2008 XX XX Ehrbar Gotthard Base Tunnel Experiences With Different Tunnelling Methods
2008 XX XX Ehrbar Gotthard Base Tunnel Experiences With Different Tunnelling Methods
2008 XX XX Ehrbar Gotthard Base Tunnel Experiences With Different Tunnelling Methods
Heinz Ehrbar1
Abstract – At the time when it is completed, the Gotthard Base Tunnel in Switzerland, with a total length of 57 km,
will be the longest railway tunnel in the world. The complete tunnel system consists of 153.3 km of access tunnels,
shafts, railway tunnels, connecting galleries and auxiliary structures. Excavation of the main system started in 2002.
More than 108 km, or more than 70% of the full 153.3 km of tunnel system, had been completed by the end of March
2008. Conventional tunnelling as well as excavation by TBM have been used. The experience gained is sufficient to
allow conclusions to be drawn regarding each method.
1
AlpTransit Gotthard Ltd. Zentralstrase 5, CH 6003 Lucerne, +41 41 226 06 25, [email protected]
2º Congresso Brasileiro de Túneis e Estruturas Subterrâneas
Seminário Internacional “South American Tunnelling” - 2008
1 Introduction
On several occasions, the Swiss voters took the decision to construct a new high-speed rail link through the Alps.
Switzerland’s New Rail Link through the Alps (NRLA) will provide a faster and more reliable rail link between
northern and southern Europe. It will enable much of the freight traffic to be shifted from road to rail. There are two
NRLA lines: the Lötschberg axis (in operation since 2007) in the west, and the Gotthard axis in central Switzerland (to
be completed by 2019). The 57-km-long Gotthard Base Tunnel is the main structure of the Gotthard axis. When it is
completed, the GBT will be the world’s longest railway tunnel.
Preliminary work for the Gotthard Base Tunnel started in 1996, with excavation of access tunnels and shafts.
The main construction work began in 2002, and will be completed in 2015. After completion of the railway installations
and commissioning, the Gotthard Base Tunnel will start commercial operation at the end of 2017.
To shorten construction time, the length of the tunnel has been divided into five sections, and is being excavated
from several sites simultaneously. Excavation is taking place from the portals at Erstfeld in the north and Bodio in the
south, as well as from three intermediate attack points through access tunnels at Amsteg and Faido, and two vertical
shafts at Sedrun (Fig. 1).
The Gotthard Base Tunnel consists of two parallel single-track tubes with an excavation diameter varying from
8.8 to 9.5 m and linked by cross-passages approximately every 312 m. Two multifunction stations (MFS) are located in
the Sedrun and Faido sections, one-third and two-thirds along the length of the tunnel respectively. These will be used
for the diversion of trains to the other tube via crossovers, to house technical infrastructure and equipment, and as
emergency stopping stations for the evacuation of passengers.
Much of the tunnel will have a very high overburden: more than 1,000 m overburden over approximately 30 km
of the tunnel, more than 1,500 m over 20 km, and more than 2,000 m over approx. 5 km. The maximum overburden is
about 2,400 m.
So far, approximately 108 km of access tunnels, shafts and main tunnels have been excavated, or 70% of the
total length of 153.3 km. Around 65 % of the entire tunnel system is being excavated by tunnel boring machines
(TBMs). Around 35 % of the total length, mainly the access tunnels, the main tunnels in the central construction section
of Sedrun, and the multifunction station at Faido, are being driven by the conventional tunnelling method.
Figure 2: Gotthard Base Tunnel: general longitudinal profile with excavation methods
2º Congresso Brasileiro de Túneis e Estruturas Subterrâneas
Seminário Internacional “South American Tunnelling” - 2008
2 Selection of the excavation method
• Excavation, using drilling and blasting or mechanical excavators other than full-face TBMs
• Mucking
• Placement of the primary support elements such as
Ó Steel ribs or lattice girders
Ó Soil or rock bolts
Ó Meshes
Ó Shotcrete or cast in situ concrete,
either not reinforced or reinforced with wire mesh or fibres.
Conventional tunnelling is carried out in a cyclical process of steps, each comprising excavation followed by the
application of relevant primary support, both of which depend on existing ground conditions and ground behaviour. An
experienced team of tunnel workers (miners), assisted by standard and/or special plant and equipment, executes each
individual cycle of tunnel construction.
The conventional tunnelling method using mainly standard equipment, and allowing access to the tunnel
excavation face at almost any time, is very flexible in situations or areas that require a change in the structural analysis
or design, and as a result also require changes in the supporting measures.
A standard set of equipment for conventional tunnelling may consist of the following items:
• Drilling jumbo to drill holes for blasting, rock bolting, water and pressure release, grouting etc.
• Road header or excavator in cases where blasting is not possible or not economic
• Lifting platform allowing the miners to reach each part of the tunnel crown and tunnel face
• Lifting equipment for steel sets
• Loader or excavator for loading excavated rock onto dump trucks
• Dump trucks for hauling excavated rock
• Set of shotcrete manipulators for application of wet or dry shotcrete.
Using this standard set of equipment, the following changes can easily be made during construction if rock
conditions change, or if monitoring results call for action:
• Increase or decrease of support, e.g. the thickness of shotcrete, number and/or lengths of rock bolts per linear
meter of tunnel, spacing and dimensions of steel arches, number and lengths of spiles, application of shotcrete
at the tunnel face, bolting the face etc.
• Variation of ring closure time – which is the time between the excavation of a section of the tunnel and the
application of partial or full support – or variation of ring closure distance from the excavation face
• Introduction of primary support ring closure
• Variation of the explosive charge per blasting round and variation of detonator sequences.
Other variations during construction allow changes to be made in function of the stand-up time of the rock
encountered:
• Increased or decreased length of excavation round (common round lengths vary from 0.5 m to 4.0 m)
• Partial excavation by splitting the excavation face into the crown, bench, and invert excavation steps, or even
further in pilot and sidewall galleries and in staggered bench/invert excavations.
If exceptional rock conditions are encountered – regardless of whether or not they were predicted – the
conventional tunnelling method can respond with a variety of auxiliary construction technologies such as:
• Grouting: consolidation grouting, fissure grouting, pressure grouting, compensation grouting
• Technologies to stabilize and improve the rock ahead of the actual tunnel face
such as forepoling, pipe umbrella, horizontal jet grouting, ground freezing etc.
It is the responsibility of experienced engineers to make the most appropriate choice according to the science of
engineering and their personal experience for a safe and economic tunnel construction. The realisation of the
appropriate solution is only possible if the contractual conditions allow it. As shown later on conventional tunnelling
calls for adapted contract models.
Two different types of TBMs are used according to the expected ground conditions: open type machines and
closed type machines. Open type machines can be used in ground conditions where the face of the excavation is self-
standing.
• Gripper TBM
Gripper TBMs are essentially used in rock where the face of the tunnel is self-standing. The advance rate of a
Gripper TBM depends essentially on the time required to install rock support devices such as steel ribs, rock
anchors, meshes and shotcrete.
• Single Shield TBM
Single Shield TBMs are field machines without a closed system for pressure compensation at the tunnel face
and can be used where the breast is self-standing. The support will be done with a segment lining. Single
Shield TBMs have a very wide range of applications from hard to brittle or soft rock.
Tunnelling by TBM usually allows high advance rates, which, in similar ground conditions, are significantly
higher than (more than double) the rates attained by conventional tunnelling.
Tunnelling by open Gripper TBM (as they are used at the Gotthard Base tunnel) is especially appropriate for
• Comparatively homogenous ground conditions
• Projects with a comparatively low risk of water inflow under high pressure
On the way from the definition of the project requirements to the realisation of the project, risk factors can
complicate (hazards) or facilitate (opportunities) achievement of the goal.
Figure 4: Sedrun section, longitudinal geological profile with exploratory drillings and squeezing rock
2º Congresso Brasileiro de Túneis e Estruturas Subterrâneas
Seminário Internacional “South American Tunnelling” - 2008
The test bores to the north indicated that the 1.1-km-long Tavetsch Intermediate Massif North consists to
approximately 70% of soft kakiritic rocks displaying ductile fracture behaviour. Approximately 30% of the rock is hard,
and displays brittle facture behaviour. Hard and soft rocks alternate in narrow vertical layers. The predominant hazard is
the phenomenon of squeezing rock.
The phenomenon of squeezing rock manifests itself both radially and at the work-face as a tendency for the
excavated cavity to converge. In the longitudinal direction, given the expected alternation of different vertical layers of
rock, the phenomenon will be accentuated as potential instabilities at the workface. Squeezing rock causes extremely
high rock pressure in the case of strongly limited deformations.
Figure 5: Experience of tunnelling in squeezing rock and principle of steel rib support
Experience of tunnel construction indicates that rock pressure decreases as the amount of rock deformation
increases. Therefore, the project for the excavation of the zones with squeezing rock in the Sedrun construction section
is based on the following principles:
• The profile will be excavated on the static-force ideal circular shape with an additional space for deformations
of up to 70 centimetres
• The rock support elements should be able to sustain initial large deformations.
For the first rock support only highly deformable materials with a plastic failure mode will be allowed, such as
steel ribs (with special sliding joins) and rock anchors. The ground support will be comparatively low in the
first phase (yielding phase)
• Support materials with a brittle failure mode such as shotcrete will be placed only when the deformations come
practically to an end. In this phase (resistance phase) the support forces will be elevated to the necessary level
for a stable equilibrium.
It was the aim to find a construction procedure with an immediate ring closure. Only full-face excavation allows
the fastest possible ring closure time. The procedure for closing the ring was as follows:
• Full face excavation in a circular shape (80m2 to 135 m2) in steps of 1.3 m
• Placement of steel ribs after each advance (2 x TH 44, distances 33 cm, 50 cm, 66 cm and 100 cm).
• Placement of 12-m-long self-drilling radial anchors after each round.
• Placement of 18-m-long self-drilling tunnel-face anchors after every 6 m of advance.
2º Congresso Brasileiro de Túneis e Estruturas Subterrâneas
Seminário Internacional “South American Tunnelling” - 2008
• When the full length of the sliding join has been taken up, the circular force in the steel insert, and with it the
risk of buckling, increases. For perfect embedment, and to ensure the full load-bearing capacity, the steel ribs
are then completely shotcreted in. In the project, it is assumed that the yielding phase is completed 75 m
behind the tunnel face.
• Within this distance of 75 m, it is stipulated that over the entire cross section additional supporting measures
must be possible, namely
J Insertion of additional steel rings
J Re-anchoring during the deformation process
J Application of a shotcrete lining after the deformation process is complete.
The overall ground support concept is modular, so as to allow optimal deployment of the associated machinery.
Such installations for insertion of steel supports are used in mining, but not with the dimensions required on the
Sedrun section, where a weight of 50 tonnes has to be suspended from overhead rails.
The contract was signed in April 2002. In mid-May 2004, the transition zone to the area of squeezing rock was
reached in the northward drive. Until autumn 2004, even in zones of bad rock quality, no phenomena of squeezing rock
occurred at Sedrun. In December 2004, rock masses with a high potential of squeezing were detected in the exploratory
drillings. Since then, the 1.1-kilometer-long zone of squeezing rock has been excavated. Radial deformations in the
range from 20 cm to 30 cm in the average and 75 cm in the maximum were observed.
2º Congresso Brasileiro de Túneis e Estruturas Subterrâneas
Seminário Internacional “South American Tunnelling” - 2008
Breakthrough took place in October 2007, nine months ahead of the contract schedule. The average advance rate
was constantly around 1.3 metres per day. Also, the costs were slightly lower than foreseen. A very successful chapter
in the history of conventional tunnelling has been written.
3.2 Tunnel construction close to concrete arch dam with conventional tunnelling (Sedrun Southern Drive)
The limitation on the potential influence on third parties and existing facilities is one key factor for the selection
of the excavation method.
In the southern drive of the Sedrun construction section, the Gotthard Base Tunnel passes in a distance of a little
more than 1 kilometre under the 127 m high concrete arch dam at Nalps. The main hazard scenario is the occurrence of
unacceptable surface deformation due to the dewatering effects in the jointed rock mass during and after tunnel
construction. This phenomenon could be observed in Switzerland in two cases (1978 Rawil exploratory gallery;
Gotthard road tunnel). In both cases, settlements of more than 10 cm were observed. In the case of the Rawil
exploratory gallery, the nearby concrete arch dam at Zeuzier was severely damaged. The dilatation of the block joints in
an arch dam is especially critical.
In the Gotthard Base Tunnel project, many mitigation measures are foreseen to avoid unacceptable deformations.
The measures consist of a sophisticated exploratory drilling concept, and of grouting concepts in the case of the
occurrence of permeable fault zones. It is quite clear that grouting work can be done much easier in conventional
tunnelling than from a TBM, where the working space is very limited. In the owner's project, only conventional
tunnelling was foreseen in the southern drive from Sedrun.
On September 2006, a water inflow of initially 13 litres per second occurred when excavation of the western
tube of the Gotthard Base Tunnel was close to the foundations of the Nalps dam. The permeable zone had to be sealed
with cement grouting. Thanks to the free access given by the conventional tunnelling method, the grouting work could
be done from two sides from the fault, because a bypass through the more advanced eastern tube could be used. It took
102 working days to reduce the water inflow to an acceptable limit by drilling 12,800 m of drill holes and pumping 210
tonnes of grouting mixture into the rock.
From 1998 to 2001, the inclined access tunnel was excavated. At the beginning of 2002, the main contractor took
over and started excavation of the first cavern. A few weeks after starting work, a first breakdown occurred. Other
breakdowns followed. After an intense investigation campaign, a new rock model had to be defined. Two large fault
zones called for a new layout for the multifunction station at Faido. The crossover tunnels had to be moved 600 m to the
south.
After taking the decision to move the two crossovers to the south direction at the end of 2003, the geological
difficulties remained for more than further three years until March 2007, when excavation of the multifunction station
was completed. The following hazard scenarios had to be managed:
• Squeezing rock
• Rock fall
• Rock burst
• Occurrence of methane.
Thanks to the high flexibility of conventional tunnelling, all of these difficulties could be mastered. Additional
working groups and equipment could be mobilized very quickly. Nevertheless the very unfavourable ground conditions
caused a delay of two year in the excavation work and additional costs of more than 200%. A Tbm drive would not
have been feasible in the encountered conditions.
lìí=NTKMVKOMMP
få=NVKMOKOMMP
lìí=NSKMTKOMMP
b~ëí=íìÄÉ
aê få=MVKMSKOMMP tÉëí=íìÄÉ
áîá
åÖ
=Ç
áêÉ
Åíá
çå
After finishing the excavation from the bypass tunnel, the cutter head could be re-started at the end of November
2005, after 5 months of standstill with additional costs of 10 million Swiss francs.
Also in the case of Amsteg, it can be stated that the standstill in the fault zone would have been smaller than with
the TBM drive. Over the whole TBM drive, the average advance rates reach 11.5 meters per working day, and are
practically identical to the values of Bodio. A well organised conventional drive under the boundary conditions of the
Gotthard Base Tunnel can reach 50% of this value. The TBM drive was faster, whereas the costs would have been very
similar for both solutions.
Figure 16: Faido: Concept for the TBM drive and deformed steel rib in the floor at the end of the yielding phase
5.1 Conclusions
Recent experience on the Gotthard Base Tunnel shows significantly higher advance rates for long TBM drives
than for conventional tunnelling. This is still the case when isolated fault zones cause longer standstills for the TBM
drive. On the cost effects, no direct experience has been gained due to the fact that there is no situation on the Gotthard
Base Tunnel where one tube will be excavated by TBM and the other by conventional tunnelling. Experience on the
Lötschberg Base Tunnel shows only a small difference in costs between the two methods.
A well-organised conventional drive allows mastering of large deformations and thereby mastering of high
pressures in squeezing conditions. The response to changing rock conditions is easier and faster with conventional
tunnelling, as the above examples show. The application of auxiliary construction measures for ground improvement
(grouting), ground reinforcement (fore-poling, face anchoring) and dewatering is much easier for conventional
tunnelling than for TBM excavation. A TBM drive is technically and economically not feasible in very difficult rock
conditions, as demonstrated in Sedrun North and the Faido multifunction station.
Most of the above-mentioned examples had a significant impact on the construction costs and construction time.
So far, in all cases, a satisfactory solution could be found for both parties. This was only possible because the following
recommendations are included in the contracts of the Gotthard Base Tunnel Project.
5.2 Recommendations
5.2.4 Partnering
The goal of this process is to minimise disputes and prevent them from escalating in time and value by resolving
them at the lowest possible level in the project organization. It attempts to establish a win-win attitude between the
project participants, including the client, the contractor, the engineer, and the construction manager. This process
encourages dialogue among the various participants, and relies on reasonable people to resolve disagreements
reasonably. It seeks to eliminate adversarial posturing and positioning that often develop when disputes and claims
arise. Through this process, a series of dialogues and interactions is developed whereby the team members are
encouraged to work out differences in the best interests of the project. When an issue is not resolved at the lowest level,
it is brought up to a higher level for resolution.
REFERENCES
ITA WORKING GROUP 14 (2000), "Recommendations and Guidelines for Tunnel Boring Machines (TBMs)",
www.ita-aites.org
KOVÁRI, K., AMBERG, F., EHRBAR, H. (2000): “Mastering of Squeezing Rock in the Gotthard Base Tunnel“,
World Tunnelling, June 2000, page 234 to 238
EHRBAR, H., SCHÄLLIBAUM I., KÄLIN J., (2001) „Gotthard Base Tunnel, Construction Lot Sedrun, A Challenge
for Tunnel Construction“, Proc. ITA World Tunnel Congress, Milan 2001
EHRBAR H., (2004), “Vortriebskonzept in den druckhaften Zonen, Vom Projekt zur Ausführung“, Proc. EUROCK
2004, 53. Geomechanical Colloquium, Salzburg. Rotterdam: Balkema
BREMEN, R., (2005), „Oberflächensetzungen als Folge von Tunnelbauten in grosser Tiefe, Stand der heutigen
Erkenntnisse“, Proc. AlpTransit Conference, Lucerne 2005. Swiss Tunnelling Society, www.swisstunnel.ch/Shop
EHRBAR, H., (2005), „Gotthard Base Tunnel, Sedrun Section, Mastering Squeezing Rock Zones“, Proc. ITA World
Tunnel Congress, Istanbul 2005
THE INTERNATIONAL TUNNELLING INSURANCE GROUP (2006), "A Code of Practice for Risk Management of
Tunnel works", www.imia.com
WILDBOLZ, A., (2006), „Amsteg – TBM Stillstand in der Weströhre, Kleiner Unterschied – grosse Wirkung“,
Proc. Swiss Tunnel Congress, Lucerne 2006. Swiss Tunnelling Society, www.swisstunnel.ch/Shop (in german)
THEILER, A., MEIER, R., (2007), „Injektion einer wasserführenden Störzone – Konzept und Ausführung“,
Proc. Swiss Tunnel Congress, Lucerne 2007, Swiss Tunnelling Society, www.swisstunnel.ch/Shop (in german)
ITA WORKING GROUP 19 (2008), "Conventional Tunnelling, Report of the Working Group 19 ", www.ita-aites.org