EPC and FEED
EPC and FEED
EPC and FEED
Introduction
For many years now it seems that the most desired way for an Owner to procure a major
construction project, particularly one being project financed, was via a fixed price,
lump sum turnkey route; the so called engineering, procurement and construction contract
(“EPC contract”). By this route, funders and Owners expect to get the degree of
certainty as to time and costs that they require. Such has been the popularity of this
method of procurement that organisations such as FIDIC responded to the need for
appropriate standard forms that more closely reflected market conditions by, for
example, the introduction of its Conditions of Contract for EPC/Turnkey Contracts (the
Silver Book).3 Orgalime4 and ICC5 followed suit to join other standard forms produced by
organisations such as ENAA6, ICE7 and ECC8. Most recently, FIDIC has responded to the
requirements of the major development banks by introducing the MDB Harmonised
contract which contains certain amendments agreed with the multi – lateral funding
agencies to FIDIC’s Red Book.9
However, whilst it must always be appreciated that the lump sum EPC option usually
remains the most desired procurement route for Owners and funders, in response to
market conditions EPC contractors are increasingly proffering and, on occasion,
demanding, alternatives. In recent years there has been an increase in cost reimbursable
contracts (usually with a target price pain/gain share mechanism built in). 10 More
recently, there has been a significant increase in the EPCM contract procurement
route for international infrastructure and major construction works. Although historically
provide a simple and standardised contract specifically tailored for civil engineering projects.
8 Engineer Construction Contract 3rd Edition which has already been used extensively on major infrastructure
projects in the UK including Heathrow Terminal 5.
9 A modified form of the FIDIC Conditions of Contract for Construction, 1st Edition 1999, in which the General
Conditions contain the standard wording which previously had been incorporated by MDBs in the Particular
Conditions for MDB financed contracts.
10 See, for example, the ECC form of Contract, Option C used extensively on the Channel Tunnel Rail Link
project in the UK.
1
this method of procurement was certainly not uncommon in the mining sector, the use of
EPCM contracts has become more prevalent in other sectors of construction. Particularly,
EPCM contracts are increasingly the market response to major projects in the
petrochemical and mining sectors and also in the power and desalination sectors.
It seems to the authors that the meaning of EPCM (as opposed to EPC) is still relatively
unknown amongst a large part of the construction fraternity. The key confusion which often
arises is that whilst the “C” in “EPCM” stands for “Construction”, this is in the
context of “CM” i.e. Construction Management. Under the EPCM model the contractor does
no building or construction – rather he develops the design and manages the construction
process on the Owner’s behalf. The confusion is added to because there does not appear to be
any standard form of contract for this type of procurement. It is to be hoped that the likes of
FIDIC and ECC will consider the possibility of developing such a form.
This change of emphasis away from lump sum turnkey perhaps reflects the
bargaining position of many EPC contractors in today’s market and, to some extent,
the increasing size and complexity of the projects being tendered internationally. In
the petrochemical sector, as an example, there are simply not enough contractors
with the experience and balance sheet to take on the major capital projects that are coming
on stream, particularly in the Middle East. Equally, with so few major EPC contractors with
the know how, resource and experience to undertake such projects, funders have had
to open their minds to other procurement routes (and greater risks) in the face of rising
lump sum EPC prices. Bank rolling a major project with EPC contractors with no track
record of success is not usually an attractive or viable option.
As a result, the major EPC contractors have seen their negotiating position
significantly improved in recent times. This has arguably led to a correction in
market prices (profit levels for EPC contractors have increased) and levels of risk being
transferred back to project sponsors and lenders. This has resulted in a relative shift away
from the lump sum turnkey model. In some markets (petrochemical and mining sectors
particularly) obtaining a lump sum contract with one EPC contractor might even currently
be considered the exception rather than the norm.
With these market conditions in mind, the authors of this article would like to
explain how the typical EPCM contract works and, in doing so, identify some of the key
differences to the EPC contract. After all, they sound the same but there are still many
people involved in construction that are not able to elucidate the differences. Indeed, in
writing this paper the authors have not come across a single article on EPCM contracts – a
Google search of “EPCM” will bring up lists of EPCM contracts and EPCM contractors
but virtually nothing explaining what an EPCM contract is!
In short, an EPC contract is a design and construct contract where a single contractor takes
responsibility for all elements of design (engineering) 11, construction and procurement. In
contrast, an EPCM contract is a professional services contract which has a radically
different risk allocation and different legal consequences. The key difference is that under
an EPCM contract, other parties construct the project – the EPCM contractor is not the
builder/constructor.
2
The Project Participants
In addition to the Owner there are a number of other main participants in major projects.
Where a patented process is involved there may be the process supplier, who is usually an
engineering company with proprietary technology. Its prime business is to provide the
process engineering design or technology, which consists to a large extent of the
chemistry or technology necessary to achieve the process, which produces the product
from the plant.12 Where the process supplier is not also an EPC contractor, there will be
separate EPC or EPCM contractor, who is primarily responsible for the remainder of the
engineering design and, in the case of the EPC route, the construction of the project. There
are then the trade or subcontractors and major vendors engaged either by the EPC
contractor direct or, in the case of an EPCM arrangement (as explained below), direct
by the Owner.
Finally, and perhaps most importantly, there are the banks which provide the
finance for the project. For the project to proceed, the contract documents and the
allocations of risk therein, must be bankable.
This is often referred to as the Front-End Engineering and Design (FEED) stage which
generates what is known as the basic (or conceptional) engineering. The FEED is usually
executed predominately on a schedule of rates basis, although certain definable
components can be lump-summed. The FEED stage usually includes, but is not limited to,
basic engineering and design, project schedule and cost estimates for project control, and
(sometimes) procurement of certain long-lead items of equipment. The FEED stage results
in a basic engineering package or packages, sometimes referred to as process design
packages (PDPs) which (ideally) are sufficiently progressed to enable competitive bids
to be obtained on a lump sum basis.
The FEED may be produced by specialist engineering firms but increasingly major EPC
contractors have the in house capability to do this themselves. Where this occurs the
Owner’s Stage 2 options (see below) may be increased. It is also important to note that it is
not really possible or desirable to define what constitutes basic engineering or FEED in
general terms – it will vary from project to project as well as between sectors. Across
different projects and industries the FEED can be developed to a greater or lesser
extent, sometimes getting close to or constituting an element at least of detailed design.
The adoption of a staged project delivery approach with contracting options exercisable
by the Owner has the advantage of potentially providing contractual flexibility to the
Owner after the Stage 1 FEED. The Owner has various options available for project
12 Sometimes the process supplier may itself also be an EPC contractor thereby capable of offering the single point of
responsibility approach favoured by owners and funders. Indeed, where the process supplier is not also the EPC
contractor, Owners will still endeavour to make the EPC contractor responsible for the process although few EPC
contractors will accept this responsibility.
13 The term FEED is also used to refer to Front End Engineering & Development (as opposed to design) but it is not
thought that there is any significant difference (if any) in the two meanings.
3
implementation – Stage 2, although the availability of such options may change
according to the prevailing market conditions.
When planning the project the Owner and Lenders need to consider which of the following
potential options they wish to be available at the conclusion of Stage 1 (FEED):
(i) If the FEED has been produced by an EPC contractor willing and capable to develop
the FEED into a detailed design and to build the project, the Owner may seek to
continue the FEED contract on the existing or similar terms and conditions and
deliver the Project at the agreed tender rates using the FEED contractor – in certain
market conditions, this is a solution that can be imposed by the FEED contractor –
see (ii) below. This may lead to some bidders having to form joint ventures or
consortia to carry out the work;
(ii) More often, at the end of the FEED Phase, the Owner may wish the FEED contractor
to deliver the project in the form of a lump sum EPC contract. In order to ensure that a
lump sum route is still available to the Owner at the end of the FEED stage, a
mechanism ought to be built into the FEED contract thereby giving the Owner an
option to covert the FEED contract into a lump sum turnkey contract on completion
of the FEED. However, the FEED contractor often resists the imposition of such a
mechanism since it knows that on completion of the FEED there may be no other
EPC contractor available, or capable, or willing to develop the FEED and build the
project. In such circumstances, the FEED contractor is in pole position either to be
awarded the EPC contract (but at a negotiated price not dependent upon a pre-agreed
formula or mechanism), or simply to insist that it will only build the project on a cost
reimbursable basis (essentially option (i) above);
(iii) The Owner may appoint the FEED contractor (or another project management or
engineering company) to assist the Owner to manage and procure a third party EPC
Contractor to develop the detailed design from the FEED and build the project.
(iv) The Owner may appoint the FEED contractor (or possibly another engineering
company) to develop the basic engineering/FEED into a detailed design and then
manage on its behalf the procurement and construction of the works – this is the
so called EPCM contracting model upon which this article will focus.14
(v) Of course, the Owner may elect not to proceed with the project at all.
In practice, on the larger projects the FEED stage may itself be broken up into separate
process design packages with each of these been market tested and procured separately.
The decision as to which contracting model to use for the second phase is often deferred
until the latter stages of the FEED, when the Owner is then able to test the market for
prices, based on the process design packages prepared during the FEED, and will be able
to assess the level of contingency required, the cost of risk transfer, and the appetite in the
market for the EPC option. This is why, if a mechanism is not in built in the FEED
contract for conversion to lump sum turnkey, the Owner may hand the initiative to the
EPCM contractor, if the EPC option is not attractive to the wider market.
The nature of the Owner’s organisation and degree of control which the Owner wishes to
exercise during the second phase will also influence which option will be chosen.
14 There are however many variations on this theme such as appointing separate EP and CM contractors which is
becoming more common in recent times.
4
Engineering, Procurement, Construction Management (EPCM)
This might be described as being primarily a professional services contract. In some ways
the procurement structure is more akin to that under a typical construction management
approach but with the vital difference that the detailed engineering and design function is
carried out by the EPCM contractor.
(a) design (this includes producing the basic engineering/FEED and developing the
detailed design);
An important difference between the EPCM and EPC form of contract is that in the
EPCM model, the contractor is providing professional services (including design) and
is not a principal (i.e. is not a party to a contract in respect of the construction of the
project).
The EPCM contractor acts as the Owner’s agent and creates (on behalf of the Owner)
direct contractual relationships between the Owner and the suppliers and trade contractors.
Each trade contract is a contract directly between the Owner and the trade contractor or
specialist services provider or vendor. Ideally, in such an arrangement, as with typical
construction management, the Owner ought to have a large and experienced in-
house team to assist the EPCM contractor with the management and administration of
these contracts. Whilst this is strictly speaking a very large part of the important role for
which the EPCM contractor is paid, given the division of responsibilities between various
parties in an EPCM arrangement it is vital that the Owner keeps a careful eye on
performance of each, for reasons which will be explained below. Problems arising
under trade contracts between the trade contractors and the Owner such as interfaces
between trade contracts, delay and disruption and property and works damage claims, and
other claims for extra time and money, are the ultimate responsibility of the
Owner. Whilst the EPCM contractor must assist the Owner in the management and
resolution of any claims, the EPCM contractor is not a party to any dispute which arises
between the trade contractors and the Owner.
The EPCM contractor will not usually take full responsibility for delivering the completed
project by an overall completion date (thus rarely are there liquidated damages provisions
in EPCM contracts for delay to the project as a whole), nor will it take responsibility for
care of the works or for the ultimate cost to the Owner of the project. However, incentives
can and are often built in to the EPCM contract in this regard (see below).
Accordingly, the principal potential liabilities of the EPCM contractor relate to breach or
negligence in:
(e) co-ordination of the design and construction between the trade contractors
5
However, proving breach of these obligations is rarely straightforward, and in respect
of (b) and (c) the Owner may struggle to establish a real loss, however negligent the
EPCM contractor may have been.
The Contractual relationships in a typical EPCM arrangement are illustrated in
Figure. 1. Figure 1. Typical EPCM Arrangement
This contrasts with the typical EPC model set out below:
Owner
EPCM Contractor
Specialised
Process Vendors Trade Contractors
Engineering
Sub-Contractors Sub-vendors
Owner
EPC contractor
Specified
Trade
Process Vendors Site Services
Contractors
Engineering
6
The Services to be Performed under EPCM Contract
(a) Engineering/design
Where the process provider insists upon extensive limitations on liability, such
as limiting its liability to re-performance of its work-scope, further limited to a certain
value, the Owner’s sole rights associated with a process failure might be limited to
having the process provider rectify the design and test work, which was the subject of the
licence and ancillary service agreements, up to that limited value. These limitations on
liability can produce significant problems from the Owner’s risk point of view. A
failure of the process engineering may be capable of being fixed relatively easily
by introducing more equipment, for example, to deal with impurities that are
adversely affecting the product. However, more fundamental problems with
consumption of utilities and with the process itself can result in total project failure as a
consequence of the plant being unable to process the particular raw material to produce
the required quantity or quality of product at a viable cost.
Accordingly, care needs to be taken to ensure that the risk is adequately allocated
to the appropriate party. This will usually require an initial in depth risk analysis,
the development of a risk management plan, and careful negotiation of the relevant
agreements with the process provider and other contractors, together with support
from insurers.
Neither the EPCM nor EPC contractor would typically be willing to accept
responsibility for any part of the process design (unless they were themselves the
Owner of the process). This can create problems for the Owner where the plant,
for whatever reason, fails to produce to the levels the Owner required. A defence
for both EPCM and EPC contractor will often be that this is a result of a failure in
the process design rather than the detailed engineering – getting to the bottom of
such an argument may be well nigh impossible. Thus, it should be immediately
evident to the reader why it is more preferable for the Owner to seek a single point
of responsibility approach with the EPC contractor taking responsibility for all
aspects of the construction detailed design, including process, if at all possible.
7
Under the EPCM model, the EPCM contractor will usually be responsible for the
preparation of the FEED and the complete detailed engineering in accordance with
normal industry and good engineering practices, which will be needed by the
companies to be entrusted with the construction work.
Sometimes the EPCM contractor will merely complete the basic engineering
package provided by the Owner but, whatever route is used, it is crucial from the
Owner’s perspective that the EPCM contractor is responsible for ensuring that the
completed plant design will meet the required process performance. Thus, it is
important that the EPCM Contractor co-ordinates his efforts with those of the
other parties involved to ensure that the engineering and design of the project is in
full compliance with the requirements of the approved project specifications,
procedures and safety guidelines.
It is normal, therefore, for the EPCM Contractor to have overall responsibility for
establishing and maintaining both the design and construction interfaces with
vendors and construction contractors to the extent necessary to ensure that their
work is performed to the required level and quality, and to a schedule which is
compatible with the requirements of the overall project schedule. The EPCM
contractor will usually be responsible for overall co-ordination of the design and
construction process although often the EPCM contractor will also appoint a lead
contractor amongst the various trade contractors that will take some responsibility
for on site construction co-ordination – even though the EPCM contractor will of
course have a heavy site presence with its own construction management team.
(b) Procurement
A key part of the EPCM contractor’s role is to advise the Owner on the strategy for
the construction and procurement of equipment and materials and then assist the
Owner in implementing that strategy. Ideally, and usually, the Owner has an idea of
its procurement strategy at the outset even before the EPCM contractor has been
appointed. As explained above, it is important that the EPCM contract has been
set up in a way which allows the Owner to exercise his chosen option by the
time the FEED has been produced and construction activities are due to commence.
Where, however, the contract does not convert to an EPC contract at conclusion of
the FEED stage, the EPCM contractor will need to assist the Owner in letting the
major works packages to various trade contractors, advising on the terms of those
packages, and putting the contracts in place. As with any project, the timing of the
letting of the packages is a crucial factor in the success of the project – letting a
package too early when there is insufficient information to obtain a lump sum
may lead to a series of cost reimbursable trade packages or risks of large variation
claims on lump sum packages - letting the packages too late runs the risk of failing
to meet the overall project schedule.
Further, during the FEED stage, the EPCM Contractor will usually advise the Owner
that for the project schedule to have a chance of being met, long lead items of
equipment must be ordered ahead of the appointment of the contractors and often
ahead of the detailed engineering being completed, which itself creates risks.
8
The EPCM contractor will be responsible for the preparation of comprehensive
invitations to tender and then for awarding of contracts for delivery and construction
services to be rendered by third parties. A well drafted EPCM contract would require
that, for the protection of the Owner and to ensure competitive pricing, the number
of suppliers invited to quote shall be such that at least a minimum of three fully
responsible quotations are obtained.
The EPCM contractor will then be required to carry out a careful analysis of the
offers received and to make a recommendation of the technical and economic
advantages and disadvantages involved in each offer, and proposals for the
awarding of contracts, with reasons, for the Owner’s approval.
The EPCM contractor will then prepare the commercial and technical agreements.
The terms and conditions of such agreements must be agreed with the Owner in
advance but it is usually for the EPCM contractor to prepare the standard contract
documents and to ensure that these are suitable for the type of procurement being
used.
Ideally, from the Owner’s perspective, a series of lump sum contracts will then be
put in place by the EPCM contractor, on the Owner’s behalf. These contracts will
be direct agreements between the Owner and the trade contractors. It is crucial
that the terms of these contracts are properly co-ordinated with one another and
protect the Owner’s interests. The Owner may face claims during the currency of
the works that it wishes to pass on to either the EPCM contractor or to the
defaulting trade contractor responsible – the contracts must be drafted in such a
way that this is made possible.
This will include organisation and supervision of the safety management on the
construction site and comprehensive quality assurance, the securing of evidence
for any defective third party services, including the consequences arising there
from, the establishment of facts in the event of default and defective services,
including complete documentation, so that the Owner is protected against claims
from trade contractors.
9
Cost Control
The EPCM contractor is usually paid a project fee divided monthly across the term of the
project for the performance of its role. In addition, it is often paid on an actual cost basis
at rates and prices agreed in the contract for the performance of its services. So as to keep
a check on such costs and provide the EPCM contractor with an incentive to keep costs
down, often a target price will be set with the EPCM contractor sharing in any saving if
actual costs are less than the target price. There is often a schedule to the EPCM contract
which sets out the budgeted man hours for the EPCM contractor’s team – this may be
divided between the Project Management team (including the project director, project
managers, planners, cost engineers, HSE Engineer etc), procurement (mainly buyers),
construction (construction managers, site supervisors, site planners, secretaries) and
engineering (engineers split between the main disciplines, civils, piping and
instrumentation, controls, electrical and mechanical).
However, since the EPCM contractor does not construct the project, Owners and funders
will be concerned to ensure there is some control on outturn costs for the whole project.
What responsibility does the EPCM contractor have for the project outturn costs and how
does the Owner effectively control costs without the protection and relative certainty
afforded by a fixed price lump sum that the EPC contract can offer? In answering this
question, it is important to note that, at the time the EPCM contractor is first
appointed, the Owner may have little idea what the project will cost since the design will
be in its infancy and the construction packages will not have been let. It is therefore vital
that the EPCM contractor is incentivized to bring the project in within an agreed budget
with the Owner. This is also something which the funders will be acutely aware of.
As part of its services the EPCM contractor will be responsible from a very early stage for
developing budgets for the construction works and procuring, managing and
administering the construction contracts in accordance with those budgets. Of course it is
only in extremely rare instances that an EPCM contractor would ever consider
offering any form of guarantee that the project outturn costs will come within a set
budget.15 More commonly, EPCM contractors are often content to set a target price for the
outturn costs of the works package contracts and share in any saving and, sometimes,
contribute to any losses but even this, particularly in today’s market, is rare. However, this
does not mean that the EPCM contractor typically avoids any liability for a project which
comes in significantly over the budgeted cost. There are usually detailed provisions
regarding the EPCM contractor’s obligations to safeguard and advise the Owner on
project costs.
Usually the schedule of services attached to the EPCM contract will go into great
detail as to the level of services to be provided by the EPCM contractor in this regard
and the types and frequency of cost reporting and estimating required. A typical
overriding obligation1~ would be as follows:
15 Indeed in the author’s joint experience they know of only one project where this has occurred.
16 Usually developed in more detail in the scope of services.
10
each section of the works, the costs determined for this are to be
calculated, to be compared with the costs previously estimated, and to be
submitted in writing to the Owner.
It is important to recognise that with this typical type of obligation, the EPCM contractor
will not be liable to the Owner simply because the project costs exceed the budgets
and cost estimates provided at the outset. However, as the EPCM contractor performs a
largely professional role it will usually have an overriding obligation to exercise
reasonable skill and care in carrying out its services.
Common claims and complaints arising against EPCM contractors for breach of its
primary professional obligations include:
· the initial base estimate on which the decision to proceed with the project was
based was negligently low;
· that proper updates and costs estimates have not been provided;
· that the Owner’s authorisation was not obtained when contractors were incurring
additional costs;
However, in relation to the first three of these complaints, it may be difficult for
the Owner to establish any real loss.
Thus, whilst an overun in project costs beyond the budgets set by the EPCM contractor
will rarely of itself give rise to a claim by the Owner against the EPCM contractor, the
EPCM contractor will need to explain and justify the reasons for the overrun. As the
party in ultimate control of the project, and the party which has estimated the outturn
costs, it must account to the Owner for the reasons for the overrun. Usually this will lead
to the EPCM contractor blaming the poor performance of the contractors which may then
have knock on effects against other contractors leading to delays and claims for extra
payment against the Owner by trade contractors and the EPCM contractor. Often this
is where a dispute between Owner and EPCM contractor can arise. The packaging, letting
and administration of the various trade contracts is within the ambit of the EPCM
contractor. Since it is also responsible for design, when co-ordination issues arise which
lead to claims by the trade contractors against the Owner, such claims may well arise
11
from a failing on the part of the EPCM contractor. This places the EPCM contractor
in an invidious position since often part of its role is to certify payment and assess
claims by the trade contractors against the Owner. It is clearly in its interest not to
elucidate the real reasons for claims against the Owner, if these flow from failings
by the EPCM contractor itself (for example, defective engineering, late
procurement or negligent construction management).
It is also for this reason that the authors believe that it is essential that Owners have a
competent in house team to help administer the trade contracts and oversee the
performance of the EPCM contractor.
Schedule Control
The EPCM contractor is responsible for managing the co-ordination of the various trade
contractors in an attempt to ensure that the project programme is met. Usually, the
development and agreement of an overall programme for the works is the responsibility of
the EPCM contractor. One would expect to see a detailed (albeit preliminary) project
schedule included within the EPCM contract itself. This will project the final
completion date of the project and show details of when detailed design will
start/finish and the schedule for the procurement and completion of the major packages,
testing and commissioning. Of course, unlike with an EPC Contract, the EPCM contractor
is in a strong position to argue that it should not accept total responsibility for achieving
this project schedule because the EPCM contractor will not assume responsibility for the
performance of the various works package contractors. Thus the EPCM contractor’s strict
time obligations are sometimes confined to ensuring that it produces the necessary
design deliverables in accordance with the schedule in the EPCM contract. Sometimes
liquidated damages are payable upon late delivery of design deliverables but, as this is
totally within the province of the EPCM contractor, this is usually acceptable.
Notwithstanding this, it is fair to say that there is no one person in a better position to
influence successful and timely delivery of the project than the EPCM contractor.
Being responsible for the design and procurement process, means that delays by the
EPCM contractor are likely to seriously jeopardise the project schedule. The EPCM
contractor arranges the tender process and selects (in conjunction with the Owner) the
trade contractors. The EPCM contractor advises on contract/procurement strategy. Thus,
a well drafted EPCM contract should place the risk of schedule slippage firmly at the
door of the EPCM contractor, but allow extensions of time for the poor performance
of one or more defaulting contractors. In practice, with multiple interfacing contractors
each of which may themselves be more or less culpable for some of the delay, making a
successful delay claim against an EPCM contractor is fraught with difficulty.
Typically the trade contractors who are delayed will claim from the Owner that the EPCM
contractor provided the design late, or that the design had errors and was incomplete, that it
was delayed by an interfacing trade contractor or by reason of a failure to co-ordinate the
packages properly etc – all of these give rise to potential claims by the trade contractors
against the Owner – equally the EPCM contractor may claim the delay was caused by
inadequate resources by the contractor in question or defective work. Without a good in
house team cognisant of where the truth lies, one can see that the EPCM arrangement has
the potential to leave the Owner in a very difficult position if the project is late and over
budget; hence also the need for a project-wide rapid adjudication system.
12
One common way of incentivising good performance by the EPCM contractor is by
offering an early completion bonus so that achieving the project and/or key milestones by
or before the scheduled dates, generates a bonus for the EPCM contractor.
Insurance
As with other contracts, an EPCM contract will contain obligations and indemnities
resulting in possible risks for either the Owner or EPCM contractor or both. In their
broadest sense, insurances are generally employed to cover the risks associated with those
obligations and indemnities or to cover statutory obligations (such as an Owner’s liability
to its employees). It should be noted from the outset, however, that some risks are simply
not insurable.
The EPCM is essentially a professional services contract. An Owner may wish to see
the EPCM contractor’s obligations with respect to design backed by an appropriate
professional indemnity insurance to cover negligent design of the EPCM contractor.
Whilst professional indemnity insurance policies are generally considered the norm for
consultants providing services in the United Kingdom 17, it is often the case that
organisations operating outside of the United Kingdom do not in fact carry such
insurance or are reluctant to offer such insurance. In these circumstances, if the EPCM
contractor does not normally carry such insurance, the Owner will have to weigh up the
advantage of having such insurance against the likely increased cost to the Owner in
asking the EPCM contractor to procure the insurance.
In terms of the policy cover, levels of cover should be checked together with whether the
policy operates on an “each and every claim basis” or an “in the aggregate basis”. In the
case of the latter basis, the Owner may find the potential insurance exhausted if, in
the same year as the Owner notifies a claim, another unrelated claim has been
lodged in priority of time which could “wipe-out” the insurance coverage for that year.
This is particularly important if the EPCM contract contains an express provision
(as it often does) to the effect that the EPCM contractor’s liability is to be limited to the
amount recoverable under the insurance policies to be maintained by the EPCM contractor
under the contract.
Other insurances which are usually required in the EPCM contract and which may need to
be taken out by either the Owner or the EPCM contractor include third party liability
insurance, medical/disability insurance, workman’s compensation insurance and
automobile liability insurance. It is rarely the case that construction all risks (CAR) or
transit insurance is required under the EPCM contract (as the EPCM will not be
constructing the works and it is unlikely the EPCM will be providing any goods or
materials). Consideration may need to be given, however, to the impact of the EPCM’s
presence on site on the policies to be maintained by the other project participants.
Finally, it should be noted that the EPCM contractor is often required, as part of the
services to be performed, to advise the Owner on required insurances for the project and
upon the suitability of policies proposed by the project participants. On large scale
projects, the Owner may be well advised to take out “all embracing” project wide
17 Although the availability of professional indemnity insurance at commercially reasonable rates is a hot topic in the
United Kingdom construction industry following large increases in premiums and it remains to be seen what effect
the increases in premiums will have on the long-term viability of such policies and the terms upon which the policies
are offered.
13
insurance policies, naming the various project participants as co-insureds. This gives the
Owner the advantage of controlling the various insurance policies but also minimises
wasted costs by effectively reducing the overlap between individual policies of the project
participants (which ultimately the Owner would otherwise end up paying for).
Net Contribution
If current trends in the United Kingdom construction market are anything to go by, the
use of so called “net contribution” clauses is likely to become more apparent in EPCM
contracts than it currently is. At present, net-contribution clauses are more the exception
than the norm in both EPCM and EPC contracts, although it should be noted that the
FIDIC Client/Consultant Model Services Agreement (commonly referred to as the
“White Book”) contains a rudimentary form of net contribution clause.
A net contribution clause aims to limit the proportion of any loss or damage payable
by a party to that party’s ‘fair share’ or such share as would be ‘just and equitable’ for
them to pay (usually making certain assumptions, including that all others who may
be to blame have paid their fair shares).
This device is used because construction disputes often involve more than one party
that is alleged to be at fault, typically due to a mixture of design and workmanship
alleged deficiencies. This is particularly the case in an EPCM arrangement with
multiple contractors in direct agreement with the Owner. In England and Wales,
under the law of joint and several liability, any one “wrongdoer” who can be shown to
have breached its obligations could be held responsible for all of the damages
suffered. This means that the “innocent” party can choose simply to sue one of the
wrongdoers. If there is the perception that the consultant has the deepest pockets
(backed by a professional indemnity insurance policy), it may well be that it is only
the consultant (EPCM Contractor) who is sued, rather than other alleged wrongdoers.
To get around this problem, the net contribution clause was developed as a contractual
device to achieve a more equitable split in liability apportionment. The effect of the net
contribution clause is that a party will only be liable for his proportion of the damages,
whether not a contribution can be obtained from the other parties. In terms of risk
allocation, inclusion of such a clause transfers to the Owner the risk of insolvency
amongst the contractors and other consultants appointed on the project.
Dispute Resolution
From the Owner’s perspective a vital and often overlooked factor in the correct
structuring of an EPCM project are the provisions for dispute resolution. These
provisions should always be drafted with a view to what remedies the Owner will have
in circumstances where the project, as a whole, goes badly awry. When this occurs
under a typical EPC contract, the Owner will obviously have the advantage of a single
point of responsibility, being the EPC contractor, and will not have to worry about
separate or parallel proceedings and difficulties with joinder and consolidation of
separate actions since usually only one party (the EPC contractor) will be responsible.
Thus, under an EPC contract, if there is a design issue, a workmanship issue, or a time
issue, then the dispute is simply between the Owner and the EPC contractor and that can
be resolved in a single forum.18
18 This assumes that the project involves a single EPC contract. However, large projects will frequently involve 2 or
more separate EPC contracts, possibly with an EPCM overlaid.
14
A significant disadvantage to the Owner of the EPCM route is that if the project goes
awry, the Owner can find itself faced with a number of battlefronts. The Owner is
likely to find itself in dispute with one or more of the major trade contractors which
may be claiming extensions of time and loss and expense. In order to defend itself
properly, the Owner will need the assistance of the EPCM contractor, but also may need
to join in those that are truly responsible for the matters which have led to the claim
against it. If there is late provision of design, then the Owner will want recourse against
the EPCM contractor. If it is the default of another trade contractor then the Owner may
equally need recourse against that trade contractor.
Further still, problems can arise with inconsistency in the drafting between trade
contracts such that the claim by one trade contractor against the Owner may be
governed, for example, by German law, and yet a potential claim by the Owner
against the responsible defaulting trade contractor, or the EPCM contractor, may be
governed by, for example, Sharia law. Whilst this may seem an extreme example,
it is in fact based on a real life project.
Thus, it is the responsibility of the EPCM contractor to have regard to the Owner’s
interests in such scenario. Since the EPCM contractor is responsible for the placing of
the main trade contracts and for advising the Owner on the same, the EPCM contractor
and Owner ought to be having this potential situation in mind when doing so. Thus,
there is good reason for the EPCM contractor to be providing the Owner with the ability
to join all of the potentially major responsible parties to the project together in one set of
proceedings under one governing law, to protect itself against the risk of multiple
proceedings in different jurisdictions with the attendant costs and legal risks involved. It
is not the purpose of this article to advise whether courts or arbitration and, if so in what
jurisdiction, are preferable. Suffice to say that careful consideration needs to be
given to the drafting of the trade contract and the EPCM contract in this regard.
Drafting effective, valid and enforceable joinder provisions is fraught with difficulty
and will usually require the assistance of specialist lawyers, brought in by the EPCM
contractor (or its own in house legal function) and paid for by the Owner.19
Conclusion
As can be seen from the above analysis, there are good reasons for concluding, as the
title of this article suggests, that EPC and EPCM contracts are worlds apart.
The advantage from the Owners’ point of view of an EPC contract is that the
contractor takes full responsibility in respect of the following:
19 Of course sophisticated Owners may well have access to their own legal teams in this regard.
15
the Owner obtains a project of the required standard. This usually requires more than
simply stipulating performance criteria in relation to the output of the plant, and will
include design-life and maintenance issues.
Equally, from the EPC contractor's perspective, recurring problem areas in EPC contracts
are bridging the interfaces between the basic engineering and the FEED, with
execution under an EPC contract, in circumstances where the EPC contractor did not
execute the FEED itself. The EPC contractor is usually required to satisfy itself as to the
accuracy of basic engineering and/or FEED, or is deemed to have done so even where
the bid period is patently insufficient to allow it physically to do so. Current practice
in many sectors often requires the EPC contractor to accept this risk. Indeed, even in
some of the standard forms this is the case.20
From the Owner’s point of view, resolving liability for and the consequences of basic
engineering and/or FEED “defects” in the Employer’s Requirements will be
extraordinarily difficult and expensive which is why it is wise to try to place full
responsibility on the EPC contractor. The contractor which accepts such a risk without having
carried out a thorough evaluation of the basic engineering and FEED does so at its peril and is
unlikely to have recourse against the perpetrator of the errors. It could be a costly
miscalculation.
The solution for the Owner in bridging the interfaces if the EPC contractor is not willing
to assume responsibility for the basic engineering and/or FEED or it is considered
unlikely at project inception that any EPC contractor would take such a risk is to
consider alternative contract strategies including EPCM which has the potential for
providing seamless and continuous responsibility for the engineering. But these issues
need to be thought through at conception of the contract strategy taking into account the
contractors’ appetite for risk gauged according to the expected market conditions at
the time of execution. Further, since the EPCM route splits responsibility for
engineering and construction, the well advised Owner ought to be far more pro-active
in its management of the project.
Thus, the Owner is well advised to ensure that it has sufficient in-house or other
resources available to it to monitor and check the performance of the EPCM contractor
during the FEED and detailed design phases, to ensure that the Owner is getting
exactly what it wants in terms of performance, operability, maintenance and whole of
life cost and by passing as much of the risk as possible in relation to the cost of
construction, time for completion and quality of the construction work to the trade
contractors by effective trade contracts.
The selection of the appropriate pricing structure in combination with the above will
reduce the Owner’s risk.
The low EPC lump sum price is not always what it appears to be, particularly where
(as is often the case) the winning contractor has “skinnied the bid” in order to win the
contract, with a view to making claims to recover the profit.
Nick Henchie is a partner in the Construction & Engineering Group of the law
firm Mayer Brown International LLP.
20 See for example FIDIC’s Conditions of Contract for EPC Turnkey Projects (The Silver Book) where the
Contractor is responsible for errors in the Employer’s Requirements (which often comprises a basic engineering
package).
16
Mayer Brown offices
Berlin Brussels Charlotte Chicago Cologne Frankfurt
Hong Kong Houston London Los Angeles New York
Palo Alto Paris São Paulo* Washington DC
Mayer Brown is a combination of two limited liability partnerships: one named Mayer Brown International LLP, incorporated in England; and one named Mayer Brown LLP, established in Illinois, USA.
0105con
November 2007