Candy Darter
Candy Darter
Candy Darter
This letter serves as formal notice pursuant to 16 U.S.C. § 1540(g) by West Virginia
Rivers Coalition, Indian Creek Watershed Association, Appalachian Voices, Preserve Giles
County, Preserve Bent Mountain, Wild Virginia, Sierra Club, Center for Biological Diversity,
Defenders of Wildlife, Chesapeake Climate Action Network, and Protect Our Water, Heritage,
Rights (POWHR) that the U.S. Fish and Wildlife Service (“USFWS” or “the Service”) and the
Federal Energy Regulatory Commission (“FERC” or “the Commission”) are in violation of the
Endangered Species Act, 16 U.S.C. §§ 1531–1544 (“ESA”), regarding the failure to reinitiate
ESA Section 7 consultation for the Mountain Valley Pipeline (“MVP”) project. Reinitiation is
required “where discretionary Federal involvement or control over the action has been retained
or is authorized by law” and, inter alia, “[i]f a new species is listed or critical habitat designated
that may be affected by the identified action.” 50 C.F.R. § 402.16(a)(4).
Here, in a final rule published on April 7, 2021 and that became effective on May 7,
2021, the Service designated critical habitat for the candy darter. Endangered and Threatened
Wildlife and Plants; Designation of Critical Habitat for Candy Darter, 86 Fed. Reg. 17956
(April 7, 2021). This habitat would be adversely affected by MVP. The Service’s Biological
Opinion for the MVP project recognizes that reinitiation of consultation is required when new
“critical habitat [is] designated that may be affected by the action.” USFWS, Biological Opinion
and Conference Opinion for the Mountain Valley Pipeline Project, Sept. 4, 2020 (“BiOp”) at
185. See also 86 Fed. Reg. at 17957 (recognizing “that there are section 7 consultation
2101 Webster Street, Suite 1300 Oakland, CA 94612 TEL: (415) 977-5500 FAX: (510) 208-3140 www.sierraclub.org
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
requirements as a result of the listing of the candy darter and the designation of critical habitat”).
Therefore, reinitiation of consultation is now required, and the failure to do so is a violation of
the ESA.
There is no question that the MVP project will adversely affect designated critical habitat
for the candy darter. The Service has acknowledged that the pipeline project will increase
sedimentation and embeddedness in Stony Creek and the Upper Gauley River—some of the last
remaining candy darter habitat—which will affect several physical or biological features
(“PBFs”) that are “essential for the conservation needs” of the candy darter. BiOp at 63. 1 Indeed,
the Biological Opinion acknowledges that changes in the conditions of these PBFs “in the impact
areas in both critical habitat subunits 2b [Stony Creek] and 5b [Upper Gauley River] are
anticipated due to increased sedimentation from upland project activities and due to suspension
and re-deposition of substrate sediments disturbed during storm events.” BiOp at 163. Compare
86 Fed. Reg. at 17967 (“the role of critical habitat is to support physical or biological features
essential to the conservation of a listed species and provide for the conservation of the species”)
with BiOp at 163 (acknowledging that impacts to “water quality and habitat quality are expected
as a result of increased sedimentation reducing visibility, decreasing available prey, increasing
embeddedness, and filling interstitial spaces with fine sediment”). 2
Both the action agency and the consulting agency have a duty to reinitiate consultation
where, as here, such reinitiation is necessary to ensure that the proposed action will not destroy
or adversely modify newly designated critical habitat. See, e.g., Salmon Spawning & Recovery
All. v. Gutierrez, 545 F.3d 1220, 1229 (9th Cir. 2008). Reinitiation of consultation requires
issuance of a new Biological Opinion before the agency action may continue. Envtl. Prot. Info.
Ctr. v. Simpson Timber Co., 255 F.3d 1073, 1076 (9th Cir. 2001) (citation omitted). The
Commission and Mountain Valley Pipeline, LLC (“Mountain Valley”) are prohibited from
making any “irreversible or irretrievable commitment of resources” during the reinitiated
consultation under 16 U.S.C. § 1536(d) and 50 C.F.R. § 402.09. Accordingly, this letter serves as
formal notice that the Service and the Commission are in violation of the ESA as a result of their
failure to reinitiate Section 7 consultation for the MVP project.
1
These include PBF 2 (a blend of unembedded gravel and cobble that allows for normal
breeding, feeding, and sheltering behavior), PBF 3 (adequate water quality characterized by
seasonally moderated temperatures and physical and chemical parameters that support normal
behavior, growth, and viability of all life stages of the candy darter), and PBF 4 (an abundant,
diverse benthic microinvertebrate community that allows for normal feeding behavior). BiOp at
138-39.
2
The Service concluded that “authorization to construct and operate the pipeline, as proposed,
including the activities that have already been completed, is not likely to destroy or adversely
modify proposed critical habitat.” BiOp at 164-65. Several of the undersigned groups filed a
petition for review challenging the validity of the BiOp in the U.S. Court of Appeals for the
Fourth Circuit (Case No. 20-2159). That case is pending.
2
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
In the Biological Opinion for MVP, the Service recognized that two “proposed critical
habitat units are included in the action area, the Upper Gauley River unit (unit 5) and Middle
New River unit (unit 2).” BiOp at 89. The Service stated in the BiOp that FERC “may ask the
Service to confirm the [conference opinion (“CnOp”)] as a BiOp issued through formal
consultation if the [candy darter] critical habitat is designated.” Id. at 185. See also
Memorandum from J. Schmidt and C. Schulz (USFWS) to J. Baxter, April 18, 2018 (“Any
conference opinions on the critical habitat that are completed between the date when the species
listing is finalized and the date of final critical habitat designation … will need to be confirmed
as biological opinions.”). The Service further noted that if it “reviews the proposed action and
finds that there have been no significant changes in the action as planned or in the information
used during the conference, the Service will confirm the CnOp as the BiOp on the project and no
further Section 7 consultation will be necessary.” BiOp at 185-86.
Of course, the opposite must also hold true: if there have been significant changes, then
the CnOp may not be relied upon, and a new BiOp must be prepared through a reinitiated
consultation. As explained below, further Section 7 consultation is required for MVP due to both
significant changes in the action and information that was not considered during the prior
consultation process.
To the extent the crossing method is modified for tributaries to candy darter extant
streams—or for streams that may have been improperly omitted from consideration as candy
darter extant streams, see infra—the agencies must consider the impacts of this significant
change to the project on the candy darter and its designated critical habitat. The Commission
3
See, e.g., Virginia Scientist-Community Interface, MVP proposal for trenchless stream
crossings lacks critical technical planning, April 15, 2021 at 5–6 (attached as Exhibit E).
3
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
asserts that, based on the distance of these tributary crossings from the designated critical habitat,
and “the fact that the trenchless crossing method is expected to reduce the potential of any direct
impacts to the streams, [the Commission] expect[s] the change in crossing method at these
locations will be insignificant and discountable.” Letter from J. Martin (FERC) to C. Schulz
(USFWS), May 5, 2021 (eLibrary 20210505-3065). But the Commission’s conclusory
statements regarding its expectations are an insufficient basis for concluding that this significant
change to the project will not affect the candy darter or its designated critical habitat. 4 Trenchless
crossing methods pose risks to waterways that are distinct from the impacts of open-cut crossing
methods. 5 Neither the Commission’s 2017 Final Environmental Impact Statement (“EIS”) nor
the Service’s BiOp considered the effects of any of the 120 additional trenchless crossings now
proposed by Mountain Valley—let alone their cumulative effects. 6 Accordingly, this change in
construction method—as Mountain Valley’s request for a certificate amendment in a new
Commission docket confirms—constitutes a major change to the project.
4
The amendment affects tributary crossings in close proximity to their confluence with
designated critical habitat and potential candy darter extant streams. See, e.g., Abbreviated
Application for Limited Amendment to Certificate of Public Convenience and Necessity and
Request for Expedited Action, Appendix B at B-9 (eLibrary 20210219-5176). Moreover, the
Commission’s conclusory statement that “Mountain Valley will implement best management
practices to minimize any sedimentation attributed to the change in crossing method” is not a
substitute for careful analysis of those sedimentation impacts on candy darter and its newly
designated critical habitat. Letter from J. Martin (FERC) to C. Schulz (USFWS), May 5, 2021
(eLibrary 20210505-3065).
5
See, e.g., Joint NEPA Scoping Comments on Environmental Issues for the Proposed
Amendment to the Certificate of Public Convenience and Necessity for the Mountain Valley
Pipeline Project (April 15, 2021) at 10–27 (attached as Exhibit D).
6
See also Matthew Baker, PhD, Comments on Mountain Valley Pipeline’s Requested
Amendment to its Certificate of Public Convenience and Necessity (2020) at 6 (“Information in
the approved EIS was insufficient to fully appreciate or understand the site-specific hydrologic
implications or risks of borehole crossings.”) (attached as Exhibit A).
7
See, e.g., BiOp at 24-26, 72-73 (citing various letters from Mountain Valley to FERC and
USFWS).
4
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
This information indicates that the changes to the project’s crossing methods, as well as
the trenchless crossing methods previously approved for the Gauley River and Stony Creek, pose
serious risks to candy darter habitat. For example, to bore under a stream, “MVP must excavate a
pit nearby, which … may increase erosion and sedimentation. And there is risk that drilling fluid
will escape into the surface waters, or that the drilled hole might collapse, causing the waterbed
to collapse as well.” Mountain Valley Pipeline, LLC v. North Carolina Dept. of Envtl. Quality,
990 F.3d 818, 822 (4th Cir. 2021). See also Pete Nimmer, Greenstar Environmental Solutions,
LLC, Comments on Mountain Valley Pipeline’s Requested Amendment to its Certificate of
Public Convenience and Necessity at 2 (2020) (“MVP’s assertion in its application that its
proposed actions ‘would have limited, if any, environmental impacts beyond those that have
already been assessed and approved by the Commission’ does not withstand scrutiny.”) (attached
as Exhibit B); FERC, Southgate Project Final Environmental Impact Statement at 4-37, Docket
No. CP19-14 (Feb. 2020) (eLibrary No. 20200214-3010) (describing serious risks associated
with conventional boring). Indeed, “significant adverse consequences are likely to occur from
[Mountain Valley’s proposed] change of waterbody crossing method,” including “disruption of
groundwater flow, harm to drinking water supplies, dewatering of surface waters, inadvertent
return of drilling fluids, and catastrophic failure of the pipe.” Pete Nimmer, Greenstar
Environmental Solutions, Comments on FERC’s January 7, 2021 Environmental Assessment,
Mountain Valley Pipeline’s February 2021 Individual Permit Application, FERC’s March 12,
2021 Environmental Information Request, and Mountain Valley Pipeline’s March 29, 2021
Response at 2 (2021) (attached as Exhibit C).
These hydrogeological effects pose serious risks to candy darter critical habitat. 8 For
example, chronic dewatering caused by boring could result in “reduced sediment transport,
warmer water temperatures, poor aeration, and reductions in aquatic habitat.” Exhibit A at 4.
This would lead to “greater deposition of suspended fine material, increasing the embeddedness
of coarse channel substrate utilized by invertebrates and fish” such as the candy darter. Id. See
also id. (“[C]hronic dewatering would reduce the extent and the quality of aquatic habitat over
space in affected channels, but also through time.”). Similarly, bore pit pumping could result in
large discharges of sediment-laden water that “would represent significant turbidity and
potentially dramatic changes to the fine sediment load in many streams.” Id. at 5. See also id.
(“Spoil transport and relocation will further extend the time on site for any boring operation, and
this increases the potential for erosive losses to water bodies.”).
In sum, the impacts of these crossing methods on candy darter and their critical habitat
that have not yet been fully analyzed, requiring reinitiation of consultation to determine the full
impacts of the project, as the ESA requires. These impacts are particularly concerning in light of
the candy darter’s sensitivity to sedimentation, including its reliance on unembedded substrate
8
The Service also must consider such impacts to the endangered Roanoke logperch.
5
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
for spawning and feeding. Accordingly, this significant change the project, combined with the
subsequent designation of critical habitat, warrants reinitiation.
New Information Indicating that Additional Waterways are Potential Candy Darter
Extant Streams
Mountain Valley initially stated that the project would require eleven crossings of candy
darter streams, though it acknowledged that it did not complete presence/absence surveys or in
situ habitat assessments. 9 Yet in the May 2020 Supplement to the Biological Assessment
(“Supplement to the BA”) for the project, Mountain Valley stated that “[b]ased on USFWS GIS
shapefiles provided in October 2018 (USFWS 2018d), the Project crosses with [sic] extant candy
darter populations in the Gauley River in Nicholas County, West Virginia and Stony Creek in
Giles County, Virginia.” Supplement to the BA at 32. See also id. (“Neither project-specific
candy darter occupancy surveys nor habitat assessments have been completed in-situ along the
Project.”). The streams other than the Gauley River and Stony Creek that were initially presumed
to provide habitat for the species were subsequently eliminated from consideration as candy
darter extant streams. See Exhibit F, attached hereto (revised table, provided by Mountain Valley
to the Service in October 2018, explaining that each of the streams was “not identified as a candy
darter extant stream”). This error must be addressed in a reinitiated consultation.
In comments on the proposed rule to designate critical habitat for the candy darter, the
West Virginia Division of Natural Resources “noted that candy darters may also be present in
several perennial tributaries outside of the streams proposed for designation as critical habitat,
but that these tributaries have not been surveyed.” 86 Fed. Reg. at 17958. See also id. (“The State
… recommend[ed] that these streams should be considered when reviewing projects that may
affect the species.”). The Service “acknowledge[d] that the candy darter may be present in
additional streams or tributaries that have not been surveyed….” Id. Accordingly, in light of this
new information developed during the rulemaking process on the proposed critical habitat
designation, the Service must reinitiate consultation and assess whether it erred in omitting
streams other than the Gauley River and Stony Creek from consideration. 50 C.F.R. §
402.16(a)(2), (4).
9
See also Letter from J. Martin (FERC) to T. Andersen (USFWS), Feb. 14, 2018 (“The Project
would cross 11 perennial streams which could support candy darter populations including:
Strouds Creek (two crossings), Big Beaver Creek (two crossings), Gauley River, Little Laurel
Creek (two crossings), Jims Creek, Hominy Creek (two crossings) in West Virginia and Stony
Creek in Virginia.”); id. (“Mountain Valley did not complete presence/absence surveys or in situ
habitat assessments. Mountain Valley has assumed presence at these locations based on desktop
analysis and agency correspondence.”).
6
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
In the final rule designating critical habitat for the candy darter, the Service noted that
“[t]he West Virginia [Division of Natural Resources] suggested that [the Service] may have
underestimated the threat of acid precipitation in the Upper Gauley,” and acknowledged that
“[s]tream acidification in some candy darter watersheds is a serious concern” that FWS “will
address … in future recovery planning.” 86 Fed. Reg. at 17958. Because impacts from acid
precipitation were not adequately considered in the environmental baseline or cumulative effects
analyses in the 2020 BiOp, the Service must reinitiate consultation in light of this new
information and properly consider these impacts during the reinitiation process. See 50 C.F.R. §
402.16(a)(2).
Although the Service claims that the impacts to PBFs in the relevant critical habitat
subunits “are expected to be limited in relative severity and duration,” BiOp at 163, this
conclusion is not adequately supported. For example, neither the Service nor the Commission
has adequately considered the impacts of multiple crossings within candy darter watersheds, and
the predictions of only short-term or temporary impacts are not well-supported and improperly
ignore studies showing that long-term impacts are likely to result. As a senior endangered
species biologist in the West Virginia Field Office wrote regarding pipeline stream crossings:
[C]aution should be used when interpreting results of short-term studies. Yount &
Niemi (1999, p. 558) cite an example of one study that made a preliminary
determination of stream recovery within one year, but when the site was re-
examined six years later, fish biomass, fish populations, macroinvertebrate
densities, and species composition were still changing. It was suspected that shifts
in sediment and nutrient inputs to the site as a result of construction in and around
the stream contributed to the long-term lack of recovery…. There is also the
potential for cumulative effects. While a single crossing may have only short-term
or minor effects, multiple crossings or multiple sources of disturbance and
sedimentation in a watershed can have cumulative effects on fish survival and
reproduction that exceed the recovery capacity of the river, resulting in permanent
detrimental effects (Levesque & Dube 2007, pp. 406-407).
Exhibit G, attached hereto. Accounting for these long-term impacts is also critical in light of the
Service’s acknowledgment in the critical habitat designation that “high-quality streams within
the candy darter’s historical range might provide the candy darter a competitive advantage over
the introduced variegate darter.” 86 Fed. Reg. at 17958.
Accordingly, reinitiation is required to account for these long-term impacts and other
impacts from multiple crossings within candy darter watersheds, particularly in light of the candy
darter’s relative lack of motility and relatively short lifecycle.
7
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Conclusion
For the foregoing reasons, the Service and the Commission must immediately reinitiate
consultation and, during that process, take into account information that has not previously been
considered. Please do not hesitate to contact the undersigned if we can provide additional
information or otherwise assist in this matter. We look forward to your prompt response.
Sincerely,
Elly Benson
Senior Attorney, Sierra Club
2101 Webster Street, Suite 1300
Oakland, CA 94612
[email protected]
8
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Exhibit A
Document Accession #: 20210513-5107
20201221-5392 Filed Date: 05/13/2021
12/21/2020
1
Document Accession #: 20210513-5107
20201221-5392 Filed Date: 05/13/2021
12/21/2020
2
Document Accession #: 20210513-5107
20201221-5392 Filed Date: 05/13/2021
12/21/2020
be no deeper than about 24 feet to avoid risks of scour in the EIS. Therefore,
interaction with bedrock is much more likely. The deeper holes are also far more
likely to involve substantial interactions with groundwater aquifers.
Another substantive difference that will affect both hydrology and ecosystem
processes is the timing of the crossing work. In the original open-cut proposal,
crossings were to be accomplished during low water periods to avoid spawning and
reduce the need to dewater or reroute stream flow in low or zero-order channels.
During the late summer, low-flow period, most hollow soils are dry and many
headwater streams may also be dry, flowing slowly, or subterranean (i.e., flowing in
the hyporheos beneath the channel bed). In the amendment, the expedited request
makes it appear as if MVP is expecting to begin crossings as soon as January 2021
(as it has asked FERC to act by December 31, 2020, and proposes to suspend
crossings near bat hibernatories until March 2021), making these wintertime or
springtime crossings, something that was never considered by the approved EIS.
Ecological Impacts:
Dewatering -- An environmental impact report from Greenstar Environmental
Solutions (Nimmer 2020) indicated that surface water, floodplain, and wetlands
dewatering was a potential impact of conventional borehole crossings. The report
characterizes such events as ‘likely’ over the extent of MVP’s proposed amendment.
As opposed to the short-term dewatering considered in the EIS for open trench
crossings, creation of new hydraulic conduits may represent permanent alterations
to the system or a chronic condition. This would represent an entirely different
kind of alteration than previously considered.
Although many headwater and low order streams valleys in this part of Appalachia
experience seasonal drying, the timing of such drying is critical, with biota in these
ecosystems adapted to drought during the later portions of the summer and early
fall. This means many aquatic insect taxa are either in an adult (terrestrial) phase as
winged insects or, having laid their eggs, the eggs are in diapause waiting for more
favorable environmental conditions. Fish species may have moved downstream into
higher order systems with more predictable discharge but, in any case, are well
removed from sensitive spring spawning and rearing periods. In addition, although
many headwater reaches flow over bedrock with limited access to local
groundwater, others flow in colluvium from steep valley walls and still others
(especially second order systems and higher) flow in valley bottom alluvium.
Depending on the depth and configuration of such alluvium and its interaction with
local bedrock, stream reaches can be considered to be ‘gaining’ or ‘losing’ with
respect to stream flow, with water from losing reaches returning to channels at
some point downslope. Thus, disruptions to subsurface layers can reduce or
enhance these connections.
Winter is a prime period for larval growth among aquatic invertebrates in
headwater streams, the principal food supply for many insectivorous fish species
3
Document Accession #: 20210513-5107
20201221-5392 Filed Date: 05/13/2021
12/21/2020
which depend upon that stored energy for reproduction. Short term dewatering
would certainly be lethal for many aquatic organisms or displace them to
downstream habitats (something that is only realistic for more motile taxa), where
they are more vulnerable to predation. Although otherwise undisturbed systems
should be resilient enough to recover over the course of several years if flows
return, interaction with pre-existing degradation is more difficult to predict. If the
system in question is already stressed (e.g., chemically or thermally), recovery
would likely take much longer. On the other hand, chronic or prolonged dewatering
is potentially more serious and that is what has yet to be assessed. Given that the
cause of dewatering would be the creation of new conduits for groundwater flow
away from the waterbody (Nimmer 2020), dewatering created by boring in this case
would likely be a long-term issue.
Dewatering that persists through the spring or early summer could reduce
recruitment of wetland plants that depend on periods of saturated soils or shallow
water tables for germination or seasonal growth, as well as alter redox conditions
that govern many important biogeochemical processes (e.g., nitrification and
denitrification). Further, chronic dewatering in stream channels and floodplains
from hydraulic conduits accessed and/or created through borehole drilling might be
inconspicuous in the wintertime when evapotranspirative demands are low and
losses are masked by higher flows, but result in either reduced flow regimes or
truncated periods of surface flow altogether when evapotranspiration increases in
the spring and summer, with cascading environmental effects.
Detrimental effects of chronic dewatering later in the year include reduced sediment
transport, warmer water temperatures, poor aeration, and reductions in aquatic
habitat. All else being equal, reduced transport capacity would lead to less
turbulence and greater deposition of suspended fine material, increasing the
embeddedness of coarse channel substrate utilized by invertebrates and fish.
Invertebrates rely on pore spaces to shelter from predators but suffer from reduced
aeration when these spaces fill with sediment and constrict water circulation in the
stream bed. Fish also make use of coarse beds for spawning, as the same conditions
allow for protection of eggs and shelter of fry, both of which are notoriously
sensitive to sedimentation in Appalachian streams. Lower flows would also
contribute to more rapid warming of water with air temperatures and greater
diurnal fluctuation of temperatures. Warmer temperatures and slower flow would
contribute to reduced oxygen levels for aerobic respiration while increasing
metabolic rates earlier in the season. Thus, chronic dewatering would reduce the
extent and the quality of aquatic habitat over space in affected channels, but also
through time. The nature, extent, and magnitude of the impacts being described
would likely vary based on network position and the site-specific hydrogeology, but
they would accompany any dewatering caused by boring. None of these issues were
considered in the EIS used to approve MVP’s Certificate because at the time MVP
had asserted that all of its crossings would be accomplished using dry open-cut
methods.
4
Document Accession #: 20210513-5107
20201221-5392 Filed Date: 05/13/2021
12/21/2020
5
Document Accession #: 20210513-5107
20201221-5392 Filed Date: 05/13/2021
12/21/2020
and be staged for later transport to streams is likely greater than it might be if the
work was performed in the drier part of the year.
Control of sediment during construction projects like this is difficult at best and it
becomes more challenging when it remains exposed or when the material is moved
from place to place. According to the history of legal action associated with pipeline
construction thus far, several lawsuits have been filed already by state
environmental agencies with regard to MVP’s management of the project. Because
the timing of the excavation and sediment management would occur in a different
season, the nature of risk to aquatic systems is altered. Further, since the bore hole
pits are likely to be in operation longer than the permitted trenching procedures, it
would appear as if the spoil will remain exposed over longer time periods than what
was originally considered in the EIS. This longer storage period increases the
likelihood that the spoil piles will be subject to erosion and excess sediment
deposited in adjacent waterbodies.
Further information:
Based on the information provided in the proposed amendment and the Response to
Environmental Information Request, several factors seem to play a far more
important role than they did previously in assessing likely environmental impacts.
MVP claims it has already made 35 borehole crossings along the first 77 miles of the
pipeline route. Information about these crossings is missing from their proposed
amendment, which might support their claim about the ecological impacts.
However, there is no mention of any monitoring done at these locations, so it is
unclear how they know the impacts are minimal. From the maps provided by MVP,
it is worth noting that not all surveyed waterbodies are associated with proposed
borehole pits. Given that the amendment requests blanket permission to cross all
waterbodies with boreholes, the discrepancy seems at odds with their request.
Importantly, the switch to borehole crossings has emphasized the need to develop
more detailed and site-specific understanding of valley bottom geology and aquifer
characteristics. Such information is necessary to assess the potential for chronic or
permanent channel, floodplain, or wetland dewatering. Information in the approved
EIS was insufficient to fully appreciate or understand the site-specific hydrologic
implications or risks of borehole crossings. All we know is that the types of
geologies described are those where the development of new hydrologic conduits is
possible. In some cases, the impacts may be minimal as suggested by MVP, yet in
others substantial risks remain.
In developing the EIS, federal agencies never considered the potential impacts of
discharge from excavation operations during the wintertime when many more
aquatic species are resident, from deeper holes where groundwater seepage is likely
to be far greater than the shallower trenches, and when greater stream flows are
likely to transport fine material further downstream. Moreover, the proposed
amendment and MVP’s response for further information suggest a much more
6
Document Accession #: 20210513-5107
20201221-5392 Filed Date: 05/13/2021
12/21/2020
extensive earth moving operation than the local storage of spoils described in the
approved EIS. Because the information about spoil storage is left vague, there is
little ability for any agency to say with certainty whether spoil management will
reduce or enhance risks to the affected waterbodies or other drainages nearby.
As a result of differences in crossing method that expose streams to new threats,
differences in season that have implications for the type, magnitude and extent of
ecological impacts, and because of the lack of necessary information provided to
make an informed assessment, the proposed amendment clearly falls outside of the
scope of impacts considered in the EIS used to support MVP’s Certificate.
Submitted Respectfully,
Matthew Baker, PhD
Professor
Department of Geography and Environmental Systems
University of Maryland, Baltimore County
Baltimore, MD 21250
Materials Reviewed:
Federal Energy Regulatory Commission, Mountain Valley Project and Equitrans
Expansion Project: Final Environmental Impact Statement (June 2017)
(Docket No. CP16-10; eLibrary No. 20170623-4000)
Abbreviated Application for Limited Amendment to Certificate of Public
Convenience and Necessity and Request for Expedited Action (Nov. 18, 2020)
(Docket No. CP21-12; eLibrary No. 20201118-5179).
Mountain Valley Pipeline Amendment Project (Project), Docket No. CP21-12-000,
ENVIRONMENTAL INFORMATION REQUEST (Dec. 2, 2020) (eLibrary No.
20201202-3040).
Mountain Valley Pipeline, LLC, Response to Environmental Information Request
Issued December 2, 2020 (Docket No. CP21-12; eLibrary No. 20201211-
5164).
Joint Motion to Intervene and Comments in Opposition to Request for Extension of
Time by Appalachian Voices, et al. (Sept. 11, 2020) (Docket No. CP16-10;
eLibrary No. 20200911-5288).
Pete Nimmer, Greenstar Environmental Solutions, LLC, Comments on Mountain
Valley Pipeline’s Requested Amendment to its Certificate of Public Convenience
and Necessity (Dec. 2020).
7
Document Accession #: 20210513-5107
20201221-5392 Filed Date: 05/13/2021
12/21/2020
CURRICULUM VITAE
MATTHEW E. BAKER
Department of Geography & Environmental Systems
University of Maryland, Baltimore County
211 Sondheim Hall, 1000 Hilltop Circle
Baltimore, Maryland 21250
Phone: (410) 455-3759
[email protected]
EDUCATION
PROFESSIONAL EXPERIENCE
2018-2020 Expert Witness, Whiteford, Taylor & Preston L.L.P., Baltimore, Maryland
1
Document Accession #: 20210513-5107
20201221-5392 Filed Date: 05/13/2021
12/21/2020
HONORS RECEIVED
2015 IRC Summer Faculty Fellowship, College of Humanities, Arts, and Social Sciences, UMBC
2014 Finalist, Boggess Best Paper Award, American Water Resources Association (Weller &
Baker 2014)
2014-2015 Faculty Research Fellowship, College of Humanities, Arts, and Social Sciences,
UMBC
2011-12 UMBC Faculty Teaching Scholar
2010 Faculty1000 selection for recommended reading (Baker & King 2010)
2009 Summer Faculty Fellowship, UMBC
2007 William B. Gardner Foreign Travel Award
2006 Finalist, New Faculty Advisor of the Year
2005 Faculty1000 selection for recommended reading (King et al. 2005)
2002 US-IALE, Best Student Presentation Award Winner
2002 US-IALE NASA-MSU Award Winner
2000-1 Jeffery Lund Award for outstanding scholarship in Forest Ecology
2000-1 Samuel A. Graham Award for excellence in Forest Biology
1996-8 Merit based scholarships
1995-6 Samuel A. Graham Award for excellence in Forest Biology
1993 Xi Sigma Pi Forestry Honor Society
1992-5 Merit based scholarships
RESEARCH SUPPORT
2020-2023 Baker M (Co-I), Alonzo, M (Principal) “Understanding tree species response to urban
heat using high resolution remote sensing”, Sponsored by the National Science Foundation
(NSF-GSS) $416,659
2019-2020 Baker M (Principal) “Mapping woodland patches across major urban areas of the
Eastern US”, USDA Forest Service $15,000
2018-2024 Baker M (Principal) “High-resolution stream mapping across the Chesapeake Bay
Watershed” Sponsored by the U.S. Environmental Protection Agency Chesapeake Bay Program,
2
Document Accession #: 20210513-5107
20201221-5392 Filed Date: 05/13/2021
12/21/2020
$1,200,000
2018-2020 Baker M (Principal) “Patapsco River Restoration Phase II: Post-Removal Survey”
Sponsored by American Rivers/NOAA, $107,380
2018-2019 Baker M (Principal) “Patapsco River Restoration Phase II: Pre-Removal Survey”
Sponsored by the American Rivers/NOAA, $93,680
2017-2019 Baker (Principal) “New measures of aquatic habitat for assessing restoration
resilience” Sponsored by Maryland SeaGrant, $43,706
2017-2020 Baker M (Co-PI), Yu M (Principal) “Acquisition of Hybrid CPU/GPU Nodes for the
Interdisciplinary UMBC High Performance Computing Facility” Sponsored by the National
Science Foundation (NSF-MRI), $550,000
2016-2018 Baker M (Principal) “Scalable applications for mapping stream channels from
high resolution terrain data” Sponsored by the Chesapeake Bay Trust, $74,997
3
Document Accession #: 20210513-5107
20201221-5392 Filed Date: 05/13/2021
12/21/2020
2010-15 Baker M (Co-Principal), Swan C (Principal) “The role of network topology and
environmental filtering in shaping the ecology of spatially structured communities” Sponsored
by the National Science Foundation, $410,000
2010-2015 Baker M (Collaborator), Vigliano P (Principal) “Habitat template and stream fish
assemblages of sub basins of Nahuel Huapi lake, Patagonia Argentina” Sponsored by the
Argentinian National Scientific and Technical Research Council (CONICET), $70,000
(approximate)
2010-14 Baker M (Sen. Pers.), Welty C (Principal) “Acquisition of Liquid Water Isotope
Analyzer Capability for Advancing Hydrologic Research in Baltimore Ecosystem Study LTER”
Sponsored by the National Science Foundation (NSF-MRI), $244,694
2007 Baker M (Principal) “Remote analysis of watershed attributes using Shuttle Radar
Topography Mission data: Andean Patagonia” Utah State University Water Initiative, $6,000
2007 Baker M (Principal) Utah State University New Faculty Competitive Research Grant,
4
Document Accession #: 20210513-5107
20201221-5392 Filed Date: 05/13/2021
12/21/2020
$15,000
2006-10 Baker M (Principal) “A strategic planning tool for targeted buffer restoration and
enhanced coastal stewardship ” Sponsored by the National Oceanographic and Atmospheric
Administration, $308,968
2005-08 Baker M (Sen. Pers.) Prince S (Principal), “A watershed Classification System for
improved Monitoring and Restoration: Indicators of Watershed Impairment” Sponsored by the
US Environmental Protection Agency, $800,000
Ph.D. STUDENTS
MASTER’S STUDENTS
5
Document Accession #: 20210513-5107
20201221-5392 Filed Date: 05/13/2021
12/21/2020
UNDERGRADUATE STUDENTS
6
Document Accession #: 20210513-5107
20201221-5392 Filed Date: 05/13/2021
12/21/2020
PEER-REVIEWED WORKS (>3400 Google Scholar Citations, H index = 27, i10 index = 44)
Package TITAN2; Threshold Indicator Taxa Analysis (v2.2), published on the Comprehensive R
Analysis Network (CRAN), December 2019: https://cran.r-
project.org/web/packages/TITAN2/index.html
2020
52. Davies, SJ et al. 2020. ForestGEO: Understanding Forest Diversity and Dynamics through a
Global Observatory Network. Biological Conservation (in press)
51. Dixon*, A, M Baker, E Ellis. 2020. Agricultural landscape composition linked with acoustic
measures of avian diversity. Land https://doi.org/10.3390/land9050145.
7
Document Accession #: 20210513-5107
20201221-5392 Filed Date: 05/13/2021
12/21/2020
50. Bezerra*, M, M Baker, M Palmer, S Filoso. 2020. Sugarcane agriculture exacerbates gully
formation in headwater catchments in Brazil. Journal of Env. Management 110271.
49. Pickett, ST, et al. 2020. Theoretical perspectives of the Baltimore Ecosystem Study:
conceptual evolution in a social-ecological research project. Bioscience 70(4):297–314.
https://doi.org/10.1093/biosci/biz166
2019
48. Baker, ME, ML Schley*, JO Sexton. 2019. Impacts of expanding impervious surface on
specific conductance in urbanizing streams. Water Resources Research
https://doi.org/10.1029/2019WR025014.
47. Van Appledorn* M, ME Baker, AJ Miller. 2019. Empirical evaluation of 2D unsteady
hydraulic models for applications in floodplain forest ecology. Physical Geography
https://doi.org/10.1080/02723646.2019.1676186.
46. Phillips* T, M Baker, K Lautar, I Yessalonis, M Pavao-Zuckerman. 2019. The capacity of urban
forest patches to infiltrate stormwater is influenced by soil physical properties and soil
moisture. Journal of Environmental Management 246: 11-18.
45. Macchi, L, C Levers, M Baumann, M Baker, T Kummerle. 2019. Satellite-based tree and
shrub cover reveal thresholds in bird community in the South American dry Chaco. J.
Applied Ecology.
44. Van Appledorn* M, ME Baker, AJ Miller.2019. River-valley morphology, basin size, and flow-
event magnitude interact to produce wide variation in flooding dynamics. Ecosphere
10(1):e02546.
2018
2017
43. Dandois*, J, M Baker, M Olano, G Parker, E Ellis. 2017. What is the Point? Using Computer
Vision Point Clouds to Observe Vegetation Structure and Spectral Properties. Remote
Sensing 9(4), 355; doi:10.3390/rs9040355.
42. Collins, MJ, NP Snyder, G Boardman, WSL Banks, M Andrews, ME Baker, M Conlon, A Gellis,
S McClain, A Miller, P Wilcock. 2017. Channel response to sediment release: insights from a
paired dam-removal analysis. Earth Surface Processes and Landforms 10.1002/esp.4108.
2016
41. Donovan* M, AJ Miller, ME Baker. 2016. Reassessing the role of milldams in Piedmont
floodplain development and remobilization. Geomorphology 268:133-145.
40. Utz, R, K Hopkins , L Beesley, D Booth , R Hawley , ME Baker, M Freeman, and K Jones. 2016.
Do specific natural watershed and channel attributes confer ecological resistance to
urbanization in streams? Freshwater Science 35(1):380-397.
39. Lallement* M, P Macchi, P Vigliano, S Juarez, M Baker, N Bouwes, T Crowl. 2016. Rising from
the ashes: changes in salmonid fish assemblages after 30 months of the Puyehue-Cordon
Caulle volcanic eruption. Science of the Total Environment 541:1041-1051.
2015
38. Koch, BJ, CM Febria, RM Cooke, JD Hosen*, ME Baker, MA Palmer. 2015. Suburban
8
Document Accession #: 20210513-5107
20201221-5392 Filed Date: 05/13/2021
12/21/2020
9
Document Accession #: 20210513-5107
20201221-5392 Filed Date: 05/13/2021
12/21/2020
Montrone. 2012. Grand Teton National Park and John D. Rockefeller, Jr. Memorial
Parkway: Natural resource condition assessment. Natural Resource Report
NPS/GRYN/NRR—2012/550. National Park Service, Fort Collins, Colorado.
23. Studds, C, WV Deluca*, ME Baker, RS King, and PP Marra. 2012. Land cover and climatic
variation interact to shape waterbird community composition. PLoS ONE 7(4):e35969.
22. Lowry, JH*, DR Ramsey and ME Baker. 2012. Determinants of urban tree canopy in
residential neighborhoods: Household characteristics, urban form, and geophysical
landscape. Urban Ecosystems doi: 10.1007/s11252-011-0185-4.
2011
21. Tesfa, T*. DG Tarboton, DW Watson, KA Schreuders, ME Baker, RM Wallace. 2011. Parallel
evaluation of a class of new topographic variables fro distributed hydrological modeling.
Environmental Modeling and Software doi:10.1016/j.envsoft.2011.07.018
20. Budy, P, K Dahle* and ME Baker. 2011. Predicting Fish Growth Potential and Identifying
Water Quality Constraints: A Spatially-Explicit Bioenergetics Approach. Environmental
Management doi: 10.1007/s00267-011-9717-1.
19. King, RS, ME Baker, PF Kazyak, and DE Weller. 2011. How novel is too novel? Stream
community thresholds at exceptionally low levels of watershed urbanization. Ecological
Applications doi: 10.1890/10-1357-1.
18. Weller, DE, ME Baker, and TE Jordan. 2011. Empirical tests for effects of riparian buffers on
watershed nitrate discharges. Ecological Applications doi:10.1890/10-0789-1.
17. King, RS and ME Baker. 2011. An alternative view of ecological community thresholds and
appropriate analyses for their detection. Comment. Ecological Applications
doi:10.1890/10-0882- 1.
2010
16. King, RS and ME Baker. 2010. Considerations for identifying and interpreting ecological
community thresholds. Journal of the North American Benthological Association 29(3):998-
1008.
15. Baker ME and RS King. 2010. A new method for identifying and interpreting ecological
community thresholds. Methods in Ecology & Evolution 1:25-37.
2009
14. Stanfield, LW, B Kilgour, K Todd, S Holysh, A Piggott, and ME Baker. 2009. Estimating
summer low- flow in streams of the Oak Ridges Moraine ecoregion using spatial models.
Canadian Water Resources Journal 34(3):269-284.
13. Baker, ME and MJ Wiley. 2009. Multiscale controls of flooding in riparian forests of Lower
Michigan. Ecology 90(1):145-159.
2008
12. Baker, ME, MJ Wiley, and PW Seelbach. 2008. Map-based predictions of riparian ecotopes:
relating climate and hydrology to streamside forests in Lower Michigan. Michigan
Department of Natural Resources, Fisheries Technical Report 2008-2, Ann Arbor.
2007
11. Baker, ME, DE Weller, and TE Jordan. 2007. Effects of stream map resolution on measures
of riparian buffer distribution and nutrient retention potential. Landscape Ecology 22:973-
992.
2006
10
Document Accession #: 20210513-5107
20201221-5392 Filed Date: 05/13/2021
12/21/2020
10. Baker, ME, DE Weller, and TE Jordan. 2006. Improved methods for quantifying potential
nutrient interception by riparian buffers. Landscape Ecology 21(8):1327-1345.
9. Baker, ME, DE Weller, and TE Jordan. 2006. Comparison of automated watershed
delineations: effects on land cover areas, percentages, and relationships to nutrient
discharges. Photogrammetric Engineering & Remote Sensing 72(2):159-168.
2005
8. King, RS, ME Baker, DF Whigham, DE Weller, TE Jordan, PF Kazyak, and MK Hurd. 2005.
Spatial considerations for linking watershed land cover to ecological indicators in streams.
Ecological Applications 15(1):137-152.
2004
7. King, RS, J Beaman, DF Whigham, AH Hines, ME Baker, and DE Weller. 2004. Watershed land
use is strongly linked to PCBs in white perch from Chesapeake Bay subestuaries.
Environmental Science and Technology 38:6546-6552.
6. Baker, ME and MJ Wiley. 2004. Characterization of woody species distribution in riparian
forests of Lower Michigan using map-based models. Wetlands 24(3):500-561.
2003
5. Baker, ME, MJ Wiley, PW Seelbach, and ML Carlson. 2003. A GIS-based index of groundwater
potential for aquatic resource inventory, assessment, and environmental management.
Environmental Management 32:706-719.
4. Baker, ME, MJ Wiley, and PW Seelbach. 2003. Spatially-explicit models of groundwater
loading in glaciated landscapes: considerations and development in Lower Michigan.
Fisheries Research Report No. 2064, Michigan Department of Natural Resources, Ann
Arbor.
Pre-2002
3. Baker, ME, MJ Wiley, and PW Seelbach. 2001. GIS-based hydrologic modeling of riparian
areas: implications for stream water quality. Journal of the American Water Resources
Association 37(6): 1615-1628.
2. Baker, ME and BV Barnes. 1998. Landscape ecosystem diversity of river floodplains in
northwestern Lower Michigan, USA. Canadian Journal of Forest Research 28:1405-1418.
1. Seelbach, PW, MJ Wiley, JC Kotanchik and ME Baker.1997. A landscape-based ecological
classification system for river valley segments in Lower Michigan. Fisheries Research
Report No. 2036, Michigan Department of Natural Resources, Ann Arbor.
5. King, RS and ME Baker. 2014. Use, misuse, and limitations of Threshold Indicator Taxa
Analysis (TITAN) for estimating ecological community thresholds. In: G. Guntenspergen
(editor), Application of Threshold Concepts in Natural Resource Decision Making, Springer,
New York.
4. Tarboton, DG and ME Baker. 2008. Toward an algebra for terrain-based flow analysis.
Chapter 12 in N. Mount, G. Harvey, G. Priesthall, and P. Apin. (eds). Representing,
Modelling, and Visualizing the Natural Environment. Innovations in GIS series. CRC Press-
Taylor & Francis, London.
3. Gregory, S, A Allen, M Baker, K Boyer, T Dillaha, and J Elliott. 2007. Realistic expectations of
11
Document Accession #: 20210513-5107
20201221-5392 Filed Date: 05/13/2021
12/21/2020
Conference Proceedings
2. Tarboton, DG, KAT Schreuders, DW Watson, and ME Baker. 2009. Generalized terrain-based
flow analysis of digital elevation models. 18th World IMACS/MODSIM Congress, Cairns,
Australia, July 2009.
1. Nielson, BT, C. Bandaraogoda, ME Baker, JS Horsburgh, DK Stevens. 2009. Watershed
modeling for water quality trading. Proceedings of the AWRA summer specialty
conference, Snowbird, Utah, June 2009.
NON-PEER-REVIEWED WORKS
Submitted
12
Document Accession #: 20210513-5107
20201221-5392 Filed Date: 05/13/2021
12/21/2020
In Preparation
Baker, M, S Van Ryswick, A Miller. (In prep) Tracking channel change following dam removal
using low altitude remote imagery. Earth Processes and Landforms
Miller A, M Baker, S Van Ryswick, M Andrews, M Collins. (in Prep) New evidence of process-
based evacuation following dam removals. Earth Processes and Landforms
Baker ME, J Bos*, and RS King. (in prep). Reconsidering taxon-specific contributions to measures
of community change: updates to Threshold Indicator Taxa Analysis. Freshwater Science.
Baker ME and D Saavedra. (in prep).ValChanMap: geomorphic delineation of valley and channel
networks. Water Resources Research
Oakland, H, M Baker, and S Kroll. (in prep). Assessing aquatic habitat using low altitude remote
imagery. Freshwater Science.
Oakland, H, M Baker, and S Kroll. (in prep). Some restorations reduce habitat heterogeneity.
Ecological Applications.
Baker ME, I Yessalonis, K Lautar, and Nancy Sonti. (in prep) Rapid urban forest patch
characterization for monitoring and management. Ecological Applications
Baker ME and DS Rich (in prep) Observations regarding the causal consequences of
mountaintop mining. Environmental Science & Technology.
Van Appledorn* M and ME Baker. (in prep). Regional correspondence of woody riparian plant
functional traits subject to different flood regimes. Freshwater Biology.
Van Appledorn* M and ME Baker. (in prep). Regional patterns of flood regime across the
conterminous United States. Water Resources Research.
Van Appledorn* M, AJ Miller, and ME Baker. (in prep). Differentiation of functional traits along
flood regime gradients reveal role of hydraulic signals in structuring floodplain forests.
Ecology.
PRESENTATIONS
Presentations and Posters (Non-juried/Refereed)
13
Document Accession #: 20210513-5107
20201221-5392 Filed Date: 05/13/2021
12/21/2020
low altitude remote imagery. Society for Freshwater Science, May 2019, Salt Lake City
Utah.
Baker, ME, A Miller, S Van Ryswick, E Boyd, M Cashman, M Collins, M Andrews. Tracing
geomorphic change and downstream progress of sediment released by removal of Bloede
Dam, Patapsco River, Maryland. American Geophysical Union, December 2018,
Washington, DC.
Baker, ME. Assessing causality in stream assessment and restoration: a case study in
Appalachian surface mining. Invited speaker, Smithsonian Environmental Research Center,
November 2018.
Baker ME and D Saavedra. 2018. Development of automated channel extraction from LiDAR in
Chesapeake Bay Watersheds. American Water Resources Association, November 2018,
Baltimore Maryland.
Baker, ME. What We Have Learned About Baltimore’s Forests. Oral Presentation for
Baltimore’s Fantastic Forest Forum, Cylburn Arboretum, November 2017, Baltimore MD.
Rittle, A, M Baker, M Cashman, and A Miller. Workflow Evaluation of Error and Distortion in
SfM-Derived Point Clouds in Fluvial Environments. Oral Presentation for the American
Geophysical Union. Dec 2017. New Orleans, LA.
Baker, ME, D Jones, E Woytowitz, A Miller. Alternative models of hydrogeomorphic connectivity
in urbanizing Piedmont landscaps. Society for Freshwater Science Annual Meeting. May,
2017. Raleigh, NC.
Rittle, A, ME Baker, and AJ Miller. A UAV-SfM Approach fro extracting Channel Bathymetry and
Fluvial Features. Oral Presentation for the American Association of Geographers. April
2017. Boston, MA.
Clifton, Z and ME Baker.Assessing the limits of aerial detection of floodplain sediment storage
via multi-temporal LiDAR. Oral Presentation for the US- International Association for
Landscape Ecology Annual Symposium. April 2017. Baltimore, MD.
Van Appledorn, M and ME Baker. Incorporating 2D hydraulic modeling in floodplain ecosystem
investigation. Oral Presentation for the US- International Association for Landscape Ecology
Annual Symposium. April 2017. Baltimore, MD.
Van Appledorn, M and ME Baker. Flooding does not always constrain riparian species
composition: evidence of environmental filtering and limiting similarity in floodplain
forests. Oral Presentation for the US- International Association for Landscape Ecology
Annual Symposium. April 2016. Ashville, NC.
Van Appledorn, M and ME Baker. Flooding does not always constrain riparian species
composition: evidence of environmental filtering and limiting similarity in floodplain
forests. Oral Presentation for the Ecological Society of America Annual Meeting. August
2015. Baltimore, MD.
Baker, ME. Landscape approaches to nutrient and sediment management in streams: past
research and future directions . Invited presentation Society for Freshwater Science Annual
Meeting. May, 2015. Milwaukee, WI.
Van Appledorn, M and ME Baker. Quantifying hydrologic and functional diversity of riparian
forest ecosystems in Maryland: towards a more mechanistic understanding of abiotic-
biotic interactions for cost-effective restoration. Invited Oral Presentation for the
Chesapeake Modeling Symposium. May 28-29, 2014. Annapolis, MD.
14
Document Accession #: 20210513-5107
20201221-5392 Filed Date: 05/13/2021
12/21/2020
15
Document Accession #: 20210513-5107
20201221-5392 Filed Date: 05/13/2021
12/21/2020
NM.
Baker ME and RS King 2010. A new method for detecting biodiversity and ecological community
thresholds. US-IALE Annual Meeting Athens, GA.
VanAppledorn M and ME Baker. New software tools for strategic prioritization of riparian
coservation and restoration. 2010 US-IALE Annual Meeting Athens, GA.
Panunto M and ME Baker. Using a hydrogeomorhic typology to understand distributions of
riparian buffers in Central Indiana. US-IALE Annual Meeting Athens, GA.
Van Appledorn M and ME Baker 2009 Effects of relative wetness on riparian buffers potential in
Maryland. NABS Grand rapids, MI.
Baker, ME, DE Weller, TE Jordan 2009 Effects of riparian buffers on watershed nitrate
discharges: new models and m management implications. NABS annual meeting, Grand
Rapids, MI.
King RS and ME Baker. 2009. Threshold Indicator Taxa Analysis (TITAN): a new method for
detecting biodiversity and ecological community thresholds NABS, Grand Rapids, MI.
Van Appledorn M and ME Baker 2009 Effects of relative wetness on riparian buffers potential in
Maryland. IALE Annual meeting, Snowbird, UT.
Weller, DE, ME Baker, and TE Jordan Effects of riparian buffers on watershed nitrate discharges:
new models and m management implications. IALE Snowbird, UT.
Baker ME and RS King Threshold Indicator Taxa Analysis (TITAN): a new method for detecting
biodiversity and ecological community thresholds IALE ,Snowbird, UT.
Weller, DE, ME Baker, and TE Jordan Effects of riparian buffers on watershed nitrate discharges:
new models and m management implications. EBM Baltimore, MD.
Baker, ME, DE Weller, TE Jordan New tools for measuring the effects of riparian buffers. EBM
Baltimore, MD.
Baker, ME and DG Tarboton. Generalized models of flow across terrain using digital elevation
models. American Geophysical Union, San Francisco, CA December 2008.
Van Appledorn, M and ME Baker. A Comparison of Riparian Restoration Strategies for Water
Quality Improvement within and Among Watersheds. AWRA Summer specialty conference
Virginia Beach, VA June 2008.
Boomer K, DE Weller, ME Baker, and TE Jordan. Using Fine-Resolution Topography Data to Infer
Groundwater Flowpaths and Denitrification Potential in Riparian Wetlands in the
Chesapeake Bay Watershed. AWRA Summer specialty conference Virginia Beach, VA June
2008.
Van Appledorn, M and ME Baker. A simulation comparing spatially-explicit riparian restoration
strategies for water quality improvement within and among watersheds. International
Association of Landscape Ecology (US-IALE), Madison, WI, April 2008.
Baker, ME and DG Tarboton. New approaches for representing uncertainty in watershed
connectivity. International Association of Landscape Ecology (US-IALE), Madison, WI, April
2008.
Tarboton, DG, KA Schreuders, ME Baker. New TauDEM tools for deriving hydrologic information
from digital elevation models. AWRA 2008 Spring Specialty Conference, San Mateo, CA,
March
2008.
Tarboton, DG, ME Baker, KA, Schreuders. Terrain analysis and the modeling of catchment
architecture. European Geophysical Union, Vienna, Austria, April 2008.
16
Document Accession #: 20210513-5107
20201221-5392 Filed Date: 05/13/2021
12/21/2020
Baker, ME, MJ Wiley. Using structural equations to explore multi-scale predictions of riparian
hydrology. Invited: North American Benthological Society (NABS), Columbia, SC, May
2007.
Baker, ME, MA White, DE Weller, TE Jordan. Using land surface phenology to explore the
effects
of landscape and riparian features on nutrient discharges in tributary watersheds
of Chesapeake
Bay. International Association of Landscape Ecology (US-IALE), Tucson, AZ,
April 2007.
White, MA, ME Baker, DE Weller, TE Jordan. Land surface phenology in eastern United Stated
watersheds: relationships between remote sensing metrics, stream chemistry, snow cover,
and
leaf and bird phenology. American Geophysical Union, Sand Francisco, CA.
Baker, ME, DE Weller, TE Jordan. Effects of Stream Map Resolution on Measures of Riparian
Buffer Distribution and Nutrient Retention Potential. American Geophysical Union,
Baltimore, MD
May 2006.
Baker, ME, DE Weller, TE Jordan. Watershed-scale thresholds in the potential effectiveness of
riparian buffers. US-IALE, San Diego, CA, March, 2006.
Baker, ME, DE Weller, TE Jordan. Transport-distance effects in regional predictions of nitrate
discharge: implications for nitrogen transformation. NABS/AGU Joint Session, New
Orleans, LA,
June 2005.
Baker, ME, DE Weller, TE Jordan. Improved methods for quantifying patterns of riparian buffers
US-IALE, Syracuse, NY, April, 2005.
Baker, ME, DE Weller, TE Jordan. Effect of within-watershed land cover arrangement on nutrient
discharge. NABS, Vancouver, BC, June 2004.
Baker, ME, DE Weller, TE Jordan. Landscape-level effects of riparian buffers: considering spatial
configuration and hydrologic routing in geographic predictions of nutrient discharge. US-
IALE, Las Vegas, NV, April, 2004
Baker, ME, DE Weller, TE Jordan. Landscape-level effects of riparian buffers: considering spatial
configuration and hydrologic routing in geographic predictions of nutrient discharge.
Invited: Soil Science Society of America, Denver, CO, October, 2003.
Baker, ME, DE Weller, TE Jordan. The effect of distance-weighted source areas in geographic
predictions of nutrient discharge from coastal-plain watersheds. NABS, Athens, GA, May,
2003.
Baker, ME, DE Weller, TE Jordan. The effect of distance-weighted source areas in geographic
predictions of nutrient discharge. US-IALE, Banff, Alberta, Canada, April, 2003.
Baker, ME, MJ Wiley. Climatic and hydrologic influences on the spatial variation of riparian
forests. NABS, Pittsburgh, PA, May 2002.
Baker, ME, MJ Wiley, PW Seelbach. GIS-based modeling of riparian hydrology and stream water
quality. US-IALE, Lincoln, NE, April 2002.
Baker, ME, MJ Wiley. Predicting spatial variation in riparian hydrology and forest composition
across Lower Michigan. US-IALE, Tempe, AZ, April 2001.
Baker, ME, MJ Wiley. Using GIS-based models to understand riparian function and forest
composition. 62nd Midwest Fish and Wildlife Conference, Minneapolis, MN, December
2000.
Baker, ME, MJ Wiley. Predicting the structure and function of riparian ecosystems. AWRA
17
Document Accession #: 20210513-5107
20201221-5392 Filed Date: 05/13/2021
12/21/2020
Baker, ME. 2014. Impacts of development on Ten Mile Creek. Testimony before the
Montgomery County Council. Jan-Feb. Rockville, MD
Baker, ME. 2010. Opportunities at the interface of hydrology and ecology. National Research
Council’s Committee on Challenges and Opportunities in the Hydrologic Sciences. National
Academy of Sciences, Washington DC, Invited Speaker, Sept 9th, 2010.
Baker ME and RS King 2009 Threshold Indicator Taxa Analysis (TITAN): a new method for
detecting biodiversity and ecological community thresholds. Fall BES meeting, Baltimore,
MD.
Baker ME and RS King 2009 Threshold Indicator Taxa Analysis (TITAN): a new method for
detecting biodiversity and ecological community thresholds. EPA Regional Stormwater
meeting, Edison NJ.
Media Activities
18
Document Accession #: 20210513-5107
20201221-5392 Filed Date: 05/13/2021
12/21/2020
scientists-concerns/
WYPR Maryland in the Morning with Shelia Kast, February 10, 2010:
http://mdmorn.wordpress.com/2010/02/09/210102-measuring-the-biological-effects-of-
development/
Environmental Protection online, February 4th, 2010:
http://eponline.com/articles/2010/02/04/ecologists-create-a-more-precise-way-to-measure-
human-
impacts.aspx
Baltimore Sun, B’more Green with Meredith Cohn, February 3rd, 2010:
http://weblogs.baltimoresun.com/features/green/2010/02/new_way_found_to_tell_when_s
pe.html
Science Centric, February 3rd, 2010: http://www.sciencecentric.com/news/10020331-
researcher-
develops-new-method-detecting-biodiversity-losses.htm
B,more media interview with Walaika Haskins, February 1st,
2010:http://www.bmoremedia.com/innovationnews/umbcecologist020210.aspx
Legal Activities (in which I have been deposed or provided expert testimony)
1. IRS easement assessment (146 Tax Court No. Docket 5445-13, Baltimore, MD)
2. Ohio Valley Environmental Coalition v. Fola Coal, (S.D. W.Va. 2:13-21588) Liability
3. Ohio Valley Environmental Coalition v. Fola Coal, (S.D. W.Va. 2:13-5006) Remedy
4. Ohio Valley Environmental Coalition v. Fola Coal, (S.D. W.Va. 2:13-21588) Remedy
5. Ohio Valley Environmental Coalition v. Fola Coal, (S.D. W.Va. 2:15-1371) Liability
6. Canaan Christian Church and Burtonsville Crossing, LLC and Burtonsville Associates, LLC and
Jennifer M. Sarem and Marion G. Sarem v. Montgomery County, Maryland and Montgomery
County Council and Isiah Leggett, (MD Case No.:16-cv-03698-TDC)
19
Document Accession #: 20210513-5107
20201221-5392 Filed Date: 05/13/2021
12/21/2020
Courses Taught
Workshop: Threshold Indicator Taxa Analysis (TITAN) and analysis of biological community data
in R. Society for Freshwater Science: Mid-Atlantic Chapter, January 30th, 2015, Philadelphia,
PA.
Workshop: Threshold Indicator Taxa Analysis (TITAN) and analysis of biological community data
in R. Association of Mid-Atlantic Aquatic Biologists, March 27th-28th, 2014, Berkeley Springs,
WV.
Workshop: Statistical Workshop for water resource managers: Analysis of biological
community data in R. New England Association of Environmental Biologists, March 25-26th,
2014, Burlington, VT.
Workshop: R statistical computing and training and Threshold Indicator Taxa Analysis (TITAN).
New England Association of Environmental Biologists, March 19-20th, 2013, Lake Placid, NY.
Workshop: 2011. R statistical computing and Threshold Indicator Taxa Analysis (TITAN). USGS
New England Water Resource Center. Feb.
Workshop: 2010. R statistical computing and Threshold Indicator Taxa Analysis (TITAN). USGS
Maryland-Delaware-Virginia Water Resource Center. Oct.
Geography and Environmental Systems (UMBC) 600 Quantitative Methods
Geography and Environmental Systems (UMBC) 405 Applied Landscape Ecology
Geography and Environmental Systems (UMBC) 110 Physical Geography
Geography and Environmental Systems (UMBC) 404 Forest Ecology
Geography and Environmental Systems (UMBC) 419 Watershed Analysis and Modeling
Geography and Environmental Systems (UMBC) 319 Watershed Science and Management
Geography and Environmental Systems (UMBC) 400 Ecology and Management of Riparian
Ecosystems
Geography and Environmental Systems (UMBC) 602 Research Methods
Geography and Environmental Systems (UMBC) 689 Departmental Seminar
Watershed Sciences (USU) 4930/6920 Geographic Information Science.
Watershed Sciences (USU) 6200 Watershed Analysis.
Watershed Sciences (USU) 5640 Riparian Ecology and Management.
Watershed Sciences (USU) 5490 Small Watershed Hydrology, Guest lectured on GIS applications
in hydrology and watershed modeling.
Environment and Society (USU) 6200 Bioregional Analysis and Planning, Guest lectured on
analysis and assessment of watershed hydrology, four 2-hr class periods.
Natural Resources and Environment (UMich) 511 Introduction to Aquatic Ecosystems, TA
20
Document Accession #: 20210513-5107
20201221-5392 Filed Date: 05/13/2021
12/21/2020
responsible for laboratory content delivery, taught 5-hr laboratory sections and led field trips
for two semesters.
Natural Resources and Environment (UMich) 435 Forest Ecology, TA and assisted in content
delivery, taught field laboratory section.
Natural Resources and Environment (UMich) 337/437 Biology and Identification of Woody
Plants, TA, fully responsible for two 5-hr field laboratory sections, taught 4 semesters.
Environmental Law Program (Vermont Law School) Watershed Management and Protection, TA
developed and delivered field laboratory for a capstone course.
Maine Conservation School, Forest Ecology and Limnology, assisted in developing content, fully
responsible for instruction to high-school and continuing education students
SERVICE TO THE DEPARTMENT, UNIVERSITY, COMMUNITY, and PROFESSION
21
Document Accession #: 20210513-5107
20201221-5392 Filed Date: 05/13/2021
12/21/2020
22
Document Accession #: 20210513-5107
20201221-5392 Filed Date: 05/13/2021
12/21/2020
23
Document Accession #: 20210513-5107
20201221-5392 Filed Date: 05/13/2021
12/21/2020
24
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Exhibit B
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Ben Luckett
Senior Attorney
Appalachian Mountain Advocates
PO Box 507
Lewisburg, WV 24901
Greenstar appreciates the opportunity to submit the attached hydrogeologic comments for the
documents associated with the Mountain Valley Pipeline.
Please do not hesitate to contact Pete Nimmer at (917) 655-5123 with questions.
Sincerely,
Page 2
Mountain Valley Pipeline, LLC (MVP), has requested that the Federal Energy Regulatory
Commission (FERC) amend its Certificate of Public Convenience and Necessity to allow the
construction of the Project between Mileposts 0 and 77 by crossing 69 waterbodies using 41
conventional boreholes instead of the open-cut method addressed in the Final Environmental
Impact Statement (FEIS) and currently authorized by MVP’s Certificate. MVP contends this
requested change would have limited, if any, environmental impacts beyond those that have
already been assessed in the FEIS and approved by the Commission. Additionally, MVP notes
the requested change to conventional borehole crossings will not result in a change in land
requirements compared to what was previously reviewed.
However, a review of the limited documentation MVP provided establishes that significant
adverse consequences are likely to occur from this change of waterbody crossing method.
Moreover, the information MVP has provided is incomplete and inadequate to fully assess the
environmental impacts that may occur.
MVP’s assertion in its application that its proposed actions “would have limited, if any,
environmental impacts beyond those that have already been assessed and approved by the
Commission” does not withstand scrutiny. The requested change includes drilling below water
bodies, construction of pits, significant dewatering operations, and other industrial activities
which were not considered in the FEIS approved by the Commission. The potential adverse
consequences of these actions—including disruption of groundwater flow, harm to drinking
water supplies, dewatering of surface waters, and catastrophic failure of the pipe—will present
significant harm to surface water and groundwater resources. These impacts were likewise not
considered in the FEIS. MVP’s proposed methodologies threaten significant adverse
consequences, but the information MVP has provided to date does not allow FERC to adequately
assess the environmental impacts of the proposed actions. Accordingly, FERC should not
authorize the proposed actions until it gathers sufficient information regarding the boring
operations, as detailed below, such that it can rationally assess, consider, and disclose to the
public the likely impacts of MVP’s proposal.
Numerous adverse consequences are likely when using conventional boreholes to cross
waterbodies. Major issues are raised by using conventional boring techniques, and those issues
were not addressed in the original Environmental Impact Statement, in which only open-trench
crossing methods were assessed for the waterbodies implicated by MVP’s pending application.
Page 3
the borehole due to increases in soil porosity and/or permeability. The disruption of these
areas, and increased turbidity caused by the project, will adversely impact ecosystems
within the surrounding surface water bodies, flood plains and wetland areas, as well as
the wildlife habitats in these areas. Information provided by MVP in the December 11,
2020 Response to Environmental Information Request notes that pumping from bore pits
can accommodate up to 396 gallons per minute and MVP will run pumps sufficient to
control infiltration rates up to 2,750 gallons per minute. These values provide an
understanding of the volume groundwater that may be pumped from bore pits depending
on soil types and groundwater conditions. Dewatering rates of this magnitude are likely
to result in significant changes to surface water bodies, although the applicant does not
discuss what effects may result or how effects will be mitigated, or where water will be
pumped and how turbidity of the discharge will be managed to prevent fouling of surface
water resources. Further, MVP notes that groundwater withdrawal may result in short
term changes in groundwater in the immediate vicinity of bore pits. A groundwater
modeling study is cited which notes measurable affects for groundwater withdrawal up to
300 ft from the bore pits. The large volumes of water which may be pumped (hundreds
to thousands of gallons per minute) have a significant likelihood to affect nearby surface
water or groundwater. As discussed further below, it is clear there are more residences
within 150 ft than have been identified. MVP notes that measurable effects of
groundwater pumping is at least 300 ft based on similar projects. The radius of influence
from dewatering at bore pits may be larger than 300 ft depending on geologic conditions,
soil types, bedrock geology, well depth, and other variables.
Groundwater Use - Groundwater resources in the area of the crossings may be used for
residential or commercial uses. The proposed drilling methods have a significant
likelihood of threatening groundwater use through degradation of groundwater quality
which can cause drinking water well failure or pollution, changes in groundwater yield
rates and adverse changes in groundwater quality. These issues were not considered in
the Final Environmental Impact Statement when open-cut crossings were considered and
approved.
Current and Future Flooding - Crossing depths may not be adequate to prevent
pipeline surfacing within or adjacent to a water body, or damage during flood events. If
flooding results in unanticipated amounts of lateral and/or vertical erosion, pipeline
damage may occur which could cause the release of pressurized gas directly into surface
1 A related issue is the result of a failed borehole. If a borehole cannot be completed the failed borehole has the
potential to become a major underground hydraulic conduit which may result in dewatering of surface water bodies.
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Page 4
This report takes at face value Mountain Valley’s statement that conventional bores will be used
for all crossings and other technologies (i.e., HDD or Microtunneling) will not be used which
require pressurized drilling fluids. If other boring technologies and drilling fluids were used,
these would add significant risk to water bodies. For example, near surface injection of these
drilling fluids poses a major potential risk that was not considered in the FEIS. Large volumes of
pressurized fluids can be injected during drilling. Because the fluids are pressurized, they can
move in unexpected directions, including upwards, and discharge into surface water or wetlands
or into aquifers used for drinking water. The crossings being proposed are very close to the
surface and therefore, should pressurized drilling fluids be used, they would have a significant
risk of moving into surface water. Additionally, fluids may be stored in pits near surface water
or wetlands which also have a potential for release. A release of drilling fluids into surface
waters or groundwater will have significant environmental affects due to the high pH of fluids,
elevated turbidity and chemicals in the drilling fluid. Any release has the potential to cause acute
or chronic human health or ecological impacts. Releases of drilling fluids are frequent
occurrences during drilling operations. At these locations, should drilling fluids reach wetlands,
surface water bodies, or groundwater resources, significant short term and long term impacts
would result. The speed at which a drilling fluid release is detected is largely governed by the
magnitude of the release. Therefore, small or moderate releases are not likely to be recognized
before damage is done to sensitive resources and water bodies.
The information provided in the application and its supporting materials does not provide critical
information necessary to determine the extent of the significant environmental issues that may
result from the proposed change in crossing method. Most significantly, necessary information
is not included to assess how changes in groundwater or surface water flow and quality may be
affected during boring or in the future. At a minimum, the following information needs to be
provided by the applicant—and considered by FERC—to assess the potential environmental
impacts related to the proposed change in crossing method.
Page 5
Page 6
its preconstruction notification to the U.S. Army Corps of Engineers when it sought
verification that it was authorized to construct its stream crossings under Nationwide
Permit 12 reveals that neither that plan nor anything else in the docket for the pending
application provides detail on how an inadvertent return or release of drilling fluids into
wetlands or surface water will be adequately prevented. The Inadvertent Return Plan has
general descriptions of what steps may occur after an inadvertent release but no details
are provided on how drilling fluid releases will be prevented from occurring. Before it
approves a method that requires the use of pressurized drilling fluids, FERC should
require further information addressing how the release of drilling fluids will be
prevented. Given that the magnitude of the release is directly related to how quickly the
release will be identified, small or moderate releases are not likely to be recognized
before damage is done to sensitive resources and water bodies. There are no specifics
included which may address how releases of drilling fluids will be quickly identified.
Similarly, the Supplemental Environmental Report for Proposed Conventional Bore
Waterbody and Wetland Crossings from Mileposts 0 to 77, November 2020 notes boring
operations may require 24-hour operation. Visual observations are a primary method
identified in the Boring Procedures and Inadvertent Return Plan to identify if drilling
fluid releases occur. The plan does not indicate how visual observations will be made if
drilling activities are occurring after dark.
Prevention and Contingencies for Failed Boreholes – One or more failed boreholes
should be considered a likely possibility given the size of the individual crossings (up to
260 ft long), the cumulative total borehole distance (4,295 ft), and varying geologic
conditions at the 41 different locations. Several such conditions would result in a
borehole that cannot be completed to its intended length such as unexpected geology,
problematic geology or soils, or equipment issues. The descriptions of the proposed
boring technology provided in the Supplemental Environmental Report for Proposed
Conventional Bore Waterbody and Wetland Crossings from Mileposts 0 to 77, November
2020 Section 1.4 (i.e., Conventional Bore) note that boulders and cobbles up to one third
of the diameter of the installed pipe can be accommodated by the drilling method.
However, there is a very limited discussion of what actions will be taken if obstacles are
encountered which cannot be accommodated by the drilling method, or what will occur if
boreholes are abandoned to prevent environmental impacts. The December 11, 2020
Response to Environmental Information Request Issued December 2, 2020 notes:
This limited description is not a contingency plan for how a failed borehole will be
properly abandoned to prevent forming a major hydraulic conduit underlying wetlands or
surface water which may cause dewatering of surface water bodies. The large diameter
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Page 7
of the proposed boreholes has the potential to result in formation of a very large conduit
that could result in the diversion of significant quantities of surface water or groundwater.
In addition to a comprehensive plan to prevent failed boreholes to identify contingencies,
information should be provided on how often boreholes fail to reach their objective
length, which collapse or have an inadvertent return resulting in release of drilling
lubricants or water. Although it claims in its Response to Environmental Information
Request to have “successfully completed more than 35 conventional bore crossings of
more than 45 streams and wetlands between MP 0 and 77” MVP should provide
information on the number of failed, incomplete or collapsed boreholes which have
occurred on this or similar projects to evaluate how likely these occurrences may be.
It is clear that numerous adverse consequences are likely when using boreholes to cross below or
within waterbodies. Direct harm to sensitive receptors and important water resources should be
considered as possible or likely occurrences. Issues related to drilling were not considered in the
original Environmental Impact Statement when open trench crossing methods were assessed.
Providing additional information to address these issues is necessary to fully evaluate the
significant environmental harm that may result from the proposed drilling activities.
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Page 8
Mountain Valley submitted a letter dated December 11, 2020 to address FERC’s December 2,
2020 Environmental Information Request. Comments on that submission are provided below.
Original Comment: Indicate the timing for determining whether or not a particular conventional
bore is infeasible based on conditions. Describe the contingency plan for the conventional bore
crossings if the bore is deemed infeasible.
The information provided by MVP in this response indicates a contingency plan will be
implemented if the bore is deemed infeasible. However, the response does not provide a
description of an actual contingency plan. Among other issues, a contingency plan should assess
how the decision will be made to terminate a bore, how the bore will be properly abandoned so it
does not create a hydraulic conduit or damage overlying surface water, inspections, or what
actions will be taken to prevent bore collapse or limit the potential for a release of pressurized
drilling fluids. The location of the bore will be an important variable to consider, because a
failed bore under a large stream has the potential for a much larger impact than under a smaller
tributary. These issues are not discussed in the response to comment.
Original Comment: Identify all private and public groundwater wells and springs within
150 feet of the proposed bore pits.
Response: Based on publicly available databases and contacts with landowners that
began in 2017 and has continued to the present, one private groundwater well is located
within 150 feet of the proposed bore pits. A private well is located at MP 25.8
approximately 30 feet southwest of the bore pit on the northern side of crossing A-013.
This well is on a vacant parcel that previously contained a house trailer that was
removed in 2017, and the well is currently not in use. No known springs or public
groundwater wells are located within 150 feet of the proposed bore pits.
Information provided by MVP the December 11, 2020 letter notes one former well is known to
be present although this data is based on publicly available databases and land owner outreach.
However, other documentation provided by MVP in in Attachment 11-A – Nearest Noise
Sensitive Area documents there are 2 residences located within 150 ft of bore pits (at crossings
A-013 and A-014) and at least 10 additional residences are located within 300 ft of the drilling
locations. Therefore, it is clear there are more residences within 150 ft than have been identified.
Moreover, the groundwater modeling study cited notes measurable affects for groundwater
withdrawal up to 300 ft from the bore pits. Therefore, 300 ft should be used as a minimum
estimate of the distance groundwater impacts may extend from each location. A brief review of
USGS maps and Google Street View suggests there may be other residences or commercial
buildings close to bore pits or drilling areas. These are all likely to have shallow drinking water
wells which may be impacted by drilling activities or are subject to potential degradation of
water quality.
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Page 9
It is worth noting that private wells in rural areas are not likely to be represented in publicly
available databases that MVP used to search for drinking water wells. Also, the number of
residences that were successfully contacted during public outreach is not known. Instead of
relying on databases and limited outreach, a comprehensive survey should be completed to
accurately identify how many residences and wells are within 500 feet of drilling areas, or which
may be affected by bore operations. Springs are another potential source of potable water, and
the presence or absence of nearby springs should also be quantified. A monitoring plan should
be developed for these receptors to assess current conditions and ascertain what effects may be
due to drilling work in the near or long term.
Original Comment 4. Section 1.4.1 of the Supplemental Plan states “Bore-pit dewatering may
be required 24 hours per day.” and “The specific need for, and amount of, dewatering required
for each waterbody or wetland crossing cannot be determined until each individual trench or
bore-pit excavation begins.” The depths of many of the pits shown in Appendix C exceed the
practical lifting capacity of centrifugal surface pumps and may require additional pumping
schemes such as well points or combination of surface pumps and deeper dewatering. Given the
number and depth of the bore pits, and the potential duration of pumping to keep the pits dry in
order to advance the bore(s), provide:
a. a description of the means and methods necessary to pump water from each
of the proposed bore pits;
b. an assessment of the rate and volume of water pumped from the bore pits
and the anticipated duration of pumping needed; and
c. a description of possible water-level drawdown impacts on nearby wells,
springs, and wetlands within 150 feet of the bore pits.
The response provided by MVP to Comment 4a and b notes that pumping from bore pits can
accommodate up to 396 gallons per minute and MVP will run pumps sufficient to control
infiltration rates up to 2,750 gallons per minute. These values provide an understanding of the
potential volume groundwater which may be pumped from bore pits depending on soil types and
groundwater conditions. The response to Comment 4c notes that groundwater withdrawal may
result in short term changes in groundwater in the immediate vicinity of bore pits. A
groundwater modeling study is cited which notes measurable affects for groundwater withdrawal
up to 300 ft from the bore pits.
The large volumes of water which may be pumped (hundreds to thousands of gallons per minute)
have a significant likelihood to affect nearby streams and drinking water sources. As noted
above, it is clear there are more residences within 150 ft than have been identified. MVP notes
that measurable effects of groundwater pumping is at least 300 ft based on similar projects. The
radius of influence from bore pits may be larger than 300 ft depending on geologic conditions,
soil types, bedrock geology, well depth, and other variables. For these reasons a comprehensive
assessment of groundwater drinking water wells within at least 300 ft should be developed for
each crossing location. Location specific data on wells, well depths, flow rates and water
elevation should be collected and provided to document baseline conditions and how future
conditions will be monitored to ensure there is no lasting environmental impacts due to the
proposed borehole drilling. Significant changes to water table elevations due to pumping, even if
temporary, can result in significant long term degradation of water quality at nearby drinking
water wells.
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Education:
• M.S. Geology 1991, University of Iowa
• B.S. Geology, 1989, State University of New York at Stony Brook
Licenses/Certifications:
• New Jersey Licensed Site Remediation Professional (LSRP) No. 513636
• Professional Geologist License, State of New York, License No. 000794-1
• Professional Geologist License, State of Washington No. 2404
• 40 Hour OSHA with annual updates
Experience:
• Extensive experience with geology, hydrogeology and environmental sites involving groundwater flow and
contamination
• Groundwater modeling for sites with complex hydrogeology
• Remediation of groundwater within fractured bedrock
• Planning and management of complex hydrogeology projects including karst settings
• Assessment of surface water interaction with groundwater
• Aquifer yield assessments using pumping tests and computer modeling
• Optimizing long-term monitoring programs using statistics
• Assessment of complex sites involving numerous individual source areas
• Development of groundwater models used to assist in remedial design and predictive scenarios
Professional Overview:
Mr. Nimmer is a licensed Professional Geologist and New Jersey Licensed Site Remediation Professional with
experience with technical oversight for numerous environmental projects and a founding partner of Greenstar
Environmental Solutions, LLC. He has extensive experience designing, managing, and executing investigation of
groundwater issues. He has extensive experience designing, managing, and executing aquifer studies in bedrock and
karst, well yield assessments and hydrogeology investigations. He has worked extensively on-site cleanups from
initial investigation to site closeout. Clients include commercial entities, insurance companies, government
agencies, attorneys and not-for-profit clients.
Mr. Nimmer is currently the LSRP of record for several sites involving groundwater flow and cleanup. He has over
27 years of experience in the environmental industry. Mr. Nimmer has completed site assessment and closure at
numerous sites nation-wide. He has managed programs with numerous sites undergoing simultaneous investigation
and remediation.
Project Experience:
Bedrock Extraction Well Installation, New Jersey; 2005 – Present; Project Manager and Technical Leader—
Greenstar has completed several large pumping tests in conjunction with locating and designing groundwater
extraction wells. Pumping tests have included multi-day flow assessments, use of data loggers to monitor water
elevations in numerous observation wells, calculation of aquifer parameters, well design, well installation and
connection to pumping system. Completed slug testing to determine hydraulic conductivity at over 100 locations as
part of aquifer assessment. A total of 13 extraction wells have been installed in fractured bedrock at this site.
Bedrock Groundwater Yield Assessment, New Jersey, 2011 – Present; Technical Lead — As part of pre-design
study, completed aquifer flow assessments including slug testing, calculation of hydraulic conductivity, groundwater
yield and reporting.
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Multi-Year Groundwater Flow Assessment, Calvert City, Kentucky; 2011 – Present; Project Manager and
Technical Leader — Completed a multi-year groundwater flow assessment in support of remedial design at
Superfund site undergoing remediation using groundwater extraction system. Deployed pressure transducers,
collected data and provided detailed groundwater flow assessment based on results. This site is a complex
overburden site with interbedded clay, silt and sand and complex flow conditions.
Hydrogeology Assessments; Project Manager and LSRP of Record—Completed hydrogeology assessments for
numerous sites throughout the Northeast. Sites include those with impacted groundwater, assessment of
groundwater flow related to collection trenches, pump and treat systems, closed landfills and sites in complex
geologic conditions such as fractured bedrock. Prepared reports for Federal, State and community groups.
Groundwater Modeling of Groundwater Flow; Project Manager and Technical Lead—Manager of numerous
groundwater modeling assessments completed to assess groundwater and surface water interactions, effects on
surface water or wetlands due to groundwater withdrawal or injection.
Chlorinated Solvent Release, Somerset, New Jersey; 2005 – Present; Project Manager and LSRP of Record—
LSRP of record for a former research laboratory. Managed soil remediation and obtained No Further Action
approval for all site soils. Completed Remedial Investigation for groundwater and sub-slab vapor concerns of
chlorinated solvent with significant groundwater flow concerns. Completed all aspects of large scale bedrock
groundwater investigation including installation of numerous monitoring wells, low flow groundwater sampling,
groundwater remediation using combined pump and treat and in-situ chemical reduction of solvents using zero
valiance iron. Planned and managed sub-slab vapor investigation and remediation program. Submitted numerous
documents to NJDEP and other agencies including public notices, vapor intrusion work plans and reports, Remedial
Investigation Report, Remedial Action Reports, Classification Exemption Area, Well Search, groundwater remedial
action permits, groundwater remediation reports, Quality Assurance Project Plans and Data of Known Quality
reviews.
Petroleum Release Site, Elizabeth, New Jersey; 2012 – Present; Project Manager and LSRP of Record—
LSRP of record for a former industrial site with gasoline and fuel oil release. Overseen site remediation,
groundwater remediation via monitored natural attenuation, and remedial action.
Petroleum Release Site, South Hackensack, New Jersey; 2013 – Present; LSRP of Record—LSRP of Record
for a property with petroleum release and groundwater lead plume. Overseeing all aspects of LSRP program
including groundwater sampling via low flow sampling method, assessment of groundwater trends, and review of
historic fill issues.
Numerous Sites Undergoing PA/RI/RA, New York, New Jersey, Connecticut and Massachusetts; 2010 –
Present; GPR and Geophysical Technical Lead —Technical manager for ground penetrating radar and
geophysics for numerous sites in New Jersey and the North East United States. Has overseen and completed
numerous site assessments using GPR to locate tanks, lines, landfills, underground lines, septic fields, and extent of
previous soil remedial excavations. Sites have included former gas stations, dry cleaners, industrial sites, vehicle
maintenance and operation facilities and military facilities.
National Phase 2 Program, Nation Wide, 2010 – 2012; Project Manager — Project manager for nation-wide
Phase 2 investigation program. Investigated numerous properties undergoing property transfer to assess
environmental conditions and provide recommendations for remediation. Managed technical and subcontractor
resources during completion of numerous Phase 2 environmental site investigations.
Former Gasoline Station Brown Field Site, New York, 2010 – Present; Project Manager — Project manager
for investigation and remediation of former gasoline filling station impacted by petroleum from leaking USTs.
Completed soil and groundwater remedial investigation of site, developed alternative analysis plans for property and
negotiated with State regulators. Site is an unused Brownfield that is being renovated for commercial and
residential use.
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Technical Report Preparation and Review—Prepared planning documents for landfills and hazardous site
activities, including environmental Phase 1 and 2 reports, Work Plans, Field Sampling Plans, and Safety and Health
Plans. Has completed CERCLA documents for Superfund sites on the National Priority List, including Remedial
Investigations, Proposed Plans, Records of Decision, Long-Term Monitoring Plans, Monitoring Event Reports, Five
Year Reviews, Annual Sampling reports, Health and Safety Plans, and Quality Assurance / Quality Control Plans.
Provided review for FERC documents related to the Falls Street Tunnel Improvements for the Lewiston Reservoir in
Niagara Falls, New York.
Not-For-Profit Experience- Not for profit experience includes completing environmental assessments prior to
property purchase for Open Space Institute for multiple properties in New York State. Professional assessment of
sub-slab vapor concern for Dutchess County Community Action in New York. Provided consulting services related
to wetlands issues and surface water flow for the Harvey School in Millbrook, New York. Provided environmental
assessments of 14 properties in Middletown, New York to facilitate grant funding.
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Exhibit C
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Ben Luckett
Senior Attorney
Appalachian Mountain Advocates
PO Box 507
Lewisburg, WV 24901
Greenstar appreciates the opportunity to submit the attached hydrogeologic comments for the
documents associated with the Mountain Valley Pipeline.
Please do not hesitate to contact Pete Nimmer at (917) 655-5123 with questions.
Sincerely,
Page 2
COMMENTS ON
FERC’S JANUARY 7, 2021 ENVIRONMENTAL ASSESSMENT,
MOUNTAIN VALLEY PIPELINE’S FEBRUARY 2021 APPLICATIONS TO AMEND
ITS CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY AND FOR AN
INDIVIDUAL SECTION 404 PERMIT, FERC’S MARCH 12, 2021 ENVIRONMENTAL
INFORMATION REQUEST, AND MOUNTAIN VALLEY PIPELINE’S MARCH 29,
2021 RESPONSE
Mountain Valley Pipeline, LLC (MVP), has requested that the Federal Energy Regulatory
Commission (FERC) amend its Certificate of Public Convenience and Necessity to allow the use
of several boring methods at 120 locations to cross 182 streams and wetlands instead of the
open-cut method addressed in the Final Environmental Impact Statement (FEIS) and currently
authorized by MVP’s Certificate.
MVP’s assertion that its project will have “negligible effect on water supply and conservation” 1
is not supported by the provided documentation. As noted in previous comments provided in
December 2020, the requested change includes the possibility of potential adverse consequences
including drilling below water bodies, construction of pits, significant dewatering operations, and
other industrial activities which were not considered in the FEIS approved by the Commission. 2
This document addressed a variety of public comments received on MVP’s proposed amendment
to change the crossing method for all remaining wetlands and waterbodies from mile post 0 to 77
from open-cut crossing that were authorized by the Certificate to conventional bore methods.
The following issues were not fully addressed by FERC’s responses.
Section A, 5.0 Conventional Bore Construction Procedures – This section notes that for
conventional bores, “boulders and cobbles up to one third of the diameter of the installed pipe
can be accommodated,” and further observes that if boreholes cannot be completed a
contingency plan will be initiated and the borehole moved. However, should boreholes fail to be
fully installed or collapse, several adverse consequences are likely which were summarized in
previous comments (i.e., surface water or wetlands dewatering, changes in groundwater or
surface water interaction and groundwater use). The information provided in the response
indicates how these issues will be addressed after occurring (i.e., default to contingency plan) but
1 As noted in Section 4.4.12 Water Supply and Conservation in the Individual Permit Application dated February
2021.
2 On December 18, 2020, Greenstar Environmental Solutions, LLC, provided to Appalachian Mountain Advocates a
report entitled Comments on Mountain Valley Pipeline’s Requested Amendment to its Certificate of Public
Convenience and Necessity, which was then submitted to FERC. See Accession No. 20201221-5392. These
comments incorporate those December 2020 comments by reference, as if fully set forth herein.
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Page 3
significantly, does not indicate how these issues will be prevented from occurring. Due to the
serious adverse potential effects of a failed borehole, significant efforts should be made prior to
and during drilling to prevent borehole failures, deviation from the planned bore path or
encountering boulders greater than on third of the diameter of the installed pipe that may prevent
bore completion. MVP’s plan for preventing borehole completion issues should be fully
discussed.
Similarly, the use of grout to fill or seal incomplete or failed boreholes is not without risk. Use
of grout is not necessarily going to fully seal off all potential conduits. Grout is known to move
in unexpected directions and is susceptible to bridging which can leave portions of a failed
borehole open to the environment. Grout injection into horizontal bores would need to be done
under pressure and therefore potential release of the pressurized fluids into wetlands or overlying
waterbodies is a risk. Cement grout may have other materials mixed in, such as bentonite or
other additives, and release of this material can have adverse consequences in sensitive receptor
communities. Additional information regarding grouting of failed bores, such as detailed
monitoring plans and pollution prevention plans, should be provided such as detailed monitoring
plans and pollution prevention plans.
Section B, 2.1 Groundwater – This section addressed comments regarding how the proposed
crossing may affect groundwater and potable water supplies. In response to questions about how
water supplies may be affected this section states on Page 17 that
• “any groundwater-level drawdown and related impacts would be short term and
temporary and are expected to recover to non-pumping conditions following
construction[;]”
• “[t]he drilling of the borehole and installation of the product pipeline would not
permanently alter the groundwater flow or groundwater/surface water interactions near
the resource[;]” and
• “the physical pipeline would occupy only a negligible portion of the aquifer and have no
permeant influence on groundwater flow[.]”
These definitive statements are made without providing supporting evidence detailing how these
conclusions were developed. Due to the significant potential impacts that may be caused by
conventional bore crossings additional supporting evidence should be provided by FERC to
demonstrate how the proposed crossing methods will be safeguarded from causing potentially
significant impacts to water bodies and groundwater resources.
Page 18 notes, “in the event of landowner complaints that nearby wells or springs are impacted
by the dewatering activities, Mountain Valley would evaluate any complaints and identify a
suitable solution with the landowner[,]” and that “Mountain Valley would also need to continue
to fully comply with its Water Resource Identification and Testing Plan[.]” The 2017 Water
Resource Identification and Testing Plan specifies that private water supplies within 150 ft (or
500 ft in karst terrain) of the pipeline alignment will be offered water quality and quantity
testing. That discussion raises several questions:
• Were the additional structures identified within 150 of the alignment added to the water
testing program as per the requirements of the 2017 Water Resource Identification and
Testing Plan?
• Potential karst terrain is noted to be present at crossings G-017, G-024, G-023, H-017 and
H-020 (as noted in the March 29, 2021 MVP Response, Resource Report 6 – Geological
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Page 4
Resources). Have potable water supply locations within 500 ft of these crossings been
added to the monitoring program as per the 2017 Water Resource Identification and
Testing Plan?
• What do the results of the data collected so far as per the Water Resource Identification
and Testing Plan show regarding changes in baseline conditions after drilling has
occurred?
• How confident is FERC that all potable water wells have been identified?
The issue of conclusively identifying all potable resources within 150 ft to 500 ft from the
alignment and protecting potable water resources from potential adverse impacts must be more
clearly discussed in FERC and MVP documents.
The January 2021 Environmental Assessment and other documents indicate MVP is the entity
that will decide if significant impacts to water resources have occurred, and MVP will then
decide on how to address impacts. This approach appears to set up a conflict of interest and does
not seem to be protective of the public who count on water supply for daily needs.
General Comment – Groundwater Resource Impacts. Previous documents note that pumping
from bore pits can accommodate up to 396 gallons per minute and MVP will run pumps
sufficient to control infiltration rates up to 2,750 gallons per minute. These values provide an
understanding of the potential groundwater volume which may be pumped from bore pits
depending on soil types and groundwater conditions. The large volumes of water which may be
pumped (hundreds to thousands of gallons per minute) have a significant likelihood of affecting
nearby streams and drinking water sources. As noted in previous comments, it is clear there are
more residences within 150 ft than have been identified. MVP has cited a study concluding that
the radius of measurable effects of groundwater pumping is at least 300 ft based on similar
projects. The radius of influence from bore pits may be larger than 300 ft depending on geologic
conditions, soil types, bedrock geology, well depth, and other variables. For these reasons a
comprehensive assessment of groundwater drinking water wells within at least 300 ft should be
developed for each crossing location. Location specific data on wells, well depths, flow rates
and water elevation should be collected and provided to document baseline conditions and how
future conditions will be monitored to ensure there is no lasting environmental impacts due to the
proposed borehole drilling. Significant changes to water table elevations due to pumping, even if
temporary, can result in significant long term degradation of water quality at nearby drinking
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Page 5
water wells.
The proposed crossing method at two major water bodies (Elk River C-002 and Greenbrier River
F-021) are proposed using the guided conventional bore and direct pipe methods, respectively. If
drilling fluids or bentonite/water mixtures will be used during these crossings, significant risks
will be present to these sensitive water bodies. If pressurized drilling fluids are injected into the
subsurface during completion of these bores, the fluids can move in unexpected directions
including upwards and discharge into surface water or downwards into aquifers used for drinking
water. If a bentonite or a bentonite/water mixture is used during the pilot hole drilling, similar
risks of a release are present. A release of drilling fluids into surface waters or groundwater
could have significant environmental effects due to the high pH of fluids, elevated turbidity and
chemicals in the drilling fluid. Any release has the potential to cause acute or chronic human
health or ecological impacts. For example, there is evidence that the short-term effects of
releasing drilling fluid into wetlands include temporary displacement of resident fauna,
smothering of benthic organisms and plant root systems, increased turbidity of water quality, and
changes to water chemistry and wetland hydrology. Releases of drilling fluids are frequent
occurrences during drilling operations. At these locations, should drilling fluids or bentonite
reach surface water bodies or groundwater resources, significant short term and long term
impacts could result. Additional discussion should be provided to address how these type of
releases will be prevented.
The crossing length at the Greenbrier River is shown to be 1,250 ft long, which is one of the
longest crossings being proposed. Longer crossing have greater potential for adverse results
such as encountering unfavorable geologic conditions, borehole failure or mechanical issues that
may prevent borehole completion. Additionally, 24-hour operation of the drilling work may be
required, which will make identification of problems more difficult especially during overnight
work hours. FERC must require additional site-specific exploration to determine geological
conditions at this site, as well as special monitoring during construction of this crossing to ensure
surface water resources are protected from adverse impacts, and explain how that monitoring
will accomplish its goals.
Resource Report 1 – General Project Description No. 4. For the proposed guided bore
crossings, the MVP response does not indicate the volume or amounts of bentonite or slurry that
will be used, whether the slurry will be pressurized, or what pressures will be used. This
information is an important consideration for the potential for inadvertent releases of drilling
fluids. Addition of bentonite can increase turbidity and alter pH. Release of water containing
bentonite into surface water can result in significant impacts.
Resource Report 1 – General Project Description No. 5. For the proposed crossing of the Elk
River using guided conventional bore and the Greenbrier River using direct pipe, this response
indicates water used for the bore will be obtained from each water source from the same basin.
However, the response does not indicate how turbidity and/or pH will be controlled when the
water is returned to the water source. The addition of bentonite (noted in comment above) to
drilling water would result in increased turbidity and alter the pH. The likelihood of significant
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Page 6
impacts to surface water or groundwater are increased at these crossings because of the long
crossing lengths and the potential for large volumes of bentonite impacted water being used and
stored.
Resource Report 6 – Geological Resources, No. 21. This comment and response indicate five
crossings are underlain by carbonate bedrock and potential karst features. As noted in comments
above, the 2017 Water Resource Identification and Testing Plan specifies that private water
supplies within 500 ft in karst terrain of the pipeline alignment will be offered water quality and
quantity testing. Have potable water supply locations within 500 ft of these crossings been
identified and added to the monitoring program as per the 2017 Water Resource Identification
and Testing Plan? This information should be provided to clearly document which potential
potable wells are present and ensure adequate monitoring is occurring.
The presence of karst features can increase potential risks for borehole crossings due to the
presence of large voids which may dramatically increase or slow drilling rates, or act as sinks for
drilling fluids or recirculation water. Encountering voids can also reduce the accuracy of guided
bore crossings. The existing information does not adequately map karst features which can
cause these undesirable drilling effects. Therefore the potential risk of how karst may affect
drilling and bore failures should be fully examined.
Resource Report 6 – Geological Resources, No. 22. This comment and response indicate
discharge of construction related water within karst areas will be prevented from discharging
directly into a karst feature and no karst features been identified in the vicinity of the work areas.
It is important to note that the lack of surface expression does not mean the area in question is
not karst. Karst features may be present in these areas although the surface expression can be
obscured by overlying soil, partial collapse of the features, or vegetation. Rather an just relying
on visual observations for karst, the discharge receiving rates should be monitored to assess
whether unseen karst features may be accepting flow at a very high rate. If unexpectedly large
receiving rates are observed the presence of unseen karst features can be inferred and the
discharge locations should be changed. Further study of karst features using a systematic
approach is warranted due to the potential presence of karst at these locations. This should
include drainage basin testing using dye, use of LIDAR or other remote sensing technologies to
assess these areas, and monitoring well installation and hydraulic testing to investigate whether
karst features are present that may be impacted. Protection of karst groundwater is very
important to prevent groundwater impacts to potential drinking water resources.
GENERAL COMMENTS
Consideration should be given to the regional effects which may result from using so many
trenchless crossings along the length of the pipeline alignment. Several distinct aquifer units will
be crossed resulting in regional impacts such as establishing unexpected conduits between
groundwater resources, mixing of surface water and groundwater, or impacts to regional
groundwater flow conditions. The documentation provided by MVP and FERC focuses on each
site being considered for a crossing without review of potential regional impacts or cumulative
effects. Establishing multiple new conduits in the same watershed increases the risk of
significant impacts. Impacts of unintended water withdrawals due to conduit formation include
flow reduction in streams and aquifers, changes in water quality such as temperature, dissolved
oxygen, flow reduction in streams especially during summer and fall when flows are generally
low, and changes to regional aquifer conditions. These impacts can be compounded due to the
large number of crossings that are proposed. It is clear that numerous adverse consequences are
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Page 7
likely when using boreholes to cross below or within waterbodies. Direct harm to sensitive
receptors and important water resources should be considered as possible or likely occurrences.
The potential for wider impacts should be considered and assessed to prevent impacts before
they occur.
Many of the borehole crossings included in this application are within the Giles County Seismic
Zone. As a result, FERC and MVP must consider the potential impact of seismicity on the
proposed plans for drilling and on completed bores. This zone has experienced earthquakes up to
a magnitude 5.9 which is classified as a moderate earthquake. Smaller earthquakes occur more
frequently which can also cause immediate damages or long-term damage of fixed infrastructure.
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Exhibit D
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
In the Matter of
Preserve Bent Mountain, Preserve Craig, Inc., Preserve Franklin, Preserve Giles,
Virginia Highlands Conservancy, West Virginia Rivers Coalition, and Wild Virginia
1Accession No. 20210316-3075. See also Mountain Valley Pipeline. LLC, Abbreviated
Application for Limited Amendment to Certificate of Public Convenience and Necessity and
Request for Expedited Action (Accession No. 20210219-5176) (“Amendment Application”).
1
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
proposed amendment to the certificate of public convenience and necessity for the
change the method of waterbody crossing for 182 waterbodies at 120 locations along
the route of the MVP from a dry open-cut method to one of several trenchless
methods.3 The actions for which Mountain Valley has requested authorization pose
serious environmental risks that were not disclosed in the 2017 Final
convenience and necessity for the MVP relies, nor in the Commission’s more recent
in FERC Docket No. CP21-12. And neither Mountain Valley’s new Amendment
the Commission to fully and rationally assess the impacts of its proposed activities.
Accordingly, FERC cannot grant Mountain Valley’s application until it has collected
3 Mountain Valley seeks the amendment because its authorization to cross these streams
and wetlands pursuant to Clean Water Act section 404, 33 U.S.C. § 1344, has been stayed
by the U.S. Court of Appeals for the Fourth Circuit. See Sierra Club v. Army Corps of
Eng’rs, __ F.3d __, 2020 WL 7039300, at *7 (4th Cir. Dec. 1, 2020) (staying Army Corps of
Engineers’ stream and wetland crossing authorizations pursuant to Nationwide Permit 12);
Amendment Application at 2 (noting that it is seeking coverage under an individual section
404 permit for the MVP’s remaining waterbody crossings). Thus, under the status quo that
would be altered by a grant of Mountain Valley’s amendment application, Mountain Valley
is not allowed to impact any of the waterbodies along the pipeline route.
2
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Valley’s proposal and put that evaluation out for public review and comment in a
4 See Dubois v. U.S. Dep’t of Agric., 102 F.3d 1273, 1291 (1st Cir. 1996) cert. denied, 521
U.S. 1119 (1997) (“The question of a supplemental EIS is premised on the dual purposes of
the EIS: to assure that the public who might be affected by the proposed project be fully
informed of the proposal, its impacts and all major points of view; and to give the agency
the benefit of informed comments and suggestions as it takes a ‘hard look’ at the
consequences of proposed actions.”).
FERC’s timing of any actions on Mountain Valley’s application for a certificate amendment
is further constrained by Condition 9 of Mountain Valley’s existing certificate and the need
for additional action by the U.S. Fish and Wildlife Service and the U.S. Army Corps of
Engineers. Condition 9 of Mountain Valley’s Certificate of Public Convenience and
Necessity prohibits construction on the project in the absence of all required federal
approvals. Order Issuing Certificates and Granting Abandonment Authority, 161 F.E.R.C.
¶ 61043, App. C, Cond. 9, 2017 WL 4925425, at *76 (Oct. 13, 2017). Mountain Valley’s
proposed changes to its stream crossing methods requires authorization under the
Endangered Species Act from the Fish and Wildlife Service and under Section 10 of the
Rivers and Harbors Act and Section 404 of the Clean Water Action from the Army Corps of
Engineers See generally Mountain Valley Pipeline Project Amendment Environmental
Assessment, FERC Docket No. CP21-12 (Jan. 2021) (Accession No. 20210107-3064) at 43
(explaining that FERC must consult with USFWS regarding the impacts of the previously-
proposed boring activities); Amendment Application at 1-9 Table 1.10-1 (noting that
additional consultation may be required for the amendment); Mountain Valley Pipeline
Project, Individual Permit Application at 62 (Feb. 2021) (Accession No. 20210304-5122)).
Consistent with Environmental Condition 9, the earliest FERC should take action on
Mountain Valley’s pending application is when the Fish and Wildlife Service and the Corps
have both completed their decisionmaking processes.
3
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
The Commission cannot authorize Mountain Valley to bore under more than
statement for the project. The activities for which Mountain Valley seeks
authorization pose significant risks to the environment that have not been analyzed
in the Commission’s or any other agency’s previous NEPA documents for the MVP.
to occur, and . . . the new information is sufficient to show that the remaining action
5Mountain Valley proposes to use the conventional bore technique at most waterbody
crossings but also proposes the use of the guided conventional bore and Direct Pipe methods
at certain locations. Amendment Application at 1 n.3.
6Marsh v. Oregon Nat. Res. Council, 490 U.S. 360, 374 (1989) (internal citations omitted);
see also Webster v. U.S. Dep’t of Agric., 685 F.3d 411, 418 (4th Cir. 2012) (“A supplemental
EIS [is] mandatory if the agency ‘makes substantial changes in the proposed action that are
relevant to environmental concerns’ or if ‘significant new circumstances or information
relevant to environmental concerns and bearing on the proposed action or its impacts’
arise.”) (citing 40 C.F.R. § 1502.9(c)) (emphasis added); Envtl. Def. Fund v. Tennessee Val.
Auth., 468 F.2d 1164, 1177 (6th Cir. 1972) (“We believe it more consonant with
congressional intent to hold that an agency must file an impact statement whenever the
agency intends to take steps that will result in a significant environmental impact …
whether or not the proposed steps represent simply the last phase of an integrated
operation most of which was completed before that date.”); Klamath Siskiyou Wildlands
Ctr. v. Boody, 468 F.3d 549, 560 (9th Cir. 2006) (citations omitted) (“[I]f the proposed action
might significantly affect the quality of the environment, a supplemental EIS is required.”).
4
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
that agencies:
The use of the word “shall” is mandatory and creates a duty on the part of the
FEIS.”9 Changes require NEPA supplementation not only when they increase the
740 C.F.R. § 1502.9(c) (2019). As explained in Section C, infra, FERC and the Corps should
apply the pre-2020 version of the CEQ NEPA regulations. There is no substantive
difference, however, between the pre-2020 supplemental EIS regulations and the 2020
regulation. Compare id. with 40 C.F.R. § 1502(9)(d) (2020).
8 See Marsh, 490 U.S. at 372 (“The CEQ regulations, which we have held are entitled to
substantial deference, impose a duty on all federal agencies to prepare supplements to
either draft or final EIS's if there “are significant new circumstances or information
relevant to environmental concerns and bearing on the proposed action or its impacts.”)
(quoting 40 C.F.R. § 1502.9(d)) (citations omitted); Price Rd. Neighborhood Ass’n, Inc. v.
U.S. Dep’t of Transp., 113 F.3d 1505, 1509 (9th Cir. 1997) (citation omitted) (explaining
that NEPA “imposes a continuing duty to supplement previous environmental documents”).
9 In re Operation of Missouri River Sys. Litig., 516 F.3d 688, 693 (8th Cir. 2008) (citing
Dubois, 102 F.3d at 1292, quoting Forty Most Asked Questions Concerning CEQ's National
Environmental Policy Act Regulations, 46 Fed. Reg. 18026, # 29b (March 23, 1981)
(emphasis in original).
5
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
magnitude or extent of impacts, but also when they will cause the project to impact
the environment “in a significant manner” not previously considered.10 That is,
certain previously analyzed impacts if the change presents different risks that may
were not analyzed in the EIS for the MVP. As discussed below, these crossing
methods present the risk of significant environmental impacts that are distinct
from those of the open-cut crossing methods that were previously evaluated.
since FERC’s 2017 EIS, in many instances as a result of the failures of Mountain
10Marsh, 490 U.S. at 374 (emphasis added); see also Davis v. Latschar, 202 F.3d 359, 369
(D.C. Cir. 2000) (supplementation required where the effects of proposed changes are
“significantly different from those already studied”) (quoting Corridor H Alternatives, Inc. v.
Slater, 982 F.Supp. 24, 30 (D.D.C.1997)); Westlands Water Dist. v. U.S. Dep't of Interior,
376 F.3d 853, 873 (9th Cir. 2004) (explaining that supplementation is required when a
proposed change “will have a significant impact on the environment in a manner not
previously evaluated or considered.”); Miccosukee Tribe of Indians of Fla. v. United States,
420 F. Supp. 2d 1324, 1333–35 (S.D. Fla. 2006) (finding that changes to a project were
significant enough to require a supplemental EIS, which was required to include
“hydrologic modeling results”).
11 Hodges v. Abraham, 253 F. Supp. 2d 846, 853 (D.S.C. 2002) (emphasis added).
12See Dubois, 102 F.3d 1292–93 (“It would be one thing if the Forest Service had adopted a
new alternative that was actually within the range of previously considered alternatives,
e.g., simply reducing the scale of every relevant particular. It is quite another thing to adopt
a proposal that is configured differently, in which case public commenters might have
pointed out, if given the opportunity—and the Forest Service might have seriously
considered—wholly new problems posed by the new configuration (even if some of the
environmental problems present in the prior alternatives have been eliminated).”).
6
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Valley to control erosion, sedimentation, and landslides along the MVP route. A
here because this NEPA document will inform not only FERC’s consideration of
Mountain Valley’s amendment request, but also the cooperating agency U.S. Army
A. FERC and the U.S. Army Corps of Engineers Should Not Rely on CEQ’s 2020
NEPA Regulations
It is unclear the extent to which FERC intends to rely on the new NEPA
for additional environmental review of the MVP. On July 15, 2020, CEQ finalized a
revision to its regulations implementing NEPA; that revision became effective two
months later on September 14, 2020.14 The effective date for CEQ’s new NEPA
regulations was September 14, 2020. Notwithstanding this change, we urge FERC
to apply the prior NEPA regulations to the MVP, rather than these new rules, for
1333 U.S.C. § 1344. See Acceptance of Cooperating Agency Responsibility (Accession No.
20210310-5059) at 1-2 (explaining that the information in the NEPA document must be
“adequate to fulfill the Corps’ statutory requirements, including the requirements of
Section 404(b)(1) of the Clean Water Act (40 CFR 230) and the Corps’ public interest review
(33 CFR § 320.4)”); see also 40 C.F.R. § 230.10(a)(4) (requiring supplementation of NEPA
documents that do not consider alternatives in sufficient detail to address the “least
environmentally damaging practicable alternatives” requirements of the Section 404(b)(1)
guidelines).
7
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
First, the fundamental obligations governing NEPA reviews arise from the
statute itself, as interpreted by courts for fifty years. FERC must meet these
statutory requirements “to the fullest extent possible.”15 Rather than attempt to
find daylight between its statutory obligations and CEQ’s new NEPA regulations,
FERC should continue to apply the long-standing NEPA standards in place when
Mountain Valley initiated the MVP in 2015 and when FERC issued its original EIS
for the project in 2017. This choice matters: CEQ’s new regulations eschew the
foundational part of the review process since Congress enacted NEPA in 1970.17
Cumulative impacts are an especially important consideration for projects like the
MVP, which spans portions of two states and would cross hundreds of rivers,
Second, the new regulations expressly authorize agencies to use the prior
15 42 U.S.C. § 4332.
1640 C.F.R. § 1508.1(g)(3) (2021) (“Cumulative impact, defined in 40 C.F.R. 1508.7 (1978), is
repealed.”).
17See, e.g., Hanly v. Kleindienst, 471 F.2d 823, 830-31 (2d Cir. 1972) (interpreting the
statutory term “significantly” to include the absolute quantitative adverse environmental
effects of the action itself, including the cumulative harm that results from its contribution
to existing adverse conditions or uses in the affected area”).
18As hydrogeologist Pete Nimmer observes, cumulative effects of the proposed borings
could be significant. See Nimmer Update at 6–7, infra n. 35 (concluding that impacts on
surface and ground water quality and quantity “can be compounded due to the large
number of crossings that are proposed”).
1940 C.F.R. § 1506.13; see e.g., Notice of Intent To Prepare a Draft Integrated Feasibility
Report and Environmental Impact Statement, 86 Fed. Reg. 15470 (Mar. 23, 2021) (“[The
8
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
FERC is bound by the new NEPA rules (and thus the company waves off any need
to provide information about the cumulative impacts of its proposal).20 But the new
regulations give FERC a choice that is not Mountain Valley’s to make. Mountain
Valley initiated this pipeline project in 2015, and the proposed certificate
amendment now at issue is a continuation of the existing project and its original
NEPA review from 2017. Indeed, FERC and cooperating agencies like the Corps
may intend to rely on portions of the 2017 EIS to fulfill their present NEPA
obligations for the proposed certificate amendment. The only consistent and orderly
approach is for FERC to continue to apply CEQ’s prior NEPA regulations to the
MVP project.
Third, reliance on the new NEPA regulations will place the MVP in
additional legal jeopardy. The new regulations are the subject of multiple ongoing
substantial concerns about the effects of the 2020 Rule on public health,
the nation’s land, water, and air quality, communities that have been
Corps of Engineers] is exercising its discretion to employ the 1978 CEQ NEPA
Implementing Regulations to this ongoing process . . . .”).
20Mountain Valley Pipeline, LLC, Suppl. Envtl. Rep. for Proposed Certificate Amend. for
Avoidance of Waters of the U.S., Dkt. No. CP21-57, at 2-11 (Feb. 19, 2021), available at
Accession No. 2021-0219-5176 (citing 18 C.F.R. § 380.1).
9
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
A FERC environmental review for this project based on the 2020 NEPA regulations
may be defective or delayed if those regulations are later struck down or repealed.
For these reasons, FERC should apply CEQ’s prior NEPA regulations and the
caselaw interpreting those regulations when preparing the Supplemental EIS for
B. The EIS for The Project Does Not Evaluate the Potential Impacts of the
Conventional Bore, Guided Conventional Bore, or Direct Pipe Methods
In the EIS for the MVP, FERC determined that Mountain Valley would
employ only two waterbody crossing methods: the dry open-cut method and the
horizontal directional drill (HDD) method.23 These were the only methods evaluated
briefly mentions boring, but only in the context of road, railroad, and trail crossings
and Direct Pipe methods to cross more than 180 waterbodies along the route of the
23 EIS at 2-43.
10
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
MVP have therefore not been evaluated or disclosed as part of the NEPA process for
the project.
The proposed conventional bore, guided conventional bore, and Direct Pipe
methods would lead to adverse impacts on the environment that are distinct from
the risks posed by the dry open-cut waterbody crossing method previously proposed
boring methods are known, Mountain Valley has not provided sufficient information
to determine the likelihood and extent of such adverse impacts occurring for its
proposed bores.
The vast majority of the proposed borings would be completed using the
workspace in uplands on each side of” the waterbody and then subsurface drilling to
connect the two pits, in which “the construction crew advances a jacking pipe and a
11
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
rotating cutting head that is attached to the leading edge of the auger string.”27 In a
completed,” thus requiring 24-hour operation.28 Any spoil generated by the boring
that cannot be returned to the bore pits must be stored during the boring operation
FERC itself has recognized the risks of conventional bores. In the Final
acknowledged that,
Conventional bores require large entry and exit pit excavations at each
end of the bore pathway and therefore create the risk of sediment runoff
entering the adjacent waterbody. Of greatest risk to the waterbody is
the possibility of the borehole collapsing without warning. In such a case
the bed of the waterbody could collapse and reroute the waterbody into
the bore pathway.30
Likewise, the Court of Appeals for the Fourth Circuit recently explained that in
order to bore under a stream, “MVP must excavate a pit nearby, which again may
increase erosion and sedimentation. And there is risk that drilling fluid will escape
into the surface waters, or that the drilled hole might collapse, causing the
27 Id.
28 Id. at 1-6.
29 Id. at 1-4.
FERC, Southgate Project Final Environmental Impact Statement at 4-37, Docket No.
30
31Mountain Valley Pipeline, LLC v. North Carolina Dept. of Envtl. Quality, 990 F.3d 818,
822 (4th Cir. 2021)
12
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
conventional bore under the Greenbrier River, that the method presents “difficulties
Photographs of bore pits that MVP has already excavated along the route
demonstrate the groundwater intrusion and large spoil piles from boring:
13
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Mountain Valley’s compliance reports for the MVP demonstrate that the
No. CP21-12 by Pete Nimmer, PG, LSRP, Senior Geologist with Greenstar
33See, e.g., Environmental Compliance Monitoring Program - Weekly Summary Report for
August 25-31, 2019 at 3, Dkt. Nos. CP16-10 et al. (September 18, 2019) (eLibrary No.
20190918-4001) (describing winch breaking during boring and oil sheen inside the entry
bore pit due to leaking hydraulic line (MP 140.2)); Environmental Compliance Monitoring
Program, Weekly Summary Report for August 18-24, 2019 at 5, Dkt. Nos. CP16-10 et al.
(September 9, 2019) (eLibrary No. 20190909-4004) (“Topsoil was salvaged from the [bore]
pit area and segregated at the side of the extra work area. The topsoil was stacked too high
against a row of belted silt retention fence and broke through.” (MP 11.3)).
34Mr. Nimmer carries nearly 30 years of experience in the industry, including “extensive
experience designing, managing, and executing investigation of groundwater issues” and
“extensive experience designing, managing, and executing aquifer studies in bedrock and
karst, well yield assessments and hydrogeology investigations.” Pete Nimmer, Greenstar
Environmental Solutions, LLC, Comments on Mountain Valley Pipeline’s Requested
Amendment to its Certificate of Public Convenience and Necessity at 10 (2020) (“Nimmer
14
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
application and submittal of the application and related materials in Docket No.
CP21-57, Mr. Nimmer produced an update confirming the application of his earlier
findings to the instant proposal.35 Mr. Nimmer concluded that “MVP’s assertion in
its application that its proposed actions ‘would have limited, if any, environmental
impacts beyond those that have already been assessed and approved by the
unsupported claim, Nimmer found that “significant adverse consequences are likely
One of the primary risks Nimmer identifies is the potential for the creation of
Report”). That report is attached as Exhibit 2 to these comments and is hereby incorporated
by reference as if set forth fully herein.
37 Nimmer Update at 2.
38 Nimmer Report at 2.
15
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
groundwater flow compared to current conditions” and can lead to the dewatering of
Those impacts can also “lead to unsafe drinking water conditions or impacts to
private wells and/or public water supply sources in the surrounding area.”42
Such impacts can occur even when the boring is successfully completed, but
are particularly likely in the event of a failed borehole, which “has the potential to
result in formation of a very large conduit that could result in the diversion of
39 Nimmer Report at 2.
40Id. at 3; see also id. at 5 (“[T]he boreholes and tunneling excavation activities can
potentially interfere with groundwater aquifers, whether unconsolidated or bedrock
aquifers and have the potential to alter the groundwater flow pattern and aquifer
capacity.”).
41Id. at 2–3. See also id.at 3 (“Borehole-created conduits can cause dewatering of wetland
areas, significant changes in the size and quality of wetlands, or permanent drying of
wetlands and subsequent loss of habitat in these areas.”).
42 Id. at 5.
43Id. at 7; see also id. at 3 n.1 (“If a borehole cannot be completed the failed borehole has
the potential to become a major underground hydraulic conduit which may result in
dewatering of surface water bodies.”); id. at 6–7 (“The large diameter of the proposed
boreholes has the potential to result in formation of a very large conduit that could result in
the diversion of significant quantities of surface water or groundwater.”); FERC Southgate
Project FEIS at 4-37 (“Of greatest risk to the waterbody is the possibility of the borehole
16
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
borehole collapse due to their length. A report prepared by the Williams Company
for the Northeast Supply Enhancement project notes that conventional bores are
typically between 50 and 100 feet long and that a “[m]ajor factor limiting the
locations that exceed 100 feet in length, thus increasing the serious risk of bore
failure.45 Likewise, Nimmer advises that “[o]ne or more failed boreholes should be
considered a likely possibility given the size of the individual crossings …, the
collapsing without warning. In such a case the bed of the waterbody could collapse and
reroute the waterbody into the bore pathway.”).
Mountain Valley attempts to downplay the likelihood of borehole collapse by insisting that,
in most instances, “the line pipe is installed immediately behind the bore pipe once the
boring is complete, leaving no unsupported hole that could potentially collapse. Because the
borehole is continuous supported by pipe throughout the process, the risk of bore collapse is
minimal.” Amendment Application at 1-4. This does not address the situation where a
borehole has to be abandoned because of adverse geologic conditions, and the drilling rig
withdrawn from the borehole, in which case nothing would remain to support the borehole.
Nothing in FERC’s staff’s January 2021 Environmental Assessment addressed the impacts
of such a scenario, and nothing in the information submitted in support of the pending
application does either. Accordingly, the risks of borehole collapse and conduit creation are
not as minimal as Mountain Valley represents.
17
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
dewater surface streams, conventional boring also impacts water quality and
quantity due to the substantial pumping of groundwater necessary to keep the deep
bore pits dry enough to operate equipment. Mountain Valley notes that, due to the
2,750 gallons of water per minute, 24 hours per day from some of the bore pits.47
of the bore pits,” and cites a study demonstrating reduced groundwater depths 300
feet from the boring operation.48 But the company goes on to say that the magnitude
such as “the existing groundwater level” and “soil type,” that Mountain Valley
entirely fails to examine.49 Moreover, Mountain Valley may not rely on the cited
46 Nimmer Report at 6.
47Amendment Application, Resource Report 2 at 2-11 to 2-12. This “dewatering” of the bore
pits, involving pumping of groundwater that infiltrates the pits to the surface to maintain
dry workspace, is distinct from the dewatering of surface streams discussed in these
comments, whereby changes to groundwater flow paths or drawdown of groundwater
through pumping partially or entirely diminish the water flowing in surface streams and
wetlands.
48 Id. at 2-11.
49Id. see also id. (“Where groundwater is near the surface at the time of construction and
larger or multiple pumps are required to operate continuously, water-level draw down near
the bore pits could be measurable.”).
18
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
impacts are not similar to nor can be used to properly define the potential impacts
significant likelihood to affect nearby streams and drinking water sources.”51 Those
impacts could be felt at distances greater than the 300 feet analyzed by the study
geology, well depth, and other variables.”52 The groundwater drawdown associated
with the pit dewatering and other aspects of Mountain Valley’s proposed operations
51 Nimmer Report at 9.
52 Id. at 3.
53 Id. at 5.
19
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
wells.”54 Though Mountain Valley claims that there are no known public or private
groundwater wells within 150 feet of its bore pits,55 Nimmer notes the existence of
Those pumping activities are also likely to have adverse impacts on surface
water quality.57 Indeed, Mountain Valley has already been cited by the West
54 Id. at 9.
changes to surface water bodies, although the applicant does not discuss what effects may
result or how effects will be mitigated, or where water will be pumped and how turbidity of
the discharge will be managed to prevent fouling of surface water resources.”).
58See WVDEP, Notice of Violation No. W19-21-074-TJC (August 14, 2019) at 2, attached as
Exhibit 5 (“The offsite sediment laden water adjacent to 2919+50 occurred due to a
dewatering operation at the time of inspection.”); id. at 13 (showing “[o]ffsite sediment
deposits . . . where a dewatering structure was placed offsite and caused offsite deposits”);
id. at 13–14, 19–20 (showing dewatering structures failing to function as designed and
resultant offsite sediment deposits); WVDEP, Notice of Violation No. W19-17-030-JTL
(September 11, 2019) at 3, attached as Exhibit 6 (“At station No. 645+35 the dewatering
structure used for the Stream S-B75 bore was not being maintained and operated properly
causing the structure to not function as designed causing conditions not allowable in
Stream S-B75 (Goose Run)); id. (“Sediment Laden water was observed leaving a dewatering
structure used for the boring under Stream S-B75 (Goose Run).”); id. (Mountain Valley’s
boring operation “has caused conditions not allowable in waters of the State by allowing
distinctly visible settleable solids in Stream S-B75 (Goose Run).”); id. at 2 (“The dewatering
20
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
apply close scrutiny to Mountain Valley’s claims that its dewatering activities will
not have significant impacts on surface waters and collect sufficient information to
Mountain Valley proposes to use the Direct Pipe method to cross the
Greenbrier River, the longest of the proposed trenchless crossings, and to use the
guided conventional bore method at two other locations.59 In addition to the risks
identified above, the Direct Pipe and guided conventional bore methods also pose
risks due to the use of bentonite or other drilling fluids which may escape and
two proposed trenchless crossing methods that require the use of fluids—guided
conventional bore and Direct Pipe—also include a risk of inadvertent return (IR).”
structure had stagnant water inside the structure with an odor present. . . . [A]n
algae/bacterial mat was growing/forming on the ground where the discharge was
occurring.”).
59Amendment Application, Resource Report 1, Appendix 1, Table A-1; id., Resource Report
3 at 3-9.
60Mountain Valley notes that it will also likely use “small quantities of water, bentonite, or
polymer-based lubricant” to complete the longer conventional bores as well. Those crossings
thus present similar contamination risks as the Direct Pipe crossing of the Greenbrier
River. See Amendment Application, Resource Report 2 at 2-13.
21
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
fluids “add significant risk to water bodies” that was not considered in the EIS for
the project:61
volume or amounts of bentonite or slurry that will be used, whether the slurry will
be pressurized, or what pressures will be used.”63 FERC must obtain and evaluate
this information in order to reasonably predict the impacts of the crossings that will
61 Nimmer Report at 4.
63 Nimmer Update at 5.
22
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
and introduce significant additional sediment into surface waters. Those impacts
will have significant adverse consequences for the biological communities that rely
Mountain Valley’s proposal, along with the Nimmer Report, and determined that
water quality impacts described in the Nimmer Report would “reduce the extent
and the quality of aquatic habitat” both spatially and temporally, “degrade fish
64See Nimmer Report at 3 (“The disruption of these areas, and increased turbidity caused
by the project, will adversely impact ecosystems within the surrounding surface water
bodies, flood plains and wetland areas, as well as the wildlife habitats in these areas.”); id.
(“Borehole-created conduits can cause dewatering of wetland areas, significant changes in
the size and quality of wetlands, or permanent drying of wetlands and subsequent loss of
habitat in these areas.”).
23
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
One cause of the ecological impacts would be stream and wetland dewatering
activities. “Short term dewatering would certainly be lethal for many aquatic
realistic for more motile taxa), where they are more vulnerable to predation.”67 The
proposed activities, however, are likely to create “long-term issue[s]” that would
lead to “prolonged dewatering,” which has potentially much more serious impacts
wetland plants that depend on periods of saturated soils or shallow water tables for
substrate utilized by invertebrates and fish,”69 and “more rapid warming of water
66 Id. at 4–5.
67 Id. at 4.
68 Id.
24
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
would “contribute to reduced oxygen levels for aerobic respiration while increasing
maintain the bore pits would also have significant adverse impacts. If the pumped
water is laden with sediment—as has been observed in Mountain Valley’s previous
larvae are sensitive to increases in turbidity and fine sediment, and fine deposition
can degrade fish spawning beds.”72 The presence of excess sedimentation, whether
from pit dewatering or other pipeline activities such as erosion from the cleared
beds for spawning, as the same conditions allow for protection of eggs and shelter of fry,
both of which are notoriously sensitive to sedimentation in Appalachian streams.” Id. at 4.
70 Id.
71Id. at 5. See also Nimmer Update at 5 (“[T]here is evidence that the short-term effects of
releasing drilling fluid into wetlands include temporary displacement of resident fauna,
smothering of benthic organisms and plant root systems, increased turbidity of water
quality, and changes to water chemistry and wetland hydrology.”)
72 Baker Report at 5.
73See id. at 5–6 (discussing the sedimentation risks created by Mountain Valley’s proposed
storage, handling, and disposal of excess spoil).
25
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
stream dewatering, leaving streams stressed and less able to recover from periods
of reduced flow.74
not been evaluated in the EIS for the MVP and are neither equivalent to nor
As Baker explains,
Likewise, “[a]s opposed to the short-term dewatering considered in the EIS for open
74 Id. at 4.
75 Id. at 2.
76Id. at 3; see also id. at 5 (“Because the EIS only considered temporary pumping of open-
cut trenches during low water periods when many sensitive taxa are not be resident in
small streams (i.e., because many aquatic invertebrates are in terrestrial stages or
dormant, and fish have migrated to downstream habitats), and because the length of time
spent drilling at each site could either be similar to trench or substantially longer due to
geologic strata, the potential impacts of the proposed discharges are unclear, but entirely
distinct in terms of timing, magnitude, and duration from what was evaluated by the
EIS.”); id. at 3 (“It thus appears that spoil relocation will be fairly commonplace, whereas
such transport of sediment was not described as part of the original workplan considered by
the EIS.”); id. at 6 (“In developing the EIS, federal agencies never considered the potential
26
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
In order to satisfy NEPA, FERC must fully evaluate these potential impacts
adverse impacts on the quality of the environment, much more is needed to fully
evaluate the character and intensity of such impacts. Mountain Valley’s application
materials omit information that is essential to answer such critical questions as the
likelihood of borehole failure, the susceptibility of the water table to disruption, the
magnitude of expected sedimentation, and the extent and quality of the existing
to allow FERC to determine the likely impacts of the proposed activities on aquatic
impacts of discharge from excavation operations during the wintertime when many more
aquatic species are resident, from deeper holes where groundwater seepage is likely to be
far greater than the shallower trenches, and when greater stream flows are likely to
transport fine material further downstream.”).
77 See Nimmer Report at 2 (“[A] review of the limited documentation MVP provided
establishes that significant adverse consequences are likely to occur from this change of
waterbody crossing method. Moreover, the information MVP has provided is incomplete
and inadequate to fully assess the environmental impacts that may occur.”); Nimmer
Update at 2 (“FERC should not authorize the proposed actions until it gathers sufficient
information regarding the boring operations and potable wells, as detailed below, such that
it can rationally assess, consider, and disclose to the public the likely impacts of MVP’s
proposal.”).
27
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
wildlife.78 Without gathering this information, FERC cannot fulfill its duty under
The most critical analyses that Mountain Valley has failed to provide are
well as the potential for disruption to subsurface hydrology.80 Nimmer notes that, in
78 See Baker Report at 2 (concluding that the “circumstances of the proposed crossings are
different from those considered under the earlier EIS” and that “[m]ore information is
needed to adequately assess potential consequences of the proposed amendment”); id.
(“Because of these differences [in impacts between conventional bore and dry open-cut
crossings] and the site-specific nature of many of the potential consequences, the full scope
of the impacts cannot be understood without further assessment.”).
80 See, e.g., Williams (2014) at 2 (“Subsurface soil and geologic conditions must be condusive
[sic] to establishing and maintaining a safe bore pit excavation, as well as provide the
capabilities for the boring equipment to conduct a successful bore. Loose packed sediment,
free of rock material is preferred when conducting boring operations.”).
81Nimmer Report at 4; see also id. at 6 (“Several [geologic] conditions would result in a
borehole that cannot be completed to its intended length such as unexpected geology,
problematic geology or soils, or equipment issues.”); Baker Report at 2–3 (explaining that,
because the depths of the bore pits are greater than the depth of the trench in the original
crossing plans, Mountain Valley is more likely to encounter bedrock and to “involve
interactions with groundwater aquifers”); id. at 4 (“The nature, extent, and magnitude of
the impacts being described would likely vary based on network position and the site-
specific hydrogeology.”); id. at 6 (“Importantly, the switch to borehole crossings has
emphasized the need to develop more detailed and site-specific understanding of valley
bottom geology and aquifer characteristics. Such information is necessary to assess the
28
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
adverse impacts of the proposed activities may not be immediately apparent and
But FERC and Mountain Valley may not simply resign themselves to the possibility
of borehole failures. Rather, they must gather sufficient information so that they
82See Baker Report at 4 (“[C]hronic dewatering in stream channels and floodplains from
hydraulic conduits accessed and/or created through borehole drilling might be
inconspicuous in the wintertime [at the time of construction] when evapotranspirative
demands are low and losses are masked by higher flows, but result in either reduced flow
regimes or truncated periods of surface flow altogether when evapotranspiration increases
in the spring and summer, with cascading environmental effects.”).
29
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
locations, FERC must assess “soil thickness,” “the depth of the soil/bedrock
analyses in its Feasibility Assessments for six of the longest of the proposed
trenchless crossings. There, Mountain went beyond the inadequate desktop analysis
that it relies on for the vast majority of the crossings and conducted “test borings”
as well as “Resistivity Imaging Stud[ies]” that “help identify the subsurface geology
along the guided conventional bore path.”87 This sort of analysis is necessary to
determine the likely impacts at all proposed trenchless crossings, not just a handful
bore path or encountering boulders greater than on third of the diameter of the installed
pipe that may prevent bore completion.”).
85 Nimmer Report at 4.
86Id.; see also id. at 5 (“No information is provided regarding depths of water bodies,
bathometry of surface water at crossings, cross-sections, an understanding of bank
conditions and how these compare to the proposed depth of each borehole.”).
87 See, e.g., Amendment Application, Appendix F at F-1. FERC has required this sort of
geotechnical analysis in the past, such as when it required Mountain Valley to perform a
geotechnical analysis of the feasibility of crossing the Pigg River by HDD. See EIS at 4-119
(discussing Mountain Valley performing “core drilling” and other analyses to determine if it
is “geologically feasible to cross under the Pigg River”).
30
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
evaluate the likelihood of borehole failure is its refusal to provide any detailed plans
for addressing such a failed boring operation. As noted above, “[o]ne or more failed
limited discussion of what actions will be taken if obstacles are encountered which
cannot be accommodated by the drilling method, or what will occur if boreholes are
that it will “shift the bore entry ten feet to either side of the original bore entry and
attempt another bore” in the event a bore cannot be completed,90 “[t]his limited
description is not a contingency plan for how a failed borehole will be properly
surface water which may cause dewatering of surface water bodies.”91 A meaningful
contingency plan must “assess how the decision will be made to terminate a bore,
how the bore will be properly abandoned so it does not create a hydraulic conduit or
prevent bore collapse or limit the potential for a release of pressurized drilling
fluids.”92
88 Nimmer Report at 6.
89 Id.
91 Nimmer Report at 6.
92Id. at 8. Grouting, which is part of Mountain Valley’s proposal, is not a panacea. See
Nimmer Update at 3.
31
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
at each boring location, FERC also lacks the information needed to determine the
the boring activities have the potential to impact aquifers used for domestic water
supplies, FERC must collect “[l]ocation specific data on wells, well depths, flow
rates and water elevation.”93 The one groundwater study provided by Mountain
Valley observed measurable effects from pit dewatering at a radius of 300 feet, but
FERC has stated that the study is not appropriate to predict impacts to
groundwater under the conditions present in the area of the proposed amendment.94
water sources within 150 feet of the proposed bore pits, and relied on incomplete
public databases to do so.95 It is therefore “very likely that other drinking water
wells are located near all or some of the crossings, and further investigation is
needed to quantify the actual number of residences and private wells that may be
93Id. at 9; see also id. at 5 (“There is limited information provided regarding current
groundwater use, documenting current conditions, or addressing how the proposed drilling
activities will protect drinking water aquifers.”).
95 Nimmer Report at 8; id. at 9 (“It is worth noting that private wells in rural areas are not
likely to be represented in publicly available databases that MVP used to search for
drinking water wells. . . . Instead of relying on databases and limited outreach, a
comprehensive survey should be completed to accurately identify how many residences and
wells are within 500 feet of drilling areas, or which may be affected by bore operations.”).
96 Nimmer Report at 5.
32
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
determine “the radius of potential impacts” nor whether “the borehole depths are
properly located away from aquifers that are currently used for drinking water, or
how it will detect and respond to adverse impacts from its proposed boring
order to detect and mitigate such impacts, FERC must require documentation of
baseline water quality and quantity conditions at each boring site, followed by
will be observed early before significant damage to resources can occur.”99 Without
such assessment and monitoring, the impacts of the proposed waterbody crossings
97Id.; see also id. (“Information must be provided by the applicant and addressed by FERC
to assess the potential hydrological and drinking water impact of the proposed Certificate
amendment and to ensure that appropriate measures are implemented to minimize effects
on people nearby.”).
98 Id. at 7.
99 Id.
100 Id.
33
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
D. FERC May Not Authorize the Use of Alternative Crossing Methods Without
Fully Evaluating and Disclosing the Impacts of Those Methods at Specific
Locations as Part of the NEPA Process
streams using three methods: conventional bore, guided conventional bore, and
employ trenchless crossing methods that are not identified in its application, i.e.,
methods other than conventional bore, guided conventional bore, and Direct Pipe.
FERC may not approve the use of any crossing methods for which it has not
analyzed and disclosed the impacts through the NEPA process. Mountain Valley
has not provided information necessary to determine the impacts of any additional
crossing techniques. Accordingly, FERC may not authorize the use of any other
34
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
the method of trenchless crossing (even to a method that has been analyzed in a
techniques are likely to have different impacts when applied at different locations.
demonstrate, certain locations present risks that are not present at all crossing
causing more significant environmental impacts, such that knowing the extent to
which those techniques will be used is essential to predicting the intensity of the
cut method if its proposed boring methods proves unworkable is not sensible.
Although Mountain Valley claims that the 2017 final EIS “already evaluated the
impacts of open-cut crossings for the same aquatic features proposed herein to be
changed to trenchless crossings,”105 that is not the only legal hurdle it must clear to
103See, e.g., Id., Appendix F at F-1 (noting that at the Elk River crossing, geotechnical data
reveals that groundwater is expected to be encountered in the bore pits); F-3 (noting that
the C-035 crossing contains materials that will likely require rock drilling techniques as
well as additional “clearing and grading on both the launch and receiving pits side”). See
also id., Appendix I Table 1 (showing that at least six of the crossings are in areas of
sensitive karst geology).
104Id. Appendix, F at F-5 (noting that the Direct Pipe method proposed for the Greenbrier
River crossing involves the use of bentonite, which presents contamination risks in the
event of an inadvertent return that are not present with the conventional bore method in
most instances).
105 Id. at 8.
35
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
to obtain an additional individual permit from the Army Corps for that crossing
But Mountain Valley is not seeking authorization from the Corps for the
the crossing method to an open cut would require review and approval by the
Corps.”106 Because that review and approval would require an individual permit
with its own attendant NEPA process and public notice and comment procedures
the Corps), there is no reason for FERC to grant Mountain Valley that authority
now without having all the relevant facts before it. Rather, in the event that
request an additional certificate amendment from FERC at the same time it seeks
Section 404 authority from the Corps. That modification can then be analyzed in a
single NEPA document, with the benefit of FERC not having to speculate about the
the crossings using the specific methods identified in its application, it must
identify the alternative crossing methods for which it seeks authorization and
36
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
provide adequate information for FERC to evaluate the impacts of using those
methods at those specific locations, taking into account the current environmental
FERC expressed its view that the conventional bore crossing method has
107EA at 11 (Accession No. 20210107). Mountain Valley made similar representations in its
Section 404 application to the Corps: “[T]he selection of trenchless crossings typically
results in the minimization of aquatic impacts at the crossing site, as well as the
minimization of impacts to riparian vegetations.” Mountain Valley Pipeline Project,
Individual Permit Application at 62 (Feb. 2021) (Accession No. 20210304-5122).
37
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
proposed to use the conventional bore method at every single waterbody within the
first 77 miles of the MVP route.108 In its current application, however, Mountain
Valley omits numerous of those crossings that it previously claimed were feasible to
associated with those techniques and the shortage of site-specific information in the
the Corps to fulfill its obligations under both NEPA and the Clean Water Act—
FERC must consider alternatives to Mountain Valley’s proposal that require the
review is required for all locations where Mountain Valley previously claimed such
alternatives flows from the NEPA statute itself and exists for any proposal “which
111 Union Neighbors United, Inc. v. Jewell, 831 F.3d 564, 568 (D.C. Cir. 2016).
38
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Because Mountain Valley has previously stated that it can cross all waterbodies in
the first 77 miles of the MVP route with a conventional bore, an alternative that
reasonable alternative and presents an unresolved conflict over how those crossings
should occur. Further, FERC must investigate the degree to which requiring
its NEPA duty, but also for the Corps to carry out its responsibilities under the
Clean Water Act. As the Corps explained to FERC, its permitting process also
requires an analysis of alternatives. Specifically, the Corps may not authorize the
crossing if there “is a practicable alternative to the proposed discharge which would
precept of the Corps’ Regulatory Program under Section 404 of the Clean Water Act
is that the discharge of dredged and/or fill material into waters of the United States
will be avoided and minimized, where it is practicable to do so,” such that a “Section
404 of the Clean Water Act permit may only authorize the least environmentally
39
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Corps’ permitting process, it must “evaluate how the Project was designed to avoid
and minimize the discharge of dredged and/or fill material into waters of the United
So far, Mountain Valley has not provided sufficient data to inform a site-
regardless of whether the company intends to trench or bore the particular location.
In its Corps application, Mountain Valley maintains that there are site specific
considerations at each stream.116 But Mountain Valley has never detailed what
those site specific considerations are.117 In particular, for its proposed boring
114 Id.
115Id.; see also 40 C.F.R. 230.10(a)(4) (requiring supplementation of NEPA documents that
do not consider alternatives in sufficient detail to address the “least environmentally
damaging practicable alternatives” requirements of the Section 404(b)(1) guidelines).
118 Id.
40
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
accomplish using the open-cut method. In order for the Corps to be able to rely on
FERC’s NEPA analysis for the project in determining the least environmentally
locations.
F. FERC Must Provide Additional Opportunity for Public Review and Comment
of Currently Outstanding Information Necessary to Assess the Impacts of the
Proposal
process. When seeking public input in the NEPA process, agencies must “provide
circumstances, to permit members of the public to weigh in with their views and
thus inform the agency decision-making process.” Bering Strait Citizens for
Responsible Dev. v. U.S. Army Corps of Eng’rs, 524 F.3d 938, 953 (9th Cir. 2008).
FERC has failed to provide adequate information to allow the public to develop
complete comments and fully identify all significant issues that need to be
Mountain Valley has provided that preclude a full assessment of the likely impacts
of the proposed activities. Indeed, on April 12, 2021, just three days prior to the
41
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Act document,” and requested that Mountain Valley respond within 15 days.119 The
critical outstanding information that will not be subject to public review and
“the containment and disposal measures that would be used for any drilling
fluid and/or lubricants to avoid potential impacts to resources during and
after boring activities;”
information concerning “the stability of the proposed bore pits,” including a
description of “how the bore pits would be constructed in order to prevent
collapse;”
information supporting Mountain Valley’s claims regarding the likelihood of
a bore deflection to breach the stream bottom;
information regarding energy-dissipation devices that would purportedly
mitigate the impacts of the discharges from borehole dewatering devices;
the acreage of disturbance of riparian buffers;
information regarding time-of-year restrictions relative to hibernation season
for the Indiana bat;
information necessary to determine the Environmental Justice implications
of the proposed activity;
information regarding the best management practices to be applied in areas
of sensitive karst geology; and
information necessary to determine the likelihood of boring failures including
the likelihood of encountering “boulders more than one-third the size of the
casing,” “mixed-face conditions of soil and solid rock,” and “flowing/heaving
sands and artesian groundwater conditions.”120
In order to satisfy NEPA’s public participation goals, the public must have an
120 Id.
42
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Commission’s information request and any other information Mountain Valley may
submit to fill the existing information gaps as part of the NEPA process. This fact
further supports the conclusion that FERC must, after gathering adequate
information, prepare a Supplemental EIS and circulate that document for public
G. FERC Must Consider the MVP’s Climate Change Impacts as Part of Its NEPA
Analysis for the Proposed Amendment
FERC’s environmental review must fully consider the climate impacts of this
pipeline project and may not rely on the deficient and outdated discussion in its
2017 FEIS. President Biden’s executive orders addressing climate change, as well
as a recent FERC order, make clear that NEPA requires more. Because Mountain
environmental impacts of the project, its reasonable alternatives, and whether the
project is in the public interest, FERC must include a climate change analysis that
the Corps intends to rely on FERC’s environmental review for its NEPA obligations
associated with Mountain Valley’s Clean Water Act Section 404 permit application,
Because “[t]he harms associated with climate change are serious and well
121 Massachusetts v. U.S. Envtl. Prot. Agency, 549 U.S. 497, 521 (2007).
43
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
gas that will drive emissions of carbon dioxide and other greenhouse gases that
greenhouse gas emissions for its expected lifespan of fifty years,123 in conflict with
by no later than 2050.”125 In Executive Order 13990, President Biden directed all
address any Federal “actions during the last 4 years that conflict with . . . important
Gases and instructs agencies to use the Social Cost of Carbon, which has been
widely endorsed by economists, scientists, and legal scholars,127 to “capture the full
122Cf. Sierra Club v. FERC, 867 F.3d 1357, 1372 (2017) (holding that FERC must analyze
the climate change effects for a project whose purpose is to burn gas in power plants).
124See Exec. Order No. 14008, Tackling the Climate Crisis at Home and Abroad, 86 Fed.
Reg. 7619, 7619 (Jan. 27, 2021); Exec. Order 13990, Protecting Public Health and the
Environment and Restoring Science to Tackle the Climate Crisis, 86 Fed. Reg. 7037, 7037
(Jan. 25, 2021).
See NAT’L ACADS. SCI., ENG’G & MED., VALUING CLIMATE DAMAGES: UPDATING
127
ESTIMATES OF THE SOCIAL COST OF CARBON DIOXIDE 3, 10–17 (2017); NAT’L ACADS. SCI.,
ENG’G & MED., ASSESSMENT OF APPROACHES TO UPDATING THE SOCIAL COST OF CARBON:
PHASE 1 REPORT ON A NEAR-TERM UPDATE 1 (2016); Richard L. Revesz et al., Best Cost
Estimate of Greenhouse Gas, 357 SCIENCE 655 (2017).
44
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Executive Order 13990 also makes clear that agencies should look to CEQ’s
2016 guidance on climate change analysis during NEPA review.129 That guidance
also makes clear that “a statement that emissions from a proposed Federal action
represent only a small fraction of global emissions . . . is not an appropriate basis for
NEPA” because such a statement “does not reveal anything beyond the nature of
the climate change challenge itself: the fact that diverse individual sources of
The analysis in the 2017 FEIS satisfies neither FERC’s, nor the Corps’,
NEPA obligations. The 2017 FEIS discusses climate change and the harms of
emissions due to end-use combustion of the gas that would be transported by the
Council on Envtl. Quality, Final Guidance for Federal Departments and Agencies on
130
Consideration of Greenhouse Gas Emissions and the Effects of Climate Change in National
Environmental Policy Act Reviews 10 (2016) [hereinafter “CEQ Climate Guidance”].
45
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
pipeline.132 However, the FEIS stops there, stating: “Because we cannot determine
requirements.134 In Northern Natural Gas Company,135 FERC “for the first time
assessed the significance of a proposed natural gas pipeline project’s greenhouse gas
emissions and their contribution to climate change.”136 Chairman Glick stated that,
“[g]oing forward, [FERC is] committed to treating greenhouse gas emissions and
their contribution to climate change the same as all other environmental impacts
most consequential environmental impacts and we must consider all evidence in the
impact.”137
134 News Release, FERC, FERC Reaches Compromise on Greenhouse Gas Significance (Mar.
18, 2021) [hereinafter “FERC News Release”], available at https://www.ferc.gov/news-
events/news/ferc-reaches-compromise-greenhouse-gas-significance#.
135 174 FERC ¶ 61189 (2021). Although FERC concluded that the impacts of Northern
Natural were insignificant, that project was a replacement of existing pipeline rather than
a new pipeline. Id. at ¶ 1. MVP, with a capacity of 2.0 bcf/day, is one of the largest gas
pipelines proposed anywhere in the country and is exactly the kind of gas pipeline project
that poses the greatest risk of serious climate impacts.
137 Id.
46
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
climate change impacts and provides additional details on how climate change
impacts will be analyzed in similar projects. FERC notes: “In previous orders, the
The order further states that, “[f]or additional context, when states have
GHG emissions reduction targets we will endeavor to consider the GHG emissions
of a project on those state goals.”140 When states do not have emissions reduction
targets, FERC stated that it could compare the project-related emissions to the
state’s emissions in a previous year.141 Mountain Valley has not identified end users
for the vast majority of the MVP’s gas, but key downstream states have established
rigorous carbon reduction programs that FERC must consider. Virginia has set a
141 Id.
47
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
goal of achieving a net-zero carbon energy economy by 2050142 and has joined the
Regional Greenhouse Gas Initiative (“RGGI”) to help reach this target.143 Virginia
and the other RGGI members aim to collectively reduce power sector carbon dioxide
established the North Carolina Clean Energy Plan, which establishes the goal to
reduce emissions from the electric sector by 70% below 2005 levels by 2030 and
achieve carbon neutrality by 2050.146 FERC and the Corps should consider Virginia
and North Carolina’s recent policy achievements seeking a transition away from
fossil fuels, especially their 2050 net-zero goals, when weighing their respective
permitting decisions. For West Virginia and other downstream states lacking
emissions reduction targets, the agencies should consider each state’s baseline
analysis of the project’s climate change impacts, the new NEPA document should
Virginia Clean Economy Act, S.B. 851, 2020 Sess. (Va. 2020); Virginia Clean Economy
142
145If constructed, the MVP Southgate extension project (approved by FERC in Docket No.
CP19-14) would carry a portion of the MVP’s gas from the terminus of the MVP in
Pittsylvania County, Virginia to North Carolina markets.
146 N.C. Dep’t of Envtl. Quality, Clean Energy Plan 11, 12 (2019), https://bit.ly/3evSnMC.
48
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
also calculate impacts utilizing the Social Cost of Carbon for the entire anticipated
fifty-year life of the pipeline. Developed in 2010 and updated in 2016, the Social
for agencies to quantify [climate change] damage in dollars.”147 The Social Cost of
productivity, human health, property damages from increased flood risk, and the
value of ecosystem services.”149 The current values, which adjust the 2016 values for
inflation, estimate that every additional ton of carbon dioxide released from
the Social Cost of Carbon provides a more concrete, comprehensible metric that will
help FERC and the public assess the significance of the emissions. Additionally, it
will allow FERC and the Corps “to incorporate the social benefits of reducing carbon
147 Fla. Se. Connection, LLC, 162 FERC ¶ 61,233, at ¶ 45 (Mar. 14, 2018).
148See Interagency Working Group on the Social Cost of Carbon, Technical Support
Document 5 (2010), available at
https://www.epa.gov/sites/production/files/201612/documents/scc_tsd_2010.pdf.
149 Id. at 2.
49
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
pipeline.151
FERC may not rely on the deficient discussion of climate change in its 2017
FEIS but rather must fully analyze the climate change impacts of the project due to
“amendment” rather than an application for a new certificate, the requested change
is a major departure from the previous proposal that will result in previously
which the certificate cannot be amended and the pipeline cannot be built. FERC’s
Executive Order 13990. It would be arbitrary for FERC to reopen the environmental
151Interagency Working Group on the Social Cost of Carbon, Technical Support Document 1
(2010).
50
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
review without fixing the deficiencies it has identified with its discussion of climate
impacts.
Moreover, the Corps may not rely on the climate change discussion in the
2017 FEIS when processing Mountain Valley’s Section 404 permit application. In
the event that FERC’s environmental review does not sufficiently address the
project’s climate change impacts, the Corps will be required to engage in its own
individual Section 404 permit, the Corps has not yet fulfilled its independent
obligation, under NEPA152 and as part of its own separate public interest review,153
and its own recently acknowledgment that it can and must fully evaluate climate
impacts, FERC must provide a meaningful analysis of the pipeline’s climate change
targets into its analysis; and quantify the associated harms of its emissions—
including end-use emissions—using the Social Cost of Carbon. The Corps must do
152See, e.g., Wyo. Outdoor Council v. U.S. Army Corps of Eng’rs, 351 F. Supp. 2d 1232, 1243
(D. Wyo. 2005) (holding that Corps’ failure to assess cumulative impacts of proposed permit
on non-wetland environmental resources was arbitrary and capricious under NEPA).
51
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
II. FERC May Not Grant the Proposed Amendment Absent State
Certification or Waiver from West Virginia and Virginia under
Section 401 of the Clean Water Act
Mountain Valley whether its application required new certifications under Section
401 of the Clean Water Act, 33 U.S.C. § 1341.154 In Mountain Valley’s response,
submitted on March 29, 2021,155 Mountain Valley takes the position that:
[n]o additional 401 Water Quality Permit is required for the Amendment
Project, including trenchless crossings of Section 10 streams. The
Virginia State Water Control Board issued a water quality certification
on December 8, 2017, that expressly covers future modifications to the
Project approved by the Commission . . . . As required by the
certification, Mountain Valley notified the Virginia Department of
Environmental Quality of the Amendment Project on February 19, 2021.
The West Virginia Department of Environmental Protection issued a
general waiver of its authority to issue a water quality certification for
the MVP Project on November 1, 2017 . . . .156
Mountain Valley included copies of the waiver from West Virginia and certification
from Virginia that Mountain Valley claims obviate the need for Section 401
156 Id. at 1
52
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
certificate amendment triggers Section 401. Section 401 requires state certification
before “a Federal license or permit to conduct any activity including, but not limited
to, the construction or operation of facilities, which may result in any discharge into
the navigable waters” may issue.158 The name of the federal approval in question is
discharge of water will suffice and the statute “is triggered by the potential for a
(and later withdrew its request for) a similar certificate amendment that would
have approved fewer trenchless crossings than Mountain Valley seeks now, and
Commission staff determined then that Mountain Valley’s tunneling plan would
have had environmental impacts “not considered in the final environmental impact
159 Del. Riverkeeper Network v. FERC, 857 F.3d 388, 398 (D.C. Cir. 2017) (cleaned up).
Environmental Protection Agency, Clean Water Act Section 401 Certification Rule, 85
160
53
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
through inadvertent spills.”162 The same discharges surely may result here since the
discharges are not limited to those that Commission staff recently acknowledged.
bore pits on a scale that suggests at least some pumped water will flow back into
surface waters near the bore sites.163 Since those flows would constitute discharge[s]
into the navigable waters,”164 the potential for those flows triggers Section 401.
would authorize activities that “may result in [a] discharge into the navigable
waters.”165 Rather than claim its requested certificate amendment does not trigger
Section 401, Mountain Valley elides the question and insists that it has already
obtained the requisite approval in the form of a waiver from West Virginia and a
waiver from West Virginia and certification from Virginia do not cover its requested
certificate amendment. Just three months ago, the Commission confirmed in Pacific
Connector Gas Pipeline, LP, that Section 401 certifications are “specific to
5179.
165 Id.
54
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
dispute over whether a state had waived through inaction but its rule is equally
applicable here: a project proponent can “use a single application to request water
permitted by the state certifying agency and the certification application is clear as
Connector is dispositive here. Mountain Valley’s position rests on the premise that
its existing state approvals—a waiver from West Virginia and a certification from
position has two fatal flaws. First, West Virginia’s 2017 waiver expressly stated
that it was “specific to the above-referenced MVP project to construct a natural gas
pipeline in West Virginia,” and the waiver letter’s subject line referred to “FERC
Docket No. CP-16-10-000.”169 The specific iteration of the MVP project contemplated
55
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
in 2017 in Docket No. CP-16-10-000 assumed that “[a]ll waterbody crossings for the
MVP would be dry open-cut crossings.”170 In other words, West Virginia did not
issue a blanket waiver for all project activities, as Mountain Valley claims; the state
explains that a certification decision for one federal authorization is not dispositive
multiple federal authorizations, but only if the applicant “is clear as to what
amendment because the need for an amendment had not yet arisen and the EIS
the requested certificate amendment, but that choice is for West Virginia alone—
not for the Commission and certainly not for Mountain Valley.
In the case of Virginia, Mountain Valley claims that the state’s 2017 Section
56
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Valley claims, nor could it have been given the record before the Virginia State
Water Control Board at the time. To start, Mountain Valley cherry picks a sentence
from the “Definitions” section of Virginia’s 2017 certification, which states that
“[t]he 401 Water Quality Certification applies to the location of pipeline right of
way, access roads, and appurtenances as described in the EIS and any changes
naturally applies only to those subsequent changes that remain within the scope of
the EIS—that is, those that do not require supplemental review under the National
Environmental Policy Act (NEPA)—but to the extent there is any ambiguity, the
“Scope of Certification” section resolves it: “This Certification covers all relevant
upland Project activities within the route identified in the [EIS].”174 Furthermore,
Virginia could not have rationally issued the sweeping certification in 2017 that
Mountain Valley posits because the EIS assumed at that time that “[a]ll waterbody
crossings for the MVP would be dry open-cut crossings” and did not evaluate
174 Id. at 3.
57
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
different in both kind and degree from those associated with the variance requests
that the Commission has approved for Mountain Valley in the past that were not
amendment would result in less impact to resources than open-cut crossings.178 This
prediction may—or may not—prove true here, but it is beside the point. Section 401
authority belongs to the states, and neither West Virginia nor Virginia has had an
opportunity to consider whether Section 401 certifications should issue for this
federal authorization and these discharges. To our knowledge, Mountain Valley has
not yet requested a new Section 401 certification for this certificate amendment
from either state.179 Absent such certifications or waiver thereof, according to the
177Whether the Commission’s liberal use of variances for this pipeline is lawful is an issue
beyond the scope of this letter and immaterial to the question of whether new Section 401
certifications are required for this amendment application.
58
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
plain terms of Section 401, the Commission may not grant Mountain Valley’s
requested amendment.
CONCLUSION
For the foregoing reasons, FERC may not grant Mountain Valley’s
opportunity for public review and comment, and obtained Clean Water Act Section
/s/Benjamin Luckett
Benjamin A. Luckett
Derek O. Teaney
Senior Attorney
APPALACHIAN MOUNTAIN ADVOCATES
P.O. Box 507
Lewisburg, WV 24901
(304) 873-6080
[email protected]
[email protected]
sufficiently establish that the agency received a request for section 401 certification with
respect to that application.” Pacific Connector, 174 FERC ¶ 61,057 at ¶ 34.
59
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
60
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
CERTIFICATE OF SERVICE
I hereby certify that on April 15, 2021, I caused the foregoing document to be
served by electronic mail upon each person designated on the official service list
/s/Benjamin A. Luckett
Benjamin A. Luckett
APPALACHIAN MOUNTAIN ADVOCATES
61
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Exhibit E
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
MVP proposal for trenchless stream crossings lacks critical technical planning
Contents
1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
2 Deficiency in dewatering analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
3 Lack of geotechnical analysis in assessing feasibility . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
4 Deficiency in analyzing impacts to riparian zones and wetlands . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
5 Impacts of the proposed trenchless crossings on endangered species . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
6 Conclusions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
1 of 8
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
MVP proposal for trenchless stream crossings lacks critical technical planning
In Section 3, we describe the need for detailed and site- depends on the protective measures taken and whether or not
specific geotechnical analysis. A geotechnical analysis is the these measures fail.
testing of soil and rock, generally to determine the ability There has been no quantification of dewatering needs at
of an area to support an engineering project. In this case, any of the proposed boring sites. In the Supplemental Envi-
a geotechnical analysis would determine whether the area ronmental Report (p 2-11), MVP claims “The amount and du-
around the stream can support the bore pit, and also whether ration of drawdown, and lateral expanse of drawdown impact
there are boulders in the path of the proposed crossing. This from the bore pit, would depend on the existing groundwater
essential information cannot be ascertained from analyzing level at each site at the time of construction and site-specific
nearby sites or general knowledge of the area. Geotechnical characteristics such as soil type.” No further detail is provided.
analysis is a part of standard engineering practice, but MVP This is a significant oversight in the environmental analysis
has failed to conduct this for 120 of 126 proposed trenchless and must be further addressed. It is not a sufficient analysis
crossing sites. of potential environmental impacts to state that the impacts
Section 4 outlines deficiencies in the analysis of impacts will be determined upon start of construction.
to riparian zones and wetlands. MVP claims that the proposed Groundwater that has been removed and water used for the
crossings will not introduce any new impacts to these areas. lubrication of the drill head must be carefully managed and
However, this ignores important new considerations including monitored. While MVP is using the sediment control method
the impacts of digging, storing the backfill, and filling the bore of filtering wastewater through hay bales covered in filter fab-
pit once complete. Engineering plans also underestimate the ric, MVP has not analyzed the efficacy of this method other
size of the bore pit opening, so the area of impacted riparian than to simply state that doing so “greatly reduces the amount
areas is therefore underrepresented by MVP. MVP claims that of turbid water discharged from the work area and potentially
impact to riparian areas and wetlands will be insignificant, but mixing with the [...] river” (Supplemental Environmental
have done no site-specific hydrological analysis to support Report, Appendix F, p F-5). Without a detailed analysis of
this claim. the efficacy of their proposed method of sediment control,
Finally, Section 5 describes how the uncertainties in sec- impacts to the environment cannot be accurately predicted.
tions 2 through 4 could result in harm to federally protected One of the proposed trenchless crossings is in the
species. All of the deficiencies identified in this analysis ex- Greenbrier River, which is designated as a “Protected
pose risks of engineering failures that could lead to significant Stream” under the WV Natural Streams Preservation
impacts to endangered species. MVP has provided no detailed Act, is near a public drinking water supply, and con-
action plan and accountability in case of an engineering fail- tains karst forming bedrock formations. Additionally,
ure. In-stream monitoring of water quality is necessary to this river is habitat to the endangered candy darter and
monitor these potential impacts. The construction timeline is bordered by the threatened Virginia spiraea. The pro-
of five years presented by MVP poses significant risks to the posed crossing method is Direct Pipe, the method requiring
endangered candy darter and Roanoke logperch given the life the highest amount of water/clay slurry for lubrication. The
cycles of these species. amount of water to be withdrawn from Greenbrier River and
the duration of withdrawal has not been estimated, thus the
2. Deficiency in dewatering analysis impacts of the withdrawal have not been adequately assessed.
2 of 8
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
MVP proposal for trenchless stream crossings lacks critical technical planning
3 of 8
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
MVP proposal for trenchless stream crossings lacks critical technical planning
While MVP does evaluate factors such as crossing length, material safety data sheets. According to Mohammed (2018),
boring pit depth, maximum slope steepness, and more, the the amount of bentonite in drilling fluid can vary greatly, rang-
wide ranges of these physical factors serves to further high- ing from as low as 0.5% and up to 14% by weight of water.
light the non-uniformity of proposed trenchless crossing sites If 600,000 gallons of water are used, a weight of 4,998,000
(Table 1). Thus, given the heterogeneous soil and geology pounds, and assuming the bentonite content in the water is
that characterizes the region, MVP should complete a similar 0.5%, the weight of bentonite used would be 24,990 pounds.
feasibility assessment at all proposed stream crossings so that Alternatively, assuming that bentonite content in the water is
the feasibility of safely boring at each site can be reasonably 14%, the weight of bentonite used would be 699,720 pounds,
determined. a difference of 2,700%. This is a considerable variation in
the amount of bentonite that could be used, thus MVP needs
Table 1. Standard Deviation (SD) and range of values listed to provide more detail for an accurate impacts analysis.
in Table 15 of MVP’s Individual Permit Application.
Attribute SD Range
Crossing Length (ft) 132 20-1250
Pit Depth (fit)
Maximum Steep Slope (%)
7
14
11-49
1-63
“The realization of
Maximum Average Slope (%) 9 0-48 drilling works always
Maximum Winch Hill Length (ft) 142 0-702
results in introducing
3.1 Risk and Impacts of Bentonite Contamination drilling fluid into the
MVP states that,
“in some situations, particularly in longer bores
environment.”
or in bores through mixed ground or clay, small (Kwast-Kotlarek et al.,
quantities of water, bentonite, or polymer-based
lubricant may be applied to the cutting head and
2018)
exterior of the casing to reduce friction and in-
crease the likelihood of success of the crossing.
Any lubricants used will be non-petrochemical MVP has also failed to discuss how it will handle ben-
based, non-hazardous, and NSF-60-compliant tonite spills and leakage. A site-specific soil analysis should
and therefore will not adversely impact the sub- be conducted to determine where lubricant will be used, de-
ject waterbody or wetland” (Individual Permit velop detailed management plans, develop contingency plans
Application, p 54). for spills, and to identify high risk sites. A soil analysis is
Therefore, MVP is uncertain where lubricant will be used also warranted because the amount of bentonite released to
and does not propose to devise management plans, assess the environment depends on the type of soil in which the
feasibility, or evaluate impact until onsite construction has construction is conducted (Kwast-Kotlarek et al., 2018). A
begun. This presents a major risk to the the aquatic and ri- thorough evaluation of the potential effects of riparian and
parian environment. MVP claims the bentonite-laden water wetland contamination by lubricants is currently unable to be
will be contained, however, Kwast-Kotlarek et al. (2018) completed because MVP has not determined where lubricants
concluded that “the realization of drilling works always re- will be necessary, and in what quantity. MVP mentions that
sults in introducing drilling fluid into the environment”. they will rely on “contingency plans” in the event of contami-
Clay particles are very small, and therefore stay in the water nation, but they do not present the actual plans. Therefore, it
column longer, settle out more slowly, and travel farther than is unclear if these plans are adequate and will appropriately
other sediment. This results in prolonged and wider-spread ad- handle spills to adhere to regulations.
verse impacts to aquatic organisms and drinking water quality. Because of the significant environmental risks that drilling
Bentonite contamination may result in changes in soil chem- lubricants could pose in sensitive environments, considerably
istry and soil water-holding properties, as well as changes in more detail is needed in the drilling lubricant planning. MVP
photosynthetic rates and above-ground biomass of vegetation must present a clear description of whether and how much
(Mi et al., 2020). Bentonite impact on aquatic organisms has bentonite will be used at each site as a part of a geotechnical
not been well studied and thus use in sensitive environments analysis. If bentonite is to be applied, each site should be eval-
should be approached with extreme caution. MVP’s lack of uated for potential environmental exposures resulting from
clear planning for lubricant use makes it impossible to eval- such use, site-specific management and spill plans should be
uate if the lubricants will be used appropriately and without developed, and a detailed bentonite monitoring regime should
harm to the environment. be established.
The amount of bentonite required has not been quantified
in MVP’s environmental analysis, nor have they provided
4 of 8
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
MVP proposal for trenchless stream crossings lacks critical technical planning
4. Deficiency in analyzing impacts to ri- listed species, we have focused on how the uncertainty in
parian zones and wetlands impact analysis could harm the two aquatic species: candy
darters and Roanoke logperch.
While MVP claims that trenchless crossing methods are less Candy darters (Etheostoma osburni) and Roanoke log-
impactful than conventional open-cut methods, these methods perch (Percina rex) are short-lived, small-bodied, freshwater
can lead to degradation of the riparian zone and wetlands. fish that were declared federally endangered in 2018 and 1989,
Riparian zone and wetland degradation can change soil and respectively. They occupy streams in West Virginia and Vir-
sediment dynamics, and result in the loss of vegetation. Here, ginia and are currently facing major threats. Their primary
we outline deficiencies in MVP’s analysis of impacts to ripar- threat is habitat degradation. Darters in general (including
ian zones and wetlands. Roanoke logperch) are not able to tolerate dramatic increases
The slope of the inside edge of bore pits is important for in turbidity or sedimentation, as they are visual predators that
worker safety, and choosing the correct slope depends on the also need porous streambeds to lay their eggs. If sedimen-
soil characteristics (Virginia Occupational Safety and Health, tation is high enough, that section of stream can see a sharp
2016; Virginia Department of Transportation, 2021). MVP decrease in population growth rates due to lack of prey items,
has failed to do the requisite soil analysis needed to deter- particularly benthic invertebrates, in addition to losing nest
mine what slope will be needed to keep their workers safe sites (Berkman & Rabeni, 1987). Additionally, hybridization
within each bore pit at each stream crossing. Furthermore, with the introduced variegate darter (Etheostoma variatum)
deeper bore pits that require shallower slopes to create safe that can outcompete candy darters over both food resources
working conditions are larger, produce larger spoil piles, and and mating opportunities is another issue to consider. Notably,
present an increased impact on the surrounding environment. the greatest factor historically for candy darter’s sharp decline
Because MVP has not determined the proper bore pit slope, was not hybridization, but habitat destruction, degradation,
they have not calculated the total area of the riparian zone that and fragmentation (USFWS, 2018). It is therefore critical,
will be impacted by bore pits. This could lead to greater phys- and recommended by the U.S. Fish and Wildlife Service, to
ical removal of vegetation and larger impacts on surrounding avoid damaging habitat whenever possible.
vegetation in riparian zones and wetlands.
While MVP claims that the proposed trenchless crossings
“[w]ill not result in a material change to impacts and mitiga-
MVP has not calculated tion for endangered, threatened, and special concern species
the total area of the compared to the Certificated Project,” they have not conducted
a full analysis to support this. Because threatened and endan-
riparian zone that will be gered species are fragile species that need extra protections, it
is imperative to fully quantify the potential impacts trenchless
impacted crossings will have. As is, MVP assumes the impacts will
be lessened from the originally proposed work, but there is
Additionally, MVP has failed to include acreage associ- too much uncertainty to know if their work will adversely
ated with travel lanes in vegetation removal estimates. Ripar- impact at-risk species. An additional concern is the timeline
ian vegetation stabilizes stream banks and the surrounding soil of recovery. MVP states that any habitat degradation would be
and sediment landscape. The removal of vegetation for access temporary, but does not clarify what this entails. Furthermore,
roads, the digging of bore pits, and the indirect removal by dis- a disturbance lasting only a few months scheduled during the
turbance of surrounding riparian and wetland landscapes may spawning season (typically mid-April to late June for candy
result in dramatic long-term erosion and increased sediment darter and mid-April to early May for Roanoke logperch)
input downstream (Feld et al., 2018). The loss of riparian would have much greater potential impacts than construction
vegetation also inhibits the ability of riparian zones to reduce outside of the spawning season.
watershed nutrient inputs (Lowrance et al., 1997; Groh et al., MVP is assuming that no new protections are needed for
2020). the proposed trenchless crossings because trenchless crossings
are assumed to be less impactful to the aquatic environment
5. Impacts of the proposed trenchless than trenched crossings. The basis for this assumption is that
there will be no “in-stream activity” during trenchless crossing
crossings on endangered species
construction. This ignores the high risk of sediment control
The U.S. Fish and Wildlife Service determined that the pre- failures, boring failures, leaks, etc. detailed above. Even if
viously accepted project is “likely to adversely affect” five these construction activities lead to acceptable losses over
federally listed species: Virginia spiraea (Spiraea Virginiana); entire populations, if population declines are localized then
Roanoke logperch (Percina rex); candy darter (Etheostoma construction could have unacceptable impacts on the limited
osburni); Indiana bat (Myotis sodalis), and Northern long- genetic diversity of these species. MVP should conduct an
eared bat (Myotis septentrionalis; 2020 Biological Opinion). entirely new environmental impact analysis to understand how
While our concerns regarding adverse impact span all the the different crossing methodology will impact the surround-
5 of 8
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
MVP proposal for trenchless stream crossings lacks critical technical planning
ing environment and submit a Supplemental Environmental the impacts to the candy darter and Roanoke logperch, as well
Impact Statement. This document should include a robust as other federally listed species, are unclear.
monitoring plan for both sedimentation load and darter abun-
dance. Without field monitoring and accurate models based 6. Conclusions
on localized empirical data, the impacts on these species could
After reviewing MVP’s Supplemental Environmental Report
be higher than previously predicted. By performing this work
and Individual Permit Application, we conclude that there
MVP would more fully understand and potentially prevent
is a lack of detail in the provided information to accurately
impacts resulting from their activity. As stated previously, the
assess the impact of trenchless crossings on proposed streams
impact of bentonite drilling lubricant on aquatic organisms
and wetlands in Virginia and West Virginia. The environ-
has not been well studied and consequently should be used
mental risks of trenchless crossings are exacerbated in areas
with caution and every possible protective measure utilized.
with steep terrain and karst-forming topography, and require
significant planning and feasibility assessments based on site-
There is too much specific data collection. Therefore, we strongly urge MVP to
do a full impacts analysis and submit a Supplemental Environ-
uncertainty in planning mental Impact Statement describing their proposed trenchless
and insufficient analysis crossing methods in greater detail. Specifically, we have five
major recommendations that should be included in the Sup-
to know if trenchless plemental Environmental Impact Statement:
crossings will adversely 1. Given that the Appalachian Region has unique geol-
ogy compared to other areas, MVP should use region-
impact at-risk species. specific parameters (e.g. site-specific soil information)
in a model to predict the impact their dewatering may
have in the region.
This additional effort would align with the precautionary
principle, an important philosophy to consider when decisions 2. A detailed and expanded feasibility study should be
are being made that may impact threatened and endangered completed at all proposed trenchless crossing sites to
species when the most relevant science will not be available gather site-specific geotechnical information. This in-
until after the fact. Use of this principle lowers the risk of formation would reduce the likelihood of encounter-
irreversible harm by advocating for alternative plans to be ing unexpected geological materials and increase confi-
considered (e.g. National Environmental Policy Act), increas- dence in successful crossings. Additionally, this infor-
ing public input, and most importantly in this case, putting mation could inform the region-specific characteriza-
the burden of proof of no harm on MVP instead of requiring tion of the model described above.
agencies/academia to find proof of harm. This is especially 3. Determine sloping requirements for bore pits and in-
relevant when no or little empirical data is available, such as clude that new bore pit size on all engineer drawings
in the case of how much damage the proposed boring stream and in all requisite riparian/wetland disturbance calcu-
crossing methods can cause to aquatic ecosystems. lations.
The potential risks for darter species are mainly based on
the impacts to spawning habitat and food availability. Both 4. Given the environmental risks posed by drilling lubri-
candy darters and Roanoke logperch need porous streambeds cants, MVP must present a clear description of whether
to lay eggs. Turbid waters are correlated to declining and how much bentonite will be used at each site as a
macro-invertebrate populations (i.e. darter and logperch food part of a geotechnical analysis.
sources) and make prey detection more difficult. While in-
5. Lastly, we strongly recommend MVP establish a con-
creased sedimentation impacts are expected to last 5 years or
tinuous water-quality monitoring program that utilizes
less, darter life history makes them vulnerable on this time
both in-situ turbidity measurements and corresponding
scale: candy darters have lifespans of 3 years, becoming
sediment concentration measurements. This continuous
sexually mature at 2, and Roanoke logperch have lifespans
water-quality monitoring program would allow evalua-
of 6 years, becoming sexually mature at 2-3. While there
tion of water-quality impacts before, during, and after
are mixed age classes in the wild, if decreased population
construction and ensure environmental degradation is
size and growth do last longer than 5 years, it would affect
not occurring at streams being crossed.
the demography of populations to a greater degree than has
been considered by USFWS and the Federal Energy Regula- With a full impact analysis, presented as a Supplemen-
tion Commission (FERC). To understand the impact of the tal Environmental Impact Statement, we believe MVP can
proposed construction, MVP needs to detail how long con- describe the environmental consequences of their crossing
struction will last, how long the impacts may last, and what methods in more detail and accurately assess their impact on
time of year the activities will occur. Without this information, endangered aquatic species like the candy darter.
6 of 8
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
MVP proposal for trenchless stream crossings lacks critical technical planning
*Mast, Hannah, PhD Student Kemp, M.W., Batleson, R., Bergstrom, P., Carter, V., Galle-
Department of Environmental Sciences gos, C.L., Hunley, W., Karrh, L., Koch, E.W., Landwehr,
University of Virginia J.M., Moore, K.A., Murray, L., Naylor, M., Rybicki,
N.B., Court Stevenson, J., & Wilcox, D.J. (2004).
Rady, Joshua M., PhD Candidate Habitat requirements for submerged aquatic vegeta-
Department of Forest Resources and Environmental Conser- tion in Chesapeake Bay: Water quality, light regime,
vation and physical-chemical factors. Estuaries 27: 363–377.
Virginia Tech https://doi.org/10.1007/BF02803529
7 of 8
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
MVP proposal for trenchless stream crossings lacks critical technical planning
Mohammed, A.S. (2018). Electrical resistivity and rheologi- U.S. Fish and Wildlife Service. Endangered and Threatened
cal properties of sensing bentonite drilling muds modified Wildlife and Plants; Endangered Species Status for the
with lightweight polymer. Egyptian Journal of Petroleum: Candy Darter. 83 Fed. Reg. 58747. (November 21, 2018)
55-63. https://doi.org/10.1016/j.ejpe.2017.01.002 (to be codified at 50 C.F.R. pt.17).
Mountain Valley Pipeline, LLC (2021). Supplemental Envi- Virginia Occupational Safety and Health. (2016). Excavations
ronmental Report for Proposed Certificate Amendment Standard, §§1926.650- 1926.652.
for Avoidance of Waters of the United States. Docket No.
CP21-57-000. Virginia Department of Transportation. (2021). Chapter 3:
geotechnical engineering. Manual of instructions.
Tetra Tech, Inc. (2021). Mountain Valley Pipeline Project
USACE Individual Permit Application. Whittecar, G.R., Newell, W.L., & Eaton, L.S. (2016). The
Geology of Virginia: Chapter 11, Landscape Evolution
in Virginia.
8 of 8
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Exhibit F
0019584
Remove from Table 1: Strouds Creek is 1) not identified as a candy darter extant stream and 2) is a perennial,
No impact (>800m direct tributary to the Gauley River (candy darter extant stream). The Project crossing of Strouds Creek is
Yes Access Road Strouds Creek 110.1 Webster, WV Existing single-span bridge 40 0 No No No 0 0 0.00
away) 975m upstream of mouth with Gauley; therefore the crossing is more than 800m upstream of extant
population.
Remove from Table 1: Strouds Creek is 1) not identified as a candy darter extant stream and 2) is a perennial,
No impact (>800m direct tributary to the Gauley River (candy darter extant stream). The pipeline crossing of Strouds Creek is
Yes Pipeline Strouds Creek 110.1 Webster, WV Open-Cut Dry 75 0.0594 YES No No 0 0 0.00
away) 975m upstream of mouth with Gauley; therefore the crossing is more than 800m upstream of extant
population.
Remove from Table 1: Big Beaver Creek is 1) not identified as a candy darter extant stream and 2) is a
No impact (>800m perennial, direct tributary to the Gauley River (candy darter extant stream). The pipeline crossing of Big
Yes Pipeline Big Beaver Creek 114.3 Nicholas, WV Open-Cut Dry 75 0.0625 YES No No 0 0 0.00
away) Beaver Creek is more than 4,300 meters upstream of mouth with Gauley; therefore the crossing is more than
800m upstream of an extant population.
Remove from Table 1: Big Beaver Creek is 1) not identified as a candy darter extant stream and 2) is a
No impact (>800m perennial, direct tributary to the Gauley River (candy darter extant stream). The pipeline crossing of Big
Yes Pipeline Big Beaver Creek 116.2 Nicholas, WV Open-Cut Dry 75 0.124 YES No No 0 0 0.00
away) Beaver Creek is more than 4,300 meters upstream of mouth with Gauley; therefore the crossing is more than
800m upstream of an extant population.
POTENTIAL
Yes Pipeline Gauley River 118.9 Nicholas, WV Open-Cut Dry 75 2.1556 YES YES YES 1000 45 11.12 Retain in Table 1: Gauley River is identified as a candy darter extant stream.
IMPACT
Document Accession #: 20210513-5107
Retain in Table 1: Little Laurel Creek3 is 1) not identified in the original Table 1, 2) not identified as a candy
darter extant stream and 3) is a perennial, direct tributary to the Gauley River. The Project crossing of Little
POTENTIAL
No Access Road Little Laurel Creek3 119.0 Nicholas, WV Temporary single-span bridge 40 0 No No YES 0 0 0.00 Laurel Creek is within 30m upstream of mouth with Gauley; therefore impacts may potentially occur to an
IMPACT
extant candy darter population. If an 800-m downstream buffer is applicable, then 770m of Gauley River is
affected and average width of Gauley river is 45m. The level of instream impact (if any) is not currently known.
Retain in Table 1: Little Laurel Creek2 is 1) not identified as a candy darter extant stream and 2) is a perennial,
direct tributary to the Gauley River. The Project crossing of Little Laurel Creek is within 280m upstream of
POTENTIAL
Yes Access Road Little Laurel Creek2 119.0 Nicholas, WV Temporary single-span bridge 40 0.0249 No No YES 0 0 0.00 mouth with Gauley; therefore impacts may potentially occur to an extant candy darter population. If an 800-m
IMPACT
downstream buffer is applicable, then 520m of Gauley River is affected and average width of Gauley river is
45m. The level of instream impact (if any) is not currently known.
Remove from Table 1: Little Laurel Creek1 is 1) not identified as a candy darter extant stream and 2) is a
No impact (>800m perennial, direct tributary to the Gauley River (candy darter extant stream). The Project crossing of Little
Yes Access Road Little Laurel Creek1 119.0 Nicholas, WV Temporary single-span bridge 40 0.0264 No No No 0 0 0.00
away) Laurel Creek is approximately 1,100 meters upstream of mouth with Gauley; therefore the crossing is more
than 800m upstream of an extant population.
No impact (indirect Remove from Table 1: Jims Creek is 1) not identified as a candy darter extant stream and 2) is a perennial,
Yes Pipeline Jim’s Creek 123.4 Nicholas, WV Open-Cut Dry 75 0.0349 YES No No 0 0 0.00
tributary) direct tributary to Hominy Creek. Hominy Creek is not identified as a candy darter extant stream.
Remove from Table 1: Hominy Creek is 1) not identified as a candy darter extant stream and 2) is a perennial,
No impact (candy direct tributary to the Gauley River. The Gauley River is a candy darter extant stream; however, the Gauley
Yes Pipeline Hominy Creek 126.9 Nicholas, WV Open-Cut Dry 75 0.0976 YES darter population No No 0 0 0.00 River is impounded (creating Summersville Lake) and Summersville Lake is a candy darter extirpated section.
Filed Date: 05/13/2021
not present) Hominy Creek drains into Summersville Lake therefore Hominy Creek is not a direct tributary to a candy darter
extant stream section.
Remove from Table 1: Hominy Creek is 1) not identified as a candy darter extant stream and 2) is a perennial,
No impact (candy direct tributary to the Gauley River. The Gauley River is a candy darter extant stream; however, the Gauley
Yes Access Road Hominy Creek 127.0 Nicholas, WV Existing single-span bridge 25 0 No darter population No No 0 0 0.00 River is impounded (creating Summersville Lake) and Summersville Lake is a candy darter extirpated section.
not present) Hominy Creek drains into Summersville Lake therefore Hominy Creek is not a direct tributary to a candy darter
extant stream section.
POTENTIAL
Yes Pipeline Stony Creek 200.4 Giles, VA Conventional Bore 75 0 No YES YES 1000 9 2.22 Retain in Table 1: Stony Creek is identified as a candy darter extant stream.
IMPACT
JA1343
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Exhibit G
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
0013509
From: Douglas, Barbara <[email protected]>
Sent: Wednesday, December 11, 2019 11:44 AM
To: Hoskin, Sumalee <[email protected]>; Richard, Jordan C <[email protected]>;
Lennon, Tiernan M <[email protected]>; Schulz, Cindy <[email protected]>
Subject: Fwd: effects of pipeline crossings on aquatics
FYI - I sent this out a while back when ACP first started but thought I might send again as it
might be helpful. I wrote this for the NiSource BO related to diamond darter but it may be
relevant for ACP or MVP re: aquatics/fish effects. Although I wasn't able to come up with a
standard distance downstream that would be affected by crossings, the references that I cited
did include some good information on downstream monitoring and sediment transport and
may be helpful to review again - or could provide some ideas on monitoring methods that
could be included as RPMs.
Barb
---------- Forwarded message ---------
From: Douglas, Barbara <[email protected]>
Date: Wed, Oct 8, 2014 at 9:26 AM
Subject: effects of pipeline crossings
To: Tamara Lewis <[email protected]>, Tiernan Lennon <[email protected]>,
Elizabeth Stout <[email protected]>
Cc: John Schmidt <[email protected]>
Hi all - The subject of how pipeline crossings affect streams has come up a number of times
recently and most companies say that crossings have only temporary impacts to the stream. I
thought it might be helpful to share the attached summary that I drafted for the diamond darter
during the NiSource consultation which addresses this issue. Although it is written specific to
fish the same types of effects can be expected for mussels (although their recovery time would
probably be longer since they have longer reproductive cycles and less ability to move).
Anyway, I hope this is helpful. Let me know if you have any questions.
Barb
--
Barbara Douglas
Senior Endangered Species Biologist
West Virginia Field Office
U.S. Fish and Wildlife Service
694 Beverly Pike
Elkins, WV 26241
Phone: 304-636-6586 x 19
Fax: 304-636-7824
JA1009
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
0013510
**Due to an imposed hiring freeze and the inability to back fill positions, we are significantly
delayed in our project review times and response times to phone calls and emails. Please be
patient; we will address projects in the order in which they are received.**
--
Barbara Douglas
Acting Project Leader/Senior Endangered Species Biologist
West Virginia Field Office
U.S. Fish and Wildlife Service
90 Vance Drive
Elkins, WV 26241
Phone: 304-636-6586 x 19
Fax: 304-636-7824
Please note the change in our mailing address.
JA1010
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
0013511
Pipeline stream crossings can affect fish habitat; food availability; and fish behavior, heath, reproduction
and survival. The most immediate effect of instream construction is the creation of short term pulses of
highly turbid water and total suspended sediments (TSS) downstream of construction (Levesque & Dube
2007, pp. 399-400). Although these pulses are usually of relatively short duration and there is typically
a rapid return to background conditions after activities cease, instream construction has been shown to
have considerable effects on stream substrates and benthic invert communities that persist after
construction has been completed (Levesque & Dube 2007, p. 396-397). Commonly documented effects
include substrate compaction and silt deposition within the direct impact area and downstream that fills
interstitial spaces in gravel substrates and reduces water flow through the substrate, this increases
substrate embeddedness and reduces habitat quality (Levesque & Dube 2007, pp. 396-397; Penkal &
Phillips 2011, pp. 6-7; Reid & Anderson 1999, p. 243). Construction also directly alters stream channels,
beds, and banks resulting in changes in cover, channel morphology, and sediment transport dynamics.
Streambank alterations can lead to increased water velocities, stream degradation, and migrations in
stream channel. Removal of vegetation from the banks can change temperature regimes, and increase
sediment and nutrient loads (Penkal & Phillips 2011, pp. 6-7).
These instream changes not only directly affect the suitability of fish habitat, they also affect the
availability and quality of fish forage altering the composition and reducing the density of benthic
invertebrate communities within and downstream of the construction area (Levesque & Dube 2007, pp.
396-399; Penkal & Phillips 2011, pp. 6-7; Reid & Anderson 1999, pp. 235, 244). Various studies have
documented adverse effects to the benthic community that have been apparent for between six months
and four years post-construction (Levesque & Dube 2007, pp. 399-400; Reid & Anderson 1999, pp. 235,
244). Stream crossings have also been shown to affect fish physiology, survival, growth, and
reproductive success (Levesque & Dube 2007, p. 399). Studies have found decreased abundance of fish
downstream of crossings, as well as signs of physiological stress such as increased oxygen consumption
and loss of equilibrium in remaining fish downstream of crossings (Levesque & Dube 2007, pp. 399-401;
Reid & Anderson 1999, pp. 244-245). Increased sediment deposition and substrate compaction from
pipeline crossings can degrade spawning habitat, result in the production of fewer and smaller fish eggs,
impair egg and larvae development, limit food availability for young-of-year fish, and increase stress and
reduce disease resistance of fish, (Levesque & Dube 2007, pp. 401-402; Reid & Anderson 1999, pp. 244-
245).
The duration and severity of these effects depends on factors such as the duration of disturbance, the
length of stream segment directly impacted by construction, and whether there were repeated
disturbances (Yount & Niemi 1999, p. 557). Most studies documented recovery of the affected stream
reach within one to three years after construction (Reid & Anderson 1999, p. 247; Yount & Niemi 1999,
pp. 557-558, 562). However caution should be used when interpreting results of short-term studies.
Yount & Niemi (1999, p. 558) cite and example of one study that made a preliminary determination of
stream recovery within one year, but when the site was re-examined six years later, fish biomass, fish
populations, macroinvertabrate densities, and species composition were still changing. It was suspected
that shifts in sediment and nutrient inputs to the site as a result of construction in and around the
stream contributed to the long-term lack of recovery. In another study, alterations in channel
JA1011
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
0013512
morphology, such as increased channel width and reduced water depth, were evident two to four years
post-construction at sites that lacked an intact forest canopy (Reid & Anderson 1999, p. 243). There is
also the potential for cumulative effects. While a single crossing may have only short-term or minor
effects, multiple crossings or multiple sources of disturbance and sedimentation in a watershed can
have cumulative effects on fish survival and reproduction that exceed the recovery capacity of the river,
resulting in permanent detrimental effects (Levesque & Dube 2007, pp. 406-407). Whether or how
quickly a stream population recovers depends on factors such as the life history characteristics of the
species, and the availability of unaffected populations upstream and downstream as a source of
organisms for recolonization (Yount & Niemi 1999, p. 547). Species such as the diamond darter that are
particularly susceptible to the effects of sedimentation and substrate embeddedness , and that have
limited distribution and population numbers are likely to be more severely affected by instream
disturbances than other more common and resilient species.
LITERATURE CITED
Levesque, L. M. and M. G. Dube. 2007. Review of the effects of in-stream pipeline crossing
construction on aquatic ecosystems and examination of Canadian methodologies for impact
assessment. Environmental Monitoring and Assessment 132:395-409.
Penkal, R. F. and G. R. Phillips. 2011. Construction and Operation of Oil and Gas Pipelines. Fisheries
9(3): 6-8.
Reid, S. M. and P. G. Anderson. 1999. Effects of Sediment Released During Open-Cut Pipeline Water
Crossings. Canadian Water Resources Journal 24(3):235-251.
Yount, J. D. and G. J. Niemi. 1990. Recovery of Lotic Communities and Ecosystems from Disturbance –
A Narrative Review of Case Studies. Environmental Management 14(5): 547-569.
JA1012
Document Accession #: 20210513-5107 Filed Date: 05/13/2021
Document Content(s)
MVP ESA Notice Letter with Exhibits A-G_5-13-21 (3).PDF...................1