ENGINEER'S Report For Generator Set of Laundry

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 3
At a glance
Powered by AI
The report discusses a 100 kW stand-by generator and 15 HP steam boiler installed at Donggwang Clark Corporation to support laundry services. It also details the air pollution control facilities and status of the installations.

The objective of installing the air pollution control facilities is to protect the air environment and human health.

The only source of air pollution mentioned is the emission from the stand-by power generator set.

ENGINEER’S REPORT

Air Pollution Control Facilities


(100 kW Stand-by Gen Set & 15 HP Steam Boiler)

Prepared for:

DONGGWANG CLARK CORPORATION


T-304 Jose Abad Santos Avenue
Clark Freeport Zone
Pampanga

Prepared by:

MARIO S. PAN JR. NATHANIEL Z. ESTEBAN


Professional Mechanical Engineer POLLUTION CONTROL OFFICER
PRC Reg. No. PME-2517 COA NO. 16F-03PA-330
PTR No. 2592008 DONGGWANG CLARK COPORATION
Issued on January 10, 2019
Issued at Mabalacat City, Pampanga
ENGINEER’S REPORT
Air Pollution Source

I. Introduction
The Donggwang Clark Corporation has a Lease Agreement with the Clark Development
Corporation (CDC) to develop a 309-hectare estate bounded by Jose Abad Santos Avenue,
Clark Freeport Zone. Its project, called Donggwang Sunvalley Leisure Community (“DSLC
Project”), is a master planned development that will have facilities for residential, business
center, education, hotel, and recreational facilities.

Inherent to the operation/occupancy of the facilities is the consumption of water and


electricity. In the laundry room for the use of hotel and casino services, there is power
generator set established to support the continuous supply of electricity in case of power
interruption and steam boiler for the heating operation of laundry room.

a. 100 kW Stand-by Generator- a single stack stand-by gen set with a capacity of 100 kW will
be used to supply alternate power for laundry services in case of power interruption
b. 15 hp Steam Boiler- a steam boiler with 15 hp capacity will be used to heat wash water
and also to provide steam for irons and presses.

II. Project Objective


The objective of installing the air pollution control facilities is to protect the air environment
and human health.

III. Air Pollution Source Installation


The only source of air pollution is coming from the emission of the stand-by power generator
sets. The location of each stand-by gen set is shown in the attached location plan.

IV. Emission of Air Pollution Source Installation

a. Power Generator Set and Steam Boiler


The power generator set and steam boiler as powered by diesel are equipped with
exhaust systems that include packaging of catalytic exhaust systems, engineered after
treatment components and system integration services for engine manufactures. Both
power gen set and steam boiler are capable of emitting cleaner air by removing nitrogen
oxides, particulate matter, and carbon dioxides from diesel engine emissions.

In addition, to maintain its efficiency (burning of diesel), the equipment will be maintained
and operated properly. No emission testing needed for the gen set and steam boiler
because of their capacity categorized as “small source”.
IV. Status of Air Pollution Installation

a. Power Generator Set and Steam Boiler


Both installed power generator and steam boiler are equipped with controller
information and can carry out functions including automatic start/stop, data measure and
alarms. The control system consists of set mounted panel providing: a) a means of starting
and stopping the generator set, b) monitoring its operation and output causing the engine
to automatically shut down in the event of a critical condition arising, i.e. low oil pressure.
It is also equipped with an alternator circuit breaker providing a means of switching the
generator output and automatically disconnecting the generator output and
automatically disconnecting the load in the event of overload.

The generator set and steam boiler are capable of emitting cleaner air by removing
nitrogen oxides, particulate matter, hydrocarbons, and carbon monoxide from diesel
engine emissions.

Operation of the stand-by gen set and steam boiler is expected to consume an average of
10 liters of diesel fuel per month for gen set, depending on the status of power supply in
the area, and 10 liters of diesel fuel for steam boiler.

You might also like