Method Statement-Water Features
Method Statement-Water Features
Method Statement-Water Features
METHOD STATEMENT
WATER FEATURES
SCOPE OF WORK :
The scope involves Installation of Water Feature Equipments, Necessary Accessories Supports as detailed
in Contract Specification. The System comprises of filter pumps, sand filter, fountain pump, and chemical
dosing system located at various locations which are put together to form a complete system to satisfy the
specific project requirements.
Safety Shoes
Safety Helmets
Hand Gloves
Goggles
1 Ensure all required document i.e. Shop Drawings and material approvals have been obtained.
2
55/26/202010:12
AM
2 Arrange all necessary personnel, plant, equipment and services as required for the works and ensure
adequate water, lighting, power and access arrangements are in place.
3 Ensure work area is clear & safe and construction activities are co-ordinated with other works.
4 Where further information/ clarifications in respect of Contract drawings are required the matter shall be
referred to the Engineer by means of a site clarification request. (SCR)
5 Implement Employee induction procedures and Tool Box Talks for ongoing risk assessment and
identification of hazards.
6 Ensure the relevant approved shop drawings are available with the installation team.
7 Erect scaffold and access platforms in accordance with approved temporary works documents and
safety procedures by authorized registered personnel.
8 Ensure all the Equipments / Devices are calibrated where ever applicable.
1. Ensure that all the pipes, pumps & its accessories are properly packed and permit for easy handling.
2. Offload all the pipes, pumps & fittings with suitable offloading mechanism.
4. The storage area shall be clean and free from foreign materials to protect the pipes against damage. Pipes
should be stacked above ground by the use of wooden dunnages or as similar; dunnage should be position
wherein point of contacts will not cause deformation. Maximum height of stacking will be observed as per
safety requirements. Proper containment measure e.g. temporary rails to be utilized to prevent pipes from
rolling down.
5. The storage area for the pumps & other accessories shall be clean and free from foreign materials. Protect all
these equipments from climatic conditions as per material control, handling and storage instructions.
6. Ensure that the handling / storage activities are as per material control, handling and
Storage instructions.
INSTALLATIONS
1. Installation of Embedded Antivortex Drains, Main drains, Floor inlets, Over flow drains,
Vacuum fittings.
2. Ensure the availability of all the necessary tools and equipments required for the installation.
3. Ensure that the materials are supplied as per the approved Material submittal, before starting the installation.
4 Mark the location of position of the fittings in the steel structure with respect to
3
55/26/202010:12
AM
5. Install UPVC pipe with puddle flange at the centre and provide box opening in the steel
Structure around the UPVC pipe.
6 Fix the UPVC pipe rigidly by tying steel wire to the steel structure, prior to concreting.
9 Ensure that the other accessories like Valves, Strainers, and Flow Switches are installed as per the
approved drawing and manufacturer’s installation instructions
2. Installation of Pumps
2. Ensure the availability of all the necessary tools and equipments required for qualitative installation.
3. Ensure the civil works and foundation for all equipments are completed & approved
4. Ensure that the materials are supplied as per the approved Material submittal, before starting the installation.
6. Fix the pump on the proper location as per the approved drawing.
9. Install Isolation valves, Flexible connectors and Eccentric / Concentric reducers as per the shop drawing.
10. Install Pressure Gauges, water level and flow sensors and other accessories as per the
approved shop drawings and manufacture’s instructions.
11. Install all cables in compliance with electrical specification and as per
approved wiring diagram and terminate and check continuity.
13. Connect the piping network to the pump as per the approved shop drawings.
14. Install sufficient supports to the pump, valves, accessories and the piping network so
that the weight of the piping network does not rest on the pump.
2. Ensure the availability of all the necessary tools and equipments required for the installation.
3. Ensure the foundation for the filter unit is completed and approved.
4. Ensure that the materials are supplied as per the approved Material submittal, before starting the installation.
8. Install multi-port valve as per the shop drawing and manufacturer’s instruction.
2. Ensure the availability of all the necessary tools and equipments required for the installation.
3. Ensure that the materials are supplied as per the approved Material submittal, before starting the installation.
5
55/26/202010:12
AM
4. Install the lighting fixtures in the location as per the approved drawing.
5. Install the cables, junction boxes and light transformers as per the approved elecrical diagram.
6. Install cables in compliance with electrical specification and as per the approved elecrtical diagram and
terminate and check the continuity.
TESTING
After installation, visual inspection of all the Pump, Filter, Dosing unit, Valves, Gages and other
accessories shall be carried out to make sure that all the installation are correct and according to the
manufacture’s instruction and Engineer’s comments.
VERIFICATION
SAFETY