CTR - Life Camp Refurbishment Rev 1

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

RFQ FOR Technical Assessment of BRT

Kitchen, Life Camp buildings &


Activity Register & Manhours
Infrastructures / STP and Evaluation of Hours
Turbine Power Supply from BRT to Life Rev 0.0 - 05/08/19
Camp

CTR n°5 Draft Lead Project Eng. Lead Eng. Disc.


Engineering Task Description / Deliverable Name
Product man Draftman hours status hours status Leader

CTR n°5 - DETAILED ENGINEERING SCOPE -


Life Camp Refurbishment TOTAL: 336 71 946 210 0
ELECT Conceptual Design 0 0 100 - 28 - 0
ELECT Detailed Assesment Report 32 office 8 office

ELECT Weekly Meetings and Reviews 8 office 10 office

ELECT Electrical Conceptual Design Report 60 office 10 office

ELECT
ELECT Detail Design 0 0 580 - 112 - 0
ELECT Detailed Design Report 80 office 12 office

ELECT LV Cable Sizing Calculation 48 office 12 office

ELECT Cable Schedule 20 office 4 office

ELECT Load Shcedule 40 office 8 office

ELECT Electrical Equipment Data Sheets 40 office 8 office

ELECT MTO 40 office 8 office

ELECT Bill of Quantity 40 office 8 office

ELECT Priced Bill of Quantity 20 office 4 office

ELECT Detailed Construction Scope of Work 48 office 8 office

ELECT Lighting Calculation 100 office 8 office

ELECT Electrical Equipment Schedule 40 office 6 office

ELECT Detail Design Review Participation 16 office 8 office

ELECT HAZID/Design Risk Assessment Attendance 8 office 8 office

ELECT Procurement Supports 40 office 10 office

ELECT Drawings 336 71 266 - 70 - 0


ELECT Single Line Diagram 30 8 24 office 6 office

ELECT Single Line Diagram for Cafeteria and Kitchen Distribution Board 24 4 24 office 6 office

ELECT Single Line Diagram for Hostel Distribution Board 24 4 24 office 6 office

ELECT Single Line Diagram for Recreational Build Distribution Board 24 4 24 office 6 office

ELECT Single Line Diagram for Laundry Building Distribrution Board 24 4 24 office 6 office

ELECT Cable Layout 32 4 16 office 6 office

ELECT Fire Alarm Layout 16 4 10 office 4 office

ELECT Lighting and Small Power Layout 90 15 48 office 10 office

ELECT Installation Details 32 8 40 office 8 office

ELECT Perimeter Lighting Layout 20 8 16 office 6 office

ELECT PAGA System 20 8 16 office 6 office