Method Statement-Hard Landscaping Works
Method Statement-Hard Landscaping Works
Method Statement-Hard Landscaping Works
METHOD STATEMENT
Rubber mallet.
Shovel.
Straight Edge.
Sprit Level
Plum bob. & All other masonry tools
Measuring Device:
Dumpy Level
Total level
Theodolite
Measuring Tape
Tube level etc
Equipments:
Mixer machine
Hand cutting machine.
Water cutting machine
Hand drilling machine
Hand grinder.etc
METHOD STATEMENT FOR HARD LANDSCAPPING WORKS
Safety Shoes
Safety Helmets
Hand Gloves
Goggles
.
METHOD STATEMENT FOR HARD LANDSCAPPING WORKS
METHOD STATEMENT
HARD LANDSCAPING WORKS
Rubber mallet.
Shovel.
Straight Edge.
Sprit Level
Plum bob. & All other masonry tools
Measuring Device:
Dumpy Level
Total station
Measuring Tape
Tube level etc
Equipments:
Mixer machine
Hand cutting machine.
Water cutting machine
Asphalt Cutting machnine
Hand drilling machine
Hand grinder.etc
JCB
Bobcat
METHOD STATEMENT FOR HARD LANDSCAPPING WORKS
Procedure
1. All materials will be stored in proper place allocated by the main contractor and same
shall be lifted to the Hard scape area by using wheel barrow
2. All the materials will be inspected before using it for installation and damaged
materials will be rejected.
3. Based on the approved sharp drawing, RCC core filled block work marking for
landscape wall in Zone 1,2,3,4 in External area.
4. 8mm dia drilling will be carried out in the basement slab (by using Drilling machine) to
a depth of 5cm @ 200 mm center to center distance
5. The drilled surface area shall be cleaned properly before applying LOKFIX
6. The steel rod inserted in a proper alignment and LOKFIX shall be applied to the
required quantity and allow it for 3hrs. for drying.
7. The block shall be placed by inserting the steel rod one on other, by applying the
cement mortar (1:1:2) between the block
8. The center of the hollow block shall be filled with cement concrete to the entire row
9. Similarly the other row of block work will be carried to the required height as shown in
the approved shop drawing
10. The completed work will be cleaned from all debris and will be offered to consultant for
inspection.
Verification
Procedure Site made Setting Mortar: Mix and proportion cementitious materials for site
made leveling coats, setting beds & grout.
Ensure surfaces are clean and well cured, and sloped to drains where drains are provided.
Do not commence work until surface conditions are within tolerances required for proper
installation; apply leveling material where necessary to meet required tolerances.
Clean stone before setting by thoroughly scrubbing with fiber brushes followed by
thorough sponging with clear water; use only mild cleaning compounds that contain no
caustic or harsh fillers or abrasives.
Apply Portland cement mortar setting bed to proper line and tamp firmly.
Apply setting bed over areas no greater than can be covered while setting bed remains
plastic.
Trowel or brush thin layer, 1mm to 1.5mm thickness, of cement paste over setting bed.
Apply stone in place and beat firmly into straight, uniform joints.
Complete beating and leveling within one hour of setting; wipe clean with soft
damp cloth
After completion of work, point open joints and replace defective work.
Do not use wire brushes, acid type-cleaning agents, cleaning compounds with caustic or
harsh fillers, or other materials or methods, which could damage stone.
Verification
3. Setting out
6. Shop drawings
Safety