Estimate Chandpur Khad
Estimate Chandpur Khad
Estimate Chandpur Khad
to
Sr. MORD Rate
Description Unit Quantity Amount
No. Specificatio (Rs.)
(Rs.)
ns
Unit = 1 No
a) Material
b) Labour
For fabrication
Unit = cum
Taking output = 191 cum (450 tonnes)
a) Labour
Mate day 0.840 291.67 245.00
Mazdoor working with HMP, mechanical broom, paver, day 16.000 291.67 4666.72
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 291.67 1458.35
b) Machinery 0.00
Batch mix HMP @ 75 tonne per hour hour 6.000 16896.00 101376.00
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 4300.00 25800.00
cum per hour
Generator 250 KVA hour 6.000 1125.00 6750.00
Front end loader 1 cum bucket capacity hour 6.000 1281.00 7686.00
Tipper 10 tonne capacity tonne.km 450 x L 3.54x30 47790.00
Add 10 per cent of cost of carriage to cover cost of loading 4779.00
and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 1319.00 5144.10
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 2417.00 9426.30
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 741.00 2889.90
roller.
c) Material
i) Bitumen VG-30 @ 5.0 per cent of weight of mix tonne 22.500 31391.82 706315.95
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
Grading - II-13 mm (Nominal Size)
13.2 - 10 mm30 per cent cum 85.500 755.45 64590.98
10 - 5 mm 25 per cent cum 71.250 755.45 53825.81
5 mm and below43 per cent cum 122.550 730.45 89516.65
Filler @ 2 per cent of weight of aggregates. tonne 8.620 6222.96 53641.92
5.8 (ii) for Grading-II(10 mm nominal size)
d) Overhead &CP charges @15% on (a+b+c) 1185902.673 177885.40
e) Labour Cess @ 1% on (a+b+c+d) 1363788.074 13637.88
f) GST @ 12% on (a+b+c+d), except bitumen 657472.124 78896.65
Cost for 191 cum = a+b+c+d+e 1456322.61
Rate per cum = (a+b+c+d+e+f)/191 (For Grading-II) 7624.73
say 7625.00
Unit = cum
Taking ouput = 3 m x 1.5 m x 1.25 m = 5.63 cum
a) Material
Stone boulder (25 kg minimum) cum 5.63 565.13 3181.68
Stone spalls cum 1.13 565.13 638.60
GI wires 4 mm dia @ 32 kg/10 sqm kg 64.00 82.00 5248.00
b) Labour
Mate day 0.18 291.67 52.50
Mazdoor (Skilled) day 1.50 291.67 437.51
Mazdoor (Unskilled) day 3.00 291.67 875.01
c) Add for labour for weaving the wire crates @ 2 5,248.00 2.00% 104.96
per cent of cost of GI wire
10,538.25
D) Add 15.0% (Over Head @5.0% +10% Rs. 10538.25 15.00% 1580.74
Contractor Profit) on ( a+b+c)
Grand Total 12118.99
e) Add 1% Labour Cess on (a+b+c+d) 121.19
f) Add 12% Labour Cess on (a+b+c+d) 1454.28
13694.46
Rate per cum = (a+b+c+d+e)/5.63 2432.40
Unit = sqm
Taking output = 112.5 sqm
Concrete M30 grade for block, 400 x (0.450 x 0.300 x cum 8.10
Concrete M30 for edge block, 2 x 50 x (0.300 x 0.300 cum 1.35
TOTAL cum 9.45
a) Labour
Labour for Manufacturing the Cement Concrete
(i) Mate day 1.70 262.50 446.25
(ii) Mazdoor (Unskilled) day 41.00 262.50 10,762.50
(iii) Mason (2nd class) day 6.00 311.50 1,869.00
(iv) Bhisti day 1.40 262.50 367.50
b) Machinery
Concrete mixer 0.28 / 0.4 cum hour 6.00 350.00 2,100.00
Plate vibrator hour 12.00 60.00 720.00
Water tanker 6 kl capacity hour 2.00 500.00 1,000.00
c) Material
(i) Coarse aggregates (9.450 x 0.84) cum 7.94 804.24 6,385.67
(ii) Sand (9.450 x 0.42) cum 3.97 688.00 2,731.36
(iii) Cement t 3.80 7,231.56 27,479.93
(iv) Sand as per Table 1500.5 cum 1.725 688.00 1,186.80
Bed = 60*0.025 = 1.5 cum
Joints = 1.5*0.15 = 0.225 cum
(v) Cost of water kl 6.00 109.08 654.48
55,703.48
D Add 15.0% (Over Head @5.0% +10% Rs. 55703.48 15.00% 8355.52
Contractor Profit) on ( a+b+c)
Grand Total 64059.01
e Add 1% Labour Cess on 640.59
(a+b+c+d)
64699.60
Rate per Sqm = (a+b+c+d+e)/112.50 575.10
Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam
specification including premixing the material with water at OMC in mechanical mixer (Pug Mill),
carriage of mixed material by tipper to site, laying in uniform layers in sub-base/base course on a
well prepared sub-base and compacting with smooth wheel roller of 80 to 100kN weight to
achieve the desired density including lighting, barricading and maintenance of diversion, etc as
per Tables 400.11 & 400.12 and Technical Specification Clause 406.
Unit = cum
Taking output = 102.5 cum (225 t)
a) Labour
Mate day 0.52 291.67 151.67
Mazdoor day 10.00 291.67 2,916.70
(Unskilled)
Mazdoor (Skilled) day 3.00 291.67 875.01
b) Machinery
Batch mix HMP 40-60 THP @ 40 t per hour hour 6.00 16,896.00 101,376.00
Hydraulic broom actual
@ output
1250 sqm per hour hour 1.10 528.00 580.80
Air compressor 210 cfm hour 1.10 465.00 511.50
Paver finisher hour 6.00 4,300.00 25,800.00
Generator 125 hour 6.00 1,125.00 6,750.00
KVA Front end loader 1 cum bucket capacity hour 6.00 1,281.00 7,686.00
Tipper 5.5 cum, 10 t capacity hour 6.21 513.00 3,185.73
Three wheel 80-100 kN static roller for intial hour 12.00 741.00 8,892.00
break down
Vibratory roller rolling,
80-100final andintermediate
kN for finishing rolling
rolling hour 6.00 2,417.00 14,502.00
c) Material
i) Bitumen @ 3.3 per cent of mix (VG-30) t 7.425 31,391.82 233,084.26
(Weight of mix = 102.5 x 2.2 = 225 t)
ii) Aggregate
Total weight of mix = 225 t
Weight of bitumen = 7.425 t
Weight of aggregate = 225 – 7.425 = 217.575 t
Taking density of aggregate = 1.5 t/cum
(19 mm
nominal
size)
25 -10 mm - 40 per cent cum 58.02 755.45 43,831.21
10– 5 mm - 40 per cent cum 58.02 755.45 43,831.21
5 mm and below - 20 per cum 29.01 730.45 21,190.35
d) Overheads &CP @ 15.0% on (a+b+c) 77,274.67
e) Labour Cess @ 1% on (a+b+c+d) 5,924.39
f) GST @ 12% on (a+b+c+d) 71,092.69
Cost of 102.5 cum = a+b+c+d+e+f 669,456.20
Rate per cum = a+b+c+d+e+f/102.5 6,531.28
Say Rs. 6,531.30
Unit = cum
Taking output = 102.5 cum (225 t)
a) Labour
Mate day 0.52 291.67 151.67
Mazdoor day 10.00 291.67 2,916.70
(Unskilled)
Mazdoor (Skilled) day 3.00 291.67 875.01
b) Machinery
Cold Mix Plant hour 6.00 350.00 2,100.00
Hydraulic broom @ 1250 sqm per hour 1.10 528.00 580.80
Air compressor 210 cfm hour 1.10 465.00 511.50
Paver finisher hour 6.00 4,300.00 25,800.00
Generator 125 KVA hour 6.00 1,125.00 6,750.00
Front end loader 1 cum bucket hour 6.00 1,281.00 7,686.00
Tipper 5.5 cum, 10 t capacity hour 6.21 513.00 3,185.73
Three wheel 80-100 kN static roller for intial hour 12.00 741.00 8,892.00
Vibratory roller 80-100 kN for intermediate rolling hour 6.00 2,417.00 14,502.00
c) Material
i) Bitumen @ 5 per cent of mix (Cold mix) t 11.250 45,285.22 509,458.73
ii) Aggregate
Total weight of mix = 225 t
Weight of bitumen = 7.425 t
Weight of aggregate = 225 – 7.425 = 217.575 t
Taking density of aggregate = 1.5 t/cum
Volume of aggregate = 145.05 cum
(19 mm
nominal
size)
25 -10 mm - 40 per cent cum 58.02 755.45 43,831.21
10– 5 mm - 40 per cent cum 58.02 755.45 43,831.21
5 mm and below - 20 per cum 29.01 730.45 21,190.35
d) Overheads &CP @ 12.5% on (a+b+c) 86,532.86
e) Labour Cess @ 1% on (a+b+c+d) 7,787.96
f) GST @ 12% on (a+b+c+d) 93,455.49
Cost of 102.5 cum = a+b+c+d+e 880,039.22
Rate per cum = a+b+c+d+e/102.5 8,585.75
Say Rs. 8,585.75
52200.9 86117372
-1859490
Analysis of Rates
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.01 291.67 2.92
Mazdoor (Unskilled) day 0.25 291.67 72.92
b) Machinery
Tractor with ripper attachment @ 60 hour 0.25 355.00 88.75
Front end loader 1 cum bucket hour 0.30 787.00 236.10
Tipper 5.5 cum capacity, 4 trips per hour 0.68 275.00 187.00
Add 40% on Mechinery 204.74
c) Overheads &CP @ 15% on (a+b) 88.15
d) Labour Cess @ 1% on (a+b+c) 8.81
e) GST @ 12% on (a+b+c) 105.67
Cost for 100 sqm = a+b+c+d+e 995.05
Rate per sqm = (a+b+c+d+e)/100 9.95
Unit = cum
Taking output = 600 cum
a) Labour
Mate day 0.24 291.67 70.00
Mazdoor (Unskilled) day 6.00 291.67 1,750.02
b) Machinery
Tractor with ripper hour 10.00 355.00 3,550.00
Motor grader for grading hour 6.00 2,230.00 13,380.00
Water tanker 6 kl capacity hour 4.00 295.00 1,180.00
Three wheel 80-100 kN Static hour 8.60 420.00 3,612.00
Add 40% on Mechinery 8,688.80
c) Material
Water kl 24.00 158.40 3,801.60
d) Overheads &CP @ 12.5% on 4,504.05
e) (a+b)
Labour Cess @ 1% on (a+b+c) 405.36
f) GST @ 12% on (a+b+c) 4,864.38
Cost for 600 cum = a+b+c+d+e+f 45,806.21
Rate per cum = (a+b+c+d+e+f)/600 76.34
Say Rs. 67.55
Unit = sqm
Taking output = 600 sqm
a) Labour
Mate day 0.030 291.67 8.75
Mazdoor day 0.750 291.67 218.75
b) Machinery
Road marking machine @ 60 sqm per
hour 10.000 1000.00 10000.00
hour
Tractor-trolley hour 0.500 581.00 290.50
c) Material
Hot applied thermoplastic compound Litre 1500.000 160.00 240000.00
Reflectorising glass beads kg 150.000 140.00 21000.00
Overheads & CP @ 12.5% on 33939.75
(a+b+c)
Labour Cess @ 1% on (a+b+c+d) 3054.58
GST @ 12% on (a+b+c+d) 36654.93
Cost for 600 sqm = a+b+c+d+e 345167.26
Rate per sqm = a+b+c+d+e)/600 575.30
Unit = cum
Taking output = 1.25 cum
(I) By Manual Means
(C) Reinforced Cement Concrete
a) Labour
Mate day 0.15 233.33 35.00
Blacksmith day 0.25 282.33 70.58
Mazdoor day 3.50 233.33 816.66
(Unskilled)
b) Machinery
Tractor with trolley hour 0.27 345.00 93.15
Unit = cum
Taking ouput = 1.25 cum
(B) Rubble Stone Masonry in Cement Mortar
a) Labour
Mate day 0.03 233.33 7.00
Mazdoor (Unskilled) day 0.75 233.33 175.00
b) Machinery
Tractor with trolley hour 0.27 345.00 93.15
Overheads & CP @ 12.5% on 275.15 34.39
(a+b+c)
Labour Cess @ 1% on (a+b+c) 3.10
GST @ 12% on (a+b+c) 37.14
Cost for 1.25 Cum = a+b+c+d 349.78
Rate per sqm = a+b+c+d)/1.25 279.82
Say Rs. 279.82
13.5 800 Providing and laying cement concrete
wearing course M 30 grade including
reinforcement complete as per drawing
and technical specifications Clauses 800
and 1206.3
Unit = cum
a) Material
Cement t 0.43 6,222.96 2,675.87
Sand cum 0.45 675.74 304.08
20 mm aggregate cum 0.54 730.45 394.44
10 mm aggregate cum 0.36 755.45 271.96
HYSD bar reinforcement (Rate as per t 0.075 45,232.00 3,392.40
Binding Wire kg 0.01 65.00 0.65
b) Labour
Mate day 0.08 291.67 23.33
Mason (1st Class) day 0.12 432.83 51.94
Mazdoor (Unskilled) day 1.73 291.67 504.59
Bhisti day 0.27 291.67 78.75
Mazdoor (Unskilled) for cleaning deck day 0.15 291.67 43.75
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.40 350.00 140.00
d) Formwork @ 3% of cost of 197.33
e) Overheads&CP @ 12.5% on 1,009.89
f) Labour Cess @ 1% on (a+b+c+d+e) 90.89
f) GST @ 12% on (a+b+c+d+e) 1,241.78
Rate per cum = a+b+c+d+e+f 10,421.67
Say Rs. 10,421.70
ANALYSIS OF RATES
Sr. Ref to
Description Unit Qty Rate Amount
No. MoRD
(i) Gravel /Soil aggregate base/sub base Nominal Maximum size Grading 80mm
Construction of( Gravel
table 2.3 of IRC
/Soil SP 77-2008)
aggregate base/sub base Nominal Maximum size Grading 80mm as per
table 2.3 of IRC SP 77-2008 spreading in uniform layers with Tractor mount appropriate grading
arrangements on prepared surface, mixing by mix place method at OMC with Tractor mount
appropriate rotavator attachment and compaction with three wheel 80-100kN static Roller capacity to
achieve the desired density, complete as per Specification contained in Para 2.2, 3.6 and 3.7 of IRC SP
77-2008 (Using old scarrified WBM Material)
Ref to
Sr.
MORD Description Unit Qty Rate Amount
No. Speci.
8.3 A 1600 & Excavation in soil in Hilly Area by mechanical means including cutting and trimming of side
300 slopes and disposing of excavated earth with a lift upto 1.5 metre and a lead upto 20 metre as per
Technical Specification Clause 1603.1
i) Ordinary soil
Mechnical Means
Ref to
Sr.
MoRD Description Unit Qty Rate Amount
No.
Speci.
8.3 1600 & Excavation in Hilly Area in ordinary rock not requiring blasting by mechanical means including
A(ii) 300 cutting and trimming of slopes and disposal of cut material with a lift upto 1.5 metre and a lead
upto 20 metre as per Technical Specification Clause 1603.2
ANALYSIS OF RATES
Ref to
Sr. MORD Description Unit Qty Rate Amount
No. Speci.
1600 & Excavation in Hilly Area in hard rock requiring blasting by mechanical means lift upto 1.5 metre
300 and disposal of excavated rock upto a lead of 20 metre as per Technical Specification Clause
1603.2
iii) Hard Rock ( requiring blasting)
Mechnical Means
Unit = Per Cubic Metre
Taking output = 170Cubic Metre
a) LABOUR:
Mate Day 1.36 291.67 396.67
Driller Day 2.00 291.67 583.34
Blaster Day 10.00 340.67 3406.70
Mazdoor ( unskilled) Day 22.00 291.67 6416.74
Total 10803.45
b) MACHINERY:
Dozer D-50 @ 56.67Cum per Hour (blasted Hour 3.00 3330.00 9990.00
rock)
Hydraulic Excavator 0.9Cum bucket capacity @ Hour 5.00 1980.00 9900.00
34Cum per Hour
Air compresser 210cfm with two jack hamber @ Hour 28.00 495.00 13860.00
6cum per hour
Total 33750.00
c) MATERIAL:
Gelatine 80 percent Kg 67.00 98.00 6566.00
Electric Detonators @ 1detonator for 1 gelatine Nos 235.00 16.00 3760.00
stick of 285gm each
Total 10326.00
Net Total 54879.45
Add 12.5% (Over Head @2.5% +10% Rs. 54879.45 12.50% 6859.93
Contractor Profit) on ( a+b)
Total 61739.38
Add 1% Labour Cess on Rs 61739.38 1.00% 617.39
Add 12%GSTon Rs 61739.38 12.00 7408.73
Grand Total 69765.50
Cost for 170 Cum 69765.50
Rate per Cubic metre Rs. 410.39
Say Rs Rs. 410.40
Motor grader for grading@ 100cum per hour Hour 0.50 2430.00 1215.00
Water tanker 6KL capacity Hour 2.00 531.00 1062.00
Three wheel 80-100KN Static Roller @80cum Hour 1.00 756.00 756.00
per hour
Total 14943.10
c) Material:
Cost of water tanker KL 24.00 57.08 1369.92
Compensation for earth taken from private land Cum 100.00 74.71 7471.00
Net Total 24087.36
Add 12.5% (Over Head @2.5% +10% Rs. 24087.36 12.50% 3010.92
Contractor Profit) on ( a+b)
Total 27098.28
Add 1% Labour Cess on Rs 27098.28 1.00% 270.98
Add 12%GSTon Rs 27098.28 12.00 3251.79
Grand Total 30621.05
Cost for 100 Cum 30621.05
Rate per Cubic metre Rs. 306.20
Motor grader for grading@ 100cum per hour Hour 0.50 2430.00 1215.00
Water tanker 6KL capacity Hour 2.00 531.00 1062.00
Three wheel 80-100KN Static Roller @80cum Hour 1.25 756.00 945.00
per hour
Total 6552.00
c) Material:
Cost of water tanker KL 24.00 57.08 1369.92
Net Total 8073.59
Add 15.0% (Over Head @2.5% +10% Rs. 8073.59 15.00% 1211.04
Contractor Profit) on ( a+b)
Total 9284.63
Add 1% Labour Cess on Rs 9284.63 1.00% 92.85
Add 12%GSTon Rs 9284.63 12.00 1114.16
Grand Total 10491.64
Cost for 100 Cum 10491.64
Rate per Cubic metre Rs. 104.90
Ref to
Sr. MORD Description Unit Qty Rate Amount
No. Speci.
300 Earth work in excavation for structures as per drawing and technical specifications Clause 305.1
including setting out, construction of shoring and bracing, removal of stumps and other deleterious
material and disposal upto a lead of 50 metre, dressing of sides and bottam and back filling in
trenches with excavated suitable material. Ordinary soil upto 3.00 metre depth.
Ordinary Soil
Up to 3.00mtr. Depth
Unit = Per Cubic Metre
Taking output = 10Cubic Metre
a) LABOUR:
Mate Day 0.32 320.83 102.67
Mazdoor (unskilled) Day 8.00 320.83 2566.64
Total 2669.31
Add 15.0% (Over Head @5.0% +10% Rs. 2669.31 15.00% 400.40
Contractor Profit) on ( a+b)
Total 3069.70
Add 1% Labour Cess on Rs 3069.70 1.00% 30.70
Add 12%GSTon Rs 3069.70 12.00 368.36
Grand Total 3468.76
Cost for 10 Cum 3468.76
Rate per Cubic metre Rs. 346.90
Ref to
Sr.
MORD Description Unit Qty Rate Amount
No. Speci.
12.13 600 Providing weep holes in stone masonry, plain/ reinforced concrete abutment, wing walls,
return walls, retaining walls with 100mm ( one hundred millimeter) diameters, PVC pipe
extending through the full width of the structures with a slope of 1 ( one) vertical : 20
( twenty horizontal)
Ref to
Sr.
MoRD Description Unit Qty Rate Amount
No.
Speci.
PCC Grade M-10
11.4 800 & Providing and laying mechanically mixed plain/reinforced cement concrete in open foundation as
1200 per drawing and M.O.R.D. technical specification Clause 802, 803,1202 & 1203.
For Nominal Mix 1:3:6 (40mm size agg.)
Unit = Per Cubic Metre
Taking output = 1Cum
a) LABOUR:
Mate Day 0.08 291.67 23.33
Mason 1st Class Day 0.10 432.83 43.28
Mazdoor (unskilled) Day 1.63 291.67 475.42
Bhisti Day 0.27 291.67 78.75
Total 620.79
b) MACHINERY:
Concrete Mixer 0.40/0.28 Cum Cap. Fitted with Hour 0.40 360.00 144.00
water measuring device and preferably also with
load cell.
Total 144.00
c) MATERIAL:
Cement Tonne 0.25 6222.96 1555.74
Fine sand Cum 0.48 625.74 300.36
40mm aggregate Cum 0.576 705.45 406.34
20mm aggregate Cum 0.288 730.45 210.37
10mm aggregate Cum 0.096 755.45 72.52
Total 2545.33
Grand total 3310.12
Form work @ 4% on Cost of Material & Labour 132.40
Total 3442.52
Add 12.5% (Over Head @2.5% +10% Rs. 3442.52 12.50% 430.32
Contractor Profit) on ( a+b)
Total 3872.84
Add 1% Labour Cess on Rs 3872.84 1.00% 38.73
Add 12%GSTon Rs 3872.84 12.00 464.74
Grand Total 4376.31
Rate per Cubic metre 4376.30
Assistant Engineer Executive Engineer
Haroli Sub-Division Una Division
HPPWD Haroli. HP.PWD. Una.
ANALYSIS OF RATES
Sr. Ref to
Description Unit Qty Rate Amount
No. Mord
PCC Grade M-15
12.8 800 Plain/reinforced cement concrete in substructure complete as per drawings and Technical
Specification Clauses 802, 804, 805, 806, 807, 1202 and 1204 upto 5.00 metre height. Plain
Cement concrete grade M15 nominal mix 1:2.5:5.
a) LABOUR:
Mate Day 0.44 291.67 128.33
Black Smith Day 3.00 340.67 1022.01
Mazdoor (unskilled) Day 8.00 291.67 2333.36
Total 3483.70
b) MATERIAL:
TMT bars including 5per cent laps and wastage Tonne 1.05 45232.00 47493.60
Binding Wire Kg 8.00 65.00 520.00
Total 48013.60
Net Total 51497.30
Add 12.5% (Over Head @2.5% +10% Rs. 51497.30 12.50% 6437.16
Contractor Profit) on ( a+b)
Total 57934.47
Add 1% Labour Cess on Rs 57934.47 1.00% 579.34
Add 12%GSTon Rs 57934.47 12.00 6952.14
Grand Total 65465.95
Rate per Tonne 65465.90
2142.25
Say Rs 2142.00
Manual Means
Ref to Providing and laying cement concrete 1:5:10 with 15% plums and curing complete including the
Sr.
MoRD cost of form work plain/reinforced concrete in Parapets ,the size of plum should be 150mm to
No.
Speci. 300mm as per drawing and HP.PWD Technical Specification.
11.15 800 & For Nominal Mix(Mechancial Mixed) 1:5:10
1200 (40mm size agg.) with 15% plum
Tractor with rotavator 25 Cum per Hour Hour 12.00 702.00 8424.00
Total 48663.00
c) MATERIAL:
Well graded Gravel /Soil aggregate base/sub Cum 360.00 505.45 181962.00
base Nominal Maximum size Grading 80mm as
per table 2.3 of IRC SP 77-2008
Water Kl 30.00 57.08 1712.40
Total 183674.40
Net Total 234764.03
Add 12.5% (Over Head @2.5% +10% Rs. 234764.03 12.50% 29345.50
Contractor Profit) on ( a+b)
Total 264109.54
Add 1% Labour Cess on Rs 264109.54 1.00% 2641.10
Add 12%GSTon Rs 264109.54 12.00 31693.14
Cost for 300 Cum 298443.78
Rate per cubic metre Rs. 995.00
Trans f) LABOUR:
portin Mate Day 0.32 291.67 291.67
g& Mason Day 1.00 432.83 432.83
Fixing
Mazdoor Day 7.00 291.67 291.67
g)Machinery
Tractor -Trolly Litre 0.60 621.00 372.60
Add 12.5% (Over Head @2.5% +10% Rs. 1388.77 12.50% 173.60
Contractor Profit) on ( a+b)
Add 12.5% (Over Head @2.5% +10% Rs. 3739.66 12.50% 467.46
Contractor Profit) on ( a+b)
iii) Painting on MS steel tube with primer and Sqm 1.80 103.54 186.38
two coat of epoxy paint 2x2.05x0.30=1.23
1x1.10x1.88=0.21
Total 990.78
Cost per 10Sqm 1530.48
Rate per cubic metre Rs. 153.05
Total 14733.58
c) MATERIAL:
Water Kl 12.00 57.08 684.96
Commpensation for earth taken from private land Cum 30.00 74.71 2241.30
Total 2926.26
17963.18
Add 15.0% (Over Head @5.0% +10% Rs. 17963.18 15.00% 2694.48
Contractor Profit) on ( a+b)
Total 20657.65
Add 1% Labour Cess on Rs 20657.65 1.00% 206.58
Add 12%GSTon Rs 20657.65 12.00% 2478.92
Cost for 100 Cum 23343.15
Rate per cubic metre Rs. 233.43
c) MATERIAL:
Cement concrete M30 grade ( Refer Item No Cum 1.00 6752.59 6752.59
13.1 III excluding form work
HYSD bar reinforcement ( Rate as per Item Tonne 0.075 57934.47 4345.09
a 13.2)
a) LABOUR:
Mate Day 0.34 291.67 99.17
Black Smith Day 2.00 340.67 681.34
Mazdoor (unskilled) Day 6.50 291.67 1895.86
Total 2676.36
b) MATERIAL:
TMT bars including 5per cent laps and wastage Tonne 1.05 45232.00 47493.60
Binding Wire Kg 6.00 83.00 498.00
Total 47991.60
Net Total 50667.96
Add 12.5% (Over Head @2.5% +10% Rs. 50667.96 12.50% 6333.50
Contractor Profit) on ( a+b)
Total 57001.46
Add 1% Labour Cess on Rs 57001.46 1.00% 570.01
Add 12%GSTon Rs 57001.46 12.00% 6840.17
64411.64
Rate per Tonne Rs. 64411.60
Total 2002.10
C) MACHINERY:
Mechancial concrete mixer 0.4/0.28 Cum Hour 0.40 360.00 144.00
capacity fitted with water measuring device
Total 2766.89
d) Form work @ 4% on Cost of Material & Labour 2766.89 4% 110.68
2877.57
Add 15.0% (Over Head @5.0% +10% Rs. 2877.57 15.00% 431.64
Contractor Profit) on ( a+b)
Total 3309.20
Add 1% Labour Cess on Rs 3309.20 1.00% 33.09
Add 12%GSTon Rs 3309.20 12.00% 397.10
Grand Total 3739.39
Rate per Cubic metre 3739.40
a) Material
Reinforced cement concrete M-25 grade Cum 1.000 6449.50 6449.50
Rate as per item No. 13.1 II HYSD Tonne 0.050 65465.90 3273.30
reinforcement
Total 706.41
(a+b) 1120.87
Add 12.5% (Over Head @2.5% +10% Rs. 1120.87 12.50% 140.11
Contractor Profit) on ( a+b)
Total 1260.98
Add 1% Labour Cess on Rs 1260.98 1.00% 12.61
Add 12% GSTon Rs 1260.98 12.00% 151.32
Grand Total 1424.91
Rate per Cubic metre 1424.90
Assistant Engineer Executive Engineer
Haroli Sub-Division Una Division
HPPWD Haroli. HP.PWD. Una.
Taking output = 12 m
12m long x 100 mm wide x 10mm deep recess
a) Labour
Mate day 0.02 291.67 5.83
Mazdoor day 0.50 291.67 145.84
Mazdoor (Skilled) day 0.10 291.67 29.17
b) Material
Sand cum 0.012 675.74 8.11
Volume 12 x 0.1 x 0.01 = 0.012 cum
Weight 0.012 x 1400 = 16.8kg
Bitumen cum 0.001 31391.82 31.39
16.8 x 0.06 = 1 kg
c) Overhead charges @ 12.5 % on (a+b) 27.54
d) Contractor's profit @ 1 % on (a+b+c) 2.48
(a+b) 250.36
Add 12.5% (Over Head @2.5% +10% Rs. 250.36 12.50% 31.29
Contractor Profit) on ( a+b)
Total 281.65
Add 1% Labour Cess on Rs 281.65 1.00% 2.82
Add 12% GSTon Rs 281.65 12.00% 33.80
Grand Total 318.27
Cost for 12 m = (a+b+c+d) 318.27
Rate per m = (a+b+c+d)/12 26.52
say 27.00
Unit = t.km
Taking output 10 tonnes load and lead 10
km = 100 t.km
(i) Surfaced Road
Speed with load : 25 km / hour.
Speed while Returning empty :35 km /
hour.
a) Machinery.
Tipper 10 tonne capacity
Time taken for onward haulage with hour 0.400 495.00 198.00
load
Time taken for empty return trip. hour 0.290 495.00 143.55
cost for 100 t km 341.55
Rate per tonne per km 3.42
say 3.00
1.4 (ii) Unsurfaced Graveled Road
Speed with load: 20 km / hour
Speed for empty return trip :30 km / hour
a) Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage with hour 0.500 495.00 247.50
load
Time taken for empty return trip hour 0.330 495.00 163.35
cost for 100 t km 410.85
Rate per tonne per km 4.11
say 4.00
Sr Ref. to
MoRTH Description Unit Quantity Rate Rs Cost Rs
No Spec.
a) Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage hour 1.000 495.00 495.00
Time taken for empty return trip hour 0.670 495.00 331.65
cost for 100 t km 826.65
Rate per tonne per km 8.27
say 8.00
1.5 Hand Broken Stone Aggregates 63 mm
Nominal Size
Supply of quarried stone, hand breaking
into coarse aggregate 63 mm nominal size
(passing 80 mm and retained on 50 mm
sieve) and stacking as directed
Unit = cum
Taking output = 1 cum
a) Labour
Mate day 0.060 291.67 17.50
Mazdoor day 1.500 291.67 437.51
b) Material
Supply of quarried stone 150 - 200 mm cum 1.100 300.00 330.00
size
Rate per cum (a+b) 785.01
say 785.00
Sr Ref. to
MoRTH Description Unit Quantity Rate Rs Cost Rs
No Spec.
Unit = cum
Taking Output = 600 cum at crusher
location.
a) Labour
Mate day 0.760 291.67 221.67
Mazdoor Skilled day 2.000 291.67 583.34
Mazdoor including breaking of any day 17.000 291.67 4958.39
oversize boulder.
b) Material
Stone Boulder of size 150 mm and cum 800.000 300.00 240000.00
below
c) Machinery
Integrated stone crusher of 200 TPH Hour 6.000 3960.00 23760.00
including belt conveyor and vibrating
screens
Front end loader 1 cum bucket capacity Hour 20.000 1416.60 28332.00
Unit = cum
Taking Output = 670 cum at crusher
location.
a) Labour
Mate day 0.760 291.67 221.67
Mazdoor Skilled day 2.000 291.67 583.34
Mazdoor including breaking of any size day 17.000 291.67 4958.39
boulder.
b) Material
Stone Boulder of size 150 mm and cum 800.000 300.00 240000.00
below
c) Machinery
Integrated stone crusher of 200 TPH Hour 6.000 3960.00 23760.00
including belt conveyor and vibrating
screens
Front end loader 1 cum bucket capacity Hour 20.000 1416.60 28332.00
Unit = cum
Taking Output = 750 cum at crusher
location.
a) Labour
Mate day 0.760 291.67 221.67
Mazdoor Skilled day 2.000 291.67 583.34
Mazdoor day 17.000 291.67 4958.39
b) Material
Stone Boulder of size 150 mm and cum 800.000 300.00 240000.00
below
c) Machinery
Integrated stone crusher of 200 TPH Hour 6.000 3960.00 23760.00
including belt conveyor and vibrating
screens
Front end loader 1 cum bucket capacity Hour 20.000 1416.60 28332.00
I Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means
(i) Depth upto 3 m
a) Labour
Mate day 0.14 320.83 44.92
Mazdoor day 3.50 320.83 1122.91
Total 1167.82
b) Overhead charges @ 20% on (a) 20.0% 233.56
c ) Contractors Profit @10% on (a+b) 10.0% 140.14
Total 1541.52
Add 1% Labour Cess on Rs 1541.52 1.0% 15.42
Add 12%GSTon Rs 1541.52 12.0% 184.98
Grand Total 1741.92
Cost for 10 Cum 1741.92
Through Rate per cum = (a+b+c)/10 174.20
Total 1981.96
Add 1% Labour Cess on Rs 1981.96 1.0% 19.82
Add 12%GSTon Rs 1981.96 12.0% 237.84
Grand Total 2239.61
Cost for 10 Cum 2239.61
Through Rate per cum = (a+b+c)/10 224.00
Total 2642.61
Add 1% Labour Cess on Rs 2642.61 1.0% 26.43
Add 12%GSTon Rs 2642.61 12.0% 317.11
Grand Total 2986.15
Cost for 10 Cum 2986.15
Through Rate per cum = (a+b+c)/10 298.60
Total 19205.08
Add 1% Labour Cess on Rs 19205.08 1.0% 192.05
Add 12%GSTon Rs 19205.08 12.0% 2304.61
Grand Total 21701.74
Cost for 240 Cum 21701.74
Through Rate per cum = 90.40
(a+b+c+d)/240
Total 16524.23
Add 1% Labour Cess on Rs 16524.23 1.0% 165.24
Add 12%GSTon Rs 16524.23 12.0% 1982.91
Grand Total 18672.38
Cost for 210 Cum 18672.38
Through Rate per cum = 88.90
(a+b+c+d)/210
Note Cost of dewatering upto 7.5 per cent
of (a+b) may be added, where
required. Assessment for dewatering
shall be made as per site conditions..
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
2.1 (I) (iii) Depth above 6m
B
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.40 291.67 116.67
Mazdoor day 10.00 291.67 2916.70
Total 3033.37
b) Machinery
Hydraulic excavator 1.0 cum hour 6.00 1980.00 11880.00
bucket capacity
Total 14913.37
c) Overhead charges @ 5% (a+b) 5.0% 745.67
d ) Contractors Profit @10% (a+b+c) 10.0% 1565.90
A Manual Means
(i) Depth upto 3 m
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.20 291.67 58.33
Mazdoor day 5.00 291.67 1458.35
Total 1516.68
b) Overhead charges @ 5% (a) 5.0% 75.83
c ) Contractors Profit @10% (a+b) 10.0% 159.25
Total (a+b+c ) 1751.77
Add 1% Labour Cess on Rs 1751.77 1.0% 17.52
Add 12%GSTon Rs 1751.77 12.0% 210.21
Grand Total 1979.50
Cost for 10 Cum 1979.50
Through Rate per cum = (a+b+c)/10 198.00
Total 4236.29
Add 1% Labour Cess on Rs 4236.29 1.0% 42.36
Add 12%GSTon Rs 4236.29 12.0% 508.35
Grand Total 4787.01
Cost for 10 Cum 4787.01
478.70
Through Rate per cum = (a+b+c+d)/10
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Note Cost of dewatering @ 10 per cent of
(a+b) may be added, where
required Assessment for dewatering
shall be made as per site conditions.
Unit = cum
Taking output = 10 cum
B Mechanical Means
a) Labour
Mate day 0.20 291.67 58.33
Mazdoor day 5.00 291.67 1458.35
Total 1516.68
b) Machinery
Air Compressor 250 cfm with 2 hour 6.00 495.00 2970.00
leads of pneumatic breaker
Total 4486.68
c) Overhead charges @ 5% (a+b) 5.0% 224.33
d) Contractors Profit @10% (a+b+c) 10.0% 471.10
Total 5182.12
Add 1% Labour Cess on Rs 5182.12 1.0% 51.82
Add 12%GSTon Rs 5182.12 12.0% 621.85
Grand Total 5855.80
Cost for 10 Cum 5855.80
585.60
Through Rate per cum = (a+b+c+d)/10
Total 1915.07
Add 1% Labour Cess on Rs 1915.07 1.0% 19.15
Add 12%GSTon Rs 1915.07 12.0% 229.81
Grand Total 2164.03
Cost for 10 Cum 2164.03
216.40
Through Rate per cum = (a+b+c+d)/10
Unit : Cum
Taking Output : 6 cum
a) Labour
Mate day 0.12 116.67 14.00
Mazdoor for dressing sides, day 3.00 116.67 350.01
bottom and backfilling
b) Machinery
Tractor-trolley for transportation hour 2.00 390.00 780.00
c) Overhead charges @ on (a+b) 57.20
say 220.00
Labour Rate
Labour 364.01
Overhead charges @ 5% 18.20
Contractors Profit @10% 38.22
Cost for 6 cum 420.43
Labour Rate per cum 70.07
Say 70.00
say 458.00
Labour Rate
Labour 36.17
Overhead charges @ 5%= 1.81
Contractors Profit @10%= 3.80
Cost for 1cum 41.78
Labour Rate per cum 41.78
Say 42.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
2.4 2100 PCC 1:3:6 in Foundation
Plain cement concrete 1:3:6 nominal
mix in foundation with crushed stone
aggregate 40 mm nominal size
mechanically mixed, placed in
foundation and compacted by vibration
including curing for 14 days.
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.64 320.83 205.33
Mason day 1.00 476.00 476.00
Mazdoor day 15.00 320.83 4812.45
Total 5493.78
b) Material
40 mm Aggregate cum 13.50 705.45 9523.58
coarse Sand cum 6.75 675.74 4561.25
cement tonne 3.45 6222.96 21469.21
Cost of water KL 18.00 57.08 1027.44
Total 36581.47
c) Machinery
Concrete mixer (cap. 0.40/0.28 hour 6.00 360.00 2160.00
cum)
Generator 33 KVA hour 6.00 300.00 1800.00
Water tanker 6 KL capacity hour 2.00 531.00 1062.00
Total 5022.00
Cost of 15 cum 47097.25
c) Overhead charges @ 20% (a+b+c) 20.0% 9419.45
Total 62168.37
Add 1% Labour Cess on Rs 62168.37 1.0% 621.68
Add 12%GSTon Rs 62168.37 12.0% 7460.20
Grand Total 70250.26
Cost for 15 Cum 70250.26
4683.40
Through Rate per cum = (a+b+c+d)/15
Unit = cum
Taking output = 5 cum
a) Material
Bricks Ist class each 2500.00 3.00 7500.00
Cement mortar 1:3 (Rate as in cum 1.20 2924.00 3508.80
Item 2.6 A sub-analysis)
Total 11008.80
b) Labour
Mate day 0.48 291.67 140.00
Mason day 4.00 432.83 1731.32
Mazdoor day 8.00 291.67 2333.36
Total 4204.68
Total 15213.48
c) Overhead charges @ 5% (a+b) 5.0% 760.67
d) Contractors Profit @10% (a+b+c) 10.0% 1597.42
Total 17571.57
Add 1% Labour Cess on Rs 17571.57 1.0% 175.72
Add 12%GSTon Rs 17571.57 12.0% 2108.59
Grand Total 19855.88
Cost for 15 Cum 19855.88
3971.20
Through Rate per cum = (a+b+c+d)/5
say 2355.00
Labour Rate
Labour for masonary 2710.81
Labour for mortar 164.50
Overhead charges @ 5% 143.77
Contractors Profit @10% 301.91
Cost for 5cum 3320.98
Labour Rate per cum 664.20
Say 664.00
1405 Random Rubble Masonry
(B) ( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.50 400.00 2200.00
Through and bond stone each 35.00 10.00 350.00
(35nos.x0.24mx0.24mx0.39m = 0.79
cu.m)
Cement mortar 1:3 (Rate as in cum 1.55 2924.00 4532.20
Item 2.6 A sub-analysis)
b) Labour
Mate day 0.62 116.67 72.34
Mason day 6.00 211.17 1267.02
Mazdoor day 9.00 116.67 1050.03
c) Overhead charges @ on (a+b) 473.58
say 2297.00
The labour already considered in
cement mortar has been taken into
account while proposing labour for
masonry works.
Labour Rate
Labour for masonary 2389.39
Labour for mortar 169.98
Overhead charges @ 5% 127.97
Contractors Profit @10% 268.73
Cost for 5cum 2956.07
Labour Rate per cum 591.21
Say 591.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
2.8 1500, Plain/Reinforced Cement Concrete in
1700 Open Foundation complete as per
& Drawing and Technical Specifications.
2100
Total 68189.21
Add 1% Labour Cess on Rs 68189.21 1.00% 681.89
Add 12%GSTon Rs 68189.21 12.00 8182.71
Grand Total 77053.81
Cost for 15 Cum 77053.81
Rate per Cubic metre Rs. 5136.90
Total 76399.97
Add 1% Labour Cess on Rs 76399.97 1.00% 764.00
Add 12%GSTon Rs 76399.97 12.00 9168.00
Grand Total 86331.97
Cost for 15 Cum 86331.97
Rate per Cubic metre Rs. 5755.50
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
say 37185.00
Note It is assumed that earth will be
available within the working space of
crane with grab bucket.
Labour Rate
Labour 1796.72
Overhead charges @ 5% 89.84
Contractors Profit @10% 188.66
Cost for 1No. 2075.21
Labour Rate per Unit 2075.21
Say 2075.00
2.9 B Assuming depth of water 4.0 m and
height of island 4.5 m.
Unit = 1No
Taking output = 1 No
a) Material
Earth (compacted) cum 904.32 40.00 36172.80
Sand bags each 6000.00 8.00 48000.00
Wooden ballies 8" Dia and 9 m each 95.00 1800.00 171000.00
long
Wooden ballies 2" Dia for bracing metre 190.00 100.00 19000.00
b) Labour
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Mate day 5.60 116.67 653.35
Mazdoor for piling 8" dia ballies for day 18.00 116.67 2100.06
piling 8" dia ballies
Mazdoor for bracing with 2" dia day 12.00 116.67 1400.04
ballies
Mazdoor for filling sand bags, day 110.00 116.67 12833.70
stitching and placing
c) Machinery
Crane with grab 1 cum capacity hour 50.00 700.00 35000.00
Consumables and other arrangements 8154.00
for piling ballies @ 2.5 per cent of
(a+b+c).
d) Overhead charges @ on 16715.70
(a+b+c)
e) Contractor's profit @ on 35102.96
(a+b+c+d)
Through Rate per No. (a+b+c+d+e) 386132.61
say 386133.00
Note For other well diameters rate can be
worked out on the basis of cross-
sectional area of well. The diameter of
the island shall be in the conformity
with clause 1203.2 of MoRTH
specifications.
Labour Rate
Labour 16987.15
Overhead charges @ 5% 849.36
Contractors Profit @10% 1783.65
Cost for 1No. 19620.16
Labour Rate per Unit 19620.16
Say 19620.00
2.9 C Providing and constructing one span
service road to reach island location
from one pier location to another pier
location
say 1928.00
Labour Rate
Labour 728.02
Overhead charges @ 5% 36.40
Contractors Profit @10% 76.44
Cost for 30 Mtr.. 840.86
Labour Rate per Mtr. 28.03
Say 28.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
2.10 1200 Providing and Laying Cutting Edge of
& Mild Steel weighing 40 kg per metre
1900 for Well Foundation complete as per
Drawing and Technical Specification.
Unit = 1 MT
Taking output = 1 MT
a) Material
Structural steel in plates, angles, tonne 1.05 45000.00 47250.00
etc including 5 per cent wastage
Unit = 1 cum
Taking output = 1 cum
A Well curb
(i) RCC M20 Grade
Same as for 12.8 (C) except for
formwork which shall be@ 20 per cent
of the cost of concrete instead of 4 per
cent.
Case Using Concrete Mixer
I
Per Cum Basic Cost of Labour, 2642.00
Material & Machinery (a+b+c)
d) formwork @ 20 per cent of the 528.40
cost of concrete
e) Overhead charges @ on 158.52
(a+b+c+d)
f) Contractor's profit @ on 332.89
(a+b+c+d+e)
Through Rate per cum (a+b+c+d+e+f) 3661.81
say 3662.00
Labour Rate
Labour 2750.50
Overhead charges @ 5% 137.53
Contractors Profit @10% 288.80
Cost for 15 cum 3176.83
Labour Rate per cum 211.79
Say 212.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
2.11 Case With Batching Plant, Transit Mixer and
A (i) II Concrete Pump
Per Cum Basic Cost of Labour, 2542.00
Material & Machinery (a+b+c)
d) formwork @ 20 per cent of the 508.40
cost of concrete
e) Overhead charges @ on 152.52
(a+b+c+d)
f) Contractor's profit @ on 320.29
(a+b+c+d+e)
ThroughRate per cum (a+b+c+d+e+f) 3523.21
say 3523.00
Labour Rate
Labour 2831.57
Overhead charges @ 5% 141.58
Contractors Profit @10% 297.31
Cost for 120 cum 3270.46
Labour Rate Rate per cum 27.25
Say 27.00
2.11 (ii) RCC M25 Grade
A
Same as for 2.8 (E) except for
formwork which shall be@ 20 per cent
of the cost of concrete instead of 3.75
per cent.
Case Using Concrete Mixer
I
Per Cum Basic Cost of Labour, 2916.00
Material & Machinery (a+b+c)
d) formwork @ 20 per cent of the 583.20
cost of concrete
e) Overhead charges @ on 174.96
(a+b+c+d)
f) Contractor's profit @ on 367.42
(a+b+c+d+e)
Through Rate per cum (a+b+c+d+e+f) 4041.58
say 4042.00
Labour Rate
Labour 2750.50
Overhead charges @ 5% 137.53
Contractors Profit @10% 288.80
Cost for 15 cum 3176.83
Labour Rate per cum 211.78
Say 212.00
2.11 Case With Batching Plant, Transit Mixer and
A (ii) II Concrete Pump
Per Cum Basic Cost of Labour, 2816.00
Material & Machinery (a+b+c)
d) formwork @ 20 per cent of the 563.20
cost of concrete
e) Overhead charges @ on 168.96
(a+b+c+d)
f) Contractor's profit @ on 354.82
(a+b+c+d+e)
Through Rate per cum (a+b+c+d+e+f) 3902.98
say 3903.00
Labour Rate
Labour 2831.57
Overhead charges @ 5% 141.58
Contractors Profit @10% 297.31
Cost for 120 cum 3270.46
Labour Rate per cum 27.25
Say 27.00
2.11 (iii) RCC M35 Grade
A
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Same as for 2.8 (H) except for
formwork which shall be@ 20 per cent
of the cost of concrete instead of 3.0
per cent.
Case Using Concrete Mixer
I
Per Cum Basic Cost of Labour, 3008.00
Material & Machinery (a+b+c)
d) formwork @ 20 per cent of the 601.60
cost of concrete
e) Overhead charges @ on 180.48
(a+b+c+d)
f) Contractor's profit @ on 379.01
(a+b+c+d+e)
Through Rate per cum (a+b+c+d+e+f) 4169.09
say 4169.00
Labour Rate
Labour 2750.50
Overhead charges @ 5% 137.53
Contractors Profit @10% 288.80
Cost for 15 cum 3176.83
Labour Rate per cum 211.79
Say 212.00
2.11 Case With Batching Plant, Transit Mixer and
A (iii) II Concrete Pump
Per Cum Basic Cost of Labour, 2909.00
Material & Machinery (a+b+c)
d) formwork @ 20 per cent of the 581.80
cost of concrete
e) Overhead charges @ on 174.54
(a+b+c+d)
f) Contractor's profit @ on 366.53
(a+b+c+d+e)
Through Rate per cum (a+b+c+d+e+f) 4031.87
say 4032.00
Note. If curb concrete is carried out within
steel liner, cost of formwork shall be
excluded.
Labour Rate
Labour 2831.57
Overhead charges @ 5% 141.58
Contractors Profit @10% 297.31
Cost for 120 cum 3270.46
Labour Rate per cum 27.25
Say 27.00
2.11 B Well steining
(I) PCC M15 Grade
Same as for 2.8 (A) except for
formwork which shall be @ 10 per cent
of the cost of concrete instead of 4
per cent.
Case Using Concrete Mixer
I
Per Cum Basic Cost of Labour, 2293.00
Material & Machinery (a+b+c)
d) formwork @ 10 per cent of the 229.30
cost of concrete
e) Overhead charges @ on 126.12
(a+b+c+d)
f) Contractor's profit @ on 264.84
(a+b+c+d+e)
Through Rate per cum (a+b+c+d+e+f) 2913.26
say 2913.00
Labour Rate
Labour 2750.50
Overhead charges @ 5% 137.53
Contractors Profit @10% 288.80
Cost for 15 cum 3176.83
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Labour Rate per cum 211.78
Say 212.00
2.11 (ii) PCC M20 Grade
B
Same as for 2.8 (B) except for
formwork which shall be @ 10 per cent
of the cost of concrete instead of 4
per cent.
Case Using Concrete Mixer
I
Per Cum Basic Cost of Labour, 2615.00
Material & Machinery (a+b+c)
d) formwork @ 10 per cent of the 261.50
cost of concrete
e) Overhead charges @ on 143.83
(a+b+c+d)
f) Contractor's profit @ on 302.03
(a+b+c+d+e)
Through Rate per cum (a+b+c+d+e+f) 3322.36
say 3322.00
Labour Rate
Labour 2750.50
Overhead charges @ 5% 137.53
Contractors Profit @10% 288.80
Cost for 15 cum 3176.83
Labour Rate per cum 211.78
Say 212.00
2.11 (iii) RCC M20 Grade
B
Same as for 2.8 (C) except for
formwork which shall be @ 10 per cent
of the cost of concrete instead of 4
per cent.
Case Using Concrete Mixer
I
Per Cum Basic Cost of Labour, 2642.00
Material & Machinery (a+b+c)
d) formwork @ 10 per cent of the 264.20
cost of concrete
e) Overhead charges @ on 145.31
(a+b+c+d)
f) Contractor's profit @ on 305.15
(a+b+c+d+e)
Through Rate per cum (a+b+c+d+e+f) 3356.66
say 3357.00
Labour Rate
Labour 2750.50
Overhead charges @ 5% 137.53
Contractors Profit @10% 288.80
Cost for 15 cum 3176.83
Labour Rate per cum 211.78
Say 212.00
2.11 Case With Batching Plant, Transit Mixer and
B (iii) II Concrete Pump
Per Cum Basic Cost of Labour, 2542.00
Material & Machinery (a+b+c)
d) formwork @ 10 per cent of the 254.20
cost of concrete
e) Overhead charges @ on 139.81
(a+b+c+d)
f) Contractor's profit @ on 293.60
(a+b+c+d+e)
Through Rate per cum (a+b+c+d+e+f) 3229.61
say 3230.00
Labour Rate
Labour 2831.57
Overhead charges @ 5% 141.58
Contractors Profit @10% 297.31
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Cost for 120 cum 3270.46
Labour Rate per cum 27.25
Say 27.00
2.11 (iv) PCC M25 Grade
B
Same as for 2.8 (D) except for
formwork which shall be @ 10 per cent
of the cost of concrete instead of 4
per cent.
Case Using Concrete Mixer
I
Per Cum Basic Cost of Labour, 2886.00
Material & Machinery (a+b+c)
d) formwork @ 10 per cent of the 288.60
cost of concrete
e) Overhead charges @ on 158.73
(a+b+c+d)
f) Contractor's profit @ on 333.33
(a+b+c+d+e)
Through Rate per cum (a+b+c+d+e+f) 3666.66
say 3667.00
Labour Rate
Labour 2750.50
Overhead charges @ 5% 137.53
Contractors Profit @10% 288.80
Cost for 15 cum 3176.83
Labour Rate per cum 211.78
Say 212.00
2.11 Case With Batching Plant, Transit Mixer and
B (iv) II Concrete Pump
Per Cum Basic Cost of Labour, 2788.00
Material & Machinery (a+b+c)
d) formwork @ 10 per cent of the 278.80
cost of concrete
e) Overhead charges @ on 153.34
(a+b+c+d)
f) Contractor's profit @ on 322.01
(a+b+c+d+e)
Through Rate per cum (a+b+c+d+e+f) 3542.15
say 3542.00
Labour Rate
Labour 2831.57
Overhead charges @ 5% 141.58
Contractors Profit @10% 297.31
Cost for 120 cum 3270.46
Labour Rate per cum 27.25
Say 27.00
2.11 (v) RCC M25 Grade
B
Same as for 2.8 (E) except for
formwork which shall be @ 10 per cent
of the cost of concrete instead of 3.5
per cent.
Case Using Concrete Mixer
I
Per Cum Basic Cost of Labour, 2916.00
Material & Machinery (a+b+c)
d) formwork @ 10 per cent of the 291.60
cost of concrete
e) Overhead charges @ on 160.38
(a+b+c+d)
f) Contractor's profit @ on 336.80
(a+b+c+d+e)
Through Rate per cum (a+b+c+d+e+f) 3704.78
say 3705.00
Labour Rate
Labour 2750.50
Overhead charges @ 5% 137.53
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Contractors Profit @10% 288.80
Cost for 15 cum 3176.83
Labour Rate per cum 211.78
Say 212.00
2.11 Case With Batching Plant, Transit Mixer and
B (v) II Concrete Pump
Per Cum Basic Cost of Labour, 2816.00
Material & Machinery (a+b+c)
d) formwork @ 10 per cent of the 281.60
cost of concrete
e) Overhead charges @ on 154.88
(a+b+c+d)
f) Contractor's profit @ on 325.25
(a+b+c+d+e)
Through Rate per cum (a+b+c+d+e+f) 3577.73
say 3578.00
Labour Rate
Labour 2831.57
Overhead charges @ 5% 141.58
Contractors Profit @10% 297.31
Cost for 120 cum 3270.46
Labour Rate per cum 27.25
Say 27.00
2.11 (vi) PCC M30 Grade
B
Same as for 2.8 (F) except for
formwork which shall be @ 10 per cent
of the cost of concrete instead of 3.5
per cent.
Case Using Concrete Mixer
I
Per Cum Basic Cost of Labour, 2915.00
Material & Machinery (a+b+c)
d) formwork @ 10 per cent of the 291.50
cost of concrete
e) Overhead charges @ on 160.33
(a+b+c+d)
f) Contractor's profit @ on 336.68
(a+b+c+d+e)
Through Rate per cum (a+b+c+d+e+f) 3703.51
say 3704.00
Labour Rate
Labour 2750.50
Overhead charges @ 5% 137.53
Contractors Profit @10% 288.80
Cost for 15 cum 3176.83
Labour Rate per cum 211.78
Say 212.00
2.11 Case With Batching Plant, Transit Mixer and
B (vi) II Concrete Pump
Per Cum Basic Cost of Labour, 2815.00
Material & Machinery (a+b+c)
d) formwork @ 10 per cent of the 281.50
cost of concrete
e) Overhead charges @ on 154.83
(a+b+c+d)
f) Contractor's profit @ on 325.13
(a+b+c+d+e)
Through Rate per cum (a+b+c+d+e+f) 3576.46
say 3576.00
Labour Rate
Labour 2831.57
Overhead charges @ 5% 141.58
Contractors Profit @10% 297.31
Cost for 120 cum 3270.46
Labour Rate per cum 27.25
Say 27.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
2.11 RCC M30 Grade
B
(vii) Same as for 2.8 (G) except for
formwork which shall be @ 10 per cent
of the cost of concrete instead of 3.5
per cent.
Using Concrete Mixer
Case Per Cum Basic Cost of Labour, 2933.00
I Material & Machinery (a+b+c)
d) formwork @ 10 per cent of the 293.30
cost of concrete
e) Overhead charges @ on 161.32
(a+b+c+d)
f) Contractor's profit @ on 338.76
(a+b+c+d+e)
Through Rate per cum (a+b+c+d+e+f) 3726.38
say 3726.00
Labour Rate
Labour 2750.50
Overhead charges @ 5% 137.53
Contractors Profit @10% 288.80
Cost for 15 cum 3176.83
Labour Rate per cum 211.78
Say 212.00
2.11 Case With Batching Plant, Transit Mixer and
B (vii) II Concrete Pump
say 3601.00
Labour Rate
Labour 2831.57
Overhead charges @ 5% 141.58
Contractors Profit @10% 297.31
Cost for 120 cum 3270.46
Labour Rate per cum 27.25
Say 27.00
2.11 (viii) RCC M35 Grade
B
Same as for 2.8 (H) except for
formwork which shall be @ 10 per cent
of the cost of concrete instead of 3
per cent.
Case Using Concrete Mixer
I
Per Cum Basic Cost of Labour, 3008.00
Material & Machinery (a+b+c)
d) formwork @ 10 per cent of the 300.80
cost of concrete
e) Overhead charges @ on 165.44
(a+b+c+d)
f) Contractor's profit @ on 347.42
(a+b+c+d+e)
Through Rate per cum (a+b+c+d+e+f) 3821.66
say 3822.00
Labour Rate
Labour 2750.50
Overhead charges @ 5% 137.53
Contractors Profit @10% 288.80
Cost for 15 cum 3176.83
Labour Rate per cum 211.78
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Say 212.00
2.11 Case With Batching Plant, Transit Mixer and
B II Concrete Pump
(viii)
Per Cum Basic Cost of Labour, 2909.00
Material & Machinery (a+b+c)
d) formwork @ 10 per cent of the 290.90
cost of concrete
e) Overhead charges @ on 160.00
(a+b+c+d)
f) Contractor's profit @ on 335.99
(a+b+c+d+e)
Through Rate per cum(a+b+c+d+e+f) 3695.88
say 3696.00
Labour Rate
Labour 2831.57
Overhead charges @ 5% 141.58
Contractors Profit @10% 297.31
Cost for 120 cum 3270.46
Labour Rate per cum 27.25
Say 27.00
2.11 (ix) RCC M40 Grade
B
Using Batching Plant, Transit Mixer
and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 4900.00 252840.00
Coarse Sand cum 54.00 300.00 16200.00
20 mm Aggregate cum 64.80 460.00 29808.00
10 mm Aggregate cum 43.20 480.00 20736.00
Admixture kg 206.00 75.00 15450.00
b) Labour
Mate day 0.84 116.67 98.00
Meson day 3.00 211.17 633.51
Mazdoor day 18.00 116.67 2100.06
c) Machinery
Batching Plant hour 6.00 1840.00 11040.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader 1 cum capacity hour 6.00 787.00 4722.00
Transit Mixer 4 cum capacity for hour 15.00 770.00 11550.00
lead upto 1 km.
Transit Mixer 4 cum capacity for tonne.k 300xL 0.00 0.00
lead beyond 1 km. m
Concrete Pump hour 6.00 210.00 1260.00
Per Cum Basic Cost of Labour, 24610.00
Material & Machinery (a+b+c)
d) Formwork @ 10 per cent on 36913.76
cost of concrete i.e. cost of material,
labour and machinery
e) Overhead charges @ on 20302.57
(a+b+c+d)
f) Contractor's profit @ on 42635.39
(a+b+c+d+e)
cost of 120 cum = a+b+c+d+e+f 468989.29
Through Rate per cum = 3908.24
(a+b+c+d+e+f)/120
say 3908.00
Labour Rate
Labour 2831.57
Overhead charges @ 5% 141.58
Contractors Profit @10% 297.31
Cost for 120 cum 3270.46
Labour Rate per cum 27.25
Say 27.00
2.11 C Bottom Plug
C
Concrete to be placed using tremie
pipe
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Note: 10% extra cement to be added
where under water concreting is
involved
(i) PCC Grade M20
Case Using Concrete Mixer
I
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.55 4900.00 27195.00
Coarse sand cum 6.75 300.00 2025.00
40 mm Aggregate cum 5.40 440.00 2376.00
20 mm Aggregate cum 5.40 460.00 2484.00
10 mm Aggregate cum 2.70 480.00 1296.00
Admixture Kg 18.60 75.00 1395.00
b) Labour
Mate day 0.90 116.67 105.00
Mason day 1.50 211.17 316.76
Mazdoor day 20.00 116.67 2333.40
c) Machinery
Concrete mixer (cap. 0.40/0.28 hour 6.00 200.00 1200.00
cum)
Generator 33 KVA hour 6.00 300.00 1800.00
Light Crane 3 tonnes capacity for hour 6.00 300.00 1800.00
handling tremie pipe
Per Cum Basic Cost of Labour, 2956.00
Material & Machinery (a+b+c)
Add 5 per cent of cost of material and 1976.31
labour towards cost of forming sump,
protective bunds, chiselling and
making arrangements for under water
concreting with tremie pipe..
Unit ; cum
Taking Output = 120 cum
a) Material
Cement tonne 44.40 4900.00 217560.00
Coarse sand cum 54.00 300.00 16200.00
20 mm Aggregate cum 64.80 460.00 29808.00
10 mm Aggregate cum 43.20 480.00 20736.00
Admixture Kg 148.80 75.00 11160.00
b) Labour
Mate day 0.88 116.67 102.67
Mason day 3.00 211.17 633.51
Mazdoor day 18.00 116.67 2100.06
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1840.00 11040.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader 1 cum capacity hour 6.00 787.00 4722.00
Transit Mixer 4 cum capacity for hour 15.00 770.00 11550.00
lead upto 1 km.
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Transit Mixer 4 cum capacity, lead tonne.k 300L 0.00 0.00
beyond 1 Km, L - lead in Kilometer m
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 47.88 4900.00 234612.00
Coarse sand cum 54.00 300.00 16200.00
20 mm Aggregate cum 64.80 460.00 29808.00
10 mm Aggregate cum 43.20 480.00 20736.00
Admixture Kg 172.80 75.00 12960.00
b) Labour
Mate day 0.88 116.67 102.67
Mason day 3.00 211.17 633.51
Mazdoor day 18.00 116.67 2100.06
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1840.00 11040.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader 1 cum capacity hour 6.00 787.00 4722.00
Transit Mixer 4 cum capacity for hour 15.00 770.00 11550.00
lead upto 1 km.
Transit Mixer 4 cum capacity, lead tonne.k 300L 0.00 0.00
beyond 1 Km, L - lead in Kilometer m
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.64 4900.00 238336.00
Coarse sand cum 54.00 300.00 16200.00
20 mm Aggregate cum 64.80 460.00 29808.00
10 mm Aggregate cum 43.20 480.00 20736.00
Admixture Kg 172.80 75.00 12960.00
b) Labour
Mate day 0.88 116.67 102.67
Mason day 3.00 211.17 633.51
Mazdoor day 18.00 116.67 2100.06
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1840.00 11040.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader 1 cum capacity hour 6.00 787.00 4722.00
Transit Mixer 4 cum capacity for hour 15.00 770.00 11550.00
lead upto 1 km.
Transit Mixer 4 cum capacity, lead tonne.k 300L 0.00 0.00
beyond 1 Km, L - lead in Kilometer m
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.28 4900.00 246372.00
Coarse sand cum 54.00 300.00 16200.00
20 mm Aggregate cum 64.80 460.00 29808.00
10 mm Aggregate cum 43.20 480.00 20736.00
Admixture Kg 172.80 75.00 12960.00
b) Labour
Mate day 0.88 116.67 102.67
Mason day 3.00 211.17 633.51
Mazdoor day 18.00 116.67 2100.06
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1840.00 11040.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader 1 cum capacity hour 6.00 787.00 4722.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Transit Mixer 4 cum capacity for hour 15.00 770.00 11550.00
lead upto 1 km.
Transit Mixer 4 cum capacity, lead tonne.k 300L 0.00 0.00
beyond 1 Km, L - lead in Kilometer m
say 3414.00
Labour Rate
Labour 2755.16
Overhead charges @ 5% 137.76
Contractors Profit @10% 289.29
Cost for 15 cum 3182.21
Labour Rate per cum 212.14
Say 212.00
2.11 Case Using Batching Plant, Transit Mixer
D (i) II and Crane/concrete pump
say 3173.00
Labour Rate
Labour 2836.24
Overhead charges @ 5% 141.81
Contractors Profit @10% 297.81
Cost for 120 cum 3275.86
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Labour Rate per cum 27.30
Say 27.00
2.11 (ii) Grade M25 PCC
D
Same as in bottom plug concrete,
excluding cost of forming sump,
protective bunds, chiseling etc.As per
2.11 C-ii
Case Using Concrete Mixer
I
Per Cum Basic Cost of Labour, 3114.00
Material & Machinery (a+b+c)
d) Overhead charges @ on 155.70
(a+b+c)
e) Contractor's profit @ on 326.97
(a+b+c+d)
Through Rate per cum = (a+b+c+d+e) 3596.67
say 3597.00
Labour Rate
Labour 2755.16
Overhead charges @ 5% 137.76
Contractors Profit @10% 289.29
Cost for 15 cum 3182.21
Labour Rate per cum 212.14
Say 212.00
2.11 Case Using Batching Plant, Transit Mixer
D (ii) II and Crane/concrete pump
say 3354.00
Labour Rate
Labour 2836.24
Overhead charges @ 5% 141.81
Contractors Profit @10% 297.81
Cost for 120 cum 3275.86
Labour Rate per cum 27.30
Say 27.00
2.11 (iii) Grade M30 PCC
D
Same as in bottom plug concrete,
excluding cost of forming sump,
protective bunds, chiseling etc.As
per2.11C-iii
Case Using Concrete Mixer
I
Per Cum Basic Cost of Labour, 3144.00
Material & Machinery (a+b+c)
d) Overhead charges @ on 157.20
(a+b+c)
e) Contractor's profit @ on 330.12
(a+b+c+d)
Through Rate per cum = (a+b+c+d+e) 3631.32
say 3631.00
Labour Rate
Labour 2755.16
Overhead charges @ 5% 137.76
Contractors Profit @10% 289.29
Cost for 15 cum 3182.21
Labour Rate per cum 212.14
Say 212.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
2.11 Case Using Batching Plant, Transit Mixer
D (iii) II and Crane/concrete pump
say 3390.00
Labour Rate
Labour 2836.24
Overhead charges @ 5% 141.81
Contractors Profit @10% 297.81
Cost for 120 cum 3275.86
Labour Rate per cum 27.30
Say 27.00
2.11 E Top plug
(i) Grade M15 PCC
Same as Item 2.8(a) excluding
formwork
Case Using Concrete Mixer
I
Per Cum Basic Cost of Labour, 2293.00
Material & Machinery (a+b+c)
d) Overhead charges @ on 114.65
(a+b+c)
e) Contractor's profit @ on 240.77
(a+b+c+d)
Through Rate per cum = (a+b+c+d+e) 2648.42
say 2648.00
Labour Rate
Labour 2750.50
Overhead charges @ 5% 137.53
Contractors Profit @10% 288.80
Cost for 15 cum 3176.83
Labour Rate per cum 212.00
2.11 (ii) Grade M20 PCC
E
Same as Item 2.8(b) excluding
formwork
Case Using Concrete Mixer
I
Per Cum Basic Cost of Labour, 2615.00
Material & Machinery (a+b+c)
d) Overhead charges @ on 130.75
(a+b+c)
e) Contractor's profit @ on 274.58
(a+b+c+d)
Through Rate per cum = (a+b+c+d+e) 3020.33
say 3020.00
Labour Rate
Labour 2750.50
Overhead charges @ 5% 137.53
Contractors Profit @10% 288.80
Cost for 15 cum 3176.83
Labour Rate per cum 212.00
2.11 (iii) Grade M25 PCC
E
Same as Item 2.8 (d) excluding
formwork
Case Using Concrete Mixer
I
Per Cum Basic Cost of Labour, 2886.00
Material & Machinery (a+b+c)
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
d) Overhead charges @ on 144.30
(a+b+c)
e) Contractor's profit @ on 303.03
(a+b+c+d)
Through Rate per cum = (a+b+c+d+e) 3333.33
say 3333.00
Labour Rate
Labour 2750.50
Overhead charges @ 5% 137.53
Contractors Profit @10% 288.80
Cost for 15 cum 3176.83
Labour Rate per cum 212.00
2.11 Case Using Batching Plant, Transit Mixer
E (iii) II and Crane/concrete pump
say 3220.00
Labour Rate
Labour 2831.57
Overhead charges @ 5% 141.58
Contractors Profit @10% 297.31
Cost for 120 cum 3270.46
Labour Rate per cum 27.25
Say 27.00
2.11 (iv) Grade M30 PCC
E
Same as Item 2.8(f) excluding
formwork
Case Using Concrete Mixer
I
Per Cum Basic Cost of Labour, 2915.00
Material & Machinery (a+b+c)
d) Overhead charges @ on 145.75
(a+b+c)
e) Contractor's profit @ on 306.08
(a+b+c+d)
Through Rate per cum = (a+b+c+d+e) 3366.83
say 3367.00
Labour Rate
Labour 2750.50
Overhead charges @ 5% 137.53
Contractors Profit @10% 288.80
Cost for 15 cum 3176.83
Labour Rate per cum 211.78
Say 212.00
2.11 Case Using Batching Plant, Transit Mixer
E (iv) II and Crane/concrete pump
say 3251.00
Labour Rate
Labour 2831.57
Overhead charges @ 5% 141.58
Contractors Profit @10% 297.31
Cost for 120 cum 3270.46
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Labour Rate per cum 27.25
Say 27.00
2.11 F Well cap
(i) RCC Grade M20
Case Using Concrete Mixer
I
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.12 4900.00 25088.00
Coarse sand cum 6.75 300.00 2025.00
20 mm Aggregate cum 8.10 460.00 3726.00
10 mm Aggregate cum 5.40 480.00 2592.00
b) Labour
Mate day 0.86 116.67 100.34
Mason day 1.50 211.17 316.76
Mazdoor day 20.00 116.67 2333.40
c) Machinery
Concrete mixer (cap. 0.40/0.28 hour 6.00 200.00 1200.00
cum)
Generator 33 KVA hour 6.00 300.00 1800.00
Form Work @ 4 per cent of a+b+c 1567.26
say 1691.00
Labour Rate
Labour 364.01
Overhead charges @ 5% 18.20
Contractors Profit @10% 38.22
Cost for 1 m 420.43
Labour Rate per Mtr 420.43
Say 420.00
2.12 (ii) Beyond 3m upto 10m depth
A
Rate of sinking = 0.33 m per hour.
a) Labour
Mate day 0.15 116.67 17.50
Sinker day 1.25 116.67 145.84
Sinking helper ( semi-skilled ) day 2.50 116.67 291.68
b) Machinery
Hire & running charges of crane hour 3.00 500.00 1500.00
with grab bucket of 0.75 cum
capacity and accessories
Consumables in sinking @10 per 150.00
cent of (b)
c) Overhead charges @ on (a+b) 105.25
say 2431.00
Labour Rate
Labour 455.02
Overhead charges @ 5% 22.75
Contractors Profit @10% 47.78
Cost for 1 m 525.55
Labour Rate per Mtr 525.55
Say 526.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
2.12 (iii) Beyond 10m upto 20m depth
A
Add 5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
11th m 5% 2553.00
12th m 5% 2681.00
13th m 5% 2815.00
14th m 5% 2956.00
15th m 5% 3104.00
16th m 5% 3259.00
17th m 5% 3422.00
18th m 5% 3593.00
19th m 5% 3773.00
20th m 5% 3962.00
Total Cost from 10m upto 20m 32118.00
Avg Rate per metre 3212.00
Labour Rate
Beyond 10m upto 20m
Add 5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
11th m 5% 552.00
12th m 5% 580.00
13th m 5% 609.00
14th m 5% 639.00
15th m 5% 671.00
16th m 5% 705.00
17th m 5% 740.00
18th m 5% 777.00
19th m 5% 816.00
20th m 5% 857.00
Total Cost from 10m upto 20m 6946.00
Avg Rate per metre 695.00
2.12 (iv) Beyond 20m upto 30 m depth
A
Add 7.5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
Labour Rate
Beyond 30m upto 40 m
Add 10 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
say 2431.00
Labour Rate
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Labour 455.02
Overhead charges @ 5% 22.75
Contractors Profit @10% 47.78
Cost for 1 m 525.55
Labour Rate per Mtr 525.55
Say 526.00
2.12 (ii) Beyond 3m upto 10m depth
B
Rate of sinking = 0.17 m per hour.
a) Labour
Mate day 0.30 116.67 35.00
Sinker day 3.00 116.67 350.01
Sinking helper ( semi-skilled ) day 4.50 116.67 525.02
b) Machinery
Hire & running charges of crane hour 6.00 500.00 3000.00
with grab bucket of 0.75 cum
capacity and accessories.
Air compressor with pneumatic hour 2.00 300.00 600.00
chisel attachment for cutting hard
clay.
Consumables in sinking @ 10 per 360.00
cent of (b)
c) Overhead charges @ on (a+b) 243.50
say 5625.00
Labour Rate
Labour 910.03
Overhead charges @ 5% 45.50
Contractors Profit @10% 95.55
Cost for 1 m 1051.08
Labour Rate per Mtr 1051.08
Say 1051.00
2.12 (iii) Beyond 10 m upto 20 m depth
B
Add 5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
Add for dewatering @ 5 per cent of Including for
cost, if required. dewatering
@ 5% of
cost, if
required
11th m 5% 5906.00 6201.00
12th m 5% 6201.00 6511.00
13th m 5% 6511.00 6837.00
14th m 5% 6837.00 7179.00
15th m 5% 7179.00 7538.00
16th m 5% 7538.00 7915.00
17th m 5% 7915.00 8311.00
18th m 5% 8311.00 8727.00
19th m 5% 8727.00 9163.00
20th m 5% 9163.00 9621.00
Total Cost from 10m upto 20m 74288.00 78003.00
Avg Rate per metre 7429.00 7800.00
Labour Rate
Beyond 10 m upto 20 m
Add 5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
Add for dewatering @ 5 per cent of Including for
cost, if required. dewatering
@ 5% of
cost, if
required
11th m 5% 1103.65 1159.00
12th m 5% 1159.00 1217.00
13th m 5% 1217.00 1278.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
14th m 5% 1278.00 1342.00
15th m 5% 1342.00 1409.00
16th m 5% 1409.00 1479.00
17th m 5% 1479.00 1553.00
18th m 5% 1553.00 1631.00
19th m 5% 1631.00 1713.00
20th m 5% 1713.00 1799.00
Total Cost from 10m upto 20m 13884.65 14580.00
Avg Rate per metre 1388.00 1458.00
Say 2579.00
Labour Rate
Labour 455.02
Overhead charges @ 5% 22.75
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Contractors Profit @10% 47.78
Cost for 1 m 525.55
Labour Rate per metre 525.55
Say 526.00
2.13 (ii) Beyond 3m upto 10m depth
A
Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.18 116.67 21.00
Sinker day 1.50 116.67 175.01
Sinking helper ( semi-skilled ) day 3.00 116.67 350.01
b) Machinery
Hire & running charges of crane hour 4.50 500.00 2250.00
with grab bucket of 0.75 cum
capacity and accessories.
Consumables in sinking @10 per 225.00
cent of (b)
c) Overhead charges @ on (a+b) 151.05
say 3489.00
Labour Rate
Labour 546.02
Overhead charges @ 5% 27.30
Contractors Profit @10% 57.33
Cost for 1 m 630.65
Labour Rate per metre 630.65
Say 631.00
2.13 (iii) Beyond 10m upto 20m depth
A
a Add 5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
11th m 5% 3664.00
12th m 5% 3847.00
13th m 5% 4039.00
14th m 5% 4241.00
15th m 5% 4453.00
16th m 5% 4676.00
17th m 5% 4910.00
18th m 5% 5156.00
19th m 5% 5414.00
20th m 5% 5685.00
Total Cost from 10m upto 20m 46085.00
Avg Rate per metre 4609.00
Labour Rate
Beyond 10m upto 20m
Add 5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
11th m 5% 662.00
12th m 5% 695.00
13th m 5% 730.00
14th m 5% 767.00
15th m 5% 805.00
16th m 5% 845.00
17th m 5% 887.00
18th m 5% 931.00
19th m 5% 978.00
20th m 5% 1027.00
Total Cost from 10m upto 20m 8327.00
Avg Rate per metre 833.00
2.13 (iv) Beyond 20m upto 30 m depth
A
a Add 7.5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
b Add 20 per cent of cost for Kentledge Including
including supports, loading 20% for
arrangement and Labour). Kentledge
21st m 7.5% 6111.00 7333.00
22nd m 7.5% 6569.00 7883.00
23rd m 7.5% 7062.00 8474.00
24th m 7.5% 7592.00 9110.00
25th m 7.5% 8161.00 9793.00
26th m 7.5% 8773.00 10528.00
27th m 7.5% 9431.00 11317.00
28th m 7.5% 10138.00 12166.00
29th m 7.5% 10898.00 13078.00
30th m 7.5% 11715.00 14058.00
Total Cost from 20m upto 30m 86450.00 103740.00
8645.00 10374.00
Labour Rate
Beyond 20m upto 30 m
Add 7.5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
say 3489.00
Labour Rate
Labour 546.02
Overhead charges @ 5% 27.30
Contractors Profit @10% 57.33
Cost for 1 m 630.65
Labour Rate per metre 630.65
Say 631.00
2.13 (ii) Beyond 3m upto 10m depth
B
Rate of sinking = 0.17 m per hour.
a) Labour
Mate day 0.26 116.67 30.33
Sinker day 2.00 116.67 233.34
Sinking helper ( semi-skilled ) day 4.00 116.67 466.68
b) Machinery
Hire & running charges of crane hour 6.00 500.00 3000.00
with grab bucket of 0.75 cum
capacity and accessories.
Air compressor with pneumatic hour 3.25 300.00 300.00
chisel attachment for cutting hard
clay.
Consumables in sinking @ 10 per 330.00
cent of (b)
c) Overhead charges @ on (a+b) 218.02
say 5036.00
Labour Rate
Labour 730.35
Overhead charges @ 5% 36.52
Contractors Profit @10% 76.69
Cost for 1 m 843.55
Labour Rate per metre 843.55
Say 844.00
2.13 (iii) Beyond 10 m upto 20 m depth
B
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
a Add 5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
b Add for dewatering @ 5 per cent of Including for
cost, if required. dewatering
@ 5% of
cost, if
required
11th m 5% 5288.00 5552.00
12th m 5% 5552.00 5830.00
13th m 5% 5830.00 6122.00
14th m 5% 6122.00 6428.00
15th m 5% 6428.00 6749.00
16th m 5% 6749.00 7086.00
17th m 5% 7086.00 7440.00
18th m 5% 7440.00 7812.00
19th m 5% 7812.00 8203.00
20th m 5% 8203.00 8613.00
Total Cost from 10m upto 20m 66510.00 69835.00
Avg Rate per metre 6651.00 6984.00
Labour Rate
Beyond 10 m upto 20 m
a Add 5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
b Add for dewatering @ 5 per cent of Including for
cost, if required. dewatering
@ 5% of
cost, if
required
11th m 5% 885.73 930.00
12th m 5% 930.00 977.00
13th m 5% 977.00 1026.00
14th m 5% 1026.00 1077.00
15th m 5% 1077.00 1131.00
16th m 5% 1131.00 1188.00
17th m 5% 1188.00 1247.00
18th m 5% 1247.00 1309.00
19th m 5% 1309.00 1374.00
20th m 5% 1374.00 1443.00
Total Cost from 10m upto 20m 11144.73 11702.00
Avg Rate per metre 1114.00 1170.00
2.13 (iv) Beyond 20m upto 30 m depth
B
a Add 7.5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
Labour Rate
Beyond 20m upto 30 m
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
a Add 7.5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
say 6690.00
Labour Rate
Labour 1820.05
Overhead charges @ 5% 91.00
Contractors Profit @10% 191.11
Cost for 1 m 2102.16
Labour Rate per metre 2102.16
Say 2102.00
2.13 D Hard Rock ( 7m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in Hard rock strata up to 3 m
Rate of sinking = 0.17 m per hour.
a) Material
Gelatine 80 per cent Kg 7.00 75.00 525.00
Electric Detonators each 30.00 7.00 210.00
b) Labour
Mate day 1.60 116.67 186.67
Driller day 2.00 116.67 233.34
Blaster day 0.25 158.67 39.67
Mazdoor day 18.00 116.67 2100.06
Mazdoor (Skilled) day 4.00 116.67 466.68
Diver day 0.50 158.67 79.34
c) Machinery
Hire & running charges of crane hour 6.00 500.00 3000.00
with grab bucket of 0.75 cum
capacity and accessories.
Hire & running charges of hour 2.00 300.00 600.00
compressor with pneumatic
breaker/Jack hammer for drilling.
say 3172.00
Labour Rate
Labour 546.02
Overhead charges @ 5% 27.30
Contractors Profit @10% 57.33
Cost for 1 m 630.65
Labour Rate per metre 630.65
Say 631.00
2.14 (ii) Beyond 3m upto 10m depth
A
Rate of sinking @ 0.20 m/hour
a) Labour
Mate day 0.25 116.67 29.17
Sinker day 1.75 116.67 204.17
Sinking helper ( semi-skilled ) day 3.50 116.67 408.35
b) Machinery
Hire & running charges of crane hour 5.00 500.00 2500.00
with grab bucket of 0.75 cum
capacity and accessories.
Consumables in sinking @10 per 250.00
cent of (b)
c) Overhead charges @ on (a+b) 169.58
say 3917.00
Labour Rate
Labour 641.70
Overhead charges @ 5% 32.09
Contractors Profit @10% 67.38
Cost for 1 m 741.16
Labour Rate per metre 741.16
Say 741.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
2.14 (iii) Beyond 10m upto 20m
A
a Add 5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
11th m 5% 4113.00
12th m 5% 4319.00
13th m 5% 4535.00
14th m 5% 4762.00
15th m 5% 5000.00
16th m 5% 5250.00
17th m 5% 5513.00
18th m 5% 5789.00
19th m 5% 6078.00
20th m 5% 6382.00
Total Cost from 10m upto 20m 51741.00
Avg Rate per metre 5174.00
Labour Rate
Beyond 10m upto 20m
Add 5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
11th m 5% 778.00
12th m 5% 817.00
13th m 5% 858.00
14th m 5% 901.00
15th m 5% 946.00
16th m 5% 993.00
17th m 5% 1043.00
18th m 5% 1095.00
19th m 5% 1150.00
20th m 5% 1208.00
Total Cost from 10m upto 20m 9789.00
Avg Rate per metre 979.00
2.14 (iv) Beyond 20m upto 30 m depth
A
a Add 7.5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
say 4265.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Labour Rate
Labour 667.36
Overhead charges @ 5% 33.37
Contractors Profit @10% 70.07
Cost for 1 m 770.80
Labour Rate per metre 770.80
Say 771.00
2.14 (ii) Beyond 3m upto 10m depth
B
Rate of sinking @ 0.17 m/hour
a) Labour
Mate day 0.32 116.67 37.33
Sinker day 2.50 116.67 291.68
Sinking helper ( semi-skilled ) day 4.50 116.67 525.02
b) Machinery
Hire & running charges of crane hour 6.00 500.00 3000.00
with grab bucket of 0.75 cum
capacity and accessories.
Air compressor with pneumatic hour 3.50 300.00 1050.00
chisel attachment for cutting hard
clay.
Consumables in sinking @ 10 per 405.00
cent of (b)
c) Overhead charges @ on (a+b) 265.45
say 6132.00
Labour Rate
Labour 854.03
Overhead charges @ 5% 42.70
Contractors Profit @10% 89.67
Cost for 1 m 986.40
Labour Rate per metre 986.40
Say 986.00
2.14 (iii) Beyond 10 m upto 20 m
B
a Add 5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
b Add for dewatering @ 5 per cent of Including for
cost, if required. dewatering
@ 5% of
cost, if
required
11th m 5% 6439.00 6761.00
12th m 5% 6761.00 7099.00
13th m 5% 7099.00 7454.00
14th m 5% 7454.00 7827.00
15th m 5% 7827.00 8218.00
16th m 5% 8218.00 8629.00
17th m 5% 8629.00 9060.00
18th m 5% 9060.00 9513.00
19th m 5% 9513.00 9989.00
20th m 5% 9989.00 10488.00
Total Cost from 10m upto 20m 80989.00 85038.00
Avg Rate per metre 8099.00 8504.00
Labour Rate
Beyond 10 m upto 20 m
Add 5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
Add for dewatering @ 5 per cent of Including for
cost, if required. dewatering
@ 5% of
cost, if
required
11th m 5% 1036.00 1088.00
12th m 5% 1088.00 1142.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
13th m 5% 1142.00 1199.00
14th m 5% 1199.00 1259.00
15th m 5% 1259.00 1322.00
16th m 5% 1322.00 1388.00
17th m 5% 1388.00 1457.00
18th m 5% 1457.00 1530.00
19th m 5% 1530.00 1607.00
20th m 5% 1607.00 1687.00
Total Cost from 10m upto 20m 13028.00 13679.00
Avg Rate per metre 1303.00 1368.00
2.14 (iv) Beyond 20m upto 30 m
B
a Add 7.5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
Labour Rate
Beyond 30m upto 40 m
Add 10 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
say 7388.00
Labour Rate
Labour 2104.76
Overhead charges @ 5% 105.24
Contractors Profit @10% 221.00
Cost for 1 m 2431.00
Labour Rate per metre 2431.00
Say 2431.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
2.14 D Hard Rock ( 8m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.17 m/hour
a) Material
Gelatine 80 per cent Kg 8.00 75.00 600.00
Electric Detonators each 32.00 7.00 224.00
b) Labour
Mate day 1.09 116.67 127.17
Driller day 2.00 116.67 233.34
Blaster day 0.25 158.67 39.67
Mazdoor day 20.00 116.67 2333.40
Mazdoor (Skilled) day 4.00 116.67 466.68
c) Machinery
Hire & running charges of crane hour 6.00 500.00 3000.00
with grab bucket of 0.75 cum
capacity and accessories.
Hire & running charges of hour 2.00 300.00 600.00
compressor with pneumatic
breaker/Jack hammer for drilling.
say 3207.00
Labour Rate
Labour 576.36
Overhead charges @ 5% 28.82
Contractors Profit @10% 60.52
Cost for 1 m 665.70
Labour Rate per metre ) 665.70
Say 666.00
2.15 (ii) Beyond 3m upto 10m depth
A
Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.27 116.67 31.50
Sinker day 1.75 116.67 204.17
Sinking helper ( semi-skilled ) day 4.00 116.67 466.68
b) Machinery
Hire & running charges of crane hour 5.50 500.00 2750.00
with grab bucket of 0.75 cum
capacity and accessories.
Consumables in sinking @10 per 275.00
cent of (b)
c) Overhead charges @ on (a+b) 186.37
say 4305.00
Labour Rate
Labour 702.35
Overhead charges @ 5% 35.12
Contractors Profit @10% 73.75
Cost for 1 m 811.21
Labour Rate per metre ) 811.00
2.15 (iii) Beyond 10m upto 20m depth
A
a Add 5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
11th m 5% 4520.00
12th m 5% 4746.00
13th m 5% 4983.00
14th m 5% 5232.00
15th m 5% 5494.00
16th m 5% 5769.00
17th m 5% 6057.00
18th m 5% 6360.00
19th m 5% 6678.00
20th m 5% 7012.00
Total Cost from 10m upto 20m 56851.00
Avg Rate per metre 5685.00
Labour Rate
Beyond 10m upto 20m
Add 5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
11th m 5% 852.00
12th m 5% 895.00
13th m 5% 940.00
14th m 5% 987.00
15th m 5% 1036.00
16th m 5% 1088.00
17th m 5% 1142.00
18th m 5% 1199.00
19th m 5% 1259.00
20th m 5% 1322.00
Total Cost from 10m upto 20m 10720.00
Avg Rate per metre 1072.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
2.15 (iv) Beyond 20m upto 30 m depth
A
a Add 7.5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
Labour Rate
Beyond 20m upto 30 m
Add 7.5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
say 4494.00
Labour Rate
Labour 728.02
Overhead charges @ 5% 36.40
Contractors Profit @10% 76.44
Cost for 1 m 840.86
Labour Rate per metre 840.86
Say 841.00
2.15 (ii) Beyond 3m upto 10m depth
B
Rate of sinking 0.15 m / hour
a) Labour
Mate day 0.34 116.67 39.67
Sinker day 2.50 116.67 291.68
Sinking helper ( semi-skilled ) day 5.00 116.67 583.35
b) Machinery
Hire & running charges of crane hour 6.50 500.00 3250.00
with grab bucket of 0.75 cum
capacity and accessories.
Air compressor with pneumatic hour 3.75 300.00 1125.00
chisel attachment for cutting hard
clay.
Consumables in sinking @ 10 per 437.50
cent of (b)
c) Overhead charges @ on (a+b) 286.36
say 6615.00
Labour Rate
Labour 914.70
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Overhead charges @ 5% 45.74
Contractors Profit @10% 96.04
Cost for 1 m 1056.48
Labour Rate per metre 1056.48
Say 1056.00
2.15 (iii) Beyond 10 m upto 20 m depth
B
a Add 5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
b Add for dewatering @ 5 per cent of Including for
cost, if required. dewatering
@ 5% of
cost, if
required
11th m 5% 6946.00 7293.00
12th m 5% 7293.00 7658.00
13th m 5% 7658.00 8041.00
14th m 5% 8041.00 8443.00
15th m 5% 8443.00 8865.00
16th m 5% 8865.00 9308.00
17th m 5% 9308.00 9773.00
18th m 5% 9773.00 10262.00
19th m 5% 10262.00 10775.00
20th m 5% 10775.00 11314.00
Total Cost from 10m upto 20m 87364.00 91732.00
Avg Rate per metre 8736.00 9173.00
Labour Rate
Beyond 10 m upto 20 m
Add 5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
Add for dewatering @ 5 per cent of Including for
cost, if required. dewatering
@ 5% of
cost, if
required
11th m 5% 1109.00 1164.00
12th m 5% 1164.00 1222.00
13th m 5% 1222.00 1283.00
14th m 5% 1283.00 1347.00
15th m 5% 1347.00 1414.00
16th m 5% 1414.00 1485.00
17th m 5% 1485.00 1559.00
18th m 5% 1559.00 1637.00
19th m 5% 1637.00 1719.00
20th m 5% 1719.00 1805.00
Total Cost from 10m upto 20m 13939.00 14635.00
Avg Rate per metre 1394.00 1464.00
2.15 (iv) Beyond 20m upto 30 m depth
B
a Add 7.5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
Labour Rate
Beyond 20m upto 30 m
Add 7.5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
say 8002.00
Labour Rate
Labour 2379.13
Overhead charges @ 5% 118.96
Contractors Profit @10% 249.81
Cost for 1 m 2747.90
Labour Rate per Mtr 2747.90
Say 2748.00
2.15 D Hard Rock ( 9m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.15 m / hour
a) Material
Gelatine 80 per cent Kg 10.00 75.00 750.00
Electric Detonators each 40.00 7.00 280.00
b) Labour
Mate day 1.17 116.67 136.50
Driller day 2.00 116.67 233.34
Blaster day 0.25 158.67 39.67
Mazdoor day 22.00 116.67 2566.74
Mazdoor (Skilled) day 4.00 116.67 466.68
Diver day 1.00 158.67 158.67
c) Machinery
Hire & running charges of crane hour 7.00 500.00 3500.00
with grab bucket of 0.75 cum
capacity and accessories.
Hire & running charges of hour 2.50 300.00 750.00
compressor with pneumatic
breaker/Jack hammer for drilling.
say 3877.00
Labour Rate
Labour 606.69
Overhead charges @ 5% 30.33
Contractors Profit @10% 63.70
Cost for 1 m 700.73
Labour Rate per Mtr 700.73
Say 701.00
2.16 (ii) Beyond 3m upto 10m depth
A
Rate of sinking 0.17 m / hour
a) Labour
Mate day 0.31 116.67 36.17
Sinker day 2.00 116.67 233.34
Sinking helper ( semi-skilled ) day 4.25 116.67 495.85
b) Machinery
Hire & running charges of crane hour 5.75 500.00 2875.00
with grab bucket of 0.75 cum
capacity and accessories.
Consumables in sinking @10 per 287.50
cent of (b)
c) Overhead charges @ on (a+b) 196.39
say 4537.00
Labour Rate
Labour 765.36
Overhead charges @ 5% 38.27
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Contractors Profit @10% 80.36
Cost for 1 m 883.99
Labour Rate per Mtr 883.99
Say 884.00
2.16 (iii) Beyond 10m upto 20m depth
A
a Add 5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
11th m 5% 4764.00
12th m 5% 5002.00
13th m 5% 5252.00
14th m 5% 5515.00
15th m 5% 5791.00
16th m 5% 6081.00
17th m 5% 6385.00
18th m 5% 6704.00
19th m 5% 7039.00
20th m 5% 7391.00
Total Cost from 10m upto 20m 59924.00
Avg Rate per metre 5992.00
Labour Rate
Beyond 10m upto 20m
Add 5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
11th m 5% 928.00
12th m 5% 974.00
13th m 5% 1023.00
14th m 5% 1074.00
15th m 5% 1128.00
16th m 5% 1184.00
17th m 5% 1243.00
18th m 5% 1305.00
19th m 5% 1370.00
20th m 5% 1439.00
Total Cost from 10m upto 20m 11668.00
Avg Rate per metre 1167.00
2.16 (iv) Beyond 20m upto 30 m depth
A
a Add 7.5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
Labour Rate
Beyond 30m upto 40 m
Add 10 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
say 4923.00
Labour Rate
Labour 962.54
Overhead charges @ 5% 48.13
Contractors Profit @10% 101.07
Cost for 1 m 1111.73
Labour Rate per Mtr 1111.73
Say 1112.00
2.16 (ii) Beyond 3m upto 10m depth
B
Rate of sinking 0.15m/hour.
a) Labour
Mate day 0.40 116.67 46.67
Sinker day 3.00 116.67 350.01
Sinking helper ( semi-skilled ) day 5.50 116.67 641.69
b) Machinery
Hire & running charges of crane hour 6.00 500.00 3000.00
with grab bucket of 0.75 cum
capacity and accessories.
Air compressor with pneumatic hour 4.00 300.00 1200.00
chisel attachment for cutting hard
clay
Consumables in sinking @ 10 per 420.00
cent of (b)
c) Overhead charges @ on (a+b) 282.92
say 6535.00
Labour Rate
Labour 1038.37
Overhead charges @ 5% 51.92
Contractors Profit @10% 109.03
Cost for 1 m 1199.32
Labour Rate per Mtr 1199.32
Say 1199.00
2.16 (iii) Beyond 10 m upto 20 m depth
B
a Add 5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
b Add for dewatering @ 5 per cent of Including for
cost, if required. dewatering
@ 5% of
cost, if
required
11th m 5% 6862.00 7205.00
12th m 5% 7205.00 7565.00
13th m 5% 7565.00 7943.00
14th m 5% 7943.00 8340.00
15th m 5% 8340.00 8757.00
16th m 5% 8757.00 9195.00
17th m 5% 9195.00 9655.00
18th m 5% 9655.00 10138.00
19th m 5% 10138.00 10645.00
20th m 5% 10645.00 11177.00
Total Cost from 10m upto 20m 86305.00 90620.00
Avg Rate per metre 8631.00 9062.00
Labour Rate
Beyond 10 m upto 20 m
Add 5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add for dewatering @ 5 per cent of Including for
cost, if required. dewatering
@ 5% of
cost, if
required
11th m 5% 1259.00 1322.00
12th m 5% 1322.00 1388.00
13th m 5% 1388.00 1457.00
14th m 5% 1457.00 1530.00
15th m 5% 1530.00 1607.00
16th m 5% 1607.00 1687.00
17th m 5% 1687.00 1771.00
18th m 5% 1771.00 1860.00
19th m 5% 1860.00 1953.00
20th m 5% 1953.00 2051.00
Total Cost from 10m upto 20m 15834.00 16626.00
Avg Rate per metre 1583.00 1663.00
2.16 (iv) Beyond 20m upto 30 m depth
B
a Add 7.5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
Labour Rate
Beyond 20m upto 30 m
Add 7.5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
say 9438.00
Labour Rate
Labour 2655.88
Overhead charges @ 5% 132.79
Contractors Profit @10% 278.87
Cost for 1 m 3067.54
Labour Rate per Mtr 3067.54
Say 3068.00
2.16 D Hard Rock (10m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.12 m/ hour.
a) Material
Gelatine 80 per cent Kg 11.00 75.00 825.00
Electric Detonators each. 44.00 7.00 308.00
b) Labour
Mate day 1.27 116.67 148.17
Driller day 2.00 116.67 233.34
Blaster day 0.25 158.67 39.67
Mazdoor day 24.00 116.67 2800.08
Mazdoor (Skilled) day 4.00 116.67 466.68
c) Machinery
Hire & running charges of crane hour 8.50 500.00 4250.00
with grab bucket of 0.75 cum
capacity and accessories.
Hire & running charges of hour 3.00 300.00 900.00
compressor with pneumatic
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost 257.50
(c), if required.
Consumables in sinking @ 10 per 909.54
cent of cost of (b+c).
d) Overhead charges @ on 556.90
(a+b+c)
e) Contractor's profit @ on 1169.49
(a+b+c+d)
Rate per metre = (a+b+c+d+e) 12864.37
say 12864.00
Labour Rate
Labour 3687.94
Overhead charges @ 5% 184.40
Contractors Profit @10% 387.23
Cost for 1 m 4259.57
Labour Rate per Mtr 4259.57
Say 4260.00
2.17 1200 Sinking of 11 m external diameter well
( other than pneumatic method of
sinking ) through all types of strata
namely sandy soil, clayey soil and rock
as shown against each case, complete
as per drawing and technical
specifications. Depth of sinking is
reckoned from bed level.
Labour Rate
Beyond 20m upto 30 m
Add 7.5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
Labour Rate
Beyond 30m upto 40 m
Add 10 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
Labour Rate
Beyond 10 m upto 20 m
Add 5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
Add for dewatering @ 5 per cent of Including for
cost, if required. dewatering
@ 5% of
cost, if
required
11th m 5% 1370.00 1439.00
12th m 5% 1439.00 1511.00
13th m 5% 1511.00 1587.00
14th m 5% 1587.00 1666.00
15th m 5% 1666.00 1749.00
16th m 5% 1749.00 1836.00
17th m 5% 1836.00 1928.00
18th m 5% 1928.00 2024.00
19th m 5% 2024.00 2125.00
20th m 5% 2125.00 2231.00
Total Cost from 10m upto 20m 17235.00 18097.00
Avg Rate per metre 1724.00 1810.00
Labour Rate
Beyond 20m upto 30 m
Add 7.5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
Labour Rate
Beyond 30m upto 40 m
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add 10 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
Labour Rate
Beyond 10 m upto 20 m depth
Add 5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
Add for dewatering @ 5 per cent of Including for
cost, if required. dewatering
@ 5% of
cost, if
required
11th m 5% 1447.00 1519.00
12th m 5% 1519.00 1595.00
13th m 5% 1595.00 1675.00
14th m 5% 1675.00 1759.00
15th m 5% 1759.00 1847.00
16th m 5% 1847.00 1939.00
17th m 5% 1939.00 2036.00
18th m 5% 2036.00 2138.00
19th m 5% 2138.00 2245.00
20th m 5% 2245.00 2357.00
Total Cost from 10m upto 20m 18200.00 19110.00
Avg Rate per metre 1820.00 1911.00
2.18 (iv) Beyond 20m upto 30 m depth
B
a Add 7.5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
Labour Rate
Beyond 30m upto 40 m
Add 10 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
say 4195.00
Labour Rate
Labour 606.68
Overhead charges @ 5% 30.33
Contractors Profit @10% 63.70
Cost for 1 m 700.72
Labour Rate per Mtr 700.72
Say 701.00
2.19 (ii) Beyond 3m upto 10m depth
A
Rate of sinking @ 0.17 m/hour
a) Labour
Mate day 0.30 116.67 35.00
Sinker day 1.50 116.67 175.01
Sinking helper (semi-skilled) day 4.00 116.67 466.68
b) Machinery
Hire & running charges of crane hour 5.88 500.00 2940.00
with grab bucket of 0.75 cum
capacity and accessories.
Consumables in sinking @10 per 294.00
cent of (b)
c) Overhead charges @ on (a+b) 195.53
say 4517.00
Labour Rate
Labour 676.69
Overhead charges @ 5% 33.83
Contractors Profit @10% 71.05
Cost for 1 m 781.58
Labour Rate per Mtr 781.58
Say 782.00
2.19 (iii) Beyond10m upto 20m depth
A
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
a Add 5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
11th m 5% 4743.00
12th m 5% 4980.00
13th m 5% 5229.00
14th m 5% 5490.00
15th m 5% 5765.00
16th m 5% 6053.00
17th m 5% 6356.00
18th m 5% 6674.00
19th m 5% 7008.00
20th m 5% 7358.00
Total Cost from 10m upto 20m 59656.00
Avg Rate per metre 5966.00
Labour Rate
Add 5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
11th m 5% 821.00
12th m 5% 862.00
13th m 5% 905.00
14th m 5% 950.00
15th m 5% 998.00
16th m 5% 1048.00
17th m 5% 1100.00
18th m 5% 1155.00
19th m 5% 1213.00
20th m 5% 1274.00
Total Cost from 10m upto 20m 10326.00
Avg Rate per metre 1033.00
2.19 (iv) Beyond 20m upto 30 m deoth
A
a Add 7.5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
say 4881.00
Labour Rate
Labour 788.69
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Overhead charges @ 5% 39.43
Contractors Profit @10% 82.81
Cost for 1 m 910.94
Labour Rate per Mtr 910.94
Say 911.00
2.19 (ii) Beyond 3m upto 10m depth
B
Rate of sinking @ 0.15 m/hour
a) Labour
Mate day 0.45 116.67 52.50
Sinker day 3.25 116.67 379.18
Sinking helper (semi-skilled) day 6.00 116.67 700.02
b) Machinery
Hire & running charges of crane hour 6.67 500.00 3335.00
with grab bucket of 0.75 cum
capacity and accessories.
Air compressor with pneumatic hour 4.50 300.00 1350.00
chisel attachment for cutting hard
clay.
Consumables in sinking @ 10 per 468.50
cent of (b)
c) Overhead charges @ on (a+b) 314.26
say 7259.00
Labour Rate
Labour 1131.70
Overhead charges @ 5% 56.59
Contractors Profit @10% 118.83
Cost for 1 m 1307.11
Labour Rate per Mtr 1307.11
Say 1307.00
2.19 (iii) Beyond 10 m upto 20 m depth
B
a Add 5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
b Add for dewatering @ 5 per cent of Including for
cost, if required. dewatering
@ 5% of
cost, if
required
11th m 5% 7622.00 8003.00
12th m 5% 8003.00 8403.00
13th m 5% 8403.00 8823.00
14th m 5% 8823.00 9264.00
15th m 5% 9264.00 9727.00
16th m 5% 9727.00 10213.00
17th m 5% 10213.00 10724.00
18th m 5% 10724.00 11260.00
19th m 5% 11260.00 11823.00
20th m 5% 11823.00 12414.00
Total Cost from 10m upto 20m 95862.00 100654.00
Avg Rate per metre 9586.00 10065.00
Labour Rate
Beyond 10 m upto 20 m
Add 5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
Add for dewatering @ 5 per cent of Including for
cost, if required. dewatering
@ 5% of
cost, if
required
11th m 5% 1372.00 1441.00
12th m 5% 1441.00 1513.00
13th m 5% 1513.00 1589.00
14th m 5% 1589.00 1668.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
15th m 5% 1668.00 1751.00
16th m 5% 1751.00 1839.00
17th m 5% 1839.00 1931.00
18th m 5% 1931.00 2028.00
19th m 5% 2028.00 2129.00
20th m 5% 2129.00 2235.00
Total Cost from 10m upto 20m 17261.00 18124.00
Avg Rate per metre 1726.00 1812.00
2.19 (iv) Beyond 20m upto 30 m depth
B
a Add 7.5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
Labour Rate
Beyond 20m upto 30 m
Add 7.5 per cent for every additional
meter depth of sinking over the rate of
sinking for the previous meter
say 10976.00
Labour Rate
Labour 2613.42
Overhead charges @ 5% 130.67
Contractors Profit @10% 274.41
Cost for 1 m 3018.50
Labour Rate per Mtr 3018.50
Say 3019.00
2.19 D Hard Rock (Twin D Type Well )
Unit = Running Meter
Taking output = 1 m
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.10 m/hour
a) Material
Geletine80 per cent Kg 10.00 75.00 750.00
Electric detonators each. 40.00 7.00 280.00
b) Labour
Mate day 1.34 116.67 156.34
Driller day 2.00 116.67 233.34
Blaster day 0.25 158.67 39.67
Mazdoor day 25.00 116.67 2916.75
Mazdoor (Skilled) day 4.25 116.67 495.85
c) Machinery
Hire & running charges of crane hour 10.00 500.00 5000.00
with grab bucket of 0.75 cum
capacity and accessories.
Hire & running charges of hour 3.00 300.00 900.00
compressor with pneumatic
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost 487.10
of (b+c), if required.
Consumables in sinking @ 10 per 638.71
cent of (b).
d) Overhead charges @ on 594.89
(a+b+c)
e) Contractor's profit @ on 1249.26
(a+b+c+d)
Through Rate per metre = 13741.90
(a+b+c+d+e)
say 13742.00
Labour Rate
Labour 3841.95
Overhead charges @ 5% 192.10
Contractors Profit @10% 403.40
Cost for 1 m 4437.45
Labour Rate per Mtr 4437.45
Say 4437.00
2.20 1200 Pneumatic sinking of wells with
equipment of approved design,
drawing and specifications worked by
competent and trained personnel and
comprising of compression and
decompression chambers, reducers,
two air locks separately for men and
plant & materials, arrangement for
supply of fresh air to working
chambers, check valves, exhaust
valves, shafts made from steel plates
of riveted construction not less than 6
mm thick to withstand an air pressure
of 0.50 MPa, controlled blasting of
hard rock where required, staircases
and 1 m wide landing plateforms with
railing, arrangement for compression
and decompression, electric lighting of
50 V maximum, proper rooms for rest
and medical examinations and
compliance with safety precautions as
per IS:4138, all as per clause1207.6 of
MoRTH Specifications.
Unit - 1 cum
Taking output = 5 cum
a) Material
M35 grade RCC corbel provided Cum 8.00 2909.00 23272.00
for supporting of equipment
(Dimensions as per ground
conditions). Rate may be adopted
vide Item 2.8 (H)
HYSD bar reinforcement in corbel tonne 0.48 45000.00 21600.00
Blasting material
Gelatine 80 per cent Kg 1.50 75.00 112.50
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Electric detonators each 6.00 7.00 42.00
b) Labour
Medical Officer day 0.50 1000.00 500.00
Para medical personnel day 1.00 500.00 500.00
Mate day 1.86 116.67 217.01
Driller day 1.00 116.67 116.67
Blaster day 0.50 158.67 79.34
Mazdoor (for cutting, blasting, day 30.00 116.67 3500.10
cleaning, removal of Material etc.)
Unit = 1 cum
Taking output = 1 cum
a) Material
Sand (assuming 20 per cent voids cum 1.20 300.00 360.00
)
b) Labour
Mate day 0.01 116.67 1.17
Mazdoor day 0.30 116.67 35.00
c) Overhead charges @ on (a+b) 19.81
say 458.00
Labour Rate
Labour 36.17
Overhead charges @ 5% 1.81
Contractors Profit @10% 3.80
Cost for 1 cum 41.78
Labour Rate per cum 41.78
Say 42.00
2.2 1200 Providing Steel Liner 10 mm thick for
& Curbs and 6 mm thick for Steining of
1900 Wells including Fabricating and Setting
out as per Detailed Drawing.
Unit = 1 MT
Taking output = 1 MT
a) Material
i) Structural steel including 5 per tonne 1.05 45000.00 47250.00
cent wastage
b) Labour
Mate day 1.24 116.67 144.67
Fitter day 6.00 148.16 888.96
Blacksmith day 5.00 148.17 740.85
Welder day 5.00 186.67 933.35
Mazdoor day 10.00 116.67 1166.70
Electrodes, cutting gas and other 2362.50
consumables @ 5 per cent on
cost a (a) above.
c) Overhead charges @ on (a+b) 2674.35
say 61778.00
Labour Rate
Labour 4110.78
Overhead charges @ 5% 205.54
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Contractors Profit @10% 431.63
Cost for 1 T 4747.95
Labour Rate per MT 4747.95
Say 4748.00
2.23 1100 Bored cast-in-situ M35 grade R.C.C.
& Pile excluding Reinforcement
1700 complete as per Drawing and
Technical Specifications and removal
of excavated earth with all lifts and
lead upto 1000 m.
Pile diameter-750 mm
Unit = meter
Taking output = 15 m
a) Materials
PCC Grade M35 cum 6.62 3625.00 23997.50
Rate for concrete may be adopted
same as for bottom plug vide item no.
2.11( C ) (IV)
Concrete to be cast with a tremie pipe
200mm dia.
b) Machinery( for boring and
construction )
Hire and running charges of hour 6.00 4500.00 27000.00
hydraulic piling rig with power unit
and complete accessories
including shifting from one bore
location to another.
Hire and running charges of light hour 0.50 300.00 150.00
crane for lowering reinforcement
cage
Hire and running charges of hour 6.00 Rate
Bentonite pump included in
piling rig
Loader I cum bucket capacity. hour 0.30 787.00 236.10
Tipper 5.5 cum capacity for hour 0.30 275.00 82.50
disposal of muck from pile bore
hole
Bentonite kg 300.00 175.00 52500.00
c) Labour
Mate/Supervisor day 0.14 116.67 16.33
Mazdoor day 3.50 116.67 408.35
d) Overhead charges @ on (b+c) 4019.66
Pile diameter-1000 mm
Unit = meter
Taking output = 10 m
a) Materials
PCC Grade M35 cum 7.85 3625.00 28456.25
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Rate for concrete may be adopted
same as for bottom plug vide item no.
2.11( C ) (IV)
Concrete to be cast with a tremie pipe
200mm dia.
b) Machinery( for boring and
construction )
Hire and running charges of hour 6.00 4500.00 27000.00
hydraulic piling rig with power unit
and complete accessories
including shifting from one bore
location to another.
Hire and running charges of light hour 0.50 300.00 150.00
crane for lowering reinforcement
cage
Hire and running charges of hour 6.00 Rate
Bentonite pump included in
piling rig
Loader I cum bucket capacity. hour 0.40 787.00 314.80
Tipper 5.5 cum capacity for hour 0.40 275.00 110.00
disposal of muck from pile bore
hole
Bentonite kg 350.00 175.00 61250.00
c) Labour
Mate/Supervisor day 0.16 116.67 18.67
Mazdoor day 4.00 116.67 466.68
d) Overhead charges @ on (b+c) 4465.51
Pile diameter-1200 mm
Unit = meter
Taking output = 9 m
a) Materials
PCC Grade M35 cum 10.17 3625.00 36866.25
Rate for concrete may be adopted
same as for bottom plug vide item no.
2.11( C ) (IV)
Concrete to be cast with a tremie pipe
200mm dia.
b) Machinery( for boring and
construction )
Hire and running charges of hour 6.00 4500.00 27000.00
hydraulic piling rig with power unit
and complete accessories
including shifting from one bore
location to another.
Hire and running charges of light hour 0.50 300.00 150.00
crane for lowering reinforcement
cage
Hire and running charges of hour 6.00 Rate
Bentonite pump included in
piling rig
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Loader I cum bucket capacity. hour 0.50 787.00 393.50
Tipper 5.5 cum capacity for hour 0.50 275.00 137.50
disposal of muck from pile bore
hole
Bentonite kg 385.00 175.00 67375.00
c) Labour
Mate/Supervisor day 0.18 116.67 21.00
Mazdoor day 4.50 116.67 525.02
d) Overhead charges @ on (b+c) 4780.10
d) Labour
Mate/Supervisor day 0.12 116.67 14.00
Mazdoor day 3.00 116.67 350.01
e) Overhead charges @ on 1308.20
(b+c+d)
f) Contractor's profit @ on 2747.22
(b+c+d+e)
Cost for 40 m = a+b+c+d+e 94236.93
Through Rate per metre 2355.92
(a+b+c+d+e)/40
say 2356.00
Note 1.The quantity of concrete required to
be removed above the designed top
level of concrete, if any, will be
provided for in the rate analysis.
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
2.In case steel lining is included in the
design for driven cast-in-situ pile and
is planned to be retained, the same
may be included in the rate analysis.
In case the temporary steel casing
used during casting is planned to be
removed, an additional cost @ 0.50
per cent of cost of concrete may be
provided to cover its usage.
Labour Rate
Labour 364.01
Overhead charges @ 5% 18.20
Contractors Profit @10% 38.22
Cost for 40m 420.43
Labour Rate per Mtr 10.51
Say 11.00
2.27 1100 Driven cast-in-place vertical M35
& grade R.C.C. Pile excluding
1700 Reinforcement complete as per
Drawing and & Technical Specification
Hire and running charges for light hour 0.50 300.00 150.00
crane for lowering reinforcement
cage.
d) Labour
Mate/Supervisor day 0.16 116.67 18.67
Mazdoor day 4.00 116.67 466.68
e) Overhead charges @ on 1321.77
(b+c+d)
f) Contractor's profit @ on 2775.71
(b+c+d+e)
Cost for 30 m = a+b+c+d+e 115901.58
Through Rate per metre 3863.39
(a+b+c+d+e)/30
say 3863.00
Note 1.The quantity of concrete required to
be removed above the designed top
level of concrete, if any, will be
provided for in the rate analysis.
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
2.In case steel lining is included in the
design for driven cast-in-situ pile and
is planned to be retained, the same
may be included in the rate analysis.
In case the temporary steel casing
used during casting is planned to be
removed, an additional cost @ 0.50
per cent of cost of concrete may be
provided to cover its usage.
Labour Rate
Labour 485.35
Overhead charges @ 5% 24.27
Contractors Profit @10% 50.96
Cost for 30 m 560.58
Labour Rate per Mtr 18.69
Say 19.00
2.28 1100 Driven cast-in-place vertical M35
& grade R.C.C. Pile excluding
1700 Reinforcement complete as per
Drawing and & Technical Specification
d) Labour
Mate/Supervisor day 0.18 116.67 21.00
Mazdoor day 4.50 116.67 525.02
e) Overhead charges @ on 1317.30
(b+c+d)
f) Contractor's profit @ on 2766.33
(b+c+d+e)
Cost for 20 m = a+b+c+d+e 112390.90
Through Rate per metre 5619.54
(a+b+c+d+e)/20
say 5620.00
Note 1.The quantity of concrete required to
be removed above the designed top
level of concrete, if any, will be
provided for in the rate analysis.
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
2.In case steel lining is included in the
design for driven cast-in-situ pile and
is planned to be retained, the same
may be included in the rate analysis.
In case the temporary steel casing
used during casting is planned to be
removed, an additional cost @ 0.50
per cent of cost of concrete may be
provided to cover its usage.
Labour Rate
Labour 546.02
Overhead charges @ 5% 27.30
Contractors Profit @10% 57.33
Cost for 20m 630.65
Labour Rate per Mtr 31.53
Say 32.00
2.29 1100 Driven precast vertical M35 grade
& R.C.C. Piles excluding Reinforcement
1700 complete as per Drawing and &
Technical Specification
c) Machinery
Crane20 t capacity hour 6.00 600.00 3600.00
Vibrating Pile driving hammer hour 6.00 1500.00 9000.00
complete with power unit and
accessories.
d) Labour
Mate/Supervisor day 0.12 116.67 14.00
Mazdoor day 3.00 116.67 350.01
Add 1 per cent of (a+b+c) for 817.09
carriage of piles from casting yard
to work site and stacking, and
other imponderables during
installation.
e) Overhead charges @ on 2106.55
(b+c+d)
f) Contractor's profit @ on 4423.77
(b+c+d+e)
Cost for 60 m = a+b+c+d+e+f 89420.22
Through Rate per metre 1490.34
(a+b+c+d+e+f)/60
say 1490.00
Note The quantity of concrete required to be
removed above the designed top level
of concrete, if any, will be provided for
in the rate analysis.
Labour Rate
Labour 1181.10
Overhead charges @ 5% 59.06
Contractors Profit @10% 124.02
Cost for 60 m 1364.17
Labour Rate per Mtr 22.74
Say 23.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
2.30 1100 Driven precast vertical M35 grade
& R.C.C. Piles excluding Reinforcement
1700 complete as per Drawing and &
Technical Specification
c) Machinery
Crane 40 T capacity hour 6.00 750.00 4500.00
Vibrating Pile driving hammer hour 6.00 1500.00 9000.00
complete with power unit and
accessories.
d) Labour
Mate/Supervisor day 0.16 116.67 18.67
Mazdoor day 4.00 116.67 466.68
Add 1 per cent of (a+b+c) for 1101.97
carriage of piles from casting yard
to work site and stacking, and
other imponderables during
installation.
e) Overhead charges @ on 1769.37
(b+c+d)
f) Contractor's profit @ on 3715.67
(b+c+d+e)
Cost for 50 m = a+b+c+d+e+f 117269.15
Through Rate per metre 2345.38
(a+b+c+d+e+f)/50
say 2345.00
Note The quantity of concrete required to be
removed above the designed top level
of concrete, if any, will be provided for
in the rate analysis.
Labour Rate
Labour 1587.32
Overhead charges @ 5% 79.37
Contractors Profit @10% 166.67
Cost for 50 m 1833.35
Labour Rate per Mtr 36.67
Say 37.00
2.31 1100 Driven precast vertical M35 grade
& R.C.C. Piles excluding Reinforcement
1700 complete as per Drawing and &
Technical Specification
c) Machinery
Crane 10 tonne capacity hour 6.00 500.00 3000.00
Vibrating Pile driving hammer hour 6.00 1500.00 9000.00
complete with power unit and
accessories.
d ) Labour
Mate/Supervisor day 0.12 116.67 14.00
Mazdoor day 3.00 116.67 350.01
Add 1 per cent of (a+b+c) for 590.34
carriage of piles from casting yard
to work site and stacking, and
other imponderables during
installation.
e) Overhead charges @ on 2065.22
(b+c+d)
f) Contractor's profit @ on 4336.96
(b+c+d+e)
Cost for 60 m = a+b+c+d+e+f 66390.52
Through Rate per metre 1106.51
(a+b+c+d+e+f)/60
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
say 1107.00
Note The quantity of concrete required to be
removed above the designed top level
of concrete, if any, will be provided for
in the rate analysis.
Labour Rate
Labour 954.35
Overhead charges @ 5% 47.72
Contractors Profit @10% 100.21
Cost for 60 m 1102.27
Labour Rate per Mtr 18.37
Say 18.00
2.33 1100 Driven precast vertical M35 grade
&170 R.C.C. Piles excluding Reinforcement
0 complete as per Drawing and &
Technical Specification
c) Machinery
Crane 20 tonne capacity hour 6.00 600.00 3600.00
Vibrating Pile driving hammer hour 6.00 1500.00 9000.00
complete with power unit and
accessories.
d ) Labour
Mate/Supervisor day 0.16 116.67 18.67
Mazdoor day 4.00 116.67 466.68
Add 1 per cent of (a+b+c) for 754.50
carriage of piles from casting yard
to work site and stacking, and
other imponderables during
installation.
e) Overhead charges @ on 1671.99
(b+c+d)
f) Contractor's profit @ on 3511.18
(b+c+d+e)
Cost for 50 m = a+b+c+d+e+f 81873.02
Through Rate per metre 1637.46
(a+b+c+d+e+f)/50
say 1637.00
Note The quantity of concrete required to be
removed above the designed top level
of concrete, if any, will be provided for
in the rate analysis.
Labour Rate
Labour 1239.85
Overhead charges @ 5% 61.99
Contractors Profit @10% 130.18
Cost for 50 m 1432.03
Labour Rate per Mtr 28.64
Say 29.00
2.34 1100 Driven precast vertical M35 grade
&170 R.C.C. Piles excluding Reinforcement
0 complete as per Drawing and &
Technical Specification
c) Machinery
Crane 20 tonne capacity hour 6.00 600.00 3600.00
Vibrating Pile driving hammer hour 6.00 1500.00 9000.00
complete with power unit and
accessories.
d ) Labour
Mate/Supervisor day 0.18 116.67 21.00
Mazdoor day 4.50 116.67 525.02
Add 1 per cent of (a+b+c) for 1100.50
carriage of piles from casting yard
to work site and stacking, and
other imponderables during
installation.
e) Overhead charges @ on 1692.33
(b+c+d)
f) Contractor's profit @ on 3553.88
(b+c+d+e)
Cost for 40 m = a+b+c+d+e+f 116942.73
Through Rate per metre 2923.57
(a+b+c+d+e+f)/40
say 2924.00
Note The quantity of concrete required to be
removed above the designed top level
of concrete, if any, will be provided for
in the rate analysis.
Labour Rate
Labour 1646.52
Overhead charges @ 5% 82.33
Contractors Profit @10% 172.88
Cost for 40 m 1901.73
Labour Rate per Mtr 47.54
Say 48.00
2.35 1100, Driven Vertical Steel Piles complete as
1900 per Drawing and & Technical
Specification
Section of the pile - H Section steel
column 400 x 250 mm (ISHB Series)
Unit = 1 MT
Taking output = 1 MT
a) Initial and routine load test tonne 1.00 300.00 300.00
b) Lateral load test tonne 1.00 5000.00 5000.00
Note Although, this item is incidental to work
and is not required to be included in
BOQ of contract, the same is required
to be added in the estimate to assess
cost of work.
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
2.38 1100, Cement Concrete for Reinforced
1500 Concrete in Pile Cap complete as per
&170 Drawing and Technical Specification
0
c) Machinery
Concrete mixer (cap. 0.40/0.28 hour 6.00 200.00 1200.00
cum)
Generator (capacity 33 KVA) hour 6.00 300.00 1800.00
Formwork @ 4 per cent on cost 1568.96
of concrete i.e. cost of a)
Material, b) Labour and c)
Machinery
d) Overhead charges @ on 2039.65
(a+b+c)
e) Contractor's profit @ on 4283.27
(a+b+c+d)
Cost for 15 cum = a+b+c+d+e 47115.96
Through Rate per metre 3141.06
(a+b+c+d+e)/15
say 3141.00
Labour Rate
Labour 2793.08
Overhead charges @ 5% 139.65
Contractors Profit @10% 293.27
Cost for 15cum 3226.01
Labour Rate per cum 215.07
Say 215.00
Using Batching Plant, Transit Mixer
2.38A and Concrete Pump
(ii) a) Material
Cement tonne 5.12 4900.00 25088.00
Coarse sand cum 6.75 300.00 2025.00
20 mm Aggregate cum 8.10 460.00 3726.00
10 mm Aggregate cum 5.40 480.00 2592.00
b) Labour
Mate day 0.16 116.67 18.67
Mason day 0.38 158.67 60.29
Mazdoor for concreting day 2.50 116.67 291.68
Mazdoor for breaking pile head, day 1.00 116.67 116.67
bending bars, cleaning etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1840.00 1380.00
Generator 100 KVA hour 0.75 450.00 337.50
Loader (capacity 1 cum) hour 0.75 787.00 590.25
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 770.00 1540.00
Lead beyond 1 Km, L - lead in tonne.k 37.5L 0.00 0.00
Kilometer m
Concrete Pump hour 0.75 210.00 157.50
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Formwork @ 4 per cent on cost 1516.94
of concrete i.e. cost of a)
Material, b) Labour and c)
Machinery
d) Overhead charges @ on 1972.02
(a+b+c)
e) Contractor's profit @ on 4141.25
(a+b+c+d)
Cost for 15 cum = a+b+c+d+e 45553.78
Through Rate per metre 3036.92
(a+b+c+d+e)/15
say 3037.00
Note The value of a, b and c may be taken
as applicable i.e. either using concrete
mixer or batching plant.
Labour Rate
Labour 487.31
Overhead charges @ 5% 24.37
Contractors Profit @10% 51.17
Cost for 15cum 562.84
Labour Rate per cum 37.52
Say 38.00
2.38 B RCC Grade M25
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement tonne 5.99 4900.00 29351.00
Coarse sand cum 6.75 300.00 2025.00
20 mm Aggregate cum 8.10 460.00 3726.00
10 mm Aggregate cum 5.40 480.00 2592.00
b) Labour
Mate day 0.90 116.67 105.00
Mason day 1.50 158.67 238.01
Mazdoor for concreting day 20.00 116.67 2333.40
Mazdoor for breaking pile head, day 1.00 116.67 116.67
bending bars, cleaning etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 hour 6.00 200.00 1200.00
cum)
Generator (capacity 33 KVA) hour 6.00 300.00 1800.00
Formwork @ 4 per cent on cost 1739.48
of concrete i.e. cost of a)
Material, b) Labour and c)
Machinery
d) Overhead charges @ on 2261.33
(a+b+c)
e) Contractor's profit @ on 4748.79
(a+b+c+d)
Cost for 15 cum = a+b+c+d+e 52236.68
Through Rate per metre 3482.45
(a+b+c+d+e)/15
say 3482.00
Labour Rate
Labour 2793.08
Overhead charges @ 5% 139.65
Contractors Profit @10% 293.27
Cost for 15cum 3226.01
Labour Rate per cum 215.07
Say 215.00
2.38B Using Batching Plant, Transit Mixer
and Concrete Pump
(ii) a) Material
Cement tonne 5.99 4900.00 29351.00
Coarse sand cum 6.75 300.00 2025.00
20 mm Aggregate cum 8.10 460.00 3726.00
10 mm Aggregate cum 5.40 480.00 2592.00
b) Labour
Mate day 0.16 116.67 18.67
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Mason day 0.38 158.67 60.29
Mazdoor for concreting day 2.50 116.67 291.68
Mazdoor for breaking pile head, day 1.00 116.67 116.67
bending bars, cleaning etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1840.00 1380.00
Generator 125 KVA hour 0.75 670.00 502.50
Loader (capacity 1 cum) hour 0.75 787.00 590.25
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 770.00 1540.00
Lead beyond 1 Km, L - lead in tonne.k 37.5L 0.00 0.00
Kilometer m
Concrete Pump hour 0.75 210.00 157.50
Formwork @ 4 per cent on cost 1694.06
of concrete i.e. cost of a)
Material, b) Labour and c)
Machinery
d) Overhead charges @ on 2202.28
(a+b+c)
e) Contractor's profit @ on 4624.79
(a+b+c+d)
Cost for 15 cum = a+b+c+d+e 50872.69
Through Rate per metre 3391.51
(a+b+c+d+e)/15
say 3392.00
Note The value of a, b and c may be taken
as applicable i.e. either using concrete
mixer or batching plant.
Labour Rate
Labour 487.31
Overhead charges @ 5% 24.37
Contractors Profit @10% 51.17
Cost for 15cum 562.84
Labour Rate per cum 37.52
Say 38.00
2.38 C RCC Grade M30
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement tonne 6.10 4900.00 29890.00
Coarse sand cum 6.75 300.00 2025.00
20 mm Aggregate cum 8.10 460.00 3726.00
10 mm Aggregate cum 5.40 480.00 2592.00
b) Labour
Mate day 0.90 116.67 105.00
Mason day 1.50 158.67 238.01
Mazdoor for concreting day 20.00 116.67 2333.40
Mazdoor for breaking pile head, day 1.00 116.67 116.67
bending bars, cleaning etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 hour 6.00 200.00 1200.00
cum)
Generator (capacity 33 KVA) hour 6.00 300.00 1800.00
Formwork @ 4 per cent on cost 1761.04
of concrete i.e. cost of a)
Material, b) Labour and c)
Machinery
d) Overhead charges @ on 2289.36
(a+b+c)
e) Contractor's profit @ on 4807.65
(a+b+c+d)
Cost for 15 cum = a+b+c+d+e 52884.12
Through Rate per metre 3525.61
(a+b+c+d+e)/15
say 3526.00
Labour Rate
Labour 2793.08
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Overhead charges @ 5% 139.65
Contractors Profit @10% 293.27
Cost for 15cum 3226.01
Labour Rate per cum 215.07
Say 215.00
(ii) Using Batching Plant, Transit Mixer
2.38C and Concrete Pump
a) Material
Cement tonne 6.10 4900.00 29890.00
Coarse sand cum 6.75 300.00 2025.00
20 mm Aggregate cum 8.10 460.00 3726.00
10 mm Aggregate cum 5.40 480.00 2592.00
b) Labour
Mate day 0.16 116.67 18.67
Mason day 0.38 158.67 60.29
Mazdoor for concreting day 2.50 116.67 291.68
Mazdoor for breaking pile head, day 1.00 116.67 116.67
bending bars, cleaning etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1840.00 1380.00
Generator 100 KVA hour 0.75 450.00 337.50
Loader (capacity 1 cum) hour 0.75 787.00 590.25
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 770.00 1540.00
Lead beyond 1 Km, L - lead in tonne.k 37.5L 0.00 0.00
Kilometer m
Concrete Pump hour 0.75 210.00 157.50
Formwork @ 4 per cent on cost 1709.02
of concrete i.e. cost of a)
Material, b) Labour and c)
Machinery
d) Overhead charges @ on 2221.73
(a+b+c)
e) Contractor's profit @ on 4665.63
(a+b+c+d)
Cost for 15 cum = a+b+c+d+e 51321.94
Through Rate per metre 3421.46
(a+b+c+d+e)/15
say 3421.00
Note The value of a, b and c may be taken
as applicable i.e. either using concrete
mixer or batching plant.
Labour Rate
Labour 487.51
Overhead charges @ 5% 24.38
Contractors Profit @10% 51.19
Cost for 15cum 563.07
Labour Rate per cum 37.54
Say 38.00
12.38 D RCC Grade M35
Unit = cum
Taking output = 15 cum
Using Concrete Mixer
(i) a) Material
Cement tonne 6.33 4900.00 31017.00
Coarse sand cum 6.75 300.00 2025.00
20 mm Aggregate cum 8.10 460.00 3726.00
10 mm Aggregate cum 5.40 480.00 2592.00
b) Labour
Mate day 0.90 116.67 105.00
Mason day 1.50 158.67 238.01
Mazdoor day 20.00 116.67 2333.40
Mazdoor for breaking pile head, day 1.00 116.67 116.67
bending bars, cleaning etc.
c) Machinery
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Concrete mixer (cap. 0.40/0.28 hour 6.00 200.00 1200.00
cum)
Generator (capacity 33 KVA) hour 6.00 300.00 1800.00
Formwork @ 4 per cent on cost 1806.12
of concrete i.e. cost of a)
Material, b) Labour and c)
Machinery
d) Overhead charges @ on 2347.96
(a+b+c)
e) Contractor's profit @ on 4930.72
(a+b+c+d)
Cost for 15 cum = a+b+c+d+e 54237.88
Through Rate per metre 3615.86
(a+b+c+d+e)/15
say 3616.00
Labour Rate
Labour 2793.08
Overhead charges @ 5% 139.65
Contractors Profit @10% 293.27
Cost for 15cum 3226.01
Labour Rate per cum 215.07
Say 215.00
(ii) Using Batching Plant, Transit Mixer
'2.38D and Concrete Pump
a) Material
Cement tonne 6.33 4900.00 31017.00
Coarse sand cum 6.75 300.00 2025.00
20 mm Aggregate cum 8.10 460.00 3726.00
10 mm Aggregate cum 5.40 480.00 2592.00
b) Labour
Mate day 0.16 116.67 18.67
Mason day 0.38 158.67 60.29
Mazdoor for concreting day 2.50 116.67 291.68
Mazdoor for breaking pile head, day 1.00 116.67 116.67
bending bars, cleaning etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1840.00 1380.00
Generator 125 KVA hour 0.75 670.00 502.50
Loader (capacity 1 cum) hour 0.75 787.00 590.25
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 770.00 1540.00
Lead beyond 1 Km, L - lead in tonne.k 37.5L 0.00 0.00
Kilometer m
Concrete Pump hour 0.75 210.00 157.50
Formwork @ 4 per cent on cost 1760.70
of concrete i.e. cost of a) Material,
b) Labour and c) Machinery
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including5 per cent tonne 1.05 45000.00 47250.00
overlaps and wastage
Binding wire Kg 6.00 50.00 300.00
b) Labour for cutting, bending,
shifting to site, tying and placing in
position
Mate day 0.40 116.67 46.67
Blacksmith day 2.00 186.67 373.34
Mazdoor day 6.00 116.67 700.02
c) Overhead charges @ on (a+b) 2433.50
say 56214.00
Labour Rate
Labour 1120.03
Overhead charges @ 5% 56.00
Contractors Profit @10% 117.60
Cost for 1MT 1293.63
Labour Rate per MT 1293.63
Say 1294.00
2.41 1600 Supplying, fitting and placing un-
coated Mild steel reinforcement
complete in foundation as per drawing
and technical specification
Unit = 1 MT
Taking output = 1 MT
a) Material
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
MS bars including 5 per cent tonne 1.05 40000.00 42000.00
overlaps and wastage
Binding wire Kg 6.00 50.00 300.00
b) Labour for straightening, cutting,
bending, shifting to site, tying and
placing in position
Mate day 0.43 116.67 50.17
Blacksmith day 2.25 186.67 420.01
Mazdoor day 6.50 116.67 758.36
c) Overhead charges @ on (a+b) 2176.43
say 50275.00
Labour Rate
Labour 1228.54
Overhead charges @ 5% 61.43
Contractors Profit @10% 129.00
Cost for 1MT 1418.96
Labour Rate per MT 1418.96
Say 1419.00
CHAPTER-3
SUB-STRUCTURE
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
3.1 1300 Brick masonry work in 1:3 in sub-structure
& complete excluding pointing and plastering,
2200 as per drawing and Technical
Specifications
Unit = cum
Taking output = 1 cum
a) Material
Bricks Ist class each 500.00 3.00 1500.00
Cement mortar 1:3 (Rate as in Item 2.6 cum 0.24 2924.00 701.76
A sub-analysis)
b) Labour
Mate day 0.06 116.67 7.00
Mason day 0.80 211.17 168.94
Mazdoor day 0.80 116.67 93.34
Add for scaffolding @ 5 per cent of 123.55
cost of material and labour
c) Overhead charges @ on (a+b) 129.73
d) Contractor's profit @ on (a+b+c) 272.43
Rate per cum (a+b+c+d) 2996.74
say 2997.00
Labour Rate
Labour for masonary 269.28
Labour for mortar cum 0.24 109.67 26.32
Add for scaffolding @ 5 per cent of 13.46
cost labour
Overhead charges @ 5% 15.45
Overhead charges @ 10% 32.45
Cost for 1 cum 440.32
Rate per cum 440.32
Say 440.00
3.2 1300 Pointing with cement mortar (1:3 ) on brick
& work in substructure as per Technical
2200 Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item 2.6 cum 0.03 2924.00 87.72
)
b) Labour
Mate day 0.04 116.67 4.67
Mason day 0.50 211.17 105.59
Mazdoor day 0.50 116.67 58.34
c) Overhead charges @ on (a+b) 12.82
d) Contractor's profit @ on (a+b+c) 26.91
Rate per 10 sqm (a+b+c+d) 296.03
Page 1
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
say 296.00
Note Scaffolding is already included in item 3.1
Labour Rate
Labour 168.60
Labour for mortor cum 0.03 109.67 3.29
Overhead charges @ 5% 8.59
Contractors Profit @10% 18.05
Cost for 10 Sqm 198.53
Rate perSqm 198.53
Say 199.00
3.3 1300 Plastering with cement mortar (1:3 ) on
& brick work in sub-structure as per Technical
2200 Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item cum 0.144 2924.00 421.06
2.6)
b) Labour
Mate day 0.04 116.67 4.67
Mason day 0.50 211.17 105.59
Mazdoor day 0.50 116.67 58.34
c) Overhead charges @ on (a+b) 29.48
d) Contractor's profit @ on (a+b+c) 61.91
Rate per 10 sqm (a+b+c+d) 681.04
say 681.00
Note 1.Scaffolding is already included in item no.
3.1
2.The number of masons and Mazdoors
already catered in the cement mortar have
been taken into account while providing
these categories in brick masonry, pointing
and plastering.
Labour Rate
Labour 168.60
Labour for mortor cum 0.144 109.67 15.79
Overhead charges @ 5% 9.22
Contractors Profit @10% 19.36
Cost for 10 Sqm 212.97
Rate per 10Sqm 212.97
Say 213.00
3.4 1400 Stone masonry work in cement mortar 1:3
& for substructure complete as per drawing
2200 and Technical Specifications
Page 2
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
A Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.00 400.00 400.00
Through and bond stone No 7.00 10.00 70.00
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.10 400.00 440.00
Through and bond stone each 7.00 10.00 70.00
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Page 3
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
c) Overhead charges @ on (a+b) 99.38
d) Contractor's profit @ on (a+b+c) 208.70
Rate per cum (a+b+c+d) 2295.69
say 2296.00
Labour Rate
Labour 505.77
Labour for mortor 0.30 109.67 32.90
Overhead charges @ 5% 26.93
Contractors Profit @10% 56.56
Cost for I Cum 622.17
Cost for I Cum 622.17
Say 622.00
3.4 C Ashlar masonry ( first sort )
Plain ashlar
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.11 500.00 555.00
Through and bond stone each 7.00 10.00 70.00
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Page 4
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
3.5 1500, Plain/Reinforced cement concrete in sub-
1700 structure complete as per drawing and
& Technical Specifications
2200
Unit = cum
Taking output = 1 cum
A PCC Grade M15
(p) Height upto 5m
Same as Item 2.8 (A) upto 5 m height,
except for formwork which shall be 10 per
cent instead of 4 per cent of cost of
material, labour and machinery.
Per Cum Basic Cost of Labour, Material & 2293.00
Machinery (a+b+c) of Item 2.8 (A)
d) formwork
Add 10 per cent of cost of material, 10.00 229.30
labour and machinery (a+b+c) for
Formwork
e) Overhead charges @ on (a+b+c+d) 126.12
d) formwork
Add 10 per cent of cost of material, 10.00 261.50
labour and machinery (a+b+c) for
Formwork
e) Overhead charges @ on (a+b+c+d) 143.83
Page 5
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
f) Contractor's profit @ on (a+b+c+d+e) 302.03
d) formwork
Add 10 per cent of cost of material, 10.00 288.60
labour and machinery (a+b+c) for
Formwork
e) Overhead charges @ on (a+b+c+d) 158.73
d) formwork
Page 6
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add 10 per cent of cost of material, 10.00 278.80
labour and machinery (a+b+c) for
Formwork
e) Overhead charges @ on (a+b+c+d) 153.34
d) formwork
Add 12 per cent of cost of material, 12.00 343.92
labour and machinery (a+b+c) for
Formwork
Add 2 per cent of cost of material, 2.00 57.32
Labour and machinery excluding
formwork to cater for extra lift
e) Overhead charges @ on (a+b+c+d) 163.36
Page 7
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Cost for 1 cum 211.79
Rate per cum 211.79
Say 212.00
3.5 C Case With Batching Plant, Transit Mixer and
(q) II Concrete Pump
Per Cum Basic Cost of Labour, Material & 2788.00
Machinery (a+b+c) of Item 2.8 (D) Case II
d) formwork
Add 12 per cent of cost of material, 12.00 334.56
labour and machinery (a+b+c) for
Formwork
Add 2 per cent of cost of material, 2.00 55.76
Labour and machinery excluding
formwork to cater for extra lift
e) Overhead charges @ on (a+b+c+d) 158.92
d) formwork
Add 15 per cent of cost of material, 15.00 429.90
labour and machinery (a+b+c) for
Formwork
Page 8
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add 4 per cent of cost of material, 4.00 114.64
Labour and machinery excluding
formwork to cater for extra lift
e) Overhead charges @ on (a+b+c+d) 170.53
d) formwork
Add 15 per cent of cost of material, 15.00 418.20
labour and machinery (a+b+c) for
Formwork
Add 4 per cent of cost of material, 4.00 111.52
Labour and machinery excluding
formwork to cater for extra lift
e) Overhead charges @ on (a+b+c+d) 0.00
Page 9
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Same as Item 2.8 (F) upto 5 m height with
the only change that the provision of form
work shall be 10 per cent instead of 3.50
per cent of cost of material, labour and
machinery.
Case I Using concrete Mixer
d) formwork
Add 10 per cent of cost of material, 10.00 291.50
labour and machinery (a+b+c) for
Formwork
e) Overhead charges @ on (a+b+c+d) 160.33
d) formwork
Add 10 per cent of cost of material, 10.00 281.50
labour and machinery (a+b+c) for
Formwork
e) Overhead charges @ on (a+b+c+d) 154.83
Page 10
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Rate per cum 27.26
say 27.00
3.5 D (q) Height 5m to 10m
Same as Item 2.8 (F) with the following
changes: (i) Add 2 per cent of cost of
material, Labour and machinery excluding
form work to cater for extra lift. (ii) The
provision of form work shall be 12 per cent
instead of 3.50 per cent of cost of
material, labour and machinery.
d) formwork
Add 12 per cent of cost of material, 12.00 349.80
labour and machinery (a+b+c) for
Formwork
Add 2 per cent of cost of material, 2.00 58.30
Labour and machinery excluding
formwork to cater for extra lift
e) Overhead charges @ on (a+b+c+d) 166.16
d) formwork
Add 12 per cent of cost of material, 12.00 337.80
labour and machinery (a+b+c) for
Formwork
Page 11
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add 2 per cent of cost of material, 2.00 56.30
Labour and machinery excluding
formwork to cater for extra lift
e) Overhead charges @ on (a+b+c+d) 160.46
d) formwork
Add 15 per cent of cost of material, 15.00 437.25
labour and machinery (a+b+c) for
Formwork
Add 4 per cent of cost of material, 4.00 116.60
Labour and machinery excluding
formwork to cater for extra lift
e) Overhead charges @ on (a+b+c+d) 173.44
Page 12
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Cost for 1 cum 211.79
Rate per cum 211.79
Say 212.00
3.5 D Case With Batching Plant, Transit Mixer and
(r) II Concrete Pump
Per Cum Basic Cost of Labour, Material & 2815.00
Machinery (a+b+c) of Item 2.8 (F) Case II
d) formwork
Add 15 per cent of cost of material, 15.00 422.25
labour and machinery (a+b+c) for
Formwork
Add 4 per cent of cost of material, 4.00 112.60
Labour and machinery excluding
formwork to cater for extra lift
e) Overhead charges @ on (a+b+c+d) 194.29
d) formwork
Add 10 per cent of cost of material, 10.00 264.20
labour and machinery (a+b+c) for
Formwork
e) Overhead charges @ on (a+b+c+d) 145.31
Page 13
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
f) Contractor's profit @ on (a+b+c+d+e) 305.15
d) formwork
Add 10 per cent of cost of material, 10.00 254.20
labour and machinery (a+b+c) for
Formwork
e) Overhead charges @ on (a+b+c+d) 139.81
d) formwork
Page 14
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add 12 per cent of cost of material, 12.00 317.04
labour and machinery (a+b+c) for
Formwork
Add 2 per cent of cost of material, 2.00 52.84
Labour and machinery excluding
formwork to cater for extra lift
e) Overhead charges @ on (a+b+c+d) 150.59
d) formwork
Add 12 per cent of cost of material, 12.00 305.04
labour and machinery (a+b+c) for
Formwork
Add 2 per cent of cost of material, 2.00 50.84
Labour and machinery excluding
formwork to cater for extra lift
e) Overhead charges @ on (a+b+c+d) 144.89
Page 15
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Same as Item 2.8 (C) with the following
changes: (i) Add 4 per cent of cost of
material, labour and machinery excluding
form work to cater for extra lift. (ii) The
provision of form work shall be 15 per cent
instead of 4 per cent of cost of material,
labour and machinery.
d) formwork
Add 15 per cent of cost of material, 15.00 396.30
labour and machinery (a+b+c) for
Formwork
Add 4 per cent of cost of material, 4.00 105.68
Labour and machinery excluding
formwork to cater for extra lift
e) Overhead charges @ on (a+b+c+d) 157.20
d) formwork
Add 15 per cent of cost of material, 15.00 381.30
labour and machinery (a+b+c) for
Formwork
Add 4 per cent of cost of material, 4.00 101.68
Labour and machinery excluding
formwork to cater for extra lift
e) Overhead charges @ on (a+b+c+d) 151.25
Page 16
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
f) Contractor's profit @ on (a+b+c+d+e) 317.62
d) formwork
Add 10 per cent of cost of material, 10.00 291.60
labour and machinery (a+b+c) for
Formwork
e) Overhead charges @ on (a+b+c+d) 160.38
d) formwork
Page 17
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add 10 per cent of cost of material, 10.00 281.60
labour and machinery (a+b+c) for
Formwork
e) Overhead charges @ on (a+b+c+d) 154.88
d) formwork
Add 11.8 per cent of cost of material, 11.80 344.09
labour and machinery (a+b+c) for
Formwork
Add 1.8 per cent of cost of material, 1.80 52.49
Labour and machinery excluding
formwork to cater for extra lift
Page 18
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Say 212.00
3.5 F Case With Batching Plant, Transit Mixer and
(q) II Concrete Pump
Per Cum Basic Cost of Labour, Material & 2816.00
Machinery (a+b+c) of Item 2.8 (E) Case II
d) formwork
Add 11.8 per cent of cost of material, 11.80 332.29
labour and machinery (a+b+c) for
Formwork
Add 1.8 per cent of cost of material, 1.80 50.69
Labour and machinery excluding
formwork to cater for extra lift
d) formwork
Add 15 per cent of cost of material, 15.00 437.40
labour and machinery (a+b+c) for
Formwork
Add 4 per cent of cost of material, 4.00 116.64
Labour and machinery excluding
formwork to cater for extra lift
e) Overhead charges @ on (a+b+c+d) 173.50
Page 19
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
f) Contractor's profit @ on (a+b+c+d+e) 364.35
d) formwork
Add 15 per cent of cost of material, 15.00 422.40
labour and machinery (a+b+c) for
Formwork
Add 4 per cent of cost of material, 4.00 112.64
Labour and machinery excluding
formwork to cater for extra lift
e) Overhead charges @ on (a+b+c+d) 167.55
Page 20
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Per Cum Basic Cost of Labour, Material & 2933.00
Machinery (a+b+c) of Item 2.8 (G) Case I
d) formwork
Add 10 per cent of cost of material, 10.00 293.30
labour and machinery (a+b+c) for
Formwork
e) Overhead charges @ on (a+b+c+d) 161.32
d) formwork
Add 10 per cent of cost of material, 10.00 283.40
labour and machinery (a+b+c) for
Formwork
e) Overhead charges @ on (a+b+c+d) 155.87
Page 21
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
For height, upto 10m, add 1.6 per cent of
cost as above excluding formwork. For cost
of formwork add 11.5 per cent of cost of
material, labour and machinery
d) formwork
Add 11.5 per cent of cost of material, 11.50 337.30
labour and machinery (a+b+c) for
Formwork
Add 1.6 per cent of cost of material, 1.60 46.93
Labour and machinery excluding
formwork to cater for extra lift
d) formwork
Add 11.5 per cent of cost of material, 11.50 325.91
labour and machinery (a+b+c) for
Formwork
Add 1.6 per cent of cost of material, 1.60 45.34
Labour and machinery excluding
formwork to cater for extra lift
Page 22
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
f) Contractor's profit @ on (a+b+c+d+e) 336.55
d) formwork
Add 14 per cent of cost of material, 14.00 410.62
labour and machinery (a+b+c) for
Formwork
Add 3.5 per cent of cost of material, 3.50 102.66
Labour and machinery excluding
formwork to cater for extra lift
Page 23
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Per Cum Basic Cost of Labour, Material & 2834.00
Machinery (a+b+c) of Item 2.8 (G) Case II
d) formwork
Add 14 per cent of cost of material, 14.00 396.76
labour and machinery (a+b+c) for
Formwork
Add 3.5 per cent of cost of material, 3.50 99.19
Labour and machinery excluding
formwork to cater for extra lift
d) formwork
Add 10 per cent of cost of material, 10.00 300.80
labour and machinery (a+b+c) for
Formwork
e) Overhead charges @ on (a+b+c+d) 165.44
Page 24
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Labour 183.37
Overhead charges @ 5% 9.17
Contractors Profit @10% 19.25
Cost for 1 cum 211.79
Rate per cum 211.79
Say 212.00
3.5 H Case With Batching Plant, Transit Mixer and
(p) II Concrete Pump
Per Cum Basic Cost of Labour, Material & 2909.00
Machinery (a+b+c) of Item 2.8 (H) Case II
d) formwork
Add 10 per cent of cost of material, 10.00 290.90
labour and machinery (a+b+c) for
Formwork
e) Overhead charges @ on (a+b+c+d) 160.00
d) formwork
Add 11 per cent of cost of material, 11.00 330.88
labour and machinery (a+b+c) for
Formwork
Add 1.4 per cent of cost of material, 1.40 42.11
Labour and machinery excluding
formwork to cater for extra lift
Page 25
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
e) Overhead charges @ on (a+b+c+d) 169.05
d) formwork
Add 11 per cent of cost of material, 11.00 319.99
labour and machinery (a+b+c) for
Formwork
Add 1.4 per cent of cost of material, 1.40 40.73
Labour and machinery excluding
formwork to cater for extra lift
Page 26
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Per Cum Basic Cost of Labour, Material & 3008.00
Machinery (a+b+c) of Item 2.8 (H) Case I
d) formwork
Add 13 per cent of cost of material, 13.00 391.04
labour and machinery (a+b+c) for
Formwork
Add 3 per cent of cost of material, 3.00 90.24
Labour and machinery excluding
formwork to cater for extra lift
e) Overhead charges @ on (a+b+c+d) 174.46
d) formwork
Add 13 per cent of cost of material, 13.00 378.17
labour and machinery (a+b+c) for
Formwork
Add 3 per cent of cost of material, 3.00 87.27
Labour and machinery excluding
formwork to cater for extra lift
e) Overhead charges @ on (a+b+c+d) 168.72
Page 27
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
say 27.00
Note The basic components of this analysis are
the same as those of items 3.8 (A to H).
The only changes are as under:
a) Ramps/Stairs: Extra expenditure on
structures which are more than 5 m high @
2 per cent of cost for height upto 10 m and
4 per cent for heights above 10 m will be
involved for approaching the work spot by
providing higher ramp/stair case for use by
the working parties.
Output: MT
Taking output = 1 MT
a) Material
HYSD bars including 5 per cent tonne 1.05 45232.00 47493.60
overlaps and wastage
Binding wire kg 6.00 65.00 390.00
Total 47883.60
b) Labour for cutting, bending, shifting to
site, tying and placing in position
Page 28
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Unit = MT
Taking output = 1 MT
a) Material
MS bars including 5 per cent overlaps tonne 1.05 40000.00 42000.00
and wastage
Binding wire kg 6.00 50.00 300.00
b) Labour for straightening, cutting,
bending, shifting to site, tying and placing
in position
Mate day 0.28 116.67 32.67
Blacksmith day 1.50 186.67 280.01
Mazdoor day 5.50 116.67 641.69
c) Overhead charges @ on (a+b) 2162.72
d) Contractor's profit @ on (a+b+c) 4541.71
Rate for per MT (a+b+c+d) 49958.78
say 49959.00
Labour Rate
Labour 954.37
Overhead charges @ 5% 47.72
Contractors Profit @10% 100.21
Cost for 1 cum 1102.30
Rate per cum 1102.30
Say 1102.00
3.8 2706 Providing weep holes in Brick
& masonry/Plain/ Reinforced concrete
2200 abutment, wing wall/ return wall with 100
mm dia AC pipe, extending through the full
width of the structure with slope of 1V :20H
towards drawing face. Complete as per
drawing and Technical Specifications
Unit = Nos.
Taking output = 30 Nos.
a) Material
AC pipe 100 mm dia. (including metre 31.50 500.00 15750.00
wastage @ 5 per cent )
Page 29
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Average length of weep hole is taken as
one metre for the purpose of estimating.
Page 30
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Granular material cum 12.00 325.74 3908.88
Total 3908.88
c) Machinery
Plate compactor/power rammer hour 2.50 99.00 247.50
Water Tanker hour 0.05 531.00 26.55
Total 274.05
Net Total 6518.57
c) Overhead charges @ 20% (a+b) 20.0% 1303.71
d) Contractors Profit @10% (a+b+c) 10.0% 782.23
Total 8604.52
Add 1% Labour Cess on Rs 8604.52 1.00% 86.05
Add 12%GSTon Rs 8604.52 12.00 1032.54
Grand Total 9723.11
Cost for 15 Cum 9723.11
Rate per Cubic metre Rs. 972.30
Page 31
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
3.10 710.1. Providing and laying of Filter media with
4.of granular materials/stone crushed
IRC:78 aggregates satisfying the requirements laid
and down in clause 2504.2.2. of MoRTH
2200 specifications to a thickness of not less
than 600 mm with smaller size towards the
soil and bigger size towards the wall and
provided over the entire surface behind
abutment, wing wall and return wall to the
full height compacted to a firm condition
complete as per drawing and Technical
Specification.
Unit = cum
Taking output = 10 cum.
a) Labour
Mate day 0.32 116.67 37.33
Mazdoor for filling, watering, ramming day 7.00 116.67 816.69
etc.
Mazdoor (Skilled) day 1.00 116.67 116.67
b) Material
Filter media of stone aggregate cum 12.00 250.00 3000.00
conforming to clause 2504.2.2. of
MoRTH specifications.
c) Machinery
Water Tanker of 6 KL capacity hour 0.06 295.00 17.70
d) Overhead charges @ on (a+b+c) 199.42
Page 32
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
3.11 2000, Supplying, fitting and fixing in position true
1000 to line and level cast steel rocker bearing
& conforming to IRC: 83(Pt.-1) section IX and
2200 clause 2003 of MoRTH specifications
complete including all accessories as per
drawing and Technical Specifications.
say 187.00
Labour Rate
Labour 182.01
Overhead charges @ 5% 9.10
Contractors Profit @10% 19.11
Cost for 250T capacity load 210.22
Rate per Tonne load 0.84
Say 1.00
3.12 2000 , Supplying, fitting and fixing in position true
1000 to line and level forged steel roller bearing
& conforming to IRC: 83(Pt.-1) section IX and
2200 clause 2003 of MoRTH specifications
complete including all accessories as per
drawing and Technical Specifications.
Page 33
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Unit: one tonne capacity
Considering a 250 tonne capacity bearing
for this analysis
a) Labour
Mate day 0.06 116.67 7.00
Mazdoor day 1.00 116.67 116.67
Mazdoor (Skilled) day 0.50 116.67 58.34
b) Material
Forged steel roller bearing of 250 tonne each. 1.00 60000.00 60000.00
design load capacity duly painted
complete with all its components as per
drawing and specifications
say 281.00
Labour Rate
Labour 182.01
Overhead charges @ 5% 9.10
Contractors Profit @10% 19.11
Cost for 250 T capacity bearing 210.22
Rate per tonne capacity 0.84
Say 1.00
3.13 2000 Supplying, fitting and fixing in position true
& to line and level sliding plate bearing with
2200 PTFE surface sliding on stainless steel
complete including all accessories as per
drawing and Technical Specifications and
BS: 5400, section 9.1 & 9.2 (for PTFE)
and clause 2004 of MoRTH Specifications.
Page 34
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Mazdoor (Skilled) day 0.50 116.67 58.34
b) Material
PTFE sliding plate bearing assembly of each. 1.00 120000.00 120000.00
80 tonnes design load capacity duly
painted complete with all its
components as per drawing and
Technical Specifications
Add 1 per cent for foundation 1200.00
anchorage bolts and consumables.
c) Overhead charges @ on (a+b) 6069.10
d) Contractor's profit @ on (a+b+c) 12745.11
cost for 80 tonnes capacity bearing = 140196.22
a+b+c+d
Rate per tonne capacity = (a+b+c+d)/80 1752.45
say 1752.00
Labour Rate
Labour 182.01
Overhead charges @ 5% 9.10
Contractors Profit @10% 19.11
Cost for 250 T capacity bearing 210.22
Rate per cum 0.84
Say 1.00
3.14 2000 Supplying, fitting and fixing in position true
& to line and level elastomeric bearing
2200 conforming to IRC: 83 (Part-II) section IX
and clause 2005 of MoRTH specifications
complete including all accessories as per
drawing and Technical Specifications.
Page 35
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Elastomeric bearing assembly each. 1.00 50000.00 50000.00
consisting of 7 layers of elastomer
bonded to 6 nos. internal reinforcing
steel laminates by the process of
vulcanisation, complete with all
components as per drawing and
Technical Specifications.
a) Labour
Mate day 0.04 116.67 4.67
Mazdoor day 0.75 116.67 87.50
Mazdoor (Skilled) day 0.35 116.67 40.83
b) Material
Supply of sliding plate bearing of 80 each. 1.00 50000.00 50000.00
tonne design capacity complete as per
drawings and Technical Specifications.
Page 36
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add 1 per cent of cost of bearing 500.00
assembly for foundation anchorage
bolts and consumables.
c) Overhead charges @ on (a+b) 2531.65
d) Contractor's profit @ on (a+b+c) 5316.47
cost for 80 tonnes of capacity bearing = 58481.12
a+b+c+d
Through rate per tonne capacity of load 731.01
say 731.00
Labour Rate
Labour 182.01
Overhead charges @ 5% 9.10
Contractors Profit @10% 19.11
Cost for 80 T capacity bearing 210.22
Rate of bearing per Tonne load 2.63
Say 3.00
3.16 2000 Supplying, fitting and fixing in position true
& to line and level POT-PTFE bearing
2200 consisting of a metal piston supported by a
disc or unreinforced elastomer confined
within a metal cylinder, sealing rings, dust
seals, PTFE surface sliding against
stainless steel mating surface, complete
assembly to be of cast steel/fabricated
structural steel, metal and elastomer
elements to be as per IRC: 83 part-I & II
respectively and other parts conforming to
BS: 5400, section 9.1 & 9.2 and clause
2006 of MoRTH Specifications complete as
per drawing and approved Technical
Specifications.
Page 37
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Pot type bearing assembly consisting each. 1.00 120000.00 120000.00
of a metal piston supported by a disc,
PTFE pads providing sliding surfaces
against stainless steel mating together
with cast steel assemblies/fabricated
structural steel assemblies duly painted
with all components as per clause 2006
and complete as per drawings and
Technical Specifications.
say 561.00
Labour Rate
Labour 242.68
Overhead charges @ 5% 12.13
Contractors Profit @10% 25.48
Cost for 250 T bearing 280.30
Rate per tonne capacity 1.12
Say 1.00
Page 38
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
3.5 1500, Plain/Reinforced cement concrete in sub-
1700 structure complete as per drawing and
& Technical Specifications
2200
Unit = cum
Taking output = 1 cum
A PCC Grade M15
(p) Height upto 5m
Same as Item 2.8 (A) upto 5 m height,
except for formwork which shall be 10 per
cent instead of 4 per cent of cost of
material, labour and machinery.
Per Cum Basic Cost of Labour, Material & 2293.00
Machinery (a+b+c) of Item 2.8 (A)
d) formwork
Add 10 per cent of cost of material, 10.00 229.30
labour and machinery (a+b+c) for
Formwork
e) Overhead charges @ on (a+b+c+d) 126.12
d) formwork
Add 10 per cent of cost of material, 10.00 261.50
labour and machinery (a+b+c) for
Formwork
e) Overhead charges @ on (a+b+c+d) 143.83
Page 39
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
f) Contractor's profit @ on (a+b+c+d+e) 302.03
d) formwork
Add 10 per cent of cost of material, 10.00 288.60
labour and machinery (a+b+c) for
Formwork
e) Overhead charges @ on (a+b+c+d) 158.73
d) formwork
Page 40
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add 10 per cent of cost of material, 10.00 278.80
labour and machinery (a+b+c) for
Formwork
e) Overhead charges @ on (a+b+c+d) 153.34
d) formwork
Add 12 per cent of cost of material, 12.00 343.92
labour and machinery (a+b+c) for
Formwork
Add 2 per cent of cost of material, 2.00 57.32
Labour and machinery excluding
formwork to cater for extra lift
e) Overhead charges @ on (a+b+c+d) 163.36
Page 41
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Cost for 1 cum 211.79
Rate per cum 211.79
Say 212.00
3.5 C Case With Batching Plant, Transit Mixer and
(q) II Concrete Pump
Per Cum Basic Cost of Labour, Material & 2788.00
Machinery (a+b+c) of Item 2.8 (D) Case II
d) formwork
Add 12 per cent of cost of material, 12.00 334.56
labour and machinery (a+b+c) for
Formwork
Add 2 per cent of cost of material, 2.00 55.76
Labour and machinery excluding
formwork to cater for extra lift
e) Overhead charges @ on (a+b+c+d) 158.92
d) formwork
Add 15 per cent of cost of material, 15.00 429.90
labour and machinery (a+b+c) for
Formwork
Page 42
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add 4 per cent of cost of material, 4.00 114.64
Labour and machinery excluding
formwork to cater for extra lift
e) Overhead charges @ on (a+b+c+d) 170.53
d) formwork
Add 15 per cent of cost of material, 15.00 418.20
labour and machinery (a+b+c) for
Formwork
Add 4 per cent of cost of material, 4.00 111.52
Labour and machinery excluding
formwork to cater for extra lift
e) Overhead charges @ on (a+b+c+d) 0.00
Page 43
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Same as Item 2.8 (F) upto 5 m height with
the only change that the provision of form
work shall be 10 per cent instead of 3.50
per cent of cost of material, labour and
machinery.
Case I Using concrete Mixer
d) formwork
Add 10 per cent of cost of material, 10.00 291.50
labour and machinery (a+b+c) for
Formwork
e) Overhead charges @ on (a+b+c+d) 160.33
d) formwork
Add 10 per cent of cost of material, 10.00 281.50
labour and machinery (a+b+c) for
Formwork
e) Overhead charges @ on (a+b+c+d) 154.83
Page 44
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Cost for 1 cum 211.79
Rate per cum 211.79
Say 212.00
3.5 D Case With Batching Plant, Transit Mixer and
(r) II Concrete Pump
Per Cum Basic Cost of Labour, Material & 2815.00
Machinery (a+b+c) of Item 2.8 (F) Case II
d) formwork
Add 15 per cent of cost of material, 15.00 422.25
labour and machinery (a+b+c) for
Formwork
Add 4 per cent of cost of material, 4.00 112.60
Labour and machinery excluding
formwork to cater for extra lift
e) Overhead charges @ on (a+b+c+d) 194.29
d) formwork
Add 10 per cent of cost of material, 10.00 264.20
labour and machinery (a+b+c) for
Formwork
e) Overhead charges @ on (a+b+c+d) 145.31
Page 45
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
f) Contractor's profit @ on (a+b+c+d+e) 305.15
d) formwork
Add 10 per cent of cost of material, 10.00 254.20
labour and machinery (a+b+c) for
Formwork
e) Overhead charges @ on (a+b+c+d) 139.81
d) formwork
Page 46
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
f) Contractor's profit @ on (a+b+c+d+e) 317.62
d) formwork
Add 10 per cent of cost of material, 10.00 291.60
labour and machinery (a+b+c) for
Formwork
e) Overhead charges @ on (a+b+c+d) 160.38
d) formwork
Page 47
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Per Cum Basic Cost of Labour, Material & 2933.00
Machinery (a+b+c) of Item 2.8 (G) Case I
d) formwork
Add 10 per cent of cost of material, 10.00 293.30
labour and machinery (a+b+c) for
Formwork
e) Overhead charges @ on (a+b+c+d) 161.32
d) formwork
Add 10 per cent of cost of material, 10.00 283.40
labour and machinery (a+b+c) for
Formwork
e) Overhead charges @ on (a+b+c+d) 155.87
Page 48
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Per Cum Basic Cost of Labour, Material & 2834.00
Machinery (a+b+c) of Item 2.8 (G) Case II
d) formwork
Add 14 per cent of cost of material, 14.00 396.76
labour and machinery (a+b+c) for
Formwork
Add 3.5 per cent of cost of material, 3.50 99.19
Labour and machinery excluding
formwork to cater for extra lift
d) formwork
Add 10 per cent of cost of material, 10.00 300.80
labour and machinery (a+b+c) for
Formwork
e) Overhead charges @ on (a+b+c+d) 165.44
Page 49
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Labour 183.37
Overhead charges @ 5% 9.17
Contractors Profit @10% 19.25
Cost for 1 cum 211.79
Rate per cum 211.79
Say 212.00
3.5 H Case With Batching Plant, Transit Mixer and
(p) II Concrete Pump
Per Cum Basic Cost of Labour, Material & 2909.00 0.00
Machinery (a+b+c) of Item 2.8 (H) Case II
d) formwork
Add 10 per cent of cost of material, 10.00 290.90
labour and machinery (a+b+c) for
Formwork
e) Overhead charges @ on (a+b+c+d) 160.00
d) formwork
Add 11 per cent of cost of material, 11.00 330.88
labour and machinery (a+b+c) for
Formwork
Add 1.4 per cent of cost of material, 1.40 42.11
Labour and machinery excluding
formwork to cater for extra lift
Page 50
CHAPTER-3
SUB-STRUCTURE
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
3.1 1300 Brick masonry work in 1:3 in sub-structure
& complete excluding pointing and plastering,
2200 as per drawing and Technical
Specifications
Unit = cum
Taking output = 1 cum
a) Material
Bricks Ist class each 500.00 3.00 1500.00
Cement mortar 1:3 (Rate as in Item 2.6 cum 0.24 2924.00 701.76
A sub-analysis)
b) Labour
Mate day 0.06 116.67 7.00
Mason day 0.80 211.17 168.94
Mazdoor day 0.80 116.67 93.34
Add for scaffolding @ 5 per cent of 123.55
cost of material and labour
c) Overhead charges @ on (a+b) 129.73
d) Contractor's profit @ on (a+b+c) 272.43
Rate per cum (a+b+c+d) 2996.74
say 2997.00
Labour Rate
Labour for masonary 269.28
Labour for mortar cum 0.24 109.67 26.32
Add for scaffolding @ 5 per cent of 13.46
cost labour
Overhead charges @ 5% 15.45
Overhead charges @ 10% 32.45 a
Cost for 1 cum 440.32
Rate per cum 440.32
Say 440.00
3.2 1300 Pointing with cement mortar (1:3 ) on brick
& work in substructure as per Technical
2200 Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item 2.6 cum 0.03 2924.00 87.72
)
b) Labour
Mate day 0.04 116.67 4.67
Mason day 0.50 211.17 105.59
Mazdoor day 0.50 116.67 58.34
c) Overhead charges @ on (a+b) 12.82
d) Contractor's profit @ on (a+b+c) 26.91
Rate per 10 sqm (a+b+c+d) 296.03
Page 51
CHAPTER-4
SUPER-STRUCTURE
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
4.1 1500 Furnishing and Placing Reinforced/
&1600 Prestressed cement concrete in super-
1700 structure as per drawing and Technical
Specification
Page 1
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
say 212.00
4.1A (q) Height 5m to 10m
Case I (i)
Page 2
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
#REF! #REF!
Cost for 15 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/15 #REF!
say #REF!
Labour Rate
Labour 2750.50
Overhead charges @05% 137.53
Contractors profit @10% 288.80
Rate for 15 Cum 3176.83
Rate per Cum 211.78
say 212.00
4.1A (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 15 cum
d) Formwork and staging 30 per 30.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 15 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/15 #REF!
say #REF!
Labour Rate
Labour 2750.50
Overhead charges @05% 137.53
Contractors profit @10% 288.80
Rate for 15 Cum 3176.83
Rate per Cum 211.78
say 212.00
4.1A (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 15 cum
d) Formwork and staging 35 per 35.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 15 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/15 #REF!
say #REF!
Labour Rate
Labour 2750.50
Overhead charges @05% 137.53
Contractors profit @10% 288.80
Rate for 15 Cum 3176.83
Page 3
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Rate per Cum 211.78
say 212.00
4.1A Case Using Batching Plant, Transit Mixer and
II Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 40.92 #REF! #REF!
Coarse sand cum 54.00 #REF! #REF!
20 mm Aggregate cum 64.80 460.00 29808.00
10 mm Aggregate cum 43.20 480.00 20736.00
b) Labour
Mate day 0.84 #REF! #REF!
Mason day 3.00 #REF! #REF!
Mazdoor day 18.00 #REF! #REF!
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 #REF! 11040.00
Generator 100 KVA hour 6.00 #REF! 2700.00
Loader hour 6.00 #REF! 4722.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 hour 15.00 #REF! 11550.00
Km
Lead beyond 1 Km, L - lead in tonne.k 300L 0.00 #REF!
Kilometer m
Concrete Pump hour 6.00 #REF! 1260.00
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
Say #REF!
For formwork and staging add the
following:
4.1A (i) For solid slab super-structure, 20-30
Case II per cent of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
d) Formwork and staging 20 per 20.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
say #REF!
Labour Rate
Labour 2831.57
Overhead charges @05% 141.58
Page 4
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Contractors profit @10% 297.31
Rate for 120 Cum 3270.46
Rate per Cum 27.25
say 27.00
4.1A (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
d) Formwork and staging 25 per 25.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
say #REF!
Labour Rate
Labour 2831.57
Overhead charges @05% 141.58
Contractors profit @10% 297.31
Rate for 120 Cum 3270.46
Rate per Cum 27.25
say 27.00
4.1A (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
d) Formwork and staging 30 per 30.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
say #REF!
Labour Rate
Labour 2831.57
Overhead charges @05% 141.58
Contractors profit @10% 297.31
Rate for 120 Cum 3270.46
Rate per Cum 27.25
say 27.00
4.1A (ii) For T-beam & slab, 25-35 per cent of
Case II (a+b+c)
(p) Height upto 5m
Page 5
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
d) Formwork and staging 25 per 25.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
say #REF!
Labour Rate
Labour 2831.57
Overhead charges @05% 141.58
Contractors profit @10% 297.31
Rate for 120 Cum 3270.46
Rate per Cum 27.25
say 27.00
4.1A (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
d) Formwork and staging 30 per 30.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
say #REF!
Labour Rate
Labour 2831.57
Overhead charges @05% 141.58
Contractors profit @10% 297.31
Rate for 120 Cum 3270.46
Rate per Cum 27.25
say 27.00
4.1A (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
d) Formwork and staging 35 per 35.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Page 6
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Rate per cum = (a+b+c+d+e+f)/120 #REF!
say #REF!
Labour Rate
Labour 2831.57
Overhead charges @05% 141.58
Contractors profit @10% 297.31
Rate for 120 Cum 3270.46
Rate per Cum 27.25
say 27.00
4.1 B RCC Grade M25
Case Using Concrete Mixer
I
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 5.99 #REF! #REF!
Coarse sand cum 6.75 #REF! #REF!
20 mm Aggregate cum 8.10 #REF! #REF!
10 mm Aggregate cum 5.40 #REF! #REF!
b) Labour
Mate day 0.86 #REF! #REF!
Mason day 1.50 #REF! #REF!
Mazdoor day 20.00 #REF! #REF!
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 #REF! #REF!
Page 7
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Contractors profit @10% 288.80
Rate for 15 Cum 3176.83
Rate per Cum 211.78
say 212.00
4.1B (q) Height 5m to 10m
Case I (i)
Page 8
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
d) Formwork and staging 25 per 25.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 15 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/15 #REF!
say #REF!
Labour Rate
Labour 2750.50
Overhead charges @05% 137.53
Contractors profit @10% 288.80
Rate for 15 Cum 3176.83
Rate per Cum 211.78
say 212.00
4.1B (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 15 cum
d) Formwork and staging 30 per 30.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 15 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/15 #REF!
say #REF!
Labour Rate
Labour 2750.50
Overhead charges @05% 137.53
Contractors profit @10% 288.80
Rate for 15 Cum 3176.83
Rate per Cum 211.78
say 212.00
4.1B (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 15 cum
d) Formwork and staging 35 per 35.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 15 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/15 #REF!
say #REF!
Labour Rate
Labour 2750.50
Page 9
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Overhead charges @05% 137.53
Contractors profit @10% 288.80
Rate for 15 Cum 3176.83
Rate per Cum 211.78
say 212.00
4.1B Case Using Batching Plant, Transit Mixer and
II Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 47.95 #REF! #REF!
Coarse sand cum 54.20 #REF! #REF!
20 mm Aggregate cum 64.80 460.00 29808.00
10 mm Aggregate cum 43.20 480.00 20736.00
b) Labour
Mate day 0.84 #REF! #REF!
Mason day 3.00 #REF! #REF!
Mazdoor day 18.00 #REF! #REF!
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 #REF! #REF!
Generator 100 KVA hour 6.00 #REF! #REF!
Loader hour 6.00 #REF! #REF!
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 hour 15.00 #REF! #REF!
Km
Lead beyond 1 Km, L - lead in tonne.k 300L 0.00 #REF!
Kilometer m
Concrete Pump hour 6.00 #REF! #REF!
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
say #REF!
Labour Rate
Page 10
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Labour 2831.57
Overhead charges @05% 141.58
Contractors profit @10% 297.31
Rate for 120 Cum 3270.46
Rate per Cum 27.25
say 27.00
4.1B (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
d) Formwork and staging 25 per 25.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
say #REF!
Labour Rate
Labour 2831.57
Overhead charges @05% 141.58
Contractors profit @10% 297.31
Rate for 120 Cum 3270.46
Rate per Cum 27.25
say 27.00
4.1B (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
d) Formwork and staging 30 per 30.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
say #REF!
Labour Rate
Labour 2831.57
Overhead charges @05% 141.58
Contractors profit @10% 297.31
Rate for 120 Cum 3270.46
Rate per Cum 27.25
say 27.00
Page 11
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
4.1B (ii)For T-beam & slab, 25-35 per cent of
Case II (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
d) Formwork and staging 25 per 25.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
say #REF!
Labour Rate
Labour 2831.57
Overhead charges @05% 141.58
Contractors profit @10% 297.31
Rate for 120 Cum 3270.46
Rate per Cum 27.25
say 27.00
4.1B (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
d) Formwork and staging 30 per 30.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
say #REF!
Labour Rate
Labour 2831.57
Overhead charges @05% 141.58
Contractors profit @10% 297.31
Rate for 120 Cum 3270.46
Rate per Cum 27.25
say 27.00
4.1B (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
d) Formwork and staging 35 per 35.00 #REF!
cent of (a+b+c)
Page 12
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
say #REF!
Labour Rate
Labour 2831.57
Overhead charges @05% 141.58
Contractors profit @10% 297.31
Rate for 120 Cum 3270.46
Rate per Cum 27.25
say 27.00
4.1 C RCC Grade M 30
Case Using Concrete Mixer
I
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 6232.06 38015.57
Coarse sand cum 6.75 675.74 4561.25
20 mm Aggregate cum 8.10 730.45 5916.65
10 mm Aggregate cum 5.40 755.45 4079.43
b) Labour
Mate day 0.90 320.83 288.75
Mason day 1.50 476.00 714.00
Mazdoor day 21.00 320.83 6737.43
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 360.00 2160.00
Page 13
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add 12%GSTon Rs 110420.64 12.00 13250.48
Grand Total 124775.33
Cost for 15 Cum 124775.33
Rate per Cubic metre Rs. 8318.40
Page 14
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
4.1C (ii)For T-beam & slab, 25-35 per cent of
Case I (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & 69710.00
Machinery (a+b+c) for 15 cum
d) Formwork and staging 25 per 25.00 17427.50
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 15 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/15 #REF!
say #REF!
Labour Rate
Labour 2871.83
Overhead charges @05% 143.59
Contractors profit @10% 301.54
Rate for 15 Cum 3316.96
Rate per Cum 221.13
say 221.00
4.1C (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & 69710.00
Machinery (a+b+c) for 15 cum
d) Formwork and staging 30 per 30.00 20913.00
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 15 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/15 #REF!
say #REF!
Labour Rate
Labour 2871.83
Overhead charges @05% 143.59
Contractors profit @10% 301.54
Rate for 15 Cum 3316.96
Rate per Cum 221.13
say 221.00
4.1C (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & 69710.00
Machinery (a+b+c) for 15 cum
d) Formwork and staging 35 per 35.00 24398.50
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Page 15
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Cost for 15 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/15 #REF!
say #REF!
Labour Rate
Labour 2871.83
Overhead charges @05% 143.59
Contractors profit @10% 301.54
Rate for 15 Cum 3316.96
Rate per Cum 221.13
say 221.00
4.1C Case Using Batching Plant, Transit Mixer and
II Concrete Pump.
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.79 6222.96 303618.22
Coarse sand cum 54.60 675.74 36895.40
20 mm Aggregate cum 64.80 730.45 47333.16
10 mm Aggregate cum 43.20 755.45 32635.44
b) Labour
Mate day 0.88 291.67 256.67
Mason day 3.00 432.83 1298.49
Mazdoor day 19.00 291.67 5541.73
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 #REF! #REF!
Generator 100 KVA hour 6.00 #REF! #REF!
Loader hour 6.00 #REF! #REF!
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 hour 15.00 #REF! #REF!
Km
Lead beyond 1 Km, L - lead in tonne.k 300L 0.00 #REF!
Kilometer m
Concrete Pump hour 6.00 #REF! #REF!
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
Page 16
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Rate per cum = (a+b+c+d+e+f)/120 #REF!
say #REF!
Labour Rate
Labour 2952.91
Overhead charges @05% 147.65
Contractors profit @10% 310.06
Rate for 120 Cum 3410.61
Rate per Cum 28.42
say 28.00
4.1C (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
d) Formwork and staging 25 per 25.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
say #REF!
Labour Rate
Labour 2952.91
Overhead charges @05% 147.65
Contractors profit @10% 310.06
Rate for 120 Cum 3410.61
Rate per Cum 28.42
say 28.00
4.1C (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
d) Formwork and staging 30 per 30.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
say #REF!
Labour Rate
Labour 2952.91
Overhead charges @05% 147.65
Contractors profit @10% 310.06
Page 17
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Rate for 120 Cum 3410.61
Rate per Cum 28.42
say 28.00
4.1C (ii)For T-beam & slab, 25-35 per cent of
Case II (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
d) Formwork and staging 25 per 25.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
say #REF!
Labour Rate
Labour 2952.91
Overhead charges @05% 147.65
Contractors profit @10% 310.06
Rate for 120 Cum 3410.61
Rate per Cum 28.42
say 28.00
4.1C (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
d) Formwork and staging 30 per 30.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
say #REF!
Labour Rate
Labour 2952.91
Overhead charges @05% 147.65
Contractors profit @10% 310.06
Rate for 120 Cum 3410.61
Rate per Cum 28.42
say 28.00
4.1C (r) Height above 10m
Case II
(ii)
Page 18
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
d) Formwork and staging 35 per 35.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
say #REF!
Labour Rate
Labour 2952.91
Overhead charges @05% 147.65
Contractors profit @10% 310.06
Rate for 120 Cum 3410.61
Rate per Cum 28.42
say 28.00
4.1 D RCC/PSC Grade M35
Case Using Concrete Mixer.
I
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 #REF! #REF!
Coarse sand cum 6.75 #REF! #REF!
20 mm Aggregate cum 8.10 #REF! #REF!
10 mm Aggregate cum 5.40 #REF! #REF!
b) Labour
Mate day 0.90 #REF! #REF!
Mason day 1.50 #REF! #REF!
Mazdoor day 21.00 #REF! #REF!
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 #REF! #REF!
Page 19
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Rate per cum = (a+b+c+d+e+f)/15 #REF!
say #REF!
Labour Rate
Labour 2871.83
Overhead charges @05% 143.59
Contractors profit @10% 301.54
Rate for 15 Cum 3316.96
Rate per Cum 221.13
say 221.00
4.1D (q) Height 5m to 10m
Case I (i)
Page 20
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
4.1D (ii)For T-beam & slab, 23-33 per cent of
Case I (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 15 cum
d) Formwork and staging 23 per 23.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 15 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/15 #REF!
say #REF!
Labour Rate
Labour 2871.83
Overhead charges @05% 143.59
Contractors profit @10% 301.54
Rate for 15 Cum 3316.96
Rate per Cum 221.13
say 221.00
4.1D (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 15 cum
d) Formwork and staging 28 per 28.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 15 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/15 #REF!
say #REF!
Labour Rate
Labour 2871.83
Overhead charges @05% 143.59
Contractors profit @10% 301.54
Rate for 15 Cum 3316.96
Rate per Cum 221.13
say 221.00
4.1D (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 15 cum
d) Formwork and staging 33 per 33.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Page 21
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Cost for 15 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/15 #REF!
say #REF!
Labour Rate
Labour 2871.83
Overhead charges @05% 143.59
Contractors profit @10% 301.54
Rate for 15 Cum 3316.96
Rate per Cum 221.13
say 221.00
4.1D (iii) For box girder and balanced cantilever,
Case I 38-58 per cent of cost of concrete.
Page 22
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Rate for 15 Cum 3316.96
Rate per Cum 221.13
say 221.00
4.1D (r) Height above 10m
Case I
(iii)
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 15 cum
d) Formwork and staging 58 per 58.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 15 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/15 #REF!
say #REF!
Labour Rate
Labour 2871.83
Overhead charges @05% 143.59
Contractors profit @10% 301.54
Rate for 15 Cum 3316.96
Rate per Cum 221.13
say 221.00
Case Using Batching Plant, Transit Mixer and
II Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.64 #REF! #REF!
Coarse sand cum 54.00 #REF! #REF!
20 mm Aggregate cum 64.80 460.00 29808.00
10 mm Aggregate cum 43.20 480.00 20736.00
b) Labour
Mate day 0.88 #REF! #REF!
Mason day 3.00 #REF! #REF!
Mazdoor day 19.00 #REF! #REF!
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 #REF! #REF!
Generator 100 KVA hour 6.00 #REF! #REF!
Loader hour 6.00 #REF! #REF!
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 hour 15.00 #REF! #REF!
Km
Lead beyond 1 Km, L - lead in tonne.k 300L 0.00 #REF!
Kilometer m
Concrete Pump hour 6.00 #REF! #REF!
Page 23
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
say #REF!
Labour Rate
Labour 2952.91
Overhead charges @05% 147.65
Contractors profit @10% 310.06
Rate for 120 Cum 3410.61
Rate per Cum 28.42
say 28.00
4.1D (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
d) Formwork and staging 23 per 23.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
say #REF!
Labour Rate
Labour 2952.91
Overhead charges @05% 147.65
Contractors profit @10% 310.06
Rate for 120 Cum 3410.61
Rate per Cum 28.42
say 28.00
4.1D (r) Height above 10m
Case II
(i)
Page 24
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
d) Formwork and staging 28 per 28.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
say #REF!
Labour Rate
Labour 2952.91
Overhead charges @05% 147.65
Contractors profit @10% 310.06
Rate for 120 Cum 3410.61
Rate per Cum 28.42
say 28.00
4.1D (ii)For T-beam & slab, 23-33 per cent of
Case II (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
d) Formwork and staging 23 per 23.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
say #REF!
Labour Rate
Labour 2952.91
Overhead charges @05% 147.65
Contractors profit @10% 310.06
Rate for 120 Cum 3410.61
Rate per Cum 28.42
say 28.00
4.1D (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
d) Formwork and staging 28 per 28.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Page 25
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Rate per cum = (a+b+c+d+e+f)/120 #REF!
say #REF!
Labour Rate
Labour 2952.91
Overhead charges @05% 147.65
Contractors profit @10% 310.06
Rate for 120 Cum 3410.61
Rate per Cum 28.42
say 28.00
4.1D (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
d) Formwork and staging 33 per 33.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
say #REF!
Labour Rate
Labour 2952.91
Overhead charges @05% 147.65
Contractors profit @10% 310.06
Rate for 120 Cum 3410.61
Rate per Cum 28.42
say 28.00
4.1D (iii) For box girder and balanced cantilever,
Case II 38-58 per cent of cost of concrete.
say #REF!
Labour Rate
Labour 2952.91
Overhead charges @05% 147.65
Page 26
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Contractors profit @10% 310.06
Rate for 120 Cum 3410.61
Rate per Cum 28.42
say 28.00
4.1D (q) Height 5m to 10m
Case II
(iii)
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
d) Formwork and staging 48 per 48.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
say #REF!
Labour Rate
Labour 2952.91
Overhead charges @05% 147.65
Contractors profit @10% 310.06
Rate for 120 Cum 3410.61
Rate per Cum 28.42
say 28.00
4.1D (r) Height above 10m
Case II
(iii)
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
d) Formwork and staging 58 per 58.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
say #REF!
Labour Rate
Labour 2952.91
Overhead charges @05% 147.65
Contractors profit @10% 310.06
Rate for 120 Cum 3410.61
Rate per Cum 28.42
say 28.00
4.1 E PSC Grade M-40
Case Using concrete mixer.
1
Page 27
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.45 #REF! #REF!
Coarse sand cum 6.75 #REF! #REF!
20 mm Aggregate cum 8.10 #REF! #REF!
10 mm Aggregate cum 5.40 #REF! #REF!
Admixture @ 0.4 per cent of cement kg 25.80 #REF! #REF!
b) Labour
Mate day 0.96 #REF! #REF!
Mason day 2.00 #REF! #REF!
Mazdoor day 22.00 #REF! #REF!
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 #REF! #REF!
Page 28
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Cost for 15 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/15 #REF!
say #REF!
Labour Rate
Labour 3101.08
Overhead charges @05% 155.05
Contractors profit @10% 325.61
Rate for 15 Cum 3581.75
Rate per Cum 238.78
say 239.00
4.1E (r) Height above 10m
Case I (i)
Page 29
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
say 239.00
4.1E (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 15 cum
d) Formwork and staging 30 per 30.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 15 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/15 #REF!
say #REF!
Labour Rate
Labour 3101.08
Overhead charges @05% 155.05
Contractors profit @10% 325.61
Rate for 15 Cum 3581.75
Rate per Cum 238.78
say 239.00
4.1E (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 15 cum
d) Formwork and staging 35 per 35.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 15 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/15 #REF!
Say 4988.00
Labour Rate
Labour 3101.08
Overhead charges @05% 155.05
Contractors profit @10% 325.61
Rate for 15 Cum 3581.75
Rate per Cum 238.78
say 239.00
4.1E Case Using Batching Plant, Transit Mixer and
II Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 #REF! #REF!
Coarse sand cum 54.00 #REF! #REF!
20 mm Aggregate cum 64.80 460.00 29808.00
Page 30
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
10 mm Aggregate cum 43.20 480.00 20736.00
Admixture @ 0.4 per cent of cement kg 206.40 #REF! #REF!
b) Labour
Mate day 0.94 #REF! #REF!
Mason day 3.50 #REF! #REF!
Mazdoor day 20.00 #REF! #REF!
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 #REF! #REF!
Generator 100 KVA hour 6.00 #REF! #REF!
Loader hour 6.00 #REF! #REF!
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 hour 15.00 #REF! #REF!
Km
Lead beyond 1 Km, L - lead in tonne.k 300L 0.00 #REF!
Kilometer m
Concrete Pump hour 6.00 #REF! #REF!
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
For formwork and staging add the
following:
4.1E (i) For solid/voided slab super-structure,
Case II 18-28 per cent of (a+b+c)
say #REF!
Labour Rate
Labour 3182.17
Overhead charges @05% 159.11
Contractors profit @10% 334.13
Rate for 120 Cum 3675.41
Rate per Cum 30.62
say 31.00
4.1E (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
Page 31
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
d) Formwork and staging 23 per 23.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
say #REF!
Labour Rate
Labour 3182.17
Overhead charges @05% 159.11
Contractors profit @10% 334.13
Rate for 120 Cum 3675.41
Rate per Cum 30.62
say 31.00
4.1E (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
d) Formwork and staging 28 per 28.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
Say #REF!
Labour Rate
Labour 3182.17
Overhead charges @05% 159.11
Contractors profit @10% 334.13
Rate for 120 Cum 3675.41
Rate per Cum 30.62
say 31.00
4.1E (ii)For T-beam & slab, 23-33 per cent of
Case II (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
d) Formwork and staging 23 per 23.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
Page 32
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Say #REF!
Labour Rate
Labour 3182.17
Overhead charges @05% 159.11
Contractors profit @10% 334.13
Rate for 120 Cum 3675.41
Rate per Cum 30.62
say 31.00
4.1E (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
d) Formwork and staging 28 per 28.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
say #REF!
Labour Rate
Labour 3182.17
Overhead charges @05% 159.11
Contractors profit @10% 334.13
Rate for 120 Cum 3675.41
Rate per Cum 30.62
say 31.00
4.1E (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
d) Formwork and staging 33 per 33.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
Say #REF!
Labour Rate
Labour 3182.17
Overhead charges @05% 159.11
Contractors profit @10% 334.13
Rate for 120 Cum 3675.41
Rate per Cum 30.62
Page 33
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
say 31.00
4.1E (iii) For cast-in-situ box girder, segment
Case II construction and balanced cantilever,
38-58 per cent of cost of concrete.
Say #REF!
Labour Rate
Labour 3182.17
Overhead charges @05% 159.11
Contractors profit @10% 334.13
Rate for 120 Cum 3675.41
Rate per Cum 30.62
say 31.00
4.1E (q) Height 5m to 10m
Case II
(iii)
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
d) Formwork and staging 48 per 48.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
say #REF!
Labour Rate
Labour 3182.17
Overhead charges @05% 159.11
Contractors profit @10% 334.13
Rate for 120 Cum 3675.41
Rate per Cum 30.62
say 31.00
4.1E (r) Height above 10m
Case II
(iii)
Page 34
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
d) Formwork and staging 58 per 58.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
Say #REF!
Labour Rate
Labour 3182.17
Overhead charges @05% 159.11
Contractors profit @10% 334.13
Rate for 120 Cum 3675.41
Rate per Cum 30.62
say 31.00
4.1F F PSC Grade M-45
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 55.80 #REF! #REF!
Coarse sand cum 54.00 #REF! #REF!
20 mm Aggregate cum 64.80 460.00 29808.00
10 mm Aggregate cum 43.20 480.00 20736.00
Admixture @ 0.4 per cent of cement kg 223.20 #REF! #REF!
b) Labour
Mate day 0.94 #REF! #REF!
Mason day 3.50 #REF! #REF!
Mazdoor day 20.00 #REF! #REF!
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 #REF! #REF!
Generator 100 KVA hour 6.00 #REF! #REF!
Loader hour 6.00 #REF! #REF!
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 hour 15.00 #REF! #REF!
Km
Lead beyond 1 Km, L - lead in tonne.k 300L 0.00 #REF!
Kilometer m
Concrete Pump hour 6.00 #REF! #REF!
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
Page 35
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
4.1F (i) For solid slab/voided slab super-
structure, 16-26 per cent of cost of
concrete (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
d) Formwork and staging 16 per 16.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
Say #REF!
Labour Rate
Labour 3182.17
Overhead charges @05% 159.11
Contractors profit @10% 334.13
Rate for 120 Cum 3675.41
Rate per Cum 30.62
say 31.00
4.1F (i) (q) Height 5m to 10m
say #REF!
Labour Rate
Labour 3182.17
Overhead charges @05% 159.11
Contractors profit @10% 334.13
Rate for 120 Cum 3675.41
Rate per Cum 30.62
say 31.00
4.1F (i) (r) Height above 10m
Page 36
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
say #REF!
Labour Rate
Labour 3182.17
Overhead charges @05% 159.11
Contractors profit @10% 334.13
Rate for 120 Cum 3675.41
Rate per Cum 30.62
say 31.00
4.1F (ii) For T-beam & slab including launching
of precast girders by launching truss
upto 40 m span, 21-31 per cent of cost
of concrete.
Say #REF!
Labour Rate
Labour 3182.17
Overhead charges @05% 159.11
Contractors profit @10% 334.13
Rate for 120 Cum 3675.41
Rate per Cum 30.62
say 31.00
4.1F (ii) (q) Height 5m to 10m
Page 37
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Labour 3182.17
Overhead charges @05% 159.11
Contractors profit @10% 334.13
Rate for 120 Cum 3675.41
Rate per Cum 30.62
say 31.00
4.1F (ii) (r) Height above 10m
say #REF!
Labour Rate
Labour 3182.17
Overhead charges @05% 159.11
Contractors profit @10% 334.13
Rate for 120 Cum 3675.41
Rate per Cum 30.62
say 31.00
4.1F (iii) For cast-in-situ box girder, segmental
construction and balanced cantilever,
36-56 per cent of cost of concrete.
Say #REF!
Labour Rate
Labour 3182.17
Overhead charges @05% 159.11
Contractors profit @10% 334.13
Rate for 120 Cum 3675.41
Rate per Cum 30.62
say 31.00
Page 38
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
4.1F (iii) (q) Height 5m to 10m
say #REF!
Labour Rate
Labour 3182.17
Overhead charges @05% 159.11
Contractors profit @10% 334.13
Rate for 120 Cum 3675.41
Rate per Cum 30.62
say 31.00
4.1F (iii) (r) Height above 10m
Say #REF!
Labour Rate
Labour 3182.17
Overhead charges @05% 159.11
Contractors profit @10% 334.13
Rate for 120 Cum 3675.41
Rate per Cum 30.62
say 31.00
4.1 G PSC Grade M-50
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 58.80 #REF! #REF!
Coarse sand cum 54.00 #REF! #REF!
20 mm Aggregate cum 64.80 460.00 29808.00
10 mm Aggregate cum 43.20 480.00 20736.00
Page 39
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Admixture @ 0.4 per cent of cement kg 235.20 #REF! #REF!
b) Labour
Mate day 0.94 #REF! #REF!
Mason day 3.50 #REF! #REF!
Mazdoor day 20.00 #REF! #REF!
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 #REF! #REF!
Generator 100 KVA hour 6.00 #REF! #REF!
Loader hour 6.00 #REF! #REF!
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 hour 15.00 #REF! #REF!
Km
Lead beyond 1 Km, L - lead in tonne.k 300L 0.00 #REF!
Kilometer m
Concrete Pump hour 6.00 #REF! #REF!
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
Say #REF!
Labour Rate
Labour 3182.17
Overhead charges @05% 159.11
Contractors profit @10% 334.13
Rate for 120 Cum 3675.41
Rate per Cum 30.62
say 31.00
4.1G (i) (q) Height 5m to 10m
Page 40
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
d) Formwork and staging 45 per 45.00 #REF!
cent of (a+b+c)
#REF! #REF!
#REF! #REF!
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
say #REF!
Labour Rate
Labour 3182.17
Overhead charges @05% 159.11
Contractors profit @10% 334.13
Rate for 120 Cum 3675.41
Rate per Cum 30.62
say 31.00
4.1G (i) (r) Height above 10m
say #REF!
Labour Rate
Labour 3182.17
Overhead charges @05% 159.11
Contractors profit @10% 334.13
Rate for 120 Cum 3675.41
Rate per Cum 30.62
say 31.00
4.1 H PSC Grade M- 55
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 63.50 #REF! #REF!
Coarse sand cum 54.00 #REF! #REF!
20 mm Aggregate cum 64.80 460.00 29808.00
10 mm Aggregate cum 43.20 480.00 20736.00
Admixture @ 0.4 per cent of cement kg 254.00 #REF! #REF!
b) Labour
Mate day 0.94 #REF! #REF!
Mason day 3.50 #REF! #REF!
Page 41
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Mazdoor day 20.00 #REF! #REF!
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 #REF! #REF!
Generator 100 KVA hour 6.00 #REF! #REF!
Loader hour 6.00 #REF! #REF!
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 hour 15.00 #REF! #REF!
Km
Lead beyond 1 Km, L - lead in tonne.k 300L 0.00 #REF!
Kilometer m
Concrete Pump hour 6.00 #REF! #REF!
Basic Cost of Labour, Material & #REF!
Machinery (a+b+c) for 120 cum
Say #REF!
Labour Rate
Labour 3182.17
Overhead charges @05% 159.11
Contractors profit @10% 334.13
Rate for 120 Cum 3675.41
Rate per Cum 30.62
say 31.00
4.1H (i) (q) Height 5m to 10m
Page 42
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Cost for 120 cum = a+b+c+d+e+f #REF!
Rate per cum = (a+b+c+d+e+f)/120 #REF!
say #REF!
Labour Rate
Labour 3182.17
Overhead charges @05% 159.11
Contractors profit @10% 334.13
Rate for 120 Cum 3675.41
Rate per Cum 30.62
say 31.00
4.1H (i) (r) Height above 10m
say #REF!
Labour Rate
Labour 3182.17
Overhead charges @05% 159.11
Contractors profit @10% 334.13
Rate for 120 Cum 3675.41
Rate per Cum 30.62
say 31.00
Note 1.Where ever concrete is carried out
using batching plant, transit mixer,
concrete pump, admixers conforming
IS: 9103 @ 0.4 per cent of weight of
cement may be added for achieving
desired slump of concrete.
Page 43
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
3. The items like needle and surface
vibrators are part of minor T & P which
is already covered under the overhead
charges. As such these items have not
been added separately in the rate
analysis.
4.2 1600 Supplying, fitting and placing HYSD bar
reinforcement in super-structure
complete as per drawing and technical
specifications
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including 5 per cent for tonne 1.05 45251.96 47514.56
laps and wastage
Binding wire Kg 8.00 65.00 520.00
b) Labour for cutting, bending, tying
and placing in position
Total 68463.12
Add 1% Labour Cess on Rs 68463.12 1.0% 684.63
Add 12%GSTon Rs 68463.12 12.0% 8215.57
Grand Total 77363.33
Cost for M.T 77363.33
Through Rate per M.T 77363.30
Unit = 1 MT
Taking output = 0.377 MT
Page 44
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Details of cost for 12T13 strand 40 m
long cable (weight = 0.377 MT)
a) Material
H.T. Strand @ 9.42 kg/m including 2 tonne 0.39 #REF! #REF!
per cent for wastage and extra length
for jacking
Sheathing duct ID 66 mm along with 5 metre 42.00 #REF! #REF!
per cent extra length 40 x 1.05 = 42 m.
Page 45
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Rate per MT 2727.21
say 2727.00
Note Cost of HT steel has been taken for
delivery at site. Hence carriage has not
been considered.
4.4 2702 Providing and laying Cement concrete
wearing coat M-30 grade including
reinforcement complete as per drawing
and Technical Specifications
Unit = 1 cum
Taking output = 1 cum
a) Material
Cement concrete M30 Grade Refer cum 1.00 4647.33 4647.33
relevant item of concrete in Item 4.1-C
-ii excluding formwork
b) Labour
Mazdoor for cleaning deck slab day 0.15 320.83 48.12
concrete surface.
Total 8585.41
c)Overhead charges @ 20% on 20.0% 1717.08
(a+b+c+d)
d)Contractor's profit @ 10 % on 10.0% 1030.25
(a+b+c+d+e)
Total 11332.74
Add 1% Labour Cess on Rs 11332.74 1.00% 113.33
Add 12%GSTon Rs 11332.74 12.00 1359.93
Grand Total 12806.00
Cost for 1 Cum 12806.00
Rate per Cubic metre Rs. 12806.00
Page 46
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Providing and laying 12 mm thick
mastic asphalt wearing course on top of
deck slab excluding prime coat with
paving grade bitumen meeting the
requirements given in table 500-29,
prepared by using mastic cooker and
laid to required level and slope after
cleaning the surface, including
providing antiskid surface with bitumen
precoated fine grained hard stone
chipping of 9.5 mm nominal size at the
rate of 0.005cum per 10 sqm and at an
approximate spacing of 10 cm center to
center in both directions, pressed into
surface when the temperature of
surfaces not less than 100 deg. C,
protruding 1 mm to 4 mm over mastic
surface, all complete as per clause 515.
Unit = sqm
Taking output = 72.46 sqm (2 tonnes)
(0.869 cum) assuming a density of 2.3
tonnes/cum.
a) Labour
Mate day 0.49 #REF! #REF!
Mazdoor day 11.00 #REF! #REF!
Mazdoor (Skilled) day 1.25 #REF! #REF!
b) Machinery
Mechanical broom @ 1250 sqm per hour 0.06 #REF! #REF!
hour
Air compressor 250 cfm hour 0.06 #REF! #REF!
Mastic cooker 1 tonne capacity hour 6.00 #REF! #REF!
Bitumen boiler 1500 litres capacity hour 6.00 #REF! #REF!
Tractor for towing and positioning of hour 1.00 #REF! #REF!
mastic cooker and bitumen boiler
c) Material
Base mastic (without coarse
aggregates) = 60 per cent
Coarse aggregate(3.35mm to 9.5 mm
size) = 40 per cent .
Proportion of material required for
mastic asphalt with coarse aggregates
(based on mix design done by CRRI for
a specific case)
Page 47
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
i) Bitumen 80/100 or 60/70 or 30/40 @ tonne 0.204 #REF! #REF!
10.2 per cent by weight of mix. 2 x
10.2/100 = 0.204
ii) Crusher stone dust @ 31.9 per cent cum 0.39 #REF! #REF!
by weight of mix = 2 x 31.9/100 = 0.638
tonnes = 0.638/1.625 = 0.39
iii) Lime stone dust filler with calcium tonne 0.36 #REF! #REF!
carbonate content not less than 80 per
cent by weight @ 17.92 per cent by
weight of mix = 2 x 17.92/100 = 0.36
say #REF!
Labour Rate
Labour 1486.38
Overhead charges @05% 74.32
Contractors profit @10% 156.07
Rate for 72.46 sqm 1716.77
Rate per sqm 23.69
say 24.00
Page 48
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
3.The quantities of binder, filler and
aggregates are for estimating purpose.
Exact quantities shall be as per mix
design.
4.This rate analysis is based on design
made by CRRI for a specific case and
is meant for estimating purposes only.
Actual design is required to be done for
each case.
5.The quantity of bitumen works out 17
per cent of the mastic asphalt blocks
without aggregates and falls within the
standards laid down by MoRTH
Specifications.
4.6 2703, Construction of precast RCC railing of
1500, M30 Grade, aggregate size not
1600 & exceeding 12 mm, true to line and
1700 grade, tolerance of vertical RCC post
not to exceed 1 in 500, centre to centre
spacing between vertical post not to
exceed 2000 mm, leaving adequate
space between vertical post for
expansion, complete as per approved
drawings and technical specifications.
Unit = 1 RM
Taking output = 2 x 24 m span = 48 m
a) Material
Cement concrete M30 Grade Refer cum 6.25 4647.33 29055.13
relevant item of concrete in Item 4.1-C
-ii excluding formwork
No. of vertical posts = (12 + 2)2 = 28
Nos., External area of vertical post
0.25x0.275 = 0.069sqm, Concrete in
Vertical posts = 0.069 x 28 = 1.932
cum, Hand rail in 3 tiers = 3 x 24 = 72
m, External area = 0.170 x 0.175 = 0.03
sqm, Concrete in hand rails = 0.03 x 72
= 2.16 cum, Total Concrete = 1.932 +
2.16 = 4.092 cum. (Refer MoRTH SD /
202).
Page 49
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add 5 per cent of above cost for form 1452.76
work for casting in casting yard.
Total 106097.93
b)Overhead charges @ 5 % on (a) 5.0% 5304.90
c)Contractor's profit @ 10 % on (a+b) 10.0% 11140.28
Total 122543.11
Add 1% Labour Cess on Rs 122543.11 1.00% 1225.43
Add 12%GSTon Rs 122543.11 12.00 14705.17
Grand Total 138473.71
Cost for 1RM 138473.71
Rate per 1 RM Rs. 2884.90
Unit = 1 RM
Taking output = 2 x 24 m span = 48 m.
Page 50
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
a) Material
Cement concreteM30 Grade Refer cum 4.092 2835.00 11600.82
relevant item of concrete in Item 4.1(C)
by using batching plant, excluding
formwork i.e. per cum basic cost
(a+b+c)
No. of vertical posts = (12 + 2)2 = 28
Nos., External area of vertical post
0.25x0.275 = 0.069sqm, Concrete in
vehicle posts = 0.069 x 28 = 1.932 cum,
Hand rail in 3 tiers = 3 x 24 = 72 m,
External area = 0.170 x 0.175 = 0.03
sqm, Concrete in hand rails = 0.03 x 72
= 2.16 cum, Total Concrete = 1.932 +
2.16 = 4.092 cum. (Refer MoRTH SD /
202).
Page 51
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Unit = 1 RM
Taking output = 2 x 50 m span = 100 m
a) Material:
1) ISMC 100 = 2.806 x 1.05 = 2.946 MT tonne 2.95 45000.00 132570.00
Unit = 1 No.
Taking output = 1 No.
Page 52
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
a) Material
Corrosion resistant Structural steel Kg 4.00 80.00 320.00
including 5 per cent wastage
GI pipe 100mm dia metre 6.00 120.00 720.00
GI bolt 10 mm Dia each 6.00 55.00 330.00
Galvanised MS flat clamp each 2.00 35.00 70.00
b) Labour
For fabrication
Mate day 0.02 320.83 6.42
Skilled (Blacksmith, welder etc.) day 0.02 374.50 7.49
Mazdoor day 0.02 320.83 6.42
For fixing in position
Mate day 0.01 320.83 3.21
Mason day 0.01 374.50 3.75
Mazdoor day 0.20 320.83 64.17
Add @ 5 per cent of cost of material 4.57
and labour for electrodes, cutting gas,
sealant, anti-corrosive bituminous paint,
mild steel grating etc.
Total 1536.01
c)Overhead charges @ 20 % on (a+b) 20.0% 307.20
Total 2027.54
Add 1% Labour Cess on Rs 2027.54 1.00% 20.28
Add 12%GSTon Rs 2027.54 12.00 243.30
Grand Total 2291.12
Cost for 1 No. 2291.12
Rate per No. Rs. 2291.10
Assistant Engineer Executive Engineer
Haroli Sub-Division Una Division
HPPWD Haroli. HP.PWD. Una.
Note 1. In case of viaducts in urban areas,
the drainage spouts should be
connected with suitably located
pipelines to discharge the surface run-
off to drains provided at ground level.
Page 53
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
4.10 2700 PCC M15 Grade leveling course below
approach slab complete as per drawing
and Technical specification
Unit = 1 cum
Taking output = 1 cum
Material
Concrete, Rate as per item No. 2.8 (A) cum 1.00 5136.90 5136.90
excluding formworks
Rate per cum say 5137.00
4.11 1500,16 Reinforced cement concrete approach
00,1700 slab including reinforcement and
& 2704 formwork complete as per drawing and
Technical specification
Unit = 1 cum
Taking output = 1 cum
a) Material
Cement concreteM30 Grade Refer cum 1.00 6612.50 6612.50
relevant item of concrete in item
2.8(G)by using batching plant,
excluding formwork i.e. per cum basic
cost (a+b+c) (Excluding OH & CP)
Total 9338.05
b)Overhead charges @ 20% on (a) 20.0% 1867.61
c)Contractor's profit @ 10 % on (a+b) 10.0% 1120.57
Total 12326.23
Add 1% Labour Cess on Rs 12326.23 1.00% 123.26
Add 12%GSTon Rs 12326.23 12.00 1479.15
Grand Total 13928.64
Cost for 1 Cum 13928.64
Rate per Cubic metre Rs. 13928.60
Page 54
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Note The grade of reinforced cement
concrete may be adopted as M30 for
severe conditions and M25 for
moderate conditions.
4.12 1600 Providing anti-corrosive treatment to
HYSD reinforcement with Fusion
Bonded Epoxy Coating (FBEC)
Unit = 1 MT
Taking output = 1 MT
To be taken as per the prevailing
market rates.
Note Contractors generally do not have
expertise for this item . The job is
therefore, got done from specialised
firms who have the expertise in the field
of construction chemicals. The
prevailing rate in the market is required
to be ascertained from the market and
added in the cost estimate. Detailed
guidelines in this regard have been
issued by MoRTH vide their circular no.
RW/NH-34041/44/91-S&R dated
21.3.2000.
Unit = 1 cum
Taking output = 1 cum
Grade of concrete - M40
a) Material
Cement tonne 0.47 #REF! #REF!
Coarse sand cum 0.45 #REF! #REF!
20 mm Aggregate cum 0.54 460.00 248.40
10 mm Aggregate cum 0.36 480.00 172.80
Admixture @ 0.4 per cent of cement Kg 1.88 #REF! #REF!
Page 55
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add consumables such as binding wire, #REF!
foam, packing tape, shuttering oil,
HDPE pipe for unbonding of strand, bolt
& nuts etc @ 1 per cent of material
cost
b) Labour
(i) Cutting, bending, making
reinforcement cage, placing in position,
binding etc. complete
Taking quantity of steel 100 Kg/cum of
concrete including laps and wastage
Page 56
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Mate day 0.01 #REF! #REF!
Mazdoor day 0.25 #REF! #REF!
(vii) Placement of girders in position
over pier caps including placement of
sand jacks, channel, levelling etc.
Page 57
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Consumables for sealing joints etc.@ 5 #REF!
per cent of cost of material
b) Labour
Mate day 0.01 #REF! #REF!
Fitter day 0.05 #REF! #REF!
Mazdoor day 0.20 #REF! #REF!
#REF! #REF!
#REF! #REF!
Rate per RM (a+b+c+d) #REF!
say #REF!
Labour Rate
Labour 31.91
Overhead charges @05% 1.60
Contractors profit @10% 3.35
Rate for 1 RM 36.86
Rate per RM 36.86
say 37.00
4.15 800 Crash Barriers
4.16 800 Painting on concrete surface
Providing and applying 2 coats of water
based cement paint to unplastered
concrete surface after cleaning the
surface of dirt, dust, oil, grease,
efflorescence and applying paint @ of 1
litre for 2 sqm.
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.01 #REF! #REF!
Painter day 0.25 #REF! #REF!
Mazdoor (Skilled) day 0.25 #REF! #REF!
b) Material
Water based paint of approved quality Litres 5.00 200.00 1000.00
for cement concrete surface
#REF! #REF!
#REF! #REF!
Cost for 10 sqm (a+b+c+d) #REF!
Rate per sqm (a+b+c+d)/10 #REF!
say #REF!
Labour Rate
Labour 67.38
Overhead charges @05% 3.37
Contractors profit @10% 7.07
Rate for 10 sqm 77.82
Rate per sqm 7.78
say 8.00
Page 58
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
4.17 2604 Burried Joint
Providing and laying a burried
expansion joint, expansion gap being
20 mm, covered with 12 mm thick, 200
mm wide galvanised weldable structural
steel plate as per IS: 2062, placed
symmetrical to centre line of the joint,
resting freely over the top surface of the
deck concrete, welding of 8 mm dia.
100 mm long galvanised nails spaced
300 mm c/c along the centre line of the
plate, all as specified in clause 2604.
Page 59
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
(i) Providing & fixing 2 mm thick
corrugated copper plate in expansion
joint complete as per drawing &
Technical Specification.
Page 60
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
20 mm thick compressible fibre board sqm 3.00 #REF! #REF!
12 m long x 25 cm deep.
Area = 12 x 0.25 = 3 sqm
#REF! #REF!
#REF! #REF!
Cost for 12 m = (a+b+c+d) #REF!
Rate per m = (a+b+c+d)/12 #REF!
say #REF!
Labour Rate
Labour 24.27
Overhead charges @05% 1.21
Contractors profit @10% 2.55
Rate for 12 m 28.03
Rate per RM 2.34
say 2.00
4.18 (iii) Providing and fixing in position 20 mm
thick premoulded joint filler in expansion
joint for fixed ends of simply supported
spans not exceeding 10 m to cater for a
horizontal movement upto 20 mm,
covered with sealant complete as per
drawing and technical specifications.
Page 61
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
HPPWD Haroli. HP.PWD. Una.
4.18 (iv) Providing and filling joint sealing
compound as per drawings and
technical specifications with coarse
sand and 6 per cent bitumen by weight
Page 62
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Providing and laying of asphaltic plug
joint to provide for horizontal movement
of 25 mm and vertical movement of 2
mm, depth of joint varying from 75 mm
to 100 mm, width varying from 500 mm
to 750 mm (in traffic direction), covered
with a closure plate of 200mm x 6mm of
weldable structural steel conforming to
IS: 2062, asphaltic plug to consist of
polymer modified bitumen binder,
carefully selected single size aggregate
of 12.5 mm nominal size and a heat
resistant foam caulking/backer rod, all
as per approved drawings and
specifications.
Page 63
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Labour Rate
Labour 157.74
Overhead charges @05% 7.89
Contractors profit @10% 16.56
Rate for 12 m 182.19
Rate per RM 15.18
say 15.00
Note The nominal size of aggregates shall be
12.5 mm for depth of joint upto 75 mm
and 20 mm for joints of depth more
than 75 mm.
4.20 2606 Elastomeric Slab Steel Expansion Joint
Page 64
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add 5 per cent of cost of material for #REF!
anchorage reinforcement, welding and
other incidentals.
#REF! #REF!
#REF! #REF!
Cost for 12 m = (a+b+c+d) #REF!
Rate per m = (a+b+c+d)/12 #REF!
say #REF!
Labour Rate
Labour 182.01
Overhead charges @05% 9.10
Contractors profit @10% 19.11
Rate for 12 m 210.22
Rate per RM 17.52
say 18.00
4.21 2600 Compression Seal Joint
Providing and laying of compression
seal joint consisting of steel armoured
nosing at two edges of the joint gap
suitably anchored to the deck concrete
and a preformed chloroprene elastomer
or closed cell foam joint sealer
compressed and fixed into the joint gap
with special adhesive binder to cater for
a horizontal movement upto 40 mm and
vertical movement of 3 mm.
Page 65
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Preformed continuous chloroprene metre 12.00 #REF! #REF!
elastomer or closed cell foam sealing
element with high tear strength,
vulcanised in a single operation for the
full length of a joint to ensure water
tightness.
Add 1 per cent of cost of sealing #REF!
element for lubricant-cum-adhesive and
other consumables.
#REF! #REF!
#REF! #REF!
Cost for 12 m = (a+b+c+d) #REF!
Rate per m = (a+b+c+d)/12 #REF!
say #REF!
Labour Rate
Labour 109.20
Overhead charges @05% 5.46
Contractors profit @10% 11.47
Rate for 12 m 126.13
Rate per RM 10.51
say 11.00
Note 1. The installation shall be done by the
manufacturer or his authorised
representative to the satisfaction of the
Engineer.
2. The concreting for joining the
expansion joint assembly with the deck
has not been included in this analysis
as the same is catered in the quantities
of RCC deck.
3. The anchoring bars of the expansion
joint assembly shall be welded to the
main reinforcement of the deck.
Page 66
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Unit = Running meter
Taking output = 12 m
a) Labour
Mate day 0.05 #REF! #REF!
Mazdoor day 1.00 #REF! #REF!
Mazdoor (Skilled) day 0.25 #REF! #REF!
b) Material
Supply of complete assembly of strip metre 12.00 #REF! #REF!
seal expansion joint comprising of edge
beams, anchorage, strip seal element
and complete accessories as per
approved specifications and drawings.
Page 67
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Providing and laying of a modular strip
Box seal expansion joint including
anchorage catering to a horizontal
movement beyond 70 mm and upto
140mm, complete as per approved
drawings and standard specifications to
be installed by the
manufacturer/supplier or their
authorised representative ensuring
compliance to the manufacturer's
instructions for installation.
#REF! #REF!
#REF! #REF!
Cost for 12 m Modular strip/box seal #REF!
joint = (a+b+c+d)
Rate per m = (a+b+c+d)/12 #REF!
say #REF!
Labour Rate
Labour 169.87
Overhead charges @05% 8.49
Contractors profit @10% 17.84
Rate for 12 m 196.20
Rate per RM 16.35
say 16.00
Note 1. The installation shall be done by the
manufacturer or his authorised
representative to the satisfaction of the
Engineer.
Page 68
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
2. The concreting for joining the
expansion joint assembly with the deck
has not been included in this analysis
as the same is catered in the quantities
of RCC deck.
3. The anchoring bars of the expansion
joint assembly shall be welded to the
main reinforcement of the deck.
#REF! #REF!
#REF! #REF!
Cost for 12 m Modular strip/box seal #REF!
joint = (a+b+c+d)
Rate per m = (a+b+c+d)/12 #REF!
say #REF!
Labour Rate
Page 69
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Labour 212.35
Overhead charges @05% 10.62
Contractors profit @10% 22.30
Rate for 12 m 245.26
Rate per RM 20.44
say 20.00
Note 1. The installation shall be done by the
manufacturer or his authorised
representative to the satisfaction of the
Engineer.
2. The concreting for joining the
expansion joint assembly with the deck
has not been included in this analysis
as the same is catered in the quantities
of RCC deck.
3. The anchoring bars of the expansion
joint assembly shall be welded to the
main reinforcement of the deck.
Page 70
CHAPTER - 5
RIVER TRAINING AND PROTECTION WORKS
Sr Ref. to
MoRTH Description Unit Quantity Rate Rs Cost Rs
No Spec.
5.1 2503 Providing and laying boulders apron on
river bed for protection against scour
with stone boulders weighing not less
than 40 kg each complete as per
drawing and Technical specification.
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.00 #REF! #REF!
a) Material cum 0.20 #REF! #REF!
b) Labour
Mate day 0.04 #REF! #REF!
Mason day 0.35 #REF! #REF!
Mazdoor * day 0.75 #REF! #REF!
#REF! #REF!
#REF! #REF!
Rate per cum = (a+b+c+d) #REF!
say #REF!
* Including excavation for trimming for
preparation of bed.
Note Nominal excavation required for
preparation of bed has been taken into
account while making provision for
labour.
Labour Rate
Labour 166.08
Overhead charges @05% 8.30
Contractors profit @10% 17.44
Rate for 1 Cum 191.82
Rate per Cum 191.82
say 192.00
5.2 2503 Boulder Apron Laid in Wire Crates
Page 71
Sr Ref. to
MoRTH Description Unit Quantity Rate Rs Cost Rs
No Spec.
Unit = cum
Taking output = 3 mx1.5mx1.25m = 5.63
cum
a) Material
4mm GI wire crates woven in mesh sqm 22.00 192.00 4224.00
size of 100 mm x 100 mm.
Rate for 1 Sqm = 3.2x 60 =192.00 Rs.
(Mentioned in note)
add 2% of weaving of GI wire as note 2.0% 84.48
given below
Stone cum 5.63 565.13 3181.68
Stone Spalls cum 1.13 565.13 638.60
Total 8128.76
b) Labour
Mate day 0.18 291.67 52.50
Mazdoor (Skilled) day 1.50 291.67 437.51
Mazdoor day *3.00 291.67 875.0
Total 1365.02
Net Total 9493.77
c) Overhead charges @ 5% (a+b ) 5.0% 474.69
d) Contractors Profit @10% (a+b+c) 10.0% 996.85
Total 10965.31
Add 1% Labour Cess on Rs 10965.31 1.00% 109.65
Add 12%GSTon Rs 10965.31 12.00% 1315.84
Grand Total 12390.80
Cost for 5.63 Cum 12390.80
Rate per Cubic metre Rs. 2200.90
Page 72
Sr Ref. to
MoRTH Description Unit Quantity Rate Rs Cost Rs
No Spec.
Unit = cum
Taking out put = 1 cum
Concrete Grade M15 Rate as per cum 1.00 5136.90 5136.90
item No. 2.8 (A) including OH,CP
labour cess and GST
Add 2 per cent of cost to account for 102.74
excavation for preparation of bed,
nominal surface reinforcement and
filling of granular material in
recesses between blocks.
A Stone/Boulder
Unit = cum
Taking output = 1 cum
a) Material
Stone weighing not less than 40kg cum 1.00 #REF! #REF!
b) Labour
Mate day 0.04 #REF! #REF!
Mason day 0.35 #REF! #REF!
Mazdoor day 0.75 #REF! #REF!
Page 73
Sr Ref. to
MoRTH Description Unit Quantity Rate Rs Cost Rs
No Spec.
#REF! #REF!
#REF! #REF!
Rate per cum = (a+b+c+d) #REF!
say #REF!
Labour Rate
Labour 166.08
Overhead charges @05% 8.30
Contractors profit @10% 17.44
Rate for 1 Cum 191.82
Rate per Cum 191.82
say 192.00
5.4 B Cement Concrete Blocks of size 0.3x0.3
x0.3 m cast in cement concrete of Grade
M15
Unit = cum
Taking output = 1 cum
Concrete Grade M15 Rate as per cum 1.00 #REF! #REF!
item No. 2.8 (A)
Add 2 per cent of cost to account for #REF!
nominal surface reinforcement and
filling of granular material in
recesses between blocks.
Rate per cum #REF!
say #REF!
Labour Rate per cum(Same as initem 212.00
2.8-A
5.5 2504 Providing and laying Filter material
underneath pitching in slopes complete
as per drawing and Technical
specification
Unit = cum
Taking output = 1 cum
a) Material
Graded stone aggregate of required cum 1.20 #REF! #REF!
size
b) Labour
Mate day 0.05 #REF! #REF!
Mazdoor (Skilled) day 0.25 #REF! #REF!
Mazdoor * day 1.00 #REF! #REF!
#REF! #REF!
#REF! #REF!
Rate per cum = (a+b+c+d) #REF!
say #REF!
Includes Mazdoor required for trimming
of slope to proper profile and preparation
of bed.
Labour Rate
Page 74
Sr Ref. to
MoRTH Description Unit Quantity Rate Rs Cost Rs
No Spec.
Labour 151.67
Overhead charges @05% 7.58
Contractors profit @10% 15.93
Rate for 1 Cum 175.18
say 175.00
5.6 700 & Geotextile Filter
2504
Unit = sqm
Taking output = 10 sqm.
a) Labour
Mate day 0.02 #REF! #REF!
Mazdoor day 0.30 #REF! #REF!
Mazdoor (Skilled) day 0.10 #REF! #REF!
b) Material
Permeable synthetic geotextile sqm 11.00 #REF! #REF!
including 5 per cent for overlap and
wastage
#REF! #REF!
#REF! #REF!
Cost for 10 sqm = a+b+c+d #REF!
Rate per sqm = (a+b+c+d)/10 #REF!
say #REF!
Labour Rate
Labour 49.00
Overhead charges @05% 2.45
Contractors profit @10% 5.15
Rate for 10 Sqm 56.60
Rate per Sqm 5.66
say 6.00
5.7 2504.4 Toe protection
Page 75
Sr Ref. to
MoRTH Description Unit Quantity Rate Rs Cost Rs
No Spec.
A toe wall for toe protection can either be
in dry rubble masonry in case of dry
rubble pitching or pitching with stones in
wire crates or it can be in PCC M15
nominal mix if cement concert block
have been used for pitching . Rates for
toe wall can be adopted from respective
clauses depending upon approved
design. The rate for excavation for
foundation, dry rubble masonry and PCC
M15 have been analysed and given in
respective chapters.
Unit = cum
Taking output = 1 cum
a) Cement mortor 1:3 (Rate as in Item cum 0.33 #REF! #REF!
2.6 sub-analysis) excluding OH & CP
c) Material
Stone cum 1.00 #REF! #REF!
Stone Spalls cum 0.20 #REF! #REF!
d) Labour
Mate day 0.08 #REF! #REF!
Mason day 0.50 #REF! #REF!
Mazdoor (for laying stones, filling of day 1.50 #REF! #REF!
quarry spalls)
#REF! #REF!
#REF! #REF!
Page 76
Sr Ref. to
MoRTH Description Unit Quantity Rate Rs Cost Rs
No Spec.
Rate per cum = (a+b+c+d+e+f) #REF!
say #REF!
* Includes cement mortar for laying and
filling of joints.
Labour Rate
Labour 289.93
Overhead charges @05% 14.50
Contractors profit @10% 30.44
Rate per Cum 334.87
say 335.00
5.8 B Cement Concrete blocks Grade M15
Unit = cum
Taking Output = 1 cum
Concrete Grade M15 block. (Rate as cum 1.00 #REF! #REF!
per item No. 2.8 (A) including OH &
CP.
Add for cement concrete bedding cum 0.33 #REF! #REF!
(M15 Nominal mix) vide Item 2.8 (A)
including OH & CP. Quantity shall be
adopted as per design ( Assume
Cement Concrete blocks thickness
300mm and cement concrete
bedding thickness 100mm)
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.00 #REF! #REF!
Stone Spalls cum 0.20 #REF! #REF!
b) Labour
Mate day 0.10 #REF! #REF!
Mason day 0.50 #REF! #REF!
mazdoor day 1.50 #REF! #REF!
Page 77
Sr Ref. to
MoRTH Description Unit Quantity Rate Rs Cost Rs
No Spec.
Add 1 per cent of (b) for trimming #REF!
and preparation of base.
#REF! #REF!
#REF! #REF!
Rate per cum = (a+b+c+d) #REF!
say #REF!
Labour Rate
Labour 295.19
Overhead charges @05% 14.76
Contractors profit @10% 30.99
Rate for 1 Cum 340.94
Rate per Cum 340.94
say 341.00
5.10 2507.2 Curtain wall complete as per drawing
and Technical specification
Unit = cum
Taking Output = 1 cum
a) Material
Stone cum 1.00 #REF! #REF!
Stone Spalls cum 0.20 #REF! #REF!
b) Labour
Mate day 0.05 #REF! #REF!
Page 78
Sr Ref. to
MoRTH Description Unit Quantity Rate Rs Cost Rs
No Spec.
Mason day 0.25 #REF! #REF!
Mazdoor day 1.00 #REF! #REF!
Add 1 per cent of cost of (a+b) for #REF!
trimming and preparation of bed.
#REF! #REF!
#REF! #REF!
Rate per cum = (a+b+c+d) #REF!
say #REF!
Labour Rate
Labour 180.44
Overhead charges @05% 9.02
Contractors profit @10% 18.95
Rate for 1 Cum 208.41
Rate per Cum 208.41
say 208.00
5.12 2503.3 Gabian Structure for Retaining Earth
Unit = cum
Taking output = 7 x 3 x 0.6 = 12.60 cum
a) Labour
Mate day 0.28 #REF! #REF!
Mazdoor day 5.00 #REF! #REF!
Mazdoor (Skilled) day 2.00 #REF! #REF!
b) Material
Page 79
Sr Ref. to
MoRTH Description Unit Quantity Rate Rs Cost Rs
No Spec.
Galvanised steel wire crates of mesh sqm 61.00 #REF! #REF!
size 100 mm x 100 mm woven with
4mm dia. GI wire in rolls of required
size.
Stone boulders with least dimension cum 12.60 #REF! #REF!
of 200 mm
Stone spalls of minimum size 25 mm cum 2.52 #REF! #REF!
#REF! #REF!
#REF! #REF!
Cost for 12.60 cum (a+b+c+d) #REF!
Rate per cum (a+b+c+d)/12.60 #REF!
say #REF!
Note Readymade woven wire crate rolls have
been considered in the rate analysis. In
case readymade rolls are not available,
GI wire 4mm dia. @ 32 kg per 10 sqm
may be provided. In that case 2 per cent
of the cost of GI wire may be added for
weaving the wire crates.
Labour Rate
Labour 849.36
Overhead charges @05% 42.47
Contractors profit @10% 89.18
Rate for 12.60 Cum 981.01
Rate per Cum 77.85
say 78.00
5.13 2503.3 Gabian Structure for Erosion Control,
River Training Works and Protection
works
Page 80
Sr Ref. to
MoRTH Description Unit Quantity Rate Rs Cost Rs
No Spec.
Providing and constructing gabian
structures for erosion control, river
training works and protection works with
wire crates of size 2 m x 1 m x 0.3 m
each divided into 1m compartments by
cross netting, made from 4 mm
galvanised steel wire @ 32 kg per 10
sqm having minimum tensile strength of
300 Mpa conforming to IS:280 and
galvanizing coating conforming to
IS:4826, woven into mesh with double
twist, mesh size not exceeding 100 mm
x 100 mm, filled with boulders with least
dimension of 200 mm, all loose ends to
be securely tied with 4 mm galvanised
steel wire.
Unit = cum
Taking output = 2 x 1 x 0.3 x 10 Nos. =
6.00 cum
a) Labour
Mate day 0.14 #REF! #REF!
Mazdoor day 2.50 #REF! #REF!
Mazdoor (Skilled) day 1.00 #REF! #REF!
b) Material
Galvanised steel wire crates of mesh sqm 65.00 #REF! #REF!
size 100 mm x 100 mm woven with
4mm dia. GI wire in rolls of required
size to cover 6.00 cum.
#REF! #REF!
#REF! #REF!
Cost for 6.00 cum (a+b+c+d) #REF!
Rate per cum (a+b+c+d)/6.00 #REF!
say #REF!
Labour Rate
Labour 424.68
Overhead charges @05% 21.23
Contractors profit @10% 44.59
Rate for 6 Cum 490.51
Rate per Cum 81.75
say 82.00
Page 81
Sr Ref. to
MoRTH Description Unit Quantity Rate Rs Cost Rs
No Spec.
Note Readymade woven wire crate rolls have
been considered in the rate analysis. In
case readymade rolls are not available,
GI wire 4mm dia. @ 32 kg per 10 sqm
may be provided. In that case 2 per cent
of the cost of GI wire may be added for
weaving the wire crates.
Page 82
CHAPTER-6
REPAIR AND REHABILITATION
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
6.1 2809 Unit = Sq m ( Thickness 75 mm)
Taking output = 10 sqm
Removal of existing cement concrete
wearing coat including its disposal
complete as per Technical Specification
without causing any detrimental effect to
any part of the bridge structure and
removal of dismantled material with all
lifts and lead upto 1000 m
a) Labour
Mazdoor day 1.00 #REF! #REF!
Mate day 0.06 #REF! #REF!
b) Machinery
Air Compressor 250 cfm with hour 1.00 #REF! #REF!
pneumatic breaker/jack hammer
along with accessories.
Tractor Trolly hour 0.50 390.00 195.00
#REF! 29.68
#REF! 62.33
Cost for 10 sqm = (a+d+c+d) #REF!
Rate per sqm = (a+b+c+d)/10 68.56
say 69.00
Labour Rate
Labour 123.67
Overhead charges @05% 6.18
Contractors profit @10% 12.99
Rate for 10 Sqm 142.84
Rate per Sqm 14.28
say 14.00
6.2 2809 Removal of existing asphaltic wearing
coat comprising of 50 mm thick asphaltic
concert laid over 12 mm thick mastic
asphalt including disposal with all lift and
lead upto 1000 m.
Unit = Sq m
Taking output = 10 sqm
a) Labour
Mate day 0.03 #REF! #REF!
Mazdoor day 0.75 #REF! #REF!
b) Machinery
Air Compressor 250 cfm with hour 0.75 #REF! #REF!
pneumatic breaker.
Page 1
Tractor-trolley. hour 0.40 #REF! #REF!
#REF! #REF!
#REF! #REF!
Cost for 10 sqm = (a+d+c+d) #REF!
Rate per sqm = (a+b+c+d)/10 #REF!
say #REF!
Labour Rate
Labour 91.00
Overhead charges @05% 4.55
Contractors profit @10% 9.56
Rate for 10 Sqm 105.11
Rate per Sqm 10.51
say 11.00
6.3 2807 Guniting concrete surface with cement
mortar applied with compressor after
cleaning surface and spraying with
epoxy complete as per Technical
Specification
Unit = Sq m
Taking output = 1 sqm
Assuming thickness 25 mm
a) Material
Cement kg 16.00 #REF! #REF!
Graded sand cum 0.04 #REF! #REF!
Wire mesh 50mm x 50mm size of kg 2.00 #REF! #REF!
3mm wire
Epoxy kg 0.67 #REF! #REF!
Accelerator compound for guniting kg 0.64 #REF! #REF!
@ 4 per cent of weight of cement
#REF! #REF!
#REF! #REF!
Rate per sqm = (a+b+c+d+e) #REF!
say 505.00
Labour Rate
Labour 25.95
Overhead charges @05% 1.30
Page 2
Contractors profit @10% 2.72
Rate for per Sqm 29.97
Rate per Sqm 29.97
say 30.00
6.4 2800 Providing and inserting nipples with
approved fixing compound after drilling
holes for grouting as per Technical
Specifications including subsequent
cutting/removal and sealing of the hole
as necessary of nipples after completion
of grouting with Cement/Epoxy
Unit = Number
Taking output = 1 No.
a) Material
Nipples each 1.00 #REF! #REF!
Cement, fixing compound and #REF!
consumables @ 15 per cent of cost
of nipple
b) Labour
Mate day 0.01 #REF! #REF!
Mazdoor (Skilled) labour for drilling day 0.08 #REF! #REF!
A Cement Grout
Unit = kg
Taking output = 1 kg
a) Material
Page 3
Cement including 10 per cent kg 1.10 #REF! #REF!
wastage
Admixtures (anti shrinkage #REF!
compound) @ 20 per cent of
cost of cement
b) Labour
Mate day 0.08 #REF! #REF!
Mazdoor (Skilled) day 0.10 #REF! #REF!
Mazdoor day 0.10 #REF! #REF!
c) Machinery
Grout pump with agitator and hour 0.10 #REF! #REF!
accessories
#REF! #REF!
#REF! #REF!
Rate per kg = (a+b+c+d+e) #REF!
say #REF!
Labour Rate
Labour 32.67
Overhead charges @05% 1.63
Contractors profit @10% 3.43
Rate for per kg 37.73
Rate per kg 37.73
say 38.00
B Cement Mortar (1:1) Grouting
Unit = kg
Taking output = 1 kg
a) Material
Cement including 10 per cent kg 0.55 #REF! #REF!
wastage
Sand including 10 per cent wastage kg 0.55 #REF! #REF!
Page 4
37.73
say 38.00
6.6 2800 Patching of damaged concrete surface
with polymer concrete and curing
compounds, initiator and promoter,
available in present formulations, to be
applied as per instructions of
manufacturer and as approved by the
Engineer.
Unit = sqm
Taking output = 10 sqm for an average
thickness of 25mm.
a) Labour
Mate day 0.06 #REF! #REF!
Mazdoor (Skilled) day 0.75 #REF! #REF!
Mazdoor day 0.75 #REF! #REF!
b) Material
a Pre-packed polymer concrete based kg 315.00 #REF! #REF!
on epoxy system complete with
curing compound, intiator and
promoter including 5 per cent
wastage.
c) Machinery
Grout pump with agitator and hour 2.00 #REF! #REF!
accessories
#REF! #REF!
#REF! #REF!
Cost for 10 sqm = a+b+c+d+e #REF!
Rate per sqm = (a+b+c+d+e)/10 #REF!
say #REF!
Note This item is a proprietory item available
in market as pre-packed polymer
concrete and is required to be applied
as per instructions of the manufacturer.
Labour Rate
Labour 182.00
Overhead charges @05% 9.10
Contractors profit @10% 19.11
Rate for per 10 Sqm 210.21
Rate per Sqm 21.02
say 21.00
6.7 2803 Sealing of crack / porous concrete with
Epoxy Grout by injection through nipples
complete as per clause 2803.1.
Unit = kg
Taking output = 1 kg
a) Material
Page 5
Epoxy including 10 per cent kg 1.10 #REF! #REF!
wastage
b) Labour
Mate day 0.08 #REF! #REF!
Mazdoor (Skilled) day 0.10 #REF! #REF!
Mazdoor day 0.10 #REF! #REF!
c) Machinery
Epoxy Injection gun hour 0.10 #REF! #REF!
#REF! #REF!
#REF! #REF!
Rate per kg = (a+b+c+d+e) #REF!
say #REF!
Labour Rate
Labour 32.67
Overhead charges @05% 1.63
Contractors profit @10% 3.43
Rate for per kg. 37.73
37.73
say 38.00
6.8 2804 Applying epoxy mortar over leached,
honey combed and spalled concrete
surface and exposed steel
reinforcement complete as per
Technical Specification
Unit = sqm
Taking output = 10 sqm
Assume average 10mm thickness of
epoxy mortar
a) Material
Epoxy resin-hardener mix for prime kg 2.50 #REF! #REF!
coat
Epoxy mortar kg 2.20 #REF! #REF!
Epoxy resin -hardener mix for seal kg 2.00 #REF! #REF!
coat.
Add 3 per cent cost of material for #REF!
other consumables like acetone etc
and to cover wastage.
b) Labour
Mate day 0.04 #REF! #REF!
Mazdoor (Skilled) day 0.50 #REF! #REF!
Mazdoor day 0.50 #REF! #REF!
#REF! #REF!
#REF! #REF!
Cost for 10 sqm = a+b+c+d #REF!
Rate per sqm = (a+b+c+d)/10 #REF!
say #REF!
Labour Rate
Labour 121.35
Page 6
Overhead charges @05% 6.07
Contractors profit @10% 12.74
Rate for per 10 Sqm 140.16
Rate per Sqm 14.02
say 14.00
6.9 2807 Removal of defective concrete, cleaning
the surface up to 40 mm thickness
thoroughly, applying the shotcrete
mixture mechanically with compressed
air under pressure, comprising of
cement, sand, coarse aggregates, water
and quick setting compound in the
proportion as per clause 2807.1., sand
and coarse aggregates conforming to
IS: 383 and table 1 of IS: 9012
respectively, water cement ratio ranging
from 0.35 to 0.50, density of gunite not
less than 2000 kg/cum, strength not less
than 25 Mpa and workmanship
conforming to clause 2807.6.
unit: sqm
Taking output = 10 sqm, 40 mm average
thickness.
a) Labour
Mate day 0.04 #REF! #REF!
Mazdoor day 0.50 #REF! #REF!
Mazdoor (Skilled) day 0.50 #REF! #REF!
b) Machinery
Air compressor 250 cfm hour 1.00 #REF! #REF!
Shotcreteing equipment hour 1.00 #REF! #REF!
water tanker 6 KL capacity hour 0.02 #REF! #REF!
c) Material
Cement kg 120.00 #REF! #REF!
Sand cum 0.15 #REF! #REF!
Coarse aggregate of size 4.75mm cum 0.15 #REF! #REF!
Page 7
Contractors profit @10% 12.74
Rate for per 10 Sqm 140.16
Rate per Sqm 14.02
say 14.00
6.10 2800 Applying pre-packed cement based
polymer mortar of strength 45 Mpa at 28
days for replacement of spalled concrete
Unit = sqm
Taking output = 10 sqm
Assumed thickness - 10 mm
a) Material
Acrylic polymer bonding coat Litre 1.40 #REF! #REF!
pre-packed cement based polymer kg 12.00 #REF! #REF!
mortar of strength 45 Mpa at 28
days
Add 3 per cent of (a ) above for #REF!
wastage.
b) Labour
Mate day 0.04 #REF! #REF!
Mazdoor (Skilled) day 0.50 #REF! #REF!
Mazdoor day 0.50 #REF! #REF!
#REF! #REF!
#REF! #REF!
Cost for 10 sqm = a+b+c+d #REF!
Rate per sqm = (a+b+c+d)/10 #REF!
say #REF!
Labour Rate
Labour 121.35
Overhead charges @05% 6.07
Contractors profit @10% 12.74
Rate for per 10 Sqm 140.16
Rate per Sqm 14.02
say 14.00
6.11 2805 Epoxy bonding of new concrete to old
concrete
Unit = sqm
Taking output = 10 sqm
a) Material
Epoxy resin with pot life not less kg 8.00 #REF! #REF!
than 60-90 minutes and satisfying
testing as per clause 2803.9
Page 8
#REF! #REF!
Cost for 10 sqm = a+b+c+d #REF!
Rate per sqm = (a+b+c+d)/10 #REF!
say #REF!
Labour Rate
Labour 121.35
Overhead charges @05% 6.07
Contractors profit @10% 12.74
Rate for per 10 Sqm 140.16
Rate per Sqm 14.02
say 14.00
6.12 2810 Providing external prestressing with high
tensile steel wires/strands including
drilling for passage of prestessing steel,
all accessories for stressing and
stressing operation and grouting
complete as per drawing and Technical
Specification
Span assumed: 25 m
No. of cables: 4 no.
No. of anchorages : 8 no.
Unit = MT
Taking output = 1 MT
Assume 12.7mm dia. Strand in 12T13
system. Weight-9.42 kg/m of cable.
a) Material
HTS strand including 5 per cent tonne 1.05 #REF! #REF!
wastage and extra length for jacking
b) Labour
i) For making holes in the structure .
Page 9
ii) For making and fixing anchorages for
cables and placement of cables .
Span assumed: 50 m
No. of cables: 4 no.
No. of anchorages : 8 no.
Unit = MT
Taking output = 3.10 MT
Assume 12.7mm dia. Strand in 19T13
system. Weight-14.73 kg/m of cable.
a) Material
HTS strand including 5 per cent tonne 3.10 #REF! #REF!
wastage and extra length for jacking
Page 10
Tube anchorage set complete with each 8.00 #REF! #REF!
bearing plate, permanent wedges
etc
Epoxy kg 10.00 #REF! #REF!
MS plates for deviator (where tonne 7.00 #REF! #REF!
deviator blocks are not provided)
Add 20 per cent cost of material for #REF!
other materials like lead sheet,
sleeves, deviator fixtures etc.
b) Labour
i) For making holes in the structure .
Page 11
6.14 2810 Providing external prestressing with high
tensile steel wires/strands including
drilling for passage of prestessing steel,
all accessories for stressing and
stressing operation and grouting
complete as per drawing and Technical
Specification
a) Material
HTS strand including 5 per cent tonne 9.28 #REF! #REF!
wastage and extra length for jacking
b) Labour
i) For making holes in the structure .
Page 12
Mate/Supervisor day 1.00 #REF! #REF!
Mason day 5.00 #REF! #REF!
Mazdoor day 20.00 #REF! #REF!
c) Machinery
Stressing jack with pump hour 10.00 #REF! #REF!
Grouting pump with agitator hour 10.00 #REF! #REF!
#REF! #REF!
#REF! #REF!
Cost for 9.28 MT = a+b+c+d+e #REF!
Rate per MT = (a+b+c+d+e)/9.28 #REF!
Say 183860.00
Labour Rate
Labour 21113.94
Overhead charges @05% 1055.70
Contractors profit @10% 2216.96
Rate for 9.28 MT 24386.60
Rate per MT 2627.86
say 2628.00
6.15 2808 Replacement of Bearings complete as
per Technical Specification
Unit = No
Taking output = 3 No.
Lifting of superstructure span by jacking
up from below i.e. by placing the jacks
on pier/abutment caps for span length of
30m.
a) Lifting of span
i) Hire charges for jack of 40 tonne Day 3.00 #REF! #REF!
lifting capacity.
Mate day 0.64 #REF! #REF!
Mazdoor (Skilled) day 4.00 #REF! #REF!
Mazdoor day 12.00 #REF! #REF!
v) Wooden packing cum 0.15 #REF! #REF!
b) Replacement of bearing
Cost of bearing. each 3.00 #REF! #REF!
#REF! #REF!
#REF! #REF!
Cost of repair of 3 bearings = a+b+c+d #REF!
say #REF!
Note The work entails replacement of all the
bearings on one side of the span.
Labour Rate
Labour 1941.39
Overhead charges @05% 97.07
Contractors profit @10% 203.85
Page 13
Rate for 3 No 2242.31
Rate per Unit 747.10
say 747.00
6.16 2808 Rectification of Bearings as per
Technical Specifications
Unit = 1 No
Taking output = 3 No.
a) Lifting of superstructure span by
jacking up from below i.e. by placing the
jacks on pier/abutment caps for span
length of 30m.
say #REF!
Note The rectification of 3 bearings included
in this analysis are on the same side of
the span.
Labour Rate
Labour 1941.39
Overhead charges @05% 97.07
Contractors profit @10% 203.85
Rate for 3 No 2242.31
Rate per Unit 747.10
say 747.00
6.17 Replacement of Expansion Joints
complete as per drawings
Unit -1 RM
Taking output = 12 RM
a) Material
Epoxy for bonding new concrete to kg 9.60 #REF! #REF!
old concrete @ 0.8 kg/sqm
M-30 grade cement concrete cum 3.60 #REF! #REF!
excluding OH & CP (Rate as per
items 14.1 C (i)
b) Labour
Page 14
Removal of old expansion joint including
breaking of concrete, cutting of lugs and
shifting of broken material etc.
Labour Rate
Labour 788.69
Overhead charges @05% 39.43
Contractors profit @10% 82.81
Rate for 12 RM 910.94
Rate per RM 75.91
say 76.00
6.18 Replacement of Damaged Concrete
Railing.
Unit = RM
Taking output = 10 RM
a) Labour
Labour for dismantling old railing and
disposal of dismantled material.
Mate day 0.20 #REF! #REF!
Mazdoor day 5.00 #REF! #REF!
b) Machinery
Tractor-trolley for disposal of hour 1.00 #REF! #REF!
dismantled material
#REF! #REF!
#REF! #REF!
Cost for 10 m = a+b+c+d #REF!
Rate per metre = (a+b+c+d)/10 #REF!
say #REF!
Note The rate for the provision of new railing
may be adopted from the chapter on
superstructure.
Labour Rate
Labour 606.68
Overhead charges @05% 30.33
Contractors profit @10% 63.70
Page 15
Rate for 10 RM 700.72
Rate per RM 70.07
say 70.00
6.19 Replacement of Crash Barrier.
Unit = RM
Taking output = 10 M
a) Labour
Labour for dismantling old railing and
disposal of dismantled material.
Mate day 0.40 #REF! #REF!
Mazdoor day 10.00 #REF! #REF!
b) Machinery
Tractor-trolley for disposal of hour 1.00 #REF! #REF!
dismantled material
#REF! #REF!
#REF! #REF!
Cost for 10 m = a+b+c+d #REF!
Rate per metre = (a+b+c+d)/10 #REF!
say #REF!
Note The rate for the construction of new
crash barrier may be adopted from
chapter 8 on Traffic and Transportation.
Labour Rate
Labour 1213.37
Overhead charges @05% 60.67
Contractors profit @10% 127.40
Rate for 10 RM 1401.44
Rate per RM 140.14
say 140.00
6.20 Replacement of Damaged Mild Steel
Railing
Unit = RM
Taking output = 10 M
a) Labour
Labour for dismantling old railing and
disposal of dismantled material.
Mate day 0.16 #REF! #REF!
Mazdoor day 4.00 #REF! #REF!
b) Machinery
Tractor-trolley for disposal of hour 1.00 #REF! #REF!
dismantled material
#REF! #REF!
#REF! #REF!
Cost for 10 m = a+b+c+d #REF!
Rate per metre = (a+b+c+d)/10 #REF!
say #REF!
Labour Rate
Labour 485.35
Overhead charges @05% 24.27
Page 16
Contractors profit @10% 50.96
Rate for 10 RM 560.58
Rate per RM 56.06
say 56.00
6.21 Repair of Crash Barrier
Repair of concrete crash barrier with
cement concert of M-30 grade by cutting
and trimming the damaged portion to a
regular shape, cleaning the area to be
repaired thoroughly, applying cement
concert after erection of proper form
work.
#REF! #REF!
#REF! #REF!
Cost for 10 m = a+b+c+d #REF!
Rate per m = (a+b+c+d)/10 #REF!
say #REF!
Labour Rate
Labour 121.34
Overhead charges @05% 6.07
Contractors profit @10% 12.74
Rate for 10 RM 140.15
Rate per RM 14.02
say 14.00
6.22 Repair of RCC Railing
Carrying out repair of RCC M30 railing
to bring it to the original shape.
Page 17
It is assumed that damage is to the
extent of 10 per cent .
a) Material
M-30 grade cement concrete cum 0.10 #REF! #REF!
excluding OH & CP (Rate as per
items 4.1 C (i)
HYSD bar reinforcement Rate as tonne 0.01 #REF! #REF!
per item No 4.2(Excluding OH & CP)
b) Labour*
Mate day 0.016 #REF! #REF!
mazdoor day 0.20 #REF! #REF!
* For dismantling and trimming the
surface to a regular shape and removal
of damaged material.
#REF! #REF!
#REF! #REF!
Cost for 10 m = a+b+c+d #REF!
Rate per m = (a+b+c+d)/10 #REF!
say #REF!
Labour Rate
Labour 25.20
Overhead charges @05% 1.26
Contractors profit @10% 2.65
Rate for 10 RM 29.11
Rate per RM 2.91
say 3.00
6.23 Repair of Steel Railing
Repair of steel railing to bring it to the
original shape
It is assumed that the damage to the
steel railing is to the extent of 10 per
cent .
Unit = Running meter.
Taking output = 10 M.
a) Material
Mild steel ISMC series kg 29.00 #REF! #REF!
Flat iron kg 10.00 #REF! #REF!
MS Bolt and nuts kg 1.00 #REF! #REF!
Add 5 per cent of cost of material #REF!
for painting.
b) Labour
Mate day 0.016 #REF! #REF!
Mazdoor (Skilled) day 0.20 #REF! #REF!
Mazdoor day 0.20 #REF! #REF!
#REF! #REF!
#REF! #REF!
Cost of repair for10m = a+b+c+d #REF!
Cost of meter = (a+b+c+d)/10 #REF!
say #REF!
Page 18
Labour Rate
Labour 48.53
Overhead charges @05% 2.43
Contractors profit @10% 5.10
Rate for 10 RM 56.05
Rate per RM 5.60
say 6.00
6.24
Extra for providing and mixing polyester
trinagular synthetic fibres in specified
ratio 6-18mm length''
Page 19
MACHINERY RATE
USAGE RATES OF PLANT & MACHINERY
Item Output of
Sr. No. Description of Usage Rates in Rs. Enhancement
Code machine
@ 80%
Machine Activity Unit Output Unit Rate
Supplying
301 PM-001 Air Compressor 210 cfm cfm 210.00 per hour 275.00 495.00
compressed air
BM, DBM, SDBC,
302 PM-002 Batch mix HMP 40-60 TPH t/h 50.00 per hour 10300.00 18540.00
PM
BM, DBM, SDBC,
303 PM-003 Batch type HMP 30/40 TPH t/h 35.00 per hour 8400.00 15120.00
PM
304/305 PM-004 200 litre Heating of Bitumen litre / h 400.00 per hour 240.00 432.00
309 PM-007 Crane upto 8T Lifting of materials per hour 500.00 900.00
327 PM-012 Hydraulic broom with tractor Surface cleaning sqm/h 1250.00 per hour 320.00 576.00
326 PM-013 Hydraulic Excavator 0.9 cum Excavation cum/h 100.00 per hour 1100.00 1980.00
Mixing of bituminous
335 PM-017 Mixall 6-10 t capacity t/h 8.00 per hour 1450.00 2610.00
materials
Vibrating cement
338 PM-019 Needle vibrator cum/h 3.50 per hour 55.00 99.00
concrete mix
339 PM-020 Paver finisher Laying/spreading t/h 75.00 per hour 2480.00 4464.00
Item Output of
Sr. No. Description of Usage Rates in Rs. Enhancement
Code machine
@ 80%
Machine Activity Unit Output Unit Rate
340 PM-021 Plate compactor Compaction cum/h per hour 55.00 99.00
341 PM-022 Plate vibrator Compaction cum/h per hour 55.00 99.00
342 PM-023 Screed vibrator Compaction cum/h per hour 55.00 99.00
Earth:- Embankment
cum/h 1.14 420.00 756.00
or sub- grade
Surfaces Dressing 2
sqm/h 500.00 420.00 756.00
nd Coat
345 PM-027 Tipper 5.5 cum/10 t Carriage cum/trip 5.50 per hour 275.00 495.00
346 PM-028 Tractor with Disc Harrows Pulverisation of Soil cum/h 80.00 per hour 390.00 702.00
Transportation of
348 PM-030 Tractor with trolley t/trip 3 to 5 per hour 345.00 621.00
material
Tractor with Rotavator Scarifice cum/h 25.00 per hour 390.00 702.00
349 PM-031
Tractor Mount Grader Spreading cum/h 26.00 per hour 690.00 1242.00
350 PM-032 Truck 10 t capacity Carriage cum/trip 5.50 per hour 275.00 495.00
Compaction of Soil
cum/h 100.00 1,390.00 2502.00
WMM
351 PM-033 Vibratory roller 80-100 kN per hour
Compaction of BM cum/h 60.00 1,390.00 2502.00
Item Output of
Sr. No. Description of Usage Rates in Rs. Enhancement
Code machine
@ 80%
Machine Activity Unit Output Unit Rate
Water tanker 6 kl capacity
352 PM-034 Carriage of water liter/h 12000.00 per hour 295.00 531.00
(Truck Mounted)
354 PM-035 Wet mix plant (Pug Mill) Wet mix cum/h 25.00 per hour 1050.00 1890.00
Name of work: Detailed Project Report for Construction of 34.550m R.C.C. Box Cell
Bridge over Chandpur Khad at Km-29/650 on Panjawar - Bathri road Under NABARD.
Unit = each
Taking output = one traffic sign
i) Excavation for foundation
As per item No.11.1 of Chapter 11 cum 0.126 346.90 43.71
ii) Cement concrete M15 grade
As per item No.11.4 of Chapter 11 cum 0.126 4,776.00 601.78
iii) Painting Angle Iron Post with
Primer and two coats of ready
mixed Paint as per specifications
10.4 1700, 800 Direction and Place Identification signs with size 900x600mm
& 300 A. Retro-reflectorised Traffic Signs
Unit = sqm
Taking output = 1.50 sqm
i) Excavation for foundation
As per item No.11.1 of Chapter 11 cum 0.126 346.90 43.71
ii) Cement concrete M-15 grade
As per item No.11.4 of Chapter 11 cum 0.126 4,776.00 601.78
iii) Painting Angle Iron Post with
Primer and two coats of ready
mixed Paint specifications
As per item No.10.7 of Chapter 10 sqm 0.887 103.54 91.84
a) Labour (For fixing at site)
Mate day 0.01 291.67 2.92
Mazdoor (Unskilled) day 0.25 291.67 72.92
b) Material
Mild steel angle iron 75 mm x 75 mm x kg 24.56 55.00 1,350.80
6 mm, 3.50 m long, 2 nos. with 5 per
cent wastage
Aluminium sheeting fixed with 2 mm sqm 0.54 500.00 270.00
encapsulated lens type reflective
sheeting of size including lettering and
signs as applicable background with
epoxy paint
10.4 1700, 800 Direction and Place Identification signs with size 1200x900mm
& 300
A. Retro-reflectorised Traffic Signs
(i) Providing and erecting direction and place identification
retro-\reflectorised sign as per IRC:67 made of encapsulated lens type
reflective sheeting vide Clause 1701.2.3, fixed over aluminium
sheeting, 2 mm thick with area exceeding 0.9 sqm supported on mild
steel angle iron posts 75 mm x 75 mm x 6 mm, 2 Nos. firmly fixed to
the ground by means of properly designed foundation with M-15 grade
cement concrete 450 mm x 450 mm x 600 mm, 600 mm below ground
level as per approved drawing and Technical Specification Clause
1701
Unit = sqm
Taking output = 1.50 sqm
i) Excavation for foundation
As per item No.11.1 of Chapter 11 cum 0.243 346.90 84.30
ii) Cement concrete M-15 grade
As per item No.11.4 of Chapter 11 cum 0.243 4,776.00 1,160.57
iii) Painting Angle Iron Post with
Primer and two coats of ready
mixed Paint specifications
f) Labour
Unit = Each
Taking out put = one typical board
(i) Excavation for foundations
As per item No. 11.1 of Chapter 11 cum 0.252 346.90 87.42
(ii) Cement Concrete M15 grade
As per item No. 11.4 of Chapter 11 cum 0.252 4,776.00 1,203.55
b) Material
2 nos. MS tubes 75mx75mm of 12 kg 63.15 55.00 3,473.25
SWG sheet 2550 mm long
1 nos. MS tubes 75mx75mm of 12 kg 14.29 55.00 785.95
SWG sheet 1200 mm long
1 No. MS tube 47mm x 47mm of 12 kg 4.47 55.00 245.85
SWG 1100 mm long
Angle iron 50mm x 50mm x 5 mm for kg 2.12 55.00 116.60
lugs
1.6 mm thick MS sheet strengthened sqm 1.44 2,000.00 2,880.00
by 25mm x 5 MS flat iron on logo and
middle plate angle iron 25mm x 25mm
x 5mm on bottom plate painting with
stove enameled paint on both sides as
per MORD specifications
10.16 1700 Providing and Fixing 'Logo' of PMGSY Project double sided
Providing and fixing of typical PMGSY Logo as per MORD specifications
and drawing. All M.S. will be stove enameled on both sides. Lettering and
printing arrows, border etc. will be painted with ready mixed synthetic
enamel paint of superior quality in required shade and colour. All sections
of framed posts and steel tube will be painted with primer and two coats of
epoxy paint as per drawing Clause 1701 and Annexure 1700.1
Unit = Each
Taking out put = one typical board
b) Material
10.16 1700 Providing and Fixing Citizen Informatory Board of PMGSY Project
Providing and fixing of typical PMGSY Citizen informatory sign board as per
MORD specifications and drawing. Two MS Plates of 1.6 mm thick duly
welded with MS angle iron frame of 25mm x 25mm x 3mm. The angle iron
frame will be welded to 2 nos. 75mm x 75 mm of 12 SWG sheet tubes
posts duly embedded in cement concrete M-15 grade blocks of 600mm x
600mm x 750mm, 600mm below ground level. All M.S. will be stove
enameled on both sides. Lettering and printing arrows, border etc. will be
painted with ready mixed synthetic enamel paint of superior quality in
required shade and colour. All sections of framed posts and steel tube will
be painted with primer and two coats of epoxy paint as per drawing Clause
1701 and Annexure 1700.1
Unit = Each
Taking out put = one typical board
2x1.00x0.30 = 0.60
2x14x0.05x0.05 = 0.07
b) Material
2 nos. MS tubes 75mx75mm of 12 kg 72.68 55.00 3,997.40
SWG sheet 3050 mm long
2 nos. MS tubes 75mx75mm of 12 kg 23.83 55.00 1,310.65
SWG sheet 1000 mm long
Angle iron 50mm x 50mm x 5 mm for kg 2.12 55.00 116.60
lugs
1.6 mm thick MS sheet strengthened sqm 1.35 2,000.00 2,700.00
by 25mm x 5 MS flat iron on logo and
middle plate angle iron 25mm x 25mm
x 5mm on bottom plate painting with
stove enameled paint on both sides as
per MORD specifications
1 2 3 4 5 6 7 8 9
1 M-119 Sand (Coarse) Cum 600.00 23.00 7.46 45.28 675.74
2 M-120 Sand (Fine) Cum 550.00 23.00 7.46 45.28 625.74
3 M-015 Agg.10mm Cum 650.00 45.35 7.46 52.64 755.45
4 M-016 Agg.20mm Cum 625.00 45.35 7.46 52.64 730.45
5 Agg.25mm Cum 625.00 45.35 7.46 52.64 730.45
6 M-017 Agg.40mm Cum 600.00 45.35 7.46 52.64 705.45
7 M-018 Agg. Crushable type such as
Cum 625.00 45.35 7.46 52.64 730.45
moorum /gravel for grading
8 M-021 GSB Cum 400.00 45.35 7.46 52.64 505.45
9 25-10mm Cum 650.00 45.35 7.46 52.64 755.45
10 10-5mm Cum 650.00 45.35 7.46 52.64 755.45
11 5mm and below Cum 625.00 45.35 7.46 52.64 730.45
12 45-22.4mm Cum 625.00 45.35 7.46 52.64 730.45
13 M-022 22.4-2.36mm Cum 650.00 45.35 7.46 52.64 755.45
14 M-023 2.36mm to 75micron Cum 625.00 45.35 7.46 52.64 730.45
15 9.5-4.75mm Cum 625.00 45.35 7.46 52.64 730.45
16 4.75mm below Cum 600.00 45.35 7.46 52.64 705.45
17 M-031 Binding Material Cum 200.00 23.00 7.46 5.66 236.12
18 M-033 Bitumen (VG-30) Tonne 30080.00 122.04 110.08 1079.70 31391.82
19 Bitumen Emulsion MS Tonne 45000.00 122.04 110.08 53.10 45285.22
20 M-038 Bitumen Emulsion RS-I Tonne 38108.00 122.04 110.08 53.10 38393.22
21 M-039 Bitumen Emulsion SS-I Tonne 39915.00 122.04 110.08 53.10 40200.22
22 M-045 Cement Tonne 6000.00 104.40 104.40 14.16 6222.96
23 M-108 RCC Hume Pipe 900mm dia Per meter 3000.00 72.04 50.30 47.25 3169.59
23 M-108 RCC Hume Pipe 1200mm dia Per meter 4500.00 72.04 50.30 47.25 4669.59
24 M-125 Steel Tonne 45000.00 113.44 104.40 14.16 45232.00
25 M-140 Water K.L. 50.00 0.00 0.00 7.08 57.08
26 - Stone boulder/stone spalls Cum 450.00 45.35 7.46 62.32 565.13
27 M-082 Granular material Cum 250.00 23.00 7.46 45.28 325.74
28 Earth Cum 40.00 23.00 7.46 4.25 74.71
29 Paver Block Per sqm 650.00 45.35 7.46 7.12 709.93
30 G.I Pipe 100 mm dia. Per meter 120.00 0.00 0.00 0.00 120.00
31 G.I Bolt 10 mm dia. Each 55.00 0.00 0.00 0.00 55.00
32 Galvanized MS Flat Clamp Each 35.00 0.00 0.00 0.00 35.00
Certify that lead taken above is shortest and economical
Amount
S. No. Description of Items Unit Quantity Rate (Rs.)
(Rs.)
1 Earth work in excavation of foundation of structures as per drawing and technical Per Cubic 1039.53 174.20 181086.00
specification, including setting out, construction of shoring and bracing, removal Metre
of stumps and other deleterious matter, dressing of sides and bottom and
backfilling with approved material.
2 Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone Per Cubic 7.95 4683.40 37217.00
aggregate 40 mm nominal size mechanically mixed, placed in foundation and Metre
compacted by vibration including curing for 14 days.
3 Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone Per Cubic 86.55 4683.40 405338.00
aggregate 40 mm nominal size mechanically mixed, placed in foundation and Metre
compacted by vibration including curing for 14 days.
4 Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing Per Cubic 43.27 5136.90 222294.00
and Technical Specifications. PCC Grade M15 Metre
5 Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing Per Cubic 266.41 5755.50 1533322.00
and Technical Specifications. PCC Grade M 20 Metre
6 Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing Per Cubic 109.20 5136.90 560949.00
and Technical Specifications. PCC Grade M15 Metre
7 Providing and laying plain / reinforced cement concrete in Sub- structure Per Cubic 57.70 6038.90 348435.00
complete as per drawing and technical specifications. RCC grade M-20 Metre
8 Providing and laying of boulder apron laid in wire crates made with 4mm dia GI Per Cubic 785.92 2200.90 1729731.00
wire conforming to IS: 280 & IS:4826 in 100mm x 100mm mesh (weaved Metre
diagonally) including 10 per cent extra for laps and joints laid with stone
boulders weighing not less than 40 kg each.
Amount
S. No. Description of Items Unit Quantity Rate (Rs.)
(Rs.)
9 Providing and laying of apron with cement concrete blocks of size 0.5x0.5x0.5 m Per Cubic 207.30 5239.64 1086177.00
cast in-situ and made with nominal mix of M-15 grade cement concrete with a Metre
minimum cement content of 250 kg/cum as per IRC: 21-2000. Cement Concrete
Blocks (size 0.5 x 0.5 x 0.5 m)
10 Back filling behind abutment, wing wall and return wall complete as per Per Cubic 38.40 972.30 37336.00
drawings and Technical Specification Clause 1204.3.8 Metre
11 Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, Each 16.00 1020.90 16334.00
wing wall/ return wall with 100 mm dia AC pipe, extending through the full
width of the structure with slope of 1V :20H towards drawing face. Complete as
per drawing and Technical Specifications
Total 6158219.00
Name of work: Detailed Project Report for Construction of 34.550m R.C.C. Box Cell Bridge over Chandpur Khad at Km-
29/650 on Panjawar - Bathri road Under NABARD.
1 Furnishing and placing reinforced/ prestressed cement concrete M30 in super Per Cubic 211.16 8318.40 1756546.00
structure as per drawing and technical specifications. Using concrete mixer Metre
for T-Beam and Slab. RCC grade M-30
2 Supplying, fitting and placing HYSD bar reinforcement in super-structure Per Tonne 20.974 77363.30 1622618.00
complete as per drawing and technical specifications
3 PCC M15 Grade leveling course below approach slab complete as per Per Cubic 10.020 5137.00 51473.00
drawing and Technical specification Metre
4 Furnishing and placing reinforced/ prestressed cement concrete M30 in super Per Cubic 89.888 8318.40 747722.00
structure as per drawing and technical specifications. Using concrete mixer Metre
for T-Beam and Slab. RCC grade M-30
5 Reinforced cement concrete approach slab including reinforcement and Per Cubic 20.040 13928.60 279129.00
formwork complete as per drawing and Technical specification Metre
6 Providing and laying Cement concrete wearing coat M-30 grade including Per Cubic 23.934 12806.00 306504.00
reinforcement complete as per drawing and Technical Specifications Metre
Sr. Rate Amount
Description Of Items Unit Quantity
No. (Rs.) (Rs.)
7 Construction of precast RCC railing of M30 Grade, aggregate size not Per 85.10 2884.90 245505.00
exceeding 12 mm, true to line and grade, tolerance of vertical RCC post not to Running
exceed 1 in 500, centre to centre spacing between vertical post not to exceed Metre
2000 mm, leaving adequate space between vertical post for expansion,
complete as per approved drawings and technical specifications.
8 Providing and fixing Drainage Spout of 100mm dia galvanished MS down No.s 20.00 2291.10 45822.00
pipes typical head of 6mm thick plate, flat iron grating etc complete shown as
per standrad drawing .
9 Providing and fixing in position 20 mm thick premoulded joint filler in Per Metre 120.24 236.10 28389.00
expansion joint for fixed ends of simply supported spans not exceeding 10 m
to cater for a horizontal movement upto 20 mm, covered with sealant
complete as per drawing and technical specifications.
Total 5083708.00
1`
COST ESTIMATE FOR THE CONSTRUCTION OF APPROACHES OF THE BRIDGE
Name of work: Detailed Project Report for Construction of 34.550m R.C.C. Box Cell Bridge over Chandpur Khad at Km-29/650 on Panjawar -
Bathri road Under NABARD.
2 Construction of sub grade and earthen shoulder with approved materials obtained 2 60 7.5 0.30 270.00 Per 233.43 63027
from borrow pits, with in all leads and lifts, transporting to site, spearding Cubic
grading to required slope and compacted to meet requirement of table 300.2 as per Metre
M.O.R.D. technical specifications Clause 303.1
Total 251847
2 Providing and laying cement concrete 1:4:8 complete including the cost of form 346.50 Per 3739.40 1295702
work plain/reinforced concrete in retaining walls, breast walls , as per drawing Cubic
and Technical Specification. Metre
3 Backfilling behind abutment, wing wall and return wall complete as per drawings & 155.01 Per 912.80 141493
technical specification Clause 1204.3.8 Cubic
Metre
4 Providing and laying 100mm dia PVC. pipe weep holes in brick masonry/ stone 204.00 Each 376.60 76826
masonry, plain/reinforced concrete abutment, wing wall, return wall and retaining/breast
walls extending through the full width of the structures with slope of 1(V): 20(H)
towards drawing face complete as per drawing and M.O.R.D. technical specifications
clause 614,709,1204.3.7
Total
1555250
2 Providing, laying, spreading and compacting graded stone aggregate to wet mix 2 60 7.0 0.225 189.00 P/Cum 1649.73 311799
macadam specification including premixing the material with water at OMC in
mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying
in uniform layers in sub-base/base course on a well prepared sub-base and
compacting with smooth wheel roller of 80 to 100kN weight to achieve the
desired density including lighting, barricading and maintenance of diversion, etc
as per Tables 400.11 & 400.12 and Technical Specification Clause 406.
3 Providing and applying primer coat with bitumen emulsion (SS-1) on prepared 2 60 7.0 -- 840.00 Per 46.60 39144
surface of granular base including cleaning of road surface and spraying primer at Sqm
the rate of 0.70-1.0 kg/sqm using mechanical means as per Technical
Specification Clause 502
4 Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion 2 60 7.0 -- 840.00 Per 16.00 13440
distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared granular surfaces Sqm
treated with primer & cleaned with Hydraulic broom as per Technical
Specification Clause 503.
5 Providing and laying 50mm thick Bituminous Macadam with hot mix plant 2 60 7.0 0.050 42.00 P/Cum 6531.30 274315
using crushed aggregates of grading as per Table 500.4 premixed with
bituminous binder, transported to site upto a lead of 1000 m laid over a previously
prepared surface with paver finisher to the required grade, level and alignment and
rolled to achieve the desired compaction as per Technical Specification Clause
504.
Sr. No L B D/H Qty Unit Rate Amount
No Description of Item
1 2 3 4 5 6 7 8 9 10
6 Providing and laying 30mm thick Bituminous concrete with 60-90 TPH batch 2 60 7.0 0.030 25.20 P/Cum 7625.00 192150
type hot mix plant producing an average output of 75 tonnes per hour using
crushed aggregates of specified grading, premixed with bituminous binder @ 5.4
to 5.6 per cent of mix and filler, transporting the hot mix to work site, laying
with a hydrostatic paver finisher with sensor control to the required grade, level
and alignment, rolling with smooth wheeled, vibratory and tandem rollers to
achieve the desired compaction as per MORTH specification clause No. 509
complete in all respects.
Total 955034
7.1 Direction and Place Identification signs with size 900x600mm 4 Each 3055.00 12220
7.2 Direction and Place Identification signs with size 1200x900mm 4 Each 6034.00 24136
Sr. No L B D/H Qty Unit Rate Amount
No Description of Item
1 2 3 4 5 6 7 8 9 10
8 Providing and fixing of typical PMGSY Logo as per MORD specifications and drawing. 2 Each 9045.00 18090
All M.S. will be stove enameled on both sides. Lettering and printing arrows, border etc.
will be painted with ready mixed synthetic enamel paint of superior quality in required
shade and colour. All sections of framed posts and steel tube will be painted with primer
and two coats of epoxy paint as per drawing Clause 1701 and Annexure 1700.1,
{ Providing and Fixing 'Logo' of PMGSY Project double sided}
9 Providing and fixing of typical PMGSY Citizen informatory sign board as per MORD 2 Each 19543.00 39086
specifications and drawing. Two MS Plates of 1.6 mm thick duly welded with MS angle
iron frame of 25mm x 25mm x 3mm. The angle iron frame will be welded to 2 nos.
75mm x 75 mm of 12 SWG sheet tubes posts duly embedded in cement concrete M-15
grade blocks of 600mm x 600mm x 750mm, 600mm below ground level. All M.S. will
be stove enameled on both sides. Lettering and printing arrows, border etc. will be
painted with ready mixed synthetic enamel paint of superior quality in required shade
and colour. All sections of framed posts and steel tube will be painted with primer and
two coats of epoxy paint as per drawing Clause 1701 and Annexure 1700.1 Providing
and Fixing Citizen Informatory Board of PMGSY Project
10 Providing and laying of hot applied thermoplastic compound 2.5 mm thick including
reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of
surface applied glass beads as per IRC:35 .The finished surface to be level, uniform and
free from streaks and holes.
Edge Line+zebra crossing = 2 x 60 x 0.15 = 18+ 100 = 118 118 sqm 575.30 67885
11 Providing & fixing Road Cat Eyes complete as per drawing and technical 200 Each 250.00 50000
specification clause 805 of MORDSpecifications 2013 and direction of the
Engineer.
Total 255743
1 Earth work in excavation of foundation of structures as per drawing and 170.10 Per Cubic 346.90 59008
technical specification, including setting out, construction of shoring and Metre
bracing, removal of stumps and other deleterious matter, dressing of sides
and bottom and backfilling with approved material.
2 Providing and laying of boulder apron laid in wire crates made with 4mm 825.00 Per Cubic 2432.40 2006730
dia GI wire conforming to IS: 280 & IS:4826 in 100mm x 100mm mesh Metre
(weaved diagonally) including 10 per cent extra for laps and joints laid
with stone boulders weighing not less than 40 kg each.
Total 2065738
Name of work: Detailed Project Report for Construction of 34.550m R.C.C. Box Cell Bridge over Chandpur Khad at Km-29/650 on Panjawar -
Bathri road Under NABARD.
1 Providing and applying tack coat with Bitumen emulsion (RS-1) 1 120 7.00 -- 840.00 Per Sqm 16.00 13440
using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on
the prepared granular surfaces treated with primer & cleaned with
Hydraulic broom as per Technical Specification Clause 503.
2 Providing and laying 30mm thick bituminous concrete with 60-90 1 120 7.00 0.030 25.20 P/Cum 7625.00 192150
TPH batch type hot mix plant producing an average output of 75
tonnes per hour using crushed aggregates of specified grading,
premixed with bituminous binder @ min.5.40 per cent of mix and
filler, transporting the hot mix to work site, laying with a hydrostatic
paver finisher with sensor control to the required grade, level and
alignment, rolling with smooth wheeled, vibratory and tandem rollers
to achieve the desired compaction as per MORTH specification clause
No. 509 complete in all respects.
Edge Line+zebra crossing = 2 x 60 x 0.15 = 18+ 100 = 118 118.00 Each 575.30 67885
Total = 273475
Add Enhancement @ 30.5% 83410
G.Total = 356885
Box Cell D/S Toe wall 1 34.550 1.25 0.10 4.32 Cum
Box Cell U/S Toe wall 1 34.550 1.05 0.10 3.63 Cum
Toe wall for Apron U/s & D/s 2 34.550 0.75 0.10 5.18 Cum
Total 7.95 Cum
Sr. Description of Item No. L B H/D Qty
No.
3 Plain cement concrete 1:3:6
nominal mix in foundation with
crushed stone aggregate 40 mm
nominal size mechanically mixed,
placed in foundation and
compacted by vibration including
curing for 14 days.
Toe wall D/S 1st step 1 34.550 1.05 0.70 25.39 Cum
2nd step 1 34.550 0.95 0.70 22.98 Cum
3rd step 1 34.550 0.85 0.70 20.56 Cum
4th step 1 34.550 0.75 0.60 15.55 Cum
5th step 1 34.550 0.65 0.60 13.47 Cum
6th step 1 34.550 0.55 0.60 11.40 Cum
Toe wall U/S 1st step 1 34.550 0.85 0.70 20.56 Cum
2nd step 1 34.550 0.75 0.60 15.55 Cum
3rd step 1 34.550 0.65 0.60 13.47 Cum
4th step 1 34.550 0.55 0.50 9.50 Cum
Both wing walls Base 4 4.00 3.761 0.20 12.04 Cum
1st step 4 4.00 3.561 0.20 11.40 Cum
2nd step 4 4.00 3.361 0.20 10.76 Cum
3rd step 4 4.00 3.161 0.20 10.12 Cum
4th step 4 4.00 2.961 0.20 9.48 Cum
5th step 4 4.00 2.761 0.20 8.84 Cum
6th step 4 4.00 2.661 0.20 8.52 Cum
Sr. Description of Item No. L B H/D Qty
No.
7th step 4 4.00 2.561 0.20 8.20 Cum
Apron D/s & U/S Ends 2 34.550 0.45 0.60 18.66 Cum
Total 266.41 Cum
6 Plain/Reinforced Cement Concrete
in Open Foundation complete as
per Drawing and Technical
Specifications. PCC Grade M15
Box Cells
Bottam 1 34.550 8.35 0.30 86.55 Cum
3-Unit Box cell side walls LHS 2 8.35 0.40 3.00 20.04 Cum
Box Cell Middle walls 2 8.35 0.30 3.00 15.03 Cum
4-Unit Box Cell Sides walls Middle 2 8.35 0.40 3.00 20.04 Cum
(Side Walls)
Box Cell Middle Walls 3 8.35 0.30 3.00 22.55 Cum
3-Unit Box cell side walls RHS 2 8.35 0.40 3.00 20.04 Cum
Box Cell Middle walls 2 8.35 0.30 3.00 15.03 Cum
Bottam Hunch 20 8.35 1/2x(0.20x0.20) 3.34 Cum
202.61 Cum
(0.475+0.425
)/2
Road kerb both side 2 34.550 0.45 0.275 8.55 Cum
Total 211.16 Cum
2 Supplying, fitting and placing
HYSD bar reinforcement in super-
structure complete as per drawing
and technical specifications
Box Cells
Top of Box Cell 1 34.550 8.35 0.30 86.55 Cum
Top Hunch 20 8.35 1/2x(0.20x0.20) 3.34 Cum
Total 89.89 Cum
5 Reinforced cement concrete
approach slab including
reinforcement and formwork
complete as per drawing and
Technical specification
Sr. Kilometre Excavation in earth Cement concrete 1:4:8 Back filling Weep Hole Remarks
Length in
Height in
Location
No. work
mtr.
Mtr
From To Area Qty in Area Qty Area Qty Nos Row Qty
Cum
Retaining
1 22450 22480 RHS 3.00 30.00 1.04 31.19 3.15 94.50 Cum 1.38 41.40 Cum 28 2 56 Nos
wall
Retaining
2 22450 22480 LHS 3.00 30.00 1.13 33.82 3.15 94.50 Cum 1.39 41.76 Cum 28 2 56 Nos
wall
Retaining
3 22520 22545 RHS 3.00 25.00 0.99 24.81 3.15 78.75 Cum 1.43 35.85 Cum 23 2 46 Nos
wall
Retaining
4 22520 22545 LHS 3.00 25.00 1.16 29.03 3.15 78.75 Cum 1.44 36.00 Cum 23 2 46 Nos
wall
110.00 118.85 346.50 Cum 155.01 Cum 204 Nos
BF
Earth Filling
2.30
2.32
3.00
3.00
0.50
0.65
1.04
1.02
1.35 1.35
0.34 0.34
1.39 1.39
Earth Work 1x1.35x(0.50+1.04)/2 1.04 Sqm Earth Work 1x1.35x(0.65+1.02)/2 1.13 Sqm
CC 1:4:8 1x1.35x0.34/2 0.23 Sqm CC 1:4:8 1x1.35x0.34/2 0.23 Sqm
1x(1.35+0.60)/2x3.0 2.92 Sqm 1x(1.35+0.60)/2x3.0 2.92 Sqm
3.15 Sqm 3.15 Sqm
Total Total
Back filling 1x0.60x2.30 1.38 Sqm Back filling 1x0.60x2.32 1.39 Sqm
BF
Earth Filling
2.39
2.40
3.00
3.00
0.52
0.58
0.95
1.14
1.35 1.35
0.34 0.54
1.39 1.39
Earth Work 1x1.35x(0.52+0.95)/2 0.99 Sqm Earth Work 1x1.35x(0.58+1.14)/2 1.16 Sqm
CC 1:4:8 1x1.35x0.34/2 0.23 Sqm CC 1:4:8 1x1.35x0.34/2 0.23 Sqm
1x(1.35+0.60)/2x3.0 2.92 Sqm 1x(1.35+0.60)/2x3.0 2.92 Sqm
3.15 Sqm 3.15 Sqm
Total Total
Back filling 1x0.60x2.39 1.43 Sqm Back filling 1x0.60x2.40 1.44 Sqm
Guide Bund U/S 1st step 2 25.00 2.50 1.25 156.25 Cum
Guide Bund 2nd step 2 25.00 2.20 1.25 137.50 Cum
Guide Bund U/S 3rd step 2 25.00 1.90 1.25 118.75 Cum
Guide Bund D/S 1st step 2 25.00 2.50 1.25 156.25 Cum
Guide Bund D/S 2nd step 2 25.00 2.20 1.25 137.50 Cum
Guide Bund D/S 3rd step 2 25.00 1.90 1.25 118.75 Cum
Total 825.00 Cum
8250/190 = 44
1 a 12 190 5940
6x44 264 1568.16 0.888
8250/95 = 87
2 b 10 95 2210
25x87 = 2175 2175 4806.75 0.617
8250/190 = 44
3 c 8 190 2220
44x25 =1100 1100 2442.00 0.395
8250/200 = 41
4 d 10 200 3520
6x41 = 246 246 865.92 0.617
10300/300 = 35
10 300 7950
2x4x35 = 280 280 2226.00 0.617
5 d1
13600/300 = 45
10 300 7950
4x45 = 180 180 1431.00 0.617
3500/200 = 18
6 d2 10 200 7950
18 x 26 = 468 468 3720.60 0.617
8250/190 = 44
7 e 12 190 7384
7 x44 = 308 2274.27 0.888
8250/150 = 55
10 150 10300
2 x 55 110 1133.00 0.617
8 f
8250/150 = 55
9 g 8 150 3660
7 x 55 = 385 385 1409.10 0.395
8250/190 = 44
10 190 10300
2x 44 = 88 88 906.40 0.617
10 h
8250/95 = 87
11 i 12 95 1900
7 x 87 = 609 609 1157.10 0.888
8250/190 = 44
10 190 10300
2 x 44 = 88 88 906.40 0.617
12 j
10 190 13600
8250/190 = 44 44 598.40 0.617
8250/95 = 87
13 k 12 95 1900
7 x 87 = 609 609 1157.10 0.888
8250/120 = 69
12 120 10300
2 x 69 = 138 138 1421.40 0.888
14 l
12 120 13600
8250/120 = 69 69 938.40 0.888
8250/150 = 55
15 m 8 150 824
14 x 55 = 770 770 634.48 0.395
8250/150 = 55
16 n 8 150 812
12 x 55 = 660 660 535.92 0.395
3761/150 = 25 50
12 150 4000
25 x 2 200.00 0.888
17 o
4000/150 = 27 54
12 150 3761
27 x 2 = 54 203.09 0.888
Total Weight
of steel in
Tonne
EAR OPENING 3.0 X3.0m
Total
Remarks
Weight (Kg)
Side walls
400mm
1392.53 thick
2965.76
964.59
534.27
3-Unit Cell
1373.44
4-Unit Cell
882.93
2295.61
2019.55
3-Unit Cell
699.06
4-Unit Cell
461.52
556.59
3-Unit Cell
559.25
4-Unit Cell
369.21
1027.50
3-Unit Cell
559.25
4-Unit Cell
369.21
1027.50
3-Unit Cell
1262.20
4-Unit Cell
833.30
250.62
211.69
177.60 Approach
slab
180.35
20973.55
PCC Grade M15
Unit = cum
a) Material
Cement tonne 0.275 6483.30 1782.91
Coarse sand cum 0.48 1345.77 645.97
40 mm Aggregate cum 0.48 963.10 462.29
20 mm Aggregate cum 0.24 1013.10 243.14
10 mm Aggregate cum 0.08 1013.10 81.05
Total 3215.36
b) Labour
Mate day 0.08 320.83 25.67
Mason day 0.10 476.00 47.60
Mazdoor day 1.63 320.83 522.95
Bhisti day 0.27 320.83 86.62
Total 682.84
c) Machinery
Concrete mixer (cap. hour 0.40 360.00 144.00
0.40/0.28 cum) Total 144.00
Total (a+b+c) 4042.20
Formwork @ 4% on cost of labour,material and machinery 161.69
Total 4203.89
Add 15% overhead charges +
C.P. 630.58
Total 4834.47
Add 1% L.cess 48.34
Add 12% GST 580.14
Total 5462.95
Rate per cubic meter 5462.95