Inlet Line Replacement Procedure
Inlet Line Replacement Procedure
Inlet Line Replacement Procedure
Page 1 of 6
Inlet Line Replacement Procedure
Job Background:
Tail Gas Turbine (Y-102) Inlet line expansion joint was expanded and
spring support was impinged in the bulged line causing increase in
turbine radial vibrations resulting in plant shutdown. A temporary
repair was performed with pad welding at bulged pipe portion and
fixing the expansion joint its expanded form to start-up the plant.
The inlet line condition haven’t changed since the repair but
rehabilitation of line to its orignal condition is necessary for which
subject job is being carried out.
Job Scope:
Rehabilitate the inlet line to its original condition by replacement of
pipe bulged portion, inlet elbow, expansion joint and bottom spring
support (ST-052).
Piping Detail:
Job Duration:
Job Protocol:
Job will be started after the machine barring is stopped. During barring
activity, side activities such as S/F arrangements for canopy removal,
chain blocks tie-in etc. which shall not disturb the inlet line/nozzle
flange can be carried-out to minimize the shutdown time.
Page 2 of 6
Inlet Line Replacement Procedure
Job Steps:
1.4.Shop joint of Bellow with Elbow (01 No. of Bellow with Elbow 32”
Dia).
2. Shutdown Activities:
During Machine Barring Activity:
As mentioned in job protocol above, to reduce the outage time side
activities will be
performed in this period (from plant shutdown till machine
complete stoppage). These side activities are as below:
Page 3 of 6
Inlet Line Replacement Procedure
3. Post-Handover Activities:
3.1.Lock the Spring Supports (ST-052) and (ST-049) in its cold
position and PTE to note down the readings before proceeding for
next steps i.e. machine flange de-bolting, line cutting (Hold Point:
PTE).
Page 4 of 6
Inlet Line Replacement Procedure
3.12. Rigging the spool S1 for installation and hold it with chain
blocks.
3.13. Loose bolting of machine flange for alignment of the spool in
place.
3.14. Rigging the Spool S2 to its location for installation and
holding it with chain blocks.
3.15. Install back the new spring support (ST-052) in locked
condition with its bottom structure.
3.16. Loose bolting with control valve flange for alignment
purpose.
3.17. Field Joint weld to be done with back-pass of weld no. W3
and W4.
3.18. Dial reading by Machinery before start of machine flange
bolting. (Machinery)
3.19. Machine 1st flange bolting with new gasket. Maintain the
tolerances as per vendor manual. (Attached below)
3.20. Dial reading by Machinery after machine flange bolting.
(Hold Point: Machinery)
3.21. Burner Hall outside Line alignment. (Hold Point: PTE)
3.22. Internal inspection of line before final box-up. (Hold Point:
Inspection)
3.23. C.V flange bolting with new gaskets.
3.24. Unlock the spring supports at their cold positions. (Hold
Point: PTE)
3.25. Remove the chain blocks from location.
3.26. Insulation first pad redressing.
3.27. Necessary Housekeeping (Removal of combustible items,
consumables etc.) before start-up.
Appendix:
Page 5 of 6
Inlet Line Replacement Procedure
Page 6 of 6