Method Statement For Clearing and Grubbing (For Review) 12-7-2020
Method Statement For Clearing and Grubbing (For Review) 12-7-2020
Method Statement For Clearing and Grubbing (For Review) 12-7-2020
CP N-05 : Building and Civil Engineering Work for Depot Building Including
Related Infrastructure and Track Work Ballast (Contract No : NSCREX-03-N05)
Method Statement
for
Clearing and Grubbing Works
※ ISSUE TYPE: “Class 1” for Approval, “Class 2” for Review, “Class 3” for Information and Record
North-South Commuter Railway Extension Project
CP N-05 : Building and Civil Engineering Work for Depot Building Including
Related Infrastructure and Track Work Ballast (Contract No : NSCREX-03-N05)
REVISION LOG
Date Revised Detail
Rev. (dd/mm/yyyy
) Item Page Article Description
INDEX
1. Introduction................................................................................................................................................4
North-South Commuter Railway Extension Project
CP N-05 : Building and Civil Engineering Work for Depot Building Including
Related Infrastructure and Track Work Ballast (Contract No : NSCREX-03-N05)
2. Definition...........................................................................................................................5
3. Scope of Work..................................................................................................................5
5. Field Works......................................................................................................................11
5.1. Personnel...........................................................................................................11
5. Other Deliverable.................................................................................................................................12
North-South Commuter Railway Extension Project
CP N-05 : Building and Civil Engineering Work for Depot Building Including
Related Infrastructure and Track Work Ballast (Contract No : NSCREX-03-N05)
1. Introduction
- The Purpose of this procedure is to outline the Clearing and Grubbing. The
detailed guide will provide the clear steps undertaken to complete the process
of the clearing and grubbing activity in a safe, systematic and efficient manner
in compliance to the statutory and environmental requirements.
-4-
North-South Commuter Railway Extension Project
CP N-05 : Building and Civil Engineering Work for Depot Building Including
Related Infrastructure and Track Work Ballast (Contract No : NSCREX-03-N05)
2. Definition
- The Engineer: GCR Consortium
3. Scope of Work
The works in this section shall consist of:
1) Clearing, grubbing, disposing all vegetation and debris within the limits
except such objects that are designated to remain in place or are to be
removed in consonance with other provisions of MCRP CP N-05 Specification.
-5-
North-South Commuter Railway Extension Project
CP N-05 : Building and Civil Engineering Work for Depot Building Including
Related Infrastructure and Track Work Ballast (Contract No : NSCREX-03-N05)
Procedure Status
-6-
North-South Commuter Railway Extension Project
CP N-05 : Building and Civil Engineering Work for Depot Building Including
Related Infrastructure and Track Work Ballast (Contract No : NSCREX-03-N05)
- Cutting and disposal of Marked trees, which are 15cm diameter and above will
be the responsibility of DENR. Roots and small branches are excluded and
shall be the responsibility of the Contractor for hauling and disposal in a
designated and approved location by the Engineer.
- Unmarked Trees, which are less than 15cm in diameter will be cut to smaller
length for ease in hauling and disposal.
- Cavities left from structure removal shall be backfilled to the level of the
surrounding ground and, if within the area of construction, shall be compacted
to meet the requirements of the contract documents for embankment.
- All personnel entering the project site shall have received a site safety
induction.
- Access to site shall be studied and proposed shall be submitted to the Engineer
-7-
North-South Commuter Railway Extension Project
CP N-05 : Building and Civil Engineering Work for Depot Building Including
Related Infrastructure and Track Work Ballast (Contract No : NSCREX-03-N05)
- Area shall be divided into zones based on the priority as per construction
schedule.
- Temporary access road shall be developed for equipment and other vehicles.
- All surface objects and all stumps, roots and other protruding obstructions, not
designated to remain, shall be cleared and/or grubbed, including mowed as
-8-
North-South Commuter Railway Extension Project
CP N-05 : Building and Civil Engineering Work for Depot Building Including
Related Infrastructure and Track Work Ballast (Contract No : NSCREX-03-N05)
2) Grubbing of pits, channel changes and ditches will be required only to the
depth necessitated by the proposed excavation within such areas.
3) In areas covered by cogon, wild grass and other vegetations, top soil shall
be cut to a maximum depth of 150mm below the original ground surface or
as designated by the Engineer, and disposed outside the clearing and
grubbing limits as indicated in the Drawings or directed by the Engineer.
- Burying shall be done in layers. Each layer shall be covered or mixed with earth
material by the land-fill method to fill all voids. The top layer of material buried
shall be covered with at least 300mm of earth or other approved material and
shall be graded, shaped and compacted to present a pleasing appearance.
- If the disposal location is off the project, the Contractor shall make all
necessary arrangements with property owners in writing for obtaining suitable
disposal locations which are outside the limits of view from the project. The
disposal areas shall be seeded, fertilized and mulched at the Contractor’s
-9-
North-South Commuter Railway Extension Project
CP N-05 : Building and Civil Engineering Work for Depot Building Including
Related Infrastructure and Track Work Ballast (Contract No : NSCREX-03-N05)
expense.
-10-
North-South Commuter Railway Extension Project
CP N-05 : Building and Civil Engineering Work for Depot Building Including
Related Infrastructure and Track Work Ballast (Contract No : NSCREX-03-N05)
5.1. Personnel
Project Manager
The Project Manager shall be responsible for the overall direction, monitoring,
coordination and control of all the construction activities and related to the site
clearance works.
Construction Manager
The Civil Manager shall be responsible for the overall implementation and
monitoring of all activities involved in the site clearance works.
Site Engineer
The Site Engineer is responsible for coordination and supervision of technical
aspects of survey work including solving technical issues providing advice,
management and preparing reports.
HSE Manager
The HSE Manager shall review the safe work as planned work permit prior to
start of the work and must be implemented and observed during the site
clearance works.
Surveyor
The Surveyor shall make exact measurements and determine property
boundaries. Provide data relevant to the shape, contour, gravitation, location,
elevation and dimension of land or land features on or near the earth’s surface
for engineering, map making land evaluation, construction and other purposes.
-11-
North-South Commuter Railway Extension Project
CP N-05 : Building and Civil Engineering Work for Depot Building Including
Related Infrastructure and Track Work Ballast (Contract No : NSCREX-03-N05)
6. Other Deliverable
Contractor shall submit to engineer following reports during work period.
• Daily activity report (by E-mail)
• Daily manpower & equipment mobilization reports (by E-mail)
• Regular progress report during the execution of work (by E-mail)
-12-
North-South Commuter Railway Extension Project
CP N-05 : Building and Civil Engineering Work for Depot Building Including
Related Infrastructure and Track Work Ballast (Contract No : NSCREX-03-N05)
TASK: R - Routine Activities, NR - Non-routine Activities, E - Emergency Activities | RISK TYPE (RT): S - Safety Risk, H - Health Risk, E - Environmental Impact | RISK
RATING (RR) = S x L
Monitoring
Responsibili
Item Task Activity RT Hazard / Aspect Risk / Impact Control Measures Responsibil
ty
ity
• Awareness/orientation of employees on present
Lack of knowledge hazards/aspects and risks/impacts
HSE
or understanding • HSE Orientation/briefing on site specific activities HSE/ Supervis Operations
1 R Awareness/ SHE
about HSE
Serious injuries to fatality
or Head
Briefing • HSE briefing prior to travel and start of Survey
requirements
-13-
North-South Commuter Railway Extension Project
CP N-05 : Building and Civil Engineering Work for Depot Building Including
Related Infrastructure and Track Work Ballast (Contract No : NSCREX-03-N05)
-14-
North-South Commuter Railway Extension Project
CP N-05 : Building and Civil Engineering Work for Depot Building Including
Related Infrastructure and Track Work Ballast (Contract No : NSCREX-03-N05)
-15-
North-South Commuter Railway Extension Project
CP N-05 : Building and Civil Engineering Work for Depot Building Including
Related Infrastructure and Track Work Ballast (Contract No : NSCREX-03-N05)
POSCO E&C
- Mr. Ariel Sun
Sr. Earthwork Engr.
09287841191
Know the emergency contact numbers - Mr. Jin Gon Lee
How an emergency Designate trained and certified First aider & Emergency HSE Manager
rescue will be executed? Safety officer Contact
-16-
North-South Commuter Railway Extension Project
CP N-05 : Building and Civil Engineering Work for Depot Building Including
Related Infrastructure and Track Work Ballast (Contract No : NSCREX-03-N05)
-17-