Standard Costing PSBA Manila
Standard Costing PSBA Manila
Standard Costing PSBA Manila
lOMoARcPSD|4017738
Marley Company
Standards:
Material 3.0 feet per unit @ P4.20 per foot
Labor 2.5 hours per unit @ P7.50 per
hour
Actual:
Production 2,750 units produced during the month
Material 8,700 feet used; 9,000 feet purchased @ P4.50 per
foot Labor 7,000 direct labor hours @ P7.90 per hour
1. Refer to Marley Company. What is the material price variance (calculated at point of
purchase)? a. P2,700 U
b. P2,700 F
c. P2,610 F
d. P2,610 U
McCoy Company
McCoy Company has the following information available for October when 3,500 units were
produced (round answers to the nearest Peso).
Standards:
Material 3.5 pounds per unit @ P4.50 per pound
Labor 5.0 hours per unit @ P10.25 per hour
Actual:
Material purchased 12,300 pounds @ P4.25
Material used 11,750 pounds
17,300 direct labor hours @ P10.20 per hour
7. Refer to McCoy Company. What is the material price variance (based on quantity
purchased)? a. P3,075 U
b. P2,938 U
c. P2,938 F
d. P3,075 F
9. Refer to McCoy Company. Assume that the company computes the material price variance on
the basis of material issued to production. What is the total material variance?
a. P2,850 U
b. P5,188 U
c. P5,188 F
d. P2,850 F
Scott Manufacturing
The following March information is available for Scott Manufacturing Company when it produced
2,100 units:
Standard:
Material 2 pounds per unit @ P5.80 per pound
Labor 3 direct labor hours per unit @ P10.00 per hour
Actual:
Material 4,250 pounds purchased and used @ P5.65 per
pound Labor 6,300 direct labor hours at P9.75 per hour
Forrest Company uses a standard cost system for its production process and applies overhead based on
direct labor hours. The following information is available for August when Forrest made 4,500 units:
Standard:
DLH per unit 2.50
Variable overhead per DLH P1.75
Fixed overhead per DLH P3.10
Budgeted variable overhead P21,875
Budgeted fixed overhead P38,750
Actual:
Direct labor hours 10,000
Variable overhead P26,250
Fixed overhead P38,000
14. Refer to Forrest Company. Using the one-variance approach, what is the total overhead
variance? a. P6,062.50 U
b. P3,625.00 U
c. P9,687.50 U
d. P6,562.50 U
15. Refer to Forrest Company. Using the two-variance approach, what is the controllable
variance? a. P5,812.50 U
b. P5,812.50 F
c. P4,375.00 U
d. P4,375.00 F
16. Refer to Forrest Company. Using the two-variance approach, what is the uncontrollably variance?
a. P3,125.00 F
b. P3,875.00 U
c. P3,875.00 F
d. P6,062.50 U
17. Refer to Forrest Company. Using the three-variance approach, what is the spending
variance? a. P4,375 U
b. P3,625 F
c. P8,000 U
d. P15,750 U
18. Refer to Forrest Company. Using the three-variance approach, what is the efficiency variance?
a. P9,937.50 F
b. P2,187.50 F
c. P2,187.50 U
d. P2,937.50 F
lOMoARcPSD|4017738
19. Refer to Forrest Company. Using the three-variance approach, what is the volume
variance? a. P3,125.00 F
b. P3,875.00 F
c. P3,875.00 U
d. P6,062.50 U
20. Refer to Forrest Company. Using the four-variance approach, what is the variable overhead
spending variance?
a. P4,375.00 U
b. P4,375.00 F
c. P8,750.00 U
d. P6,562.50 U
21. Refer to Forrest Company. Using the four-variance approach, what is the variable overhead
efficiency variance?
a. P2,187.50 U
b. P9,937.50 F
c. P2,187.50 F
d. P2,937.50 F
22. Refer to Forrest Company. Using the four-variance approach, what is the fixed overhead
spending variance?
a. P7,000 U
b. P3,125 F
c. P750 U
d. P750 F
23. Refer to Forrest Company. Using the four-variance approach, what is the volume
variance? a. P3,125 F
b. P3,875 F
c. P6,063 U
d. P3,875 U
Rainbow Company
Rainbow Company uses a standard cost system for its production process. Rainbow Company applies
overhead based on direct labor hours. The following information is available for July:
Standard:
Direct labor hours per unit 2.20
Variable overhead per hour P2.50
Fixed overhead per hour
(based on 11,990 DLHs) P3.00
Actual:
Units produced 4,400
Direct labor hours 8,800
Variable overhead P29,950
Fixed overhead P42,300
24. Refer to Rainbow Company Using the four-variance approach, what is the variable overhead
spending variance?
a. P7,950 U
b. P25 F
c. P7,975 U
d. P10,590 U
25. Refer to Rainbow Company Using the four-variance approach, what is the variable
overhead efficiency variance?
a. P9,570 F
b. P9,570 U
c. P2,200 F
d. P2,200 U
26. Refer to Rainbow Company Using the four-variance approach, what is the fixed overhead
spending variance?
a. P15,900 U
b. P6,330 U
c. P6,930 U
d. P935 F
27. Refer to Rainbow Company Using the four-variance approach, what is the volume
variance? a. P6,930 U
b. P13,260 U
C. P0
d. P2,640 F
28. Refer to Rainbow Company Using the three-variance approach, what is the spending
variance? a. P23,850 U
b. P23,850 F
c. P14,280 F
d. P14,280 U
29. Refer to Rainbow Company Using the three-variance approach, what is the efficiency
variance? a. P11,770 F
b. P2,200 F
c. P7,975 U
d. P5,775 U
30. Refer to Rainbow Company Using the three-variance approach, what is the volume
variance? a. P13,260 U
b. P2,640 F
c. P6,930 U
D. P0
31. Refer to Rainbow Company Using the two-variance approach, what is the controllable
variance? a. P21,650 U
b. P16,480 U
c. P5,775 U
d. P12,080 U
32. Refer to Rainbow Company Using the two-variance approach, what is the noncontrollable
variance? a. P26,040 F
b. P0
c. P6,930 U
d. P13,260 U
33. Refer to Rainbow Company Using the one-variance approach, what is the total
variance? a. P19,010 U
b. P6,305 U
c. P12,705 U
d. P4,730 U
34. Actual fixed overhead is P33,300 (12,000 machine hours) and fixed overhead was estimated at
P34,000 when the predetermined rate of P3.00 per machine hour was set. If 11,500 standard hours
were allowed for actual production, applied fixed overhead is
a. P33,300.
b. P34,000.
c. P34,500.
d. not determinable without knowing the actual number of units produced.
35. One unit requires 2 direct labor hours to produce. Standard variable overhead per unit is P1.25 and
standard fixed overhead per unit is P1.75. If 330 units were produced this month, what total amount
of overhead is applied to the units produced?
a. P990
b. P1,980
c. P660
d. cannot be determined without knowing the actual hours worked
36. Western Company uses a standard cost accounting system. The following overhead costs
and production data are available for August:
Using the two-way analysis of overhead variances, what is the controllable variance for
January? a. P3,000 F
b. P5,000 F
c. P9,000 F
d. P10,500 U
Actual OH P15,000
Fixed OH expenses, actual P7,200
Fixed OH expenses, budgeted P7,000
Actual hours 3,500
Standard hours 3,800
Variable OH rate per DLH P2.50
Assuming that Fitzgerald uses a three-way analysis of overhead variances, what is the overhead
spending variance?
a. P750 F
b. P750 U
c. P950 F
d. P1,500 U
39. Hagman Company uses a two-way analysis of overhead variances. Selected data for the
April production activity are as follows:
Assuming that budgeted fixed overhead costs are equal to actual fixed costs, the controllable variance
for April is
a. P2,000 F.
b. P4,000 U.
c. P4,000 F.
d. P6,000 F.
40. Oxygen Company uses a standard cost system. Overhead cost information for October is as
During April, 85,000 units were scheduled for production, but only 80,000 units were actually
produced. The following data relate to April:
41. Refer to Uniform Company. The variable overhead spending variance for April
was a. P15,000 U.
b. P23,000 U.
c. P38,000 F.
d. P38,000 U.
42. Refer to Uniform Company. The variable overhead efficiency variance for April
was a. P15,000 U.
b. P23,000 U.
c. P38,000 F.
d. P38,000 U.
43. Refer to Uniform Company. The fixed overhead spending variance for April
was a. P40,000 U.
b. P40,000 F.
c. P60,000 F.
d. P60,000 U.
44. Refer to Uniform Company. The fixed overhead volume variance for April
was a. P60,000 U.
b. P60,000 F.
c. P100,000 F.
d. P100,000 U.
Ultra Shine Company
Ultra Shine Company manufactures a cleaning solvent. The company employs both skilled and
unskilled workers. To produce one 55-gallon drum of solvent requires Materials A and B as well as
skilled labor and unskilled labor. The standard and actual material and labor information is presented
below:
Standard:
Material A: 30.25 gallons @ P1.25 per gallon
Material B: 24.75 gallons @ P2.00 per gallon
Actual:
Material A: 10,716 gallons purchased and used @ P1.50 per gallon
Material B: 17,484 gallons purchased and used @ P1.90 per gallon
45. Refer to Ultra Shine Company. What is the total material price
variance? a. P877 F
b. P877 U
c. P931 U
d. P931 F
46. Refer to Ultra Shine Company. What is the total material mix
variance? a. P3,596 F
b. P3,596 U
c. P4,864 F
d. P4,864 U
47. Refer to Ultra Shine Company. What is the total material yield
variance? a. P1,111 U
b. P1,111 F
c. P2,670 U
d. P2,670 F
48. Refer to Ultra Shine Company. What is the labor rate variance?
a. P0
b. P1,083 U
c. P2,583 U
d. P1,083 F
49. Refer to Ultra Shine Company. What is the labor mix
variance? a. P1,083 U
b. P2,588 U
c. P1,083 F
d. P2,588 F
50. Refer to Ultra Shine Company. What is the labor yield
variance? a. P2,583 U
b. P2,583 F
c. P1,138 F
d. P1,138 U