Gaseous Hydrogen Piping Specification
Gaseous Hydrogen Piping Specification
Gaseous Hydrogen Piping Specification
C.1 GENERAL
This specification provides guidelines for designing and installing the gaseous low-pressure (<275
psig) and high-pressure (276 to 7,000 psig) high-purity hydrogen process piping. For both low- and high-
pressure, stainless steel (303, 304, 316) tubing, piping, fittings, and components are preferred. Piping
systems should be designed and built to meet ANSI/ASME B31.3 for process piping. Specifications for
the tubing are ASTM A269 TP 304 and 316. Maximum hardness is 80 Rb.
The components specified in the Instrument Summary are primarily 1/2-in. and are configured with
either 1/2-in. female pipe ports or compression style tube fittings, depending on availability. The piping
designer/contractor may choose to modify the specified end connection when ordering the components to
facilitate installation. If the end connections are modified, then confirm with the supplier that the pressure
rating for the component with the new end connection still meets the required MAWP for the system
(7,000 psig).
C.3 FITTINGS
Parker Hannifin Triple-Lok 37 degree flared tube compression fittings having a pressure rating of
7000 psig are acceptable in sizes up to 1-in. OD. Cone-and-thread style fittings such as the BuTech M/P
fittings are also acceptable up to 1-in. OD.
The maximum allowable diameter misalignment for butt welds should be less than 0.005 in.
Pipe/tube ends should be cut and prepped so that there are no nicks, burrs, chamfers, or sharp edges and
no reduction in diameter or wall thickness. The ends should be square and perpendicular within 0.003 in.
The weld must have 100% penetration and show no points of discontinuity. The weld may have no
undercut that will render the weld wall thickness thinner than the pipe/tube nominal wall thickness. The
weld bead should be 2–5% thicker than the nominal wall thickness and should not be 10% thicker than
the nominal wall thickness. The welds should have no porosity or inclusions when inspected under
magnification and under white light. The weld bead should have uniform width and should not be more
than three times the nominal wall thickness. Discoloration of the weld should be kept to a minimum
through proper purging with argon. All socket weld joints must have a 1/16-in. gap between the pipe end
and the socket bottom (ASME B31.3, Fig. 328.5.2C).
It is recommended that 5% of each welder's joints should be 100% radiographed in accordance with
ASME B31.3. For each failed weld, two additional welds made by the same welder should be
radiographed. Radiographs will be made until no defects are found or until all welds have been examined
and repaired. All socket weld final passes will be 100% dye penetrant tested.
The performance of the welder and the weld machine should be checked periodically by performing
a sample weld, sectioning the weld lengthwise, and inspecting the weld under bright white light. Weld
performance should be checked when there are substantial changes to the welds being made: change in
pipe/tube diameter, new welder, after maintenance of welding unit, after power failure, after a change in
weld program/schedule, after any defective weld.
C.5 BENDING
Tubing may be bent where needed. The minimum mandrel bend radius must be equal to or greater
than five times the OD of the tubing.
Oxygen cleaning should be conducted in a clean, dust free area. The cleaning can be accomplished
with a range of acceptable cleaners (see CGA Pamphlet G-4.1). The detergent Blue Gold, used with hot
water (140ºF minimum) or steam, is an effective, environmentally safe method. Components that are not
cleaned by the equipment manufacturer should be disassembled, and the internal parts and surfaces
cleaned. Piping, tubing, and fittings should be soaked in the Blue Gold solution (detergent in water in a
1:20 ratio) and cleaning swabs pushed through the piping/tubing. Continue to swab the pipe/tube ID until
the swabs show no discoloration after passing through the tube. After cleaning, the parts should be rinsed
with clean warm water and allowed to dry.
The parts should be inspected after they are cleaned and dried. Under a bright white light, there
should be no indication of discoloration, oils, grease, nor indication of particulate matter (dust, fiber,
chips, etc.). Finally, inspect the parts under an ultraviolet (UV, 3660 angstrom wavelength) lamp. The
UV lamp will cause any hydrocarbon contaminants to fluoresce. Any contaminants found under either
white or UV light should be removed by recleaning and then re-inspected. Parts that have been cleaned
and that pass inspection should be tagged as “Cleaned and Inspected” and stored in 4-mil-thick
polyethylene bags and sealed until ready to use. Pipes or tubes that are cleaned and accepted should also
be tagged and the ends capped with plastic caps and stored in a secure, clean area.
C.7 TESTING
All circuits of the piping system must be tested before putting the system into operation. Testing
should consist of both a pressure retention test and a leak test. Testing should be conducted using utmost
caution. The process lines will contain in excess of 6,000 psig. Failure of a joint or component will
expose test personnel to high-pressure gas, which could result in injury. The number of testing personnel
should be kept to a minimum in the test area. A pressure test supervisor should be appointed to direct all
pressure tests and to control the access of personnel into the test areas. Maintain a minimum distance of
25 feet from the test circuit while the circuit is being pressurized and while it is under pressure. Test
personnel should continually monitor the test until it is completed and the test circuit is depressurized.
Post test warning signs around the test area to warn personnel that high-pressure pneumatic testing is
underway.
Clean dry nitrogen should be used for the test gas. Be sure that the testing is done in a ventilated
area. Nitrogen is an asphyxiant. Leakage of nitrogen into the test area may create an oxygen-deficient
atmosphere that can asphyxiate personnel in the area. Isolate or remove any components from the system
that are not rated for 1.1 times the maximum allowable working pressure of the system. Slowly
pressurize the circuit, increasing the pressure in stages. Pressurize the system to 1.1 times the MAWP
Conduct the pressure test at 110% of the design pressure of the system. The test supervisor will be
responsible for controlling access to the area during testing, which is off limits to everyone except test
personnel. A Safety Work Permit is required before testing may begin. This permit will be issued to the
test supervisor after the test procedures have been completely reviewed and understood by all test
personnel. The facility manager is the only person authorized to issue a Safety Work Permit.
Devices that are not rated to the full test pressure (relief devices) may be temporarily removed for the
test. The openings will be plugged for testing. Upon completion of the test, these devices will be
reinstalled.
C.8 LABELING
All process gas lines should be clearly marked to show the type of gas contained in the line and to
show the flow direction of the gas. Where possible, the normal operating pressure should also be
indicated on the labeling. Lab Safety Supply labels P/N OA-5339, “Hydrogen”; OA-51835, “High
Pressure”; OA-18194, “Nitrogen”; and OA-5349, “Natural Gas,” are suitable labels. All piping is color
coded and labeled.