simply falls.
o When the slope of the ground is more or less uniform and the slope is greater than the permissible
bed slope of canal. In that case also the canal falls are necessary.
o In cross-drainage works, when the difference between bed level of canal and that of drainage is
small or when the F.S.L of the canal is above the bed level of drainage then the canal fall is
necessary to carry the canal water below the stream or drainage.
76
Types of Canal Falls
The following are the different types of canal falls that may be adopted according to the site condition:
Ogee Fall
In this type of fall, an ogee curve (a combination of convex curve and concave curve) is provided for
carrying the canal water from higher level to lower level. This fall is recommended when the natural
ground surface suddenly changes to a steeper slope along the alignment of the canal.
o The fall consists of a concrete vertical wall and concrete bed.
o Over the concrete bed the rubble masonry is provided in the shape of ogee
curve.
o The surface of the masonry is finished with rich cement mortar (1:3).
o The upstream and downstream side of the fall is protected by stone pitching with cement grouting.
o The design consideration of the ogee fall depends on the site condition.
77
Rapid Fall
The rapid fall is suitable when the slope of the natural ground surface is even and long. It consists of a
long sloping glacis with longitudinal slope which varies from 1 in 10 to 1 in 20.
o Curtain walls are provided on the upstream and downstream side of the sloping
glacis.
o The sloping bed is provided with rubble masonry.
o The upstream and downstream side of the fall is also protected by rubble masonry.
o The masonry surface is finished with rich cement mortar (1: 3).
Stepped Fall
Stepped fall consists of a series of vertical drops in the form of steps. This fall is suitable in places
where the sloping ground is very long and requires long glacis to connect the higher bed level with lower
bed level.
o This fall is practically a modification of the rapid fall.
o The sloping glacis is divided into a number of drops so that the flowing water may not cause any
damage to the canal bed. Brick walls are provided at each of the drops.
o The bed of the canal within the fall is protected by rubble masonry with surface finishing by rich
cement mortar (1:3).
78
Trapezoidal Notch Fall
In this type of fall a body wall is constructed across the canal. The body wall consists of several
trapezoidal notches between the side piers and the intermediate pier or piers. The sills of the notches are
kept at the upstream bed level of the canal.
o The body wall is constructed with masonry or concrete.
o An impervious floor is provided to resist the scoring effect of the falling water.
o The upstream and downstream side of the fall is protected by stone pitching finished by cement
grouting.
o The size and number of notches depends upon the full supply discharge of the canal.
Glacis Fall
It consists of a straight sloping glacis provided with a crest. A water cushion is provided on the
downstream side to dissipate the energy of flowing water.
79
o The sloping glacis is constructed with cement concrete.
o Curtain walls and toe walls are provided on the upstream and downstream side.
o The space between the toe walls and curtain walls is protected by stone pitching.
o This type of fall is suitable for drops up to 1.5 m.
For the improvement in energy dissipation, the glacis falls have been modified as follows:
80
The main body of the fall is constructed with cement concrete. Toe walls and curtain walls
are same as in the case of straight sloping glacis. The bed protection by stone pitching is also
same.
Canal Outlets/Modules:
A canal outlet or a module is a small structure built at the head of the water course so as to
connect it with a minor or a distributary channel.
It acts as a connecting link between the system manager and the farmers.
Requirements of a good module:
It should fit well to the decided principles of water distribution.
It should be simple to construct.
It should work efficiently with a small working head.
It should be cheaper.
81
It should be sufficiently strong with no moving parts, thus avoiding periodic
maintenance.
It should e such as to avoid interference by cultivators.
It should draw its fair share of silt.
82
Free Pipe Outlet. Pipe outlet discharging freely into the atmosphere is the simplest and
the oldest type of a flexible outlet. The discharge through such an outlet with depends
only upon the water level of the distributary, and will be independent of the water level of
the water-course so long as the pipe is discharging freely. Silt conduction for such an
outlet is quite good and efficiency is high. But a freely falling jet outlet can be provided
only at a few places where sufficient level difference between the distributary and water-
course is available. The discharge can be easily computed by using the equation.
where Cd is coefficient of discharge = 0.62 for average condition of free over fall.
H0 = Head on u/s side measured from FSL of distributary up to the centre of pipe outlet.
A = Area of cross-section' of pipe
Venturi Flume Outlet or Kennedy's Gauge Outlet. Kennedy's Gauge Outlet is of a
Venturi flume type and is shown in Fig. It is made of cast iron and consists of three main
parts:
(a) an orifice with a bell mouth entry ;
(b) a long expanding delivery pipe ;
(c) an air-vent connecting the throat of the delivery pipe to the atmosphere.
83
expanding flume. The formation of hydraulic jump makes the outlet discharge
independent of the water level in the water course; thus making it a semimodule.
84
Types of Rigid Modules
There are a few types of rigid modules which have no moving parts, such as :
(i) Gibb's module ;
(ii) Khannas rigid module
(iii) Foote module.
85