GEO Publication No. 1 - 2009
GEO Publication No. 1 - 2009
GEO Publication No. 1 - 2009
1/2009
PRESCRIPTIVE MEASURES
FOR MAN-MADE SLOPES
AND RETAINING WALLS
PRESCRIPTIVE MEASURES
FOR MAN-MADE SLOPES
AND RETAINING WALLS
Prepared by :
Top Right : Soil and Rock Cut Slope at Tin Hau Temple Road, North Point
FOREWORD
This Publication presents a recommended standard of good practice for the application
of prescriptive measures as improvement works on existing man-made slopes and retaining
walls in Hong Kong. The scope of application covers a range of prescriptive measures items
in the form of preventive maintenance works, upgrading works or repair works to landslides.
Various types of prescriptive measures have been developed for soil/rock cut slopes,
fill slopes and masonry/concrete retaining walls. The findings and recommendations of the
studies on the formulation of the prescriptive measures framework are given in a series of
technical reports and guidance documents published by the Geotechnical Engineering Office
from 1995 to 2007. This Publication integrates and rationalises the recommendations and
provides a comprehensive guidance document on the application of prescriptive measures to
existing man-made slopes and retaining walls.
Copies of a draft version of this document were circulated to local professional bodies,
consulting engineers, academics and Government departments. Many individuals and
organisations made useful comments, which have been taken into account in finalising this
Publication. All contributions are gratefully acknowledged.
R.K.S. Chan
Head, Geotechnical Engineering Office
August 2009
4
CONTENTS
Page
No.
TITLE PAGE 1
FOREWORD 3
CONTENTS 4
LIST OF TABLES 7
LIST OF FIGURES 9
1. INTRODUCTION 11
2. APPLICATIONS 12
2.1 GENERAL 12
Page
No.
3.1 GENERAL 24
4.1 GENERAL 31
5.1 GENERAL 41
Page
No.
6. OTHER CONSIDERATIONS 67
6.1 GENERAL 67
6.4 BUILDABILITY 68
6.8 MAINTENANCE 69
REFERENCES 70
GLOSSARY OF SYMBOLS 74
7
LIST OF TABLES
Table Page
No. No.
Table Page
No. No.
LIST OF FIGURES
Figure Page
No. No.
5.5 Prescriptive Soil Nails on a Soil Cut Slope with Toe Wall 53
Figure Page
No. No.
1. INTRODUCTION
General guidance on the application of prescriptive measures, together with the merits
and limitations of their use, is outlined in Chapter 2. The required qualifications of
personnel responsible for the design of prescriptive measures are also given in this chapter.
2. APPLICATIONS
2.1 GENERAL
Many of the engineered man-made slopes in Hong Kong were designed using the
conventional analytical approach based on detailed ground investigations and design analyses.
However, the annual failure rate of engineered slopes, in particular those without robust
engineering measures such as unsupported soil cuts (e.g. slope cut back with no structural
support), is not low (Ho et al, 2003). Systematic landslide investigations carried out by the
Geotechnical Engineering Office (GEO) revealed that failures in engineered slopes were
mainly associated with problems including uncontrolled surface runoff and presence of
adverse geological features and/or adverse groundwater conditions. This reflects the
inherent uncertainties and limitations of the conventional analytical approach, which include
inadequate engineering geological input during ground investigation, poor detailing in slope
drainage provisions, etc.
The use of prescriptive measures is not a new concept in Hong Kong, as the
prescriptive approach has long been adopted in some types of man-made slope works.
These included rock slope stabilisation works (e.g. Brand et al, 1983; Dubin et al, 1986), and
surface recompaction of loose fill slopes (e.g. GCO, 1984; Knill et al 1999). The idea of
developing prescriptive measures for general use in improvement works on man-made slopes
in Hong Kong was first considered in the 1980s (Malone, 1985). The use of prescriptive
measures was formally recognised for retaining wall design in the second edition of
Geoguide 1 : Guide to Retaining Wall Design (GEO, 1993).
The use of prescriptive measures had also been recognised as one of the approaches to
geotechnical design in some overseas design codes. For example, Eurocode 7 (BSI, 2004)
allows the use of prescriptive measures in situations where calculation methods are not
available or are not necessary.
13
Another study was initiated in 1999 to develop a prescriptive approach involving the
use of reinforced concrete skin walls for upgrading existing masonry retaining walls. The
prescriptive approach was formulated based on a review of past cases of skin wall design for
upgrading existing masonry retaining walls (Wong & Pun, 1999).
In 1999, all the then prevailing guidelines on the application of prescriptive measures
were consolidated in the second edition of GEO Report No. 56 : Application of Prescriptive
Measures to Slopes and Retaining Walls (Wong et al, 1999). In response to the rising
expectations of the public in respect of slope appearance, guidelines for prescriptive use of
vegetation cover on soil cut slopes to improve slope appearance were also given in the Report.
In 2003, a study was carried out to review the use of prescriptive measures on rock cut
slopes and the findings were documented in GEO Report No. 161 : Guidelines on the Use of
Prescriptive Measures for Rock Cut Slopes (Yu et al, 2005). The use of prescriptive
approach in rock slope stabilisation works has been widely applied in local practice for many
years. The guidelines developed in 2003 were aimed at rationalising the design practice and
providing detailed technical guidance on the use of different items of prescriptive measures on
rock cut slopes. In the course of developing the guidelines, more than 100 rock slopes
upgraded under the LPM Programme were reviewed.
Another study was carried out in 2004 to extend the application of prescriptive soil
nails to concrete retaining walls, masonry retaining walls and soil cut slopes with toe walls.
Prescriptive soil nail design guidelines were derived based on the review and analysis of some
past cases in which soil nails designed by conventional analytical approach were used to
upgrade concrete retaining walls, masonry retaining walls and soil cut slopes with toe walls.
The guidelines are given in GEO Report No. 165 : Prescriptive Soil Nail Design for Concrete
and Masonry Retaining Walls (Lui & Shiu, 2005).
14
Prescriptive measures have basically been developed for use under two categories of
slope improvement works, namely preventive maintenance works as defined in Geoguide 5 :
Guide to Slope Maintenance (GEO, 2003) and upgrading works. Some of the prescriptive
measures can also be applied as repair works to landslides.
Prescriptive measures may not be applicable for upgrading retaining walls with
sizeable wall trees that are well anchored to the wall by their roots. In this case, the dead
weight of wall trees, together with the effect arising from wind loading on the wall trees, may
adversely affect the stability of the retaining wall. Designers should exercise due
engineering judgement in determining whether detailed analyses are warranted to evaluate the
effects of wall trees, taking into account the degree of anchorage of the tree roots.
If a slope feature that had been designed and checked to comply with the required
geotechnical standards fails, then the prescriptive approach may not be applicable and the
slope feature should be investigated to determine the necessary upgrading works.
There are, however, some inherent limitations if the prescriptive measures are used
alone. These include the following:
Provided that designers acknowledge and work within these limitations, prescriptive
measures can be adopted as effective slope improvement works. Guidance given in this
document is aimed at minimising landslide risk associated with the above limitations.
The merits and limitations of the prescriptive measures listed above are not exhaustive.
Designers should compare design options based on prescriptive approach and those based on
conventional analytical approach in option assessments, and exercise due engineering
judgement to select the best engineering solution for the problem at hand.
Prescriptive measures for slope features may broadly be classified into the following
three types according to the design objectives:
(ii) soil nails for soil cut slopes with toe walls,
In selecting the appropriate types and items of prescriptive measures, designers should
take due account of the nature of the slope-forming materials, geological conditions,
groundwater conditions, nature and locations of services, surface water pathways,
performance history of the slope, consequence in the event of failure, site constraints, together
with the type and level of improvement required. Designers should also exercise
engineering judgement when prescribing the measures recommended in this document, or in
applying other measures as deemed appropriate in order to suit the actual site conditions.
Type 3, generally
Soil cut slopes(2)
supplemented by Types 1 and/or 2
Generally Types 1 and/or 2,
sometimes Type 3
Generally Types 1 and/or 2, Generally Types 1, 2 and 3
Rock cut slopes sometimes Type 3 used in combination
Type 3, generally
Retaining walls
supplemented by Types 1 and/or 2
Generally Types 1 and/or 2
Notes: (1) Slope features should satisfy the qualifying criteria given in Chapter 5 for the application of
Type 3 prescriptive measures as upgrading works.
(2) Soil cut slopes include those slope features with toe walls.
(3) Fill slopes can be upgraded by the prescriptive approach of surface recompaction and
subsurface drainage provisions following the guidance given in the Geotechnical Manual for
Slopes (GCO, 1984), Works Bureau Technical Circular No. 13/99 (Works Bureau, 1999),
GEO Technical Guidance Note No. 7 (GEO, 2007a), GEO Report No. 225 (Fugro Scott
Wilson Joint Venture, 2008) and Pun & Urciuoli (2008). Types 1 and/or 2 prescriptive
measures may also be used in conjunction with surface recompaction.
17
Figure 2.1 Schematic Diagram of Typical Prescriptive Measures for Man-made Slope Features
18
Types 1 and 2 prescriptive measures improve the surface protection and drainage
condition of slope features. In essence, these are preventive maintenance works which will
help reduce the rate of slope deterioration. As such, no qualifying criteria are needed.
Given that the surface protection and drainage provisions on many old slopes are deficient or
do not exist, designers should apply Types 1 and 2 prescriptive measures as preventive
maintenance works to any types of existing slope features wherever practical.
Type 1 and/or 2 prescriptive measures can also be used as part of the repair works to
landslides, in particular during the time shortly after landslide occurrence when the priority is
to remove immediate danger in order to protect life and property. Although Type 3
prescriptive measures are not commonly needed as emergency repair works to landslides,
their use cannot be precluded in certain circumstances. Considerations should be given to
the scale and mechanism of failure, the consequence of further landslides, and the
effectiveness of the prescriptive measures in respect of the recovery of the emergency
situation, and each case should be treated on its own merits.
Some items of prescriptive measures need to be installed into the ground. Designers
will need to check the land status. Should the proposed prescriptive measures need to be
extended into the adjoining land, designers should seek the agreement of the land owner as
necessary before implementation of the works.
Records of Landslides
Date of Landslide Scar Height (m) Failure Volume (m3) Principal Causes of Failure Incident No.
1.
2.
3.
Attachments:
Site location plan Photographs Records of Engineer Inspections
Plan, sketches/drawings showing locations/layout/key dimensions of proposed prescriptive measures
Figure 2.2 Record Sheets for Prescriptive Measures on Man-made Slope Features (Sheet 1 of 2)
22
Works commenced on Works completed on Works certified by (Name & Post) Signature and Date
__________________ ________________ ____________________________ _________________
Figure 2.2 Record Sheets for Prescriptive Measures on Man-made Slope Features (Sheet 2 of 2)
23
For preventive maintenance works to slope features that involve only surface
protection and surface drainage prescriptive measures, the prescriptive design and
construction review may also be carried out by a professionally qualified civil engineer
competent in site formation and drainage works. It is preferable, and often more cost-
effective, to have the same professional engineer who undertakes the Engineer Inspection of
the slope feature to also design the prescriptive measures as part of the preventive
maintenance recommendations.
Regular reviews should be carried out during construction. The professional engineer
who undertakes the construction reviews should be familiar with all the information collected
in the desk study and site reconnaissance, as well as the assumptions made in prescribing the
measures. The preferred arrangement is for the same professional engineer who designed
the prescriptive measures items to carry out the construction reviews (see also Section 6.7).
Where Type 3 prescriptive measures have been applied to a slope feature as upgrading
works in accordance with the recommendations of this document, the slope feature can be
taken to have been upgraded to the required safety standards.
3.1 GENERAL
Table 3.1 shows a summary of the Type 1 prescriptive measures items and the
associated design objectives. The application of the items should be specified by designers
to best suit the slope feature type and actual site conditions.
Improve surface protection 1.2 Wire mesh/Face netting for rock slopes
(1) Surface Cover for Soil Slopes. A slope surface cover is necessary to prevent
undue surface infiltration and protect the soil slopes against erosion by surface runoff.
Where the existing slope surface cover is deficient, a new one should be provided depending
on the susceptibility of the slope to surface infiltration and erosion.
A vegetation cover may be used to provide surface protection to soil slopes. Since
the slope will be prone to surface erosion if the vegetation is not well established, the
provision of appropriate erosion control measures and suitable types of vegetation is essential
to the proper performance of the vegetation cover. Recommended measures for the
25
prescriptive use of vegetation cover for soil slopes of different gradients are given in
Table 3.2. Such measures are appropriate for both soil cut slopes and fill slopes, which have
an inadequately developed vegetation cover or a defective chunam cover which no longer
serves as a relatively impermeable cover effectively.
Notes: (1) The measures given in this Table are based on known successful experience in Hong Kong.
Other measures as given in GEO Publication No. 1/2000 (GEO, 2000a) may be used where
considered appropriate.
(2) For soil cut slopes steeper than 55°, designers may adopt similar suite of erosion control
measures as slopes with gradients between 45° and 55° but close monitoring of vegetation
growth and its performance on erosion control during maintenance is recommended.
(3) Fixing details for erosion control mats should comply with the manufacturer’s instructions.
The prescriptive use of vegetation cover for soil slopes should be in conjunction with
other suitable items of prescriptive measures as recommended in this document. For the
area below and adjacent to downslope drainage channels with convergent surface water flow,
consideration should be given to providing an impermeable, erosion-resistant surface
protective cover, e.g. apron slabs of 0.5 m to 1 m in width on both sides of the channels, to
further strengthen the surface protection of the vegetated soil slope.
Shotcrete, or any other kinds of hard slope facings, may provide a hard surface cover
for soil slopes to prevent surface infiltration and protect the slopes against surface erosion.
Designers’ attention is drawn to the need to strike a suitable balance between slope safety and
slope appearance. The government policy on slope appearance is that any existing
vegetation on a slope should be maintained as far as possible (Works Bureau, 1993 & 2000).
Prior to adopting a shotcrete facing where this is deemed appropriate, any landslide
debris or loose materials on the slope surface should be removed to ensure proper contact
between the shotcrete and the slope. Applying shotcrete directly onto a slope surface with
active seepage must be avoided. A hard surface cover is generally not necessary for the less
weathered portion (PW50/90 zone or better, as defined in Geoguide 3 : Guide to Rock and
Soil Descriptions (GCO, 1988)) of a slope formed in weathered rock.
Technical Circular No. 13/99 : Geotechnical Manual for Slopes - Guidance on Interpretation
and Updating (Works Bureau, 1999), and GEO Technical Guidance Note No. 15 : Guidelines
for Classification of Consequence-to-Life Category for Slope Features (GEO, 2007b).
However, for soil cut slopes of consequence-to-life Categories 1 and 2, the replacement of the
hard surface cover by vegetation cover should be done only where soil nailing works are also
carried out to upgrade the slope at the same time. For such cases, the soil nails should be
designed, either by means of the conventional analytical approach or the prescriptive
approach, to upgrade the slope to meet the required safety standards for a ‘new’ slope.
(2) Wire Mesh/Face Netting for Rock Slopes. Apart from local zones of
closely-fractured rock mass which may warrant shotcreting, rock slopes generally do not
require a hard surface cover. Wire mesh (sometimes referred to as face netting) may be
fixed to a rock face to prevent small rockfalls, or hung loosely over a slope to guide rocks to
the slope toe. The lower end of the mesh should be no more than about 0.6 m above the
slope toe in order to prevent rock blocks from falling and bouncing onto the facility
(e.g. road) at the slope toe. These measures are generally effective for retaining moderately
to highly fractured rock blocks with dimensions up to about 0.6 m to 1 m, but they may not be
suitable for retaining highly to completely weathered materials.
The likely volume/extent of rock mass to be retained and the minimum typical block
size of the rock face would govern the choice of wire mesh. Galvanised and PVC coated
double-twisted hexagonal wire mesh (e.g. 2.2 mm diameter wire with 80 mm x 60 mm
openings) would be suitable for use on steep cut faces to control rockfalls with dimensions of
less than about 0.6 m. For larger rock blocks, consideration may be given to the use of more
robust forms of face netting, such as cable nets or ring nets (Muhunthan et al, 2005), as
judged appropriate by the designers.
The upper edge of the wire mesh should be placed close to the potential rockfall source
so that the blocks will have little momentum when they impact on the mesh. The mesh
should be anchored in accordance with the latest version of CEDD Standard Drawing
No. C2205 : Fixing of Wire Mesh to Rock Face. The mesh should be anchored at
intermediate points by U-hooks or similar at a spacing of about 3 m. Such spacing will
generally permit the detached rock blocks to work their way down to the slope toe rather than
accumulating behind the mesh. Near the bottom of the slope, U-hooks with an extension
connector should be provided at the lowest row so that they can be loosened and removed
from the anchored end to enable the mesh to be lifted for removal of the detached rock blocks.
cuts where the reduced height and setback from the carriageway would mean any minor
rockfalls would not reach the road, mixed rock/soil slopes where wire mesh is only warranted
on the ‘hard-rock’ portion with credible rockfall potential, etc.
(3) Surface Protection for Retaining Walls. Surface protection works to retaining
walls include sealing of cracks on the surfaces of concrete walls, sealing of cracked mortar
joints or missing pointing on masonry walls, and repairing of defective joint sealant on
concrete walls. Loose or dislocated blocks of pointed masonry walls should be fixed with
cement mortar. Where there are concerns regarding surface infiltration at the crest of a
retaining wall, the crest area should be paved.
A review of all potential surface water pathways that could affect the slope feature
should be carried out prior to the design of prescriptive surface drainage measures. Potential
convergent surface water flow should be diverted away from the slope feature where possible
or should be directed downslope, preferably with no change in the flow direction, by means of
drains with adequate capacity.
Consideration should be given to providing an upstand for the crest drainage channel
of a slope feature to minimise possible uncontrolled spillage of surface water, and increasing
the channel gradient and size. Details of the upstand are shown in the latest version of
CEDD Standard Drawing No. C2509 : Shotcrete to Upslope Area and Crest Channel with
Upstand. However, the possibility of local ponding behind the upstand at the crest channel
should be considered. Where an upstand is provided, the gradient along the alignment of the
channel should exceed 1 in 10. Similar details may be adopted for the berm channels, except
that the height of the upstand may be reduced.
Special attention should be given to the layout and detailing of the surface drainage
system to ensure adequate flow capacity and containment of flow within the channels,
together with adequate discharge capacity at the downstream side. For instance, abrupt
changes in the flow directions, which can be conducive to spilling or overflow along the
channels, should be avoided. Environmental factors, such as potential sources of
concentrated flow of surface water which may adversely affect slope stability, should be dealt
with properly. Further discussions on the role of environmental factors in slope instability
are given by Au & Suen (1991a & b).
In the case of a rock slope, excavations in rock for the construction of drainage
channels will be tedious. Alternative typical details of the crest flat drainage channel are
shown in Figure 3.1. For a steeply inclined rock face, the size of catchment for the rock face
itself is generally small. Half-round channels may be used on berms to minimise
excavations in rock. If the amount of surface runoff on the rock face is not large, berm
channels which require excavations in rock may be omitted. However, the berms should still
be paved with concrete to prevent water ingress into any open rock joints. The use of
stepped channels on steep rock slopes may result in spillage of water. Site-specific designed
downpipes are an alternative to stepped channels.
Figure 3.1 Alternative Flat Drainage Channel Details to Minimise Excavation in Rock
29
Loose rocks may be removed by hand-held scaling bars. However, removal should
only be done where it is certain that the new face will be stable and there is no risk of
undermining the upper part of the rock slope. Designers should re-examine and re-assess the
stability of the rock face following local trimming and scaling of certain loose rocks.
Removal of loose rocks on the slope face may not be effective where the rock is highly
fractured. Other measures such as use of wire mesh may be considered in such cases.
(2) Dentition. In the case of rock slopes, dentition can be used to backfill slots
resulting from trimming of bands of soft materials, or to support an overhang formed on the
rock face. Typical details of dentition works are shown in the latest version of CEDD
Standard Drawing No. C2204 : Typical Rock Face Dentition. A grout pipe may be provided
for subsequent grouting to ensure good contact between the overhang and the supporting
concrete dentition.
30
B A/2
A/2
4.1 GENERAL
Table 4.1 shows a summary of the Type 2 prescriptive measures items and the
associated design objectives. The application of the items should be specified by designers
to best suit the type of slope feature and actual site conditions.
Where the build-up of groundwater pressure is likely to be so rapid that drainage from
the slope surface alone may not be adequate to avoid failure, subsurface drainage provisions
should be provided.
(1) Raking Drains. Raking drains can be effective in lowering the groundwater
level and relieving the groundwater pressure at depth. Three items of prescriptive measures
may be used:
32
Notes: (1) For details of raking drains, see the latest version of CEDD Standard Drawing
No. C2403 : Typical Arrangement of Raking Drains.
(2) The spacing of the raking drains is nominal and may be varied to suit actual site
conditions as determined by designers.
Notes: (1) For details of raking drains, see the latest version of CEDD Standard Drawing
No. C2403 : Typical Arrangement of Raking Drains.
(2) The spacing of the raking drains is nominal and may be varied to suit actual site
conditions as determined by designers.
If raking drains are used in conjunction with soil nails on a slope feature, the drains
should be oriented and/or lengthened to intercept any groundwater behind the soil-nailed zone
as deemed appropriate by designers. The raking drains should be installed after all the soil
nails at elevations higher than the raking drains have been grouted.
(2) Toe Drains. For slope features affected by high groundwater level,
construction of toe drains (Figure 4.3) provides an effective means of lowering the
groundwater level close to the lower part of the slope face. These may be used in
combination with other Type 2 prescriptive measures to facilitate subsurface drainage, or as
contingency provisions.
(3) Counterfort Drains. For slope features which are liable to a rapid build-up of
groundwater pressures, such as development of a perched water table in a relatively thin
surface mantle of loose colluvium overlying weathered rock (e.g. Pun & Li, 1993;
Wong & Ho, 1995), the use of raking drains alone may not necessarily provide sufficient
drainage capacity to quickly relieve the transient groundwater pressures to avoid failure. In
such cases, counterfort drains (Figure 4.4) could be used, either on their own or in
combination with raking drains.
To be more effective, counterfort drains should be extended into the underlying less
permeable ground. If this cannot be achieved, raking drains should be provided to intercept
any groundwater flow beneath the counterfort drains. Particular care should be taken to
ensure that the watertightness of the ‘impermeable’ membrane at the base of the drain is
achieved in construction.
(4) Relief Drains. Where there are signs of potential seepage sources (e.g. rock
joints with signs of seepage) behind a hard surface cover, relief drains should be provided as
shown in the latest version of CEDD Standard Drawing No. C2404 : Relief Drain Details. It
is important to avoid sliding instability at the interface between the rock and the geosynthetic
material by providing proper anchorage by the use of nails or plaster. The drainage material
should be covered by an impermeable fabric with a hole cut through to insert a PVC flange
and pipe for drainage.
(5) Drainage for Hard Surface Cover. Inadequate drainage behind hard surface
cover (e.g. shotcrete) can be a contributory cause of failure on slopes with subsurface seepage
flow. Geosynthetic composite drainage material can be installed behind the hard surface
cover, together with the provision of a no-fines concrete toe (Figure 4.5) or relief drains
(Figure 4.6) in order to minimise the build-up of water pressure. This is particularly
important at locations where preferential flowpaths, such as soil pipes, erosion channels or
holes left behind by rotted tree roots or burrowing animals, exist in the ground behind the
hard surface cover.
It is important to avoid sliding failure at the interface of the soil and geosynthetic
composite drainage material by providing proper anchorage and ensuring that there are no
significant gaps at the interface which may result in erosion. The spacing of the
geosynthetic composite drainage material as shown in Figures 4.5 and 4.6 may be adjusted on
site to suit the locations of seepage and preferential flowpaths, provided that the overall area
of the surface covered by the drainage material is within about one-third of the area of the
hard surface cover.
35
It should be noted that geosynthetic composite drainage material has a limited drainage
capacity but it is suitable for relieving groundwater pressures in the soil close to the hard
surface cover. Where a larger drainage capacity is required, the use of a no-fines concrete
cover (see Item (6) below) should be considered. Installation of geosynthetic composite
drainage material may be difficult if the slope surface is irregular, e.g. at landslide scars. In
such cases, the use of no-fines concrete may be more convenient.
Where the existing provisions are deficient, new or additional weepholes should be
provided for slopes with hard surface cover and for retaining walls. Where skin walls are
constructed on existing retaining walls, the existing weepholes should be extended through
any new skin walls.
Notes: (1) Toe drain details should be similar to that of cut-off drain given in the latest version of
CEDD Standard Drawing No. C2401 : Cut-off Drain Details, except that non-woven
polypropylene geotextile filter should be placed against both side walls of the trench.
(2) If required, the compacted backfill to the drains may be replaced by concrete or shotcrete
in order to blend in with the surrounding hard surface.
Isometric View
Section A-A
Notes: (1) Details of counterfort drain should be similar to cut-off drain given in the latest version of
CEDD Standard Drawing No. C2401 : Cut-off Drain Details, except that the coarse
granular filter material is to be replaced by no-fines concrete and the non-woven
polypropylene geotextile filter should be placed against both side walls of the trench.
(2) If required, the compacted backfill to the drains may be replaced by concrete or shotcrete
in order to blend in with the surrounding hard surface.
Elevation
d
Section A-A
Figure 4.5 Drainage for Hard Surface Cover (with No-fines Concrete Toe)
38
Elevation
d
Section A-A
Figure 4.6 Drainage for Hard Surface Cover (with Relief Drains)
39
(6) No-fines Concrete Cover. No-fines concrete has good drainage capacity and
its dead weight offers some stabilisation effects. It can conveniently be built against
irregular ground profile to give a uniform surface, and if used properly in conjunction with a
geotextile filter or geosynthetic composite drainage material, it is effective in controlling
slope surface instability and erosion (Figure 4.7).
Loose material on the slope surface should be removed before placing the no-fines
concrete. Care should be exercised during placement of no-fines concrete to avoid
damaging and blocking the geotextile filter or geosynthetic composite drainage material,
which is required to prevent internal soil erosion. If necessary, an additional protective layer
of geotextile filter or sand bags may be placed over the geotextile filter or geosynthetic
composite drainage material to protect it from damage during casting of the no-fines concrete.
The no-fines concrete cover should be founded on firm ground to ensure stability.
Benching of the concrete into the slope should be considered to improve the stability,
especially on steep slopes. Galvanised steel dowel bars may also be used to tie the no-fines
concrete block and geotextile filter (or geosynthetic composite drainage material) to the slope.
40
5.1 GENERAL
Table 5.1 shows a summary of Type 3 prescriptive measures items and the associated
areas of application. The type, extent and details of application of the items should be
specified by designers to suit the actual site conditions.
Soil nails have been used in upgrading a vast number of substandard soil cut slopes in
Hong Kong with a good track record in terms of slope performance (Pun & Urciuoli, 2008).
Prescriptive soil nail layouts have been standardised based on a review of past designs. Soil
cut slopes are deemed to satisfy the required safety standards with the prescriptive soil nails
applied as upgrading works, provided that the slopes satisfy the qualifying criteria given in
Table 5.2. In the case where not all the qualifying criteria are satisfied, the prescriptive
measures may be used as preventive maintenance works.
42
Table 5.2 Qualifying Criteria for Application of Prescriptive Soil Nails to Soil Cut Slopes
Preventive
maintenance (Qualifying criteria not applicable)
works
Notes: (1) The various facility groups are given in GEO Technical Guidance Note No. 15 (GEO, 2007b).
(2) When specifying prescriptive soil nails for emergency repair works to landslides,
considerations should be given to the scale and mechanism of slope failure, the potential
consequence of further landslides, and the effectiveness of the prescriptive measures in respect
of the recovery of the emergency situation.
(3) Soil cut slopes include cuttings in a weathered rock mass in the Residual Soil, PW0/30 and/or
PW30/50 zone as defined in Geoguide 3 (GCO, 1988), with or without any overlying
colluvium. Where substandard fill (or loose or soft colluvium) is present and where the size
of the fill body (or colluvium mass) meets GEO’s slope registration criteria, the fill body (or
colluvium mass) should be dealt with using the conventional analytical approach.
(4) ‘Permanent’ refers to ‘typical wet season water level’ as described in the Geotechnical Manual
for Slopes (GCO, 1984).
(5) These qualifying criteria are also applicable to the application of prescriptive soil nails to soil
cut slopes with toe walls mentioned in Section 5.3.
43
Prescriptive soil nail design should be carried out in accordance with the following
steps:
(ii) range II for a moderate ∆FOS (0.1 < ∆FOS ≤ 0.3), and
(b) Determine the standard soil nail layout from Table 5.4,
based on the required range of ∆FOS and the maximum
effective height of slope feature, He, using the following
equation:
Figure 5.1 shows the prescriptive soil nailing to a soil cut slope. The soil nail layout,
derived from prescriptive design based on the consideration of the maximum effective height
of the slope, may be applied to the entire slope. Alternatively, the slope may be split into
different sections where there is a large variation in height along the slope, with the soil nail
layout for each section designed according to the maximum effective height for the respective
sections. This would enhance the cost-effectiveness of the prescriptive designs, especially
for large soil cut slopes.
44
Table 5.3 Stability Enhancement for Application of Prescriptive Soil Nails to Soil Cut Slopes
Consequence-to-life
Consequence-to-life
Failure consequence category
Category 1 Category 2 Category 3
Notes: (1) The conditions for designating a slope as a ‘new’ slope or as an ‘existing’ slope are stipulated
in the Geotechnical Manual for Slopes (GCO, 1984) and Works Bureau Technical Circular
No. 13/99 (Works Bureau, 1999).
(2) Reference should be made to GCO (1984), Works Bureau (1999), and GEO Technical
Guidance Note No. 15 (GEO, 2007b) for the classification of consequence-to-life and
economic consequence categories of slope features. The choice of the required range of
increase in factor of safety (∆FOS) should be based on the higher consequence of either
consequence-to-life category or economic consequence category, if the slope does not satisfy
the conditions for an ‘existing’ slope.
(3) Past instability includes both recorded and observed failures. ‘Ma’, ‘Mi’ and ‘No’ refer to
slopes with major (i.e. failure volume ≥ 50 m3, or where a fatality has occurred), minor
(i.e. failure volume < 50 m3) and no past instability respectively.
(4) ‘I’, ‘II’, and ‘III’ refer to the following ranges of ∆FOS: 0.3 < ∆FOS ≤ 0.5, 0.1 < ∆FOS ≤ 0.3
and 0 < ∆FOS ≤ 0.1, respectively. ‘I+’ is similar to ‘I’ except that Type 2 prescriptive
measures (e.g. raking drains) must be adopted as contingency provisions.
(5) Slopes that require a ∆FOS of over 0.5 are beyond the scope of application of prescriptive
measures.
45
Table 5.4 Standard Prescriptive Soil Nail Layouts for Soil Cut Slopes
Standard I II III
Soil Nail
He φr φh
(m) (mm) (mm)
Layouts N L (m) Sh (m) N L (m) Sh (m) N L (m) Sh (m)
Elevation
Notes: (1) L = Length of soil nail; H = Slope feature height; D = Depth of soil-nailed zone;
β = Gradient of terrain above slope feature.
(2) N, L, Sh, Sv and other dimensions for the soil nails are given in Table 5.4 based on the type
of soil nail layout as specified by designers.
(3) The alternative soil nail arrangement may be adopted as appropriate to suit actual site
conditions.
Soil nail heads have to be provided in conjunction with the prescriptive soil nails.
Sizes of prescriptive soil nail heads are given in Table 5.5. Typical details of soil nail heads
47
for use on slopes with vegetation cover are shown in the latest version of CEDD Standard
Drawing No. C2106/2 : Soil Nail Head Details, and Nos. C2106/4 and C2106/5 : Details of
Recessed Soil Nail Head. Typical details of soil nail heads for a gently inclined slope given
in Figure 5.6 of Geoguide 7 : Guide to Soil Nail Design and Construction (GEO, 2008) may
be used as appropriate.
For vegetated slopes steeper than 45°, a wire mesh structurally connected to the soil
nail heads should be provided. The structural connection of the wire mesh to the soil nail
heads is shown in the latest version of CEDD Standard Drawings Nos. C2511/1 and C2511/2 :
Fixing Details for Erosion Control Mat and Wire Mesh with Soil Nails. The wire mesh
should be continuous and span across soil nail heads.
Typical details of a soil nail head for use on slopes with hard surface cover are shown
in the latest version of CEDD Standard Drawing No. C2106/3 : Soil Nail Head Details for
Sprayed Concrete Slope Surface.
For soil cut slopes steeper than 65°, reinforced concrete tie beams embedded in the
slope, instead of isolated soil nail heads, should be used. Typical details of the tie beams for
use on slopes with prescriptive soil nails are shown in the latest version CEDD Standard
Drawing No. C2525 : Details of Embedded Tie Beam for Steep Cut Slopes.
5.3 PRESCRIPTIVE SOIL NAILS FOR SOIL CUT SLOPES WITH TOE WALLS
Soil nail layouts for soil cut slopes with toe walls have been standardised based on a
review of past designs. Soil cut slopes with toe walls are deemed to satisfy the required
safety standards with the prescriptive soil nails applied as upgrading works, provided that the
slopes satisfy the qualifying criteria given in Table 5.2 and the additional qualifying criteria in
Table 5.6. In the case where not all the qualifying criteria are satisfied, the prescriptive
measures may be used as preventive maintenance works.
Table 5.6 Additional Qualifying Criteria for Application of Prescriptive Soil Nails to Soil
Cut Slopes with Toe Walls as Upgrading Works
Subjects Qualifying Criteria for Application
1. The slope feature should be a soil cut slope with a concrete or masonry
retaining wall at the toe.
2. For concrete toe wall, it should be a mass concrete wall, or a reinforced
concrete wall of L-shaped, inverted L-shaped or inverted T-shaped as shown
Slope and wall type
in Figure 5.2.
3. For masonry toe wall, it should be of a condition no worse than wall
condition Class B and no worse than observed state of wall deformation
No. (2) as defined in Tables 5.7 and 5.8 respectively.
(a) Gravity Retaining Wall (b) Reinforced Concrete Retaining Wall (with or without key)
Figure 5.2 Types of Concrete Retaining Walls covered by the Scope of Application of
Prescriptive Soil Nails
49
Notes: (1) In general, the state of distress and deformation of old masonry retaining walls can be
assessed reliably by means of experience and engineering judgement. Reference may be
made to Table 5.8 and GEO Circular No. 33 (GEO, 2004) for guidance.
(2) For walls without tie members, a conservative assessment should be made, with the overall
wall condition downgraded by one class, where appropriate.
(3) If the condition of the wall is known to be deteriorating, the next wall condition class
appropriate to the worst possible wall condition anticipated should be chosen instead.
(4) Dry-packed random rubble walls of up to 5 m high should be assigned a wall condition
Class C, irrespective of the condition and deformation profile of the wall.
(5) Dry-packed random rubble walls of more than 5 m high should be assigned a wall condition
Class D, irrespective of the condition and deformation profile of the wall.
Table 5.8 Guidelines for Evaluation of the State of Masonry Retaining Wall Deformation
Observed State of Wall
Forward Movement Bulging
Deformation
Legend:
Figure 5.3 Simplified Geometry of a Slope Feature Incorporating a Soil Cut and a Mass
Concrete or Masonry Retaining Wall at Toe
51
Legend:
Figure 5.4 Simplified Geometry of a Slope Feature Incorporating a Soil Cut and a Reinforced
Concrete Retaining Wall at Toe
52
Prescriptive soil nail design should be carried out in accordance with the following
steps:
(ii) range II for a moderate ∆FOS (0.1 < ∆FOS ≤ 0.3), and
(c) Determine the total length of soil nails, Ltotal, as follows (see
Figure 5.5):
Ltotal = L + Lfree
A typical pattern of prescriptive soil nailing to a soil cut slope with toe wall is shown
in Figure 5.5. The soil nail layout, derived from prescriptive design based on the
consideration of the maximum effective height of the slope feature, may be applied to the
entire slope feature. Alternatively, the slope feature may be split into different sections, with
the soil nail layout for each section designed according to the maximum effective height for
the respective sections. This would enhance the cost-effectiveness of the prescriptive
designs.
53
Elevation
Section A-A
Notes: (1) L = Length of the portion of soil nail in material behind wall backfill; Lfree = Length of the
portion of the soil nail within the retaining wall and wall backfill; H = Slope feature
height; Hr = Height of retained ground; Tw = Average retaining wall thickness;
β = Gradient of terrain above slope feature.
(2) N, L, Sv, Sh and other dimensions for the soil nails are given in Table 5.4 based on the type
of soil nail layout specified by designers.
(3) If the height of the toe wall is less than the vertical spacing of soil nails, at least one row
of soil nails should be installed through the toe wall.
(4) If tie beams and/or tie columns are provided, the soil nails may not necessarily be
staggered.
Figure 5.5 Prescriptive Soil Nails on a Soil Cut Slope with Toe Wall
54
Guidance on the design of soil nail head and/or wall facing is given in Sections 5.2.3
and 5.4.3 respectively.
Soil nail layouts for retaining walls have been standardised based on a review of past
designs. Retaining walls are deemed to satisfy the required safety standards with the
prescriptive soil nails applied as upgrading works, provided that the retaining walls satisfy the
qualifying criteria given in Table 5.9. In the case where not all the qualifying criteria are
satisfied, the prescriptive measures may be used as preventive maintenance works.
Table 5.9 Qualifying Criteria for Application of Prescriptive Soil Nails to Concrete or
Masonry Retaining Walls as Upgrading Works
Subjects Qualifying Criteria for Application
Legend:
Figure 5.6 Simplified Geometry of a Mass Concrete or Masonry Retaining Wall Feature
56
Legend:
Prescriptive soil nail design should be carried out in accordance with the following
steps:
(d) Determine the total length of soil nails, Ltotal, as follows (see
Figure 5.5):
Ltotal = L + Lfree
A typical pattern of prescriptive soil nailing to a retaining wall is shown in Figure 5.9.
The soil nail layout, derived from prescriptive design based on the consideration of the
maximum effective height of the slope feature, may be applied to the entire slope feature.
Alternatively, the feature may be split into different sections, with the soil nail layout for each
section designed according to the maximum effective height for the respective sections.
5
Minimum Wall Thickness (m)
0
2 3 4 5 6 7 8 9 10
Maximum Effective Height of Slope Feature, He (m)
Legend:
Concrete retaining wall (‘existing’ wall standard)
Concrete retaining wall (‘new’ wall standard)
Masonry retaining wall (‘existing’ and ‘new’ wall standards)
Note: This chart is only applicable to concrete or masonry retaining walls that satisfy the qualifying
criteria listed in Table 5.9, and situations where the surcharge behind the feature does not
exceed 10 kPa.
Figure 5.8 Minimum Required Thickness of Concrete or Masonry Retaining Walls where No
Type 3 Prescriptive Measures are Needed
59
Table 5.10 Standard Prescriptive Soil Nail Layouts for Concrete or Masonry Retaining Walls
Notes: (1) The conditions for designating a retaining wall as a ‘new’ retaining wall or as an ‘existing’
retaining wall are stipulated in the Geotechnical Manual for Slopes (GCO, 1984) and Works
Bureau Technical Circular No. 13/99 (Works Bureau, 1999).
(2) He is the maximum effective height of slope feature, φr the soil nail diameter, φh the drillhole
diameter, Sh the horizontal spacing of soil nails, and L the length of the portion of soil nail in
material behind wall backfill.
(3) Total length of a soil nail, Ltotal, should include the length of the portion of soil nail within the
retaining wall and wall backfill, Lfree, and L.
(4) For He between any of the two consecutive values in the above table, the soil nail layout
corresponding to the higher He value should be adopted.
(5) N is the number of soil nails per vertical column required at the critical section, i.e. the section
with the maximum effective height, He. At other parts of the retaining wall, soil nails should
be provided at vertical and horizontal spacing similar to that at the critical section.
Alternatively, different soil nail layouts according to the He of that part of the retaining wall
may be adopted.
(6) The vertical spacing (Sv) of soil nails, as defined in Figure 5.1, should not be less than 1.5 m.
If necessary, designers may adjust N and Sh to achieve the required minimum Sv value. In so
doing, the adjusted layout should maintain the same soil nail density as that of the layout
given in this Table, with Sh ≥ 1.0 m. Where the designers opt for a specific Sv value
(e.g. 2 m) to suit site constraints or other considerations, the soil nail layout may be adjusted
by maintaining the same soil nail density as that given in this Table, with Sh ≥ 1.0 m.
(7) Soil nails should be evenly spaced over the face of the retaining wall.
(8) Steel reinforcement for soil nails shall be of Type 2 high yield deformed bars.
(9) If rock is encountered in the process of drilling such that part of the soil nails will be installed
in rock (e.g. installation through a PW50/90 zone or better, see Geoguide 3 (GCO, 1988)),
designers may exercise professional judgement to reduce the soil nail length.
(10) Designers should check the land status to establish whether the soil nails would encroach into
the adjoining land and, if so, whether this is acceptable to the land owner.
(11) Sections of a retaining wall that are lower than 2 m in height do not usually require
reinforcement by soil nails.
60
Elevation
Section A-A
Notes: (1) L = Length of the portion of soil nail in material behind the wall backfill; Lfree = Length of
the portion of the soil nail within the retaining wall and wall backfill; H = Slope feature
height; Hr = Height of retained ground; Tw = Average retaining wall thickness;
β = Gradient of terrain above slope feature.
(2) N, L, Sv, Sh and other dimensions for the soil nails are given in Table 5.10 based on the
type of soil nail layout specified by designers.
(3) If tie beams and/or tie columns are provided, the soil nails may not necessarily be
staggered.
Skin walls, tie beams or tie columns should be provided to connect soil nails, in
particular those installed in masonry retaining walls with poor wall conditions, such as
dry-packed walls or walls with signs of distress. Isolated concrete soil nail heads can be
61
used in concrete or well-constructed masonry retaining walls, because these walls generally
have better structural integrity. For well-constructed masonry retaining walls, recessed soil
nail heads are preferred in order to preserve the wall fabric and appearance. Due care needs
to be exercised in the temporary removal of the masonry blocks to facilitate construction of
recessed soil nail heads.
Typical details of a prescriptive reinforced concrete skin wall for connecting the soil
nails in a concrete or masonry retaining wall together are shown in the latest version of CEDD
Standard Drawing No. C2520 : Typical Details of Skin Wall with Soil Nails.
Typical details of the prescriptive exposed reinforced concrete tie beams and tie
columns for connecting soil nails in a concrete or masonry retaining wall together are shown
in the latest version of CEDD Standard Drawings No. C2524 : Details of Exposed Tie Beam
for Retaining Wall and No. C2523 : Details of Embedded Tie Column for Masonry Retaining
Wall.
Typical details of the exposed soil nail heads are shown in the latest version of CEDD
Standard Drawing No. C2522 : Typical Details of Soil Nail Head on Rock or Concrete Wall
Surface.
The following factors should be considered in the choice of the types of soil nail heads
and facing for use on a wall face:
Concrete skin walls are commonly used for upgrading masonry retaining walls. The
prescriptive skin wall may be considered as upgrading works for masonry retaining walls if
the qualifying criteria given in Table 5.11 are satisfied. In the case where not all of the
qualifying criteria are satisfied, the skin wall may be used as preventive maintenance works.
Table 5.11 Qualifying Criteria for Application of Prescriptive Skin Walls to Masonry
Retaining Walls as Upgrading Works
Subjects Qualifying Criteria for Application
Wall Geometry
Legend:
α Gradient of terrain in front of slope feature
β Gradient of terrain above slope feature
γ Unit weight of soil
θ Wall face angle
H Slope feature height
He Maximum effective height of slope feature, where He = H (1 + 0.35 tan β ) + q/γ
Hr Height of retained ground
Hw Height of design groundwater level behind the wall
i Wall back angle
q Design surcharge
Tw Average thickness of masonry retaining wall
ts Prescriptive skin wall thickness
Design groundwater table
The prescriptive skin wall design should be carried out in accordance with the
following steps:
Typical skin wall details are given in the latest version of CEDD Standard Drawing
No. C2521 : Typical Details of Skin Wall without Soil Nails.
Where a rockfall has occurred leading to the formation of a cavity on the slope face, it
may be necessary to construct a concrete buttress in the cavity to prevent further rockfalls.
A buttress serves two functions, viz. to retain and protect areas of weak rock and to support
the overhang. It may also be used to prevent local toppling failure of the rock face. Rock
dowels are commonly used in conjunction with concrete buttresses to stabilise and tie the
rocks together. Typical details of a concrete buttress are shown in the latest version of
CEDD Standard Drawing No. C2203 : Typical Details of Concrete Buttress Type A.
The degree of rock exposure is usually the controlling factor in determining the
accuracy of the collected data. In the event that the rock slope face is fully exposed, there
should be sufficient good quality data for rock mass discontinuity assessment. If little or no
exposure is available on the slope, knowledge of the local geology may permit extrapolation
from areas outside the slope. The key to this lies in the recognition of discontinuity patterns.
Where extrapolation is necessary, designers should determine whether the rock mass and
discontinuity pattern in the area of data collection are akin to those of the rock slope by
consideration of the local geological conditions.
Where there are doubts on this, the discontinuity data should be collected from the
covered rock slope direct. Techniques for investigating partially and fully covered rock
faces include surface cover stripping, window opening, coring and drillhole inspection.
Where stripping is used, a scanline survey may be undertaken as opposed to stripping the
whole slope. Where prescriptive measures are specified without a close inspection of all the
rock blocks to be treated, the actual rock block size and the measures needed should be
reviewed once the conditions and dimensions of the block can be examined on site more
accurately during the construction stage, particularly when the slope surface cover is removed
and/or safe access for close inspection is provided.
Designers should review the overall stability of a rock slope before concentrating on
stabilising small unstable rock blocks by means of prescriptive measures. Desk study,
collection of relevant rock joint data and assessment of the stability of an existing rock slope
through detailed visual inspection in the field should be carried out as needed.
Loosening and detachment of small rock blocks on the slope face can be prevented by
the installation of passive rock dowels, which are composed of reinforcing steel bars grouted
into holes drilled in the underlying stable rock.
Prescriptive rock dowels can be applied as upgrading works to rock cut slopes which
66
satisfy the qualifying criteria given in Table 5.12. In the case where not all the qualifying
criteria are satisfied, the rock dowels may be used as preventive maintenance works.
Standard rock dowel design has been developed as shown in Figure 5.11 for
prescriptive application. The rock block sliding angle and rock block volume should be
estimated prior to using the design table to determine the number of dowels required. By
reading off from the design table with the appropriate volume of potentially unstable rock
block, the required number of dowels can be estimated. Typical details of a rock dowel are
shown in the latest version of CEDD Standard Drawing No. C2202 : Typical Arrangement of
Rock Dowel.
Table 5.12 Qualifying Criteria for Application of Prescriptive Rock Dowels to Rock Cut
Slopes as Upgrading Works
Subjects Qualifying Criteria for Application
1. The volume of the rock block should not be greater than 5 m3 and the rock
block is not supporting any foundations of structures or surcharge.
Geometry 2. The angle between the slope at the rock face and the potential sliding surface
should not be smaller than 10°.
3. The angle of the rock block basal sliding surface should be smaller than 60°.
1. The rock type is granitic or volcanic and of decomposition grades I to III.
Engineering and geology
2. No daylighting clay-infilled or silt-infilled discontinuities.
Notes: (1) Dowel bars shall be of 32 mm in diameter (hot dip galvanised type 2 high yield steel bars to
be used).
(2) Angle of dowels to be approximately perpendicular to potential sliding surface of the rock
block.
(3) Dowel length = 3 x thickness of potentially unstable rock block, subject to a minimum length
of 3 m and a maximum length of 6 m.
(4) The layout of the rock dowels as applied to a sliding rock block/wedge shall be at least 0.3 m
from the identified periphery of the rock block/wedge in order to provide effective
stabilisation.
(5) The vertical and horizontal spacing of the rock dowels shall be from a minimum of 0.3 m to
an effective spacing evenly distributed to cover the sliding area of the block.
6. OTHER CONSIDERATIONS
6.1 GENERAL
Due consideration should be given to making the appearance of a slope feature with
prescriptive measures as natural as possible and minimising the potential visual impact to the
existing environment. Whenever possible, vegetation should be used as the primary surface
protection for slopes. General guidance on greening and landscape treatment for slope
features is given in GEO Publication No. 1/2000 : Technical Guidelines on Landscape
Treatment and Bio-engineering for Man-made Slopes and Retaining Walls (GEO, 2000a).
Guidance on selection of vegetation types (grass, shrubs, trees, creepers and/or other
herbaceous plants), species and planting techniques (e.g. hydroseeding mix) can be found in
GEO (2000a). Selection of vegetation type and species for area-specific or site-specific
applications should be made in consultation with a landscape architect, the advice of whom
could also be sought with regard to visual and ecological aspects. The party responsible for
maintenance of the slope feature and the horticulture should also be consulted as appropriate.
Further information on vegetation species suitable for slope greening can be found in the
booklet “Tree Planting and Maintenance in Hong Kong” published by the Information
Services Department (Hong Kong Government, 1991) and in GEO Technical Guidance Note
No. 20 : Update of GEO Publication 1/2000 – Technical Guidelines on Landscape Treatment
and Bio-engineering for Man-made Slopes and Retaining Walls (GEO, 2007c).
6.4 BUILDABILITY
When carrying out improvement works to slope features in the vicinity of sensitive
structures, such as old buildings with shallow foundations, buildings that have previously
been subjected to disturbance and important underground service utilities that are vulnerable
to ground movement, designers should ensure that the proposed prescriptive measures will
not induce undue disturbance or excessive ground movement to the sensitive structures.
Where deemed necessary, suitable preventive or mitigation measures should be implemented
to minimise the potential disturbance that could be caused by the prescriptive measures. The
need for condition or defects survey of the sensitive structures and setting up of an
appropriate monitoring system should also be considered.
The necessary construction control for prescriptive measures is similar to that for any
other form of slope works which are designed analytically. Adequate site supervision and
control should be provided during the implementation of the measures. General guidance on
aspects of construction control is given in Chapter 9 of the Geotechnical Manual for Slopes
(GCO, 1984). Chapter 6.2 of Geoguide 7 : Guide to Soil Nail Design and Construction
(GEO, 2008) also provides guidance on construction supervision and control of soil nailing
works.
Construction reviews should include site inspections and assessment of the geology,
slope-forming materials and groundwater conditions, together with verification of whether the
qualifying criteria for application of the prescriptive measures have been met. The reviews
should also include an evaluation of the suitability and adequacy of the specified types and
items of prescriptive measures, as well as recommendations on the necessary design
modifications to cater for the actual site and ground conditions as revealed.
between the actual conditions and that assumed during the design stage. This can be done
most effectively at the time when the prevailing slope surface cover has been removed, during
excavation for subsurface drainage works, and during drilling for raking drains or soil nails.
Where deemed necessary, geological advice may be sought from an experienced engineering
geologist on the presence of any adverse geological conditions. The importance of
engineering geological input during construction is emphasised in GEO Publication
No. 1/2007 : Engineering Geological Practice in Hong Kong (GEO, 2007d).
6.8 MAINTENANCE
Regular and proper maintenance should be provided to slope features with prescriptive
measures. General guidance on recommended good practice for maintenance works for
slope features, including the provision of safe access, is given in Geoguide 5 (GEO, 2003).
Where water-carrying services are present which are judged to have a destabilising
effect on a slope feature in the event of leakage, the guidance given in Geoguide 5
should be followed.
70
REFERENCES
Au, S.W.C. & Suen, R.Y.C. (1991a). The Role of Environmental Factors in Triggering
Failures (Special Project Report No. SPR 3/91). Geotechnical Engineering Office,
Civil Engineering Department, Hong Kong, 103 p.
Au, S.W.C. & Suen, R.Y.C. (1991b). The effect of road drainage and geometry in causing
roadside slope failures. Proceedings of the Ninth Asian Regional Conference on Soil
Mechanics and Foundation Engineering, Bangkok, vol. 1, pp. 373-376.
Brand, E.W., Hencher, S.R. & Youdan, D.G. (1983). Rock slope engineering in Hong Kong.
Proceedings of the Fifth International Rock Mechanics Congress, Melbourne, vol. 1,
pp. C17-C24. (Discussion, vol. 3, G126).
BSI (2004). Eurocode 7. Geotechnical Design. General Rules (BS EN 1997-1 : 2004).
British Standard Institution, London, 172 p.
CEDD (2006). General Specification for Civil Engineering Works. Civil Engineering and
Development Department, Hong Kong.
Dubin, B.I., Watkins, A.T. & Chang, D.C.H. (1986). Stabilisation of existing rock faces in
urban areas of Hong Kong. Proceedings of the Conference on Rock Engineering and
Excavation in an Urban Environment, Hong Kong, pp. 155-171.
ETWB (2006b). Tree Preservation (Environment, Transport and Works Bureau Technical
Circular (Works) No. 3/2006). Environment, Transport and Works Bureau,
Government Secretariat, Hong Kong, 14 p.
Furgo Scott Wilson Joint Venture (2008). Review of Sub-surface Drainage Provisions for
Recompacted Fill Slopes (GEO Report No. 225). Geotechnical Engineering Office,
Civil Engineering and Development Department, Hong Kong, 69 p.
GCO (1984). Geotechnical Manual for Slopes. (2nd Edition). Geotechnical Control Office,
Civil Engineering Services Department, Hong Kong, 295 p.
GCO (1987). Guide to Site Investigation (Geoguide 2). Geotechnical Control Office, Civil
Engineering Services Department, Hong Kong, 359 p.
GCO (1988). Guide to Rock and Soil Descriptions (Geoguide 3). Geotechnical Control
Office, Civil Engineering Department, Hong Kong, 189 p.
GEO (1993). Guide to Retaining Wall Design (Geoguide 1). (2nd Edition). Geotechnical
Engineering Office, Civil Engineering Department, Hong Kong, 258 p.
71
GEO (2003). Guide to Slope Maintenance (Geoguide 5). (3rd Edition). Geotechnical
Engineering Office, Civil Engineering Department, Hong Kong, 132 p.
GEO (2004). Guidelines for Assessment of Old Masonry Retaining Walls in Geotechnical
Studies and for Action to be Taken on Private Walls (GEO Circular No. 33).
Geotechnical Engineering Office, Civil Engineering and Development Department,
Hong Kong, 16 p.
GEO (2006). Hydraulic Design of Stepped Channels on Slopes (GEO Technical Guidance
Note No. 27). Geotechnical Engineering Office, Civil Engineering and Development
Department, Hong Kong, 16 p.
GEO (2008). Guide to Soil Nail Design and Construction (Geoguide 7). Geotechnical
Engineering Office, Civil Engineering and Development Department, Hong Kong,
97 p.
Hencher, S.R. (1985). Limitations of stereo-graphic projections for rock slope stability
analysis. Hong Kong Engineer, vol. 13, No. 7, pp. 37-41.
Ho, K.K.S., Sun, H.W. & Hui, T.H.H. (2003). Enhancing the Reliability and Robustness of
Engineered Slopes (GEO Report No. 139). Geotechnical Engineering Office, Civil
Engineering Department, Hong Kong, 63 p.
Hoek, E. & Bray, J. (1981). Rock Slope Engineering (Revised 3rd Edition). Institution of
Mining and Metallurgy, London, 358 p.
72
Hong Kong Government (1991). Tree Planting and Maintenance in Hong Kong. Hong
Kong Government, 53 p.
Hui, T.H.H., Sun, H.W. & Ho, K.K.S. (2007). Review of Slope Surface Drainage with
Reference to Landslide Studies and Current Practice (GEO Report No. 210).
Geotechnical Engineering Office, Civil Engineering and Development Department,
Hong Kong, 61 p.
Knill, J.L., Lumb, P., Mackey, S., de Mello, V.F.B., Morgenstern, N.R. & Richards, B.G.
(1999). Report of the Independent Review Panel on Fill Slopes (report reprinted as
GEO Report No. 86). Geotechnical Engineering Office, Civil Engineering Department,
Hong Kong, 36 p.
Lam, T.S.K., Sivaloganathan, K. & So, C.W. (1989). Monitoring and Maintenance of
Horizontal Drains (Technical Note No. TN 2/89). Geotechnical Control Office, Civil
Engineering Department, Hong Kong, 24 p.
Lui, B.L.S. & Shiu, Y.K. (2005). Prescriptive Soil Nail Design for Concrete and Masonry
Retaining Walls (GEO Report No. 165). Geotechnical Engineering Office, Civil
Engineering and Development Department, Hong Kong, 76 p.
Malone, A.W. (1985). Reliability of the Design of Cuttings in Hong Kong (Discussion Note
No. DN 3/85). Geotechnical Control Office, Civil Engineering Department, Hong
Kong, 20 p.
Martin, R.P., Siu, K.L. & Premchitt, J. (1995). Performance of Horizontal Drains in Hong
Kong (GEO Report No. 42). Geotechnical Engineering Office, Civil Engineering
Department, Hong Kong, 109 p.
Muhunthan, B., Shu, S., Sasiharan, N., Hattamleh, O.A., Badger, T.C., Lowell, S.M. &
Duffy, J.D. (2005). Design Guidelines for Wire Mesh/Cable Net Slope Protection.
Washington State Transportation Centre, Washington, 60 p.
Pun, W.K. & Li, A.C.O. (1993). Report on the Investigation of the 16 June 1993 Landslip at
Cheung Shan Estate, Kwai Chung (Advisory Report No. ADR 10/93). Geotechnical
Engineering Office, Civil Engineering Department, Hong Kong, 14 p.
Pun, W.K., Pang, P.L.R. & Li, K.S. (2000). Recent developments in prescriptive measures for
slope improvement works. Proceedings of the Symposium on Slope Hazards and
their Prevention, Jockey Club Research and Information Centre for Landslip
Prevention and Land Development, Hong Kong, pp. 303-308.
Pun, W.K. & Urciuoli, G. (2008). Soil nailing and subsurface drainage for slope stabilisation.
Proceedings of the Tenth International Symposium on Landslides and Engineered
Slopes, Xian, vol. 1, pp. 85-126.
Shiu, Y.K. & Chang, G.W.K. (2005). Soil Nail Head Review (GEO Report No. 175).
Geotechnical Engineering Office, Civil Engineering and Development Department,
Hong Kong, 106 p.
73
Sun, H.W. & Lam, T.T.M. (2006). Use of Standardised Debris-resisting Barriers for
Mitigation of Natural Terrain Landslide Hazards (GEO Report No. 182).
Geotechnical Engineering Office, Civil Engineering and Development Department,
Hong Kong, 92 p.
Wong, A.C.W. & Pun, W.K. (1999). Prescriptive Design of Skin Walls for Upgrading Old
Masonry Retaining Walls (Special Project Report No. SPR 3/99). Geotechnical
Engineering Office, Civil Engineering Department, Hong Kong, 36 p.
Wong, H.N. & Ho, K.K.S. (1995). General Report on Landslips on 5 November 1993 at
Man-made Features in Lantau (GEO Report No. 44). Geotechnical Engineering
Office, Civil Engineering Department, Hong Kong, 78 p. plus 1 drawing.
Wong, H.N. & Pang, L.S. (1996). Application of Prescriptive Measures to Soil Cut Slopes
(GEO Report No. 56). Geotechnical Engineering Office, Civil Engineering
Department, Hong Kong, 52 p.
Wong, H.N., Pang, L.S., Wong, A.C.W., Pun, W.K. & Yu, Y.F. (1999). Application of
Prescriptive Measures to Slopes and Retaining Walls (GEO Report No. 56).
(2nd Edition). Geotechnical Engineering Office, Civil Engineering Department, Hong
Kong, 73 p.
Works Bureau (1993). Control of Visual Impact of Slopes (Works Bureau Technical Circular
No. 25/1993). Works Bureau, Government Secretariat, Hong Kong, 4 p.
Works Bureau (1999). Geotechnical Manual for Slopes - Guidance on Interpretation and
Updating (Works Bureau Technical Circular No. 13/99). Works Bureau, Government
Secretariat, Hong Kong, 12 p.
Works Bureau (2000). Improvement to the Appearance of Slopes (Works Bureau Technical
Circular No. 17/2000). Works Bureau, Government Secretariat, Hong Kong, 3 p.
Yu, Y.F., Siu, C.K. & Pun, W.K. (2005). Guidelines on the Use of Prescriptive Measures for
Rock Cut Slopes (GEO Report No. 161). Geotechnical Engineering Office, Civil
Engineering and Development Department, Hong Kong, 31 p.
74
GLOSSARY OF SYMBOLS
75
GLOSSARY OF SYMBOLS
H Slope feature height, i.e. the maximum height of slope feature from toe to crest
Lfree Length of portion of soil nail within retaining wall and wall backfill
N Number of soil nails per vertical column required at the critical section