Method Statement-Hard Landscaping Works

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 7
At a glance
Powered by AI
The document outlines the method statement for hard landscaping works including scope of work, equipment, materials, safety measures, and installation procedures.

Equipment will include mixers, cutting machines, drilling machines, and vehicles like JCB. Materials will include blocks, concrete, mortar, and other masonry tools.

Basic PPE like safety shoes, helmets, gloves and goggles will be provided. A safety induction will be conducted and the supervisor will ensure a safe working environment.

AKAR TECHNICAL SERVICES CO. LLC.

METHOD STATEMENT FOR HARD LANDSCAPPING WORKS

PROJECT : DUBAI PROPERTIES - 2

DUBAI PROPOERTIES OFFICE BUILDING P-115

METHOD STATEMENT

HARD LANDSCAPING WORKS

Scope of Work : This Method statement provides the control sequence of


construction and methodology that will be used for Hard landscaping work in
order to achieve compliance with the BOQ pages & approved Shop drawings

Equipments & Materials:


As per approved MAR,

 Hard landscaping (All works as per BOQ):


 Pavements
 Coping
 Walls
 Seats

 Rubber mallet.
 Shovel.
 Straight Edge.
 Sprit Level
 Plum bob. & All other masonry tools
Measuring Device:
 Dumpy Level
 Total level
 Theodolite
 Measuring Tape
 Tube level etc
Equipments:
 Mixer machine
 Hand cutting machine.
 Water cutting machine
 Hand drilling machine
 Hand grinder.etc
METHOD STATEMENT FOR HARD LANDSCAPPING WORKS

PROJECT : DUBAI PROPERTIES - 2

Personal Protective Equipment:

The basic P.P.E will be provided as

 Safety Shoes
 Safety Helmets
 Hand Gloves
 Goggles
.
METHOD STATEMENT FOR HARD LANDSCAPPING WORKS

PROJECT : DUBAI PROPERTIES - 2

AKAR TECHNICAL SERVICES CO. LLC.

DUBAI PROPOERTIES OFFICE BUILDING P-115

METHOD STATEMENT
HARD LANDSCAPING WORKS

Scope of Work : This Method statement provides the control sequence of


construction and methodology that will be used for Hard landscaping work in
order to achieve compliance with the BOQ pages & approved Shop drawings

Equipments & Materials:


As per approved MAR,

 Pedestrian crossing 1,2 & 3 (All works as per BOQ):

 Rubber mallet.
 Shovel.
 Straight Edge.
 Sprit Level
 Plum bob. & All other masonry tools
Measuring Device:
 Dumpy Level
 Total station
 Measuring Tape
 Tube level etc
Equipments:
 Mixer machine
 Hand cutting machine.
 Water cutting machine
 Asphalt Cutting machnine
 Hand drilling machine
 Hand grinder.etc
 JCB
 Bobcat
METHOD STATEMENT FOR HARD LANDSCAPPING WORKS

PROJECT : DUBAI PROPERTIES - 2

Procedure

1. All materials will be stored in proper place allocated by the main contractor and same
shall be lifted to the Hard scape area by using wheel barrow

2. All the materials will be inspected before using it for installation and damaged
materials will be rejected.

3. Based on the approved sharp drawing, RCC core filled block work marking for
landscape wall in Zone 1,2,3,4 in External area.

4. 8mm dia drilling will be carried out in the basement slab (by using Drilling machine) to
a depth of 5cm @ 200 mm center to center distance

5. The drilled surface area shall be cleaned properly before applying LOKFIX

6. The steel rod inserted in a proper alignment and LOKFIX shall be applied to the
required quantity and allow it for 3hrs. for drying.

7. The block shall be placed by inserting the steel rod one on other, by applying the
cement mortar (1:1:2) between the block

8. The center of the hollow block shall be filled with cement concrete to the entire row

9. Similarly the other row of block work will be carried to the required height as shown in
the approved shop drawing

10. The completed work will be cleaned from all debris and will be offered to consultant for
inspection.

Verification

1. Setting out by surveyor based on issued latest Architectural layout.


2. Approved Shop drawing of landscape wall.
METHOD STATEMENT FOR HARD LANDSCAPPING WORKS

PROJECT : DUBAI PROPERTIES - 2

Procedure Site made Setting Mortar: Mix and proportion cementitious materials for site
made leveling coats, setting beds & grout.

Grout: Mix and proportion grout material in accordance with


manufacturers recommendations.

Prior to installing, ensure surfaces are level.

Ensure surfaces are clean and well cured, and sloped to drains where drains are provided.

Do not commence work until surface conditions are within tolerances required for proper
installation; apply leveling material where necessary to meet required tolerances.

Clean stone before setting by thoroughly scrubbing with fiber brushes followed by
thorough sponging with clear water; use only mild cleaning compounds that contain no
caustic or harsh fillers or abrasives.

Prepare Portland Cement Setting Bed in mix 1:3:

Thoroughly clean sub floor and moisten without soaking.

Apply Portland cement mortar setting bed to proper line and tamp firmly.

Setting bed shall be of uniform 25mm to 40mm thick nominal thickness.

Apply setting bed over areas no greater than can be covered while setting bed remains
plastic.

Trowel or brush thin layer, 1mm to 1.5mm thickness, of cement paste over setting bed.

Apply stone in place and beat firmly into straight, uniform joints.

Bring surfaces to true level at proper elevation.


METHOD STATEMENT FOR HARD LANDSCAPPING WORKS

PROJECT : DUBAI PROPERTIES - 2

Complete beating and leveling within one hour of setting; wipe clean with soft
damp cloth

After completion of work, point open joints and replace defective work.

Clean surfaces free of foreign matter upon completion of grouting.

Use clean water and stiff bristle fiber brushes.

Do not use wire brushes, acid type-cleaning agents, cleaning compounds with caustic or
harsh fillers, or other materials or methods, which could damage stone.

If other finishing trades are involved, we recommend that the installation be


covered in heavy-duty polythene for protection against soiling and damage.
However, the covered hard landscaping should be ventilated to prevent an
excessive build-up of moisture.

Verification

3. Setting out

4. Sample of materials at site

5. Progress inspection at site

6. Shop drawings

Safety

 A safety induction talk will be conducted prior to commencement of works.


 Akar supervisor will be having regular visits to ensure the safe working
environment
 All safety aids (Helmet, Safety shoes, safety Belt etc) to be carried
along with the people who are all working at the site.