Electrial Power Distribution Systems
Electrial Power Distribution Systems
Electrial Power Distribution Systems
Distribution Systems
3 PDH / 3 CE Hours
PDH Academy
PO Box 449
Pewaukee, WI 53072
www.pdhacademy.com
[email protected]
888-564-9098
1. With regards to transformer losses, in general, a heavily loaded transformer has lower
losses, and therefore has __________, than when it is lightly loaded.
a. lower life cycle cost
b. longer life expectancy
c. higher life cycle cost
d. shorter life expectancy
2. Considering line regulation, the voltage drop for primary lines shall not exceed:
a. 5 percent
b. 3 percent
c. 10 percent
d. 2 percent
3. With respect to cable types, lead-sheathed cable is generally used for submarine
(underwater) installations and is usually:
a. carbon-composite
b. clad in poly-vinyl chloride
c. annealed-magnesium
d. armored
4. In determining the strength requirements and the adequate physical and structural
requirements for overhead system support poles, the designer should refer to
_______________________________ and ANSI C2.
a. ASTM-E2018
b. Fink and Beaty, Standard Handbook for Electrical Engineers
c. National Electrical Institute Wiring and Distribution Reference Volume 2
d. United States Steel Structural Design Guide, 2005 Edition
7. Where an underwater cable crossing is subjected to flow or tidal currents, _______ are
usually required to prevent excessive drifting or shifting of the cable along the bottom.
a. trenches
b. conduits
c. stand-offs
d. anchors
10. With regards to transformers, primary unit substations require less land space, are
visually less objectionable, and because of the integrated transformer to secondary
connection, _________ than separate substation transformers and secondary protective
devices.
a. are less reliable.
b. are more reliable
c. are more complicated
d. are more difficult to install
UFC 3-550-03N
16 January 2004
CONTENTS
Page
CHAPTER 1 INTRODUCTION
i
UFC 3-550-03N
16 January 2004
APPENDIX A
MIL-HDBK 1004/2A
POWER DISTRIBUTION SYSTEMS
A-1
MIL-HDBK-1004/2A
15 JANUARY 1992
SUPERSEDING
MIL-HDBK-1004/2
31 MARCH 1988
INCLUDING NOTICE 1
15 FEBRUARY 1991
MILITARY HANDBOOK
AREA FACR
MIL-HDBK-1004/2A
ABSTRACT
This handbook covers design criteria for electric power distribution systems
including basic data, overhead and underground distribution systems, submarine
cable systems, and substations. The basic design guidance has been developed
from extensive reevaluation of facilities and is intended for use by
experienced architects and engineers.
ii
MIL-HDBK-1004/2A
FOREWORD
This handbook has been developed from an evaluation of facilities in the shore
establishment, from surveys of the availability of new materials and
construction methods, and from selection of the best design practices of the
Naval Facilities Engineering Command (NAVFACENGCOM), other Government
agencies, and the private sector. This handbook was prepared using, to the
maximum extent feasible, national professional society, association, and
institute standards. Deviations from this criteria, in the planning,
engineering, design, and construction of Naval shore facilities, cannot be
made without prior approval of NAVFACENGCOM HQ Code 04.
Design cannot remain static any more than can the functions it serves or the
technologies it uses. Accordingly, recommendations for improvement are
encouraged and should be furnished to Commander, Pacific Division, Naval
Facilities Engineering Command, (Code 406), Pearl Harbor, HI 96860-7300;
Telephone (808) 471-8436.
iii
MIL-HDBK-1004/2A
Criteria Title PA
Manual
iv
MIL-HDBK-1004/2A
CONTENTS
Page
Section 1 INTRODUCTION
1.1 Scope........................................... 1
1.2 Cancellation.................................... 1
1.3 Technical Factors............................... 1
1.3.1 Feeders......................................... 1
1.3.2 Current (Ampere) Levels and Interrupting Duties. 1
1.3.3 Equipment Requirements.......................... 1
1.3.4 Weather Extremes................................ 1
1.3.5 Local Codes..................................... 1
1.4 Economic Factors................................ 2
1.4.1 Number of Circuits.............................. 2
1.4.2 Voltage......................................... 2
1.4.3 Transformer Losses.............................. 2
1.5 Special Construction............................ 2
1.6 Shore-To-Ship Distribution Systems.............. 3
1.7 Good Practice................................... 3
v
MIL-HDBK-1004/2A
Page
vi
MIL-HDBK-1004/2A
Page
vii
MIL-HDBK-1004/2A
Page
Section 5 SUBSTATIONS
5.1 General Considerations.......................... 29
5.1.1.1 Type of System Supplied......................... 30
5.1.1.2 Location........................................ 30
viii
MIL-HDBK-1004/2A
Page
5.1.2 Definitions..................................... 30
5.1.3 Typical Substation Layouts...................... 30
5.2 Indoor Unit Substations......................... 30
5.2.1 Preliminary Considerations...................... 30
5.2.1.1 Location........................................ 30
5.2.1.2 Capacity........................................ 30
5.2.1.3 Safety.......................................... 31
5.2.2 Design.......................................... 31
5.2.2.1 Mounting........................................ 31
5.2.2.2 Short-Circuit Duty.............................. 31
5.2.2.3 Primary Protection.............................. 31
5.2.2.4 Lightning Protection............................ 31
5.2.2.5 Secondary Protection............................ 31
5.2.2.6 Instrumentation................................. 31
5.2.3 Arrangements.................................... 32
5.2.3.1 Reversed........................................ 32
5.2.3.2 Double-Ended.................................... 32
5.2.3.3 Secondary Spot-Network.......................... 32
5.2.4 Transformer Insulations......................... 32
5.2.4.1 Dry-Type Units.................................. 33
5.2.4.2 Nondry-Type Units............................... 33
5.2.4.3 Insulation Comparisons.......................... 33
5.2.5 Unit Substation Rooms........................... 33
5.2.5.1 Drainage........................................ 33
5.2.5.2 Access.......................................... 33
5.2.5.3 Ventilation..................................... 39
5.2.5.4 Noise........................................... 40
5.2.5.5 Emergency Lighting.............................. 40
5.3 Outdoor Utilization Voltage Substations......... 40
5.3.1 Secondary Unit Substation Types................. 40
5.3.2 Pad-Mounted Compartmental-Type Transformer Units 40
5.3.2.1 Units 500 Kilovolt-Amperes and Smaller.......... 40
5.3.2.2 Units Larger than 500 Kilovolt-Amperes.......... 40
5.4 Outdoor Distribution Voltage Substations........ 40
5.4.1 Structure-Mounted Equipment..................... 41
5.4.2 Transformers.................................... 41
5.4.3 Connection to Primary Distribution Lines........ 41
5.5 Substation Considerations....................... 41
5.5.1 Site Effects.................................... 41
5.5.2 Electric Configuration.......................... 41
5.5.3 Incoming-Line Switching......................... 42
5.5.3.1 Circuit Breakers................................ 42
5.5.3.2 Switches........................................ 42
5.5.3.3 Current Limiting Protectors..................... 42
5.5.4 Outgoing-Feeder Switchgear...................... 42
5.5.4.1 600 Volts and Less.............................. 42
5.5.4.2 Over 600 Volts.................................. 43
ix
MIL-HDBK-1004/2A
Page
x
MIL-HDBK-1004/2A
Page
FIGURES
TABLES
REFERENCES.........................................................49
xi
MIL-HDBK-1004/2A
SECTION 1: INTRODUCTION
1.1 Scope. This handbook presents data and considerations that are
necessary for the proper design of overhead and underground distribution
systems, submarine cable systems, and substations having medium-voltage (601
to 35,000 V) or low-voltage (up to 600 V) secondaries.
1.3 Technical Factors. Ensure that design does not violate these
technical constraints.
1.3.5 Local Codes. Where state safety rules are predominantly accepted as
a standard in that state, such rules may be used provided they are essentially
as stringent as those of NFPA 70, the American National Standards Institute
(ANSI) C2, National Electrical Safety Code (NESC), and approval of
NAVFACENGCOM Headquarters is obtained. An example of such a code is the State
of California Public Utilities Commission, General Order No. 95, Overhead Line
Construction. This code is also of interest because it has more extensive
coverage on armless construction than does ANSI C2, and it contains useful
data on conductors, clearances, typical problems, and illustrative diagrams on
1
MIL-HDBK-1004/2A
various rules. The wind and ice loadings are different from those of ANSI C2,
but the clearances illustrated are generally more stringent. Use of these
illustrations will provide a safe and economic installation. The Institute of
Electrical and Electronics Engineers (IEEE) also publishes Clapp, NESC
Handbook which was developed to aid users in understanding and correctly
applying this code.
2
MIL-HDBK-1004/2A
3
MIL-HDBK-1004/2A
Table 1
Information Required For Circuit Design
___________________________________________________________________________
ITEM SPECIFIC INFORMATION REQUIRED
___________________________________________________________________________
Individual building
demand loads Determine proposed demand loads utilizing calculation
methods similar to that used in Table 4 of MIL-HDBK-
1004/1 or based on field measurements.
--------------------------------------------------------------------------
Coincident peak
demand
Determine facility peak demand utilizing calculation
methods similar to that use in Table 7 of MIL-HDBK-
1004/1 or based on field measurements.
--------------------------------------------------------------------------
Number of circuits
and voltage level Select number of circuits and voltage level. Number
of circuits will depend upon location and magnitude of
individual loads. Voltage level or type of distribution
should be in accordance with data in MIL-HDBK-1004/1.
Provide sufficient future capacity (+ or - 25 percent).
--------------------------------------------------------------------------
Other considerations Balance single phase loads on multi-phase circuits.
Design large starting loads to have a minimal effect
on demands.
___________________________________________________________________________
2.1.2 Capacity. Make provision for spare capacity in each portion of the
circuit.
4
MIL-HDBK-1004/2A
2.1.3 Wire Size. Select wire size in accordance with the current-carrying
capacity required and, where applicable, the voltage-drop limitation.
2.2.1.2 Heights and Classes. Limitations on pole heights and classes for
wood poles are given in Table 2. Class normally used refers to primary poles
spaced not more than 200 feet (61 m) apart, which serve industrial or housing
areas and which are generally at least 40 feet (12 m) or more in height. See
ANSI C2 for definition of classes. Refer to Table 3 for data on transformer
poles. Refer to Fink and Beaty, Standard Handbook for Electrical Engineers to
determine the limitations on minimum heights and classes for poles carrying
other equipment.
2.2.1.4 Safety Factors. Refer to ANSI C2 for the minimum safety factors to
be used.
2.2.1.5 Pole Installation. For pole depth, refer to the criteria in Fink
and Beaty, Standard Handbook for Electrical Engineers and ANSI C2. Refer to
Fink and Beaty, Standard Handbook for Electrical Engineers for pole placement
with respect to anchors or braces. Footings or reinforcements of the pole
butt-end shall be as required by foundation conditions.
2.2.1.7 Crossarms. Use crossarms mainly for equipment support. Follow the
criteria in Fink and Beaty, Standard Handbook for Electrical Engineers.
5
MIL-HDBK-1004/2A
Table 2
Height and Class of Wood
___________________________________________________________________________
Transformer platform
using two poles:
(1) Existing poles -- 5 --
(2) New poles -- 3 --
Underground cable
riser poles 2.4 thru
35 kV -- 3 --
Pole--top switch -- 3 --
__________________________________________________________________________
(a) Increase heights by not less than 5 feet (1.5 meters) if telephone or
signal wires are caried or are likely to be installed.
2.2.2 Guys and Anchors. Provide guys and anchors to support poles or line
towers against horizontal unbalanced loads caused by angles, corners, and dead
ends of lines and where required because of extreme wind loadings. Refer to
Fink and Beaty, Standard Handbook for Electrical Engineers for criteria.
6
MIL-HDBK-1004/2A
Table 3
Wood Pole Sizes for Single Pole Transformer Installations
___________________________________________________________________________
MAXIMUM TRANSFORMER RATING (KVA)
___________________________________________________________________________
POLE ONE
BANK OF THREE
ONE
MINIMUM CLASS SINGLE-PHASE SINGLE-PHASE (CLUSTER MOUNTED) THREE-PHASE
--------------------------------------------------------------------------
5 5 -- --
4 15 -- --
4 25 -- --
3 37-1/2 -- 15
3 -- 3-15 30
2 50 3-25 45
2 75 3-37-1/2 75
1 100 3-50 112-1/2
___________________________________________________________________________
2.2.3.1 Size Limitations. Normally limit the use of pole line conductors in
accordance with Table 4, except for primary wires which usually should be not
less than No. 6 AWG (13.3 square mm) copper or No. 2 AWG (33.6 square mm)
aluminum. The range of conductors in Table 4 gives the most economical system
from the installation, operational, and maintenance points of view. Special
instances may require larger conductors. In all cases be sure that the type
and size of conductors used has adequate strength for span lengths and loading
conditions. Select conductor sizes to provide required minimum strengths in
accordance with loading requirements of ANSI C2 for areas in the United States
and in accordance with facility loading requirements for areas outside the
United States.
2.2.3.2 Normal Primary Lines. Normally, specify bare conductors for primary
lines stranded or solid construction as suitable to the size and composition
as follows:
7
MIL-HDBK-1004/2A
Table 4
Conductor Sizes for Overhead Lines
___________________________________________________________________________
CONDUCTOR SIZE
TYPE
---------------------------------------------------------------------------
Not larger than Not smaller than
---------------------------------------------------------------------------
Copper 4/0 AWG (107 mm2) 8 AWG (8.37 mm2)
2
Aluminum 336.4 kcm (170 mm ) 6 AWG (13.3mm2)
___________________________________________________________________________
8
MIL-HDBK-1004/2A
2.3 Line Regulation. The voltage drop for primary lines shall not
exceed 3 percent. Maintain the power factor of the line as close to unity as
economically practical so as to minimize system losses. Regulation utilizing
load-tap-changing transformers to correct line voltage variations resulting
from changing loads or utility company sending-end voltage swings is covered
in Section 5. Requirements for line equipment follow:
9
MIL-HDBK-1004/2A
2.4.1 Pole Mounting. For single-pole mounting, limit the size of single-
phase or three-phase units in accordance with Table 3. Do not use pole-
platform mounting (two-pole structures) except in instances where other
methods are not satisfactory. It is recommended that maximum transformer size
be limited to the sizes shown in Table 3. For installations of 225 to 500
kVA, pad-mounted, compartmental-type transformers are recommended.
10
MIL-HDBK-1004/2A
11
MIL-HDBK-1004/2A
2.5.3 Circuit Breakers. Use a circuit breaker rating adequate for the
load interrupting duty and which provides selectivity with circuit breakers
and fuses ahead of or after the circuit breaker.
12
MIL-HDBK-1004/2A
are often used for protection of transmission lines. In areas where annual
lightning storms are few, no protection for lightning-induced surges may be
necessary. Local naval facility or utility company practice should generally
be followed (refer to MIL-HDBK-1004/6, Lightning Protection) for equipment
protection, aerial-to-underground transition points, and other appropriate
locations.
2.8.2 Ground Resistance Path. Provide a low impedance path at the source
of fault currents, if a circuit contains a deliberate ground connection.
2.8.4.1 Ground Rods. Ground rods may be used either singly or in clusters.
Drive the ground rods to ground water level for an effective and permanent
installation. Provide for corrosion prevention by a proper choice of metals
or by cathodic protection. Where ground water cannot be reached, chemicals
such as magnesium sulphate (MgSO4) or copper sulphate (CuSO4) may be used to
improve soil conductivity where necessary. Manufacturers of ground rods can
13
MIL-HDBK-1004/2A
provide data on such treatment. Provide for easy maintenance and periodic
testing. Driving ground rods deeper using sectional rods may be more
effective than using multiple rods. In many cases, soil variations and
possible bedrock may make provision of additional rods less expensive.
2.8.4.4 Ground Connections. Keep wires running from protective devices (for
example, gaps, grading rings, expulsion or protection tubes, and surge
arresters) to ground as straight and short as possible. Where bends are
necessary, provide them of large radii to keep the surge impedance as low as
possible.
2.8.5 Overhead Ground Wires. Where overhead ground wires are used for
protection of electric lines, provide a ground connection from the overhead
ground wire to a wire loop or a ground plate at the base of the pole or to a
driven rod, depending on the existing soil conditions. Use of wire wraps or
pole butt plates is allowed by ANSI C2 only in areas of very low soil
resistivity. Ground the overhead ground wire at each pole.
14
MIL-HDBK-1004/2A
2.10.2 Trees. Because trees adjacent to any overhead line pose a line
clearance problem, ensure that growing trees do not result in any line outage
or damage. Complete removal of all trees in the right-of-way is probably
environmentally unacceptable. Remove tree species, which in conjunction with
the weather and soil condition are liable to uprooting if their location poses
a clear danger to the line. Otherwise trim trees to provide a hazard-free
operation for at least 2 years. Competent persons shall do the trimming to
avoid excessive tree damage and to assure that trees off the right-of-way are
not trimmed by mistake. Obtain the landowner's permission for any trimming
and conduct a though cleanup after trimming.
15
MIL-HDBK-1004/2A
3.2 Direct Burial. Install direct-burial cables only in areas that are
rarely disturbed. After first considering economic, maintenance, and
reliability effects, restrict direct burial to light loads, to roadway
lighting systems, and to long untapped runs in low density areas. In some
instances, a minimal amount of taps may be acceptable.
3.2.2 Installation
3.3 Draw-In Systems. Draw-in systems consist of duct systems (which may
include access points such as manholes and handholes) in which cable is drawn
after the duct system has been installed. Provide a draw-in system where
overhead distribution is not feasible (refer to MIL-HDBK-1004/1). Provide a
draw-in system for distribution of large blocks of electric power, where many
circuits follow the same route or are run under permanent hard pavements, or
where service reliability is paramount.
3.3.1.1 Routes. Select duct line routes to balance maximum flexibility with
minimum cost and to avoid foundations for future buildings and other
structures.
16
MIL-HDBK-1004/2A
3.3.1.3 Clearance. Keep electric and communication ducts clear of all other
underground utilities, especially high-temperature water or steam pipes.
3.3.1.5 Size of Ducts. Base the size of conduits in a duct bank shall be
based on consideration of the following factors:
c) special cases may require use of larger sizes, but such sizes
shall be functionally justified.
3.3.1.8 Spare Capacity. Include ducts for planned future expansion, plus 25
percent additional spare ducts for unplanned expansion.
17
MIL-HDBK-1004/2A
18
MIL-HDBK-1004/2A
3.3.2 Manholes and Handholes. Use double manholes where electric power
and communication lines follow the same route. Select manholes and handholes
of a suitable type from NFGS-16301.
3.3.2.3 Use. Use manholes for all main duct runs and wherever medium-
voltage cable is installed. Handholes may be used on laterals from manhole
and duct line systems for low-voltage power and communication lines for
building services.
3.3.2.6 Stubs. Provide a set of spare stubs so that the manhole wall will
not need to be disturbed when a future extension is made.
19
MIL-HDBK-1004/2A
20
MIL-HDBK-1004/2A
3.4.3.1 Advantages. Both XLP and EPR are thermosetting, solid dielectric
compounds with excellent electrical insulation properties, good chemical
resistance and physical strength charateristics, and both remain flexible at
low temperatures.
3.4.3.2 Disadvantages. Although EPR is more expensive than XLP and both
have excellent moisture resistance, the degradation phenomenon called treeing
appears to occur more frequently in XLP and is aggravated by the presence of
water. EPR also is less susceptible to corona discharge activity than XLP,
but in a properly designed and manufactured cable, damaging corona is not
expected to be present at the usual operating voltages.
3.4.4.6 Rubber. Use rubber insulated conductors for ease of splicing, good
moisture resistance, and low dielectric losses.
21
MIL-HDBK-1004/2A
22
MIL-HDBK-1004/2A
3.4.11.1 Sulfur hexaflouride Gas. This gas has five times the density of air
and acts as an "invisible liquid" as it stays in place even when exposed to
air. It is electro-negative with no oxygen or carbon; has a high arc
resistance; will not support combustion; and is odorless, tasteless, and
nontoxic. When used with XLP and EPR insulations, it prevents water vapor
diffusion, water treeing, and gaseous ionization. It provides monitoring for
indication of mechanical damage during shipment, installation, and during
operation. Sulfur hexaflouride gas improves the lightning and impulse
strength and can provide a rehealing of insulation after an electromagnetic
pulse insulation failure. The gas pressure protects against internal
corrosion of metal parts. The SF6 gas provides extra electrical strength in
splices and terminations.
23
MIL-HDBK-1004/2A
Adjustment factors are given only for different ambient earth temperatures.
No corrections are included for different load factors, thermal resistances,
conductor spacings, or cable temperatures. A load factor of 50 percent and an
RHO of 60 are not unusual which could increase the listed ampacity by as much
as 15 to 50 percent. Detailed calculation methods along with ampacities for
other conditions are contained in IEEE/ICEA P-46-426, Power Cable Ampacities.
24
MIL-HDBK-1004/2A
4.1.1 Where Permitted. Use submarine cable only where local conditions
rule out the use of any other system.
4.2.2.2 Currents. Provide cables installed across rivers with currents with
a curved upstream concave alinement. Determination of the amount of curved
alinement necessary depends upon the speed of the current.
4.2.2.3 Variable (Changing) Waters. Obtain approval for routes and minimum
depths for crossings under variable waters from the Department of the Army,
Corps of Engineers or by the corresponding authority.
4.2.4 Marine Traffic. Bury any cables crossing through waters adjacent to
marine traffic to a depth that eliminates any damage from dragging anchors.
Large ships may drop anchors up to 15 feet (4.5 m) in depth on sand bottoms.
4.3 Installation. Install cables to lie on the bottom, with ample slack
so that slight shifting will not place excessive strain on them. Because of
the great weights involved when any considerable length of submarine cable is
to be sunk across a waterway, use installation methods to keep tensile
stresses at a minimum. The ideal lay of a submarine cable on a bottom is a
series of horizontal S-curves. This pattern provides the slack necessary to
25
MIL-HDBK-1004/2A
prevent injurious straining of the cable. Where two parallel cables cross,
provide a separation of 100 feet (30.5 m) to avoid fouling and to permit work
space (refer to criteria in the Underground Systems Reference Book).
4.3.5 Maps. The development of accurate maps is one of the most important
steps in an extension of a submarine cable installation. Maps indicate the
exact location of the cable at various points along its length, as established
by surveying instruments. To estimate cable movement or drifting on the
bottom, the maps must also indicate the exact length of the cable installed
between any two reference points.
26
MIL-HDBK-1004/2A
4.5.1 Terminations
27
MIL-HDBK-1004/2A
4.5.3 Bonding. Cable sheaths and armor shall be bonded together at every
splice and at both shore ends.
28
MIL-HDBK-1004/2A
SECTION 5: SUBSTATIONS
Table 5
Substation Terminology
______________________________________________________________________________
TERM DEFINITION
______________________________________________________________________________
29
MIL-HDBK-1004/2A
5.2.1.2 Capacity. Transformers larger than 500 kVA for 208Y/120 V building
service are not permitted. Similarly, do not specify transformers in ratings
of over 1,000 kVA or in exceptional cases larger than 1,500 kVA for 480Y/277 V
building service and only where functionally required. The use of smaller
transformers supplying larger loads adds flexibility and reliability to the
system. Shore-to-ship service may require larger transformers. Transformers
rated 1,500 kVA or larger should utilize secondary busway where a connection
to a nonintegral secondary switchgear section is required unless such a
30
MIL-HDBK-1004/2A
5.2.2.6 Instrumentation. Provide unit substations of more than 500 kVA with
at least an ammeter and a secondary voltmeter. The use of wattmeters
(recording or indicating) and voltmeters, for primary service metering, will
depend on the individual installation. For provision of watthour demand
meters with pulse initiators, see requirements for energy monitoring in this
section.
31
MIL-HDBK-1004/2A
32
MIL-HDBK-1004/2A
functional justification for the type of unit provided. Select the insulation
type on the basis of surrounding atmosphere and basic impulse insulation level
required. Check loading characteristics from ANSI C57.91, C57.92, or C57.96
making sure that the lower impulse level standardly provided for dry-type
units are adequately protected. Ensure equipment conforms to NFGS-16465.
5.2.5 Unit Substation Rooms. Ensure unit substation rooms do not contain
any pipes, ducts, or other foreign systems, except those required for fire
protection, ventilation, and drainage of the room; however, dry-type units may
be installed without a separate room if piping is not run immediately over
such units.
33
MIL-HDBK-1004/2A
34
MIL-HDBK-1004/2A
MIL-HDBK-1004/2A
MIL-HDBK-1004/2A
37
MIL-HDBK-1004/2A
38
MIL-HDBK-1004/2A
Table 6
Comparison of Types of Transformer Insulation
______________________________________________________________________________
LIQUID-INSULATEDDRY-TYPE
TRANSFORMER
QUALITIES OIL LESS- CONVENTIONAL EPOXY- GAS-
FLAMMABLE ENCASED FILLED
______________________________________________________________________________
Relative 100% 100% Varies(1) Varies(1) Varies(1)
Impulse strength
(BIL)
Relative X X X + 10 dB X + 10 dB X + 10 dB
audio sound
level in dB (2)
Relative Cost 237% (100%) 200% (130%) 125% (127%) 200% (200%)
220% (220%)
______________________________________________________________________________
(1) Varies from 33 to 66% depending on voltage level. Higher BIL ratings for
dry-type transformer are available, but an increased cost for conventional
and gas-filled types.
(2) X indicates normal decibel level for liquid-immersed units.
(3) Indoor also in fire-resistant vaults when more economical than other
types.
(4) Not recommended in extreme environment containing excessive dirt or dust
or containing concentration of corrosive elements.
39
MIL-HDBK-1004/2A
5.2.5.4 Noise. If local conditions require less than NEMA TR-1 recommended
audio sound levels, make an economic comparison between the cost of
transformers having lower than standard noise levels, and the cost of sound
and vibration isolation of the transformer room. Avoid locating unit
substation rooms near critical spaces requiring low noise levels, such as
auditoriums, sick bays, or living quarters (refer to NAVFAC DM-1.03,
Architectural Acoustics).
5.3.2.1 Units 500 Kilovolt-Amperes and Smaller Units are not Provided with
Either Taps or a Minimum Percent Impedance Unless Specified. To prevent
excessive interrupting duty on secondary equipment it may be necessary to
check manufacturers' ranges of available impedances, as there is no industry
standard.
5.3.2.2 Units Larger than 500 kVA. Pad-mounted units in three-phase units
larger than 500 kVA are available up to a capacity of 2,500 kVA. These units
are less expensive than secondary substation units. However, because primary
protective devices available for such larger sizes do not provide dead-front
load-break features within the pad-mount construction, the use of units larger
than 750 kVA is not recommended.
40
MIL-HDBK-1004/2A
5.4.2 Transformers. Primary unit substations require less land space, are
visually less objectionable, and because of the integrated transformer to
secondary connection, are more reliable than separate substation transformers
and secondary protective devices.
41
MIL-HDBK-1004/2A
a) number of circuits,
b) capacity of circuits,
c) voltage and phase, and
d) overhead or underground distribution required.
5.5.3.1 Circuit Breakers. Use circuit breakers only when the circuit
interrupting or relaying requirements do not allow the use of switches.
Provide a disconnect and bypass switching features where drawout circuit
breakers cannot be utilized.
5.5.4.1 600 V and Less. For load circuits below 600 V, select from one of
the following:
42
MIL-HDBK-1004/2A
5.5.4.2 Over 600 Volts. For load circuits over 600 V, use criteria in MIL-
HDBK-1004/3 to select from the following:
5.5.6 Transformers
5.5.6.1 Selection. Consider the types of insulation that are suitable for
the site and the system voltages (see Table 6). Select oil-insulated for
outdoor applications, except where fire safety considerations require the use
of less-flammable, liquid-insulated insulation which is not usually available
for voltages above 34.5 kilovolts. For indoor installations, see the
paragraph on transformer insulations of this section.
5.5.6.2 Cooling. Forced cooled ratings are only available on larger size
transformers; check their availability before specifying. Dependent upon
standard ratings and overload capacity calculations, specify the cooling
method from one of the following:
43
MIL-HDBK-1004/2A
44
MIL-HDBK-1004/2A
5.5.8.3 Control Cables. For control cables refer to IEEE No. 525, Guide for
the Selection and Installation of Control and Low-Voltage Cable Systems in
Substations.
5.6 Substation Working Space and Access Requirements. Design indoor and
outdoor substation layouts to provide safe working space and access to meet
the requirements of NFPA 70 keeping in mind any need for installing and
removing equipment, vehicle access necessary for outdoor substations, and
adequacy of floor or foundations to support equipment weights.
45
MIL-HDBK-1004/2A
5.7.1.1 Girdle Type. Use girdle type systems for pad-mounted com-partmental-
type transformers and secondary unit substations (see Figure 4).
5.7.1.2 Grid Type. For the much larger voltage gradients at substations for
utility-Navy interconnections use the grid-type, buried grounding network.
Mesh spacings of 10 to 12 feet (3 to 3.5 m) are commonly used and normally
such spacings can control surface voltage gradients even though the ground
resistance may be relatively high.
5.7.1.3 Special Techniques. See recommendations of IEEE 80, Guide for Safety
in Substation Grounding. Where the local utility or activity indicates the
special grounding techniques are necessary because of poor soil conductivity,
their recommendations should be followed. Refer to IEEE 142,
Recommended Practice for Grounding of Industrial and Commercial Power Systems
for a discussion of soil resistivity. Refer to NFGS-16302 for maximum
allowable ground resistance values.
46
MIL-HDBK-1004/2A
5.7.4.1 Fault Current. NFPA 70 requires a low impedance ground path for
fault currents. Where reliable low impedance paths for utilization
substations cannot be provided because of soil conditions, equipment
locations, or other factors, install a ground wire with the primary feeder
cable back to the distribution system substation.
5.8 Safety Considerations. Provide for public safety and for protection
of operating personnel with respect to the factors described in paras. 5.8.1
through 5.8.5.
47
MIL-HDBK-1004/2A
5.8.4 Bonding of Gates. For grounding purposes, provide gates with bonding
straps across hinges.
5.8.5 Legal Warning Signs. Legal warning signs are required on fences and
electrical equipment enclosures which are unfenced. Guidance for warning
signs in family housing and community center areas is given in NEMA 260,
Safety Labels for Padmounted Switchgear and Transformers Sited in Public
Areas.
48
MIL-HDBK-1004/2A
REFERENCES
49
MIL-HDBK-1004/2A
Industrial Power Systems Handbook, Donald Beeman, Editor, McGraw Hill Book
Company, New York, NY 10020, 1955.
Institute of Electrical and Electronic Engineers (IEEE), 345 East 47th Street,
New York, NY 10017. The following publications are IEEE Standards.
50
MIL-HDBK-1004/2A
Substations
51
MIL-HDBK-1004/2A
52
MIL-HDBK-1004/2A
Copies are available from the Commanding Officer, Naval Publications and Forms
Center Directorate, ASO Code 10, 5801 Tabor Avenue, Philadelphia, PA 19120.
Government activities must use the Military Standard Requisitioning and Issue
Procedure (MILSTRIP), using the stock control number obtained from NAVSUP
Publication 2002. Commercial organizations may obtain copies from the above
address, Attention: Cash Sales, Code 1051.
Overhead Line Construction, General Order No. 95, State of California, Public
Utilities Commission, Sacramento, CA 95820.
Standard Handbook for Electrical Engineers, Donald G. Fink and H. Wayne Beaty,
Editors, McGraw-Hill Book Company, New York, NY 10020, Eleventh Edition.
Underground Systems Reference Book, EEI No. 55-16, Edison Electric Institute,
New York, NY 10016, 1957.
CUSTODIAN
PREPARING ACTIVITY
NAVY - YD NAVY - YD
PROJECT NO.
FACR-1066
53