Construction of Decks
Construction of Decks
Construction of Decks
1. OBJECT
2. SCOPE
3. RELATED DOCUMENTS
4. RESPONSIBILITIES
5. PROCEDURE
5.1.- Description of the works
5.2.- Materials, Plant and Equipment
6.- QUALITY
6.1- Witness and Hold Points
7.- SAFETY
1. - OBJECT
POST RESPONSIBILITIES
The purpose of this Method Statement is to Surveying as built
provide an outline procedure which will positions of both
enable those people involved in the crossheads.
construction of the decks to do so in a diligent
manner and to follow the correct technical Section Organise human and
standards. Manager mechanical means.
/Site Agent
In addition it provides the frame work to
undertake the work in a safer manner and Foreman Organise human and
with due care of environmental matters mechanical means;
execute works as per this
2. - SCOPE Method Statement;
guarantee works are
This scope of works involves all in-situ done in a safe manner.
activities required for the construction of
decks including, assembling of the Quality and Monitor all the aspects
reinforcement, shuttering the reinforcement, Environment of works regarding
setting levels and pouring the concrete for all Manager quality or environment
new decks over the entire M50 project. on the site
Noise from the varoius machines / High Noisy areas should be accurately defined using a noise
excavators / pumping equipment meter. Low
vibrators etc leading to hearing loss. Ear defenders to be provided, maintained and worn.
White fingers from excessive vibration Noise control measures to be practised. These include,
closing plant engine covers or erecting earth, plywood
or some other dense material screen in the path of the
noise.
Rotation between operatives during vibration of
concrete and scabbling Low
Persons incapacitated to work due to Low Persons under the suspicion of drugs and alcohol to be
influence of drugs and alcohol disciplined and removed from site.
The undermining of adjacent structures Medium The stability of adjacent structures to be assessed and
leading to their collapse. where appropriate precautions taken. This may require
a structural survey
Overall Environment media including Variabl Comply with any environmental impact Low
wildlife and plants e assessment/study and any other contract environmental
conditions
Low
Un Loading Shutters Un loading area to be clear of all unnecessary
Crushing injury High personnel
All Slings to be choked & visually checked
All certs will be in M50 D&C safety office Low
Tag lines to be on all lifts
Banks man to be in full view of truck crane operator
Installing Shutter All carpenters to operate a buddy system at all times Low
High lifting shutters and timbers
All off cuts to be removed on an ongoing basis
Carpenters will hand ball shutters into excavations and
assemble them.
All clips not used to replaced in silages
Low
ITP, Structures
DOCUMENTED ACTIVITIES NECESSARY TO BE COMPLETED FRECUENCY CONTROL DOCUMENTS RESPONSABILITY VERIFYING DOCUMENT SREMARKS
BEFORE CONSTRUCTION
placeConfirm risk assessments and Method Statements are in Each Structure Method Statement I (H.P.) W.P. M M M Engineers Level Book
Verify that main setting out is completed in the area and Each Structure Relevant drawings I (H.P.) W.P. W.P. M M Survey book
MATERIALS
Confirm all materials are approved for use Each Structure Cl 1705 I & N (H.P.) I (H.P.) H.P. W.P. H.P. RAM & RSF Product Certificate
Signed delivery docket 12 Hours notice
DURING CONSTRUCTION
Set out structure Each Location Relevant drawings I & N (H.P.) I (H.P.) W.P. M M Survey
Excavate and approve subformation Each Formation DrawingsLevel as specified on I & N (H.P.) I (H.P.) H.P. I(H.P .) H.P. RISF
prepare formation Each Formation DrawingsLevel as specified on I & N (H.P.) I (H.P.) W.P. M M MAR
Approve formation Each Formation Bearing capacity required I & N (H.P.) I (H.P.) I (H.P.) I (H.P.) I (H.P.) RISF& Laboratory 24 Hours notice
reports
Place blinding Each Formation Relevant drawings I & N (H.P.) I (H.P.) W.P. M M RIW 3 Hours notice
Confirm all Pile testing carried out and results satisfactory Each Formation (where applicable) Laboratory Reports I & N (H.P.) I (H.P.) W.P. M M Lab results
Cut/Trim pile heads (where applicable) Each Formation Sound concrete at cut-off I & N (H.P.) I (H.P.) W.P. M M survey 0
level. As drawings Cl. 1603.21
Prepare Construction joints ( where applicable ) Each Location Agreed position and finish. Cl I & N (H.P.) I (H.P.) W.P. M M RCPI / RIW 0
1710.1
Fix Reinforcement: schedule bars, stars bars, laps, cover Each Location Relevant drawings / schedules I & N (H.P.) I (H.P.) W.P. M M RCPI 0
(minimum/maximum), spacers, joints, surfaces clean, wire... & Cl 1714
Prior to erect Formwork: finish, joint prep., cleanliness, joints Each Location Line & level of works schedulr I & N (H.P.) I (H.P.) W.P. M M RCPI 0
tight, release agent, Setting out and level check... tolerance / Cl 1710.1 & 2 / Cl
1708
Fix cast-in items Each Location Relevant drawings I & N (H.P.) I (H.P.) W.P. M M RCPI 0
Ensure correct quantity and grade of concrete is ordered Each Location Relevant drawings I & N (H.P.) I (H.P.) W.P. M M RCPI 0
RESPONSABILITY
CONTROL DOCUMENTS VERIFYING DOCUMENT REMARKS
SITE Q.A. PPP DESIGN A.R.
Relevant drawings 1
Product Certificate 12 Hours
I & N (H.P.) I (H.P.) W.P. M M POUR RECORD SHEET
notice
2
Cl. 1727
Pour record sheet
I & N (H.P.) I (H.P.) W.P. M M ILAB Accredited Lab 24 Hours notice
/Laboratory results
4
5
Cl. 1710.3 I & N (H.P.) I (H.P.) W.P. M M Monthly inspection
0
POST CONSTRUCTION 6
Relevant drawings / Cl. 1710 I & N (H.P.) I (H.P.) W.P. M M PIR/RIW Product Certificate 12 Hours
7
Relevant drawings / Cl. 1710 I & N (H.P.) I (H.P.) I (H.P.) I (W.P.) (H.P.)I PIR 8
Relevant drawings / Schedules & Cl 1709 I & N (H.P.) I (H.P.) I (H.P.) I (W.P.) (H.P.)I ITWP-N6CL-17.02 noticeProduct Certificate 12 Hours 9
Relevant drawings / Schedules I & N (H.P.) I (H.P.) W.P. M W.P Survey book / RIW
11
I: Inspection W .P.: Witness Point PTP: Permission to Pour RIE: Req. Inspection of Eathw
12
N: Notification H .P.: Hold Point RW: Specification for Road Works RSF: Reception & Storage File
M: Monitor SP: Specificat. Procurements ITWP: Inspection & Test Witness / Hold Points RAM: Req. Approval of Mater.
13
W: Witness MDD: Max. Dry Density A: Approval of Document / Material RID: Req. Inpection of Drain.
14
T: Test PTL: Permission to Load RIW : Request for Inspection of Works Proforma RIC: Req. Inspection of Chamb.
ITEM REF DOCUMENTED ACTIVITIES NECESSARY TO BE COMPLETED
Before placing concrete, check delivery ticket for correct grade, quantity and location. Carry out visual
16 examination of concrete
17 Before placing concrete, check compaction equipment (people, pokers, generator, pump, ...)
18 During placing concrete, check compaction equipment, max drop vertically (2m), placed rate, cold joints,...
Laboratory test: ensure all test will be made (cubes, slamp, ...)
19
21 Strike Formwork: hours/days after, curing agent, weather conditions, test results (where applicable),...
NRA: Authority
LEGEND