Method Statement - Turfing and Landscape
Method Statement - Turfing and Landscape
Method Statement - Turfing and Landscape
1. INTRODUCTION
This method statement covers the following work activities associated with the requirement of the contract
document for (your project's name).
It is intended to assist site personnel in carrying out the performance of the activities. It also serves to demonstrate to
the client that we as the contractor understand the work scope and is capable of undertaking it.
2. REFERENCES
2.1 Construction Drawing
2.2 Contract Specification
3. EQUIPMENT
3.1 Back Pusher
3.2 Water Pump and Pipe
3.3 Drum / Water Tank
3.4 Lorry
3.5 One Tonne Roller Compactor
4.1 Topsoil
Topsoil is the original surface layer or soil from cultivated land or forest area. It does not generally include soil from
swampy area, padi field or tin mining areas.
It is usually a darker shade of brown, grey or red than the subsoil that lies immediately beneath it. Topsoil tends to
be friable and show some degree of porosity. It should be free from subsoil, admixture of stones, lumps, plants or
roots and other extraneous matter. Topsoil shall not deliver or used while in a muddy condition.
The sods shall be free from weeds and shall be delivered to site and planted promptly to avoid desiccation.
5.0 METHOD OF PLANTING
5.1 Site Preparation
The Main Contractor is required to grade the planting area to finish grades and allowed for a smooth and uniform to
the consultant approval. The Main Contractor is required to roll, scarify, rake and level so to obtain the even
planting area. All loose stones, gravel, tree stumps in which is not desirable is required to cart away from site to the
approved dumping area. To lay 50mm thick layer of approved black vegetable soil / top soil before turf.
5.2 Close Turfing
Turfing shall be carried out at all the terrace and slope area as specified (refer to the construction drawing).
The grass sod used for close turfing shall be cut and supplied at approximate size of 300mm square and minimum
thickness 50mm with original sod adhering to the roots. The sods shall be 50% pure comprised of Axonupus
Compressus. Close turfing shall consist of approximately 300mm square turfing laid side by side with gaps not
exceeding 30mm. If necessary, each sod shall be stack with 200mm peg through the sod into the soil base, to prevent
soil erosion.
The sods shall be laid onto the surface of the prepared ground with leaf turfs upwards, but jointed as closed as
possible to achieve a uniform cover. The turf shall be laid off planks working over turns previously laid. The whole
area should present an even smooth surface when completed. Top dressing of the turf area shall be carried out
immediately after the turf is laid and monthly intervals thereafter.
5.3 Spot Turfing
Turfing shall be carried out to all the flat area as specified. The grass sod used for turfing shall be cut and supplied at
approximate size of 300mm square and minimum thickness 50mm with original sod adhering to the roots.
The sods shall be 50% pure comprised of Axonupus Compressus. Spot turfing shall consists of approximately
300mm square turfing laid side by side with gaps on all sides of the turfing not exceeding 300mm. If necessary, each
sod shall be stack with 200mm peg through the sod into soil base, to prevent soil erosion.
The sods shall be laid onto the surface of the prepared ground with leaf turfs upwards, but jointed as closed as
possible to achieve a uniform cover. The turf shall be laid off planks working over turns previously laid. The whole
area should present an even smooth surface when completed. Top dressing of the turf area shall be carried out
immediately after the turf is laid and monthly intervals thereafter.
5.5 Watering
Watering shall be carried out immediately after the completion of planting. The completed areas shall be lightly
sprayed with water and keep the areas moist.
5.6 Maintenance
Maintenance shall begin immediately after each portion of turfed and planting area is installed and shall continue for
the period of maintenance as specified commencing from the date of acceptance. Maintenance is including watering,
fertilizing, spraying and mowing.
NPK 15:15:15 shall be used at the rate of 200gms for each plant every month for the first year period. For the next
year after, fertilizing shall be continued every 4 months. This fertilizer must be applied around the plant, outside the
canopy area.
6.0 SAFETY
6.1 Safety
1) The workers shall provide with PPE (Personal Protective Equipment) and shall be worn all the time.
2) During fertilizer work, the workers shall provide additional equipment such as safety goggles and mouth and nose
filters to avoid contact with fertilizer.
3) Site safety member should be available at all the time.
6.2 Environmental
1) The Contractor shall ensure no open burning is allowed at the site.
2) All the waste shall be collected and disposed correctly.
3) The Contractor shall ensure there is no oil leakages from machinery (cutting machine) which is could harm the
environment.