Commissioning Schedule

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

28-Feb-18 IKAL_I-18 - Kalsel-1 CFPP (Indonesia) Level 3 Rev.

1 Monthly Updated Schedule_20180228EPC)_Full 2

2018 2019
February March April May June July August September October November December January February March April May

15-Mar-18 29-Mar-18 02-Apr-18 22-Apr-18 26-Apr-18 06-May-18 07-May-18 27-May-18 31-May-18 21-Jun-18 25-Jun-18 07-Jul-18 21-Jul-18 01-Aug-18 10-Aug-18 19-Aug-18 22-Aug-18 02-Sep-18 04-Sep-18 29-Sep-18 03-Oct-18 22-Oct-18 22-Oct-18 13-Nov-18 17-Dec-18 02-Jan-19 02-Jan-19 18-Jan-19 19-Jan-19 05-Feb-19 11-Feb-19 15-Apr-19 21-Apr-19 01-May-19 07-May-19
02-Feb-18 09-Feb-18 13-Feb-18 13-Feb-18 17-Feb-18 12-Feb-18 13-Feb-18 10-Jun-18 14-Jun-18 05-Jul-18 09-Jul-18 16-May-18 30-May-18 19-Jun-18 28-Jun-18 17-Jun-18 20-Jun-18 01-Jul-18 03-Jul-18 17-Aug-18 21-Aug-18 08-Sep-18 08-Sep-18 29-Sep-18 02-Nov-18 18-Nov-18 18-Nov-18 04-Dec-18 05-Dec-18 22-Dec-18 28-Dec-18 01-Mar-19 07-Mar-19 17-Mar-19 23-Mar-19

[Unit 1] - 6.9kV Power WWT System Motor No- RWT System Motor No- Agiator Test for WWT [Unit 2] - EHC Oil Pump [Unit 2] - EHC Oil System [Unit 2] - LV SWGR & MCC [Unit 2] - Bag Filter Interlock [Unit 2] - Closed Cooling [Unit 2] - Air Line Blowing [Unit 2] - Air & Gas Damper [Unit 2] - Boiler FO Initial [Unit 2] - Steam Blowing [Unit 2] - Initial Coal Firing [Unit 2] - AVR offline Test [Unit 2] - Sootblower Actual [Unit 2] - Emissiong Test [Unit 2] - PT Instrument
Receiving Load Test Load Test Clarifier Motor No- Load Test Test Test (B/F & AHS Bldg) Test Water Line Flushing Test Firing Out Test Removal

17-Feb-18 11-Mar-18 15-Mar-18 04-Apr-18 10-Apr-18 30-Apr-18 01-May-18 13-May-18 19-May-18 01-Jun-18 20-Jun-18 05-Jul-18 09-Jul-18 22-Jul-18 23-Jul-18 05-Aug-18 06-Aug-18 23-Aug-18 01-Sep-18 12-Sep-18 21-Sep-18 04-Oct-18 05-Oct-18 22-Oct-18 27-Oct-18 06-Nov-18 15-Nov-18 26-Nov-18 30-Nov-18 18-Dec-18 01-Jan-19 12-Jan-19 12-Jan-19 28-Jan-19 06-Feb-19 22-Apr-19 07-May-19
31-Jan-18 10-Jan-18 14-Jan-18 20-Mar-18 26-Mar-18 16-Feb-18 17-Feb-18 17-Feb-18 23-Feb-18 15-Jun-18 04-Jul-18 24-Apr-18 28-Apr-18 06-Jun-18 07-Jun-18 20-Jun-18 21-Jun-18 21-Jun-18 30-Jun-18 27-Jul-18 05-Aug-18 22-Aug-18 23-Aug-18 08-Sep-18 13-Sep-18 02-Oct-18 11-Oct-18 24-Oct-18 28-Oct-18 03-Nov-18 17-Nov-18 28-Nov-18 28-Nov-18 15-Dec-18 24-Dec-18 08-Mar-19 23-Mar-19

[Unit 1] - Backfeed Power [Unit 2] - IPB Test [Unit 2] - DC & UPS System Agitator Test for RWT Chemical Dosing Test for [Unit 2] - EHC Oil Line [Unit 1] - Condensate [Unit 2] - ACW PP Motor [Unit 2] - Chemical Dosing [Unit 2] - Closed Cooling [Unit 2] - Condensate [Unit 2] - Draft System Test [Unit 2] - Boiler Refractory [Unit 2] - Coal Receiving [Unit 2] - Fly Ash Handling [Unit 2] - Bed Ash Removal [Unit 2] - Steam Admission [Unit 2] - FWH System Test [Unit 2] - Performance
Unit #1 Test Conc. Tank Demi. System Flushing System Test Flushing & N… No- Load Test System Flushing Water System Test System Test (Load Test) Dry Out from Owner No-Load Test System Test for Unit #2 Guarantees Test

28-Feb-18 03-Mar-18 16-Mar-18 17-Mar-18 31-Mar-18 01-Apr-18 18-Apr-18 24-Apr-18 05-May-18 05-May-18 22-May-18 31-May-18 12-Jun-18 12-Jun-18 10-Jul-18 14-Jul-18 24-Jul-18 30-Jul-18 17-Aug-18 18-Aug-18 02-Sep-18 22-Sep-18 06-Oct-18 07-Oct-18 28-Oct-18 11-Nov-18 30-Nov-18 04-Dec-18 18-Dec-18 23-Dec-18 02-Jan-19 11-Jan-19 20-Jan-19 21-Jan-19 06-Feb-19 13-Feb-19 15-Apr-19 21-Apr-19 08-May-19 15-May-19
27-Jan-18 28-Jan-18 15-Jan-18 16-Jan-18 16-Mar-18 17-Mar-18 07-Feb-18 13-Feb-18 11-Feb-18 11-Feb-18 05-Jun-18 14-Jun-18 23-Mar-18 23-Mar-18 29-Apr-18 03-May-18 08-Jun-18 14-Jun-18 15-Jun-18 16-Jun-18 22-Jul-18 11-Aug-18 24-Aug-18 25-Aug-18 14-Sep-18 28-Sep-18 24-Oct-18 28-Oct-18 03-Nov-18 08-Nov-18 18-Nov-18 27-Nov-18 06-Dec-18 07-Dec-18 24-Dec-18 31-Dec-18 01-Mar-19 07-Mar-19 24-Mar-19 31-Mar-19

[Unit 1] - Fire Fighting [Unit 2] - IPB Sealing Test [Unit 2] - F/F System Ready Chemical Dosing System WWT Clarifier Ready [Unit 2] - TBN Oil Pump Demi. Water Transfer [Unit 1] - Condensate [Unit 2] - ACW Line [Unit 2] - CCW PP Motor [Unit 2] - Feedwater System [Unit 2] - Boiler Air Balance [Unit 2] - Refractory [Unit 2] - Bed Ash Handling [Unit 2] - Temporary Piping [Unit 2] - Water & Steam [Unit 2] - Exciter / Electrical [Unit 1] - NDC Test [Unit 2] - PT Instrument [Unit 2] - NDC Test
Pump Test Completed for Batter Room Test for RWT System Motor No- Load Test System Test System Test Flushing No- Load Test Test Test Inspection No- Load Test Restoration Purity Control Test Installation

04-Mar-18 08-Mar-18 02-Apr-18 03-Apr-18 22-Apr-18 23-Apr-18 08-May-18 17-May-18 27-May-18 31-May-18 22-Jun-18 31-Jul-18 11-Aug-18 23-Aug-18 02-Sep-18 04-Sep-18 21-Sep-18 30-Sep-18 11-Oct-18 20-Oct-18 01-Nov-18 10-Nov-18 25-Nov-18 29-Nov-18 18-Dec-18 01-Jan-19 13-Jan-19 13-Jan-19 13-Feb-19 13-Feb-19 15-May-19 15-May-19
29-Jan-18 30-Jan-18 18-Mar-18 19-Mar-18 22-Apr-18 23-Apr-18 18-Feb-18 27-Feb-18 10-Jun-18 14-Jun-18 09-Jun-18 18-Jul-18 29-Jun-18 11-Jul-18 19-Aug-18 21-Aug-18 09-Aug-18 18-Aug-18 29-Aug-18 07-Sep-18 27-Sep-18 06-Oct-18 19-Oct-18 23-Oct-18 03-Nov-18 17-Nov-18 29-Nov-18 29-Nov-18 31-Dec-18 31-Dec-18 31-Mar-19 31-Mar-19

[Unit 1] - TR Area FF Spray [Unit 2] - VAC System [Unit 2] - F/F System Ready RWT Clarifirer System Test [Unit 2] - TBN Lube Oil [Unit 2] - BFP LO Flushing [Unit 2] - Bag Filter Pulse [Unit 2] - Draft System [Unit 2] - Flame Scanner [Unit 2] - CEMS Test [Unit 2] - MV SWGR Test [Unit 2] - Ash Crusher No- [Unit 2] - Lime Stone [Unit 2] - TBN initial Rolling [Unit 1] - COD of Unit#1 [Unit 2] - COD of Un
Test Ready for Battery Room for Each Panel Room Flushing Preparation Air Test Interlock Test Test (CHS Bldg) Load Test Feeding System Test

28-Feb-18 01-Mar-18 30-Mar-18 05-Apr-18 14-Apr-18 15-Apr-18 29-Apr-18 29-Apr-18 20-May-18 22-May-18 02-Jun-18 03-Jun-18 18-Jun-18 20-Jun-18 13-Jul-18 19-Jul-18 31-Jul-18 05-Aug-18 20-Aug-18 21-Aug-18 04-Sep-18 04-Sep-18 21-Sep-18 30-Sep-18 11-Oct-18 13-Oct-18 28-Oct-18 29-Oct-18 21-Nov-18 25-Nov-18 05-Dec-18 09-Dec-18 18-Dec-18 01-Jan-19 14-Jan-19 15-Jan-19 30-Jan-19 05-Feb-19 14-Feb-19 23-Feb-19 06-May-19 15-May-19
26-Jan-18 26-Jan-18 30-Mar-18 05-Apr-18 09-Mar-18 10-Mar-18 15-Feb-18 15-Feb-18 28-Feb-18 02-Mar-18 23-Mar-18 24-Mar-18 21-May-18 23-May-18 03-Jul-18 09-Jul-18 15-Jun-18 20-Jun-18 03-Sep-18 04-Sep-18 12-Jul-18 12-Jul-18 09-Aug-18 18-Aug-18 29-Aug-18 31-Aug-18 14-Sep-18 15-Sep-18 19-Oct-18 23-Oct-18 22-Oct-18 26-Oct-18 03-Nov-18 17-Nov-18 30-Nov-18 01-Dec-18 17-Dec-18 23-Dec-18 01-Jan-19 10-Jan-19 22-Mar-19 31-Mar-19

[Unit 1] - Fire Fighting [Unit 2] - Backfeed Power [Unit 1] - ACW PP Motor RWT Clarifier Ready Multi-Cell Filter Test [Unit 1] - Chemical Dosing [Unit 1] - Draft System [Unit 2] - ID Fan Lube Oil [Unit 2] - Aux Cooling Water [Unit 2] - Turning Gear [Unit 2] - Smoke Air Leak [Unit 2] - MFT Interlock Test [Unit 2] - BLR Blowdown [Unit 2] - Temporary Piping [Unit 2] - Fly Ash Blower [Unit 2] - Coal Crusher [Unit 2] - Fly Ash [Unit 2] - TBN Stretch-out [Unit 1] - PT Instrument [Unit 1] - Reliability Run [Unit 2] - Reliability Run
Pump Motor No- Load Test SWYD No- Load Test System Flushing Interlock Test Flushing System Test Motor No- Load Test Test System Test Restoration Test Motor No- Load Test Recirculation System Test Check Removal Test Test

11-Apr-18 13-Apr-18 30-Apr-18 01-May-18 25-May-18 25-May-18 04-Jun-18 18-Jun-18 10-Jul-18 19-Jul-18 01-Aug-18 03-Aug-18 22-Aug-18 24-Aug-18 07-Sep-18 11-Sep-18 22-Sep-18 25-Sep-18 08-Oct-18 12-Oct-18 23-Oct-18 23-Oct-18 18-Nov-18 07-Dec-18 19-Dec-18 23-Dec-18 16-Jan-19 17-Jan-19
06-Mar-18 08-Mar-18 16-Feb-18 17-Feb-18 05-Mar-18 05-Mar-18 25-Mar-18 08-Apr-18 29-Apr-18 08-May-18 19-Jul-18 21-Jul-18 05-Sep-18 07-Sep-18 22-Jul-18 26-Jul-18 07-Aug-18 10-Aug-18 26-Aug-18 30-Aug-18 09-Sep-18 09-Sep-18 14-Oct-18 02-Nov-18 04-Nov-18 08-Nov-18 02-Dec-18 03-Dec-18

[Unit 1] - Cooling Tower Fan Raw Water Intake Pump DCS ready [Unit 1] - Chemical Dosing [Unit 1] - Feedwater System [Unit 2] - BFP Motor No- [Unit 2] - Turning Gear Test [Unit 2] - Condensate [Unit 1] - Aux. Steam [Unit 2] - Boiler Vent & [Unit 2] - Boiler Chemical [Unit 2] - Sand Handling [Unit 2] - Aux. Steam [Unit 2] - TBN / Generator
Test Test System Test Test Load Test System Test Flushing & N… System Control Valve Test Drain MOV Test Cleaning System Test System Control Valve Test No-load Test

30-Mar-18 02-Apr-18 13-Apr-18 27-Apr-18 08-May-18 21-May-18 01-Jun-18 09-Aug-18 26-Aug-18 04-Sep-18 19-Sep-18 23-Sep-18 12-Oct-18 10-Nov-18 25-Nov-18 14-Dec-18 24-Dec-18 24-Dec-18 22-Jan-19 22-Jan-19
13-Mar-18 16-Mar-18 13-Apr-18 27-Apr-18 18-Feb-18 03-Mar-18 15-Jun-18 23-Aug-18 12-Aug-18 21-Aug-18 04-Aug-18 08-Aug-18 30-Aug-18 28-Sep-18 19-Oct-18 07-Nov-18 09-Nov-18 09-Nov-18 08-Dec-18 08-Dec-18

[Unit 1] - EHC Oil Pump [Unit 2] - LV SWGR & MCC WWT System Test [Unit 2] - TBN Lube Oil [Unit 2] - Loop Seal HP [Unit 2] - Burner Adjstment [Unit 2] - Temporary Piping [Unit 2] - Limestone [Unit 2] - Aux. Steam [Unit 2] - Mechanical
Motor No- Load Test Test ( WT Building) Flushing Blower System Test Installation Handling System Test Function Test Completion

09-Apr-18 10-Apr-18 29-Apr-18 29-Apr-18 23-May-18 24-May-18 13-Jun-18 22-Jun-18 07-Jul-18 08-Jul-18 23-Jul-18 29-Jul-18 10-Aug-18 19-Aug-18 31-Aug-18 06-Sep-18 21-Sep-18 23-Sep-18 09-Oct-18 20-Oct-18 11-Nov-18 20-Nov-18 08-Dec-18 12-Dec-18 26-Dec-18 29-Dec-18 22-Jan-19 23-Jan-19
04-Mar-18 05-Mar-18 15-Feb-18 15-Feb-18 03-Mar-18 04-Mar-18 24-Mar-18 02-Apr-18 24-May-18 25-May-18 13-Jul-18 19-Jul-18 24-Aug-18 02-Sep-18 14-Jul-18 20-Jul-18 12-Aug-18 14-Aug-18 26-Aug-18 06-Sep-18 07-Oct-18 16-Oct-18 03-Nov-18 07-Nov-18 11-Nov-18 14-Nov-18 08-Dec-18 09-Dec-18

[Unit 1] - Cooling Tower Fan Raw Water Intake Motor Potable Water System [Unit 1] - Closed Cooling [Unit 1] - Draft System Test [Unit 2] - SA Fan Lube Oil [Unit 2] - TBN Lube Oil Test [Unit 2] - CEP Motor No- [Unit 1] - Vacuum Pump [Unit 2] - Burner System [Unit 2] - LV SWGR & MCC [Unit 2] - Sand Silo Sand [Unit 2] - Bypass System [Unit 2] - GEN First
Motor No- Load Test No- Load Test Motor No- Load Test Water System Test (Load Test) Flushing Load Test System Test Test Test (CHS Elec Bldg) Receiving Valve Test Synchro.

08-Apr-18 08-Apr-18 24-Apr-18 25-Apr-18 09-May-18 09-May-18 25-May-18 31-May-18 13-Jun-18 15-Jun-18 09-Jul-18 10-Jul-18 02-Aug-18 11-Aug-18 22-Aug-18 05-Sep-18 16-Sep-18 18-Sep-18 01-Oct-18 07-Oct-18 21-Oct-18 21-Oct-18 06-Nov-18 12-Nov-18 25-Nov-18 29-Nov-18 15-Dec-18 16-Dec-18 02-Jan-19 03-Jan-19 24-Jan-19 13-Apr-19
03-Mar-18 03-Mar-18 24-Apr-18 25-Apr-18 23-Feb-18 23-Feb-18 05-Mar-18 11-Mar-18 10-May-18 12-May-18 26-May-18 27-May-18 23-Jul-18 01-Aug-18 07-Jul-18 21-Jul-18 13-Aug-18 15-Aug-18 19-Aug-18 25-Aug-18 07-Sep-18 07-Sep-18 23-Sep-18 29-Sep-18 12-Oct-18 16-Oct-18 01-Nov-18 02-Nov-18 16-Nov-18 17-Nov-18 10-Dec-18 27-Feb-19

[Unit 1] - Fire Fighting [Unit 2] - VAC System Filtered Water Storage Tank Potable Water System Test [Unit 1] - Loop Seal HP [Unit 1] - Boiler Air Balance [Unit 2] - SA Fan System [Unit 2] - Pre-boiler Line [Unit 2] - CW Line Flushing [Unit 2] - Ignitoer & Burner [Unit 2] - Overall Check [Unit 1] - Sootblower Actual [Unit 2] - Coal Conveyor-1 [Unit 2] - Process Aux. [Unit 2] - Bypass System [Unit 2] - Commissioing Test
Ready for Cooling Twer Ready for Each Panel Ro… Ready Blower Motor Solo Run Test Test Test Chemical Cleaning Test Test No- Load Test Steam Line Flushing Cold Function Test (Functional Test)

13-Apr-18 27-Apr-18 23-May-18 24-May-18 16-Jun-18 26-Jun-18 06-Jul-18 07-Jul-18 23-Jul-18 01-Aug-18 12-Aug-18 21-Aug-18 09-Sep-18 10-Sep-18 04-Oct-18 08-Oct-18 21-Oct-18 21-Oct-18 01-Dec-18 20-Dec-18 30-Dec-18 03-Jan-19 13-Jan-19 16-Jan-19
13-Apr-18 27-Apr-18 03-Mar-18 04-Mar-18 13-May-18 23-May-18 01-Jun-18 02-Jun-18 13-Jul-18 22-Jul-18 02-Aug-18 11-Aug-18 03-Aug-18 04-Aug-18 21-Aug-18 25-Aug-18 07-Sep-18 07-Sep-18 29-Oct-18 17-Nov-18 13-Nov-18 17-Nov-18 29-Nov-18 02-Dec-18

[Unit 2] - LV SWGR & MCC Filtered W/S PP Motor No- [Unit 1] - Loop Seal HP [Unit 2] - Cooling Tower Fan [Unit 2] - ID Fan System [Unit 2] - PA Fan System [Unit 1] - Process Aux. [Unit 2] - Lime Stone Blower [Unit 2] - Insulation [Unit 2] - Fly Ash Handling [Unit 2] - Condenser [Unit 2] - HP & LP FWH
(CCB) Test Load Test Blower System Test Motor No- Load Test Test Test Steam Line Flushing Test Completed (Boiler / Pipin… System Test Vacuum Up Test Shell Side Flushing

13-Apr-18 27-Apr-18 23-May-18 11-Jun-18 23-Jun-18 28-Jun-18 11-Jul-18 15-Jul-18 30-Jul-18 01-Aug-18 19-Aug-18 21-Aug-18 12-Sep-18 15-Sep-18 30-Sep-18 03-Oct-18 17-Oct-18 21-Oct-18 01-Nov-18 05-Nov-18 30-Nov-18 09-Dec-18 24-Dec-18 27-Dec-18 13-Jan-19 27-Jan-19
13-Apr-18 27-Apr-18 03-Mar-18 22-Mar-18 03-Apr-18 08-Apr-18 28-May-18 01-Jun-18 20-Jul-18 22-Jul-18 09-Aug-18 11-Aug-18 09-Aug-18 12-Aug-18 17-Aug-18 20-Aug-18 03-Sep-18 07-Sep-18 27-Sep-18 01-Oct-18 17-Oct-18 26-Oct-18 09-Nov-18 12-Nov-18 30-Nov-18 14-Dec-18

[Unit 2] - MV SWGR (CCB) Demi. Water Treatment Compressed Air System [Unit 1] - Boiler Vent & [Unit 2] - SA Fan Motor Solo [Unit 2] - Loop Seal HP [Unit 2] - CWP Motor No- [Unit 2] - Lime Stone Blower [Unit 2] - Boiler Chemical [Unit 2] - Coal Truck Scale [Unit 2] - Coal Conveyor-1 [Unit 2] - Boiler Pressure [Unit 2] - FWH Vent & Drain
Test System Test Test Drain MOV Test Run Test Blower Motor Solo Run Test Load Test No- Load Test Cleaning Preparation Test Load Test Raising Test System Test

04-Apr-18 08-Apr-18 23-Apr-18 28-Apr-18 25-May-18 25-May-18 11-Jun-18 11-Jun-18 28-Jun-18 29-Jun-18 11-Jul-18 22-Jul-18 02-Aug-18 08-Aug-18 19-Aug-18 19-Aug-18 08-Sep-18 12-Sep-18 01-Oct-18 20-Oct-18 30-Oct-18 08-Nov-18 10-Dec-18 19-Dec-18 28-Dec-18 01-Jan-19 14-Jan-19 20-Jan-19
12-Mar-18 16-Mar-18 18-Mar-18 23-Mar-18 05-Mar-18 05-Mar-18 22-Mar-18 22-Mar-18 05-Jun-18 06-Jun-18 28-May-18 08-Jun-18 23-Jul-18 29-Jul-18 11-Jul-18 11-Jul-18 24-Jul-18 28-Jul-18 19-Aug-18 07-Sep-18 16-Sep-18 25-Sep-18 27-Oct-18 05-Nov-18 13-Nov-18 17-Nov-18 01-Dec-18 07-Dec-18

[Unit 1] - TBN Oil Pump [Unit 1] - Aux Cooling Water Filtered Water Supply Pump Demi Water Make-up PP [Unit 1] - Turning Gear [Unit 1] - Burner System [Unit 2] - PA Fan Lube Oil [Unit 2] - Completion of Flue [Unit 1] - Coal Crusher [Unit 2] - Sootblower Dry [Unit 1] - FWH System Test [Unit 2] - Coal Crusher Test [Unit 2] - Boiler Safety Valve [Unit 1] - Emissiong Test
Motor No- Load Test System Test Test Motor No- Load Test Motor No- Load Test Test Flushing Gas Duct Construction Motor No- Load Test Test Poping Test

16-Apr-18 22-Apr-18 19-May-18 21-May-18 06-Jun-18 15-Jun-18 29-Jun-18 01-Jul-18 20-Jul-18 22-Jul-18 09-Aug-18 11-Aug-18 05-Sep-18 14-Sep-18 27-Sep-18 01-Oct-18 27-Oct-18 09-Nov-18 25-Nov-18 15-Dec-18 28-Dec-18 01-Jan-19 14-Jan-19 20-Jan-19
11-Mar-18 17-Mar-18 24-Feb-18 26-Feb-18 10-Apr-18 19-Apr-18 09-Apr-18 11-Apr-18 10-Jul-18 12-Jul-18 30-Jul-18 01-Aug-18 19-Jul-18 28-Jul-18 15-Aug-18 19-Aug-18 29-Sep-18 12-Oct-18 12-Oct-18 01-Nov-18 13-Nov-18 17-Nov-18 01-Dec-18 07-Dec-18

[Unit 1] - ACW Line DWT System Motor No- [Unit 2] - TR Protection Test [Unit 1] - Air Line Blowing [Unit 2] - ID Fan Motor Solo [Unit 2] - PA Fan Motor Solo [Unit 1] - Coal Conveyor-1 [Unit 1] - Condenser [Unit 2] Sampling System [Unit 2] - Coal Storage [Unit 2] - TBN Valve Test [Unit 1] - PT Instrument
Flushing Load Test Run Test Run Test Load Test Vacuum Up Test Test Shed Stacking Test Installation

30-Mar-18 08-Apr-18 28-Apr-18 04-May-18 19-May-18 19-May-18 16-Jun-18 16-Jun-18 02-Jul-18 06-Jul-18 27-Jul-18 29-Jul-18 14-Aug-18 17-Sep-18 03-Oct-18 03-Oct-18 19-Oct-18 20-Oct-18 18-Dec-18 01-Jan-19 21-Jan-19 05-Feb-19
07-Mar-18 16-Mar-18 31-Mar-18 06-Apr-18 25-Feb-18 25-Feb-18 30-Apr-18 30-Apr-18 19-May-18 23-May-18 18-Jun-18 20-Jun-18 01-Jul-18 04-Aug-18 20-Aug-18 20-Aug-18 05-Sep-18 06-Sep-18 03-Nov-18 17-Nov-18 08-Dec-18 23-Dec-18

[Unit 1] - TBN Lube Oil [Unit 1] - ID Fan Lube Oil Demi. Water Storage Tank [Unit 2] - Back Energizing [Unit 1] - Air & Gas Damper [Unit 2] - Bag Filter [Unit 1] - Steam Blowing [Unit 1] - Initial Coal Firing [Unit 1] - AVR offline Test [Unit 2] - Coal FDR & [Unit 1] - Performance
Flushing Preparation Flushing Ready Unit #2 Test Installation Completed Out Tripper Test Guarantees Test

28-Feb-18 07-Jun-18 17-Jun-18 18-Jun-18 05-Jul-18 05-Jul-18 24-Jul-18 24-Jul-18 07-Aug-18 21-Aug-18 31-Aug-18 04-Sep-18 18-Sep-18 23-Sep-18 03-Oct-18 12-Oct-18 21-Oct-18 22-Oct-18 28-Dec-18 01-Jan-19
01-Mar-18 08-Jun-18 01-May-18 02-May-18 31-May-18 31-May-18 10-Jun-18 10-Jun-18 22-Jun-18 06-Jul-18 14-Jul-18 18-Jul-18 05-Aug-18 10-Aug-18 20-Aug-18 29-Aug-18 07-Sep-18 08-Sep-18 13-Nov-18 17-Nov-18

[Unit 1] - Communication [Unit 2] - 6.9kV Power [Unit 2] - Fire Fighting [Unit 1] - Boiler FO Initial [Unit 2] - Chemical Dosing [Unit 1] - Coal Conveyor-1 [Unit 1] - Temporary Piping [Unit 1] - Water & Steam [Unit 1] - Exciter / Electrical [Unit 2] - SH Temperature
System Receiving Ready for Cooling Twer Firing System Test No- Load Test Restoration Purity Control Test Control Test

23-Apr-18 27-Apr-18 12-May-18 14-May-18 01-Jun-18 03-Jun-18 18-Jun-18 22-Jun-18 08-Jul-18 10-Jul-18 24-Jul-18 29-Jul-18 08-Aug-18 12-Aug-18 23-Aug-18 01-Sep-18 26-Sep-18 26-Sep-18 13-Oct-18 13-Oct-18 18-Dec-18 27-Dec-18
06-Apr-18 10-Apr-18 18-Apr-18 20-Apr-18 05-Apr-18 07-Apr-18 29-Mar-18 02-Apr-18 03-Jun-18 05-Jun-18 10-Jun-18 15-Jun-18 29-Jun-18 03-Jul-18 09-Jul-18 18-Jul-18 11-Aug-18 11-Aug-18 30-Aug-18 30-Aug-18 03-Nov-18 12-Nov-18

[Unit 1] - EHC Oil System [Unit 1] - SA Fan Motor Solo [Unit 2] - GCB Test Air Dryer Test [Unit 2] - Cooling Tower Fan [Unit 1] - Boiler Refractory [Unit 1] - Coal Truck Scale [Unit 1] - LV SWGR & MCC [Unit 1] - Aux. Steam [Unit 1] - Steam Admission [Unit 2] - Bed Material
Test Run Test Test Dry Out Test Test (CHS Elec Bldg) Function Test for Unit #1 System Test

03-Apr-18 22-Apr-18 12-May-18 18-May-18 29-May-18 29-May-18 14-Jun-18 17-Jun-18 29-Jun-18 03-Jul-18 14-Jul-18 16-Jul-18 30-Jul-18 13-Aug-18 23-Aug-18 27-Aug-18 18-Sep-18 02-Oct-18 14-Oct-18 17-Oct-18 28-Dec-18 01-Jan-19
17-Mar-18 05-Apr-18 22-Apr-18 28-Apr-18 25-Apr-18 25-Apr-18 25-Mar-18 28-Mar-18 19-Apr-18 23-Apr-18 31-May-18 02-Jun-18 16-Jun-18 30-Jun-18 14-Jul-18 18-Jul-18 05-Aug-18 19-Aug-18 31-Aug-18 03-Sep-18 13-Nov-18 17-Nov-18

[Unit 1] - EHC Oil Line [Unit 1] - PA Fan Lube Oil [Unit 2] - Fire Fighting Air Compressor MTR Test [Unit 1] - CEP Motor No- [Unit 1] - BLR Blowdown [Unit 1] - Refractory [Unit 1] - Coal Storage [Unit 1] - Fly Ash [Unit 1] - HP & LP FWH [Unit 2] - Bed Material
Flushing Flushing Pump Motor No- Load Test Load Test System Test Inspection Shed Stacking Test Recirculation System Test Shell Side Flushing Feeding to Boiler

05-May-18 11-May-18 30-May-18 31-May-18 23-Jun-18 25-Jun-18 25-Jul-18 25-Jul-18 13-Aug-18 22-Aug-18 02-Sep-18 05-Sep-18 18-Sep-18 02-Oct-18 17-Oct-18 18-Oct-18 05-Dec-18 20-Dec-18 30-Dec-18 31-Dec-18
11-Apr-18 17-Apr-18 26-Apr-18 27-Apr-18 15-May-18 17-May-18 11-Jun-18 11-Jun-18 29-Jun-18 08-Jul-18 27-Jul-18 30-Jul-18 05-Aug-18 19-Aug-18 03-Sep-18 04-Sep-18 29-Oct-18 13-Nov-18 16-Nov-18 17-Nov-18

[Unit 1] - SA Fan Lube Oil [Unit 2] - Fire Fighting [Unit 1] - CW Line Flushing [Unit 1] - Boiler Chemical [Unit 1] - MV SWGR Test [Unit 1] - Bed Ash Handling [Unit 1] - Coal FDR & [Unit 1] - TBN / Generator [Unit 2] - Bed Ash Handling [Unit 2] - Coal Silo Coal
Flushing Pump Test Cleaning (CHS Bldg) No- Load Test Tripper Test No-load Test System Test Receiving

01-Jun-18 02-Jun-18 26-Jun-18 03-Jul-18 30-Jul-18 31-Jul-18 28-Aug-18 31-Aug-18 18-Sep-18 27-Sep-18 07-Oct-18 08-Oct-18 23-Oct-18 23-Oct-18 15-Dec-18 16-Dec-18
28-Apr-18 29-Apr-18 18-May-18 25-May-18 16-Jun-18 17-Jun-18 27-Jul-18 30-Jul-18 05-Aug-18 14-Aug-18 18-Aug-18 19-Aug-18 09-Sep-18 09-Sep-18 08-Nov-18 09-Nov-18

[Unit 2] - TR Area FF Spray [Unit 1] - Circulating Water [Unit 1] - Temporary Piping [Unit 1] - Fly Ash Handling [Unit 1] - Bed Material [Unit 1] - Bypass System [Unit 1] - Mechanical [Unit 2] - Limestone Silo
Test System Test Restoration No-Load Test System Test Cold Function Test Completion Receiving

28-May-18 01-Jun-18 19-Jun-18 22-Jun-18 03-Jul-18 05-Jul-18 23-Jul-18 23-Jul-18 13-Aug-18 22-Aug-18 18-Sep-18 02-Oct-18 23-Oct-18 24-Oct-18 26-Dec-18 26-Dec-18
21-Apr-18 01-May-18 11-May-18 14-May-18 21-Apr-18 23-Apr-18 09-Jun-18 09-Jun-18 04-Jul-18 13-Jul-18 05-Aug-18 19-Aug-18 09-Sep-18 10-Sep-18 09-Nov-18 09-Nov-18

[Unit 1] - SA Fan System [Unit 1] - CWP Motor No- [Unit 1] - BFP Motor No- [Unit 1] - Overall Check [Unit 1] - Coal Receiving [Unit 1] - Lime Stone [Unit 1] - GEN First [Unit 2] - Vacuum Pump No-
Test Load Test Load Test from Owner Feeding System Test Synchro. Load Test

25-May-18 02-Jul-18 23-Jul-18 23-Jul-18 26-Aug-18 14-Sep-18 24-Sep-18 27-Sep-18 14-Oct-18 14-Oct-18 27-Dec-18 29-Dec-18
13-Mar-18 20-Apr-18 09-Jun-18 09-Jun-18 21-Jul-18 09-Aug-18 11-Aug-18 14-Aug-18 31-Aug-18 31-Aug-18 10-Nov-18 12-Nov-18

[Unit 1] - BFP LO Flushing [Unit 1] - Insulation [Unit 1] - Sand Handling [Unit 1] - Boiler Pressure [Unit 1] - TBN initial Rolling [Unit 2] - Vacuum Pump
Completed (Boiler / Pipin… System Test Raising Test System Test

27-May-18 11-Jun-18 03-Jul-18 09-Jul-18 19-Jul-18 23-Jul-18 26-Aug-18 14-Sep-18 25-Sep-18 27-Sep-18 15-Oct-18 29-Oct-18 28-Dec-18 01-Jan-19
08-Apr-18 23-Apr-18 21-May-18 27-May-18 05-Jun-18 09-Jun-18 21-Jul-18 09-Aug-18 12-Aug-18 14-Aug-18 01-Sep-18 15-Sep-18 23-Nov-18 27-Nov-18

[Unit 1] - Pre-boiler Line [Unit 1] - Ignitoer & Burner [Unit 1] - Boiler Chemical [Unit 1] - Limestone [Unit 1] - TBN Gland Seal [Unit 1] - FWH Vent & Drain [Unit 2] - TBN Drain System
Chemical Cleaning Test Cleaning Preparation Handling System Test Steam System Test System Test Test

19-May-18 28-May-18 08-Jun-18 12-Jun-18 23-Jun-18 02-Jul-18 14-Jul-18 23-Jul-18 25-Aug-18 27-Aug-18 28-Sep-18 02-Oct-18 15-Oct-18 16-Oct-18 23-Dec-18 25-Dec-18
21-Apr-18 30-Apr-18 02-May-18 12-May-18 11-May-18 20-May-18 31-May-18 09-Jun-18 15-Jul-18 17-Jul-18 15-Aug-18 19-Aug-18 01-Sep-18 02-Sep-18 09-Nov-18 11-Nov-18

[Unit 1] - FO Storage Tank [Unit 1] - PA Fan System [Unit 1] - MFT Interlock Test [Unit 1] - CEMS Test [Unit 1] - Ash Crusher No- [Unit 1] - TBN Valve Test [Unit 1] - TBN Stretch-out [Unit 2] - TBN Gland Seal

1. This commissioning sequence is filtered from SRP


Cleaning & Filling Test Load Test Check Steam System Test

20-May-18 22-May-18 05-Jun-18 07-Jun-18 20-Jun-18 24-Jun-18 15-Jul-18 13-Aug-18 25-Aug-18 27-Aug-18 23-Sep-18 02-Oct-18 28-Dec-18 01-Jan-19
07-Apr-18 09-Apr-18 29-Apr-18 01-May-18 23-May-18 27-May-18 01-Jun-18 30-Jun-18 24-Jul-18 26-Jul-18 10-Aug-18 19-Aug-18 23-Nov-18 27-Nov-18

[Unit 1] - ID Fan Motor Solo


Run Test
[Unit 1] - PA Fan Motor Solo
Run Test
[Unit 1] - Lime Stone Blower
Test
[Unit 1] - Temporary Piping
Installation
[Unit 1] - Fly Ash Blower
Test
[Unit 1] - Generator
Protection Test
[Unit 2] - Vibration
Monitoring System Test 2. TPI appreciate if HGU could updates this every
week.
14-May-18 21-Aug-18 15-Sep-18 24-Sep-18 03-Oct-18 12-Oct-18 23-Dec-18 01-Jan-19
29-May-18 05-Sep-18 29-Jul-18 07-Aug-18 20-Aug-18 29-Aug-18 18-Nov-18 27-Nov-18

[Unit 2] - Communication [Unit 1] - Coal Crusher Test [Unit 1] - TBN Protection [Unit 2] - TBN Protection
System System Test System Test

07-Mar-18 03-Aug-18 26-Aug-18 08-Sep-18 19-Sep-18 26-Sep-18 08-Oct-18 12-Oct-18 13-Dec-18 22-Dec-18
02-Feb-18 01-Jul-18 01-Jul-18 14-Jul-18 16-Aug-18 23-Aug-18 25-Aug-18 29-Aug-18 08-Nov-18 17-Nov-18

[Unit 1] - Fire Fighting & [Unit 1] Sampling System [Unit 2] - Circulating Water [Unit 1] - Vibration [Unit 2] - Generator
Alarm System Test System Test Monitoring System Test Protection Test

29-May-18 02-Jun-18 17-Jun-18 19-Jun-18 03-Jul-18 22-Jul-18 21-Sep-18 26-Sep-18 08-Oct-18 12-Oct-18 23-Dec-18 29-Dec-18
01-May-18 05-May-18 20-May-18 22-May-18 21-May-18 09-Jun-18 05-Aug-18 10-Aug-18 25-Aug-18 29-Aug-18 09-Nov-18 15-Nov-18

[Unit 1] - FO Supply Pump [Unit 1] - Lime Stone Blower [Unit 1] - Sootblower Dry [Unit 1] - Coal Distribution [Unit 1] - TBN Drain System [Unit 2] - Coal Distribution
Motor No- Load Test No- Load Test Test Con. No-Load Test Test Conveyoy Load Test

03-Jun-18 07-Jun-18 23-Jun-18 02-Jul-18 28-Sep-18 02-Oct-18 18-Dec-18 22-Dec-18


06-May-18 10-May-18 11-May-18 20-May-18 15-Aug-18 19-Aug-18 04-Nov-18 08-Nov-18

[Unit 1] - Burner Adjstment [Unit 1] - Flame Scanner [Unit 1] - Boiler Safety Valve [Unit 2] - Coal Distribution
Test Poping Test Con. No-Load Test

03-Jun-18 12-Jun-18 23-Jun-18 05-Jul-18 28-Sep-18 02-Oct-18 20-Dec-18 29-Dec-18


06-May-18 15-May-18 11-May-18 23-May-18 15-Aug-18 19-Aug-18 06-Nov-18 15-Nov-18

[Unit 1] - FO System [Unit 1] - Bag Filter Pulse [Unit 1] - Bed Material [Unit 2] - Coal Conveyor-2
Flushing Air Test Feeding to Boiler Load Test

23-May-18 27-May-18 13-Jun-18 22-Jun-18 18-Sep-18 02-Oct-18 15-Dec-18 19-Dec-18


10-Apr-18 20-Apr-18 16-May-18 25-May-18 05-Aug-18 19-Aug-18 01-Nov-18 05-Nov-18

[Unit 1] - ID Fan System [Unit 1] - FO Supply System [Unit 1] - Bed Ash Removal [Unit 2] - Coal Conveyor-2
Test Test System Test No- Load Test

24-May-18 24-May-18 13-Jun-18 22-Jun-18 28-Sep-18 02-Oct-18 25-Oct-18 13-Jan-19


08-Apr-18 08-Apr-18 01-May-18 10-May-18 15-Aug-18 19-Aug-18 11-Sep-18 30-Nov-18

[Unit 1] - Bag Filter [Unit 1] - Bag Filter Interlock [Unit 1] - SH Temperature [Unit 1] - Commissioing Test
Installation Completed Test Control Test (Functional Test)

05-Jun-18 01-Nov-18
02-May-18 28-Sep-18

[Unit 2] - Fire Fighting &


Alarm System

01-Jun-18 01-Jun-18 18-Jun-18 27-Jun-18 27-Sep-18 03-Oct-18


09-Apr-18 09-Apr-18 26-May-18 04-Jun-18 11-Aug-18 17-Aug-18

[Unit 1] - Smoke Air Leak [Unit 1] - TBN Lube Oil Test [Unit 1] - Coal Distribution
Test Conveyoy Load Test

31-May-18 31-May-18 30-Jun-18 02-Jul-18 19-Sep-18 23-Sep-18 05-Oct-18 06-Oct-18


08-Apr-18 08-Apr-18 07-Jun-18 09-Jun-18 03-Aug-18 07-Aug-18 18-Aug-18 19-Aug-18

[Unit 1] - Completion of Flue [Unit 1] - Turning Gear Test [Unit 1] - Coal Conveyor-2 [Unit 1] - Coal Silo Coal
Gas Duct Construction No- Load Test Receiving

02-Jun-18 05-Jun-18 25-Sep-18 04-Oct-18


20-Mar-18 23-Mar-18 08-Aug-18 17-Aug-18

[Unit 1] - Closed Cooling [Unit 1] - Coal Conveyor-2


Water Line Flushing Load Test

31-May-18 01-Jun-18 20-Sep-18 20-Sep-18


18-Mar-18 19-Mar-18 11-Aug-18 11-Aug-18

[Unit 1] - CCW PP Motor [Unit 1] - Vacuum Pump No-


No- Load Test Load Test

09-Apr-18 17-Jun-18 15-Sep-18 19-Sep-18 03-Oct-18 06-Oct-18


17-Mar-18 25-May-18 10-Aug-18 14-Aug-18 14-Aug-18 17-Aug-18

[Unit 1] - TBN Lube Oil [Unit 1] - Sand Silo Sand [Unit 1] - Bypass System
Flushing Receiving Valve Test

13-May-18 27-May-18 15-Sep-18 16-Sep-18


31-Mar-18 14-Apr-18 10-Aug-18 11-Aug-18

[Unit 1] - LV SWGR & MCC [Unit 1] - Limestone Silo


Test (B/F & AHS Bldg) Receiving

01-Sep-18 20-Sep-18
31-Jul-18 19-Aug-18

[Unit 1] - Fly Ash Handling


System Test

06-Sep-18 25-Sep-18
31-Jul-18 19-Aug-18

[Unit 1] - Bed Ash Handling


System Test

Non-driving, non-critical
Actual Work
Remaining Work Driving, non-critical
Critical Remaining Work Critical
Milestone
Summary Data Date Line