CIRED2011 0499 Final

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

CIRED 21st International Conference on Electricity Distribution Frankfurt, 6-9 June 2011

Paper 0499

TECHNICAL IMPLEMENTATION OF CROSS BONDING ON UNDERGROUND HIGH


VOLTAGE LINES PROJECTS

António Sobral Ângela Moura Maria Carvalho


EDP Distribuição – Portugal EDP Distribuição – Portugal EDP Distribuição – Portugal
[email protected] [email protected] [email protected]

 : Sheath loss factor;


Where:

 : Armour loss factor;


ABSTRACT

: Resistance of the conductor at service temperature;


In three-phase underground systems of monopole cables the
: Conductor current carrying capacity at permanent regime.
metallic sheaths are connected to earth at certain points of the
circuit. The alternated current that flows on the conductor core
causes energy losses on the sheaths due to the inductive and
Foucault currents, which results in additional losses decreasing Substituting the equations 2, 3 and 4 in the Equation 1 results:
the transmission capacity of the power lines. A solution to
1
Δ  
       
reduce those losses is to connect the shield to earth. This paper

 2
presents the main differences between the several methods of
  1         
connecting the sheaths to the earth, to reduce the losses and to
improve the distribution capacity. It will be also presented a
case study that supports a technical and economic validation of Equation 6
cross bonding implementation on the project phase.
The Equation 6 allows to quantify the losses on a circuit of
INTRODUCTION underground cables, namely to different types of sheaths
connections to earth as it is presented on the section of the
In three-phase underground systems of monopole cables the “Case Study” section. Note that for different types of sheaths

constant, just change the loss factor .


losses of a cable on permanent regime can be expressed, connection to earth, keeping the other installation conditions of
according Neher-McGrath, through the following circuit:

SHEATHS CONNECTIONS TO EARTH


SCHEMES
To reduce the influence of the sheaths current on the energy
losses, one of the schemes presented can be applied to connect
Figure 1. Equivalent electrical scheme [1] the shields to the earth. Thus, it is possible to increase the cable
current carrying capacity as well as make the three-phase
Considering the Figure 1, it can be obtain the temperature system more balanced.
variation, ∆t, through the following equation:
Both ends bonding
1
∆    
   
       
        
2
The magnetic field effect caused by the phase conductor current
induces a longitudinal voltage along the metallic sheaths of the
Equation 1 cables. This voltage is proportional to the length of the
underground power line. Therefore, to reduce the risk of
 : Conductor Joule losses;
Where: excessive voltages the sheaths are grounded at their both ends.

: Dielectric losses on the conductor isolation;
 : Sheath losses;
 : Armour losses;
: Thermal resistance between the conductor and the sheath;
 : Thermal resistance of the internal sheath;
 : Thermal resistance of the external sheath;
 : Thermal resistance of the environment.

To derive an expression from where the ampacity can be


directly calculated, the heat sources W’s, that represent the
electrical losses, are expressed as proportion of the Wc – the Figure 2 – Both ends bonding
conductor losses. The conductor losses are obtained through the
conductor resistance and the respective current. Thus, As it can be verified in Figure 2, this scheme establishes a

   
closed circuit for the induced currents. The induced currents
circulation results in heat and consequent reduction of cable
   
Equation 2 current carrying capacity. The constant current flow through the
sheaths during normal operation of the power line leads to
  
Equation 3
increased losses and to the need of oversize the section of the
Equation 4 cable conductors to guarantee a certain carrying capacity. Given

Paper No 0499 1/4


CIRED 21st International Conference on Electricity Distribution Frankfurt, 6-9 June 2011

Paper 0499

the above, to avoid this disadvantage the sheath circuit should appropriate cross bonding boxes to the sheaths. These boxes
be interrupted or the sheaths should be connected to the earth include SVL.
according particular schemes which do not allow the closed
circuit between them.

One end bonding


To eliminate the effect of the induced current, one of the sheath
ends can be disconnected. However, in this situation it can be
observed on the other end of the circuit an increasing of the
voltage that is proportional to the length of the line, as well as a
potential difference between the sheaths. As long the circuit is,
the voltage on the sheaths can take prohibitive values.

Single point
For circuits up to 1 km [2], the effect of the potential increases Figure 4 – Cross bonding [2]
can be minimised introducing a sheath voltage limiter (SVL) in
star configuration with the centre connected to earth. The SVL In this solution, the length of the circuit is not a limitation. For
lock the circulation of current in normal operation and in case of this reason, the cross bonding sheaths has a greater applicability
short circuits. to the electrical distribution systems. The main disadvantage of
this method is because it can become an expensive
implementation.

CROSS BONDING COMPONENTS


To a cross bonding system implementation the following
equipments are applied:

a) Cross bonding boxes to execute the crossing of the sheaths.


These boxes include SLV and each box should have an earth
electrode itself for create an earth return circuit in each divided
section of the line.

Figure 3 – Single point bonding [2]

The point at which the shields are bonding between them and
connected to the earth is one of the ends of the power line.
Although, if in this situation are generated high voltages on the
sheaths the bonding point can be moved to an intermediate
point.

In this method, it is provided a return circuit for the induced


currents through an earth copper continuity conductor [3] that
allows balancing the electrical potential at both ends of the Figure 5– Cross bonding box [4]
circuit, avoiding constant flowing of the currents by the sheaths
during normal operation of the power line. The continuity These boxes should be watertight and capable of containing the
conductor should be insulated to prevent corrosion problems effects of the thermal or electrical failures of any element inside
and it should be installed as close as possible to the three-phase the box, including a possible internal short circuit.
circuit to minimize the voltage increase results from a defect in
one phase. The section and electrical conductivity of that To facilitate its maintenance, these boxes should be installed in
conductor should be suitable for the short-circuit current of the joints boxes with easy access (for example through the
system. placement of manholes) and they should not be at more than
one meter below the ground level [3].
A disadvantage on this method is the fact that it only can be
implemented on limited lengths of cable because the induced b) Direct bonding boxes are usually applied on the ends of the
voltages are proportional to the circuit length. line to connect the sheath directly to earth. These boxes include
earth electrode but, unlike cross bonding boxes, they do not
Cross bonding include SLV.
For underground circuits longer than 1 km, the losses on the
metallic sheaths can be minimized making in each joint a cross c) Kits for shield interruption: it is necessary for each phase
bonding of the cable shields. This method consists in dividing joint to introduce an additional kit to remove the shield outside
the cable length into three approximately equal sections with the the respective box and to connect a concentric cable. Is this
sheaths connected and grounded at the ends of the circuit. Thus, coaxial cable that will connect the sheaths to the cross bonding
the vectorial sum of the induced voltage is practically null. The boxes.
natural points to establish the crossings are the joints, where

Paper No 0499 2/4


CIRED 21st International Conference on Electricity Distribution Frankfurt, 6-9 June 2011

Paper 0499

d) Cables to the sheaths connection to cross bonding boxes: 48 k€. Analysing the graphics in Figure 8 and 9 it can be
should be coaxial cables insulated with XLPE (cross linked verified that for nominal load capacity, the cross bonding
polyethylene) or flexible monopole conductors. The section of implementation represents a gain of 10.600W (17.000 W –
these cables is determined by the maximum value of short 6.400 W) related with the sheaths losses by the Joule effect, per
circuit current of the power line. cable, comparing to the both ends bonding solution.

Considering the monopole conductors solution, instead of the


coaxial cables one, it is not necessary to include the additional
kits for shield interruption. Thus, the monopole conductors are
directly connected to the cross bonding boxes.

The sheaths connections should be designed to minimise the


cable length, which should not exceed the 10 meters [3].

Figure 8 – Shield losses with both ends bonding [2]

Figure 6 – Cross bonding installation

CASE STUDY
The case study presented is an underground power line, with a
nominal transport capacity of 120 MVA, through three-phase
alternated current with a frequency of 50 Hz and a voltage of
63kV. This line is constituted by six LXHIOLE 1x1000/135
mm2 cables and its length is 2.900 meters.

The analysis of the carrying-current capacity in the scenarios Figure 9 – Shield losses with cross bonding [2]
following presented had the cooperation of a firm representative
of the cables sector that developed the sheath loss studies
regarding different types of connections to earth. SCENARIO II - Single point solution
To minimise the cables sheaths losses by single point
In the economic assessment performed, it was not considered implementation, the total circuit was divided in four sections of
the costs related to men power regarding the implementation identical lengths, as it is illustrated in Figure 10.
neither to costs of maintenance.

SCENARIO I - Cross bonding solution


To minimise the cables sheaths losses by cross bonding
implementation, the total circuit was divided in six sections of
identical lengths, as it is illustrated in Figure 7.

Figure 10 – Scenario II connections scheme (single point)

Figure 7 – Scenario I connections scheme (cross bonding)


For the equipment applied in scenario II the cost investment is
208 k€. Analysing the Figure 11 graphic, for nominal load
A market survey was conducted for the equipment costs to capacity, the single point solution results in a gain of 12.200 W
implement the scenario I resulting in a total investment cost of (17.000 W - 4.800 W) per cable, regarding the sheath losses,
when compared to the both ends bonding solution.

Paper No 0499 3/4


CIRED 21st International Conference on Electricity Distribution Frankfurt, 6-9 June 2011

Paper 0499

To avoid these additional losses, the shields are connected to


earth following schemes which exclude the formation of close
circuits between them, or that can cancel the electromotive
forces induced in the possible closed circuits. Achieved that
objective, it appears in addition to the benefits referred, two
others:

• The separation distance between phases can be increased


to achieve better heat dissipation to the environment;
• As the necessary conductor section can be smaller the
capacitive current absorbed by the line is also lower.
Figure 11 – Shield losses with single point bonding [2]
For the case study presented are remarkable the gains inherent
Analysing of the scenarios described previously, and in these types of solutions - cross bonding and single point.
considering an operation of 60% of the nominal load capacity, Moreover, it is concluded that the amortisation period of
for the scenario I (cross bonding solution) it results in a gain of investment required for their implementations is reduced when
approximately 56 MWh per cable per year. Assuming that the compared with the lifetime of an installation of underground
unit losses value is 0,0595 €/kWh, it would be obtained a total high voltage power lines- 30 years.
losses cost of 3.300€ per year and per cable, so for the six
cables it would be 20 k€ per year. Considering the data presented in the case study, the gains
obtained during the lifetime of an underground line are
For the scenario II (single point solution), and considering an approximately 550 k€ and 480 k€ to the solutions of the cross
operation of 60% of the nominal load capacity, it was obtained and single point bonding, respectively. Additionally, it is the
a gain of approximately 64 MWh per cable per year. Assuming solution of cross bonding that is the most advantaged because it
that the unit losses value is 0,0595 €/kWh, it would result in a has an initial investment of about three times lower than the
total cost losses of around 3.800 € per year and per cable, so for single point solution.
the six cables it would be 23 k€ per year.
On the other hand, the single point solution increases men
As a conclusion, it can be calculated that for the scenarios I and power for their implementation and maintenance costs, inherent
II the amortisation period of the respective investments are 2,5 in the earth continuity conductor. Moreover, the reliability of
and 9,0 years, respectively. this kind of systems can also become smaller because of the
existence of the additional conductor between the direct
CONCLUSIONS bonding boxes and the boxes with SLV that in case of defect is
not easily detectable.
In a three-phase alternated current, the system formed by the
shields and their connections is a secondary circuit strongly
linked to the primary circuit, formed by the main conductors
REFERENCES
submitted at the grid voltage. Thus, during the normal operation [1] Francisco de León, 2005, "Calculation of Underground
of phase cables it may appear considerable intensity currents Cable Ampacity".
flowing at the shields that generate additional losses.
[2] Pedro Cavaleiro, 2006, "Esquemas de ligação à terra da
The type of the sheaths connection to earth influences the blindagem", Solidal Condutores Eléctricos, S.A.
ampacity in the monopole underground cables, reflected by the
loss factor λ (see Equation 6). Actually, this can be considered [3] General Cable, 2005, "Ligações à terra em circuitos de
the second most important parameter for calculating the current- alta tensão".
carry capacity in a cable, after the external thermal resistance of
that cable. For this reason, it is an important aspect to be [4] Tyro Elecrtonic Energy Division, “Link boxes – Cross
considered at the design and construction of underground power bonding and sectionalisation for high voltage cable
lines. systems”.

Considering the additional losses and heating due to the current [5] B. Novák, L. Koller and I. Berta, 2010, "Loss reduction in
shield, it should be and adopted, in many cases, mitigation cable sheathing".
methods. It is characterised in this document schemes for
grounding the shields more often used: [6] Norberto dos Santos Nunes, 2007, "Cálculo de Parâmetros
de Cabos Subterrâneos para Redes de Distribuição".
• Both ends bonding;
• One end bonding;
• Single point;
• Cross bonding.

The system grounding at both ends provides a closed circuit for


the induced currents generating additional heat production, with
the consequent reduction of the transmission capacity of the
line.

Paper No 0499 4/4

You might also like