4.SUPREME TREON APQP/1.APQP 2000x1000x9.9kg/1A.ED-021 APQP DEVELOPMENT PLAN

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 10

DOC.NO.

:- FRM-ED-021

HITECH POLYRUBB APQP DEVELOPMENT PLAN REV.NO. :- 00

Date(origin) 04.06.2018

PART NAME: PART NO.: CUSTOMER:

PROJECT START DATE : TARGET DATE : MONTH : ACTUAL COMPL. DATE :


PHASE

PLAN V/S ACTUAL


S. No. ACTIVITY RESP. Remarks
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

1 Marketing Department Receipt the Drawing.

Engineering Department Will receipt the


2
Drawing for Request for Query

3 P

4 NPD shall carry out Cost Estimation

Marketing Department shall submit the


5
Quotation to Customer
PHASE (I) (PLAN & DEFINE)

Cross Functional Team shall study Lesson


6
Learnt Sheet

Cross Functional Team shall study Past


7
Defect History Sheet

Cross Functional Team shall consider


8
Special Characteristics (if any)

Cross Functional Team shall carry out


9
Feasibility Study

NPD shall prepare Bill of Material (if


10
Applicable)

NPD shall prepare Advanced Product & Quality


11 Planning (APQP) Timing Plan as per Advanced
Product & Quality Planning Matrix (APQP)

NPD shall prepare Pre liminary Process


12
Flow Diagram

Legends: P Plan D Delay R Review A Done


Review Frequency:

Prepared by: Approved by:


DOC.NO.:- FRM-ED-021

HITECH POLYRUBB APQP DEVELOPMENT PLAN REV.NO. :- 00

Date(origin)

PART NAME: PART NO.: CUSTOMER:

PROJECT START DATE : TARGET DATE : MONTH : ACTUAL COMPL. DATE :

PLAN V/S ACTUAL


PHASE

S. No. ACTIVITY RESP.


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

13 NPD Department shall study Part Drawing

Cross Functional Team shall prepare


14
PFMEA

15 P
PHASE (II) (PRODUCT DESIGN & DEVELOPMENT)

Cross Functional Team shall describe


16
Gauge Testing Equipment (if Any)

NPD Department shall prepare Tool


17
Development Plan

NPD Department shall prepare Tool Design


18
& Drawing

Marketing Department shall define Sourcing


19
for Raw Material & Bought Out Parts

NPD Department shall conduct Sample Trial


20 run and Machine Parameter Standard with
the help of Cross Functional Team

NPD Department shall Follow up result


21
during Product Development

Legends: P Plan D Delay R Review A Done

Review Frequency:

Prepared by: Approved by:


FRM-ED-021

- 00

04.06.2018

Remarks
DOC.NO.:- FRM-ED-021

HITECH POLYRUBB APQP DEVELOPMENT PLAN REV.NO. :- 00

Date(origin)

PART NAME: PART NO.: CUSTOMER:

PROJECT START DATE : TARGET DATE : MONTH : ACTUAL COMPL. DATE :

PLAN V/S ACTUAL


PHASE

S. No. ACTIVITY RESP.


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

Quality Assurance Department shall prepare


22
MSA Plan

Engineering Department will Follow up result


23
during Product Development
PHASE (III) (PROCESS DESIGN & DEVELOPMENT)

24 P

NPD Department shall Prepare Process


25
Flow Diagram (Prelaunch)

NPD Department shall Prepare Control Plan


26
(Pre Launch)

Production Department shall Study


27
Manpower Planning and Training

NPD shall prepare Operation Control


28
Standard & Work Instruction

Legends: P Plan D Delay R Review A Done

Review Frequency:

Prepared by: Approved by:


FRM-ED-021

- 00

04.06.2018

Remarks
DOC.NO.:- FRM-ED-021

HITECH POLYRUBB APQP DEVELOPMENT PLAN REV.NO. :- 00

Date(origin) 04.06.2018

PART NAME: PART NO.: CUSTOMER:

PROJECT START DATE : TARGET DATE : MONTH : ACTUAL COMPL. DATE :

PLAN V/S ACTUAL


PHASE

S. No. ACTIVITY RESP. Remarks


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

MSA Study shall be done for defined


29
Instrument & Gauges

Cross Functional Team shall conduct


30 Production Trial Run as per Pre Launch
Control Plan

31 P

Quality Assurance Department shall prepare


32 Sample/Production Trial Run Parts
Inspection Report

Cross Functional Team shall carry


33
Packaging Evaluation
PHASE (IV) (PROCESS & PRODUCT VALIDATION)

NPD Department shall submit the Sample to


34
customer as per customer requirement.

Marketing Department shall take Feed Back


35 from Customer (Customer Inspection
Report)

If Sample/Production Trial Run Parts


rejected by Customer then correction shall
36
be done and again Pilot Lot trial Run shall be
conduct.

NPD Department shall conduct PPAP lot


37
preparation

Quality Assurance Department shall carry


38 PPAP lot Inspection on the sampling basis or
as per customer requirement

39 NPD Department shall submit PPAP to Customer

NPD Department shall give Part Submission


40
Warranty

NPD Department shall Prepare Production


41
Control Plan
Legends: P Plan D Delay R Review A Done
Review Frequency:
Prepared by: Approved by:
DOC.NO.:- FRM-ED-021

HITECH POLYRUBB APQP DEVELOPMENT PLAN REV.NO. :- 00

Date(origin)

PART NAME: PART NO.: CUSTOMER:

PROJECT START DATE : TARGET DATE : MONTH : ACTUAL COMPL. DATE :

PLAN V/S ACTUAL


PHASE

S. No. ACTIVITY RESP.


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

NPD Department shall receive Customer


42
Approval

NPD Department shall carry Feedback


43
Analysis & Corrective Action
PHASE (V)

44 P

NPD Department shall take feedback for


45
SOP run at customer end

NPD Department shall take feedback for


46
SOP run at customer (OEM)

Legends: P Plan D Delay R Review A Done

Review Frequency:

Prepared by: Approved by:


FRM-ED-021

- 00

04.06.2018

Remarks