Steam Blowing Process
Steam Blowing Process
Steam Blowing Process
PLANT DETAILS
Plant Details
LDO Consumption
1) First Unit- 1700 kl (approx)
2) Second Unit-1880 kl (approx)
3) Third Unit- 800 kl (approx)
4) Fourth Unit- In progress
2
EFFECT OF BLOWING DEPENDS ON
1) Thermal shock
2) Removal force of steam
3) Cleaning force of steam
3
CLEANING FORCE RATIO (CFR)
4
Huff & Puff Method
To give a thermal shock to the contour being purged, to dislodge the scale
etc.
Procedure: Raise the boiler pressure to a pre-determined value (40-60
kg/cm2), shut off firing and at the same time open the quick opening
valve(EOTV), thus allowing the steam to escape to atm. with high velocity
carrying with it the loose debris.
5
Network for Huff & Puff Method(CDQ 11)
6
Network for Huff & Puff Method(PRDS)
7
Sliding Pressure Method
Boiler is in by-pass operation at
about 20 to 40 % Load.
• The cleaning effect is achieved by sliding pressure against atmosphere,
resulting in low pressure and high Steam velocities.
8
Network for Sliding Pressure Method(PRDS)
9
Network for Sliding Pressure Method(CDQ 10 & 11)
10
Steam Blowing Circuit Diagram
11
Difference between Shock & Sliding Pressure method
Huff & Puff Sliding Pressure
P11 pipe & costly quick operating Low Grade temporary piping can be used
sacrificial valve is required & operating valves is not required.
12
Difference between Shock & Sliding Pressure method
Huff & Puff Sliding Pressure
13
Target Plates
14
Steam Blowing Arrangement
15