2019 Saes W 016
2019 Saes W 016
2019 Saes W 016
Contents
1 Scope ................................................................ 2
2 Conflicts and Deviations ................................... 3
3 References........................................................ 3
4 General ............................................................. 5
5 High Temperature Applications ......................... 5
6 Corrosive Services ............................................ 6
7 Special Requirements for 22 Cr Duplex
and 25 Cr Duplex Stainless Steels .................. 11
8 Special Requirements
for Titanium and its Alloys ............................... 13
Revision Summary................................................. 16
1 Scope
1.1 This standard specifies the requirements for welding and testing of special
corrosion-resistant materials of pipelines, on-plot pipes, pressure vessels and
heat exchangers. This is defined as stainless steel, nickel-based alloys and
titanium or titanium alloys in severe corrosion service and high temperature
service, as defined below.
1.1.4 Strip lining and weld overlay applications are not included.
Commentary Note:
1.1.6 These requirements are in addition to the requirements of ASME SEC IX.
1.2 This entire standard may be attached to and made part of purchase orders.
Any conflicts between this document and other applicable Mandatory Saudi Aramco
Engineering Requirements (MSAERs) shall be addressed to the EK&RD Coordinator.
Any deviation from the requirements herein shall follow internal company procedure
SAEP-302.
3 References
The selection of material and equipment, and the design, construction, maintenance, and
repair of equipment and facilities covered by this standard shall comply with the latest
edition of the references listed below, unless otherwise noted.
ASTM International
ASTM A833 Indentation Hardness of Metallic Materials by
Comparison Hardness Testers
ASTM A923 Standard Test Methods for Detecting Detrimental
Intermetallic Phase in Duplex Austenitic /
Ferritic Stainless Steels
ASTM E140 Hardness Conversion Tables for Metals
ASTM E562 Standard Test Method for Determining Volume
Fraction by Systematic Manual Point Count
4 General
4.1 All welding procedures shall be qualified in accordance with ASME SEC IX
plus the additional requirements of SAES-W-010, SAES-W-011, SAES-W-012,
as applicable, and this standard.
4.2 Ferrite measurement for stainless steel welds shall be performed using point
count technique as per ASTM E562 for welding procedure qualification.
AWS A4.2 shall be used for verification in production welding.
4.3 Abrasive tooling and/or grinding disks shall not have been used on either carbon
steel or any other grade of stainless steel material. The selection of grinding and
cleaning tools shall be appropriate for the base material, e.g., carbon steel
brushes shall not be used on stainless steel material.
Commentary Note:
During welding or heat treatment of stainless steel and duplex stainless steel, if
zinc is present in the weld area, Liquid Metal Embrittlement (LME) can lead to
cracking.
4.4 All filler materials shall be individually and clearly stamped, flagged or
stenciled to ensure traceability and correct usage on site. Precautions shall be
taken throughout storage, conditioning and fabrication to minimize
contamination of corrosion-resistant alloy (CRA) consumables resulting from
direct contact with carbon and low alloy steels.
4.5 Handling & storage of base materials: All necessary precautions shall be taken
throughout fabrication to minimize contamination of CRA materials resulting
from direct contact with carbon steels, exposure to ferrous dust, swarf or other
debris and from residual deposits on or near fusion faces during welding.
Supports, rollers and other pipe handling equipment shall be of compatible
material or shall be suitably lined to prevent damage or contamination.
5.1 The welding procedure qualification for austenitic stainless steels, except type
310 and 6% Mo super-austenitic stainless steel, shall include a determination of
the Ferrite Number in the as-welded condition. The Ferrite Number shall be
between 3 and 10 FN.
5.2 For production welds, the ferrite content shall be checked in the as-welded
condition. The Ferrite Number shall be between 3 and 10 FN.
5.3 Any welding on high carbon grades of austenitic stainless steel material
(e.g., 304H or HK40) after service times exceeding 1 year shall require a
re-solution heat treatment prior to welding.
5.4 Welds for high temperature service above 400C with stabilized grades shall be
subject to thermal stabilizing post weld heat treatment. This shall also apply for
cold worked parts in such grades and applications.
Commentary Note:
6 Corrosive Services
6.1 The GTAW process shall be used for the following applications:
1) The root pass of single-sided groove welds without backing.
2) For all passes for piping, tubes, and nozzles of 2 inch nominal diameter or
less.
3) For all passes for wall thickness less than 9.5 mm for duplex stainless steel
or for wall thickness less than 6.5 mm for other Corrosion Resistant Alloys
(CRA).
4) For all passes and wall thicknesses for Titanium and its alloys.
6.2 All manual GTAW shall use a high frequency start and post-purge gas flow for
the torch. A remote current control (pedal or torch mounted) is required. Pre-set
power source current start/rise and decay/stop controls triggered by a foot switch
or torch mounted control is an acceptable alternative for the remote control.
6.3 For all GTAW welding, filler metal shall be added. Autogenous welding of any
pass is not permitted.
The filler metal shall be of matching grade and composition as the base metal
with the exception of alloys listed Table 1. The approval of alternate
consumables shall be through the WPS review process.
6.4 Preheating, if used to remove moisture, shall be carried out with lamps,
resistance heaters, or induction heating equipment or dry air. The maximum
interpass temperature during welding of austenitic stainless steel and nickel
alloy materials shall not exceed 175°C.
6.5 Purging for welding of stainless steels and Ni-based alloys shall be done as
follows:
6.5.1 An inert backing gas shall be used for GTAW or GMAW on single-sided
groove welds.
6.5.2 During pre-weld purging, the joint area shall be adequately sealed at all
openings to maintain the purge and prevent any air ingress.
6.5.3 The purge times for the backing gas shall be calculated to give a theoretical
volume change of 6 times the enclosed pipe volume. Table 2 is shown
for information and can be used for the standard conditions as listed in
the table. Extra purging time is necessary if the purge gas inlet and
outlet (vent) cannot be placed at opposite ends of the enclosed volume in
order to insure complete displacement of the original air.
Commentary Note:
During welding, the purging flow rate shall be appropriate to ensure that
there is no positive pressure on the root and hence absence of any root
suck back.
6.5.5 The purge shall achieve actual oxygen levels inside or exiting the joint
(via the vent) no greater than 0.05% prior to and during welding, as
measured using an oxygen analyzer. The actual oxygen levels achieved
in production shall be measured periodically (i.e., on a random basis for
the number of joints to be performed). Analyzers shall be used for all
joints if excessive internal oxidation is observed on any joints based on
the visual appearance of the oxide tint. Analyzers shall be calibrated as
per manufacturer recommendations and copy of calibration certificate
shall be available for reference/verification by inspector, if required.
6.5.6 During pre-weld purging, the joint area shall be adequately sealed at all
openings to maintain the purge and prevent any air ingress.
6.5.7 If purge dams are to be used but cannot be retrieved after welding, then
proprietary dissolvable (water soluble) dams shall be used.
Commentary Note:
The contractor shall ensure that in that case, on dissolution, the purge
dams do not increase chloride content in water to or beyond the
Saudi Aramco: Company General Use
Page 7 of 18
©Saudi Aramco 2019. All rights reserved.
Document Responsibility: Welding Standards Committee SAES-W-016
Issue Date: 20 February 2019
Next Planned Update: 20 February 2022 Welding of Special Corrosion-resistant Materials
maximum limit specified for hydrotest. The contractor shall also ensure
that any residue left behind does not cause fouling of any valves in the
piping system during or after hydrotest.
6.5.9 Purging shall be carried out for partial thickness repairs in stainless steel,
when the remaining ligament after the removal of the defect is less than
10 mm. Root or through-thickness repairs of stainless steel groove welds
in the field are not permitted, unless purging is carried out.
6.5.10 The entire piping spool/circuit shall be purged with backing gas for root
or through-thickness repairs of stainless steel groove welds in the field.
Commentary Note:
For GTAW, the root gaps must be specified and maintained during welding at
equal to or larger than the root pass filler wire diameter.
Maximum internal misalignment between pipe or tube sections shall not exceed
1.6 mm.
6.7 Tacking
Either root tacks or bridge tacks are permitted. Root tacks shall be welded in
accordance with the approved WPS for welding the joint using qualified
welders. Root tacks must be either feathered or ground out prior to making the
root pass. The requirements for purging in paragraph 6.5 shall also apply for
any tacks that are incorporated in the weld root (root tacks).
6.8 Technique
Either high frequency (HF) or high voltage (HV) arc initiation shall be used.
The continuous feed technique shall be used for the root pass (i.e., the filler wire
is positioned between the root faces and fed continuously into the weld pool).
Commentary Note:
The welder must avoid narrow root gaps and improper travel speeds in order to
achieve the proper root bead deposit chemistry.
Stringer beads shall be used. Minor arc oscillation to ensure sidewall fusion is
permitted.
Whenever the welder stops welding, the welding current shall be gradually
decreased by use of the remote current control. The torch shall be held in position
close to the weld pool until the gas shielding post-purge flow is completed.
6.9 Inspection
6.9.1.1 All weld surfaces and heat affected zones must be free of dark
colored and heavy 'sugary' oxidization, pinholes, cracks,
crevices, undercut, lack of penetration, and incomplete fusion.
7.1 Qualification of welding procedures for duplex stainless steel material shall
include the following supplementary essential variables and testing requirements:
7.1.1 The base metal UNS number shall be considered an essential variable.
7.1.2 The size of the filler wire used in welding the root pass of the test
coupon is considered an essential variable.
7.1.3 GTAW process must be used for the root and cold passes if the wall
thickness is equal to or greater than 9.5 mm. Heat input for second pass
or cold pass should be approximately 75% to that of root pass to prevent
secondary austenite formation.
7.1.5 Ferrite content of the weld metal shall be measured, unless the weld metal
is nickel-based. The ferrite range must be within 35 to 60% as measured
by metallographic methods using a point count technique in accordance
with ASTM E562. Minimum ferrite content shall be 50% for services that
have potential for chloride stress cracking. The fabricator shall establish a
correlation between the percent ferrite as measured by metallographic
methods and the Ferrite Number (FN) as measured using AWS A4.2.
Ferrite measurements using both methods shall be recorded on the PQR.
7.1.7 Charpy impact testing shall be conducted on the weld metal and
HAZ at a test temperature of -20°C, or the minimum design temperature,
whichever is less. The minimum absorbed energy shall be 34/27 J
(25/20 ft-lb) for full size (10 x 10 mm) specimens. All of the
ASME SEC IX supplementary essential variables for impact tested
applications shall apply plus the special tolerances and restrictions on the
heat input as listed below.
7.1.11 The requirements for purging in paragraph 6.5 shall be applicable, unless
specifically modified below.
7.2.3 For GTAW welding of duplex stainless steel, hydrogen free shielding
and purging gas (e.g., argon) shall be used to avoid possible cracking and
embrittlement of the weld. The purge shall achieve actual oxygen levels
inside or exiting the joint (via the vent) no greater than 0.05% prior to
and during welding, as measured using an oxygen analyzer. The actual
oxygen levels achieved in production shall be measured periodically
(i.e., on a random basis for the number of joints to be performed).
Analyzers shall be used for all joints if excessive internal oxidation is
observed on any joints based on the visual appearance of the oxide tint.
Care to prevent contamination of the titanium by air must be exercised at all stages of
welding. Auxiliary gas or trailing gas shield shall be used to protect the weld.
Commentary Note:
Molten titanium weld metal must be totally protected from contamination by air. Also, hot
heat-affected zones and root side of titanium welds must be shielded until temperatures
drop below 800°F (427°C).
Similarly, hot titanium reacts with and is embrittled by most materials, including
organic and inorganic compounds and some metals. And in the case of welding
titanium to other refractory/reactive metals, detrimental alloy compositions or
compounds may form. Hence, the parts to be welded must be meticulously cleaned of
mill scale, oil and grease from machining operations, dust, dirt, moisture, and other
potential contaminants.
8.1 Qualification of welding procedures for titanium and its alloys shall include the
following supplementary essential variables and testing requirements:
8.1.1 The base metal UNS number shall be considered an essential variable.
8.1.2 The size of the filler wire used in welding of the test coupon is
considered an essential variable.
8.1.3 The trailing shield used for the qualification shall be the same as that
proposed to be used for the production.
8.1.5 Filler wire brand and type shall be considered an essential variable.
8.2.2 The welding area shall be kept clean and protected from dirt, smoke, and
other airborne contaminants from welding, cutting, and grinding
operations. The working area shall be protected from wind and drafts
that can interfere with inert gas shielding. The humidity in the welding
area shall be monitored and all equipment, fixtures, etc., shall be free
from moisture.
8.2.3 When tack welds are used, the same cleaning and shielding requirements
used for all titanium welds shall be employed, including the use of
trailing shielding and purging.
8.2.4 Before starting welding, the torch, trailing shield, and purging gas hoses
and devices shall be pre-purged to minimize potential contamination at
the start of welding. Welding equipment and the GTA torch shall be
equipped with upslope, downslope control for current, pre-purge and
post-purge controls for shielding gas.
Saudi Aramco: Company General Use
Page 14 of 18
©Saudi Aramco 2019. All rights reserved.
Document Responsibility: Welding Standards Committee SAES-W-016
Issue Date: 20 February 2019
Next Planned Update: 20 February 2022 Welding of Special Corrosion-resistant Materials
8.2.5 Preheating, if used to remove moisture shall be carried out with lamps,
resistance heaters, or induction heating equipment; wiping with a volatile
solvent like acetone may also be used to dry material.
8.2.7 For GTA welding of Titanium and its alloys, only argon and helium or a
mixture of helium and argon is permitted for shielding, trailing and
purging. The purity of the gas shall be at least 99.995% and the dew
point of the gas shall be at least -60°F [-50°C].
8.2.8 The purge shall achieve actual oxygen levels inside or exiting the joint
(via the vent) no greater than 0.05% prior to and during welding, as
measured using an oxygen analyzer. Analyzers shall be used for all
joints if excessive internal oxidation is observed on any joints based on
the visual appearance of the oxide tint.
Commentary Note:
Light and dark straw colors indicate light contamination that is normally
acceptable. Dark blue indicates heavier contamination that may be
acceptable depending on the service conditions. Light blue, grey and
white indicate such a high level of contamination that they are regarded
as unacceptable.
8.2.11 Repairs are not permitted, weld shall be cut out and rewelded in the case
of any defects.
Revision Summary
10 November 2014 Major revision to revising requirements for duplex stainless steel welding and added
requirements for qualification. Added requirements for Titanium welding qualifications and
production welding.
1 January 2018 Editorial revision to modify and/or delete paragraph 6.1 (4).
20 February 2019 Major revision. Clarify the welding purging requirements for stainless steel materials to
prevent the recurrence of MIC filature in SA capital projects in line with SAER-8166.
Clarity the RT and UT procedure and acceptance criteria similar to the mother welding
standards SAES-W-011 and in line with ASME requirements. Maintain the welding
standards up to date aligned with the international requirements/ practices and easily
interpreted.
Summary of Changes
Table 2 - Backing Gas Purge Times for Stainless Steel and Nickel alloy Pipe
Nominal Pipe Size Purge Time (minimum)
2 inch NS 0.5 minutes
4 2 minutes
6 4 minutes
8 7 minutes
10 10 minutes
12 15 minutes
16 25 minutes
Assumes use of argon gas at a flow rate of 20 CFH (9 lpm).
Listed times are for each 300 mm of pipe length to be purged (multiply
by actual length). Use the values for 300 mm for any shorter length.
Saudi Aramco: Company General Use
Page 18 of 18
©Saudi Aramco 2019. All rights reserved.