Analysis of PWD Schedule of Rates 2018 I
Analysis of PWD Schedule of Rates 2018 I
Analysis of PWD Schedule of Rates 2018 I
Analysis of PW 2
SL Items Rate Unit
22 Helper to diesel hammer mounted rig oTk. 390.00 per day
23 Rig operator including site allowances fTk. 600.00 per day
24 Assistant laboratory technician Tk. 800.00 per day
25 Laboratory technician (Diploma in enggTk. ### per day
26 Laboratory engineer (minimum BSc in rTk. ### per day
27 Ghorami Tk. 500.00 per day
28 Sweeper for ODD JOB Tk. 800.00 per use
29 Tube-well mistry Tk. 500.00 per day
30 Tube-well head mistry Tk. 600.00 per day
31 Surveyor (10yrs Exp / diploma EngineerTk. ### per day
32 Helper to surveyor Tk. 800.00 per day
C2 EQUIPMENT, TOOLS & PLANTS, VEHICLE, SCAFFOLDING ETC.
33 Scaffolding Tk. 9.00 per sft
34 Carrying charge of earth by 5-ton capacTk. ### per trip
35 Carrying charge of earth by 5-ton capacTk. ### per trip
36 Carrying charge of earth by 5-ton capaciTk. 950.00 per trip
area
Carrying charge of earth by 5-ton capacity truck in all district except Dhaka/ Chittagong/
37 Rajshahi / Barisal / Khulna and NarayanTk. 800.00 per trip
38 Carriage of earth by any means for sit Tk. 7.50 cft
Carriage of earth by any means for site development in Narayanganj / Chittagong / Sylhet
39 city Tk. 6.00 cft
40 Carriage of earth by any means for siteTk. 5.50 cft
41 Carriage of earth by any means for siteTk. 4.50 cft
Chittagong, and Narayangonj city
42 5-ton capacity truck-fare in Dhaka city Tk. ### per trip
43 Hire charge of concrete mixer machineTk. ### per day
44 Hire charge of concrete vibrator Tk. 600.00 per day
45 Hire charge of water pump for concretiTk. 500.00 per day
46 Hire charge of diesel operated 1/4 cus Tk. 600.00 per day
Analysis of PW 3
SL Items Rate Unit
47 Hire charge of electricity operated 1 Tk. 800.00 per day
48 Hire charge of 1 cusec capacity diesel Tk. ### per day
49 Fuel & lubricant for mixer machine, vibTk. ### per day
50 Hire charge of mosaic cutting machineTk. 400.00 per day
51 Hire charge of marble cutting and shapiTk. 400.00 per day
52 Hire charge of marble polishing machinTk. 550.00 per day
53 Hire charge of marble cutting disk Tk. 400.00 per day
54 Hire charge of electric grinding machinTk. 260.00 per day
55 Hire charge of cast in situ pile boring Tk. ### per day
56 Hire charge of pre-cast pile driving co Tk. ### per day
57 Hire charge of pre-cast micro pile driv Tk. ### per day
58 Hire charge of load testing devices inclTk. ### per test
59 Hire charge of pile load testing devicesTk. ### per test
60 Hire charge of diesel hammer mountedTk. ### per day
61 Hire charge of auger boring complete rTk. ### per day
62 Hire charge of crane for auger boring Tk. ### per day
63 Hire charge of air compressor for augerTk. ### per day
64 Hire charge of concreting equipment foTk. ### per day
65 Hire charge of generator for auger boriTk. ### per day
66 Hire charge of excavator for auger boriTk. ### per day
67 Hire charge of desander for auger bori Tk. ### per day
68 Hire charge of mud silo for auger borinTk. ### per day
69 Hire charge of water bowser for auger Tk. ### per day
70 Hire charge of hydraulic static pile driv Tk. ### per day
71 Generator, fuel, lubricant for hydraulic sTk. ### per day
72 Hire charge of 3HP mud pump Tk. 600.00 per day
73 Hire charge of MS steel tank (6'-6" x 10'Tk. 350.00 per trip
74 Truck fare for carrying diesel hammer Tk. 15,000.00 per trip
Analysis of PW 4
SL Items Rate Unit
75 Hire charge of 8 - 12 ton road roller Tk. ### per day
76 Hire charge of vibratory (ride on) rolle Tk. ### per day
77 Hire charge of pneumatic multiple tiredTk.r ### per day
78 Hire charge of asphalt plant Tk. 15,000.00 per day
79 Hire charge of AC paver Tk. ### per day
80 Hire charge of dump truck/ tripping tru Tk. ### per day
81 Hire charge of distributor Tk. ### per day
82 Hire charge of water tanker (truck mouTk. ### per day
83 Hire-charge of chain dozer Tk. ### per day
84 Fuel & lubricants, spares, maintenance,Tk. ### per day
85 Hire charge of paint spray machine Tk. 650.00 per day
86 Hire charge of machine for cutting terraTk. 500.00 per % sft
87 Chisel for heavy duty power hammer (10 Tk. ### each
88 Hire charge of heavy duty chisel machiTk. 650.00 per day
89 Shuttering including prop for partial di Tk. 27.00 per sft
90 Hire charge of welding machine Tk. 700.00 per day
91 Hire charge of survey instrument (LevelTk. 950.00 per day
C3 WORK RATE EXCLUDING COST OF MATERIALS
92 Breaking of 50 mm down brick chips Tk. 850.00 per % cft
93 Breaking of 20 mm down brick chips Tk. 950.00 per % cft
94 Breaking of 12 mm (1/2") down brick chTk. ### per % cft
95 Breaking of 20 mm down stone chips Tk. ### per % cft
96 Breaking of 12 mm down stone chips Tk. ### per % cft
97 Placing and removing of shutter for fo Tk. 15.00 per sft
98 Making steel shutter for formwork Tk. 75.00 per sft
99 Making steel door-window frame and shTk. 65.00 per sft
100 Making fixed steel glazed frame Tk. 55.00 per sft
101 Making steel grill Tk. 45.00 per sft
Analysis of PW 6
SL Items Rate Unit
126 241 mm x 70 mm x 12.7 mm machine made Tk. 28,000.00 per % 0 nos
127 242 mm x 70 mm x 12.7 mm machine made Tk. 34,000.00 per % 0 nos
128 4.5'' x 4.5'' x 4.5''/ 112.5 mm x 112.5 Tk. 28,000.00 per % 0 nos
129 5.5'' x 5.5'' x 4'' / 137.5 mm x 137.5 Tk. 34,000.00 per % 0 nos
130 6" x 6" x 4" / 150 mm x 150 mm x 100 Tk. 37,000.00 per % 0 nos
131 8'' x 8'' x 4.25''/ 200 mm x 200 mm x Tk. 47,000.00 per % 0 nos
132 8'' x 4.75'' x 4''/ 200 mm x 118.75 mm Tk. 47,000.00 per % 0 nos
133 6" x 6" x 6" / 150 mm x 150 mm x 150 Tk. 37,000.00 per % 0 nos
134 9.5'' x 4.5'' x 2.75''/ 237.5 mm x 112 Tk. 37,000.00 per % 0 nos
135 190 mm x 190 mm size glass bricks Tk. 350.00 each
C6 CEMENT
136 Ordinary Portland Cement, BDS-EN - Tk. 415.00 per bag
I, 50 kg bag
Portland Composite Cement, (CEM-II/A - M 42.5N (42.5MPa) (6-20% constituents other
137 than clinker): 50 kg bag Tk. 395.00 per bag
138 White Cement Tk. 26.00 per kg
C7 STONE / BOULDER / MOSAIC CHIPS, BITUMEN / ADMIXTURE / MEMBRANE
139 Uncrushed boulder Tk. 16,000.00 per % cft
140 19 mm (3/4") down grade crushed stonTk. 19,500.00 per % cft
141 12 mm (1/2") down grade stone chips Tk. 16,500.00 per % cft
142 6 mm (1/4") down grade stone chips Tk. 14,000.00 per % cft
143 Stone shingles Tk. 12,000.00 per % cft
144 Stone dust (2.38 mm down grade) Tk. ### per % cft
145 Pea-gravel Tk. ### per % cft
146 Slaked lime Tk. 20.00 per kg
147 Surki from 1st class brick Tk. 70.00 per cft
148 Pakistan origin (onix) mosaic chips Tk. 20.00 per kg
149 Indian origin (deradun) mosaic chips Tk. 18.00 per kg
150 Pumice stone for finishing mosaic workTk. 175.00 each
Analysis of PW 7
SL Items Rate Unit
151 Minar stone for finishing mosaic work Tk. 420.00 each
152 Colour pigment Tk. 70.00 per lbs
153 20 mm x 50 mm glass strip Tk. 10.00 per foot
154 60/70 grade bitumen for road work Tk. 52,000.00 per M. ton
155 Water-proofing PVC membrane Tk. 600.00 per sqm
156 Primer for laying PVC membrane on waTk. 600.00 per litre
157 Water reducing admixture in concrete: Tk. 150.00 per litre
158 Retarding admixture in concrete: Type Tk. 130.00 per litre
159 Accelerating admixture in concrete: Ty Tk. 115.00 per litre
160 Water reducing and retarding admixtureTk. 220.00 per litre
161 Water reducing and accelerating admixtTk. 170.00 per litre
162 Water reducing high range admixture inTk. 230.00 per litre
163 Water reducing high range retarding adTk. 160.00 per litre
164 Micro fibre for concrete Tk. 750.00 per kg
165 Shutter releasing agent / form oil Tk. 150.00 per litre
166 Polymer based curing compound Tk. 220.00 per litre
167 Epoxy bonding agent Tk. ### per litre
168 Salt guard coating Tk. 700.00 per litre
C8 EARTH/SAND
169 Royalty of earth Tk. ### per % 0 cft
170 Royalty of sand Tk. ### per % 0 cft
171 Royalty of turf Tk. 15.00 per % sft
172 Sand (F.M. 0.8) Tk. 900.00 per % cft
173 Sand (F.M. 1.2) Tk. ### per % cft
174 Sand (F.M. 2.2) Tk. ### per % cft
C9 TIMBER / BOARD / TIMBER PRODUCT
175 Garjan/Jam/local Sal Tk. ### per cft
176 Mehgani Tk. ### per cft
Analysis of PW 9
SL Items Rate Unit
203 M.S. plain bar and F.I. bar (non-structuTk. 55,000.00 per M. ton
204 Solid square bar Tk. 55,000.00 per M. ton
205 0.45 mm thick C.I. sheet: Tk. 79,500.00 per M. ton
206 0.45 mm thick coloured C.I. sheet: Tk. 81,000.00 per M. ton
207 0.27 mm thick 6'-0" x 18" ridging: Tk. 350.00 per pc
208 0.27 mm thick 6'-0" x 18" coloured ridgiTk. 400.00 per pc
209 Anchor bolt fiting charge Tk. 25.00 per Kg
210 Galvanized anchor bolt of varying dia Tk.120,000.00 per M.Ton
211 MS plate of grade 345 Mpa Tk. 75,000.00 per M.Ton
212 MS plate of grade 275 Mpa Tk. 70,000.00 per M.Ton
213 Hot rolled W, I, S, T shape sections Tk. 80,000.00 per M.Ton
214 MS tube / angle Tk. 70,000.00 per M.Ton
Fabrication charge for column, beam, rafter using MS plates including the cost of
215 electricity, LP gas, machinares etc. Tk. 20,000.00 per M.Ton
216 Fabrication charge for column, beam, raTk. 12,000.00 per M.Ton
electricity, LP gas, machinares etc.
217 MS sheet for purlin of any thickness Tk. 75,000.00 per M.Ton
218 GP sheet for purlin of any thickness Tk. 98,000.00 per M.Ton
219 0.70 mm thick GP decking sheet of Gr Tk.125,000.00 per M.Ton
220 0.47mm colour profile sheet Tk.155,000.00 per M.Ton
221 Fastner / roof, wall screw Tk. 4.00 per pcs
222 Decking screw Tk. 8.00 per pcs
223 Galvanized nut bolt of varying dia AS Tk. 250.00 per Kg
224 Galvanized nut bolt of varying dia AS Tk. 205.00 per Kg
225 Fabrication charge for roof / wall sheet Tk. ### per M.Ton
226 8 mm thick double bubble insulation Tk. 175.00 per sqm
227 Fabrication charge for decking panel Tk. ### per M.Ton
228 Fabrication charge for Purlin Tk. ### per M.Ton
229 Erection charge for built-up or hot rolle Tk. ### per M.Ton
Analysis of PW 10
SL Items Rate Unit
230 Erection charge for decking panel Tk. 8.00 per Kg
231 Erection charge for purlin Tk. 4.00 per Kg
232 Erection charge for roof/wall sheet inc Tk. 10.00 per Kg
233 Fitting and fxing of dubble bubble insulTk. 50.00 sqm
234 Anti corrosive epoxy paint Tk. 950.00 per litre
235 Anti corrosive red oxide paint Tk. 180.00 per litre
236 Thinner for anti corrosive red oxide paiTk. 120.00 per litre
237 Labour charge for redoxide painting Tk. 600.00 per M.Ton
238 Labour charge for enamel painting Tk. ### per M.Ton
239 Labour charge for application of non-shTk. 50.00 per cft
240 16 mm steel wire Tk. 120.00 per meter
241 16 mm I bolt with heal side washer an Tk. 175.00 per set
242 12 mm I bolt with heal side washer an Tk. 150.00 per set
243 Shear stud of variable dia of grade 27 Tk. 120.00 per Kg
244 Making thread for sag rod Tk. 12.00 per Kg
245 Nut with washer for 12 mm dia sag rodTk. 150.00 per Kg
246 cost of non-shrink grout per bag (25 kgTk. ### per bag
247 Labour charge for wire bracing Tk. 10.00 per foot
248 Local carriage, load-unload Tk. ### per M.Ton
C11 TILES / MARBLE STONE / GRANITE STONE
249 18 mm thick marble stone, Indian standTk. 450.00 per sft
equivalent)
16 mm thick marble stone, Indian standard quality (Bansowara/ Indian grey/ Indian pink or
250 equivalent) Tk. 400.00 per sft
12 mm thick marble stone, Indian standard quality (Bansowara/ Indian grey/ Indian pink or
251 Tk. 370.00 per sft
equivalent)
252 12 mm thick marble stone, Indian superi Tk. 400.00 per sft
253 18 mm thick marble stone, Indian superi Tk. 500.00 per sft
254 16 mm thick marble stone, Indian superi Tk. 420.00 per sft
Analysis of PW 12
SL Items Rate Unit
283 Mirror polish 1200 mm x 1200 mm floorTk. 500.00 per sft
284 Matt or rustic floor tiles of size 600 Tk. 170.00 per sft
(China/equivalent) made
foreign (China/ equivalent) glazed wall tiles of size 300 mm x 600 mm with mathcing floor
285 tiles, décor and border (if any) Tk. 150.00 per sft
286 foreign (China/equivalent) rustic wall Tk. 150.00 per sft
tiles, décor and border (if any)
287 20 mm to 25 mm thick machine made cTk. 130.00 per sft
288 Roof tiles of size 100 mm x 200 mm orTk. 14,000.00 per % sft
Roof tiles of size 125 mm x 170 mm to 200 mm x 200 mm or equivalent (red colour)
289 (country made) Tk. 17,575.00 per % sft
290 Roof tiles of size 160 mm x 268 mm orTk. 15,600.00 per % sft
291 Roof tiles of size 225 mm x 300 mm orTk. 16,200.00 per % sft
292 Flower shaped roof tiles of size 175 m Tk. 22,420.00 per % sft
made)
293 Roof tiles of size 100 mm x 200 mm orTk. 14,500.00 per % sft
294 Roof tiles of size 125 mm x 170 mm t Tk. 18,500.00 per % sft
(country made)
295 Roof tiles of size 225 mm x 300 mm orTk.l 18,000.00 per % sft
296 Flower shaped roof tiles of size 175 m Tk. 23,600.00 per % sft
made)
Flower shaped roof tiles of size 175 mm x 175 mm or equivalent (grey or black colour)
297 (country made) Tk. 26,200.00 per % sft
298 Pasting tiles adhesive Tk. 21.00 per kg
299 Tiles grout / joint filler Tk. 81.00 per kg
300 18 mm thick granite stone (Indian/equivTk. 550.00 per sft
301 18 mm thick granite stone (Italian/equivTk. 650.00 per sft
302 12 mm thick granite stone(Indian/equivTk. 400.00 per sft
303 12 mm thick granite stone(Italian/equivTk. 500.00 per sft
304 Acid stone Tk. 450.00 each
305 Water Proofing Paper (12 Size) Tk. 22.00 each
306 Water Proofing Paper (320 Size) Tk. 24.00 each
Analysis of PW 13
SL Items Rate Unit
C12 PROPS / PIPES / I-SECTION/BOX CHANNEL FOR CONCRETING WORK
307 Bamboo prop including top supports Tk. 120.00 each
308 Salballah prop including top supports Tk. ### each
309 50 mm/2" dia M.S. pipe Tk. 140.00 per foot
310 38 mm/1.5" dia M.S. pipe Tk. 115.00 per foot
311 50 mm/2" dia G.I. pipe Tk. 180.00 per foot
312 38 mm/1.5" dia G.I. pipe Tk. 148.00 per foot
313 19 mm/3/4" dia G.I. pipe Tk. 70.00 per foot
314 13 mm/1/2" dia G.I. pipe Tk. 52.00 per foot
315 Adjustable mechanism including top anTk. 600.00 per set
316 I-section joist to support inclined prop Tk. 400.00 per foot
317 4" x 2" M.S. box channel with 1/8" thic Tk. 350.00 per foot
318 Steel prop with adjustable mechanism iTk. ### per set
319 Turn-buckle including tie rod Tk. 450.00 per set
C13 PAINT / POLISHING
320 Standard exterior emulsion paint Tk. 279.00 per litre
321 Premium exterior emulsion paint Tk. 397.00 per litre
322 Sealer for exterior emulsion paint Tk. 174.00 per litre
323 Silicon based paint/coating Tk. 280.00 per litre
324 Ready-mix putty ( exterior) Tk. 50.00 per litre
325 Ready-mix putty ( interior) Tk. 52.00 per kg
326 Thinner for oil-based paint (turpentine) Tk. 120.00 per kg
327 Synthetic polyvinyl (S.P.) distemper Tk. 80.00 per litre
328 Synthetic polyvinyl (S.P.) distemper priTk. 149.00 per litre
329 Acrylic plastic emulsion paint (plastic/mTk. 202.00 per litre
330 Acrylic plastic emulsion paint (silky fin Tk. 391.00 per litre
331 Acrylic plastic emulsion paint (odorlessTk. 500.00 per litre
332 Sealer for acrylic plastic emulsion paintTk. 149.00 per litre
Analysis of PW 14
SL Items Rate Unit
333 Standard synthetic enamel paint Tk. 200.00 per litre
334 Premium synthetic enamel paint Tk. 270.00 per litre
335 Oil based anticorrosive primer Tk. 175.00 per litre
336 Thinner for oil-based paint (turpentine) Tk. 120.00 per litre
337 Chlorinated rubber paint Tk. 588.00 per litre
338 Chlorinated rubber sealer Tk. 523.00 per litre
339 Chlorinated rubber paint thinner Tk. 212.00 per litre
340 Epoxy enamel primer including base, cuTk. 500.00 per litre
341 Epoxy enamel paint including base, curTk. 523.00 per litre
342 Textured coating including sealer, text Tk. 250.00 per litre
343 Wood varnishing: Yacht ( alkyd based)Tk. 250.00 per litre
344 Wood varnishing: Egg-shell ( alkyd basTk. 250.00 per litre
345 Wood varnishing: Matt ( alkyd based) Tk. 250.00 per litre
346 Thinner for alkyd based wood varnishi Tk. 130.00 per litre
347 Self leveling epoxy coating (4 mm thic Tk. 150.00 per sft
348 Oxalic acid Tk. 95.00 per litre
349 Wax for polishing Tk. 299.00 per kg
350 Design Paint including base coat , desiTk. 390.00 per litre
French-Polishing
351 French powder Tk. 46.00 per kg
352 Spirit Tk. 130.00 per Ib
353 Gala Tk. 780.00 per kg
354 Karpa Tk. 550.00 per kg
355 Sand paper Tk. 14.00 each
356 Putty Tk. 90.00 per kg
357 Markin cloth Tk. 10.00 per yard
358 Cotton Tk. 90.00 per lbs
Analysis of PW 18
SL Items Rate Unit
II. Accessories for aluminium door-window works
425 Swing door clouser Tk. ### set
426 Swing door lock Tk. 625.00 set
427 Swing door Mohiar Tk. 5.00 foot
428 Fixed Neoprene Tk. 2.60 foot
429 Flush bolt Tk. 320.00 set
430 Sliding door lock Tk. 200.00 set
431 Sliding door /window wheel Tk. 70.00 no
432 Sliding door /window Mohiar Tk. 1.30 foot
433 Sliding Neoprene Tk. 2.70 foot
434 Sealant Tk. 3.00 gm
435 Sliding window key lock Tk. 80.00 set
436 Bolts and Screws including sealants Tk. 70.00 LS
437 4-bar hinge Tk. 700.00 no
438 Casement handle Tk. 260.00 no
439 Rivet Tk. 5.00 no
440 S.S. screw Tk. 2.50 no
441 Screws Tk. 1.00 no
442 5 mm tinted glass Tk. 82.00 sft
443 5 mm clear glass Tk. 66.00 sft
444 Rubber gasket Tk. 1.90 sft
445 Aluminium sheet Tk. 382.00 Kg.
446 Protector bit (Single) Tk. 19.33 foot
447 Protector bit (Double) Tk. 26.76 foot
448 Silicon (1 piece 300 mm) Tk. 300.00 each
449 Steel rowel bolt Tk. 40.00 each
450 Rivets (Big) Tk. 2.00 each
451 Norton Tap Tk. 27.00 each
Analysis of PW 19
SL Items Rate Unit
452 Masking tape Tk. 25.00 each
453 Structural sealant Tk. 12.00 each
454 Casement 4-bar huge Tk. 500.00 each
455 Casement handle Tk. 245.00 each
456 Sealant Gum Tk. 365.00 each
457 Arm lock Tk. 400.00 each
458 M.S. angle Tk. 108.00 each
459 Curtain wall jointer Tk. 313.00 each
460 Dow coling silicon gum Tk. 620.00 pcs
461 Fin connector Tk. ### each
462 Fin hanger Tk. ### each
463 SS U Channel Tk. 200.00 foot
464 SS Spider Set Tk. ### each
465 6 mm thick PVC board of size 600x60 Tk. 40.00 per sft
466 0.6 mm thick plain aluminium board o Tk. 95.00 per sft
467 0.6 mm thick perforated aluminium bo Tk. 75.00 per sft
468 6 mm thick Fiber cement board Tk. 80.00 per sft
469 38x12.5x0.5 mm U bar/ Furring channeTk. 20.00 per foot
470 19 mm x 0.5 mm G.I. angle Tk. 22.00 per foot
471 12 mm thick solid PVC board Tk. 100.00 per sft
472 Wall paper Tk. 60.00 per sft
III. Vertical Venetian Blinds
473 Head rail, Aluminium Tk. 9.00 per foot
474 Rod tilt / Hexagon Aluminium Rod Tk. 8.50 per foot
475 End cap set / End closure set Tk. 75.00 per set
476 Weight plate / Weight bar Tk. 11.00 each
477 Link Chain / Weight Chain Tk. 11.00 per foot
478 Ball Chain / Plastic Chain Tk. 10.00 per foot
Analysis of PW 20
SL Items Rate Unit
479 Plastic Washer / Fabric upper clip Tk. 2.75 each
480 Spacer (Link) / Plastic Runner Spring Tk. 9.00 each
481 Handling Cord /Nylon Cord Tk. 3.00 per foot
482 Thread bar Tk. 10.00 each
483 Angle Clip Tk. 8.00 each
484 Plastic Runner Tk. 4.00 each
485 Glass fiber Fabrics (special quality, fo Tk. 100.00 per sft
486 Angle Tk. 5.00 each
487 Fitting-fixing charge Tk. 4.00 per sft
IV. Horizontal Venetian Blind/Horizontal Zebra Blind
488 Head rail Tk. 8.50 per foot
489 Bottom rail Tk. 5.00 per foot
490 Aluminium Strips (special quality, fore Tk. 80.00 per foot
491 synthetic net Tk. 60.00 per foot
492 polyester fabrics Tk. 70.00 per foot
493 vinyl or PVC coated strip Tk. 90.00 per foot
494 Rod till / hexagon aluminium Rod Tk. 7.00 per foot
495 Gear box /tilter Tk. 10.00 each
496 Support and cord drum Tk. 6.00 each
497 Cord lock Tk. 6.00 each
498 Stop ring Tk. 8.00 each
499 Tassel Tk. 5.00 ach
500 Ladder cord Tk. 4.00 per foot
501 Stick / tilt wand Tk. 8.00 each
502 Bracket/metal intermediate bracket Tk. 7.50 each
503 Bottom cap / end cap for head rail Tk. 10.00 each
504 Tape holder Tk. 6.00 each
505 Steel washer Tk. 8.00 each
Analysis of PW 21
SL Items Rate Unit
506 Head cap set Tk. 12.00 each
507 Handling cord Tk. 5.00 per foot
508 Labour cost Tk. 3.50 per sft
V. Blackout/ Translucent roller Blind
509 Head control tube, 38mm aluminium tuTk. 20.00 per foot
510 one idler aluminium rod Tk. 15.00 per foot
511 End cap set/end closure set Tk. 50.00 Per set
512 Weight plate/weight bar Tk. 11.00 each
513 Link chain/weight chain Tk. 11.00 per foot
514 Ball chain/plastic chain Tk. 10.00 per foot
515 Plastic washer/fabricupper clip Tk. 2.75 each
516 mounting brackets cover Tk. 12.00 per foot
517 Handling cord/nylon cord Tk. 3.00 per foot
518 Thread bar Tk. 10.00 each
519 Angle clip Tk. 8.00 each
520 Plastic runner Tk. 4.00 each
521 PVC/ vinyl laminated fiberglass fabrics Tk. 90.00 per sft
522 Angle Tk. 5.00 each
523 clip in brackets with cover Tk. 10.00 per set
524 38mm clutch Tk. 20.00 each
525 piano wire flat springs Tk. 15.00 per foot
526 elastic spindle Tk. 25.00 each
527 38mm thick rope chain bead clutch Tk. 70.00 per set
528 bead chain Tk. 20.00 per foot
529 25mm thick bottom aluminum tube withTk. 15.00 per foot
530 lifting plastic kit Tk. 10.00 rach
531 clutch connectors Tk. 80.00 each
532 mounting profile for outside mount of roTk. 30.00 per foot
Analysis of PW 22
SL Items Rate Unit
533 bottom bar end cap Tk. 15.00 each
534 pull with tassel Tk. 50.00 each
535 Fitting-fixing charge Tk. 4.00 per sft
C15 PVC
I. uPVC Pipe for Electric Conduit
536 Wall grade 3/4" / 19 mm dia pipe, 1.2 Tk. 5.00 per foot
537 Wall grade 1"/ 25 mm dia pipe, 1.2 mmTk. 7.00 per foot
538 Roof grade 3/4"/19 mm dia pipe, 1.5 mTk. 5.50 per foot
539 Roof grade 1"/ 25 mm dia pipe, 1.5 mmTk. 8.50 per foot
540 Roof grade 1.25"/ 32 mm dia pipe, 1.5 Tk. 11.00 per foot
II. Fittings for uPVC Pipe for Electric Conduit
541 3/4"/19 mm Socket Tk. 45.00 per dzn
542 1" / 25 mm Socket Tk. 60.00 per dzn
543 1.25"/ 32 mm Socket Tk. 65.00 per dzn
544 3/4" / 19 mm Plain bend Tk. 75.00 per dzn
545 1"/ 25 mm Plain bend Tk. 80.00 per dzn
546 1.25"/ 32 mm Plain bend Tk. 120.00 per dzn
547 3/4"/ 19 mm Circular box single Tk. 96.00 per dzn
548 3/4" / 19 mm Circular box double Tk. 96.00 per dzn
549 1"/ 25 mm Circular box single Tk. 108.00 per dzn
550 1"/ 25 mm Circular box double Tk. 108.00 per dzn
551 Solvent cement for jointing Tk. 2.00 per grm
III. Plastic Door, Windows & Partition
552 PVC door frame thickness min 2.5 mmTk. 107.00 per meter
553 G.I inner joint (76.2 mm x 38.1 mm) cl Tk. 12.00 each
554 G.I inner joint (72.2 mm x 76.2 mm) cl Tk. 13.00 each
555 G.I outer clamp Tk. 12.00 each
556 G.I. wall clamp (216 x 19 mm) Tk. 14.00 each
Analysis of PW 23
SL Items Rate Unit
557 Rivet ø 3.17 ø 3 x ↔12.17 mm Tk. 1.50 each
558 Garjan wood 25.4 x 22.22 mm Tk. 27.00 per meter
559 uPVC hollow section wall thickness 2. Tk. 880.00 per meter
560 uPVC side clip 2.5 mm Tk. 26.00 per meter
561 Screw 25.5 mm Tk. 3.00 each
562 Tower bolt Ø 9.38 x 152.4 mm Tk. 56.00 each
563 Plastic handle 146 mm long Tk. 53.00 each
564 Hinges 76.2 x 57.15 mm Tk. 48.00 each
565 Hasp bolt Ø 25 x ↔ 254 mm Tk. 190.00 each
566 Round lock normal (China/Korea/TaiwaTk. 550.00 each
567 Rod Ø 9.52 mm x 3 pcs Tk. 40.00 each
568 Nut with washer 6 pcs Tk. 12.00 each
569 Rowel plug Tk. 1.00 each
570 T-frame Tk. 130.00 per meter
571 L-frame Tk. 130.00 per meter
572 Hollow bit Tk. 60.00 per meter
573 Screw for hollow partition Tk. 2.00 each
574 T-inner joint clamp Tk. 9.00 each
575 L-inner joint clamp Tk. 14.00 each
576 Glass bit Tk. 60.00 per meter
577 Round rubber bit Tk. 20.00 per meter
578 Rubber bit Tk. 10.00 per meter
579 Adhesive Tk. 200.00 per kg
580 10mm glass for partition wall Tk. 300.00 per sqm
IV. Plastic Door, Windows & Partition
581 8 mm thick PVC sheet Tk. ### per pc
582 Partition frame (Profile) Tk. 60.00 per foot
583 4" New sash (Profile) Tk. 140.00 per foot
Analysis of PW 25
SL Items Rate Unit
612 Metal Handle Tk. 185.00 each
613 Cloth Tk. 10.00 per yrds
614 Rowl plug (10 Nos. per pack) Tk. 20.00 per pack
615 1" Aluminium main tee Tk. 27.00 per foot
616 1" Aluminium cross tee Tk. 23.00 per foot
617 1" Aluminium L-section Tk. 23.00 per foot
C16 GAS CONNECTION WORK
I. 50 PSI API 5L, Grade-B ERW M.S. Pipe
618 75 mm ND (88.90 mm OD) Tk. 312.94 per foot
619 50 mm ND (60.30 mm OD) Tk. 205.00 per foot
620 25 mm ND (33.40 mm OD) Tk. 100.00 per foot
621 20 mm ND (26.70 mm OD) Tk. 65.00 per foot
II. Consumable
622 4" x 400' Black tape Tk. ### per roll
623 2" x 200' Black tape Tk. ### per roll
624 Primer Tk. 315.00 per litre
III. Butt welded joints
625 75 mm ND (88.90 mm OD) Tk. 149.75 each
626 50 mm ND (60.30 mm OD) Tk. 127.26 each
627 25 mm ND (33.40 mm OD) Tk. 99.73 each
628 20 mm ND (26.70 mm OD) Tk. 85.32 each
IV. Fittings & accessories
629 50 x 50 x 50 mm N.D. Tee CD40 Tk. 231.55 each
630 50 x 50 x 25 mm N.D. Tee CD40 Tk. 258.30 each
631 25 x 25 x 25 mm N.D. Tee CD40 Tk. 146.76 each
632 50 mm x 90o Elbow Tk. 172.43 each
633 25 mm x 90o Elbow Tk. 52.77 each
634 50 mm x 45o Elbow Tk. 74.36 each
Analysis of PW 26
SL Items Rate Unit
635 50 x 25 mm reducer Tk. 82.44 each
636 20 mm plug/socket Tk. 260.00 each
637 50 x 20 mm saddle Tk. 199.17 each
638 50 mm dia end cap Tk. 64.26 each
639 25 mm dia end cap Tk. 40.39 each
640 50 x 50 mm equal tee Tk. ### each
641 25 x 25 x 25 mm service tee Tk. ### each
642 50 x 25 mm service tee Tk. ### each
643 50 mm insulating kits Tk. ### each
644 50 mm flange W/N 150 R/F Tk. 786.95 each
645 5/8" x 3" long nut bolt including washerTk. 74.18 each
646 Valve Pit (Titas Gas T&D Co. Ltd. desigTk. ### each
647 M.S. sheet cover supplied by Titas GasTk. ### each
648 Testing & purging Tk. 21.82 per meter
649 50 mm ND dia ball valve class 150 R.FTk. ### each
650 25 mm ND dia plug valve class 150 R.FTk. ### each
651 25 mm dia flange W/N 150 R.F. Tk. 385.83 each
652 50 mm dia flange W/N 150 R.F. Tk. 786.95 each
653 50 mm dia gasket Tk. 279.28 each
654 25 mm dia gasket (asbestos) Tk. 45.62 each
655 1/2" x 2.5" nut-bolt Tk. 33.75 each
656 3/4" / 19 mm dia G.I. pipe (NTL or eqv.Tk. 41.70 per foot
657 1/2" / 12 mm dia G.I. pipe (NTL or eqv.Tk. 32.00 per foot
658 12 x 6 mm gas stop cock Tk. 193.00 each
659 20 x 20 mm gas stop cock Tk. 308.56 each
C17 TERMITE TREATMENT
660 DURS BAN 20 EC Tk. 920.00 per litre
661 NEOCIDOL-60 Tk. 140.00 per % ml
Analysis of PW 27
SL Items Rate Unit
662 Kerosene / Diesel Tk. 68.00 per litre
C18 CONCRETE HOLLOW BLOCKS & PAVING STONE WORKS
663 70 mm non load bearing concrete holloTk. 24.00 each
664 Transportation 70 mm block Tk. 3.66 each
665 Mortar mix Tk. 281.08 per litre
666 90 mm non load bearing concrete holloTk. 36.00 each
667 Transportation 90 mm block Tk. 3.00 each
668 140 mm non load bearing concrete hollTk. 53.00 each
669 Transportation 140/190 mm block Tk. 7.87 each
670 140 mm load bearing concrete hollow bTk. 56.06 each
671 190 mm load bearing concrete hollow bTk. 60.00 each
672 150 mm concrete ceiling block Tk. 64.87 each
673 Transportation 150/200 mm ceiling blo Tk. 8.74 each
674 200 mm concrete ceiling block Tk. 94.01 each
675 External plaster mix Tk. 286.57 per litre
676 60 mm grey uniblock: 15 N/mm2 Tk. 14.00 each
677 60 mm coloured uniblock: 15 N/mm2 Tk. 18.00 each
678 Transportation 60/80 mm uniblock/RecTk. 2.06 each
679 60 mm grey uniblock: 49 N/mm2 Tk. 17.00 each
680 60 mm coloured uniblock: 49 N/mm2 Tk. 20.00 each
681 80 mm grey uniblock: 49 N/mm2 Tk. 22.00 each
682 80 mm coloured uniblock: 49 N/mm2 Tk. 28.00 each
683 Rectangular grey block Tk. 15.00 each
684 Rectangular coloured block Tk. 18.00 each
685 250 x 250 mm grey engraved CC tiles Tk. 46.66 per sft
686 250 x 250 mm coloured engraved CC tiTk. 56.51 per sft
687 Transportation of 250 mm x 250 mm tilTk. 1.90 per sft
688 Roof Engraved Tile Tk. 36.63 per sft
Analysis of PW 28
SL Items Rate Unit
689 Solid block (215 x 100 x 65) mm Tk. 14.00 each
690 Transportation Solid block (215 x 100 Tk. 1.64 each
691 200 mm x 92 mm x 37.5 mm grey solidTk. 13.00 each
692 Transportation solid cladding block Tk. 2.31 each
693 200 mm x 92 mm x 37.5 mm coloured so Tk. 15.00 each
694 400 mm x 92 mm x 50 mm grey split clTk. 16.61 each
695 Transportation split cladding Tk. 2.00 each
696 400 mm x 92 mm x 50 mm coloured spli Tk. 21.45 each
697 420 mm x 330 mm x 15 mm coloured fac Tk. 35.21 each
698 418 mm x 330 mm x 17 mm red colourTk. r 150.00 each
699 Transportation roof tiles Tk. 3.45 each
700 J-hook with nut and washer Tk. 10.35 each
701 418 mm x 330 mm x 17 mm oriental colo Tk. 42.56 each
702 418 mm x 330 mm x 17 mm antique redTk.c 49.05 each
703 418 mm x 330 mm x 17 mm green colour Tk. 53.36 each
704 600 mm x 300 mm x 100 mm kerb stonTk. 150.00 each
705 Transportation of kerb stone Tk. 31.19 each
706 100 mm non-load bearing concrete holTk. 30.68 each
707 Transportation of 100 mm hollow blockTk. 3.75 each
708 250 mm concrete ceiling block Tk. 94.45 each
709 Transportation 250 mm ceiling block Tk. 8.75 each
710 300 mm concrete ceiling block Tk. 114.76 each
711 Transportation of 300 mm ceiling blockTk. 13.23 each
712 100 mm concrete ceiling block Tk. 37.32 each
713 Transportation of 100 mm ceiling blockTk. 5.36 each
714 418 mm x 330 mm x 17 mm brown colour Tk. 49.45 each
715 418 mm x 330 mm x 17 mm Navy blueTk. ro 52.87 each
716 418 mm x 330 mm x 17 mm MahoganyTk. co 56.00 each
Analysis of PW 29
SL Items Rate Unit
717 418 mm x 330 mm x 17 mm Rust GoldTk. co 56.00 each
718 All type concrete ridge: red colour Tk. 150.00 each
719 60 mm gray trihex Tk. 20.00 each
720 60 mm colour trihex Tk. 30.00 each
721 400 mm x 200 mm x100 mm sand cemen Tk. 28.00 each
722 250 mm x 115 mm x 115 mm sand ceme Tk. 10.00 each
723 300 mm x 115 m x 115 mm size thermaTk. 22.00 each
724 240 mm x 115 mm x 70 mm size compr Tk. 7.00 each
725 300 mm x 115 mm x 70 mm size sand Tck. 11.00 each
C19 SANITARY AND WATER SUPPLY WORK
I. Misc. items
726 Water sealed heavy type 18" dia C.I. MTk. 900.00 each
727 Water sealed heavy type 24" dia C.I. MTk. ### each
728 RCC tees Tk. 425.00 each
729 CI brackets Tk. 115.00 per pair
730 Heavy type CI brackets Tk. 158.00 per pair
731 Nuts with washer Tk. 26.00 each
732 Clamp Tk. 50.00 each
733 50 mm screw & rowel plug Tk. 9.00 each
734 75 mm Screw, Rowel plug & Washer Tk. 13.00 each
735 Plastic clip Tk. 10.00 each
736 Solvent cement Tk. 0.70 per ml
737 Hem Tk. 30.00 per sqm
738 Scaffolding Tk. 3.00 per foot
739 Teflon Tk. 16.00 per pcs
740 Nipples with jum-nuts Tk. 60.00 each
741 PVC connection pipe Tk. 30.00 each
Analysis of PW 31
SL Items Rate Unit
Light Colour Ba530 x 430 x 210 mm, 12.5
768 kg Tk. 887.00 each
Cabinet Basin
Analysis of PW 34
SL Items Rate Unit
847 150 x 150 mm size stainless steel floorTk. 740.00 each
848 75 x 75 mm size stainless steel floor grTk. 195.00 each
849 62mm dia stainless steel floor grating Tk. 95.00 each
850 150 x 150mm size plastic-grating with Tk. 75.00 each
851 Plastic low down complete set includingTk. 900.00 per set
852 Internal and external fittings for plasti Tk. 540.00 per set
853 CP soap tray Tk. 130.00 each
854 Porcelain soap tray: white Tk. 230.00 each
855 Porcelain soap tray: coloured Tk. 275.00 each
856 Stainless steel soap tray Tk. 230.00 each
857 Surface mounted automatic liquid soapTk. ### each
858 Automatic wall-mounted liquid soap di Tk. ### each
859 Liquid soap dispenser (push-up type) Tk. 500.00 each
III. Pipes & Accessories
(a) HDPE Pipe
860 110 mm dia HDPE pipe Tk. 167.00 per foot
861 110 mm HDPE plain tee/T-Y Tk. ### each
862 110 mm HDPE plain bend Tk. 885.00 each
863 160 mm dia HDPE pipe Tk. 307.00 per foot
864 160 mm HDPE plain tee/T-Y Tk. ### each
865 160 mm HDPE plain bend Tk. ### each
866 200 mm dia HDPE pipe Tk. 552.00 per foot
867 200 mm HDPE plain tee/T-Y Tk. ### each
868 200 mm HDPE plain bend Tk. ### each
869 250 mm dia HDPE pipe Tk. 860.00 per foot
870 250 mm HDPE plain tee/T-Y Tk. ### each
871 250 mm HDPE plain bend Tk. ### each
872 Electro fusion welding joint(upto 110 Tk. 400.00 each
Analysis of PW 35
SL Items Rate Unit
873 Electro fusion welding joint(over 110 Tk. 500.00 each
874 110 mm dia HDPE pipe for under-grouTk. 167.00 per foot
875 110 mm HDPE plain Tee/T-Y for underTk. 646.00 each
876 110 mm HDPE plain Bend for under-grTk. 465.00 each
877 160 mm dia HDPE pipe for under-grouTk. 307.00 per foot
878 160 mm HDPE plain Tee/T-Y for underTk. 916.00 each
879 160 mm HDPE plain bend for under-grTk. 802.00 each
880 200 mm dia HDPE pipe for under-grouTk. 552.00 per foot
881 200 mm HDPE plain tee/T-Y for under-Tk. ### each
882 200 mm HDPE plain bend for under-grTk. ### each
883 250 mm dia HDPE pipe for under-grouTk. 850.00 per foot
884 250 mm HDPE plain tee/T-Y for under-Tk. ### each
885 250 mm HDPE plain bend for under-grTk. ### each
886 280 mm dia HDPE pipe for under-grouTk. ### per foot
887 280 mm HDPE plain tee/T-Y for under-Tk. ### each
888 280 mm HDPE plain bend for under-grTk. ### each
889 315 mm dia HDPE pipe for under-grouTk. ### per foot
890 315 mm HDPE plain tee/T-Y for under-Tk. ### each
891 315 mm HDPE plain bend for under-grTk. ### each
892 400 mm dia HDPE pipe for under-grouTk. ### per foot
893 400 mm HDPE plain tee/T-Y for under-Tk. ### each
894 400 mm HDPE plain bend for under-grTk. ### each
895 630 mm dia HDPE pipe for under-grouTk. ### per foot
896 630 mm HDPE plain tee/T-Y for under-Tk. ### each
897 630 mm HDPE plain bend for under-grTk. ### each
898 710 mm dia HDPE pipe for under-grouTk. ### per foot
899 710 mm HDPE plain tee/T-Y for under-Tk. 50,689.00 each
900 710 mm HDPE plain bend for under-grTk. 42,570.00 each
Analysis of PW 36
SL Items Rate Unit
901 900 mm dia HDPE pipe for under-grouTk. 11,110.00 per foot
902 900 mm HDPE plain Tee/T-Y for underTk. 90,894.00 each
903 900 mm HDPE plain bend for under-grTk. 70,420.00 each
Butt Welding Joint
904 Butt fusion welding joint(75-355 mm d Tk. 350.00 each
905 Butt fusion welding joint(400-560 mm Tk. 450.00 each
906 Butt fusion welding joint(630-1000 mm Tk. 600.00 each
(b) uPVC
907 12 mm dia uPVC pipe Tk. 6.75 per foot
908 12 mm dia uPVC plain Tee Tk. 5.50 each
909 12 mm dia uPVC plain elbow Tk. 4.50 each
910 12 mm dia uPVC faucet elbow Tk. 6.00 each
911 12 mm dia uPVC plain socket Tk. 4.00 each
912 12 mm dia uPVC thread plug Tk. 3.00 each
913 19 mm dia uPVC pipe Tk. 10.00 per foot
914 19 mm dia uPVC plain tee Tk. 8.00 each
915 19 mm dia uPVC plain elbow Tk. 7.50 each
916 19 mm dia uPVC plain socket Tk. 5.00 each
917 19mm x 12 mm dia uPVC reduced tee Tk. 20.00 each
918 19mm x 12 mm dia uPVC reduced elb Tk. 20.00 each
919 25 mm dia uPVC pipe Tk. 13.00 per foot
920 25 mm x 19 mm dia reduced tee Tk. 22.50 each
921 32 mm dia uPVC pipe Tk. 20.00 per foot
922 32 mm dia uPVC tee Tk. 22.50 each
923 32 mm dia uPVC socket Tk. 29.00 each
924 32 mm dia elbow Tk. 17.50 each
925 32 mm plain bend 900 Tk. 17.50 each
926 37 mm dia uPVC pipe Tk. 14.50 per foot
Analysis of PW 37
SL Items Rate Unit
927 37 mm dia uPVC tee Tk. 22.50 each
928 37 mm dia uPVC socket Tk. 29.00 each
929 37 mm dia uPVC elbow Tk. 21.00 each
930 50 mm dia uPVC pipe: 20 foot (6m) lonTk. 32.00 per foot
931 50 mm dia uPVC bend/offset Tk. 23.00 each
932 50 mm dia uPVC Tee/T-Y/Y (50 x 50 Tk. 99.00 each
933 60 mm dia uPVC pipe Tk. 40.00 per foot
934 60 mm tee Tk. 123.00 each
935 60 mm socket Tk. 60.00 each
936 60 mm elbow Tk. 85.00 each
937 75 mm dia uPVC pipe Tk. 54.00 per foot
938 75 mm dia tee Tk. 165.00 each
939 75 mm dia socket Tk. 71.00 each
940 75 mm dia elbow Tk. 137.00 each
941 88 mm dia uPVC pipe Tk. 60.00 per foot
942 88 mm dia tee Tk. 175.00 each
943 88 mm dia socket Tk. 105.00 each
944 88 mm dia elbow Tk. 150.00 each
945 114 mm dia uPVC pipe Tk. 80.00 per foot
946 114 mm dia tee Tk. 250.00 each
947 114 mm dia socket Tk. 125.00 each
948 114 mm dia elbow Tk. 160.00 each
949 100 mm dia uPVC Pipe: 20 foot (6m) l Tk. 79.00 per foot
950 100 mm dia uPVC bend/offset Tk. 146.00 each
951 100 mm dia uPVC Tee/T-Y/Y (50 x 50 Tk. 179.00 each
952 110 mm dia uPVC pipe Tk. 68.00 per foot
953 110 mm dia door tee (Back) Tk. 180.00 each
954 110 mm dia uPVC plain bend 90 Tk. 100.00 each
Analysis of PW 38
SL Items Rate Unit
955 110 mm dia uPVC long trap Tk. 212.00 each
956 110 mm dia round grating Tk. 295.00 each
957 110 mm dia uPVC vent cowl Tk. 28.00 each
958 150 mm dia uPVC Pipe: 20 foot (6m) l Tk. 167.00 per foot
959 150 mm dia uPVC bend/offset/cowl Tk. 354.00 each
960 150 mm dia uPVC Tee/T-Y/Y (50 x 50 Tk. 307.00 each
961 150 mm dia uPVC for under-ground Tk. 129.00 per foot
962 200 mm dia uPVC pipe for under-grou Tk. 257.00 per foot
963 250 mm dia uPVC pipe for under-grou Tk. 405.00 per foot
964 280 mm dia uPVC pipe for under-grou Tk. 540.00 per foot
965 315 mm dia uPVC pipe for under-grou Tk. 550.00 per foot
(c) G.I. Pipe & fittings
966 12 mm dia GI pipe Tk. 33.00 per foot
967 12 mm dia elbow Tk. 23.00 each
968 12 mm dia tee Tk. 28.00 each
969 12 mm dia nipple Tk. 18.00 each
970 12 mm dia plug Tk. 11.00 each
971 12 mm dia socket Tk. 14.50 each
972 20 mm dia GI pipe Tk. 48.00 per foot
973 20 mm dia elbow Tk. 35.00 each
974 20 mm dia tee Tk. 44.00 each
975 20 mm dia nipple Tk. 23.00 each
976 20 mm dia plug Tk. 12.00 each
977 20 mm dia reducer Tk. 35.00 each
978 20 mm dia socket Tk. 25.00 each
979 25 mm dia GI pipe Tk. 66.00 per foot
980 25 mm dia elbow Tk. 49.00 each
981 25 mm dia tee Tk. 54.00 each
Analysis of PW 40
SL Items Rate Unit
1010 62 mm dia nipple Tk. 176.00 each
1011 62 mm dia plug Tk. 60.00 each
1012 62 mm dia reducer Tk. 126.00 each
1013 62 mm dia socket Tk. 148.00 each
1014 75 mm dia GI pipe Tk. 215.00 per foot
1015 75 mm dia elbow Tk. 400.00 each
1016 75 mm dia tee Tk. 322.00 each
1017 75 mm dia nipple Tk. 176.00 each
1018 75 mm dia plug Tk. 135.00 each
1019 75 mm dia reducer Tk. 153.00 each
1020 75 mm dia socket Tk. 147.00 each
1021 100 mm dia G.I. pipe Tk. 310.00 per foot
1022 100 mm dia elbow Tk. 612.00 each
1023 100 mm dia tee Tk. 785.00 each
1024 100 mm dia nipple Tk. 395.00 each
1025 100 mm dia plug Tk. 252.00 each
1026 100 mm dia reducer Tk. 342.00 each
1027 100 mm dia socket Tk. 348.00 each
(d) SS Pipe & fittings
1028 62 mm dia stainless steel (2 mm thick)Tk. 248.00 per foot
1029 50 mm dia stainless steel (2 mm thick)Tk. 197.00 per foot
1030 40 mm dia stainless steel (2 mm thick)Tk. 148.00 per foot
1031 25 mm dia stainless steel (2 mm thick)Tk. 95.00 per foot
1032 20 mm dia stainless steel (2 mm thick)Tk. 68.00 per foot
1033 12 mm dia stainless steel (2 mm thick)Tk. 34.00 per foot
1034 6 mm dia stainless steel (1.5 mm thick)Tk. 20.00 per foot
1035 25 mm x 25 mm SS square solid bar Tk. 111.00 per foot
1036 Top cap for 40 mm dia SS pipe Tk. 80.00 each
Analysis of PW 41
SL Items Rate Unit
1037 Bottom cap for 40 mm dia SS pipe Tk. 60.00 each
1038 65 mm x 55 mm x 6 mm SS plate Tk. 150.00 each
1039 50 mm x 25 mm x 2 mm SS box: Tk. 60.00 per foot
1040 19 mm x 19 mm x 3 mm SS angle Tk. 80.00 per foot
1041 25 mm x 25 mm x 3 mm SS angle Tk. 110.00 per foot
1042 25 mm x 25 mm x 6 mm SS angle Tk. 190.00 per foot
1043 30 mm x 30 mm x 6 mm SS angle Tk. 210.00 per foot
1044 38 mm x 38 mm x 3 mm SS angle Tk. 180.00 per foot
1045 38 mm x 38 mm x 6 mm SS angle Tk. 270.00 per foot
1046 50 mm x 50 mm x 3 mm SS angle Tk. 220.00 per foot
1047 50 mm x 50 mm x 5 mm SS angle Tk. 250.00 per foot
1048 50 mm x 50 mm x 6 mm SS angle Tk. 350.00 per foot
1049 19 mm x 3 mm SS flat bar Tk. 45.00 per foot
1050 25 mm x 3 mm SS flat bar Tk. 55.00 per foot
1051 38 mm x 3 mm SS flat bar Tk. 90.00 per foot
1052 50 mm x 3 mm SS flat bar Tk. 110.00 per foot
1053 50 mm x 5 mm SS flat bar Tk. 150.00 per foot
1054 50 mm x 6 mm SS flat bar Tk. 200.00 per foot
1055 SS pipe post with glass holder Tk. 300.00 per foot
1056 SS base cup 38 mm Tk. 200.00 each
1057 50 x 62 x 2 mm SS pipe post with glassTk. 300.00 each
1058 SS welding rod Tk. 6.00 per pcs
1059 Cutting charge of SS angle Tk. 6.13 each
1060 62 mm dia SS bend Tk. 65.00 each
1061 62 mm dia end socket Tk. 30.00 each
1062 50 mm dia SS bend Tk. 55.00 each
1063 50 mm dia end socket Tk. 20.00 each
1064 40 mm dia end socket Tk. 15.00 each
Analysis of PW 42
SL Items Rate Unit
1065 25 mm dia socket Tk. 12.00 each
1066 Royal bolt Tk. 50.00 each
1067 Glass hole Tk. 25.00 each
1068 Spider knob Tk. 150.00 each
(e) CPVC
1069 12 mm dia CPVC pipe Tk. 28.00 per foot
1070 12 mm dia CPVC plain tee Tk. 34.00 each
1071 12 mm dia CPVC plain elbow Tk. 26.00 each
1072 12 mm dia CPVC faucet elbow Tk. 24.00 each
1073 12 mm dia CPVC plain socket Tk. 21.00 each
1074 12 mm dia CPVC thread plug Tk. 6.00 each
1075 19 mm dia CPVC pipe Tk. 40.00 per foot
1076 19 mm dia CPVC plain tee Tk. 57.00 each
1077 19 mm dia CPVC plain elbow Tk. 54.00 each
1078 19 mm dia CPVC plain socket Tk. 17.00 each
1079 19mm x 12 mm dia CPVC reduced teeTk. 79.00 each
1080 19mm x 12 mm dia CPVC reduced el Tk. 57.00 each
1081 25 mm dia CPVC pipe Tk. 57.00 per foot
1082 25 mm x 19 mm dia redeuced Tee Tk. 140.00 each
1083 32 mm dia CPVC pipe Tk. 89.00 per foot
1084 32 mm dia CPVC tee Tk. 211.00 each
1085 32 mm dia CPVC socket Tk. 64.00 each
1086 32 mm dia elbow Tk. 130.00 each
1087 37 mm dia CPVC pipe Tk. 130.00 per foot
1088 37 mm dia CPVC tee Tk. 304.00 each
1089 37 mm dia CPVC socket Tk. 98.00 each
1090 37 mm dia CPVC elbow Tk. 258.00 each
1091 50 mm dia CPVC pipe Tk. 200.00 per foot
Analysis of PW 45
SL Items Rate Unit
1144 19 mm PP-R Gate-valve Tk. 274.00 each
1145 25 mm PP-R Gate-valve Tk. 306.00 each
1146 32 mm PP-R Gate-valve Tk. 560.00 each
1147 38 mm PP-R Gate-valve Tk. 606.00 each
1148 50 mm PP-R Gate-valve Tk. 818.00 each
(g) RCC Pipes
1149 150 mm dia RCC pipe (stone-chips, 40Tk. ### each (6'-0")
1150 225 mm dia RCC pipe (stone-chips, 40Tk. ### each (6'-0")
1151 300 mm dia RCC pipe (stone-chips, 50Tk. ### each (6'-0")
1152 375 mm dia RCC pipe (stone-chips, 50Tk. ### each (6'-0")
1153 900 mm dia RCC pipe (stone-chips, 100
Tk. 13,190.00 each (6'-0")
iv) G.I. Union
1154 12 mm dia union Tk. 35.00 each
1155 20 mm dia union Tk. 50.00 each
1156 25 mm dia union Tk. 63.00 each
1157 32 mm dia union Tk. 82.00 each
1158 40 mm dia union Tk. 127.00 each
1159 50 mm dia union Tk. 175.00 each
1160 62 mm dia union Tk. 290.00 each
1161 75 mm dia union Tk. 330.00 each
1162 100 mm dia union Tk. 465.00 each
v) G.I. Gate-Valve
1163 12 mm dia gate-valve Tk. 270.00 each
1164 20 mm dia gate-valve Tk. 320.00 each
1165 25 mm dia gate-valve Tk. 440.00 each
1166 32 mm dia gate-valve Tk. 550.00 each
1167 40 mm dia gate-valve Tk. 720.00 each
1168 50 mm dia gate-valve Tk. ### each
Analysis of PW 47
SL Items Rate Unit
1194 40 mm dia float-valve Tk. 700.00 each
ix) Drainage Pipe Fittings:
1195 50 mm plastic Y or T-Y cleanout Tk. 380.00 each
1196 100 mm plastic "P" or "S" trap Tk. 390.00 each
1197 100 mm "Y" or "T-Y" plastic cleanout Tk. 430.00 each
1198 50 mm plastic P or S trap Tk. 350.00 each
X. Faucets
1199 12 mm CP bib cock (normal) Tk. 770.00 each
1200 12 mm CP bib cock (medium) Tk. 780.00 each
1201 12 mm special quality CP bip cock Tk. 845.00 each
1202 12 mm plastic bip cock with internal br Tk. 150.00 each
1203 12 mm CP medium quality Pillar cock Tk. 950.00 each
1204 12 mm CP special heavy duty Pillar coTk. 990.00 each
CP Self closing Pillar Cock [ With Mixture ]
1205 Standard Tk. ### each
1206 Super Tk. 20,000.00 each
CP Self closing Pillar Cock [ Without Mixture ]
1207 Standard Tk. ### each
1208 Super Tk. 15,000.00 each
1209 12 mm CP medium heavy duty Pillar c Tk. 950.00 each
1210 12 mm CP concealed fixed Sink cock Tk. 875.00 each
1211 12 mm CP concealed moving sink coc Tk. ### each
1212 12 mm CP concealed moving sink cock( Tk. ### each
1213 CP basin mixture(medium) Tk. ### each
1214 CP basin mixture(special) Tk. ### each
1215 CP single handle basin mixture(mediu Tk. ### each
1216 CP single handle basin mixture(specialTk. ### each
1217 CP shower mixture including shower h Tk. ### each
Analysis of PW 48
SL Items Rate Unit
1218 CP shower mixture including shower h Tk. ### each
1219 CP bath-tub mixture with shower head Tk. ### each
1220 CP self closing pillar cock Tk. 840.00 each
1221 12 mm ordinary type (brass) for surfa Tk. 300.00 each
1222 12 mm medium quality CP stop cock Tk. 295.00 each
1223 12 mm special quality CP stop cock Tk. 900.00 each
1224 Stop cock: concealed Tk. 900.00 each
1225 Stop cock: concealed (medium) Tk. 950.00 each
1226 Stop cock: concealed (heavy) Tk. 990.00 each
1227 Surface mounted angle stop cock Tk. 665.00 each
1228 12 mm surface special heavy type anglTk. 685.00 each
1229 12 mm CP concealed angle stop cock Tk. 665.00 each
1230 12 mm medium quality concealed angleTk. 715.00 each
1231 Stop cock (Medium) Tk. 715.00 each
1232 Special concealed type heavy stop cocTk. 950.00 each
1233 12 mm CP medium quality surface & heTk. 625.00 each
1234 12 mm CP surface special heavy type Tk. 670.00 each
1235 100 mm dia CP fixed type cleansing s Tk. 440.00 each
1236 100 mm dia CP moving type cleansingTk. 900.00 each
1237 CP Moving hand shower Tk. ### each
1238 CP Moving push shower Tk. 715.00 each
XI. Water Tank, Water Purifier
1239 16 BWG GI 1200 x 1200 x 1200 mm sizTk. 10,400.00 each
1240 18 BWG GI 1200 x 1200 x 1200 mm sizTk. 10,200.00 each
1241 1000 litre food-grade Plastic over-headTk. ### each
1242 1500 litre food-grade Plastic over-headTk. 10,650.00 each
1243 2000 litre food-grade Plastic over-headTk. 14,200.00 each
1244 150 litre capacity plastic mini tank (loft Tk. ### each
Analysis of PW 49
SL Items Rate Unit
1245 300 litre capacity plastic mini tank (loft Tk. ### each
1246 500 litre capacity plastic mini tank (loft Tk. ### each
1247 500 litre capacity stainless steel water Tk. ### each
1248 1000 litre food-grade stainless steel waTk. ### each
1249 2000 litre food-grade stainless steel waTk. ### each
1250 4000 litre food-grade stainless steel waTk. ### each
1251 6000 litre food-grade stainless steel waTk. ### each
1252 400 gallon capacity Ferro-cement wateTk. ### each
1253 450 mm long metal cover connection pTk. 100.00 each
1254 600 mm long metal cover connection pTk. 120.00 each
1255 12 mm or 19 mm dia ball cock for wateTk. 130.00 each
1256 19 mm dia overflow pipe with jam-nut foTk. 80.00 each
1257 12 mm dia & 450 mm long plastic flexibTk. 40.00 each
1258 12 mm dia & 600 mm long plastic flexibTk. 50.00 each
1259 50 GPD reverse osmosis water purifierTk. ### each
1260 75 GPD reverse osmosis water purifierTk. ### each
1261 75 GPD reverse osmosis water purifierTk. ### each
1262 100 GPD reverse osmosis water purifierTk. ### each
1263 200 GPD reverse osmosis water purifieTk. ### each
1264 400 GPD reverse osmosis water purifieTk. ### each
1265 400 gal capacity ferro-cement water tank Tk. ### each
1266 Water dispencer Tk. ### each
1267 600 mm dia C I man hole cover Tk. ### each
Booster Water Pump Including Pressure Guage
1268 Local Made Tk. ### each
1269 Foreign Made Tk. 15,000.00 each
Water Pressure Reducing Valve
1270 12 mm dia water pressure reducing valTk. ### each
Analysis of PW 50
SL Items Rate Unit
1271 19 mm dia water pressure reducing valTk. ### each
1272 25 mm dia water pressure reducing valTk. ### each
1273 32 mm dia water pressure reducing valTk. ### each
1274 38 mm dia water pressure reducing valTk. ### each
1275 50 mm dia water pressure reducing valTk. 10,000.00 each
1276 62 mm dia water pressure reducing valTk. 17,000.00 each
1277 75 mm dia water pressure reducing valTk. 24,500.00 each
1278 Automatic hand drier Tk. ### each
C20 ARBORICULTURE WORK
1279 Alluvial loamy silty soil Tk. ### per % cft
1280 Well decomposed cow dung Tk. ### per % cft
1281 Possible cost/royalty of lawn grass Tk. 45.00 per % sft
1282 16'-0" long muli bamboo (for split) Tk. 120.00 each
1283 25'-0" long muli bamboo (full size) Tk. 200.00 each
1284 Borrak bamboo (for post) Tk. 12.00 per foot
1285 Borrak bamboo (full size) Tk. 375.00 each
1286 200 mm size earthen tub Tk. 32.00 each
1287 250 mm size earthen tub Tk. 40.00 each
1288 300 mm size earthen tub Tk. 56.00 each
1289 350 mm size earthen tub Tk. 82.00 each
1290 400 mm size earthen tub Tk. 145.00 each
1291 300 mm size earthen plate Tk. 24.00 each
1292 Mustard oil cake Tk. 40.00 per kg
1293 Bone mele Tk. 40.00 per kg
1294 Urea fertilizer Tk. 20.00 per kg
1295 Murate of potash Tk. 20.00 per kg
1296 Triple super phosphate (TSP) Tk. 30.00 per kg
1297 Spade (kodal) Tk. 450.00 each
Analysis of PW 51
SL Items Rate Unit
1298 Spray machine (plaotic), 5ltr capacity Tk. ### each
1299 Steel funna, 450 mm size wirth woode Tk. 350.00 each
1300 Hand hoe, 250 mm size Tk. 90.00 each
1301 Standard Steel hand trolly Tk. ### each
1302 Hedge scissors Tk. ### each
1303 10" size Secature Tk. 650.00 each
1304 22 BWG G.I. water can (2.5 gallon) Tk. 350.00 each
1305 300 mm size G.I. bucket Tk. 250.00 each
1306 19 mm dia plastic hose pipe Tk. 18.00 per foot
1307 400 mm blade Hand Lawn Mower, Mode Tk. 12,500.00 each
1308 4.5 h.p., 550 mm blade power lawn m Tk. 44,500.00 each
1309 6.5 h.p., 550 mm blade power lawn m Tk. 58,400.00 each
1310 22 h.p. 1150 mm cutting blade power Tk.449,000.00 each
1311 perfekthion 1-100ml ,bottle Tk. 230.00 each
1312 Redomil gold, 500gm packet Tk. 720.00 each
1313 Ripcord 1-100 ml bottle Tk. 200.00 each
1314 Proclaim,1 box (10gm-10 pack) Tk. 600.00 each
1315 Vertimec,1-50ml bottle Tk. 120.00 each
C21 DEEP TUBE-WELL
I. For Test boring & design
1316 Mobilization of equipment for drilling Tk. ### LS
1317 Boring by using 100 mm dia cutter (0 mTk. 158.07 meter
1318 Best quality heavy type hand type pumTk. ### each
1319 2.91 mm wall thick 38 mm dia G.I. pipeTk. 534.06 meter
1320 38 mm dia water grade PVC pipe (D-Clas Tk. 105.41 meter
1321 36 mm dia water grade PVC Strainer (D- Tk. 124.45 meter
1322 38 mm dia socket adopter Tk. 66.52 each
1323 Best quality 38 mm dia PVC Cap. Tk. 49.30 each
Analysis of PW 52
SL Items Rate Unit
1324 Complete development of the tube-wellTk. ### LS
1325 Design of production well upto 200 m Tk. ### LS
1326 Design of production well beyond 200 Tk. 12,659.00 LS
1327 Disinfections of tube-well using bleach Tk. 358.36 LS
1328 Maintaining and filling and sealing test Tk. ### each bore
II. For Production well
1329 Mobilization of drilling rig for shroude Tk. ### LS
1330 325 mm dia boring: up to 50 m depth. Tk. 777.65 meter
1331 350 mm dia boring: up to 50 m depth. Tk. 818.18 meter
1332 400 mm dia boring: up to 50 m depth. Tk. 854.13 meter
1333 600 mm dia boring: up to 50 m depth. Tk. ### meter
1334 800 mm dia boring: up to 50 m depth. Tk. ### meter
1335 50 mm dia Class C PVC pipe Tk. 113.71 meter
1336 50 mm dia Class D PVC pipe Tk. 137.76 meter
1337 50 mm dia Class E PVC pipe Tk. 190.24 meter
1338 75 mm dia Class C PVC pipe Tk. 233.33 meter
1339 75 mm dia Class D PVC pipe Tk. 308.33 meter
1340 75 mm dia Class E PVC pipe Tk. 701.22 meter
1341 100 mm dia Class C PVC pipe Tk. 386.67 meter
1342 100 mm dia Class D PVC pipe Tk. 511.67 meter
1343 100 mm dia Class E PVC pipe Tk. 645.83 meter
1344 150 mm dia Class C PVC pipe Tk. 916.67 meter
1345 150 mm dia Class D PVC pipe Tk. ### meter
1346 150 mm dia Class E PVC pipe Tk. ### meter
1347 50 mm dia PVC cap Tk. 62.95 each
1348 100 mm dia PVC cap Tk. 161.62 each
1349 150 mm dia PVC cap Tk. 419.52 each
1350 125 mm x 50 mm PVC reducer Tk. 546.60 each
Analysis of PW 53
SL Items Rate Unit
1351 150 mm x 75 mm PVC reducer Tk. 703.72 each
1352 200 mm x 100 mm PVC reducer Tk. 786.18 each
1353 200 mm x 150 mm PVC reducer Tk. ### each
1354 250 mm x 150 mm PVC reducer Tk. ### each
1354 125 mm dia PVC housing pipe Class CTk. 625.00 meter
1355 125 mm dia PVC housing pipe Class DTk. 783.33 meter
1356 125 mm dia PVC housing pipe Class ETk. 933.33 meter
1357 150 mm dia PVC housing pipe Class CTk. 916.67 meter
1358 150 mm dia PVC housing pipe Class DTk. ### meter
1359 150 mm dia PVC housing pipe Class ETk. ### meter
1360 200 mm dia PVC housing pipe Class CTk. ### meter
1361 200 mm dia PVC housing pipe Class DTk. ### meter
1362 200 mm dia PVC housing pipe Class ETk. ### meter
1363 250 mm dia PVC housing pipe Class CTk. ### meter
1364 250 mm dia PVC housing pipe Class DTk. ### meter
1365 250 mm dia PVC housing pipe Class ETk. ### meter
1366 PVC Tape Tk. 101.47 each
1367 PVC Solution / gum Tk. 660.68 no
1368 Petrol Tk. 89.00 litre
1369 Diesel Tk. 68.00 litre
1370 M.S split centralizer Tk. 451.67 meter
1371 S.S split centralizer Tk. ### meter
1372 Complete development of the tube-wellTk. ### LS
1373 Complete development of the tube-wellTk. ### LS
1374 Complete development of the tube-wellTk. ### LS
1375 Complete development of the tube-wellTk. ### LS
1376 Complete development of the tube-wellTk. 35,526.40 LS
1377 Hire charge of pump including spare a Tk. 267.26 hour
Analysis of PW 54
SL Items Rate Unit
1378 Disinfections of tube-well using bleac Tk. ### LS
1379 150 mm dia and 4 mm thick M.S. pipe Tk. ### meter
1380 200 mm dia and 6 mm thick M.S. pipe Tk. ### meter
1381 200 mm dia and 6 mm thick M.S. pipe Tk. ### meter
1382 4 mm thick 200 mm dia plate Tk. ### each
1383 5 mm thick 250 mm dia plate Tk. ### each
1384 6 mm thick 150 mm dia M.S. Cap Tk. ### each
1385 6 mm thick 200 mm dia M.S. Cap Tk. ### each
1386 150 mm dia 4.85 mm thick G.I. pipe Tk. ### meter
1387 200 mm dia 6 mm thick G.I. pipe Tk. ### meter
1388 150 mm dia stainless steel strainer of Tk. ### meter
1389 150 mm dia 2.5 mm thick stainless steel Tk. ### meter
1390 200 mm dia stainless steel strainer of Tk. ### meter
1391 200 mm dia 2.5 mm thick stainless steel Tk. ### meter
1392 75 mm dia 2.5 mm thick stainless steelTk. ### meter
1393 100 mm dia 2.5 mm thick stainless steel Tk. ### meter
1394 50 mm dia 2.5 mm thick stainless steelTk. ### meter
1395 75 mm dia 2.5 mm thick stainless steelTk. ### meter
1396 200 mm x 200 mm dia 6 mm thick M.S.Tk. ### each
1397 150 mm x 300 mm dia 6 mm thick M.S.Tk. ### each
1398 200 mm x 300 mm dia M.S. reducer Tk. ### each
1399 50 mm x 150 mm dia M.S. reducer Tk. 750.00 each
1400 75 mm x 150 mm dia M.S. reducer Tk. 750.00 each
1401 100 mm x 200 mm dia M.S. reducer Tk. ### each
1402 (i) 300 mm dia 6 mm thick M.S. housinTk. ### meter
1403 (ii) 300 mm dia 6 mm thick M.S. housi Tk. ### meter
1404 (iii) 400 mm dia 6 mm thick M.S. housi Tk. ### meter
1405 (iv) 400 mm dia 6 mm thick M.S. housiTk. 10,500.00 meter
Analysis of PW 56
SL Items Rate Unit
1433 Arsenic (As) Tk. ### per test
1434 Turbidity Tk. 400.00 per test
1435 Sieve analysis for sand from different l Tk. ### per test
C22 SUB-SOIL INVESTIGATION WORK
I. Operational cost
1436 Truck fare within 20 km including loadi Tk. ### per trip
1437 Temporary camp at site for soil investi Tk. ### per site
1438 Field Engineer including site allowanc Tk. ### per day
1439 Foundation Engineer: 5-10yrs exp , MeTk. ### per day
1440 Foreman including site allowances Tk. 800.00 per day
1441 Rig operators including site allowancesTk. 600.00 per day
1442 Helper to rig operator/c site allowancesTk. 390.00 per day
1443 Unskilled labour including site allowan Tk. 320.00 per day
1444 Asstt laboratory technician Tk. 800.00 per day
1445 Laboratory technician Tk. ### per day
1446 Laboratory engineer Tk. ### per day
1447 Conveyance within 25 km Tk. 80.00 per day
1448 Wooden plank (mango) Tk. 650.00 per cft
1449 Rope Tk. 60.00 per kg
1450 Small boat Tk. 700.00 per day
1451 Drum (defects free) Tk. ### each
1452 Hire charge of boring rig Tk. ### per day
II Laboratory Charge for Sub-Soil Investigation Work
1453 Sp. gr. test Tk. 200.00 per test
1454 Hydrometer, sieve analysis & sp. gr.,& Tk. ### per test
1455 Linear shrinkage Tk. 700.00 per test
1456 Shrinkage limit Tk. 500.00 per test
1457 Liquid limit Tk. 300.00 per test
Analysis of PW 57
SL Items Rate Unit
1458 Plastic limit Tk. 300.00 per test
1459 Unit weight (wet & dry) Tk. 250.00 per test
1460 Void ratio Tk. ### per test
1461 Moisture content Tk. 200.00 per test
1462 Organic matter content Tk. ### per test
1463 Consolidated quick test (direct shear teTk. ### per test
1464 Unconfined compression Tk. ### per test
1465 Ground water level location Tk. 500.00 per site
1466 Visual Inspection & Classification of soTk. 150.00 per test
C23 FITTINGS
I. Fittings for Wooden Door-windows/Hard wares/Glass/CI sheet
1467 250 mm long iron tower bolt Tk. 50.00 each
1468 250 mm long brass tower bolt Tk. 400.00 each
1469 200 mm long brass tower bolt Tk. 300.00 each
1470 250 mm long SS tower bolt Tk. 150.00 each
1471 200 mm socket bolt Tk. 50.00 each
1472 200 mm long brass socket bolt Tk. 300.00 each
1473 200 mm long SS socket bolt Tk. 200.00 each
1474 Hatch bolt Tk. 300.00 each
1475 100 mm long hinges nickel plated Tk. 65.00 each
1476 100 mm longs brass hinge Tk. 150.00 each
1477 75 mm longs brass hinge Tk. 110.00 each
1478 100 mm longs SS hinge Tk. 100.00 each
1479 75 mm longs SS hinge Tk. 60.00 each
1480 Nickel plated handle Tk. 75.00 each
1481 Brass handle Tk. 100.00 each
1482 SS handle Tk. 60.00 each
1483 Iron screws Tk. 17.00 per dzn
Analysis of PW 59
SL Items Rate Unit
1512 1.5 mm thick corrugated fiber glass Tk. 80.00 per sft
1513 1.5 mm thick fiber glass sheet ridging Tk. 142.00 per foot
Glass Door
1514 10 mm thick tempered glass Tk. 388.00 per sft
1515 10 mm thick non- tempered glass Tk. 164.00 per sft
1516 Auto closer set Tk. ### per set
1517 Top and bottom clamping device Tk. ### per set
1518 Locking device Tk. ### per set
1519 Top hinge Tk. ### per set
1520 Handle Tk. ### per set
I. Hardware for steel door-window
1521 Stopper handle Tk. 20.00 each
1522 300 mm long iron cleats Tk. 30.00 each
1523 50 mm long pin hinges Tk. 25.00 each
1524 100 mm long iron hinges Tk. 54.00 each
1525 Hand lock Tk. 50.00 each
1526 150 mm long clamp Tk. 35.00 each
C24 MISCELLENEOUS ITEMS
1527 Nails and wires Tk. 65.00 per kg
1528 G.I. wire Tk. 120.00 per kg
1529 Chalk powder Tk. 40.00 per kg
1530 38 mm x 38 mm x 6 mm brass Tk. 315.00 per foot
1531 Polythene sheet Tk. 250.00 per % sft
1532 EPS sheet (62mm thick) density 15 kg Tk. 90.00 per cft
1533 Perforated aluminium board Tk. 110.00 per sft
1534 Lubricants Tk. 220.00 per litre
1535 Glass fiber mesh (10mmX10mm grid aTk. 7.00 per sft
Analysis of PW 60
SL Items Rate Unit
Water proof, damp proof, dry & breathable cement STN-EN - 1015-11 , compressive
1536 strength 34 MPa), Max depth of water p(25 kg Tk. 1,500.00 per bag
bag)(Only for plaster work)
1537 Fire rated door complying standard specification Tk. 3,435.00 per sft
1538 Installation charge of fire rated door Tk. 215.00 per sft
1539 Nut-bolts, J-hooks etc. Tk. 160.00 per kg
1540 Empty gunny bags/ Polymer bag to fill sand for loadTk. 10.00 each
1541 Salballah for driving Tk. 70.00 per foot
1542 Counter-sunk rivets for shoe-plate Tk. 50.00 each
1543 20 mesh 24 BWG wire mesh Tk. 25.00 per sft
1544 18 BWG galvanized wire mesh (2 mesh per 25mm) Tk. 20.00 per sft
1545 225 mm dia RCC pipe Tk. 262.50 per foot
1546 300 mm dia RCC pipe Tk. 457.17 per foot
1547 12 BWG barbed wire Tk.120,000.00 per M. ton
1548 Rivet, washer, wire nails etc. Tk. 90.00 per kg
1549 38 mm dia M.S. wheel for collapsible gate Tk. 28.00 each
1550 75 mm - 150 mm M.S. clamp Tk. 30.00 each
1551 Electrodes including electricity Tk. 10.00 each
1552 Grease/lubricant etc. Tk. 56.00 per Ib
1553 38 mm dia iron ring Tk. 20.00 each
1554 38 mm dia heavy type gate wheel Tk. 160.00 each
1555 Clamp with huskel dumney Tk. 144.00 each
1556 Heavy duty gate locking arrangement Tk. 275.00 each
1557 125 mm M.S. hinges Tk. 68.00 each
1558 High performance elastomeric cementitious waterproTk. 280.00 per kg
1559 15.62 mm socket bolt Tk. 60.00 each
1560 China made spring for rolling shutter Tk. 50.00 per foot
1561 Spring box for rolling shutter Tk. 70.00 each
1562 12 mm dia nut-bolt Tk. 12.00 each
Analysis of PW 61
SL Items Rate Unit
1563 Coal-tar Tk. 70.00 per kg
1564 150 mm long brass tower & socket boltTk. 250.00 each
1565 75 mm long brass hinges Tk. 110.00 each
1566 150 mm long catch hooks Tk. 15.00 each
1567 Screws Tk. 10.00 per doz.
1568 24 BWG wire-net Tk. 20.00 per sft
1569 Gum Tk. 200.00 per kg
1570 Blue Tk. 200.00 per kg
1571 Pigment for colour washing Tk. 200.00 per kg
1572 300 mm long brass hasp bolt Tk. 375.00 each
1573 Hydraulic door closer Tk. ### each
1574 Mortice door lock Tk. 600.00 each
1575 Rim (round) door lock Tk. 550.00 each
1576 Magnetic door-shock absorber Tk. 100.00 each
1577 Used and empty Bitumen drum Tk. 200.00 each
1578 Fire-wood Tk. 200.00 per mound
1579 Bleaching powder Tk. 100.00 per kg
1580 Fly proof wire-net Tk. 100.00 per sqm
1581 25 mm expanded metal net Tk. 100.00 per sqm
1582 Bamboo darma Tk. 43.00 per sqm
1583 Single layer double bamboo tarja Tk. 130.00 per sqm
1584 Premix cement plaster Tk. 45.00 per kg
1585 Skim coat Tk. ### per kg
1586 Cementetious pinhole filler Tk. 100.00 per kg
1587 Bentonite Tk. 20.00 per kg
1588 16 gauge thick 50 mm x 50 mm ss hollTk. 278.00 per ft
1589 16 gauge thick 50 mm x 38 mm ss hollTk. 240.00 per ft
1590 18 gauge thick 50 mm x 12 mm ss hollTk. 175.00 per ft
Analysis of PW 62
SL Items Rate Unit
1591 2 ply petroleum asphalt (Chinese) Tk. 9.00 per sft
1592 Coal Tk. 7.00 per kg
1593 2.44 m x 1.22 m size hard board Tk. 600.00 per piece
1594 PVC water stopper Tk. 160.00 per foot
1595 Sign board including material, painting,Tk. 225.00 sft
1596 Autocad operator Tk. 800.00 per day
1597 printing of drawing Tk. 18.00 sft
1598 As built work survey & report Tk. ### per day
1599 Providing expertised Architect 5years exTk. 70,000.00 per month
1600 Providing expertised engineer 10 yearsTk.120,000.00 per month
body
1601 Providing pick up (double Cabined) Tk. 70,000.00 per month
1602 photographer Tk. ### per day
1603 photo print , post card sisez Tk. 7.00 each
1604 Engineer, Expertise in microsoft MS PTk.120,000.00 permonth
1605 Engineer, min graduate in relevant fieldTk. ### per day
1606 Diploma Engineer, min 5yrs Exp Tk. ### per day
1607 Diploma Engineer, min 1yrs Exp Tk. ### per day
per
1608 Royality of Earth Tk. ### thousand
cft
per
1609 Royality of DreTk. 800.00 thousand
cft
Analysis of PW 64
SL Items Rate Unit
1641 Asst to PIT expert engineer: civil engr Tk.100,000.00 per month
GLASS: Float / Anealed
1642 Float / annealed glass thickness :2.5mTk. 35.00 sft
1643 Float / annealed glass thickness :3.0mTk. 35.00 sft
1644 Float / annealed glass thickness :3.5mTk. 42.00 sft
1645 Float / annealed glass thickness :4.0mTk. 48.00 sft
1646 Float / annealed glass thickness :5.0mTk. 65.00 sft
1647 Float / annealed glass thickness :6.0mTk. 85.00 sft
1648 Float / annealed glass thickness :8.0mTk. 125.00 sft
1649 Float / annealed glass thickness :10. Tk. 140.00 sft
1650 Float / annealed glass thickness :12. Tk. 180.00 sft
GLASS: Tempered Glass
1651 Tempered glass thickness 5.0mm Tk. 160.00 sft
1652 Tempered glass thickness 6.0mm Tk. 190.00 sft
1653 Tempered glass thickness 8.0mm Tk. 250.00 sft
1654 Tempered glass thickness 10.0mm Tk. 280.00 sft
1655 Tempered glass thickness 12.0mm Tk. 390.00 sft
1656 Tempered glass thickness 15.0mm Tk. ### sft
1657 Tempered glass thickness 19.0mm Tk. ### sft
1658 12 mm two in one bib cock Tk. ### each
1659 Fibre mesh Tk. ### per kg
1660 3 mm thick frosted glass Tk. 45.00 sft
1661 Synthetic fly proof net. Tk. 140.00 sqm
1662 100 mm x 38 mm x 6 mm size clamp Tk. 14.00 each
1663 Stone lime Tk. 16.00 kg
1664 Surki Tk. ### cum
1665 25 mm mesh expanded metal for usingTk. 15.00 sft
1666 25 mm iron screw Tk. 8.00 dz
Analysis of PW 65
SL Items Rate Unit
1667 50 mm iron screw Tk. 15.00 dz
1668 25 mm brass screw Tk. 14.00 dz
1669 38 mm iron hinge Tk. 4.00 each
1670 38 mm brass hinge Tk. 6.00 each
1671 75 mm long cath hook Tk. 4.00 each
1672 100 mm long catch hook Tk. 6.00 each
1673 150 mm long catch hook Tk. 8.00 each
1674 200 mm long catch hook Tk. 10.00 each
1675 225 mm long catch hook Tk. 15.00 each
1676 50 mm dia 100 mm long socket bolt Tk. 8.00 each
1677 50 mm dia 100 mm long socket bolt (STk. 35.00 each
1678 50 mm dia 150 mm long socket bolt Tk. 11.00 each
1679 50 mm dia 150 mm long socket bolt(SSTk. 55.00 each
1680 50 mm dia 200 mm long socket bolt Tk. 20.00 each
1681 50mm dia 200 mm long socket bolt(SSTk. 70.00 each
1682 50 mm dia 150 mm long brass socket bTk. 110.00 each
1683 50 mm dia 200 mm long brass socket bTk. 140.00 each
1684 50 mm dia 250 mm long brass socket bTk. 180.00 each
1685 75 mm long hinge Tk. 25.00 each
1686 100 mm long hinge Tk. 50.00 each
1687 75 mm long brass hinge Tk. 110.00 each
1688 100 mm long brass hinge Tk. 150.00 each
1689 50 mm dia iron ring Tk. 15.00 each
1690 50 mm dia brass ring Tk. 40.00 each
1691 Colouring materials Tk. 180.00 kg
1692 Laqure spray polishing Tk. 500.00 litre
1693 Materials for french polishing: 3 coats Tk. 800.00 % sft
1694 Earthoil Tk. 50.00 kg
Analysis of PW 66
SL Items Rate Unit
1695 40 mm dia G.I. Socket Tk. 105.00 each
1696 3 gal capacity C. I. Cistern (Not availabTk. ### each
1697 300 long clamp: Iron Tk. 22.00 each
1698 150 long clamp: Iron Tk. 12.00 each
gallon
1699 Aluminium paint Tk. ### (U.K.)
1700 Plastic low-down cistern Tk. 800.00 each
1701 Siphon set for plastic low-down Tk. 360.00 set
1702 Jarul Tk. ### per cft
1703 Loha/Pyiankado Tk. ### per cft
1704 8 BWG welding electrodes Tk. 6.00 per piece
1705 25mm dia G.I. Pipe for structural work Tk. 75.00 foot
1706 China made spring for rolling shutter Tk. 15.00 foot
1707 Spring box for rolling shutter Tk. 120.00 each
1708 Scaffolding including safety provision Tk. 11.00 per sft
1709 Tar boiler Tk. ### per day
1710 Vibrating roller Pedestrain (0.5 - 1 ton) Tk. ### per day
1711 Cart fare within 5 km Tk. 500.00 per trip
1712 2 mm geo-textile Tk. 8.00 per sft
C25 CARRIAGE OF MATERIALS
Carriage of materials except bricks and bats by motor trucks bullock carts or any other
1713 means, including loading, unloading at both ends and stacking properly at site as per
direction of the Engineer.
(a) Up to 1.5 kilometer Tk. 190.00 per M. ton
(b) Up to 3.0 kilometer Tk. 260.00 per M. ton
(c) Up to 5.0 kilometer Tk. 340.00 per M. ton
(d) For each additional km beyond 5.0 kiloTk. 18.00 per M. ton
(e) For each additional km beyond 30.0 kilTk. 13.00 per M. ton
(f) Beyond 80.0 kilometer Tk. 9.00 per M. ton
1714 Weighing at both ends for items of steeTk. 105.00 per M. ton
Analysis of PW 67
SL Items Rate Unit
Carriage of bricks or bats by motor truck, bullock carts or any other means including
1715 loading, unloading at both ends and stacking properly at site as per direction of the
Engineer.
(a) Up to 1.5 kilometer Tk. 300.00 per % 0 nos
(b) Up to 3.0 kilometer Tk. 400.00 per % 0 nos
(c) Up to 5.0 kilometer Tk. 525.00 per % 0 nos
(d) For each additional km beyond 5.0 kiloTk. 28.00 per % 0 nos
(e) For each additional km beyond 30.0 kilTk. 18.00 per % 0 nos
(f) Beyond 80.0 kilometer Tk. 6.00 per % 0 nos
B-1. Concrete (1:3:6) work using BRICK CHIPS and sand of F.M. 1.2
Considering 100 cft of work
(a) Bricks for chips
(@ 90 cft for % 765 nos @ Tk. 8,700.00 %0 nos = Tk. 6,655.50
(b) Breaking chips 90 cft @ Tk. 950.00 % cft = Tk. 855.00
(c) Sand (F.M. 1.2 45 cft @ Tk. 1,400.00 % cft = Tk. 630.00
(d) Cement: CEM-I 13 bags @ Tk. 395.00 bag = Tk. 5,135.00
(e) Local carriage, sundries, T & P, water, laboratory charge etc. LS = Tk. 320.00
Tk. 13,595.50
135.96
B-2. Concrete (1:2:4) work using BRICK CHIPS with sand of F.M. 1.2
Considering 100 cft of work
(a) Bricks for chips
(@ 90 cft for % 765 nos @ Tk. 8,700.00 %0 nos = Tk. 6,655.50
(b) Breaking chips 90 cft @ Tk. 950.00 % cft = Tk. 855.00
(c) Sand (F.M. 1.2 45 cft @ Tk. 1,400.00 % cft = Tk. 630.00
(d) Cement: CEM- 18 bags @ Tk. 415.00 bag = Tk. 7,470.00
(e) Local carriage, sundries, T & P, water, laboratory charge etc. LS = Tk. 320.00
Total = Tk. 15,930.50
159.31
B-3 Concrete (1:2:4) work using BRICK CHIPS (sand of F.M. 1.2 and 2.2 in equal proportion)
Considering 100 cft of work
(a) Bricks for chips
(@ 90 cft for %765 nos @ Tk. 8,700.00 %0 nos = Tk. 6,655.50
(b) Breaking chips90 cft @ Tk. 950.00 % cft = Tk. 855.00
(c) Sand (F.M. 1.222.5 cft @ Tk. 1,400.00 % cft = Tk. 315.00
(d) Sand (F.M. 2.222.5 cft @ Tk. 4,500.00 % cft = Tk. 1,012.50
(e) Cement: OPC, Type-1 (CEM-I),52.5 18 bags @ Tk. 415.00 bag = Tk. 7,470.00
B-7 Concrete (1:1:2) work with CRUSHED STONE CHIPS and 100% sand of F.M. 2.2
Break-up for 100 cft
(a) 19 mm down well graded
crushed stone 76 cft @ Tk. 19,500 per % cft = Tk. 14,820.00
(b) Well graded Sy38 cft @ Tk. 4,500.00 per % cft = Tk. 1,710.00
(c) Cement: OPC,30 bags @ Tk. 415.00 Per bag = Tk. 12,450.00
(d) Local carriage, sundries, T & P, water, laboratory charge etc. LS = Tk. 320.00
= Tk. 29,300.00
293 pcft
B-8 Fair-Face Concrete (1:1.5:3) work with CRUSHED STONE CHIPS, 75% grey cement, 25% white cement and 100% sand of F.M. 2.2
Considering 100 cft of work
(a) 19 mm down cr83 cft @ Tk. 19,500.00 per % cft = Tk. 16,185.00
(b) Sand (F.M. 2.241.5 cft @ Tk. ### per % cft = Tk. 1,867.50
(c) Cement: OPC,16.5 bags @ Tk. 415.00 per bag = Tk. 6,847.50
(d) White Cement 275 kg @ Tk. 26.00 per kg = Tk. 7,150.00
(e) Colouring Pigment LS Tk. 840.00
(f) Local carriage, sundries, T & P, water, laboratory chLS = Tk. 320.00
Total (A) = Tk. 33,210.00
332.10 pcft
C-7 CORNICE, DROP-WALLS, RAILINGS, LOUVER and FINS etc. using WOODEN shutter
Assuming 3" thick 10'-0" x 3'-0" size dropwall
Shuttering Area: 62.5 sft
(i) Planks and batten
2 x 10'-0" x 3'-0 5.00 cft
2 x 3 x 3'-0" x 0 0.75 cft
1 x 10'-0" x 5" 0.34 cft
3 x 1'-6" x 0'-3" 0.19 cft
= 6.28 cft
Add 5% wastag 0.31 cft
6.59 cft @ Tk. 500.00 per cft
Using 8 times @ Tk. 62.50 per cft = Tk. 411.88
(ii) Bamboo struts i 8.0 nos @ Tk. 73.85 each
Using 8 times @ Tk. 9.23 each = Tk. 73.84
(iii) Nails and wires 0.5 kg @ Tk. 65.00 per kg = Tk. 32.50
(iv) Labour for shuttering in/c making, placing & removing:
2 x 10'-0'' x 3'- 60 sft
1 x 10'-0" x 3"= 2.5 sft
= 62.5 sft @ Tk. 15.00 per sft = Tk. 937.50
(v) Supplying & fixing rupban or equivalent sheet
and necessary hessian tape for
making water-ti 62.5 sft @ Tk. 2.50 per sft = Tk. 156.25
(vi) Curing for 28 d 62.5 sft @ Tk. 2.67 per sft = Tk. 166.88
Total = Tk. 1,778.85
Cost per sft = Tk. 28.46
Cost per sqm = Tk. 306.34
C-13 PADESTALS, COLUMN CAPITALS, LIFT WALLS and WALLS using STEEL shutter
Assuming 10'-0" x 12" x 12" Column
Shuttering Area: 40 sft
(i) 1.5" x 1.5" x 3/16" angle for frame
4 x 2 x 10'-0"= 80.00 rft
2 x 3 x 1'-4"= 7.98 rft
2 x 3 x 1'-0"= 6.00 rft
93.98 rft
Add 5% wastage = 4.699 rft
= 98.68 rft
1.79 Ibs per rft = 176.64 Ibs @ Tk. 24.94 per Ib = Tk. 4,405.40
(ii) 1" x3/16" F.I. bar for stiffner
2 x 8 x 1'-4"= 21.28 rft
Analysis of PWD 78
Cost per sft = Tk. 34.97
Cost per sqm = Tk. 376.42
Analysis of PWD 81
Cost per sqm = Tk. 362.21
Analysis of PWD 85
DIVISION 01 : GENERAL AND SITE FACILITIES
Analysis of PWD 86
Analysis of PWD 92
2.18.2 For each additional lift of one foot beyond 5'-0" and upto 10'-0"
Considering 1000 cft of excavation work
(i) Extra labour 1/2 no @ Tk. 320.00 per day = Tk. 160.00
Profit 10.00% = Tk. 16.00
Overhead 3.50% = Tk. 5.60
Total = Tk. 181.60
Add VAT with adjustment factor 1.06383 6.00% = Tk. 11.59
Grand Total = Tk. 193.19
Rate per cft = Tk. 0.19
Rate per cum = Tk. 6.71
Say Tk. 7 .00 per cum
2.18.3 For each additional lift of one foot beyond 10'-0" and upto 15'-0"
Considering 1000 cft of excavation work
(i) Extra labour 3/4 no @ Tk. 320.00 per day = Tk. 240.00
Profit 10.00% = Tk. 24.00
Overhead 3.50% = Tk. 8.40
Total = Tk. 272.40
Add VAT with adjustment factor 1.06383 6.00% = Tk. 17.39
Grand Total = Tk. 289.79
Rate per cft = Tk. 0.29
Rate per cum = Tk. 10.24
Say Tk. 10 .00 per cum
2.18.4 For each additional lift of one foot beyond 15'-0" and upto 20'-0"
Considering 1000 cft of excavation work
(i) Extra labour 1 no @ Tk. 320.00 per day = Tk. 320.00
Profit 10.00% = Tk. 32.00
Overhead 3.50% = Tk. 11.20
Total = Tk. 363.20
Add VAT with adjustment factor 1.06383 6.00% = Tk. 23.18
Grand Total = Tk. 386.38
Rate per cft = Tk. 0.39
Rate per cum = Tk. 13.77
Say, Tk. 14 .00 per cum
2.19.2 Bailing-out water using 1 cusec pump electricity operated pump set
Considering 1 day operation = 8 Hrs.
(i) Hire charge of pump including suction
and delivery pi 1 day @ Tk. 800.00 per day = Tk. 800.00
(ii) Electricity, lubricant, spares, maintenance etc. LS = Tk. 300.00
(iii) Pump operator 1 no @ Tk. 600.00 per day = Tk. 600.00
(iv) Helper 1 no @ Tk. 390.00 per day = Tk. 390.00
(v) Skilled labour 1 no @ Tk. 390.00 per day = Tk. 390.00
(vi) Provide drainage facilities and connection to discharge facilities LS = Tk. 250.00
(viii) Tools and plant, sundries etc. LS = Tk. 150.00
Sub - Total = Tk. 2,880.00
Profit 10.00% = Tk. 288.00
Overhead 3.50% = Tk. 100.80
Total = Tk. 3,268.80
Add VAT with adjustment factor 1.06383 6.00% = Tk. 196.13
Grand Total = Tk. 3,464.93
Rate per hour = Tk. 433.12
Say, Tk. 433 .00 per hour
DIVISION 04 : BRICKWORKS, PATENT STONEF IN FLOOR AND FANCY SCREEN BLOCK WORKS
Analysis of PW 116
Grand To= Tk. ###
(a) Ground floor Rate per = Tk. 378.87
Rate per = Tk. ###
Say, Tk. 13,380 .00 per cum
Item No.- 04.10
Extra rate for each additional floor for brick works (items nos- 4.2 to 4.9)
04.10.1 Add for each addl. floor up to 5th floor (@ 1.25 nos per cum = Tk. 171.00
04.10.2 Add for each addl. floor for 6th floor to 9th floor (@ per cum = Tk. 239.00
04.10.3 Add for each addl. floor for 10th floor and above (@per cum = Tk. 273.00
Analysis of PW 132
Item No.- 04.32
Extra rate for each additional floor for patent stone flooring
04.32.1 Add for each addl. floor up to 5th floor per sqm = Tk. 31.00
04.32.2 Add for each addl. floor for 6th floor to per sqm = Tk. 42.00
04.32.3 Add for each addl. floor 10th floor and per sqm = Tk. 52.00
Item No.-06.5.1
Supplying, fitting and fixing matt or rustic floor tiles on cement mortar base (1:4):
Matt or rustic floor tiles of size 600 mm x 600 mm and minimum thickness 9.8 mm foreign
Considering 100 sft work
1 Cost of tiles 100 sft @ Tk. 170.00 per sft = Tk. 17,000.00
Add wasta 5% = Tk. 850.00
2 Laying cost 100 sft @ Tk. 5,441.10 per % sft = Tk. 5,441.10
Sub - Total = Tk. 23,291.10
Profit 10.00% = Tk. 2,329.11
Overhead 3.50% = Tk. 815.19
Total = Tk. 26,435.40
Add VAT with adjustme1.06383 6.00% = Tk. 1,687.37
Grand Total = Tk. 28,122.77
Rate per sft = Tk. 281.23
Rate per sqm = Tk. 3,027.16
Say, Tk 3,027 .00 per sqm
07.1.1 Cost of concrete for individual and combined footings, pile cap, raft/mat floor slab, foundation beam up to plinth level
Considering 100 cft
(i) Materials (From Secondary Input : Item B-3) = Tk. ###
(ii) Laying/placing concrete (@ 1200 cft concreting usi = Tk. 999.83
(From Secondary Input : Item A-1) Sub - Total = Tk. ###
Profit 10.00% = Tk. 1,762.78
Overhead 3.50% = Tk. 616.97
Total = Tk. ###
Add VAT with a 1.06383 6.00% = Tk. 1,277.08
Grand Total = Tk. ###
Rate per cft = Tk. 212.85
Rate per cum= Tk. 7,516.80
Say, Tk. 7,517 .00 per cum
07.1.2 Cost of concrete for padestals, column, column capitals, lift walls and walls upto ground floor
Considering 100 cft
(i) Materials (From Secondary Input : Item B-3) = Tk. ###
(ii) Laying/placing concrete (@ 800 cft concreting usin = Tk. 1,499.75
(From Secondary Input : Item A-3) Sub - Total = Tk. ###
Profit 10.00% = Tk. 1,812.78
Overhead 3.50% = Tk. 634.47
Total = Tk. ###
Add VAT with a 1.06383 6.00% = Tk. 1,313.30
Grand Total = Tk. ###
Rate per cft = Tk. 218.88
Rate per cum= Tk. 7,729.75
Say, Tk. 7,730 .00 per cum
07.1.3 Cost of concrete for floor / roof slab, tee beams, ell beams and rectangular beams, tie Beam, lintels, stair case slab and steps etc.
upto ground floor
Considering 100 cft
(i) Materials (Fro = Tk. 16,628.00
(ii) Laying/placing concrete (@ 1000 cft concreting usi = Tk. 1,199.80
(From Secondary Input : Item A-2) Sub - Total = Tk. ###
Profit 10.00% = Tk. 1,782.78
Overhead 3.50% = Tk. 623.97
Total = Tk. ###
Add VAT with a 1.06383 6.00% = Tk. 1,291.57
Grand Total = Tk. ###
Rate per cft = Tk. 215.26
Rate per cum= Tk. 7,601.91
Say, Tk. 7,602 .00 per cum
07.1.4 Cost of concrete for cornice, railing, drop walls, louver, fins, sunshade, false ceiling, waffle and ribbed floor slab etc. up to ground
floor
Considering 100 cft
(i) Materials (Fro = Tk. 16,628.00
(ii) Laying/placing concrete (@ 600 cft concreting usin = Tk. 1,999.67
(From Secondary Input : Item A-4) Sub - Total = Tk. ###
Profit 10.00% = Tk. 1,862.77
Overhead 3.50% = Tk. 651.97
Total = Tk. ###
Add VAT with a 1.06383 6.00% = Tk. 1,349.52
Grand Total = Tk. ###
07.2.1 Cost of concrete for individual and combined footings, pile cap, raft/mat floor slab, foundation beam up to plinth level
Considering 100 cft
(i) Materials (From Secondary Input : Item B-4) = Tk. ###
(ii) Laying/placing concrete (@ 1200 cft concreting usi = Tk. 999.83
(From Secondary Input : Item A-1) Sub - Total = Tk. ###
Profit 10.00% = Tk. 2,771.23
Overhead 3.50% = Tk. 969.93
Total = Tk. ###
Add VAT with a 1.06383 6.00% = Tk. 2,007.67
Grand Total = Tk. ###
Rate per cft = Tk. 334.61
Rate per cum= Tk. ###
Say, Tk. 11,817 .00 per cum
07.2.2 Cost of concrete for padestals, column, column capitals, lift walls and walls upto ground floor
Considering 100 cft
(i) Materials (From Secondary Input : Item B-4) = Tk. ###
(ii) Laying/placing concrete (@ 800 cft concreting usin = Tk. 1,499.75
(From Secondary Input : Item A-2) Sub - Total = Tk. ###
Profit 10.00% = Tk. 2,821.23
Overhead 3.50% = Tk. 987.43
Total = Tk. ###
Add VAT with a 1.06383 6.00% = Tk. 2,043.89
Grand Total = Tk. ###
Rate per cft = Tk. 340.65
Rate per cum= Tk. ###
Say, Tk. 12,031 .00 per cum
07.2.3 Cost of concrete for floor / roof slab, tee beams, ell beams and rectangular beams, tie beam, lintels, stair case slab and steps etc.
upto ground Floor
Considering 100 cft
(i) Materials (Fro = Tk. 26,712.50
(ii) Laying/placing concrete (@ 1000 cft concreting usi = Tk. 1,199.80
(From Secondary Input : Item A-1) Sub - Total = Tk. ###
Profit 10.00% = Tk. 2,791.23
Overhead 3.50% = Tk. 976.93
Total = Tk. ###
Add VAT with a 1.06383 6.00% = Tk. 2,022.16
Grand Total = Tk. ###
Rate per cft = Tk. 337.03
Rate per cum= Tk. ###
Say, Tk. 11,903 .00 per cum
07.2.4 Cost of concrete for cornice, railing, drop walls, louver, fins, sunshade, false ceiling, waffle and ribbed floor slab etc. up to ground
floor
Considering 100 cft
(i) Materials (Fro = Tk. 26,712.50
(ii) Laying/placing concrete (@ 600 cft concreting usin = Tk. 1,999.67
(From Secondary Input : Item A-3) Sub - Total = Tk. ###
Profit 10.00% = Tk. 2,871.22
Overhead 3.50% = Tk. 1,004.93
07.3.1 Cost of concrete for individual and combined footings, pile cap, raft/mat floor slab, foundation beam up to plinth level
Considering 100 cft
(i) Materials (From Secondary Input : Item B-5) = Tk. ###
(ii) Laying/placing concrete (@ 1200 cft concreting usi = Tk. 999.83
(From Secondary Input : Item A-1) Sub - Total = Tk. ###
Profit 10.00% = Tk. 2,850.23
Overhead 3.50% = Tk. 997.58
Total = Tk. ###
Add VAT with a 1.06383 6.00% = Tk. 2,064.90
Grand Total = Tk. ###
Rate per cft = Tk. 344.15
Rate per cum= Tk. ###
Say, Tk. 12,154 .00 per cum
07.3.2 Cost of concrete for padestals, column, column capitals, lift walls and walls upto ground floor
Considering 100 cft
(i) Materials (From Secondary Input : Item B-5) = Tk. ###
(ii) Laying/placing concrete (@ 800 cft concreting usin = Tk. 1,499.75
(From Secondary Input : Item A-3) Sub - Total = Tk. ###
Profit 10.00% = Tk. 2,900.23
Overhead 3.50% = Tk. 1,015.08
Total = Tk. ###
Add VAT with a 1.06383 6.00% = Tk. 2,101.12
Grand Total = Tk. ###
Rate per cft = Tk. 350.19
Rate per cum= Tk. ###
Say, Tk. 12,367 .00 per cum
07.3.3 Cost of concrete for floor / roof slab, tee beams, ell beams and rectangular beams, tie Beam, lintels, stair case slab and steps etc.
upto ground floor
Considering 100 cft
(i) Materials (Fro = Tk. 27,502.50
(ii) Laying/placing concrete (@ 1000 cft concreting usi = Tk. 1,199.80
(From Secondary Input : Item A-2 Sub - Total = Tk. ###
Profit 10.00% = Tk. 2,870.23
Overhead 3.50% = Tk. 1,004.58
Total = Tk. ###
Add VAT with a 1.06383 6.00% = Tk. 2,079.39
Grand Total = Tk. ###
Rate per cft = Tk. 346.57
Rate per cum= Tk. ###
Say, Tk. 12,240 .00 per cum
07.3.4 Cost of concrete for cornice, railing, drop walls, louver, fins, sunshade, false ceiling, waffle and ribbed floor slab etc. up to ground
floor
Considering 100 cft
(i) Materials (Fro = Tk. 27,502.50
(ii) Laying/placing = Tk. 1,999.67
07.4.1 Cost of concrete for individual and Combined footings, pile cap, raft/mat Floor slab, foundation beam up to plinth level
Considering 100 cft
(i) Materials (From Secondary Input : Item B-6) = Tk. ###
(ii) Laying/placing concrete (@ 1200 cft concreting usi = Tk. 999.83
(From Secondary Input : Item A-1) Sub - Total Tk. ###
Profit 10.00% = Tk. 2,919.86
Overhead 3.50% = Tk. 1,021.95
Total = Tk. ###
Add VAT with a 1.06383 6.00% = Tk. 2,115.34
Grand Total = Tk. ###
Rate per cft = Tk. 352.56
Rate per cum= Tk. ###
Say, Tk. 12,451 .00 per cum
07.4.2 Cost of concrete for padestals, column, column capitals, lift walls and walls upto ground floor
Considering 100 cft
(i) Materials (From Secondary Input : Item B-6) = Tk. ###
(ii) Laying/placing concrete (@ 800 cft concreting usin = Tk. 1,499.75
(From Secondary Input : Item A-3) Sub - Total Tk. ###
Profit 10.00% = Tk. 2,969.85
Overhead 3.50% = Tk. 1,039.45
Total = Tk. ###
Add VAT with a 1.06383 6.00% = Tk. 2,151.56
Grand Total = Tk. ###
Rate per cft = Tk. 358.59
Rate per cum= Tk. ###
Say, Tk. 12,664 .00 per cum
07.4.3 Cost of concrete for floor / roof slab, tee beams, ell beams and rectangular beams, tie Beam, lintels, stair case slab and steps etc.
upto ground floor
Considering 100 cft
(i) Materials (Fro = Tk. 28,198.75
(ii) Laying/placing concrete (@ 1000 cft concreting usi = Tk. 1,199.80
(From Secondary Input : Item A-2) Sub - Total Tk. ###
Profit 10.00% = Tk. 2,939.86
Overhead 3.50% = Tk. 1,028.95
Total = Tk. ###
Add VAT with a 1.06383 6.00% = Tk. 2,129.83
Grand Total = Tk. ###
Rate per cft = Tk. 354.97
Rate per cum= Tk. ###
Say, Tk. 12,536 .00 per cum
07.4.4 Cost of concrete for cornice, railing, drop walls, louver, fins, sunshade, false ceiling, waffle and ribbed floor slab etc. up to ground
floor
Considering 100 cft
(i) Materials (Fro = Tk. 28,198.75
(ii) Laying/placing concrete (@ 600 cft concreting usin = Tk. 1,999.67
(From Secondary Input : Item A-4) Sub - Total Tk. ###
Profit 10.00% = Tk. 3,019.84
Overhead 3.50% = Tk. 1,056.94
Total = Tk. ###
Add VAT with a 1.06383 6.00% = Tk. 2,187.78
Grand Total = Tk. ###
Rate per cft = Tk. 364.63
Rate per cum= Tk. ###
Say, Tk. 12,877 .00 per cum
Item No.- 07.5
R.C.C work (1:1.:2) complete excluding the cost of reinforcement and its fabrication with stone chips & admixture
07.5.1 Cost of concrete for individual and combined footings, pile cap, raft/mat Floor slab, foundation beam up to plinth level
Considering 100 cft
(i) Materials (From Secondary Input : Item B-7) = Tk. ###
(ii) Laying/placing concrete (@ 1200 cft concreting usi = Tk. 999.83
(From Secondary Input : Item A-1) Sub - Total Tk. ###
Profit 10.00% = Tk. 3,029.98
Overhead 3.50% = Tk. 1,060.49
Total = Tk. ###
Add VAT with a 1.06383 6.00% = Tk. 2,195.13
Grand Total = Tk. ###
Rate per cft = Tk. 365.85
Rate per cum= Tk. ###
Say, Tk. 12,920 .00 per cum
07.5.2 Cost of concrete for padestals, column, column capitals, lift walls and walls upto ground floor
Considering 100 cft
(i) Materials (From Secondary Input : Item B-7) = Tk. ###
(ii) Laying/placing concrete (@ 800 cft concreting usin = Tk. 1,499.75
(From Secondary Input : Item A-2) Sub - Total Tk. ###
Profit 10.00% = Tk. 3,079.98
Overhead 3.50% = Tk. 1,077.99
Total = Tk. ###
Add VAT with a 1.06383 6.00% = Tk. 2,231.34
Grand Total = Tk. ###
Rate per cft = Tk. 371.89
Rate per cum= Tk. ###
Say, Tk. 13,134 .00 per cum
Item No.- 07.6
Fair-face concrete (1:1.5:3) complete excluding the cost of reinforcement and its fabrication with stone chips, grey cement, white cement &
admixture
07.9.4 Formwork/shuttering, prop and necessary supports etc. (steeper sqm = Tk. 337.13
Padestals, column, column capitals, lif Profit 10.00% = Tk. 33.71
(From Secondary Input : Item C-13) Overhead 3.50% = Tk. 11.80
Total = Tk. 382.64
Add VAT with adjustment factor 1.06383 6.00% = Tk. 24.42
Grand Tot = Tk. 407.06
Say, Tk. 408 .00 per sqm
07.9.5 Formwork/shuttering, prop and necessary supports etc. (steeper sqm = Tk. 346.28
Tie beam and lintels : Ground Floor Profit 10.00% = Tk. 34.63
(From Secondary Input : Item C-14) Overhead 3.50% = Tk. 12.12
Total = Tk. 393.03
Add VAT with adjustment factor 1.06383 6.00% = Tk. 25.09
Grand Tot = Tk. 418.12
Say, Tk. 419 .00 per sqm
07.9.6 Formwork/shuttering, prop and necessary supports etc. (steeper sqm = Tk. 376.42
Tee beams, Ell beams and RectangulaProfit 10.00% = Tk. 37.64
(From Secondary Input : Item C-15) Overhead 3.50% = Tk. 13.17
Total = Tk. 427.23
Add VAT with adjustment factor 1.06383 6.00% = Tk. 27.27
Grand Tot = Tk. 454.50
Say, Tk. 455 .00 per sqm
07.9.7 Formwork/shuttering, prop and necessary supports etc. (steeper sqm = Tk. 440.57
Floor and roof slab upto Ground Floor Profit 10.00% = Tk. 44.06
(From Secondary Input : Item C-16) Overhead 3.50% = Tk. 15.42
Total = Tk. 500.05
Add VAT with adjustment factor 1.06383 6.00% = Tk. 31.92
Grand Tot = Tk. 531.97
Say, Tk. 532 .00 per sqm
07.9.8 Formwork/shuttering, prop and necessary supports etc. (steeper sqm = Tk. 320.34
Cornice, railing, drop walls, louver, fin Profit 10.00% = Tk. 32.03
(From Secondary Input : Item C-17) Overhead 3.50% = Tk. 11.21
Total = Tk. 363.58
Add VAT with adjustment factor 1.06383 6.00% = Tk. 23.21
Grand Tot = Tk. 386.79
Say, Tk. 387 .00 per sqm
07.9.9 Formwork/shuttering, prop and necessary supports etc. (steeper sqm = Tk. 362.21
Sunshade, false ceiling : Ground Floor Profit 10.00% = Tk. 36.22
(From Secondary Input : Item C-18) Overhead 3.50% = Tk. 12.68
Total = Tk. 411.11
Add VAT with adjustment factor 1.06383 6.00% = Tk. 26.24
Grand Tot = Tk. 437.35
Say, Tk. 438 .00 per sqm
07.9.10 Formwork/shuttering, prop and necessary supports etc. (steeper sqm = Tk. 361.13
Stair case slab and steps upto GroundProfit 10.00% = Tk. 36.11
(From Secondary Input : Item C-19) Overhead 3.50% = Tk. 12.64
Total = Tk. 409.88
Add VAT with adjustment factor 1.06383 6.00% = Tk. 26.16
Grand Tot = Tk. 436.04
Say, Tk. 437 .00 per sqm
1 Hire charge o 1/4 day @ Tk. 600.00 per day = Tk. 150.00
2 Hire charge of 1 trip @ Tk. 350.00 per trip = Tk. 350.00
3 Hire charge of 1 trip @ Tk. 1,700.00 per trip = Tk. 1,700.00
4 Pump operator1/4 no @ Tk. 600.00 per nos = Tk. 150.00
5 Ordinary labou1/2 no @ Tk. 320.00 per nos = Tk. 160.00
6 Sundries and incidental cost LS = Tk. 100.00
Total (A+B) = Tk. 2,610.00
Profit 10.00% = Tk. 261.00
Overhead 3.50% = Tk. 91.35
Total = Tk. 2,962.35
Add VAT with adjustme1.06383 6.00% = Tk. 189.09
Grand Total = Tk. 3,151.44
Rate per cft = Tk. 15.76
Rate per cum = Tk. 556.56
Say, Tk. 557 .00 per cum
Analysis of PW 196
Sub - Total = Tk. 350,537.19
Profit 10.00% = Tk. 35,053.72
Overhead 3.50% = Tk. 12,268.80
Total = Tk. 397,859.71
Add VAT with a 1.06383 6.00% = Tk. 25,395.31
Grand Total = Tk. 423,255.02
Say, Tk. 423,255 . 00 per test
Tk. 1,058 per Mton test
Item No.- 09.9
9.9.1 For intermediate loading from 50 tonneper tonne Tk. 1,349
9.9.2 For intermediate loading from 100 tonne
per tonne Tk. 1,193
9.9.3 For intermediate loading from 150 tonne
per tonne Tk. 1,138
9.9.4 For intermediate loading from 200 tonne
per tonne Tk. 1,114
9.9.5 For intermediate loading from 250 tonne
per tonne Tk. 1,094
9.9.6 For intermediate loading from 300 tonne
per tonne Tk. 1,077
9.9.7 For intermediate loading from 350 tonne
per tonne Tk. 1,064
i) 40 x 40 x 6 mm M.S Angle.
TOP 1 X 18 X 13' 246.06 rft
BOTTOM 1 X 18 X 219.06 rft
WALL SIDE 1 X 1 27.00 rft
VERTICAL TIE 1 21.06 rft
VERTICAL TIE 1 14.94 rft
VERTICAL TIE 1 9.00 rft
VERTICAL TIE(EN 41.94 rft
INCLINED TIE 1 X 306.00 rft
PURLINE(horiz. p 400.00 rft
DIVISION 11. WOOD WORKS IN DOOR AND WINDOW FRAME, ROOF TRUSS AND RAILINGS
Analysis of 237
(a) Fittings: Same as item No.- 12. = Tk. 957.00
(b) Labour: Same as item No.- 12. = Tk. 3,750.00
(c) Qty. of wood: 3.16 cft @ Tk. 6,500.00 per cft = Tk. 20,540.00
Sub - Total = Tk. 25,247.00
Profit 10.00% = Tk. 2,524.70
Overhea 3.50% = Tk. 883.65
Total = Tk. 28,655.35
Add VAT with1.06383 6.00% = Tk. 1,829.07
Grand Total = Tk. 30,484.42
Rate per sft = Tk. 1,487.04
Rate per sqm = Tk. 16,006.50
Say, Tk 16,007 .00 per sqm
A) Cost of materials
Ctg. Teak Wood
5 1/4" X 1 1/2" X 6'-10" 0.87 cft
9 1/4" X 3 3/4" X 3'-0" X 0.34 "
6 1/4" X 1 3/4" X 3'-0" X 0.46 "
For foreign 4 1/4" X 1 3/4" X 1'-0" X 0.05 "
Panel 7 1/2" X 1 3/4" X 3'-0" X 1.09 "
7 1/2" X 1 3/4" X 2'-6" X 0.91 "
= 3.72 cft Tk. 4,390.00 per cft = Tk. 16,330.80
B) Cost of labour
i) Carpenter 3 nos @ Tk. 600.00 per day = Tk. 1,800.00
ii) Carpenter h 5 nos @ Tk. 390.00 per day = Tk. 1,950.00
iii) Extra cost for design
a) Carpenter 3 nos @ Tk. 600.00 per day = Tk. 1,800.00
b) Carpenter h 2 nos @ Tk. 390.00 per day = Tk. 780.00
C) Fitting
i) 10" long bras 1 no @ Tk. 50.00 each = Tk. 50.00
ii) 8" long bras 1 no @ Tk. 300.00 each = Tk. 300.00
iii) Brass Hasp 1 no @ Tk. 375.00 each = Tk. 375.00
iv) 4" long bra 4 nos @ Tk. 150.00 each = Tk. 600.00
v) Brass Handl 2 nos @ Tk. 100.00 each = Tk. 200.00
vi) Brass scre 1 dozens @ Tk. 20.00 per dozens = Tk. 20.00
vii) Hinged clea 1 set @ Tk. 62.00 per set = Tk. 62.00
Sub - Total = Tk. 24,267.80
Profit 10.00% = Tk. 2,426.78
Overhead 3.50% = Tk. 849.37
Total = Tk. 27,543.95
Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,758.12
Grand Total = Tk. 29,302.07
Rate per sft = Tk. 1,430.07
Rate per sqm = Tk. 15,393.27
Say, Tk. 15,393 .00 per sqm
12.7.2
For Champ veneered
For 1 No. shutter
Considering 6'-10" x 3'-0"= 20.5 sft (single leaf)
(a) Fittings: Same as- 12.7.1 = Tk. 657.00
(b) Labour: Same as- 12.7.1 = Tk. 345.00
(c) Cost of shutter
Qty. Same as 1 20.5 sft @ Tk. 240.00 = Tk. 4,920.00
Sub - Total = Tk. 5,922.00
Profit 10.00% = Tk. 592.20
Overhead 3.50% = Tk. 207.27
Total = Tk. 6,721.47
Add VAT with adjustme1.06383 6.00% = Tk. 429.03
Grand Total = Tk. 7,150.50
Rate per sft = Tk. 348.80
Rate per sqm = Tk. 3,754.48
Say, Tk. 3,754 .00 per sqm
12.7.3
For Chapalish veneered
For 1 No. shutter
Considering 6'-10" x 3'-0"= 20.5 sft (single leaf)
(a) Fittings: Same as 12.7.1 = Tk. 657.00
(b) Labour: Same as 12.7.1 = Tk. 345.00
(c) Cost of shutter
Qty. Same as 1 20.5 sft @ Tk. 240.00 = Tk. 4,920.00
Sub - Total = Tk. 5,922.00
Profit 10.00% = Tk. 592.20
Overhead 3.50% = Tk. 207.27
Total = Tk. 6,721.47
Add VAT with adjustment factor 1.06383 6.00% = Tk. 429.03
Grand Total = Tk. 7,150.50
Rate per sft = Tk. 348.80
Rate per sqm = Tk. 3,754.48
Say, Tk. 3,754 .00 per sqm
12.7.4
For Garjan veneered
For 1 No. shutter
Considering 6'-10" x 3'-0"= 20.5 sft (single leaf)
(a) Fittings: Same as 12.7.1 = Tk. 657.00
(b) Labour: Same as 12.7.1 = Tk. 345.00
(c) Cost of shutter
Qty.: Same as 20.5 sft @ Tk. 250.00 = Tk. 5,125.00
Sub - Total = Tk. 6,127.00
Profit 10.00% = Tk. 612.70
Overhead 3.50% = Tk. 214.45
Total = Tk. 6,954.15
Add VAT with adjustment factor 1.06383 6.00% = Tk. 443.88
Grand Total = Tk. 7,398.03
Rate per sft = Tk. 360.88
Rate per sqm = Tk. 3,884.51
Say, Tk. 3,885 .00 per sqm
Analysis of 256
(b) Labour: Same as item No. 12.12.1 = Tk. 2,025.00
(c) Cost of wood:
Wood req: Sam 1.567 cft @ Tk. 2,390.00 per cft = Tk. 3,745.13
Sub - Total = Tk. 6,546.51
Profit 10.00% = Tk. 654.65
Overhead 3.50% = Tk. 229.13
Total = Tk. 7,430.29
Add VAT with1.06383 6.00% = Tk. 474.27
Grand Total = Tk. 7,904.56
Rate per sft = Tk. 574.88
Rate per sqm = Tk. 6,188.01
Say, Tk 6,188 .00 per sqm
Analysis of 258
For 1 No. glazed window shutter
Considering 3'-7" x 3'-7"= 12.84 sft of work (4'-0" x 4'-0" opening)
For Chittagong teak wood
(a) Fittings in/c glass panes: Same as item No. 12.13.1 = Tk. 542.94
(b) Labour Same as item No. 12.13.1 = Tk. 2,025.00
(c) Cost of wood
Wood req.: Sa 2.627 cft @ Tk. 4,390.00 per cft = Tk. 11,532.53
Sub - Total = Tk. 14,100.47
Profit 10.00% = Tk. 1,410.05
Overhead 3.50% = Tk. 493.52
Total = Tk. 16,004.04
Add VAT with1.06383 6.00% = Tk. 1,021.53
Grand Total = Tk. 17,025.57
Rate per sft = Tk. 1,325.98
Rate per sqm = Tk. 14,272.85
Say, Tk 14,273 .00 per sqm
Analysis of 267
Item No.- 12.21
Extra cost for using brass/ SS fittings in place of iron fittings in doors & windows for all floors (super quality local).
12.21.1 Brass fittings for 1 No. of door
For 20.5 sft of work
Fittings Qty. Unit Price for iron Price for brass
(i) 12" long tower 1 no Tk. 50.00 Tk. 400.00
(ii) 8" socket bolt 1 no Tk. 50.00 Tk. 300.00
(iii) 4" long hinges 4 nos Tk. 260.00 Tk. 600.00
(iv) Nickle plated h 2 nos Tk. 150.00 Tk. 200.00
(v) Screws 5 dzn Tk. 85.00 Tk. 100.00
(vi) Hinge cleat 1 no Tk. 20.00 Tk. 20.00
(vii) Screws for hing 0.5 dzn Tk. 8.50 Tk. 10.00
Total= Tk. 623.50 Tk. 1,630.00
Extra cost for brass= Tk. 1,006.50
Profit 10.00% = Tk. 100.65
Overhea 3.50% = Tk. 35.23
Total = Tk. 1,142.38
Add VAT with1.06383 6.00% = Tk. 72.92
Grand Total = Tk. 1,215.30
Rate per sft = Tk. 59.28
Rate per sqm = Tk. 638.09
Say, Tk. 638 .00 per sqm
(iii) 12 x 12 mm M.S hollow square box (Made with 16 BG MS Plate) (2.55 lb/sft weight)
(perimeter of Plate 44.45 mm)
13 x 6'-6" = 84.50 rft
Add 5% wastag 4.23 rft
= 88.73 rft
= 12.94 sft
= 33.00 lb @ Tk. 24.94 per Ib = Tk. 823.02
(b) Workshop charge:
Labour cost for manufacturing, welding
including supply of necessary electrode, cutting steel
to required siz 29.25 sft @ Tk. 45.00 per sft Tk. 1,316.25
(c) Labour charges:
Labour charges for fitting and fixing in position of grills
(i) mason 1 no @ Tk. 600.00 per day = Tk. 600.00
(ii) skilled labour 1 no @ Tk. 390.00 per day = Tk. 390.00
(d) Carriage charge for steel materials from market to
workshop and carrying the window grill
from workshop t 1 no @ Tk. 80.00 each = Tk. 80.00
(e) Cost of CC, curing, incidental, sundries L.S = Tk. 172.64
Sub - Total = Tk. 4,505.71
DIVISION 17: LIME TERRACING, ROOF TOP WATER PROOFING FOR GARDEN AND SWIMMIMG POOL
1 Cost of SS materials
a) 62 mm dia SS pipe
1 x 17'-0" = 17.00 rft
Add 5% wasta 0.85 rft
= 17.85 rft @ Tk. 248.00 per rft = Tk. 4,426.80
b) 50 x 62 x 2 17.5 rft @ Tk. 300.00 per rft = Tk. 5,250.00
c) Base plate 5 nos @ Tk. 150.00 each = Tk. 750.00
d) Royal bolt 20 nos @ Tk. 50.00 each = Tk. 1,000.00
e) SS base cup 5 nos @ Tk. 200.00 each = Tk. 1,000.00
2 Fabrication and making post of railing support etc.
i) Welder / Fab 1.30 nos @ Tk. 600.00 per day = Tk. 780.00
ii) Welder help 2.60 nos @ Tk. 390.00 per day = Tk. 1,014.00
iii) Ordinay lab 2.60 nos @ Tk. 320.00 per day = Tk. 832.00
3 Scaffolding 100.00 sft @ Tk. 9.00 per sft = Tk. 900.00
4 Welding Rod(El 60.00 nos @ Tk. 10.00 each = Tk. 600.00
5 Argon gas, Filler rod, Tungsten rod Gardening disk electricity, woven LS = Tk. 3,500.00
Considering 10 steps
Total rft of nosing: 10 x 3'-6"= 35 rft
(a) Cost of cutting @ 3 nos of grooves per steps
for fixing 1.5" x 1.5" x 3.5" size clamps
(i) Mason 0.25 No. @ Tk. 500.00 per day = Tk. 125.00
(ii) Skilled labour 0.5 No. @ Tk. 390.00 per day = Tk. 195.00
(b) Cost of CC (1:2:4) with smaller size of chips for fixing clamps:
30 x 1.5" x1.5" 0.14 cft @ Tk. 17,763.63 per % cft = Tk. 24.87
(c) Cost of 1.5" x 1.5" x 1/4" M.S. angle: @ 2.34 Ibs per rft
10 x 3'-6"= 35 rft
Add wastage 1.75 rft
= 36.75 rft
= 86.00 Ibs @ Tk. 24.94 per Ib = Tk. 2,144.84
(d) Cost of 3/4" x 1/8" F.I. bar for clamps: @ 0.32 Ibs per rft
10 x 3 x 3"= 7.5 rft
Add wastage 0.375 rft
= 7.875 rft
= 2.52 Ibs @ Tk. 24.94 per Ib = Tk. 62.85
(e) Cutting charge of M.S. angle as per required measurement
in/c cost of T & 10 nos @ Tk. 8.00 each = Tk. 80.00
(f) Cost of welding of 3/4" x 1/8" F.I. bar for fixing one end with angle including
bifercating on 30 nos @ Tk. 8.00 each = Tk. 240.00
(g) Labour charge for fixing up the M.S. angle in the nosing of steps to
keep the angles in level and parallel with each of the steps properly
(i) Mason 0.5 no @ Tk. 500.00 per day = Tk. 250.00
(ii) Ordinary labou 0.5 no @ Tk. 320.00 per day = Tk. 160.00
Sub - Total = Tk. 3,282.56
Profit 10.00% = Tk. 328.26
Overhead 3.50% = Tk. 114.89
Total = Tk. 3,725.71
Add VAT with adjustment factor 1.06383 6.00% = Tk. 237.81
Grand Total = Tk. 3,963.52
Rate per rft = Tk. 113.24
Rate per rm = Tk. 371.54
Say, Tk. 372 .00 per meter
(a) Materials:
(i) 1.5" x 1.5" x 1/4" M.S. angle: @ 2.34 Ibs per rft
2 x 3'-3"= 6.50 rft
Horizontal: 2 x 15.50 rft
= 22 rft
Add wastage 1.1 rft
23.1 rft
= 54.05 Ibs @ Tk. 24.94 Per lb. = Tk. 1,348.01
(ii) 1/4" dia M.S. rod: @ 0.167 lbs per rft
20 x 3'-3"= 65.00 rft
8 x 7'-9"= 62.00 rft
127.00 rft
Add wastage 6.35 rft
= 133.35 rft
= 22.27 lbs @ Tk. 26.30 per Ib = Tk. 585.70
(b) Fittings, hardwares and consumables:
(i) Electrodes in/c 35.00 nos @ Tk. 10.00 each = Tk. 350.00
(c) Labour for making grill fencing
(i) Welder / fabric 1.00 no @ Tk. 600.00 per day = Tk. 600.00
(ii) Welder helper 1.00 no @ Tk. 390.00 per day = Tk. 390.00
(iii) Ordinary labou 1.00 no @ Tk. 320.00 per day = Tk. 320.00
(d) Carrying of materials to work-shop and fabricated materials to site: = Tk. 240.00
Analysis of PW 428
Rate per sft = Tk. 146.03
Rate per sqm= Tk. 1,571.28
23.7.1 For ground floor = Tk. 1,572.00
23.7.2.1 Add for each additional floor up to 5th floor = Tk. 18.00
23.7.2.2 Add for each additional floor for 6th floor to 9th floo= Tk. 28.00
23.7.2.3 Add for each additional floor for 10th floor & above = Tk. 32.00
26.1.2 Coloured commode (Bangladeshi), size 465 x 340 x 415 mm, wt.: 14 kg or equivalent
Considering 1 No. of fixture
1 Coloured com 1 no @ Tk. 1,530.00 each = Tk. 1,530.00
2 Accessories:
(a) Seat cover 1 no @ Tk. 510.00 each = Tk. 510.00
3 Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag @ Tk. 395.00 per bag = Tk. 39.50
(ii) Sand (F.M. 1.2 0.5 cft @ Tk. 1,400.00 per % cft = Tk. 7.00
(b) Nuts with wash 4 nos @ Tk. 26.00 each = Tk. 104.00
4 Labour:
(a) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(b) Skilled labour 0.5 no @ Tk. 390.00 each = Tk. 195.00
(c) Ordinary labou 0.5 no @ Tk. 320.00 each = Tk. 160.00
Sub - Total = Tk. 2,695.50
Profit 10.00% = Tk. 269.55
Overhead 3.50% = Tk. 94.34
Total = Tk. 3,059.39
Add VAT with adjustment factor 1.06383 6.00% = Tk. 195.28
Grand Total = Tk. 3,254.67
Rate per No. = Tk. 3,254.67
Say, Tk. 3,255 .00 each
26.1.3 Special coloured commode (Bangladeshi), size 465 x 340 x 415 mm, wt.: 14 kgor equivalent
Considering 1 No. of fixture
1 Special colou 1 no @ Tk. 1,670.00 each = Tk. 1,670.00
2 Accessories:
(a) Seat cover 1 no @ Tk. 510.00 each = Tk. 510.00
3 Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag @ Tk. 395.00 per bag = Tk. 39.50
(ii) Sand (F.M. 1.2 0.5 cft @ Tk. 1,400.00 per % cft = Tk. 7.00
26.2.3 Special coloured low -down (Bangladeshi), size 490 x 190 x 350 mm, wt.: 14 kg or equivalent
Considering 1 No. of fixture
1 Special colour 1 no @ Tk. 1,600.00 each = Tk. 1,600.00
2 Accessories:
(a) 32 mm dia plast 1 no @ Tk. 75.00 each = Tk. 75.00
3 Fitting fixing materials:
(a) Clamp 2 nos @ Tk. 50.00 each = Tk. 100.00
(i) 50 mm rowel pl 4 nos @ Tk. 9.00 each = Tk. 36.00
(ii) 75 mm screw, r 3 nos @ Tk. 13.00 each = Tk. 39.00
4 Labour:
(a) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(b) Skilled labour 0.5 no @ Tk. 390.00 each = Tk. 195.00
Sub - Total = Tk. 2,195.00
Profit 10.00% = Tk. 219.50
Overhead 3.50% = Tk. 76.83
Total = Tk. 2,491.33
Add VAT with adjustment factor 1.06383 6.00% = Tk. 159.02
Grand Total = Tk. 2,650.35
Rate per No. = Tk. 2,650.35
Say, Tk. 2,650 .00 each
Item No.- 26.3 Supplying, fitting and fixing European type glazed porcelain Combi closet
26.3.1 Supplying, fitting and fixing European type glazed porcelain Combi closet, in/c plastic seat cover, cistern system
26.3.1.1 Light colour (Ivory/ Alpine White/ Grey/ Pink/ Blue/ Aqua Verde) 670 x 365 x 755 mm, 31.0 kg or equivalent
Considering 1 No. of fixture
1 White Combicl 1 no @ Tk. 6,040.00 each = Tk. 6,040.00
2 Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag @ Tk. 395.00 per bag = Tk. 39.50
(ii) Sand (F.M. 1.2 0.5 cft @ Tk. 1,400.00 per % cft = Tk. 7.00
(b) Nuts with wash 4 nos @ Tk. 26.00 each = Tk. 104.00
4 Labour:
(a) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(b) Skilled labour 1 no @ Tk. 390.00 each = Tk. 390.00
(c) Ordinary labou 0.5 no @ Tk. 320.00 each = Tk. 160.00
Sub - Total = Tk. 6,890.50
Profit 10.00% = Tk. 689.05
Overhead 3.50% = Tk. 241.17
Total = Tk. 7,820.72
Add VAT with adjustment factor 1.06383 6.00% = Tk. 499.19
Grand Total = Tk. 8,319.91
Rate per No. = Tk. 8,319.91
Say, Tk. 8,320 .00 each
26.3.1.2 Coloured combicloset Coloured (Marble Shade), 670 x 365 x 755 mm,31.0 kg or equivalent
Considering 1 No. of fixture
1 Coloured combi 1 no @ Tk. 7,850.00 each = Tk. 7,850.00
2 Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag @ Tk. 395.00 per bag = Tk. 39.50
(ii) Sand (F.M. 1.2 0.5 cft @ Tk. 1,400.00 per % cft = Tk. 7.00
(b) Nuts with wash 4 nos @ Tk. 26.00 each = Tk. 104.00
4 Labour:
(a) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(b) Skilled labour 1 no @ Tk. 390.00 each = Tk. 390.00
(c) Ordinary labou 0.5 no @ Tk. 320.00 each = Tk. 160.00
Sub - Total = Tk. 8,700.50
Profit 10.00% = Tk. 870.05
Overhead 3.50% = Tk. 304.52
26.3.1.3 Special coloured combicloset Special coloured (Deep Blue/ Ruby/ Rain Forest/ Green), 670 x 365 x 755 mm,31.0 kg or equivalent
or equivalent
Considering 1 No. of fixture
1 Special colour 1 no @ Tk. 9,060.00 each = Tk. 9,060.00
2 Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag @ Tk. 395.00 per bag = Tk. 39.50
(ii) Sand (F.M. 1.2 0.5 cft @ Tk. 1,400.00 per % cft = Tk. 7.00
(b) Nuts with wash 4 nos @ Tk. 26.00 each = Tk. 104.00
4 Labour:
(a) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(b) Skilled labour 1 no @ Tk. 390.00 each = Tk. 390.00
(c) Ordinary labou 0.5 no @ Tk. 320.00 each = Tk. 160.00
Sub - Total = Tk. 9,910.50
Profit 10.00% = Tk. 991.05
Overhead 3.50% = Tk. 346.87
Total = Tk. 11,248.42
Add VAT with adjustment factor 1.06383 6.00% = Tk. 717.98
Grand Total = Tk. 11,966.40
Rate per No. = Tk. 11,966.40
Say, Tk. 11,966 .00 each
26.3.2.1 Light colour (Ivory/ Alpine White/ Grey/ Pink/ Blue/ Aqua Verde), 700x370x795mm, 32.5kg or Equivalent
Considering 1 No. of fixture
1 White Combicl 1 no @ Tk. 7,130.00 each = Tk. 7,130.00
2 Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag @ Tk. 395.00 per bag = Tk. 39.50
(ii) Sand (F.M. 1.2 0.5 cft @ Tk. 1,400.00 per % cft = Tk. 7.00
(b) Nuts with wash 4 nos @ Tk. 26.00 each = Tk. 104.00
4 Labour:
(a) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(b) Skilled labour 1 no @ Tk. 390.00 each = Tk. 390.00
(c) Ordinary labou 0.5 no @ Tk. 320.00 each = Tk. 160.00
Sub - Total = Tk. 7,980.50
Profit 10.00% = Tk. 798.05
Overhead 3.50% = Tk. 279.32
Total = Tk. 9,057.87
Add VAT with adjustment factor 1.06383 6.00% = Tk. 578.16
Grand Total = Tk. 9,636.03
Rate per No. = Tk. 9,636.03
Say, Tk. 9,636 .00 each
26.3.2.2 Coloured (Mar700x370x795mm , 32.5kg or Equivalent
Considering 1 No. of fixture
1 White Combicl 1 no @ Tk. 9,270.00 each = Tk. 9,270.00
3 Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag @ Tk. 395.00 per bag = Tk. 39.50
(ii) Sand (F.M. 1.2 0.5 cft @ Tk. 1,400.00 per % cft = Tk. 7.00
(b) Nuts with wash 4 nos @ Tk. 26.00 each = Tk. 104.00
4 Labour:
26.3.3.3 Special coloured (Deep Blue/ Ruby/ Rain Forest/ Green), 700x360x785 mm, 38 kg
Considering 1 No. of fixture
1 White Combicl 1 no @ Tk. 14,925.00 each = Tk. 14,925.00
2 Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag @ Tk. 395.00 per bag = Tk. 39.50
(ii) Sand (F.M. 1.2 0.5 cft @ Tk. 1,400.00 per % cft = Tk. 7.00
(b) Nuts with wash 4 nos @ Tk. 26.00 each = Tk. 104.00
4 Labour:
(a) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(b) Skilled labour 1 no @ Tk. 390.00 each = Tk. 390.00
(c) Ordinary labou 0.5 no @ Tk. 320.00 each = Tk. 160.00
Sub - Total = Tk. 15,775.50
Profit 10.00% = Tk. 1,577.55
Overhead 3.50% = Tk. 552.14
Total = Tk. 17,905.19
Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,142.88
Grand Total = Tk. 19,048.07
Rate per No. = Tk. 19,048.07
Say, Tk. 19,048 .00 each
26.3.4 Supplying, fitting and fixing European type glazed porcelain Combi closet, approx. 340x730x785 mm size, approx. 36.75 kg by
weigh White / Ivory colour in/c plastic seat cover
26.4.1.1 Light colour (Ivory/ Alpine White/ Grey/ Pink/ Blue/ Aqua Verde), 725x360x840 mm size, 42.7 kg
Considering 1 No. of fixture
1 White combiclo 1 no @ Tk. 12,640.00 each = Tk. 12,640.00
2 Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag @ Tk. 395.00 per bag = Tk. 39.50
(ii) Sand (F.M. 1.2 0.5 cft @ Tk. 1,400.00 per % cft = Tk. 7.00
(b) Nuts with wash 4 nos @ Tk. 26.00 each = Tk. 104.00
4 Labour:
(a) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(b) Skilled labour 1 no @ Tk. 390.00 each = Tk. 390.00
(c) Ordinary labou 0.5 no @ Tk. 320.00 each = Tk. 160.00
Sub - Total = Tk. 13,490.50
Profit 10.00% = Tk. 1,349.05
Overhead 3.50% = Tk. 472.17
Total = Tk. 15,311.72
Add VAT with adjustment factor 1.06383 6.00% = Tk. 977.34
Grand Total = Tk. 16,289.06
Rate per No. = Tk. 16,289.06
Say, Tk. 16,289 .00 each
26.4.1.3 Special coloured (Deep Blue/ Ruby/ Rain Forest/ Green), 725x360x840 mm size, 42.7 kg
Considering 1 No. of fixture
1 White combiclo 1 no @ Tk. ### each = Tk. 18,950.00
2 Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag @ Tk. 395.00 per bag = Tk. 39.50
(ii) Sand (F.M. 1.2 0.5 cft @ Tk. 1,400.00 per % cft = Tk. 7.00
(b) Nuts with wash 4 nos @ Tk. 26.00 each = Tk. 104.00
4 Labour:
(a) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(b) Skilled labour 1 no @ Tk. 390.00 each = Tk. 390.00
(c) Ordinary labou 0.5 no @ Tk. 320.00 each = Tk. 160.00
Sub - Total = Tk. 19,800.50
Profit 10.00% = Tk. 1,980.05
26.4.2 Supplying, fitting and fixing European type glazed combi closet, White colour 370x760x800 mm size, 44.69 kg by weight, in/c
plastic seat cover
26.5.1.3 Special coloured long pan with foot-rest 530x430x210 mm 12.5 kg or equivalent
Considering 1 No. of fixture
1 Special coloure 1 no @ Tk. 1,330.00 each = Tk. 1,330.00
2 Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag @ Tk. 395.00 per bag = Tk. 39.50
(ii) Sand (F.M. 1.2 0.5 cft @ Tk. 1,400.00 per % cft = Tk. 7.00
3 Labour:
(a) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(b) Skilled labour 0.5 no @ Tk. 390.00 each = Tk. 195.00
(c) Ordinary labou 0.5 no @ Tk. 320.00 each = Tk. 160.00
Sub - Total = Tk. 1,881.50
Profit 10.00% = Tk. 188.15
Overhead 3.50% = Tk. 65.85
Total = Tk. 2,135.50
Add VAT with adjustment factor 1.06383 6.00% = Tk. 136.31
Grand Total = Tk. 2,271.81
Rate per No. = Tk. 2,271.81
Say, Tk. 2,272 .00 each
26.9.2.2 Coloured
Considering 1 No. of fixture
1 Coloured wash 1 no @ Tk. 1,167.00 each = Tk. 1,167.00
2 Accessories:
(a) 32 mm dia PVC 1 no @ Tk. 150.00 each = Tk. 150.00
(b) Grating with br 1 no @ Tk. 300.00 each = Tk. 300.00
(c) CP chain with 1 no @ Tk. 80.00 each = Tk. 80.00
3 Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.01 bag @ Tk. 395.00 per bag = Tk. 3.95
(ii) Sand (F.M. 1.2 0.05 cft @ Tk. 1,400.00 per % cft = Tk. 0.70
(b) CI brakets 1 pair @ Tk. 115.00 per pair = Tk. 115.00
4 Labour:
(a) Plumber 0.15 no @ Tk. 600.00 each = Tk. 90.00
(b) Skilled labour 0.2 no @ Tk. 390.00 each = Tk. 78.00
(c) Ordinary labou 0.4 no @ Tk. 320.00 each = Tk. 128.00
Sub - Total = Tk. 2,112.65
Profit 10.00% = Tk. 211.27
Overhead 3.50% = Tk. 73.94
Total = Tk. 2,397.86
Add VAT with adjustment factor 1.06383 6.00% = Tk. 153.05
Grand Total = Tk. 2,550.91
Rate per No. = Tk. 2,550.91
Say, Tk. 2,551 .00 each
26.9.3.2 Coloured
Considering 1 No. of fixture
1 Coloured wash 1 no @ Tk. 984.00 each = Tk. 984.00
2 Accessories:
(a) 32 mm dia PVC 1 no @ Tk. 150.00 each = Tk. 150.00
(b) Grating with br 1 no @ Tk. 300.00 each = Tk. 300.00
(c) CP chain with 1 no @ Tk. 80.00 each = Tk. 80.00
3 Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.01 bag @ Tk. 395.00 per bag = Tk. 3.95
(ii) Sand (F.M. 1.2 0.05 cft @ Tk. 1,400.00 per % cft = Tk. 0.70
(b) CI brakets 1 pair @ Tk. 115.00 per pair = Tk. 115.00
4 Labour:
(a) Plumber 0.15 no @ Tk. 600.00 each = Tk. 90.00
(b) Skilled labour 0.2 no @ Tk. 390.00 each = Tk. 78.00
(c) Ordinary labou 0.4 no @ Tk. 320.00 each = Tk. 128.00
Sub - Total = Tk. 1,929.65
Profit 10.00% = Tk. 192.97
Overhead 3.50% = Tk. 67.54
Analysis of PWD 463
Total = Tk. 2,190.16
Add VAT with adjustment factor 1.06383 6.00% = Tk. 139.80
Grand Total = Tk. 2,329.96
Rate per No.= Tk. 2,329.96
Say, Tk. 2,330 .00 each
26.9.4.2 Coloured
Considering 1 No. of fixture
1 Coloured wash 1 no @ Tk. 698.00 each = Tk. 698.00
26.9.5.2 Coloured
Considering 1 No. of fixture
1 Coloured wash 1 no @ Tk. 635.00 each = Tk. 635.00
2 Accessories:
(a) 32 mm dia PVC 1 no @ Tk. 150.00 each = Tk. 150.00
(b) Grating with br 1 no @ Tk. 300.00 each = Tk. 300.00
(c) CP chain with 1 no @ Tk. 80.00 each = Tk. 80.00
3 Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.01 bag @ Tk. 395.00 per bag = Tk. 3.95
(ii) Sand (F.M. 1.2 0.05 cft @ Tk. 1,400.00 per % cft = Tk. 0.70
(b) CI brakets 1 pair @ Tk. 115.00 per pair = Tk. 115.00
4 Labour:
(a) Plumber 0.15 no @ Tk. 600.00 each = Tk. 90.00
(b) Skilled labour 0.2 no @ Tk. 390.00 each = Tk. 78.00
(c) Ordinary labou 0.4 no @ Tk. 320.00 each = Tk. 128.00
Sub - Total = Tk. 1,580.65
Profit 10.00% = Tk. 158.07
Overhead 3.50% = Tk. 55.32
Total = Tk. 1,794.04
Add VAT with adjustment factor 1.06383 6.00% = Tk. 114.51
Grand Total = Tk. 1,908.55
Rate per No. = Tk. 1,908.55
Say, Tk. 1,909 .00 each
26.9.6.2 Coloured
Considering 1 No. of fixture
1 Coloured wash 1 no @ Tk. 1,014.00 each = Tk. 1,014.00
2 Accessories:
(a) 32 mm dia PVC 1 no @ Tk. 150.00 each = Tk. 150.00
(b) Grating with br 1 no @ Tk. 300.00 each = Tk. 300.00
(c) CP chain with 1 no @ Tk. 80.00 each = Tk. 80.00
3 Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.01 bag @ Tk. 395.00 per bag = Tk. 3.95
(ii) Sand (F.M. 1.2 0.05 cft @ Tk. 1,400.00 per % cft = Tk. 0.70
(b) CI brakets 1 pair @ Tk. 115.00 per pair = Tk. 115.00
4 Labour:
(a) Plumber 0.15 no @ Tk. 600.00 each = Tk. 90.00
(b) Skilled labour 0.2 no @ Tk. 390.00 each = Tk. 78.00
(c) Ordinary labou 0.4 no @ Tk. 320.00 each = Tk. 128.00
Sub - Total = Tk. 1,959.65
Profit 10.00% = Tk. 195.97
Overhead 3.50% = Tk. 68.59
Total = Tk. 2,224.21
Add VAT with adjustment factor 1.06383 6.00% = Tk. 141.97
Grand Total = Tk. 2,366.18
Rate per No. = Tk. 2,366.18
Say, Tk. 2,366 .00 each
26.9.6.3 Coloured
Considering 1 No. of fixture
1 Coloured wash 1 no @ Tk. 1,064.00 each = Tk. 1,064.00
2 Accessories:
(a) 32 mm dia PVC 1 no @ Tk. 150.00 each = Tk. 150.00
26.9.7 Supplying, fitting and fixing White or Ivory colour , 560x410x205mm,7.90 kg glazed vitreous W/H Wash Basin excluding pedastal
Considering 1 No. of fixture
1 Coloured wash 1 no @ Tk. 3,150.00 each = Tk. 3,150.00
2 Accessories:
(a) 32 mm dia PVC 1 no @ Tk. 150.00 each = Tk. 150.00
(b) Grating with br 1 no @ Tk. 300.00 each = Tk. 300.00
(c) CP chain with 1 no @ Tk. 80.00 each = Tk. 80.00
3 Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.01 bag @ Tk. 395.00 per bag = Tk. 3.95
(ii) Sand (F.M. 1.2 0.05 cft @ Tk. 1,400.00 per % cft = Tk. 0.70
(b) CI brakets 1 pair @ Tk. 115.00 per pair = Tk. 115.00
4 Labour:
(a) Plumber 0.15 no @ Tk. 600.00 each = Tk. 90.00
(b) Skilled labour 0.2 no @ Tk. 390.00 each = Tk. 78.00
(c) Ordinary labou 0.4 no @ Tk. 320.00 each = Tk. 128.00
Sub - Total = Tk. 4,095.65
Profit 10.00% = Tk. 409.57
Overhead 3.50% = Tk. 143.35
Total = Tk. 4,648.57
Add VAT with adjustment factor 1.06383 6.00% = Tk. 296.72
Grand Total = Tk. 4,945.29
Rate per No. = Tk. 4,945.29
Say, Tk. 4,945 .00 each
26.9.8 Cabinet Basin 500x450x180 mm, 9 kg by Weight
26.9.8.1 Light colour (Ivory, Alpine White, Grey, Pink, Blue, Aqua Verde),
Considering 1 No. of fixture
1 Coloured wash 1 no @ Tk. 2,613.00 each = Tk. 2,613.00
2 Accessories:
(a) 32 mm dia PVC 1 no @ Tk. 150.00 each = Tk. 150.00
(b) Grating with br 1 no @ Tk. 300.00 each = Tk. 300.00
(c) CP chain with 1 no @ Tk. 80.00 each = Tk. 80.00
3 Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.01 bag @ Tk. 395.00 per bag = Tk. 3.95
(ii) Sand (F.M. 1.2 0.05 cft @ Tk. 1,400.00 per % cft = Tk. 0.70
(b) CI brakets 1 pair @ Tk. 115.00 per pair = Tk. 115.00
4 Labour:
(a) Plumber 0.15 no @ Tk. 600.00 each = Tk. 90.00
26.10.2 Supplying, glazed vitreous W/H Wash Basin in/c pedastal size 600 x 500 x 855 mm, 26.92kg or equivalent
Considering 1 No. of fixture
1 Coloured wash 1 no @ Tk. 4,650.00 each = Tk. 4,650.00
2 Accessories:
(a) 32 mm dia PVC 1 no @ Tk. 150.00 each = Tk. 150.00
(b) Grating with br 1 no @ Tk. 300.00 each = Tk. 300.00
(c) CP chain with 1 no @ Tk. 80.00 each = Tk. 80.00
3 Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.01 bag @ Tk. 395.00 per bag = Tk. 3.95
(ii) Sand (F.M. 1.2 0.05 cft @ Tk. 1,400.00 per % cft = Tk. 0.70
(b) CI brakets 1 pair @ Tk. 115.00 per pair = Tk. 115.00
4 Labour:
(a) Plumber 0.15 no @ Tk. 600.00 each = Tk. 90.00
(b) Skilled labour 0.2 no @ Tk. 390.00 each = Tk. 78.00
(c) Ordinary labou 0.4 no @ Tk. 320.00 each = Tk. 128.00
Sub - Total = Tk. 5,595.65
Profit 10.00% = Tk. 559.57
Overhead 3.50% = Tk. 195.85
Total = Tk. 6,351.07
Add VAT with adjustment factor 1.06383 6.00% = Tk. 405.39
Grand Total = Tk. 6,756.46
Rate per No. = Tk. 6,756.46
Say, Tk. 6,756 .00 each
26.14.2 Coloured flat/squatting urinal (Bangladeshi), size 510 x 380 x 85 mm, wt. 9.5 kg or equivalent
Considering 1 No. of fixture
1 Coloured flat/s 1 no @ Tk. 1,000.00 each = Tk. 1,000.00
2 Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.2 bag @ Tk. 395.00 per bag = Tk. 79.00
(ii) Sand (F.M. 1.2 0.1 cft @ Tk. 1,400.00 per % cft = Tk. 1.40
3 Labour:
(a) Plumber 0.2 no @ Tk. 600.00 each = Tk. 120.00
(b) Skilled labour 0.25 no @ Tk. 390.00 each = Tk. 97.50
(c) Ordinary labou 0.5 no @ Tk. 320.00 each = Tk. 160.00
Sub - Total = Tk. 1,457.90
Profit 10.00% = Tk. 145.79
Overhead 3.50% = Tk. 51.03
Total = Tk. 1,654.72
Add VAT with adjustment factor 1.06383 6.00% = Tk. 105.62
Grand Total = Tk. 1,760.34
Rate per No. = Tk. 1,760.34
Say, Tk. 1,760 .00 each
26.14.3 Special coloured flat/squatting urinal (Bangladeshi), size 510 x 380 x 85 mm, wt. 9.5 kg
Considering 1 No. of fixture
1 Special Coloure 1 no @ Tk. 1,100.00 each = Tk. 1,100.00
26.15.2 Coloured porcelain sink (Bangladeshi), size 625 x 490 x 224 mm, wt. 19.5 kg
Considering 1 No. of fixture
1 Coloured porcel 1 no @ Tk. 1,800.00 each = Tk. 1,800.00
2 Accessories:
(a) CP grating with 1 no @ Tk. 300.00 each = Tk. 300.00
(b) 32 mm dia PVC 1 no @ Tk. 150.00 each = Tk. 150.00
(c) CP chain with 1 no @ Tk. 80.00 each = Tk. 80.00
3 Fitting fixing materials:
(a) CI braket: heav 1 pair @ Tk. 158.00 per pair = Tk. 158.00
(b) Cement mortar (1:4):
(i) Cement 0.015 bag @ Tk. 395.00 per bag = Tk. 5.93
(ii) Sand 0.075 cft @ Tk. 1,400.00 per % cft = Tk. 1.05
4 Labour:
(a) Plumber 0.2 no @ Tk. 600.00 each = Tk. 120.00
(b) Skilled labour 0.3 no @ Tk. 390.00 each = Tk. 117.00
Sub - Total = Tk. 2,731.98
Profit 10.00% = Tk. 273.20
26.24.2 Special colour porcelain toilet paper holder (Bangladeshi), size 150 x 150 x 128 mm or equivalent
Considering 1 No. of fixture
1 Special Colour 1 no @ Tk. 325.00 each = Tk. 325.00
2 Fitting fixing materials:
(a) Cement mortar (1:4):
(i) Cement 0.01 bag @ Tk. 395.00 per bag = Tk. 3.95
(ii) Sand (F.M. 1.2 0.05 cft @ Tk. 1,400.00 per % cft = Tk. 0.70
3 Labour:
(a) Plumber 0.025 no @ Tk. 600.00 each = Tk. 15.00
(b) Skilled labour 0.05 no @ Tk. 390.00 each = Tk. 19.50
(c) Ordinary labou 0.01 no @ Tk. 320.00 each = Tk. 3.20
Sub - Total = Tk. 367.35
Profit 10.00% = Tk. 36.74
Overhead 3.50% = Tk. 12.86
Total = Tk. 416.95
Add VAT with adjustment factor 1.06383 6.00% = Tk. 26.61
Grand Total = Tk. 443.56
Rate per No. = Tk. 443.56
Say, Tk. 444 .00 each
Item No.- 26.25
26.25.1 White colour Special Porcelain Toilet Paper Holder
1 White porcelain 1 no @ Tk. 320.00 each = Tk. 320.00
2 Fitting fixing materials:
(a) Cement mortar (1:4):
(i) Cement 0.01 bag @ Tk. 395.00 per bag = Tk. 3.95
(ii) Sand (F.M. 1.2 0.05 cft @ Tk. 1,400.00 per % cft = Tk. 0.70
3 Labour:
(a) Plumber 0.025 no @ Tk. 600.00 each = Tk. 15.00
(b) Skilled labour 0.05 no @ Tk. 390.00 each = Tk. 19.50
(c) Ordinary labou 0.01 no @ Tk. 320.00 each = Tk. 3.20
Sub - Total = Tk. 362.35
Profit 10.00% = Tk. 36.24
Overhead 3.50% = Tk. 12.68
Total = Tk. 411.27
Add VAT with adjustment factor 1.06383 6.00% = Tk. 26.25
Grand Total = Tk. 437.52
26.36.2 20 mm dia G.I pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Considering 20 ft. long one pipe
(a) 20 mm dia G.I. 20 ft. @ Tk. 48.00 per ft = Tk. 960.00
(b) Fittings:
26.36.3 25 mm dia G.I pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Considering 20 ft. long one pipe
(a) 25 mm dia G.I. 20 ft. @ Tk. 66.00 per ft = Tk. 1,320.00
(b) Fittings:
(i) Elbow 1 no @ Tk. 49.00 each = Tk. 49.00
(ii) Tee 1 no @ Tk. 54.00 each = Tk. 54.00
(iii) Nipple 1 no @ Tk. 34.00 each = Tk. 34.00
(iv) Plug 1 no @ Tk. 21.00 each = Tk. 21.00
(v) Reducer 1 no @ Tk. 38.00 each = Tk. 38.00
(vi) Socket 1 no @ Tk. 30.00 each = Tk. 30.00
(c) Jointing & fixing materials
(i) Teflon tape 4.2 pcs @ Tk. 16.00 per pcs = Tk. 67.20
(ii) Clamp 2 nos @ Tk. 50.00 each = Tk. 100.00
(iii) Rowel plug & s 4 nos @ Tk. 9.00 each = Tk. 36.00
(iv) Scaffolding 20 ft. @ Tk. 3.00 per ft = Tk. 60.00
(d) Labour:
(i) Plumber 0.125 no @ Tk. 600.00 each = Tk. 75.00
(ii) Skilled labour 0.25 no @ Tk. 390.00 each = Tk. 97.50
(iii) Ordinary labou 0.5 no @ Tk. 320.00 each = Tk. 160.00
Sub - Total = Tk. 2,141.70
Profit 10.00% = Tk. 214.17
Overhead 3.50% = Tk. 74.96
Total = Tk. 2,430.83
Add VAT with adjustment factor 1.06383 6.00% = Tk. 155.16
Grand Total = Tk. 2,585.99
Rate per ft = Tk. 129.30
Rate per m = Tk. 424.23
Say, Tk. 424 .00 per meter
26.36.4 32 mm dia G.I pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Considering 20 ft. long one pipe
(a) 32 mm dia G.I. 20 ft. @ Tk. 84.00 per ft = Tk. 1,680.00
(b) Fittings:
(i) Elbow 1 no @ Tk. 63.00 each = Tk. 63.00
(ii) Tee 1 no @ Tk. 80.00 each = Tk. 80.00
26.36.5 40 mm dia G.I pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Considering 20 ft. long one pipe
(a) 40 mm dia G.I. 20 ft. @ Tk. 104.00 per ft = Tk. 2,080.00
(b) Fittings:
(i) Elbow 1 no @ Tk. 82.00 each = Tk. 82.00
(ii) Tee 1 no @ Tk. 82.00 each = Tk. 82.00
(iii) Nipple 1 no @ Tk. 74.00 each = Tk. 74.00
(iv) Plug 1 no @ Tk. 37.00 each = Tk. 37.00
(v) Reducer 1 no @ Tk. 82.00 each = Tk. 82.00
(vi) Socket 1 no @ Tk. 55.00 each = Tk. 55.00
(c) Jointing & fixing materials
(i) Teflon tape 6.3 pcs @ Tk. 16.00 per pcs = Tk. 100.80
(ii) Clamp 2 nos @ Tk. 50.00 each = Tk. 100.00
(iii) Rowel plug & s 4 nos @ Tk. 9.00 each = Tk. 36.00
(iv) Scaffolding 20 ft. @ Tk. 3.00 per ft = Tk. 60.00
(d) Labour:
(i) Plumber 0.125 no @ Tk. 600.00 each = Tk. 75.00
(ii) Skilled labour 0.5 no @ Tk. 390.00 each = Tk. 195.00
(iii) Ordinary labou 1 no @ Tk. 320.00 each = Tk. 320.00
Sub - Total = Tk. 3,378.80
Profit 10.00% = Tk. 337.88
Overhead 3.50% = Tk. 118.26
Total = Tk. 3,834.94
Add VAT with adjustment factor 1.06383 6.00% = Tk. 244.78
Grand Total = Tk. 4,079.72
Rate per ft = Tk. 203.99
Rate per m = Tk. 669.29
Say, Tk. 669 .00 per meter
26.36.6 50 mm dia G.I. pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Considering 20 ft. long one pipe
(a) 50 mm dia G.I. 20 ft. @ Tk. 125.00 per ft = Tk. 2,500.00
(b) Fittings:
(i) Elbow 1 no @ Tk. 122.00 each = Tk. 122.00
(ii) Tee 1 no @ Tk. 98.00 each = Tk. 98.00
(iii) Nipple 1 no @ Tk. 74.00 each = Tk. 74.00
(iv) Plug 1 no @ Tk. 46.00 each = Tk. 46.00
26.36.7 62 mm dia G.I pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Considering 20 ft. long one pipe
(a) 62 mm dia G.I. 20 ft. @ Tk. 191.00 per ft = Tk. 3,820.00
(b) Fittings:
(i) Elbow 1 no @ Tk. 222.00 each = Tk. 222.00
(ii) Tee 1 no @ Tk. 322.00 each = Tk. 322.00
(iii) Nipple 1 no @ Tk. 176.00 each = Tk. 176.00
(iv) Plug 1 no @ Tk. 60.00 each = Tk. 60.00
(v) Reducer 1 no @ Tk. 126.00 each = Tk. 126.00
(vi) Socket 1 no @ Tk. 148.00 each = Tk. 148.00
(c) Jointing & fixing materials
(i) Teflon tape 10.5 pcs @ Tk. 16.00 per pcs = Tk. 168.00
(ii) Clamp (F.I. bar 2 nos @ Tk. 50.00 each = Tk. 100.00
(iii) Rowel plug & s 4 nos @ Tk. 9.00 each = Tk. 36.00
(iv) Scaffolding 20 ft. @ Tk. 3.00 per ft = Tk. 60.00
(d) Labour:
(i) Plumber 0.5 no @ Tk. 600.00 each = Tk. 300.00
(ii) Skilled labour 1.5 nos @ Tk. 390.00 each = Tk. 585.00
(iii) Ordinary labou 2 nos @ Tk. 320.00 each = Tk. 640.00
Sub - Total = Tk. 6,763.00
Profit 10.00% = Tk. 676.30
Overhead 3.50% = Tk. 236.71
Total = Tk. 7,676.01
Add VAT with adjustment factor 1.06383 6.00% = Tk. 489.96
Grand Total = Tk. 8,165.97
Rate per ft = Tk. 408.30
Rate per m = Tk. 1,339.63
Say, Tk. 1,340 .00 per meter
26.36.8 75 mm dia G.I pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Considering 20 ft. long one pipe
(a) 75 mm dia G.I. 20 ft. @ Tk. 215.00 per ft = Tk. 4,300.00
(b) Fittings:
(i) Elbow 1 no @ Tk. 400.00 each = Tk. 400.00
(ii) Tee 1 no @ Tk. 322.00 each = Tk. 322.00
(iii) Nipple 1 no @ Tk. 176.00 each = Tk. 176.00
(iv) Plug 1 no @ Tk. 135.00 each = Tk. 135.00
(v) Reducer 1 no @ Tk. 153.00 each = Tk. 153.00
(vi) Socket 1 no @ Tk. 147.00 each = Tk. 147.00
26.36.9 100 mm dia G.I pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Considering 20 ft. long one pipe
(a) 100 mm dia G.I 20 ft. @ Tk. 310.00 per ft = Tk. 6,200.00
(b) Fittings:
(i) Elbow 1 no @ Tk. 612.00 each = Tk. 612.00
(ii) Tee 1 no @ Tk. 785.00 each = Tk. 785.00
(iii) Nipple 1 no @ Tk. 395.00 each = Tk. 395.00
(iv) Plug 1 no @ Tk. 252.00 each = Tk. 252.00
(v) Reducer 1 no @ Tk. 342.00 each = Tk. 342.00
(vi) Socket 1 no @ Tk. 348.00 each = Tk. 348.00
(c) Jointing & fixing materials
(i) Teflon tape 16.75 pcs @ Tk. 16.00 per pcs = Tk. 268.00
(ii) Clamp (F.I. bar 2 nos @ Tk. 50.00 each = Tk. 100.00
(iii) Rowel plug & s 4 nos @ Tk. 9.00 each = Tk. 36.00
(iv) Scaffolding 20 ft. @ Tk. 3.00 per ft = Tk. 60.00
(d) Labour:
(i) Plumber 1 no @ Tk. 600.00 each = Tk. 600.00
(ii) Skilled labour 2 nos @ Tk. 390.00 each = Tk. 780.00
(iii) Ordinary labou 2 nos @ Tk. 320.00 each = Tk. 640.00
Sub - Total = Tk. 11,418.00
Profit 10.00% = Tk. 1,141.80
Overhead 3.50% = Tk. 399.63
Total = Tk. 12,959.43
Add VAT with adjustment factor 1.06383 6.00% = Tk. 827.20
Grand Total = Tk. 13,786.63
Rate per ft = Tk. 689.33
Rate per m = Tk. 2,261.69
Say, Tk. 2,262 .00 per meter
Item No.- 26.37
26.37.1 1/2" or 12 mm dia uPVC pipe for plumbing purpose
Considering 20 ft. long 6 nos pipe = 120 ft. work
(a) 12 mm dia uPV 120 ft. @ Tk. 6.75 per ft = Tk. 810.00
(b) Fittings:
(i) 12 mm uPVC pl 10 nos @ Tk. 5.50 each = Tk. 55.00
(ii) 12 mm uPVC pl 25 nos @ Tk. 4.50 each = Tk. 112.50
(iii) 12 mm uPVC fa 5 nos @ Tk. 6.00 each = Tk. 30.00
(iv) 12 mm uPVC pl 6 nos @ Tk. 4.00 each = Tk. 24.00
(v) 12 mm uPVC th 5 nos @ Tk. 3.00 each = Tk. 15.00
(c) Jointing & fixing materials
(i) Solvent cement 50 ml. @ Tk. 0.70 per ml = Tk. 35.00
26.39.2 3/4" Dia PP-R Pipe : Connection including nipple, elbow, reducers, Tee etc. Complete for in-house drinking water.
Considering 20 ft. Long one pipe
(a) 3/4" Dia PP-R 20 ft. @ Tk. 20.50 per ft = Tk. 410.00
(b) Fittings:
(i) Elbow 1 no @ Tk. 10.50 each = Tk. 10.50
(ii) Tee 1 no @ Tk. 13.00 each = Tk. 13.00
(iii) End Cap 1 no @ Tk. 9.75 each = Tk. 9.75
(iv) Plug 1 no @ Tk. 7.50 each = Tk. 7.50
(v) Reducer 1 no @ Tk. 27.00 each = Tk. 27.00
(vi) Socket 1 no @ Tk. 8.00 each = Tk. 8.00
( c) Jointing & fixing Materials
(i) Teflon Tape 2 pcs @ Tk. 16.00 per pcs = Tk. 32.00
(ii) Clamp (F.I. Bar 2 nos @ Tk. 50.00 each = Tk. 100.00
(iii) Rowel Plug & 4 nos @ Tk. 9.00 each = Tk. 36.00
(iv) Scaffolding 20 ft. @ Tk. 3.00 per ft = Tk. 60.00
(d) Labour:
(i) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(ii) Skilled labour 0.5 no @ Tk. 390.00 each = Tk. 195.00
(iii) Ordinary labou 1 no @ Tk. 320.00 each = Tk. 320.00
Sub - Total = Tk. 1,378.75
Profit 10.00% = Tk. 137.88
Overhead 3.50% = Tk. 48.26
Total = Tk. 1,564.89
Add VAT with adjustment factor 1.06383 6.00% = Tk. 99.89
Grand Total = Tk. 1,664.78
Rate per ft = Tk. 83.24
Rate per m = Tk. 273.11
Say, Tk. 273 .00 per meter
26.39.3 1" Dia PP-R Pipe : Connection including nipple, elbow, reducers, Tee etc. Complete for in-house drinking water.
Considering 20 ft. Long one pipe
(a) 1" Dia PP-R Pi 20 ft. @ Tk. 29.50 per ft = Tk. 590.00
(b) Fittings:
(i) Elbow 1 no @ Tk. 17.25 each = Tk. 17.25
(ii) Tee 1 no @ Tk. 19.25 each = Tk. 19.25
(iii) End Cap 1 no @ Tk. 16.00 each = Tk. 16.00
(iv) Plug 1 no @ Tk. 14.00 each = Tk. 14.00
(v) Reducer 1 no @ Tk. 30.00 each = Tk. 30.00
(vi) Socket 1 no @ Tk. 18.00 each = Tk. 18.00
( c) Jointing & fixing Materials
(i) Teflon Tape 2 pcs @ Tk. 16.00 per pcs = Tk. 32.00
(ii) Clamp (F.I. Bar 2 nos @ Tk. 50.00 each = Tk. 100.00
(iii) Rowel Plug & 4 nos @ Tk. 9.00 each = Tk. 36.00
(iv) Scaffolding 20 ft. @ Tk. 3.00 per ft = Tk. 60.00
(d) Labour:
(i) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(ii) Skilled labour 0.5 no @ Tk. 390.00 each = Tk. 195.00
(iii) Ordinary labou 1 no @ Tk. 320.00 each = Tk. 320.00
Sub - Total = Tk. 1,597.50
Profit 10.00% = Tk. 159.75
Overhead 3.50% = Tk. 55.91
26.39.4 1.25" Dia PP-R Pipe : Connection including nipple, elbow, reducers, Tee etc. Complete for in-house drinking water.
Considering 20 ft. Long one pipe
(a) 1.25" Dia PP-R 20 ft. @ Tk. 49.00 per ft = Tk. 980.00
(b) Fittings:
(i) Elbow 1 no @ Tk. 58.50 each = Tk. 58.50
(ii) Tee 1 no @ Tk. 61.00 each = Tk. 61.00
(iii) End Cap 1 no @ Tk. 36.75 each = Tk. 36.75
(iv) Plug 1 no @ Tk. 36.00 each = Tk. 36.00
(v) Reducer 1 no @ Tk. 66.00 each = Tk. 66.00
(vi) Socket 1 no @ Tk. 21.75 each = Tk. 21.75
( c) Jointing & fixing Materials
(i) Teflon Tape 2 pcs @ Tk. 16.00 per pcs = Tk. 32.00
(ii) Clamp (F.I. Bar 2 nos @ Tk. 50.00 each = Tk. 100.00
(iii) Rowel Plug & 4 nos @ Tk. 9.00 each = Tk. 36.00
(iv) Scaffolding 20 ft. @ Tk. 3.00 per ft = Tk. 60.00
(d) Labour:
(i) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(ii) Skilled labour 0.5 no @ Tk. 390.00 each = Tk. 195.00
(iii) Ordinary labou 1 no @ Tk. 320.00 each = Tk. 320.00
Sub - Total = Tk. 2,153.00
Profit 10.00% = Tk. 215.30
Overhead 3.50% = Tk. 75.36
Total = Tk. 2,443.66
Add VAT with adjustment factor 1.06383 6.00% = Tk. 155.98
Grand Total = Tk. 2,599.64
Rate per ft = Tk. 129.98
Rate per m = Tk. 426.46
Say, Tk. 426 .00 per meter
26.39.5 1.5" Dia PP-R Pipe : Connection including nipple, elbow, reducers, Tee etc. Complete for in-house drinking water.
Considering 20 ft. Long one pipe
(a) 1.5" Dia PP-R 20 ft. @ Tk. 61.50 per ft = Tk. 1,230.00
(b) Fittings:
(i) Elbow 1 No. @ Tk. 77.00 each = Tk. 77.00
(ii) Tee 1 No. @ Tk. 81.00 each = Tk. 81.00
(iii) End Cap 1 No. @ Tk. 93.00 each = Tk. 93.00
(iv) Plug 1 No. @ Tk. 18.00 each = Tk. 18.00
(v) Reducer 1 No. @ Tk. 102.00 each = Tk. 102.00
(vi) Socket 1 No. @ Tk. 41.00 each = Tk. 41.00
( c) Jointing & fixing Materials
(i) Teflon Tape 2 pcs @ Tk. 16.00 per pcs = Tk. 32.00
(ii) Clamp (F.I. Bar 2 nos @ Tk. 50.00 each = Tk. 100.00
(iii) Rowel Plug & 4 nos @ Tk. 9.00 each = Tk. 36.00
(iv) Scaffolding 20 ft. @ Tk. 3.00 per ft = Tk. 60.00
(d) Labour:
(i) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(ii) Skilled labour 0.5 no @ Tk. 390.00 each = Tk. 195.00
(iii) Ordinary labou 1 no @ Tk. 320.00 each = Tk. 320.00
Sub - Total = Tk. 2,535.00
Profit 10.00% = Tk. 253.50
Overhead 3.50% = Tk. 88.73
Total = Tk. 2,877.23
Add VAT with adjustment factor 1.06383 6.00% = Tk. 183.65
26.39.6 2" Dia PP-R Pipe : Connection including nipple, elbow, reducers, Tee etc. Complete for in-house drinking water.
Considering 20 ft. Long one pipe
(a) 2" Dia PP-R Pi 20 ft. @ Tk. 95.00 per ft = Tk. 1,900.00
(b) Fittings:
(i) Elbow 1 no @ Tk. 137.00 each = Tk. 137.00
(ii) Tee 1 no @ Tk. 149.00 each = Tk. 149.00
(iii) End Cap 1 no @ Tk. 140.00 each = Tk. 140.00
(iv) Plug 1 no @ Tk. 20.00 each = Tk. 20.00
(v) Reducer 1 no @ Tk. 131.00 each = Tk. 131.00
(vi) Socket 1 no @ Tk. 61.00 each = Tk. 61.00
( c) Jointing & fixing Materials
(i) Teflon Tape 2 pcs @ Tk. 16.00 per pcs = Tk. 32.00
(ii) Clamp (F.I. Bar 2 no @ Tk. 50.00 each = Tk. 100.00
(iii) Rowel Plug & 4 no @ Tk. 9.00 each = Tk. 36.00
(iv) Scaffolding 20 ft. @ Tk. 3.00 per ft = Tk. 60.00
(d) Labour:
(i) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(ii) Skilled labour 0.5 nos @ Tk. 390.00 each = Tk. 195.00
(iii) Ordinary labou 1 nos @ Tk. 320.00 each = Tk. 320.00
Sub - Total = Tk. 3,431.00
Profit 10.00% = Tk. 343.10
Overhead 3.50% = Tk. 120.09
Total = Tk. 3,894.19
Add VAT with adjustment factor 1.06383 6.00% = Tk. 248.57
Grand Total = Tk. 4,142.76
Rate per ft = Tk. 207.14
Rate per m = Tk. 679.63
Say, Tk. 680 .00 per meter
Item No.- 26.40
Supplying, fitting-fixing of PP-R Union of following sizes:
26.40.1 1/2" PP-R Union
Considering 1no. Of fixture
(a) 1/2" PP-R Uni 1 no @ Tk. 131.00 each = Tk. 131.00
(b) Fittings fixing materials:
(i) Teflon Tape 2 pcs @ Tk. 16.00 per pcs = Tk. 32.00
(d) Labour:
(i) Plumber 0.025 no @ Tk. 600.00 each = Tk. 15.00
(ii) Skilled labour 0.075 nos @ Tk. 390.00 each = Tk. 29.25
(iii) Ordinary labou 0.05 nos @ Tk. 320.00 each = Tk. 16.00
Sub - Total = Tk. 223.25
Profit 10.00% = Tk. 22.33
Overhead 3.50% = Tk. 7.81
Total = Tk. 253.39
Add VAT with adjustment factor 1.06383 6.00% = Tk. 16.17
Grand Total = Tk. 269.56
Say, Tk. 270 .00 each
Supplying, fitting-fixing of PP-R Union of following sizes:
26.40.2 3/4" PP-R Union
Considering 1no. Of fixture
(a) 3/4" PP-R Uni 1 no @ Tk. 153.00 each = Tk. 153.00
(b) Fittings fixing materials:
(i) Teflon Tape 2 pcs @ Tk. 16.00 per pcs = Tk. 32.00
26.45.4 uPVC waste pipe 280 mm dia wall thickness 6.9 mm - 8.6 mm for underground laying.
Considering 20 ft. long one pipe
(a) 280 mm uPVC p 20 ft. @ Tk. 540.00 per ft = Tk. ###
(b) Jointing materials
(i) Solvent cemen 330 ml @ Tk. 0.70 per ml = Tk. 231.00
(c) Excavation 87.5 cft @ Tk. 2,958.33 per % 0 cft = Tk. 258.85
(d) Bedding by san 52.5 cft @ Tk. 1,400.00 per cft = Tk. 735.00
(e) Labour:
(i) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(ii) Skilled labour 0.5 no @ Tk. 390.00 each = Tk. 195.00
(iii) Ordinary labou 1 no @ Tk. 320.00 each = Tk. 320.00
Sub - Total = Tk. ###
Profit 10.00% = Tk. 1,268.99
Overhead 3.50% = Tk. 444.14
Total = Tk. ###
Add VAT with adjustment factor 1.06383 6.00% = Tk. 919.34
Grand Total = Tk. ###
Rate per ft = Tk. 766.12
Rate Per m = Tk. 2,513.64
Say, Tk. 2,514 .00 per meter
26.45.5 uPVC waste pipe 315 mm dia wall thickness 7.7 mm - 9.7 mm for underground laying
Considering 20 ft. long one pipe
(a) 315 mm uPVC p 20 ft. @ Tk. 550.00 per ft = Tk. ###
(b) Jointing materials
(i) Solvent cemen 330 ml @ Tk. 0.70 per ml = Tk. 231.00
(c) Excavation 87.5 cft @ Tk. 2,958.33 per % 0 cft = Tk. 258.85
(d) Bedding by san 52.5 cft @ Tk. 1,400.00 per cft = Tk. 735.00
(e) Labour:
(i) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(ii) Skilled labour 0.5 no @ Tk. 390.00 each = Tk. 195.00
(iii) Ordinary labou 1 no @ Tk. 320.00 each = Tk. 320.00
Sub - Total = Tk. ###
Profit 10.00% = Tk. 1,288.99
Overhead 3.50% = Tk. 451.14
Total = Tk. ###
Add VAT with adjustment factor 1.06383 6.00% = Tk. 933.83
Grand Total = Tk. ###
Rate per ft = Tk. 778.19
Rate Per m = Tk. 2,553.24
Say, Tk. 2,553 .00 per meter
Item No.- 26.46
Supplying, fitting-fixing of G.I. Union of following sizes:
26.46.1 12 mm dia G.I. Union
Considering 1 No. of fixture
(a) 12 mm dia G.I. 1 no @ Tk. 35.00 each = Tk. 35.00
(b) Fitting fixing materials:
(i) Teflon tape 0.53 pcs @ Tk. 16.00 per pcs = Tk. 8.48
(c) Labour:
(i) Plumber 0.025 no @ Tk. 600.00 each = Tk. 15.00
26.68.2 Food-grade plastic internal mini water tank for the use in kitchen, bathroom & toilet for
emergency storage and supply of water: 300 litre capacity
Considering 1 No. of fixture
26.68.3 Food-grade plastic internal mini water tank for the use in kitchen, bathroom & toilet for
emergency storage and supply of water: 500 litre capacity
Considering 1 No. of fixture
(a) 500 litre plasti 1 no @ Tk. 3,400.00 each = Tk. 3,400.00
(b) Carrying up to site LS = Tk. 598.40
(c) Fitting-fixing materials
(i) Teflon tape 4.2 pcs @ Tk. 16.00 per pcs = Tk. 67.20
(ii) 3/4" dia ball co 1 no @ Tk. 130.00 each = Tk. 130.00
(iii) Nipple with jam 1 no @ Tk. 60.00 each = Tk. 60.00
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 1 no @ Tk. 600.00 each = Tk. 600.00
(ii) Skilled labour 1 no @ Tk. 390.00 each = Tk. 390.00
Sub - Total = Tk. 5,245.60
Profit 10.00% = Tk. 524.56
Overhead 3.50% = Tk. 183.60
Total = Tk. 5,953.76
Add VAT with adjustment factor 1.06383 6.00% = Tk. 380.03
Grand Total = Tk. 6,333.79
Rate per No. = Tk. 6,333.79
Say, Tk. 6,334 .00 each
Item No.- 26.69
26.69.1 Food-grade foreign made stainless steel water tank: 500 litre capacity
Considering 1 No. of fixture
(a) 500 litre stainl 1 no @ Tk. 7,640.00 each = Tk. 7,640.00
(b) Carrying up to site LS = Tk. 160.00
(c) Ffitting-fixing materials
(i) 1/2" ball cock 1 no @ Tk. 130.00 per ft = Tk. 130.00
(ii) 1/2" G.I. pipe 1 no @ Tk. 60.00 each = Tk. 60.00
(iii) Other small fittings in/c out-let pipe & flange etc. LS = Tk. 240.00
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 0.75 no @ Tk. 600.00 each = Tk. 450.00
(ii) Skilled labour 1.5 nos @ Tk. 390.00 each = Tk. 585.00
Sub - Total = Tk. 9,265.00
Profit 10.00% = Tk. 926.50
Overhead 3.50% = Tk. 324.28
Total = Tk. 10,515.78
Add VAT with adjustment factor 1.06383 6.00% = Tk. 671.22
Grand Total = Tk. 11,187.00
Rate per No. = Tk. 11,187.00
Say, Tk. 11,187 .00 each
26.69.2 Food-grade foreign made stainless steel water tank: 1000 litre capacity
Considering 1 No. of fixture
(a) 1000 litre stain 1 no @ Tk. 14,036.00 each = Tk. 14,036.00
(b) Carrying up to site LS = Tk. 240.00
(c) Ffitting-fixing materials
(i) 1/2" ball cock 1 no @ Tk. 130.00 per ft = Tk. 130.00
(ii) 1/2" dia G.I. pi 1 no @ Tk. 60.00 each = Tk. 60.00
(iii) Other small fittings in/c out-let pipe & flange etc. LS = Tk. 320.00
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 1 no @ Tk. 600.00 each = Tk. 600.00
(ii) Skilled labour 2 nos @ Tk. 390.00 each = Tk. 780.00
Sub - Total = Tk. 16,166.00
Profit 10.00% = Tk. 1,616.60
Overhead 3.50% = Tk. 565.81
Total = Tk. 18,348.41
Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,171.18
Grand Total = Tk. 19,519.59
Rate per No. = Tk. 19,519.59
Say, Tk. 19,520 .00 each
26.69.3 Food-grade foreign made stainless steel water tank: 2000 litre capacity
Considering 1 No. of fixture
(a) 2000 litre stain 1 no @ Tk. 24,056.00 each = Tk. 24,056.00
(b) Carrying LS = Tk. 480.00
(c) Fitting-fixing materials
(i) 1/2" ball cock 1 no @ Tk. 130.00 per ft = Tk. 130.00
(ii) 1/2" dia G.I. p 1 no @ Tk. 60.00 each = Tk. 60.00
(iii) Other small fittings in/c out-let pipe & flange etc. LS = Tk. 480.00
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 1 no @ Tk. 600.00 each = Tk. 600.00
(ii) Skilled labour 2 nos @ Tk. 390.00 each = Tk. 780.00
Sub - Total = Tk. 26,586.00
Profit 10.00% = Tk. 2,658.60
Overhead 3.50% = Tk. 930.51
Total = Tk. 30,175.11
Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,926.07
Grand Total = Tk. 32,101.18
Rate per No. = Tk. 32,101.18
Say, Tk. 32,101 .00 each
26.69.4 Food-grade foreign made stainless steel water tank: 4000 litre capacity
Considering 1 No. of fixture
(a) 4000 litre stain 1 no @ Tk. 49,191.00 each = Tk. 49,191.00
(b) Carrying up to site LS = Tk. 800.00
(c) Fitting-fixing materials
(i) 1/2" ball cock 1 no @ Tk. 130.00 per ft = Tk. 130.00
(ii) 1/2" dia G.I. p 1 no @ Tk. 60.00 each = Tk. 60.00
(iii) Other small fittings in/c out-let pipe & flange etc. LS = Tk. 640.00
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 1 no @ Tk. 600.00 each = Tk. 600.00
(ii) Skilled labour 2 nos @ Tk. 390.00 each = Tk. 780.00
Sub - Total = Tk. 52,201.00
Profit 10.00% = Tk. 5,220.10
Overhead 3.50% = Tk. 1,827.04
Total = Tk. 59,248.14
Add VAT with adjustment factor 1.06383 6.00% = Tk. 3,781.80
Grand Total = Tk. 63,029.94
Rate per No. = Tk. 63,029.94
Say, Tk. 63,030 .00 each
26.69.5 Food-grade foreign made stainless steel water tank: 6000 litre capacity
Considering 1 No. of fixture
(a) 6000 litre stain 1 no @ Tk. 53,481.00 each = Tk. 53,481.00
(b) Carrying up to site LS = Tk. 960.00
(c) Fitting-fixing materials
(i) 1/2" ball cock 1 no @ Tk. 130.00 per ft = Tk. 130.00
(ii) 1/2" dia G.I. p 1 no @ Tk. 60.00 each = Tk. 60.00
(iii) Other small fittings in/c out-let pipe & flange etc. LS = Tk. 800.00
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 1 no @ Tk. 600.00 each = Tk. 600.00
(ii) Skilled labour 2 nos @ Tk. 390.00 each = Tk. 780.00
Sub - Total = Tk. 56,811.00
Profit 10.00% = Tk. 5,681.10
Overhead 3.50% = Tk. 1,988.39
Total = Tk. 64,480.49
Add VAT with adjustment factor 1.06383 6.00% = Tk. 4,115.78
Grand Total = Tk. 68,596.27
Rate per No. = Tk. 68,596.27
Say, Tk. 68,596 .00 each
Item No.- 26.70
Food-grade ferro-cement water tank: 400 Gallon capacity
Considering 1 No. of fixture
(a) 400 gallon capacty ferro-cement
water tank in/c 1 no @ Tk. 6,320.00 each = Tk. 6,320.00
(b) Carrying (for Dhaka city) LS = Tk. 320.00
Sub - Total = Tk. 6,640.00
Profit 10.00% = Tk. 664.00
Overhead 3.50% = Tk. 232.40
Total = Tk. 7,536.40
Add VAT with adjustment factor 1.06383 6.00% = Tk. 481.05
Grand Total = Tk. 8,017.45
Rate per No. = Tk. 8,017.45
Say, Tk. 8,017 .00 each
26.80.2 Inspection pit of internal size: 525 x 525 mm & depth 675 to 825 mm (av. 750 mm)
for single 9" dia size RCC or 300 mm plastic/PVC pipes
Considering 1 No. pit
1 Earth-work:
1 x 3-7" x 3'-7" 38.45 cft @ Tk. 2,958.33 per % 0 cft = Tk. 113.75
2 Brick-flat soling:
1 x 3'-5" x 3'-5 11.7 sft @ Tk. 32.34 Per % sft = Tk. 3.78
3 C.C. (1:3:6) on soling:
1 x 3'-5" x 3'-5" 2.92 cft @ Tk. ### per % cft = Tk. 450.52
4 C.C. (1:3:6) for invert:
1 x 1'-9" x 1'-9" 0.51 cft @ Tk. ### per % cft = Tk. 78.69
5 Brick-work (1:6):
2 x (3'-5" + 1'- 21.46 cft @ Tk. ### per % cft = Tk. 3,039.59
6 12 mm plaster with n.c.f.:
4 x (1'-9" x 2'-6 20.56 sft @ Tk. 2,158.00 per % sft = Tk. 443.68
7 Extra labour for making invert & side back-filling:
a) Plumber 0.125 no @ Tk. 600.00 each = Tk. 75.00
b) Skilled labour 0.2 no @ Tk. 390.00 each = Tk. 78.00
c) Ordinary labou 0.235 no @ Tk. 320.00 each = Tk. 75.20
Sub - Total = Tk. 4,358.21
26.80.3 Inspection pit of internal size: 600 x 600 mm & depth 750 to 900 mm (av. 825 mm)
for single 300mm dia size RCC or 375 mm plastic/PVC pipes
Considering 1 No. pit
1 Earth-work:
1 x 3'-11" x 3'- 49.94 cft @ Tk. 2,958.33 per % 0 cft = Tk. 147.74
2 Brick-flat soling:
1 x 3'-8" x 3'-8 13.47 sft @ Tk. 32.34 Per % sft = Tk. 4.36
3 C.C. (1:3:6) on soling:
1 x 3'-8" x 3'-8" 3.37 cft @ Tk. 15,428.63 per % cft = Tk. 519.94
4 C.C. (1:3:6) for invert:
1 x 2'-0" x 2'-0" 0.67 cft @ Tk. 15,428.63 per % cft = Tk. 103.37
5 Brick-work (1:6):
2 x (3'-8" + 2'-0") x 2'-9" x 0'-10"=
31.19 cft @ Tk. 14,164.00 per % cft = Tk. 4,417.75
6 12 mm plaster with n.c.f.:
4 x (2'-0" x 2'-9 28.25 sft @ Tk. 2,158.00 per % sft = Tk. 609.64
7 Extra labour for making invert & side back-filling:
(a) Plumber 0.14 no @ Tk. 600.00 each = Tk. 84.00
(b) Skilled labour 0.23 no @ Tk. 390.00 each = Tk. 89.70
(c) Ordinary labou 0.27 no @ Tk. 320.00 each = Tk. 86.40
Sub - Total = Tk. 6,062.90
Profit 10.00% = Tk. 606.29
Overhead 3.50% = Tk. 212.20
Total = Tk. 6,881.39
Add VAT with adjustment factor 1.06383 6.00% = Tk. 439.24
Grand Total = Tk. 7,320.63
Rate per No. = Tk. 7,320.63
Say, Tk. 7,321 .00 each
26.80.4 Master-pit of Size: 600 x 500 mm & average depth 750 mm for Septic tank.
Considering 1 No. pit
1 Earth-work:
1 x 2'-3" x 4'-0" 27.96 cft @ Tk. 2,958.33 per % 0 cft = Tk. 82.71
2 Brick-flat soling:
1 x 3'-8" x 2'-6 9.175 sft @ Tk. 32.34 Per % sft = Tk. 2.97
3 C.C. (1:3:6) on soling:
1 x 1'-6" x 2'-0" 0.94 cft @ Tk. ### per % cft = Tk. 145.03
4 C.C. (1:3:6) for channel making:
1 x 1'-6" x 2'-6" 1.24 cft @ Tk. ### per % cft = Tk. 191.32
5 Brick-work (1:6):
2 x 1'-8" x 2'-2 6.02 cft
1 x 3' - 8" x 2' 6.61 cft
12.63 cft @ Tk. ### per % cft = Tk. 1,788.91
6 12 mm plaster with n.c.f.:
(2' - 0" + 1' - 8" 11.5661 sft
(2' - 6" + 2' - 6" 8.67 sft
1' - 6" x 2' - 6" 3.75 sft
23.99 sft @ Tk. 2,158.00 per % sft = Tk. 517.70
7 Extra labour for making channel & back-fill to side:
(a) Plumber 0.125 no @ Tk. 600.00 each = Tk. 75.00
(b) Skilled labour 0.125 no @ Tk. 390.00 each = Tk. 48.75
(c) Ordinary labou 0.125 no @ Tk. 320.00 each = Tk. 40.00
26.82.2 1050 x 1050 x 75 mm size pit cover with 18" dia C.I. man-hole cover.
Considering 1 No. pit cover with man-hole cover
1 R.C.C. (1:2:4) for slab:
1 x (3'-5" x 3'-5"- 0.785 x 1'-6" x 1'-6") x 0'-3" =
2.48 cft @ Tk. 17,827.80 Per % cft = Tk. 442.13
2 1% re-inforceme 12.15 Ibs @ Tk. 29.74 per Ibs = Tk. 361.34
3 12 mm plaster with n.c.f.:
4 x (3'-5" x 0'-3" + 3'-5" x 3'-5" - 0.785 x 1'-6" x 1'-6") =
13.35 sft @ Tk. 2,158.00 per % sft = Tk. 288.09
4 18" dia water sealed heavy type C.I. man-hole cover with locking
arrangement in 1 no @ Tk. 900.00 each = Tk. 900.00
5 Extra labour for placing pit cover
Ordinary labou 0.1 no @ Tk. 320.00 each = Tk. 32.00
Sub - Total = Tk. 2,023.56
Profit 10.00% = Tk. 202.36
Overhead 3.50% = Tk. 70.82
Total = Tk. 2,296.74
Add VAT with adjustment factor 1.06383 6.00% = Tk. 146.60
Grand Total = Tk. 2,443.34
Rate per No. = Tk. 2,443.34
Say, Tk. 2,443 .00 each
26.82.3 1100 x 1100 x 75 mm size pit cover with 18" dia C.I. man-hole cover.
Considering 1 No. pit cover with man-hole cover
1 R.C.C. (1:2:4) for slab:
1 x (3'-8" x 3'-8"- 0.785 x 1'-6" x 1'-6") x 0'-3" =
26.83.2 525 x 525 mm and depth 675 - 825 mm, average 750 mm for single 225 mm dia RCC pipes and 400 mm
dia PVC pipe with pitcover and 450 mm dia C.I. Man-hole cover
= Tk. 7,705
Say, Tk. 7,705 .00 each
26.83.3 600 x 600 mm and depth 750 - 900 mm, average 825 mm for single 300 mm dia RCC pipes and 400 mm
dia PVC pipe with pitcover and 450 mm dia C.I. Man-hole cover
= Tk. 9,993.00
Say, Tk. 9,993 .00 each
Item No.- 26.84
Construction of septic tank of following sizes:
26.84.1 Septic tank of 200 users excluding master-pit
Considering 1 No. septic tank
1 Earth-work:
1 x 25-2" x 10'- 1812.81 cft @ Tk. 2,958.33 per % 0 cft = Tk. 5,362.89
2 Brick-flat soling:
1 x 24'-8" x 10' 250.89 sft @ Tk. 32.34 Per % sft = Tk. 81.14
3 6" R. C.C. (1:2:4) on soling:
1 x 24'-8" x 10' 125.45 cft @ Tk. 15,428.63 per % cft = Tk. 19,355.22
4 5" thick R.C.C.(1:2"4) lining
2 x (23'-0" + 6'- 162.48 cft @ Tk. 15,428.63 per % cft = Tk. 25,068.44
5 Tie beam (1:2:4)
1 x 9" x 9" x 7' 3.94 cft @ Tk. 17,827.80 per % cft = Tk. 702.42
6 R.C.C. in roof slab
1 x 24' - 8" x 8' 69.20 cft @ Tk. 17,827.80 per % cft = Tk. 12,336.84
7 Formwork 230.00 sft @ Tk. 35.03 per sft = Tk. 8,056.90
8 Brick-work (1:6):
2 x 24'-8" x 2'- 81.90 cft
2 x 24'-8" x 1'- 20.72 cft
2 x (24'-8" + 6' 348.8 cft
Total = 451.42 cft @ Tk. 14,164.00 per % cft = Tk. 63,939.13
9 5" thick brick-work (1:6)
6'-0" x 4'-5" = 26.52 sft
6'-0" x 5'-6" = 33.00 sft
PRODUCTION WELL
Analysis of PW 583
Add VAT with a 1.06383 6.00% = Tk. 1,885.11
Grand Total = Tk. 31,418.55
Say, Tk. 31,419 .00 each
27.21.2 Development of tube well for the depth beyond 200 = Tk. 37,702.26
Say, Tk. 37,702 .00 each
Analysis of PW 589
Overhead 3.50% = Tk. 1,117.73
Total = Tk. 36,246.36
Add VAT with a 1.06383 6.00% = Tk. 2,313.60
Grand Total = Tk. 38,559.96
Say, Tk. 38,560 .00 each
27.29.2 Development of tube well for the depth beyond 200 = Tk. 46,271.95
Say, Tk. 46,272 .00 each
Analysis of PW 626
(c) Local carriage & sundries LS = Tk. 192.00
Sub - Tot= Tk. ###
Incidental charges 10.00% = Tk. 226.70
Profit 10.00% = Tk. 226.70
Overhead 3.50% = Tk. 7.93
Total = Tk. ###
Add VAT with a 1.06383 6.00% = Tk. 174.15
Grand To= Tk. ###
Rate per =c Tk. 19.35
Rate per = Tk. 683.35
Say, Tk. 683 .00 per cum
Item No.- 28.3.1
Providing Butt welding joint to M.S. pipe: 75 mm ND (88.90 mm O.D.)
(a) Cost of welding as per Titas gas rate LS = Tk. 149.75
Incidental charges 10.00% = Tk. 14.98
Profit 10.00% = Tk. 14.98
Overhead 3.50% = Tk. 0.52
Total = Tk. 180.23
Add VAT with a 1.06383 6.00% = Tk. 11.50
Grand To= Tk. 191.73
Say, Tk. 192 .00 per joint
Item No.- 28.3.2
Providing Butt welding joint to M.S. pipe: 50 mm ND (60.30 mm O.D.)
(a) Cost of welding as per Titas Gas rate LS = Tk. 127.26
Incidental charges 10.00% = Tk. 12.73
Profit 10.00% = Tk. 12.73
Overhead 3.50% = Tk. 0.45
Total = Tk. 153.17
Add VAT with a 1.06383 6.00% = Tk. 9.78
Grand To= Tk. 162.95
Say, Tk. 163 .00 per joint
Item No.- 28.3.3
Providing Butt welding joint to M.S. pipe: 25 mm ND (33.40 mm O.D.)
(a) Cost of welding as per Titas Gas rate LS = Tk. 99.73
Incidental charges 10.00% = Tk. 9.97
Profit 10.00% = Tk. 9.97
Overhead 3.50% = Tk. 0.35
Total = Tk. 120.02
Add VAT with a 1.06383 6.00% = Tk. 7.66
Grand To= Tk. 127.68
Say, Tk. 128 .00 per joint
Item No.- 28.3.4
Providing Butt welding joint to M.S. pipe: 20 mm ND (26.70 mm O.D.)
(a) Cost of welding as per Titas Gas rate LS = Tk. 85.32
Incidental charges 10.00% = Tk. 8.53
Profit 10.00% = Tk. 8.53
Overhead 3.50% = Tk. 0.30
Total = Tk. 102.68
Add VAT with a 1.06383 6.00% = Tk. 6.55
Grand To= Tk. 109.23
Say, Tk. 109 .00 per joint
Analysis of PW 627
Item No.- 28.4.1
Supplying different sizes Tee, Elbow, Reducer, Plug, Socket: 50 x 50 x 50 mm N.D. Tee CD 40
Considering 1 No. Tee
(a) Equal Tee (as per Titas Gas rate) = Tk. 231.55
(b) Carrying charge LS = Tk. 5.00
Sub - Total = Tk. 236.55
Incidental charges 10.00% = Tk. 23.66
Profit 10.00% = Tk. 23.66
Overhead 3.50% = Tk. 0.83
Total = Tk. 284.70
Add VAT with a 1.06383 6.00% = Tk. 18.17
Grand Total = Tk. 302.87
Say, Tk. 303 .00 each
Item No.- 28.4.2
Supplying different sizes Tee, Elbow, Reducer, Plug, Socket: 50 x 50 x 25 mm N.D. Tee CD 40
Considering 1 No. Tee
(a) Reducing Tee (as per Titas Gas rate) = Tk. 258.30
(b) Carrying charge LS = Tk. 5.00
Sub - Total = Tk. 263.30
Incidental charges 10.00% = Tk. 26.33
Profit 10.00% = Tk. 26.33
Overhead 3.50% = Tk. 0.92
Total = Tk. 316.88
Add VAT with a 1.06383 6.00% = Tk. 20.23
Grand Total = Tk. 337.11
Say, Tk. 337 .00 each
Item No.- 28.4.3
Supplying different sizes Tee, Elbow, Reducer, Plug, Socket: 25 x 25 x 25 mm N.D. Tee CD 40
Considering 1 No. Tee
(a) Equal Tee (as per Titas Gas rate) = Tk. 146.76
(b) Carrying charge LS = Tk. 16.00
Sub - Total = Tk. 162.76
Incidental charges 10.00% = Tk. 16.28
Profit 10.00% = Tk. 16.28
Overhead 3.50% = Tk. 0.57
Total = Tk. 195.89
Add VAT with a 1.06383 6.00% = Tk. 12.50
Grand Total = Tk. 208.39
Say, Tk. 208 .00 each
Item No.- 28.4.4
Supplying different sizes Tee, Elbow, Reducer, Plug, Socket: 50 mm x 90o mm Elbow
Considering 1 No. elbow
(a) Elbow (as per Titas Gas rate) = Tk. 172.43
(b) Carrying charge LS = Tk. 16.00
Sub - Total = Tk. 188.43
Incidental charges 10.00% = Tk. 18.84
Profit 10.00% = Tk. 18.84
Overhead 3.50% = Tk. 0.66
Total = Tk. 226.77
Add VAT with a 1.06383 6.00% = Tk. 14.47
Grand Total = Tk. 241.24
Say, Tk. 241 .00 each
Analysis of PW 628
Item No.- 28.4.5
Supplying different sizes Tee, Elbow, Reducer, Plug, Socket: 25 mm x 90o mm Elbow
Considering 1 No. elbow
(a) Elbow (as per Titas Gas rate) = Tk. 52.77
(b) Carrying charge LS = Tk. 16.00
Sub - Total = Tk. 68.77
Incidental charges 10.00% = Tk. 6.88
Profit 10.00% = Tk. 6.88
Overhead 3.50% = Tk. 0.24
Total = Tk. 82.77
Add VAT with a 1.06383 6.00% = Tk. 5.28
Grand Total = Tk. 88.05
Say, Tk. 88 .00 each
Item No.- 28.4.6
Supplying different sizes Tee, Elbow, Reducer, Plug, Socket: 50 mm x 45o mm Elbow
Considering 1 No. elbow
(a) Elbow (as per Titas Gas rate) = Tk. 74.36
(b) Carrying charge LS = Tk. 16.00
Sub - Total = Tk. 90.36
Incidental charges 10.00% = Tk. 9.04
Profit 10.00% = Tk. 9.04
Overhead 3.50% = Tk. 0.32
Total = Tk. 108.76
Add VAT with a 1.06383 6.00% = Tk. 6.94
Grand Total = Tk. 115.70
Say, Tk. 116 .00 each
Item No.- 28.4.7
Supplying different sizes Tee, Elbow, Reducer, Plug, Socket: 50 x 25 mm Reducer CD 40
Considering 1 No. reducer
(a) Reducer (as per Titas Gas rate) = Tk. 82.44
(b) Carrying charge LS = Tk. 16.00
Sub - Total = Tk. 98.44
Incidental charges 10.00% = Tk. 9.84
Profit 10.00% = Tk. 9.84
Overhead 3.50% = Tk. 0.34
Total = Tk. 118.46
Add VAT with a 1.06383 6.00% = Tk. 7.56
Grand Total = Tk. 126.02
Say, Tk. 126 .00 each
Item No.- 28.4.8
Supplying different sizes Tee, Elbow, Reducer, Plug, Socket: 20 mm Plug/Socket
Considering 1 No. plug/socket
(a) Plug/socket (as per Titas Gas rate) = Tk. 260.00
(b) Carrying charge LS = Tk. 16.00
Sub - Total = Tk. 276.00
Incidental charges 10.00% = Tk. 27.60
Profit 10.00% = Tk. 27.60
Overhead 3.50% = Tk. 0.97
Total = Tk. 332.17
Add VAT with a 1.06383 6.00% = Tk. 21.20
Grand Total = Tk. 353.37
Say, Tk. 353 .00 each
Analysis of PW 629
Item No.- 28.4.9
Supplying different sizes Tee, Elbow, Reducer, Plug, Socket: 50 x 20 mm Saddle
Considering 1 No. saddle
(a) Saddle (as per Titas Gas rate) = Tk. 199.17
(b) Carrying charge LS = Tk. 16.00
Sub - Total = Tk. 215.17
Incidental charges 10.00% = Tk. 21.52
Profit 10.00% = Tk. 21.52
Overhead 3.50% = Tk. 0.75
Total = Tk. 258.96
Add VAT with a 1.06383 6.00% = Tk. 16.53
Grand Total = Tk. 275.49
Say, Tk. 275 .00 each
Item No.- 28.4.10
Supplying different sizes Tee, Elbow, Reducer, Plug, Socket: 50 mm dia End Cap CD 40
Considering 1 No. end cap
(a) End cap (as per Titas Gas rate) = Tk. 64.26
(b) Carrying charge LS = Tk. 16.00
Sub - Total = Tk. 80.26
Incidental charges 10.00% = Tk. 8.03
Profit 10.00% = Tk. 8.03
Overhead 3.50% = Tk. 0.28
Total = Tk. 96.60
Add VAT with a 1.06383 6.00% = Tk. 6.17
Grand Total = Tk. 102.77
Say, Tk. 103 .00 each
Item No.- 28.4.11
Supplying different sizes Tee, Elbow, Reducer, Plug, Socket: 25 mm dia End Cap CD 40
Considering 1 No. end cap
(a) End cap (as per Titas Gas rate) = Tk. 40.39
(b) Carrying charge LS = Tk. 16.00
Sub - Total = Tk. 56.39
Incidental charges 10.00% = Tk. 5.64
Profit 10.00% = Tk. 5.64
Overhead 3.50% = Tk. 0.20
Total = Tk. 67.87
Add VAT with a 1.06383 6.00% = Tk. 4.33
Grand Total = Tk. 72.20
Say, Tk. 72 .00 each
Item No.- 28.5.1
Supplying different sizes Valve Tee, Service Tee: 50 x 50 x 50 mm N.D. Tee
Considering 1 No. equal Tee
(a) Equal Tee (as per Titas Gas rate) = Tk. 16,191.07
(b) Carrying, welding & fitting-fixing LS = Tk. 2,560.00
Sub - Total = Tk. 18,751.07
Incidental charges 10.00% = Tk. 1,875.11
Profit 10.00% = Tk. 1,875.11
Overhead 3.50% = Tk. 65.63
Total = Tk. 22,566.92
Add VAT with a 1.06383 6.00% = Tk. 1,440.44
Grand Total = Tk. 24,007.36
Say, Tk. 24,007 .00 each
Analysis of PW 630
Item No.- 28.5.2
Supplying different sizes Valve Tee, Service Tee: 50 x 50 x 25 mm N.D.Tee CD 40
Considering 1 No. Tee
(a) Tee (as per Titas Gas rate) = Tk. 258.30
(b) Carrying, welding & fitting-fixing LS = Tk. ###
Sub - Tot= Tk. ###
Incidental charges 10.00% = Tk. 249.83
Profit 10.00% = Tk. 249.83
Overhead 3.50% = Tk. 8.74
Total = Tk. ###
Add VAT with a 1.06383 6.00% = Tk. 191.92
Grand To= Tk. ###
Say, Tk. 3,199 .00 each
Item No.- 28.5.3
Supplying different sizes Valve Tee, Service Tee: 25 x 25 x 25 mm Service Tee CD 40
Considering 1 No. Tee
(a) Service Tee (as per Titas Gas rate) = Tk. ###
(b) Carrying, welding & fitting-fixing LS = Tk. ###
Sub - Tot= Tk. ###
Incidental charges 10.00% = Tk. 332.88
Profit 10.00% = Tk. 332.88
Overhead 3.50% = Tk. 11.65
Total = Tk. ###
Add VAT with a 1.06383 6.00% = Tk. 255.72
Grand To= Tk. ###
Say, Tk. 4,262 .00 each
Item No.- 28.5.4
Supplying different sizes Valve Tee, Service Tee: 50 x 25 mm Service Tee CD 40
Considering 1 No. Tee
(a) Service Tee (as per Titas Gas rate) = Tk. ###
(b) Carrying, welding & fitting-fixing LS = Tk. ###
Sub - Tot= Tk. ###
Incidental charges 10.00% = Tk. 452.00
Profit 10.00% = Tk. 452.00
Overhead 3.50% = Tk. 15.82
Total = Tk. ###
Add VAT with a 1.06383 6.00% = Tk. 347.22
Grand To= Tk. ###
Say, Tk. 5,787 .00 each
Analysis of PW 634
Item No.- 28.13
Testing and purging the house line properly as per specification of the Titas Gas T&D Co. Ltd.
Considering 1 meter of work
(a) Testing & purging the house line LS = Tk. 16.00
Incidental charges 10.00% = Tk. 1.60
Profit 10.00% = Tk. 1.60
Overhead 3.50% = Tk. 0.06
Total = Tk. 19.26
Add VAT with a 1.06383 6.00% = Tk. 1.23
Grand Total = Tk. 20.49
Rate per rm = Tk. 20.49
Say, Tk. 20 .00 per meter
DIVISION 30 : CONCRETE HOLLOW BLOCK, FACINGS AND PAVING STONE, NON FIRE BLOCK
Analysis of PW 639
30.2.2 Add for each addl. floor up to 5th floor per sqm = Tk. 31
30.2.3 Add for each addl floor for 6th floor to per sqm = Tk. 42
30.2.4 Add for each addl floor for 10th floor per sqm = Tk. 52
Analysis of PW 640
30.4.2 Add for each addl. floor up to 5th floor per sqm = Tk. 31
30.4.3 Add for each addl floor for 6th floor to per sqm = Tk. 42
30.4.4 Add for each addl floor for 10th floor per sqm = Tk. 52
Analysis of PW 641
30.6.2 Add for each addl. floor up to 5th floor per sqm = Tk. 42
30.6.3 Add for each addl floor for 6th floor to per sqm = Tk. 52
30.6.4 Add for each addl floor for 10th floor a per sqm = Tk. 62
Item No.- 30.7
140 mm thick load bearing wall with concrete hollow block:
cement : lime : sand (1 : 1 : 6)
Consideration 100 sft of work
(a) Material
(i) 140 mm block (390 x 140 x 190 mm)
in/c wastage 116 nos @ Tk. 56.06 per block = Tk. 6,502.96
(ii) Cement 0.7 bag @ Tk. 395.00 per bag = Tk. 276.50
(iii) Lime 15 kg @ Tk. 20.00 per kg = Tk. 300.00
(iv) Sand (F.M. 1.2 4.40 cft @ Tk. 1,400.00 per % cft = Tk. 61.60
(v) Transportation 116 nos @ Tk. 7.87 each = Tk. 912.92
(b) Labour
(i) Head mason 0.1 no @ Tk. 600.00 each = Tk. 60.00
(ii) Mason 1.5 nos @ Tk. 500.00 each = Tk. 750.00
(iii) Ordinary Labou 3.25 nos @ Tk. 320.00 each = Tk. 1,040.00
(c) Scaffolding 25 sft @ Tk. 9.00 per sft = Tk. 225.00
(d) Local carriage, curing & sundries etc. LS. = Tk. 160.00
Sub - Total = Tk. 10,288.98
Profit 10.00% = Tk. 1,028.90
Overhead 3.50% = Tk. 360.11
Total = Tk. 11,677.99
Add VAT with adjustment factor 1.06383 6.00% = Tk. 745.40
Grand Total = Tk. 12,423.39
Rate per sft = Tk. 124.23
30.7.1 Ground floor Rate per sqm = Tk. 1,337.21
Say, Tk. 1,337 .00 per sqm
30.7.2 Add for each addl. floor up to 5th floor (@ 1 lab. per % sft) per sqm = Tk. 42
30.7.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 No. lab. per per sqm = Tk. 52
30.7.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per % per sqm = Tk. 62
Analysis of PW 642
30.8.2 Add for each addl. floor up to 5th floor per sqm = Tk. 42
30.8.3 Add for each addl floor for 6th floor to per sqm = Tk. 52
30.8.4 Add for each addl floor for 10th floor a per sqm = Tk. 62
(a) Skilled labour 1.25 nos @ Tk. 390.00 each = Tk. 487.50
(b) Ordinary labou 1.25 nos @ Tk. 320.00 each = Tk. 400.00
(c) Brooming, cleaning etc. LS = Tk. 32.00
(d) T & P, scaffolding, ladder, sundries etc. LS = Tk. 160.00
SubTotal = Tk. 1,079.50
Contractor's profit10% = Tk. 107.95
Overhead expenses3.50% = Tk. 37.78
Total = Tk. 1,225.23
VAT with adjustment factor 1.06383 6.00% = Tk. 78.21
Grand Total = Tk. 1,303.44
Rate per cum = Tk. 434.48
Say, Tk. 434 .00 per cum
(a) Skilled labour 0.50 nos @ Tk. 390.00 each = Tk. 195.00
(b) Ordinary labou 0.50 nos @ Tk. 320.00 each = Tk. 160.00
(c) Brooming, cleaning etc. LS = Tk. 16.00
(d) T & P, scaffolding, ladder, sundries etc. LS = Tk. 64.00
SubTotal = Tk. 435.00
Contractor's profit10% = Tk. 43.50
(a) Ordinary labou 3.00 nos @ Tk. 320.00 each = Tk. 960.00
(c) T & P, sundries etc. LS = Tk. 96.00
SubTotal = Tk. 1,056.00
Contractor's profit10% = Tk. 105.60
Overhead expenses3.50% = Tk. 36.96
Total = Tk. 1,198.56
VAT with adjustment factor 1.06383 6.00% = Tk. 76.50
Grand Total = Tk. 1,275.06
Rate per % 0 nos = Tk. 1,275.06
Say, Tk. 1,275 0.00 % 0 nos
(a) Ordinary labou 2.00 nos @ Tk. 320.00 each = Tk. 640.00
(c) T & P, sundries etc. LS = Tk. 32.00
SubTotal = Tk. 672.00
Contractor's profit10% = Tk. 67.20
Overhead expenses3.50% = Tk. 23.52
Total = Tk. 762.72
VAT with adjustment factor 1.06383 6.00% = Tk. 48.68
Grand Total = Tk. 811.40
Rate per % 0 nos = Tk. 811.40
Say, Tk. 811 0.00 % 0 nos
Considering 1 cum
(a) Labour for taking out Chowkat Same as Item No. 32.17 = Tk. 227.00
(b) Labour for re-fitting or refixing in position
i) Mason 0.25 no @ Tk. 500.00 each = Tk. 125.00
ii) Ordinary labou 0.25 no @ Tk. 320.00 each = Tk. 80.00
iii) Carpenter for r 0.25 no @ Tk. 600.00 each = Tk. 150.00
(c) Screws LS Tk. 32.00
(d) Paint on clamp & side of Chowkat in contact woth wall LS = Tk. 64.00
(e) T & P, sundries etc. LS = Tk. 32.00
SubTotal = Tk. 710.00
Contractor's profit10% = Tk. 71.00
Overhead expenses3.50% = Tk. 24.85
Total = Tk. 805.85
VAT with adjustment factor 1.06383 6.00% = Tk. 51.44
Grand Total = Tk. 857.29
Rate per No. = Tk. 857.29
Say, Tk. 857 .00 each
Item No. 32.19
Taking out and refitting wooden shutter after easing excluding cost of wood
Considering 1.07 m x 2.13 m = 2.28 sqm
(a) Carpenter 0.50 no @ Tk. 600.00 each = Tk. 300.00
(b) Helper to carpe 1.00 no @ Tk. 390.00 each = Tk. 390.00
(c) Screws 2.00 dzs @ Tk. 8.00 per dz = Tk. 16.00
(d) T & P, nails, glues sundries etc. LS = Tk. 64.00
SubTotal = Tk. 770.00
Contractor's profit10% = Tk. 77.00
Overhead expenses3.50% = Tk. 26.95
Total = Tk. 873.95
VAT with adjustment factor 1.06383 6.00% = Tk. 55.78
Grand Total = Tk. 929.73
Rate per sqm = Tk. 407.78
Say, Tk. 408 .00 per sqm
Item No. 32.20.1
Thorough repairs to wooden door and window Pannel shutter excluding cost of wood
Considering 1.83 m x 1.07 m =1.96 sqm pannel shutter
(a) Carpenter 1.00 no @ Tk. 600.00 each = Tk. 600.00
(b) Helper to carpe 1.00 nos @ Tk. 390.00 each = Tk. 390.00
(c) Screws 4.00 dzs @ Tk. 8.00 per dz = Tk. 32.00
(d) T & P, nails, glue sundries etc. LS = Tk. 64.00
SubTotal = Tk. 1,086.00
Contractor's profit10% = Tk. 108.60
Overhead expenses3.50% = Tk. 38.01
Total = Tk. 1,232.61
VAT with adjustment factor 1.06383 6.00% = Tk. 78.68
Grand Total = Tk. 1,311.29
Rate per sqm = Tk. 669.03
Say, Tk. 669 .00 per sqm
Analysis of 683
Rate for each = Tk. 29.44
Say, Tk 29 .00 each
Item No. 32.39.2
Replacing 75 mm dia brass ring
Considering 1 No. brass hinge
(a) 75 mm dia bras 1.00 no @ Tk. 40.00 each = Tk. 40.00
(b) Labour charge LS = Tk. 9.38
SubTotal = Tk. 49.38
Contractor's profit 10% = Tk. 4.94
Overhead expense 3.50% = Tk. 1.73
Total = Tk. 56.05
VAT with adj 1.06383 6.00% = Tk. 3.58
Grand Total = Tk. 59.63
Rate for each = Tk. 59.63
Say, Tk 60 .00 each
Considering 1 kg
(l) Supply of T. S. P.
Considering 1 kg
(a) brick chips 0.32 cum @ Tk. 2,944.12 per cum = Tk. 942.12
(b) Sand (f.m. 1.2) 0.28 cum @ Tk. 494.34 per cum = Tk. 138.42
(c) Cement 3.00 bags @ Tk. 395.00 per bag = Tk. 1,185.00
(d) Labour
i) Mason 3.00 nos @ Tk. 500.00 each = Tk. 1,500.00
ii) Labour 3.00 nos @ Tk. 320.00 each = Tk. 960.00
(e) T & P and sundries LS = Tk. 64.00
SubTotal = Tk. 4,789.54
Contractor's profit10% = Tk. 478.95
Overhead expenses3.50% = Tk. 167.63
Total = Tk. 5,436.12
VAT with adjustment factor 1.06383 6.00% = Tk. 346.99
Grand Total = Tk. 5,783.11
Rate per meter = Tk. 192.77
Say, Tk. 193 .00 per meter
Item No. 32.84.1
Reexcavation of kutcha drain of 0.30 m wide and avearage 0.6 m depth
Considering 30 m long kutcha drain
(i) Earth work:
30 m x 0.30 m 5.49 cum @ Tk. 73.03 per cum = Tk. 400.93
{Earth work: [PWD SoR 2018 Item No. 2.1.2}
(ii) Extra rate for slope and gradient LS = Tk. 48.00
SubTotal = Tk. 448.93
Contractor's profit10% = Tk. 44.89
Overhead expenses3.50% = Tk. 15.71
Total = Tk. 509.53
VAT with adjustment factor 1.06383 6.00% = Tk. 32.52
Grand Total = Tk. 542.05
Rate per meter = Tk. 18.07
Say, Tk. 18 .00 per meter
Item No. 32.84.2
Reexcavation of kutcha drain of 0.61 m wide and avearage 1.22 m depth
Considering 30 m long kutcha drain
(i) Earth work:
30 m x 0.61 m 22.33 cum @ Tk. 73.03 per cum = Tk. 1,630.76
(a) Sweeper FOR 1.00 use @ Tk. 800.00 per use = Tk. 800.00
(b) Hire charge of 1.00 trip @ Tk. 500.00 per trip = Tk. 500.00
(e) T & P, consumables and sundries LS = Tk. 320.00
SubTotal = Tk. 1,620.00
Contractor' 10% = Tk. 162.00
Overhead 3.50% = Tk. 56.70
Total = Tk. 1,838.70
VAT with adjustment f 1.06383 6.00% = Tk. 117.36
Grand Total = Tk. 1,956.06
Rate per No. = Tk. 1,956.06
Say, Tk1,956 .00 each
a)
Scaffolding inc 1 no @ Tk. 220.00
per day = Tk. 220.00
(d) Carrying LS = Tk. 96.00
SubTotal = Tk. 316.00
Contractor's profit10% = Tk. 31.60
Overhead expenses3.50% = Tk. 11.06
Total = Tk. 358.66
VAT with adjustment factor 1.06383 6.00% = Tk. 22.89
Grand Total = Tk. 381.55
Rate per day = Tk. 381.55
Say, Tk. 382 .00 per day
Supply of essential hard wares and consumables for repairing aluminium door window frame and shutter, partition etc