Project Report
Project Report
Project Report
ON
JAYKUMAR SINGH
Submitted Through
Wainganga College of Engineering & Management near Gumgaon Railway
Station, Dongargaon, Wardha Road, Nagpur
CERTIFICATE
The assistance and help rendered to the researcher during the course
of his investigation in the form of basic source material and information have
been duly acknowledged.
2
DECLARATION
I further declare that all the facts and figures furnished in this project report
are the outcome of my own intensive research and findings.
Place: DONGARGAON
SUBMITTED BY
3
ACKNOWLEDGEMENT
It was delightful learning experience to be associated with KSK ENERGY
VENTURES. The six weeks spent at SWPL WARORA, taught me many things
which will be with me throughout my life. It is with greatest pleasure and
pride that I present this report before you. At this moment of triumph it
would be unfair to neglect all those who helped me in the successful
completion of this project. First of all, I would like to thank the HOD MBA of
our college PROF.SANDIP PALI for the help and guidance rendered for the
completion of the project. It is beyond words to express our immense
gratitude to our project guide Ms. MAMTA NAKHATE for the guidance and
inspiration throughout this work. I am also very much thankful to managers
of all the ELECTRICAL department for their co-operation while I visited their
respective divisions. Last but not the least I thank my family members for
their encouragement and support.
Mr.JAYKUMARSINGH
4
INDEX
PAGE
CONTENTS
NO.
Introduction 6
1.1 Executive Summary
1.2 Condition monitoring
1.3 Overviews & Objectives
1.4 Principles & Methods
1.5 Course Content
1.6 Condition monitoring of motor
1.7 Condition monitoring of Transformer
1.8 Limitations
Company Profile 31
2.1 Overview of KSK ENERGY VENTURES
2.2 KSK projects
2.3 Historical Profile of KSK ENERGY VENTURES
Research Methodology 38
3.1 Objective
3.2 Hypothesis
3.3 Research design
3.4 Limitation & Scope
Data Collection & Analysis of Data 41
Reliability & Availability 52
Conclusion 53
Bibliography 54
5
INTRODUCTION
6
1.1 EXECUTIVE SUMMARY
This course will give an overview of the monitoring of the condition of
high voltage plant (mainly switchgear and power transformers) with an
emphasis in the ageing and degradation of the electrical insulation
materials.
The fundamentals of the electrical insulation affecting the Power
Systems Equipment will be explained. This will cover the insulation
structures based on solid, liquid and gas insulating materials commonly
used in the manufacturing of high voltage plant.
7
1.1 CONDITION MONITORING
Modern power plants depend heavily on rotating machines such as
steam turbines, gas turbines, and generators and so on. To maximize
power plant profit, rotating machines of power generation trains should
be operated with maximum reliability, maximum capacity, maximum
efficiency and minimum operating and maintenance costs.
9
1.4 PRINCIPLES AND METHODS:
10
A more satisfactory compromise in terms of maintenance strategy
is to carry out preventive maintenance at what may be irregular
intervals, but to determine these intervals by the ac-tual
condition of the machine at the time. For such condition-based
maintenance to be possi-ble, it is essential to have knowledge of
the machine condition and its rate of change with time. The main
function of condition monitoring is to provide this knowledge.
There are two main methods used for condition monitoring, and
these are trend monitoring and condition checking. Trend
monitoring is the continuous or regular measurement and
in-terpretation of data, collected during machine operation, to
indicate variations in the condi-tion of the machine or its
components, in the interests of safe and economical operation.
This involves the selection of some suitable and measurable
indication of machine or compo-nent deterioration, such as one of
those listed in Fig.2, and the study of the trend in this
measurement with running time to indicate when deterioration is
exceeding a critical rate. The principle involved is illustrated in
Fig.3, which shows the way in which such trend moni-toring can
give a lead time before the deterioration reaches a level at which
the machine would have to be shut down. This lead time is one of
the main advantages of using trend monitoring rather than simple
alarms or automatic shutdown devices.
12
EQUIPMENTS THAT CAN BE INSPECTED:
13
APPLICATIONS: -
Equipment to be monitored
Specific equipment that can be monitored by electrical condition
monitoring techniques are:-
1. Electrical Distribution Cabling
Mega ohm meter, Time Domain Reflectometry, Hi-Pot, IRT (if
visible), and Airborne Ultrasonic
4. Electrical Motors
Current Draw, Motor Current Spectrum Analysis, Motor Circuit
Analysis, Mega ohm meter. Hi-Pot, Surge Test, Conductor
Complex Impedance, Starting Current, and Coast-Down Time.
5. Generators
Mega ohm meter, RF, and Coast-Down Time.
6. Distribution System
Hi-Pot, Ultrasonic, Power Factor, and Harmonic Distortion
14
ADVANTAGES OF CONDITION MONITORING
1. Extend bearing service life
15
6. Improve repair time
16
1.6 TECHNIQUES FOR CONDITION MONITORING OF
MOTORS
TEMPERATURE MONITORING
Understanding what exactly a safe or normal operating
temperature is essential but not always that easy. It will be
influenced by several factors:
Design of motor
Load factor
Ventilation method
17
For larger machines, consideration should be given to installing
permanent monitoring devices to continuously monitor critical
areas such as the bearings and the stator windings. Options for
sensors are resistance temperature detectors or thermocouples.
In a low voltage motor, an option is to fit thermistors that can be
built in to trip the motor when the temperature increases above a
certain point. It is essential to regularly clean the motor to keep
the ventilation paths clear, especially on open ventilated motors
Blocked ventilation is one of the most common causes of
overheating of the machine due to restricted cooling.
Infra-red thermography is ideal for quick monitoring, showing
temperature across a whole motor very quickly. Spot
measurement using infra red thermometers is much less costly
than proper thermal imaging cameras, but is considerably more
time consuming and it is much harder to spot anomalies that may
occur in unexpected places.
VIBRATION MONITORING
ELECTRICAL TESTS
There are many electrical tests and investigations that can be
used to determine the condition of key constructional factors.
Some tests can be done while the motor is still in operation,
‘online’, while some require the motor to not be in use, ‘offline’.
Offline testing allows for more comprehensive testing to be done.
Tests include surge test, winding resistance/coil resistance
testing, meg-ohm test, polarization index testing, high potential
test and step voltage test. Testing the state of the windings by
the winding resistance and insulation resistance test is a good
way to begin, as any other test will be affected by the winding
condition. Online testing is done whilst the motor is operating,
and while tests are more limited, they do have the advantage of
reflecting real life operating conditions.
A high voltage motor (> 5 kV) can be monitored for the presence
of partial discharge, which occurs in the areas of the insulation
where there is a void or poor clearances. This test can be done
online or offline. If performed online, there are special capacitors
that are connected permanently to the motor so that the
capacitive coupling of the winding can be monitored, either
continuously or periodically. If the test is being done while the
motor is offline, a separate power supply is used to energise the
windings at a high voltage so that partial discharge can be
investigated. A technique called Electrical Scanning can also be
carried out using an Ultrasonic Acoustic Monitor to look for and
observe arcing and corona discharge throughout the motor.
A surge test and a high potential (HI Pot) test are similar in that a
voltage larger than the operating voltage is applied to the motor
to analyze its behavior. A surge test is used to determine whether
there is damage or faults in the insulation between the turns in
the winding. High voltage transients that a motor experiences
under normal operating conditions can ruin the motor’s
insulation. The test works by replicating the effect of these
transients. Each phase of the motor is tested using a value of
voltage chosen in reference to the standard functional voltage of
the system and the results are examined for signs of a defect.
Defects can be discovered at very early stages of a fault. Another
benefit of this test is that it limits the amount of energy applied
with these transients, meaning that the test can be performed
without causing additional damage. After the manufacturing
process a motor will be subjected to a High Potential test. By
applying a voltage much higher than the standard operating
voltage, twice the working voltage plus 1 kV, from the windings
to the frame of the motor, faults within the insulation windings
can be identified. This test is usually only performed once at full
voltage, as it can cause damage if done multiple times.
Sometimes, a user will ask for this to be performed following a
repair on the motor. After a minute of applying this high voltage
to the motor, the leakage current is measured and analyzed. An
unusually elevated leakage current is a warning of poor insulation
– either phase to phase, or phase to earth.
STEP VOLTAGE TEST
Mechanical problems
23
1.7 TRANSFORMER CONDITION MONITORING
TECHNIQUES:
1. Thermal analysis
2. Vibration analysis
4. PD analysis
THERMAL ANALYSIS
Thermal analysis of the transformers can provide useful
information about its condition and can indicate any incipient
inside it. Many of the incipient faults cause change in thermal
behavior of the transformer. It is usually accepted that
transformer life can be affected very much for a continuous
maximum hotspot temperature of 98°C on the paper
insulation. Beyond this, it is assumed that the rate of ageing
doubles for every increase of 6°C.Also, the transformer
subjected to degradation due to direct thermal effects, and
enhanced oil temperatures are likely to accelerate other ageing
processes. The condition of the oil can affect the ability of
transformer to withstand emergency overloading.
VIBRATION ANALYSIS
Tap Changer
28
Data Monitoring - Wireless Remote Data Logger
(Wireless SCADA): -
Once the remote data logger is connected & energized, the user
can monitor the parameters in the following ways:
1) - LCD Screen: The various electrical parameters of machine
can be monitored locally on the LCD screen of the data logger
itself.
2) - SMS Alert: User can activate SMS alerts to receive messages
on his/her mobile phone. This requires a GPRS/GSM enabled SIM
card.
3) - Email Alert: User can activate Email alerts to receive
messages on his/her mobile phone. This requires a GPRS/GSM
enabled SIM card
4) - Remote Web Account (Optional): User can monitor all the
parameters live in real time if he/she has activated the remote
web account. This service requires activation and is on annual
chargeable basis. If the user has activated his/her "Remote Web
Account" then all the parameters can be monitored from a remote
PC/Laptop. User can also do the switching operations from the
remote PC/Laptop. An exceptionally low cost wireless GPRS/GMS
based SCADA solution for remote industrial automation
Conclusions: -
Management of maintenance activities at facilities on military
installations is a complex and expensive task. This report
presents a variety of techniques that can monitor equipment
condition and anticipates failure. For some noncritical,
inexpensive, and easily replaced components, run-to-failure
method may be an acceptable practice. For large, complicated,
expensive, mission-critical items, run-to-failure may be
unacceptable. Maintenance to maximize service life of equipment
or components and surveillance of performance degradation can
allow repairs/replacement without interruption of mission-critical
activities. For certain installations, it may be more economical to
use contract services to maintain Infrequent, complex, and
expensive equipment and processes.
1.8 LIMITATIONS
The technologies presented can be divided into two categories:
Energized: -
Those technologies that can safely provide information on
energized systems and require the system be energized and
operational. These technologies include IRT, Ultrasonic, Motor
Current Readings, Starting Current, Motor Current Spectrum
Analysis RF, Power Factor, and Harmonic Distortion.
De-Energized: -
Technologies that require the circuit to be de-energized for safe
usage include Surge Testing, Hi-Pot Testing, Time Domain
Reflectometry (TDR), Mega ohm meter, Motor Circuit Analysis,
Transformer Oil Analysis, Turns Ratio, and Conductor Complex
Impedance.
30
COMPANY PROFILE
We currently have (i) Six power plants (aggregating 2062 MW) including two
units of 600 MW (that is part of our 3,600 MW Mahanadi power plant with an
aggregate of six units), that are fully operational and (ii) four remaining
units of the 3,600 MW Mahanadi power plant (aggregating 2,400 MW) that
are currently under various stages of construction. In addition, certain other
thermal, solar and hydro power projects, including outside India, are in
various stages of planning.
Off Taker: Sai Wardha Warora undertakes power supplies to local utilities
and bulk captive consumers in the state of Maharashtra.
Fuel Supply: Sai Wardha Warora Coal supplies are tied up through cost plus
Fuel Supply Agreement with western Coal Fields
2.2 KSK PROJECTS
34
2.3 HISTORICAL PROFILE:
2003 Commenced work on 10.9 MW, gas based MMS Power plant
in Tamilnadu
1 Personal Department
3 Finance Department
4 General Stores
5 Safety/ Laboratory
6 Coal Yard
7 CSR Department
8 Operation Department
9 Maintenance E&I/MECH/Operation/Civil
37
RESEARCH METHODOLOGY
38
3.1 OBJECTIVES
3.2 HYPOTHESIS
PRIMARY DATA:-
This data had been collected through meetings and interviews with various
managers and employees of the ELECTRICAL department located in Sai
Wardha power limited . At the same time I had visited various departments
for collection of data. The various areas I visited where electrical
equipment’s is installed & observed various temperature of electrical
equipment’s.
39
SECONDARY DATA:-
Apart from the Department primary data certain secondary data were
required for this project. Followings are the main sources secondary data:
1. Manuals and reports from the company library.
2. Photocopy of electrical equipment’s showing various temperature
40
DATA COLLECTION
&
ANALYSIS OF DATA
IN Sai wardha power company ltd, there is 220 KV SWITCHYARD,
various electrical equipment’s are installed like
Transformers,Busbar,Isolators,CT& PT etc.
1. Current transformer
Max temp:43.6 deg cel
2.CT with jumpers
Max temp: 41.6 deg cel
42
3. Line-1 CT with jumpers
Max temp:41 deg cel
43
4. Isolators with jumper
Max temp:43.2 deg cel
44
5. Single line thread
Max temp: 39 deg cel
45
6. Bus bar
Max temp: 40.5 deg cel
46
7. 220 KV insulator
Max temp:44.2 deg cel
47
8. Jumpers connecting to bus bar
Max temp: 42.1 deg cel
48
9.PT
Max temp: 40.2 deg cel
49
10. Isolator
Max temp: 39.3 deg cel
50
11. MOTOR
Max temp:77.3 deg cel
51
RELIABILITY AND AVAILABILITY
52
CONCLUSIONS:
53
BIBLIOGRAPHY
1.Bibliography
Data from Sai Wardha Power Limited, Group of KSK Energy Ventures.
Tran T. V., and Gol Ö.: Stator End Winding Problems in Large Synchronous
Generators and Some Remedies, International Conference on Electrical
Machines, Bruges, Belgium, Paper 406, 2002.
www.en.wikipedia.org
www.youtube.com
www.google.co.in
www.ksk.co.in
54