Uzu Sedo Gen Cw348814 00002 - r01 - Planning Procedure
Uzu Sedo Gen Cw348814 00002 - r01 - Planning Procedure
Uzu Sedo Gen Cw348814 00002 - r01 - Planning Procedure
UZU-SEDO-GEN-AA7739-00002
This document is for the property of CICO for TENDER PURPOSES and must not be
reproduced or transmitted to others without Written authorization from the company.
Revision Philosophy
Revisions for review will be issued at R01, with subsequent R02, R03, etc as required.
All revisions approved for issue or design will be issued at A01, with subsequent A02, A03, etc as
required.
Documents approved for Construction will be issued at C01, C02, C03, etc as required
Documents or drawings revised as “As built” will be issued as Z01, Z02 Z03 etc as required
Narrative sections revised from previous approved issues are to be noted in the table below and/or
highlighted in the RH margin (using the appropriate revision status) thus: A02
Previous revision highlighting to be removed at subsequent issues.
Drawings/diagrams revised from previous approved issues are highlighted by 'clouding' the affected
areas and by the use of a triangle containing the revision status.
If a document is cancelled the document will be issued at the next sequential number and suffixed with
a X. For example if 02R is the current revision then 03X will be the Cancelled revision
All revisions to this document must be approved by the relevant Technical authority
Revision History
CONTENTS
1. INTRODUCTION 4
2. PURPOSE 4
4. RESPONSIBILITY 5
7. PROGRESS REPORTING 7
1 APPENDICES 10
2. PURPOSE
This procedure gives a general overview of CONTRACTOR’S Planning and Scheduling activities
developed in order to ascertain that the works are executed in a logical manner in accordance with
the SCHEDULE OF KEY DATES established in the Tendering/bidding scope of work
It aims to set the principles for planning and scheduling on a prescribed format and context to the
satisfaction of both the Client and the Contractor and in alignment with the contractual outlines and
provisions.
Abbreviations
4. RESPONSIBILITY
Project Manager
The Project Manager is responsible of the project execution in accordance with the
CONTRACTOR’S obligation as stipulated in the Contract. He represents the Company in the
discussions, meetings, correspondence and progress payment in relation with the Contract until its
obligation is satisfactorily met.
The Project Engineer is responsible of the Project Scheduling and Progress Monitoring activities. He
makes certain that the reports required in this procedure are satisfactorily met and submitted on
time. He liaises with the department heads to ascertain the correctness of the field reports that
become the basis of Project Schedule and Progress Monitoring reports.
Planning Engineer
The Planning Engineer prepares the detailed Project Schedule based on widely accepted
engineering practices and derived reports on different management hierarchal level.
Software
The Contractor provides the facility and capability to ensure that the Planning and Monitoring reports
are generated through the use of SPDC accepted software (Microsoft excel and Primavera
Enterprise version 8.2). All Schedule, quantities, progress and resourcing data shall be submitted to
SPDC should be in Primavera Enterprise Version 8.2. Back-up of same can be sent also in Microsoft
Excel. These shall be submitted both as native files (XER and MS Excel spreadsheet) and PDF.
Primavera Enterprise Version 8.2 is the preferred and recommended principal planning software to
be used by CONTRACTOR. P6 is fully integrated planning and scheduling system designed to
manage multiple projects into one management structure called, Enterprise Project Structure, EPS.
The lowest level under the EPS is called element or project.
The project will be divided into smaller more manageable components called Work Breakdown
Structure, WBS. Management of the project components is defined in the Organizational Project
Structure, OBS.
Microsoft Office
Microsoft Office shall be used to link progress data collection and reporting with P6. The same data
interfaces with Primavera for the updating of the Project Current Schedule.
7. PROGRESS REPORTING
These activities are grouped into different levels to constitute the WBS.
The activities are assigned with a common driving resource unit that is man-hour. Man-hour is a
common measuring unit to compute the weight factor. Summing up, the project will constitute 100
percent weight factor. The weight factor will be utilized in the Progress Measurement.
Since the Weight Factor is an established unit of Measurement, the total budget man-hours will
remain constant throughout the project execution except when the schedule is revised to account for
approved changes or variations on the SoW. Therefore, on the Baseline Schedule and the Current
Schedule progress evaluation, the following items are taken into consideration in P6 to remain
constant.
Corrective actions can be introduced once the cause and impact on critical activities is identified
and previous agreement with Client is reached for actions to take in order to mitigate any impact of
events out of CONTRACTOR’S control.
After the current schedule is placed on track with the Baseline schedule, the focus of the attention
will be on those activities that fall on the Critical Path (CP). The cycle of this evaluation will
complement the Physical Progress Reporting and evaluation periodically.
Insert WBS
Insert Schedule