Safety Bulletin: Setting Outriggers To Prevent Accidents

Download as pdf or txt
Download as pdf or txt
You are on page 1of 12

SAFETY BULLETIN

SETTING OUTRIGGERS
TO PREVENT
ACCIDENTS

AMERICAN CONCRETE
PUMPING ASSOCIATION
WWW.CONCRETEPUMPERS.COM
Copyright ©2010 v1.01 ACPA – All rights reserved
Manufacturer’s recommendations supersede any
and all information provided by the ACPA.
January 22, 2010 Safety Bulletin # 05001

Safety Bulletin
Setting outriggers
to prevent accidents

Background information Before jacking the first outrigger, look under the truck
Tipping accidents have occurred as a result of: to be sure that no one has approached the pad on the
opposite side (Figure 1). When possible, use a spotter.
• Inadequate cribbing
As an outrigger is jacked, the entire unit tips the
• Misjudging the soil opposite direction. This tipping causes the outrigger
• Soil not compacted on the opposite side to become closer to the ground.
• Setting up too close to excavations or backfilled The weight and force of this movement could easily
areas crush anything that comes between the outrigger and
the ground. Be careful when jacking the outriggers!
• Hidden voids
• Wash outs
• Natural or man-made voids
Setting the outriggers of a concrete pump with placing
boom is one of the most critical jobs of the concrete
pump operator and should always be done in
accordance with the manufacturer’s recommended
procedure. If not done properly, it can lead to a serious
accident.

Setting outriggers
When arriving at the jobsite, always check-in with the
contractor. Talk with the superintendant or foreman
regarding where to set up safely. The contractor needs lookingunder.eps

to supply a safe set-up area where the soil is capable of Figure 1


supporting the outriggers and there are no voids, pipes, Look under
or other hidden dangers.
Always use the factory-supplied cribbing pads or
more, no matter what the surface, even if it is on
concrete. If jobsite conditions do not allow full
extension of all outriggers and you are required to
shortrig, be sure that you understand all of the rules. If
you do not understand the rules, do not set up!
When laying cribbing, spread the load. Use as
practical, especially on the side that will feel the
weight of the boom. Walk around the unit and center
the outrigger pads and cribbing directly under each
outrigger foot pad.
There are some additional do’s and
don’ts of outrigger stabilization:

Figure 2
Dos and don’ts of outrigger stabilization

• Do not set the outrigger on uneven soil (Figure When jacking, put the full weight of the truck on
2 A). If necessary, reposition the unit or level each outrigger, one at a time, and if the pad starts
the soil. to sink, retract the foot and supply more cribbing.
• Do not set the outrigger on a hill (Figure 2 B). Continue this process until the outrigger appears
The force of the machine weight must be stable and the pad shows no sign of sinking. Only
transmitted straight down. If you were to set up then are you ready to unfold the boom.
as shown in this example, the outrigger load If you are unable to get the outriggers to stabilize,
would be partially down and partially sideways, do not unfold the boom. Relocate the pump to a
putting undue strain on the outrigger leg. location that will support the weight of the
• Do not bridge a hole with outrigger cribbing outriggers.
(Figure 2 C). If there is no soil contact over the
hole, the pressure on the ends of the pad is
much greater. The soil could give way or the
cribbing could break.
• If you determine that you need five pieces of
cribbing to support the load but the foot only
touches three of them, the outrigger will sink
into the soil. To avoid this problem, lay dunnage
the opposite direction on top of the first layer
(Figure 2 D). The top layer of dunnage must
contact all pieces that are supporting it.

Page 2 of 10
Watch for warnings

ps
pads.e
twatch
boomou

Figure 3
Slowly slew the outrigger around the unit and watch for any outrigger sinking

As you unfold the boom, always test the stability Get as much cribbing as you need
of the unit. Slowly slew the extended boom over Safety and stability of the pump is everyone’s
each outrigger. If you see that an outrigger is concern. Most people will be happy to provide you
sinking into the soil, immediately slew the boom with whatever you need - especially if they know
back to the position it came from, and fold it up. their own safety is at stake. Wood dunnage is very
Adjust the amount of dunnage under the cribbing common and works well for well compacted, flat
pads until you have enough soil contact to hold the soil. If you are on soft soil or near the edge of an
unit without sinking. Repeat the procedure for excavation, it may be necessary to ask for a large,
each outrigger (Figure 3). Stability of the unit flat, steel plate to help distribute the weight.
must be ensured.
Retracting outriggers
While pumping, continue checking the outriggers
throughout the day to be sure they are not sinking. An outrigger may suddenly jump when weight is
removed, because the center of gravity on the
Other warning signs to watch for during your truck has shifted. Never stand behind the outrigger
initial set-up include: or between it and another fixed object when it is
• Very green grass in a circular shape being retracted (Figure 4). Clear the outrigger area
• Pipes sticking out of the ground of personnel before retracting outriggers.
• Signs of excavation
• Sprinkler heads
• Backfilled ditches
• Ditches with water in the bottom

outrigjump.eps

Figure 4
Don’t stand behind the outrigger
when it is being retracted

Page 3 of 10
Figure 5 sinking2.eps

Inadequate cribbing. Is the soil un-compacted


or soft?
sinking.eps

Figure 6
Warning clues

newbackfill.eps

The pictures in Figure 5 and Figure 6 show sink, the boom should be brought back to the
examples of signs of trouble when cribbing under travel position and adequate cribbing placed under
an outrigger is inadequate because of soil the outrigger.
conditions. Clue #1 in Figure 6 is a fresh pile of Figure 7, is an example of an accident with
dirt, indicating recent excavation. Clue #2 is the inadequate cribbing that occurred without
utility box which is another sign of recent warning. Virgin ground is capable of withstanding
excavation. Clue #3 is the outrigger (without only about 22 PSI of pressure. Because of that low
cribbing) beginning to sink into the soil. When the pressure capacity, the load must be spread over a
operator swings the boom over the outrigger, it large area.
will begin to sink. When the outrigger begins to
Had the operator provided a large area of cribbing
under the outrigger (like that in Figure 10), this
accident could have been avoided.

Figure 7
Punch through accident because of soil conditions
virginground.eps

Page 4 of 10
Do not partially extend outriggers

NO!

Outrigger
Inner Box
Outrigger
Reinforcements
Force
OK
Fulcrum
Outer Box
Reinforcements
nopartialextension.eps

1. Outrigger fully retracted.


No lever action.
Figure 8 Force absorbed by reinforcements.
Do not partially extend outriggers Force must be low, or unit will tip.

Fulcrum

CAUTION
Structural damage to outriggers is
Force
OK
possible. Do not jack outriggers unless Fulcrum
Force
they are either fully extended or fully
000467.eps

retracted.

Partial extension of telescoping outriggers is not 2. Outrigger fully extended.


acceptable at any time. Jacking the outriggers while Lever action present, but
force absorbed by reinforcements.
they are in any position other than fully extended or
force&leverOUTRIG.eps
fully retracted could cause structural damage to the
outrigger outer box and/or the inner box (Figure 8).
Fulcrum Fulcrum
The three illustrations shown in Figure 9 explain the
situation with the outrigger in all positions.
Remember that the boom must never be extended over
a retracted outrigger. Force

Force
NO!
Figure 9 3. Outrigger partially extended.
Partial extension can cause Lever action present, but force transmitted
damage to the outrigger to areas with no reinforcements. Could cause damage.

Page 5 of 10
Figure 10
Outrigger load spread properly to avoid the
possibility of accidental punch-through
spreadload.eps

Figure 10 shows an effective way to spread the Excavations and cliffs


load of the outrigger foot and bring the pressure If set-up will be done near an excavation, the one-
imposed on the ground to a minimum. to-one rule must be applied (Figure 11). The
outrigger force emits pressure as a 45˚ cone below
4’ x 8’ sheet of steel = 4608 square inches the surface, so it is very important to be aware of
Outrigger force = 32,600 washouts at the base of an embankment as shown
by the “X” in Figure 12. Engineered support walls
32,600 ÷ 4608 = 7.07 PSI can be treated differently than excavations, and the
operator may follow the advice of the contractor or
engineer on the job if he believes the advice to be
sound.
NOTE!
Measurement for the one-to-one rule shall
be made from the edge of the outrigger pad
nearest the excavation, and the distance
from the edge should be increased if soil
conditions appear unstable, if the jobsite
authorities indicate the soil conditions are
unstable, or if the manufacturer's recom-
mendation is more restrictive.
1to1rule.eps

THE ONE TO ONE RULE:


FOR EVERY 1 FOOT OF VERTICAL DROP,
STAY BACK FROM THE BASE EDGE 1 FOOT.
(DISTANCE "B" MUST BE EQUAL TO
DISTANCE
B OR GREATER THAN DISTANCE "A")

Figure 11
One-to-one rule base edge DISTANCE
A

Figure 12
Watch for this 45 Degrees
(Soil washed out at the “X”) X

Page 6 of 10
Hidden voids are hidden hazards

hidden voids.eps

Figure 13
Examples of underground hazards
Unless an operator has x-ray vision, there is no
way he can tell if he is setting up over a hidden
void (Figure 13). Some voids, like septic systems,
may have a pipe protruding from the ground.
Sprinkler heads would give some indication that
there might be buried hazards. But some voids,
like a buried box, leave no clues for even the
safest-minded operator. His only chance is
spreading the load.
Figure 14 shows an example of a punch-through
that occurred without warning because of an
underground void. The pour had progressed for
some time with no warning of the outrigger
sinking when it suddenly punched through and
brought the boom crashing down.

punchthrough.eps

Figure 14
Hidden voids cause accidents

Page 7 of 10
Inadequate cribbing load bearing capacity of 58 PSI. If an outrigger
The formula for determining the load imposed on was placed on the manufacturer’s supplied
the soil is to divide the total outrigger force cribbing pad, which has 576 square inches of
(pounds) by area of soil contact (square inches). surface, it could technically support the unit.
Soil pressure = total outrigger force ÷ area of soil 32,600 ÷ 576 = 56.59 PSI
contact It is easy to misjudge the soil material or
The following chart shows a few of the different compaction, and the information is often not
soil types and their approximate load-bearing available. The best case scenario would be to
capacities: spread out the load considerably more than the 576
square inches by placing a larger base under the
Soil Type and Approx. Load-bearing Capacity supplied pad. For example, ten 36” long 4x4’s
Virgin ground................................ 22 PSI (1260 square inches) or a 4 foot x 8 foot (4608
Asphalt.......................................... 29 PSI square inches) sheet of strong material (like steel)
Compressed, crushed stone........... 36 PSI would lower the outrigger pressure dramatically,
Clay/silt soil, firm.......................... 43 PSI reducing the chance of an outrigger sinking or
Mixed granular soil....................... 51 PSI dropping.
Firm, compacted gravel................. 58 PSI Operators are not expected to make calculations
Brittle, weathered rock..................145 PSI such the one shown above while on a jobsite. This
information is given only to show that the ground
Misjudging the soil has many different load bearing capacities, and
Operators rarely have access to the compaction boom trucks all impose a different force on the
data of a jobsite, and will generally have to make soil. The bottom line is this, the greater the force
judgment calls. Because of this, they should make imposed on the soil, the larger the dunnage area
the cribbing base as large as is practical. must be.
An example:
The decal on a pump outrigger shows a maximum
force of 32,600 pounds (Figure 15). The soil is
firm, compacted gravel, which has an approximate

32,600 LBS

Figure 15
Pump outrigger decal example

Page 8 of 10
Summary • Have a place prepared for the pump before it
arrives on the job.
Prevention
• Inform the operator of backfilled areas, soft or
Tip-over accidents can be avoided if people take
muddy areas, or underground obstructions.
precautions when the unit is set up. Both operators
and contractors must be aware of the potential • Have cribbing nearby the set-up area prior to
danger that exists when a large boom is unfolded the pump’s arrival (including steel sheets if the
and extended over outriggers. If the contractor soil is known to be bad).
remembers to offer additional cribbing and if the • Monitor the set-up. Don’t let the operator cut
operator remembers to ask for it when it isn’t corners or take chances.
offered, the problem can be minimized even before
Dispatcher
the boom is extended.
The dispatcher can help by communicating with
Cribbing: more or less? the contractor when he calls to order the pump,
• More is better and:
• The stronger the material the better • Send the size pump that is needed, if available.
• Pay close attention to the type of soil where • If availability causes you to send a unit that is
you’re setting up the unit. too big or too small, warn of possible
complications.
Training
• Ask about soil conditions or underground
Every person in the chain of a pumping job has a
obstructions.
responsibility to help protect the hose person and
other nearby personnel. Education is the key, Operator
followed closely by diligent watchfulness and The operator is ultimately in charge and must
personal protective equipment. Educational make good decisions regarding set-up including:
materials are available from the ACPA, and
everyone involved in the concrete pumping • Use as much cribbing as practical; too much is
process should be trained, including: better than too little.
• Job superintendents • Watch for all warning signs prior to set-up.
• Labor foremen • Watch for sinking outriggers while unfolding
the boom, and continue to recheck them
• Laborers throughout the day.
• Pump operators • Keep people out from under the boom
Responsibilities whenever practical.

Contractors
• One of the things a contractor can do to help is This document is intended to supplement, but not
to order the right size boom: supersede the manufacturer’s applicable instruc-
tions.
• If the boom is too small, for example, he
may have to set up too close to an
excavation to reach the pour. - By Danny Mace and Robert Edwards,
• If the boom is too large, it will require Edited by the ACPA.
much more cribbing than a smaller unit.

Page 9 of 10
I
R ICA
T F
C E

TIO
N

N
T I O

TIFIC A ER C

AMERICAN CONCRETE PUMPING ASSOCIATION


606 ENTERPRISE DRIVE | LEWIS CENTER, OH 43035
P: 614.431.5618
WWW.CONCRETEPUMPERS.COM

You might also like