High Rise Commercial Building Slide PDF
High Rise Commercial Building Slide PDF
High Rise Commercial Building Slide PDF
COMMERCIAL BUILDING
S I N A L A N D E L E M E N U TA R A K K
SHAFIRA MAYFARDA WAHID NUR AFIFAH BINTI KASSIM
BK16170003 BK16110023
GROUP
MEMBERS:
FATIN ATIQAH BINTI MD YUNOS
BK161110123
Add a Footer 2
WHAT IS A COMMERCIAL
BUILDING?
Office buildings
Retail buildings
Industrial buildings
Multifamily housing
Hotels and motels
Special-purpose buildings.
Add a Footer 3
PROJECT DESCRIPTION
Add a Footer 5
PROJECT COST
Total project cost ≈ RM 200,000,000
Administration cost
Add a Footer 66
DURATION OF PROJECT
• The total duration of this project to be done is almost six years to be completed.
• Expecting no delay onto this project.
Add a Footer 77
TYPE OF PROJECT
MANAGEMENT CONCEPT
Project for Elemen Utara KK
Add a Footer 8
Project for
Elemen Utara
KK Taman Sinar Jaya,
Terrace house 41
units
9
Project for
Elemen Utara
KK • Established in 1951 by the late Architect Billings Leong
• Early modernist architecture
ARCHITECT
(KK Times Square)
10
IKHLAS PERUNDING
Project for
Elemen Utara • Established in 1996 by Ir. Liew
KK Kian Chui
• Formerly known as KC
Consultant, but changed in
November 2002
• Provide professional
CONSULTANT consultant services (Civil,
Structural Engineering &
Project Management)
(Jalan Tuaran, KK)
11
CHINA BORNEO BUILDERS SDN BHD
Project for
Elemen Utara
KK
CONTRACTOR
• Established in 1982
• Main activities: Construction of
(Luyang, KK) Buildings & Non-residential
Building Construction
12
INITIAL WORKS BEFORE
CONSTRUCTION
The Conception of the Project
Starts with the client to do some research
01
Meeting held to discuss about client consent
Meeting between Architect and Consultant to discuss about cost and constructibilitty of the project
Design Progress
Client come up with ideas of the concept and design
02
Architect will begin to design as per Architectural Drawing
All process to need to liase with Quantity Surveyor and Mechanical and Electrical
(M&E) Consultant
03
Authority
Design completed, proposed design (e.g. Development Plan
and Infrastructure work) need to be submitted to Authority
05
Procurement
Project Team will start to order and
obtain all the materials needed for
the project construction
13
PROBLEMS DURING
CONSTRUCTION
CONSTRUCTION COST > CONTRACTUAL COST
Improve misunderstanding
or miscommunications Structural engineers
on site making sure that
architect's drawing
This should be matched up is safe and secure.
with an appropriate and
Sometimes there will be a
suitable information
difference between
communication system.
architects and consultant's
drawing
15
Add a Footer 16
THANK YOU
17